transmission efficiency project (tep) · 2016. 7. 14. · tep – 220kv quang ngai- quy nhon (phuoc...
TRANSCRIPT
-
NATIONAL POWER TRANSMISSION CORPORATION
CENTRAL VIETNAM POWER PROJECTS MANAGEMENT BOARD
TRANSMISSION EFFICIENCY PROJECT (TEP)
Subproject
220kV QUANG NGAI - QUY NHON
TRANSMISSION LINE
ENVIRONMENTAL MANAGEMENT PLAN
(EMP)
(FINAL VERSION)
December 2014
E4420 V19 P
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
ed
-
NATIONAL POWER TRANSMISSION CORPORATION
CENTRAL VIETNAM POWER PROJECTS MANAGEMENT BOARD
TRANSMISSION EFFICIENCY PROJECT (TEP)
Subproject
220kV QUANG NGAI - QUY NHON
TRANSMISSION LINE
ENVIRONMENTAL MANAGEMENT PLAN
(EMP)
(FINAL VERSION)
PROJECT OWNER
CENTRAL VIETNAM POWER
PROJECTS MANAGEMENT BOARD
CONSULTANT
POWER ENGINEERING
CONSULTING JS COMPANY 4
December 2014
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 3
TABLE OF CONTENT
ABBREVIATIONS ............................................................................................................. 4 1. INTRODUCTION ........................................................................................................... 5 2. LEGAL FRAMEWORK ................................................................................................ 5
2.1 Vietnamese Legislations .......................................................................................... 5 2.2 World Bank’s safeguard policies. ............................................................................. 8
3. SUBPROJECT DESCRIPTION .................................................................................... 9 3.1 Subproject Objectives ............................................................................................... 9 3.2 Subproject Scale ....................................................................................................... 9 3.3 Subproject Location ................................................................................................. 11 3.4 Volume of construction .......................................................................................... 14
3.4.1 Construction Volume of the 220kV Quang Ngai- Quy Nhon (Phuoc An)
transmission line ........................................................................................................ 14 3.4.2 Volume of the 220kV feeder bay items at the 220kV Quang Ngai Substation .. 16
3.5 Volume of main works ........................................................................................... 18 3.5.1. Volume of main works pre- and construction phase. ...................................... 18 3.5.2 Transportation................................................................................................... 19 3.5.3 Manpower for the subproject contruction ....................................................... 19
3.6 Subproject Implementation Schedule and Total Investment .................................. 20 3.6.1 Subproject Implementation Schedule ............................................................... 20 3.6.2. Total cost investment ....................................................................................... 23
4. BASIC DATA .............................................................................................................. 23 4.1 Geographical location and populations ................................................................... 23 4.2 Topography ............................................................................................................. 25 4.3 Climate .................................................................................................................... 29 4.4 Existing condition of environment quality in the subproject area .......................... 30 4.5 Socio-economic Features ....................................................................................... 33
4.5.1 Economic ......................................................................................................... 33 4.5.2 Public Health: .................................................................................................. 37 4.5.3 Education: ....................................................................................................... 38
4.6 Ecology. ................................................................................................................... 38 4.7 Protected areas, nature reserves, sensitive areas, cultural facilities, historical
monuments, temples and pagodas in the subproject area .............................................. 42 5. POTENTIAL IMPACTS .............................................................................................. 42 6. MITIGATION MEASURES ........................................................................................ 60 7. MONITORING PROGRAM ........................................................................................ 85
Objective ........................................................................................................................ 85 8. EMP IMPLEMENTATION ARRANGEMENTS ....................................................... 89
8.2. Cost estimation of the EMP’s implementation ....................................................... 94 9. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ........................ 94
9.1. Public Consultation ................................................................................................. 95 9.2. Imformation disclosure ........................................................................................... 97
ANNEXES......................................................................................................................... 98
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 4
ABBREVIATIONS
CPPMB: Central Vietnam Power Projects Management Board
PMB: Project Management Board
EIA: Environmental impact assessment
EMP: Environmental Management Plan
EVNNPT: National Power Transmission Corporation
PECC4: Power Engineering Consulting Joint Stock Company 4
PTC3: Power Transmission Company No. 3
TEP: Transmission Efficiency Project
TD: Technical Design
PPC: Provincial People Committee
VND: Vietnam Dong
ROW Right of Way
AH: Affected Household
AP: Affected People/Affected Person/Affected Household
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 5
1. INTRODUCTION
Subproject “220kV Quang Ngai - Quy Nhon (Phuoc An) transmission line” is one
of the subprojects that will be implemented in Phase 1 of Transmission Effeciency
Projects (TEP) funded by the World Bank.
Investment of the subproject “220kV Quang Ngai - Quy Nhon (Phuoc An)
transmission line” is fully suitable with the National Power Development Master Plan in
the phase of 2011 - 2020 with the vision to 2030 at the Decision No. 1208/QD-TTg dated
July 21st, 2011 approved by the Prime Minister.
Activities of the subprojects include:
+ Construct 220kV double-circuit Quang Ngai - Quy Nhon transmission line, in
which one circuit suspended in advance in 2016. The TL has 139,888m in length, and its
ROW is 21.2m in width.
+ Construct one 220kV outgoing bay at the 220kV Quang Ngai substation.
Those activities may cause negative impacts to environment and community during
the pre-construction, construction and operation phases.
In order to realize and minimize potential negative impacts during the process of
project implementation and comply with the Environment Assessment Policy of the
World Bank (OP/BP 4.01), Environmental management plan (EMP) of the subproject has
been prepared suitable with the guidelines in the Environment and Society Management
Framework of the TEP. This EMP consists of description of the subproject, legal and
policy frameworks, environmental national technical regulations and standards, potential
negative impacts, mitigation measures proposed to be carried out in the phases of the pre-
construction, construction and operation, implementation arrangements. Mitigation
measures proposed in the EMP will be incorporated in bidding documents and contracts
and attached to environment supervision during the implementation process.
According to the regulations of the GOV, the subproject has prepared an
Environmental impact assessment (EIA) report. In April 2014, the EIA report of the
subproject was submitted to the Ministry of Natural Resources and Environment for
appraisal and approval. It has been approved at the Decision No.2063/QD-BTNMT dated
Sep. 24th
, 2014.
2. LEGAL FRAMEWORK
2.1 Vietnamese Legislations
- Electricity Law No. 28/2004/QH11 passed by the National Assembly of the
Socialist Republic of Vietnam on Dec. 03rd
, 2003 and come into force from July 1st, 2006.
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 6
- Law on modification, supplementation on some articles of the Electricity Law
No. 24/2012/QH13 issued by the National Assembly of the Socialist Republic of
Vietnam, dated Nov. 20th
, 2012 and come into force from July 1st, 2013;
- Environmental Protection Law No. 52/2005/QH11 of the 11th
National
Assembly, the 8th
Session, passed in November 29th
, 2005 and come into force from July
1st, 2006;
- Land Law No.45/2013 /QH13 passed on Nov. 29th
, 2013 by the 6th
Session of the
13th
National Assembly of the Socialist Republic of Vietnam, and come into force from
July 1st
, 2014;
- Law of forest protection and development No.29/2004/QH11 passed on
December 3rd
, 2004 by the National Assembly of the Socialist Republic of Vietnam and
come into force from April 1st, 2005.
- Law of Construction No.16/2003/QH11 approved on November 26th
, 2003 and
come into July 1st 2004;
- Law No.38/2009/QH12 dated on June 19th
, 2009 on modification,
supplementation on some articles of the laws related to basic construction and
investment.
- Biodiversity law No.20/2008/QH12 dated Nov. 13th
, 2008 by the National
Assembly of the Socialist Republic of Vietnam, and come into force from July 1st, 2009;
- Labor Law No.10/2012/QH13 approved by the National Assembly of the
Socialist Republic of Vietnam on June 18th
, 2012, and come into force from May 1st,
2013;
- Law of Cultural Heritage No. 32/2009/QH12 dated June 18th
, 2009 regarding
modification, supplementation on some articles of the Law of Cultural Heritage No.
28/2001/QH10;
- Law of Fire Protection and Fighting No. 27/2001/QH10 approved by the
National Assembly of the Socialist Republic of Vietnam on June 29th
, 2001;
- Decree No.12/2009/ND-CP dated Feb. 10th
, 2009 of the GOV regarding project
investment and construction management;
- Decree No.29/2011/ND-CP dated April 18th
, 2006 issued by the GOV regarding
strategic environmental assessment, environmental impact assessment and environmental
protection commitment;
- Decree No.179/2013/ND-CP dated Nov. 14th
, 2013 of the GOV regarding fining
of administrative violation in environment protection;
- Decree No.23/2006/ND-CP dated March 3rd, 2006 issued by the GOV regarding
the implementation of the Law on Forest Protection and Development;
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 7
- Decree No.14/2014/ND-CP dated Feb. 26th
, 2014 promulgated by the GOV
regarding detailed regulation on the implementation of the Electricity Law on electric
safety, put into force from Apr. 15th
, 2014;
- Decree No.59/2007/ND-CP dated Apr. 9th
, 2007 of the GOV regarding solid
waste management.
- Decree No.98/2010/ND-CP of the GOV dated Sept. 21st, 2010 regarding
detailed regulations on the implementation of some articles of the Law of Cultural
Heritage, and adjustment and supplementation on some articles of the Law of Cultural
Heritage;
- Circular No.26/2011/TT-BTNMT dated July 18th, 2011 issued by the Ministry
of Natural Resources and Environment (MONRE) regarding detailed regulation on some
articles of the Decree No.29/2011/ND-CP dated April 18th, 2006 issued by the GOV
regarding strategic environmental assessment, environmental impact assessment and
environmental protection commitment;
- Circular No.35/2011/TT-BNEVNNPTNT dated May 20th
, 2011 of the Ministry
of Agriculture and Rural Development regarding regulations on logging and wood
salvage and non-wood forest products.
- Circular No.12/2011/TT-BTNMT dated Apr. 14th
, 2011 of the Ministry of
Natural Resources and Environment regarding hazardous wastes management;
- Applicable National Technical Regulations:
+ QCVN 01/2008/BCT: National Technical Regulations on Electricity Safety.
+ Norm on power equipment No.11 TCN - 19 - 2006, Part II: Power network
system.
+ Norm on power equipment No 11 TCN - 21 - 2006, Part IV: Protection and
Automation.
+ QCVN QTD-5: 2008/BCT - Volume 5: Calibration of power system equipment.
+ QCVN QTD-6: 2008/BCT -Volume 6: Operation, repair of power system
equipment.
+ QCVN QTD-7: 2008/BCT - Volume 7: Construction of power works.
+ QCVN 05:2013/BTNMT - National Technical Regulation on ambient air
quality;
+ QCVN 07:2009/BTNMT - National Technical Regulation on hazardous waste
threshold;
+ QCVN 26:2010/BTNMT - National Technical Regulation on Noise.
+ QCVN 27:2010/BTNMT - National Technical Regulation on Vibration.
+ QCVN 03:2008/BTNMT - National Technical Regulation on the allowable
limits of heavy metals in the soils.
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 8
+ QCVN 08:2008/BTNMT – National Technical Regulation on surface water
quality.
+ QCVN 14:2008/BTNMT – National Technical Regulation on domestic waste
water.
2.2 World Bank’s safeguard policies.
Environmental and social screening for the subproject was carried out in compliance
with and it showed that the WB’s policies on Environmental Assessment (OP 4.01) and
Forest (OP/OB 4.36) are necessary to be conducted for this Subproject.
- Environmental Assessment (OP/BP- 4.01): implementation of the subproject will
construct 220kV Quang Ngai - Quy Nhon double-circuit transmission line with one
circuit installed in advance in the year of 2016 and construct one 220kV feeder bay at the
220kV Quang Ngai substation. Hence, the Policy OP/BP-4.01 will be applied to
guarantee substainability for the project investment and socio-environment aspects;
supply information of potential socio-environmental impacts of the subproject for
decision makers. Subproject is screened of environment and society in compliance with
the criteria in the OP 4.01 and categorized B for environment aspect; Environmental
safety tool that the subproject shall prepare is Environmental Management Plan.
- Forests Policy (OP/BP 4.36) is intended to support sustainable and conservation-
oriented forest management. The Bank helps borrowers harness the potential of forests to
reduce poverty in a sustainable manner, integrate forests into sustainable economic
development, and protect vital local and global environmental services and values of
forests. Local people, the private sector and interest groups in the affected forest area
should be consulted.
The policy is triggered considering that some subprojects may involve acquisition of
forest land for maintaining ROW of the power transmission lines. These activities may
have the potential to have adverse impacts on the rights and welfare of local people and
their level of dependence upon low quality natural forests and plantation forests. Impacts
on forests and associated mitigation measures will be included in the subproject EIA and
EMP.
The project will not fund any subproject (1) that would involve significant conversion or
degradation of critical forest areas or other natural habitats; (2) that contravenes
applicable international environmental agreements; and (3) that involves any conversion
or degradation of critical natural habitats, including adjacent or downstream critical
natural habitats
- Involuntary resettlement: implementation of the subproject will acquire land
permanently and temporarily to construct tower foundations of the T/L. Hence, when
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 9
applying this policy, objectives of this policy is to prevent from serious, long-term
difficulties, hunger and poverty and environment damages for the affected people during
the involuntary resettlement process. A resettlement plan for the subproject will be
prepared to reach the objectives of this policy.
3. SUBPROJECT DESCRIPTION
3.1 Subproject Objectives
Subproject “220kV Quang Ngai - Quy Nhon (Phuoc An) transmission line” is
constructed to:
- Guarantee power supply for Binh Dinh province from the year of 2016, supply
power source for new-constructed 220kV substations in Binh Dinh province in the phase of
2016-2020.
- Create 220kV power network connection between the North Central region and
South Central region, guarantee flexible and safe capacity support in power supply of the
National Grid.
- 220kV Quang Ngai- Quy Nhon transmission line will be 220kV trunk supplying
power for coal-fired power complex as well as nuclear power plant in future when load
demand of the Central region increases, especially in Da Nang, creating a 220kV trunk-line
in Central coastal region.
3.2 Subproject Scale
a) 220kV Quang Ngai - Quy Nhon (Phuoc An) transmission line
Main parameters of the 220kV Quang Ngai - Quy Nhon (Phuoc An) are as below:
- Starting point : 220kV busbar of the 220kV Quang Ngai substation
- Ending point : 220kV busbar of the 220kV Phuoc An switching substation
- Voltage level : 220kV
- Number of circuits : 02 circuits
- Length of the T/L : 139.988 km
- Right of way : from the center line to each side of 10.6m (total of 21.2m)
- Land use area, including:
+ Permanent land area for constructing tower foundations : 73,888 m2.
+ Affected land area within the ROW according to the Decree No. 14/20014/ND-CP
dated Feb. 26th
, 2014 of the GOV. : 2,965,626 m2.
+ Temporary affected land area by temporary works (warehouse, worker camp,…):
57,981.2 m2.
- Construction location:
+ Mo Duc and Duc Pho districts - Quang Ngai province
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 10
+ Hoai Nhon, Hoai An, Phu My, Phu Cat, Tay Son, An Nhon and Tuy Phuoc
districts - Binh Dinh province.
- Conductor : ACSR-330/43 (for line section with two-wire phase division
2xACSR-330 from the starting point - G34, length of
84.699km); ACSR-400/51 (for three-wire phase division
3xACSR-400 from G34 - the ending point, length of
55.289km).
- Earth wire : GSW-70
- Optical Fibre : OPGW-70.
- Insulator : Glass (ceramic) or Composite (insulator will be selected
through competitive bidding).
- Tower solution : Steel tower using equilateral angle iron, connection
between bars and panel by bolts and weld.
- Foundation solution : in-situ reinforced concrete
- Earthing wire : use types of ray-form and ray - rod earthing wire.
Table 1: Main typical parameters of the transmission line
No. Typical parameters Unit Value
1 Route length km 139,988
2 Number of turning angles angle 62
3 Maximum turning angle degree 91013’
4 Minimum turning angle degree 01028’
5 Longest side km 5,794
6 Shortest side m 183
7 Number of times crossing over 110kV transmission
lines time 2
8 Number of times crossing 220kV transmission lines time 1
9 Number of times crossing over below 35kV distribution
lines
time 57
10 Number of times crossing over communication lines time 7
11 Number of times crossing over traffic roads time 178
- Number of times crossing over inter-communal/inter-
village roads
time 169
- Number of times crossing over highways time 2
- Number of times crossing over provincial roads time 6
- Number of times crossing over North-South railway time 1
12 Number of times crossing over irrigational reservoirs time 4
13 Number of times crossing over rivers time 5
14 Number of effected houses house 38
Source: Investigation report prepared by Power Engineering Consulting JSC 4 in Jan. 2014
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 11
b) 220kV feeder bay at the 220kV Quang Ngai Substation
The 220kV feeder bay at the 220kV Quang Ngai substation will be constructed in
the existing 220kV Quang Ngai substation, land area for one 220kV feeder bay was
reserved in this substation. Hence, it is not necessary to expand the substation layout.
- Construction items of the feeder bay.
+ Equipment foundation: single foundation with in-situ reinforced concrete.
+ Equipment support pier: use hot-dip galvanized form steel connected by bolt,
suitable with the existing support piers in the substation.
+ Cable trench: mainly use the existing cable trench and build new cable trench
section to new-installed devices in this feeder bay with structure similar to the existing
cable trench, underground trench with cable support rack and galvanized cable.
- Power parts of the feeder bay:
Power parts of the 220kV feeder bay at the 220kV Quang Ngai substation consist
of the following items:
- Conductor, insulator and accessories.
- Equipment support pier.
- Earthing system.
- Pipe which power cable and control cable are passed through.
- Bearing cable and control cable.
3.3 Subproject Location
- The 220kV Quang Ngai - Quy Nhon (Phuoc An) transmission line has length of
139,888m, goes through 34 communes, 09 districts of 02 provinces of Quang Ngai and
Binh Dinh. Communes and districts crossed by the Subproject and coodinates of turning
angle (G) are listed in the following table:
Table 2: Length of the transmission line
No. Name of Province,
district, commune Length (m) No.
Name of Province,
district, commune Length (m)
A
QUANG NGAI
PROVINCE 32,383 4 An Phong commune 6,757
I Mo Duc district 3,025 5
An Tuong Dong
commune 10,355
1 Duc Lan commune 3,025 III Phu My district 18,974
II Duc Pho district 29,358 1 My Trinh commune 2,494
1 Pho Phong commune 3,413 2 My Hoa commune 6,475
2 Pho Nhon commune 8,686 3 My Hiep commune 10,005
3 Pho Ninh commune 2,000 IV Phu Cat district 8,881
4 Pho Hoa commune 3,367 1 Cat Lam commune 2,912
5 Pho Cuong commune 8,591 2 Cat Hanh commune 955
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 12
No. Name of Province,
district, commune Length (m) No.
Name of Province,
district, commune Length (m)
6 Pho Khanh commune 3,301 3 Cat Hiep commune 5,014
B
BINH DINH
PROVINCE 107,505 V Tay Son district 11,435
I Hoai Nhon district 30,186 1 Binh Thuan commune 3,864
1 Hoai Son commune 9,393 2 Tay An commune 5,052
2 Hoai Chau Bac commune 968 3 Tay Vinh commune 2,367
3 Hoai Chau commune 1,093 4 Tay Binh commune 152
4 Hoai Phu commune 4,232 VI An Nhon town 16,208
5 Xa Hoai Hao 5,124 1 Nhon Phuc commune 2,735
6 Xa Hoai Tan 5,297 2 Nhon Loc commune 8,493
7 T.Tr Bong Son 2,380 3 Nhon Tho commune 1,602
8 Xa Hoai Duc 1,699 4 Nhon Hoa ward 3,378
II Hoai An district 20,442 VII Tuy Phuoc district 1,379
1 An My commune 1,429 1 Phuoc An commune 1,379
2 An Thanh commune 1,901 Total 139,888
Source: Investigation report prepared by Power Engineering Consulting JSC 4 in Jan
2014
Table 3: Coodinates of turning angle (G)
(according to coodinates system VN2000, central longitude 1110, zone 6
0)
No. Turning
angle
Coodinates No.
Turning
angle
Coodinates
X Y X Y
1
Starting
point 1,649,621 273,750 33 G33 1,582,723 281,005
2 G1 1,649,437 273,168 34 G34 1,577,984 284,339
3 G2 1,646,080 271,639 35 G35 1,575,237 286,167
4 G3 1,645,324 272,026 36 G36 1,572,465 283,929
5 G4 1,644,881 272,371 37 G37 1,571,533 284,016
6 G5 1,644,285 272,480 38 G38 1,571,100 284,448
7 G6 1,643,505 272,461 39 G39 1,569,932 284,544
8 G7 1,642,024 273,023 40 G40 1,567,321 285,172
9 G8 1,640,051 272,886 41 G41 1,563,777 285,165
10 G9 1,638,433 273,611 42 G42 1,560,860 284,609
11 G10 1,637,372 274,548 43 G43 1,557,052 282,477
12 G11 1,636,070 276,251 44 G44 1,552,087 283,388
13 G12 1,633,593 281,200 45 G45 1,546,906 285,093
14 G13 1,630,469 282,406 46 G46 1,545,086 284,886
15 G14 1,628,724 282,789 47 G47 1,543,798 285,362
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 13
No. Turning
angle
Coodinates No.
Turning
angle
Coodinates
X Y X Y
16 G15 1,628,118 283,646 48 G48 1,541,855 284,828
17 G16 1,623,188 283,345 49 G49 1,540,898 284,648
18 G17 1,619,119 283,985 50 G50 1,539,396 284,031
19 G18 1,615,571 284,340 51 G51 1,536,913 285,258
20 G19 1,611,888 283,531 52 G52 1,535,036 285,837
21 G20 1,609,029 283,098 53 G53 1,535,039 285,844
22 G21 1,606,068 281,897 54 G54 1,533,847 288,728
23 G22 1,602,334 284,307 55 G55 1,532,944 292,140
24 G23 1,598,076 283,882 56 G56 1,532,198 292,410
25 G24 1,595,792 282,973 57 G57 1,532,125 292,950
26 G25 1,595,083 282,742 58 G58 1,531,934 292,920
27 G26 1,593,814 282,219 59 G59 1,531,728 292,945
28 G27 1,592,726 282,704 60 G60 1,531,537 292,930
29 G28 1,590,655 282,602 61 G61 1,531,359 292,886
30 G29 1,590,063 281,987 62 G62 1,529,671 293,777
31 G30 1,587,399 282,995 63 ĐC 1,528,735 294,432
32 G31 1,585,692 282,067
Source: Investigation report prepared by Power Engineering Consulting JSC 4 in Jan
2014
- Location of the 220kV feeder bay at the 220kV Quang Ngai substation
220kV feeder bay at the 220kV Quang Ngai substation will be constructed in the
existing 220kV Quang Ngai substation, land area for one 220kV feeder bay was reserved
in this substation. Hence, it is not necessary to expand the substation layout.
Location of the T/L of the subproject was accepted by Quang Ngai and Binh Dinh
Provincial People Committees in the following documents:
- Correspondence No. 1891/UBND-CNXD dated Jul. 7th
, 2008 of Quang Ngai
Provincial People Committee regarding “Agreement about the route direction for the
220kV Quang Ngai- Quy Nhon transmission line”.
- Correspondence No.3725/UBND-CNXD dated Sept. 20th
, 2013 of Quang Ngai
Provincial People Committee regarding “Extension of agreement about the route
direction for the 220kV Quang Ngai - Quy Nhon transmission line”
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 14
- Correspondence No. 3593/UBND-KTN dated Otc. 27th
, 2011 of Binh Dinh
Provincial People Committee regarding “Construction location of the 220kV substation
at Phuoc An commune, Tuy Phuoc district”.
- Correspondence No. 263/UBND-CN dated Feb. 3rd
, 2009 of Binh Dinh
Provincial People Committee regarding “Agreement on the route direction of the 220kV
Quang Ngai - Quy Nhon transmission line”
3.4 Volume of construction
3.4.1 Construction Volume of the 220kV Quang Ngai- Quy Nhon (Phuoc An)
transmission line
a) Power tower foundation
With total length of the transmission line of 139.988km, total number of
foundations are 354 with 351 columnar foundations and 3 plate foundations (VT142,
VT143, VT296), in which there are 80 tower foundations in Quang Ngai province and
274 tower foundations in Binh Dinh province. Summary of construction volume for
tower foundations is shown in the below table:
Table 4: Sumary of tower foundation construction volume
No. Items Unit Volume Remarks
1 Excavation works
a Soil excavation for tower
foundation and earthing
m3 165,093.6
b Rock excavation m3 15,600.9
c Soil excavation for filling m3 2,743.5
d Soil excavation for
banking trench foot
m3 3,540.9
2 Filling works
a Soil filling for foundation
pit and earthing
m3 160,887.4
b Leveling for the
construction site and
service road
- Filling, leveling for
gathering construction
materials
m3 20,529
- Constructing new roads
for construction
m3 1,554
- Repairing road for
construction
m3 12,101.5
c Leveling, banking up
tower foundations
- Rock for constructing
foundation embankment
m3 2,192.8
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 15
No. Items Unit Volume Remarks
and paving surface of the
trench head
- Soil filling for foundation
embankment
m3 17,197.8
3 Concrete works
a Stone concrete 4x6, M50 m3 2,819.0
b Stone concrete 2x4, M200 m3 17,559.8
c Reinforcing steel ton 1,334.7
d Volume of steel towers ton 7,044.2
(Source: Technical Design prepared by PECC4, in Jan 2014)
b) Power post
Construction volume of power posts are:
- Volume of form steel: 7,044.16 tons
- Anchor bolt: 99.28 tons
c) Conductor
Total length of conductor types used for the subproject:
- Conductor ACSR-330: 254.1 km.
- Conductor ACSR-400: 165.87 km.
d) Lightning conductor and optical fibre
+ Lightning conductor GSW-70: 139.99 km.
+ Lightning conductor combined with optical fibre OPGW-70: 141.69 km.
e) Insulator and conductor accessories
- Insulator: At present, in Vietnam, there are two types of insulators of composite
and ceramic or glass, each type has typical advantages and disadvantages, so insulator for
the 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line will be selected through
competitive bidding.
- Accessories for suspending conductor: Accessories for suspending conductor and
lightning conductor will be suitable with conductor size and ensure conditions of
corrosion and durability reserve factor as regulations.
Accessories for suspending conductor are expected to be imported in sync with
insulator though competitive bidding. Types of cable rings, hangers, couplings shall have
breaking load suitable with insulator. Insulator strings are designed to have
electromagnetic balancing ring and arcing horn to improve voltage difference between
bowls of insulator strings and avoid corona effect in the surface of insulator string.
+ Bear lock of conductor and lightning conductor uses fixed brace bolt lock.
+ Conductor and lightning conductor stay locks use clamp stay lock.
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 16
+ Bear and stay lock of lightning conductor combined with optical fibre use
dedicated locks for optical fibre.
f) Compensated damper suspend on insulation string
Because the T/L goes through mountainous topographical area, difference of
elevation between tower positions is rather large, some positions of columnar posts will
reduce gravity tower distance, cause insulating string will be deflected over permission
limit, and not guarantee required distance on tower.
To compensate the reduction of gravity tower distance, solution is to suspend
compensated damper on support insulation string. Weight of compensated damper is
calculated for each position based on allowable insulation string deflection angle.
Types of compensated damper used on the line are TB-100, TB-200, TB-300, TB-
400, corresponding weight are 100kg, 200kg, 300kg, 400kg.
g) Earthing
All towers in the transmission line will be grounded suitable with resistivity of each
area which the T/L crosses over, value of grounded resistivity shall meet standard and
regulations.
Earthing on the 220kV transmission line will use ray-type earthing: TD4x30;
TD4x40 and ray- rod combination earthing: TD4x20-16; TD4x30-24; TD4x40-28.
- Ray-type earthing TD4x30 : consists of 4 rays grounded by round steel with
dimension of 12mm, length of each ray is 30m.
- Ray-type earthing TD4x40 : consists of 4 rays grounded by round steel with
dimension of 12mm, length of each ray is 40m.
- Ray-rod combination type earthing TD4x20-16 : consists of 4 rays grounded by
round steel with dimension of 12mm, length of each ray is 20m. Each ray connected with
4 steel rod Lx63x63x6 length of 2,5m.
- Ray-rod combination type earthing TD4x20-24 : consists of 4 rays grounded by
round steel with dimension of 12mm, length of each ray is 30m. Each ray connected with
6 steel rod Lx63x63x6 length of 2,5m.
- Ray-rod combination type earthing TD4x20-28 : consists of 4 rays grounded by
round steel with dimension of 12mm, length of each ray is 40m. Each ray connected with
10 steel rod Lx63x63x6 length of 2,5m.
3.4.2 Volume of the 220kV feeder bay items at the 220kV Quang Ngai Substation
- Volume of main erection of the 220kV feeder bay construction at the 220kV
Quang Ngai Substation as the following table:
Table 5: Total volume of feeder bay construction part
No. Type Unit Volume Remark
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 17
1 Disconnector foundation
a Digging grouding tower foundation m3 183.8
b Backfilling foundation base m3 153.3
c Concrete types m3 46.5
d Reinforcing concrete types ton 1.1
2 Equipment post ton 4.2
3 Troughing
a Digging troughing m3 3.8
b Backfilling troughing m3 1.3
c Concrete types m3 1.6
d Reinforcing troughing ton 0.24
(Source: Technical design prepared by PECC4 in January 2014)
- Volume of electric part of the feeder bay
Table 6: Total volume of electric part of the 220kV feeder bay at the 220kV Quang
Ngai substation
No. Type Unit Volume Remark
1 Conductor, insulator and accessories
a Standing insulator 220kV, supporting 1
conductor AAC-885mm2, including
accessories and supporting tower
Piece 6
b Aliminum conductor AAC-885mm2 m 300
c Single insulator hanging string 220kV for
hanging 1 conductor AAC-885mm2
String 3
d Branch clamp for 01 conductor AAC-
885mm2 connecting with 01 conductor
AAC -885mm2
Piece 3
e Branch clamp for 01 conductor AAC-
885mm2 connecting with 01 conductor
ACSR -1000mm2
Piece 6
f Branch clamp for 02 conductor ACSR-
330mm2 connecting with 01 conductor
AAC-885mm2
Piece 3
g Standing insulator 220kV Piece 6
2 Equipment post
a Circuit breaker 245kV - 01 phase type 3
b Disconnector 245kV with 3 phases put
outside
2
c Disconnector 245kV with 1 phases put
outside
3
d Current transformer 245kV - 01 phase
type
3
e Current transformer 245kV - 01 phase
type
3
3 Equipment grounding system
a Equipment earthing (ceiling copper kg 124,9
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 18
No. Type Unit Volume Remark
conductor M120mm2, 1,086kg/km)-115m
b Earthing the tower supporting equipment
(ceiling copper conductor M120mm2,
1,086kg/km)-216m
kg 234,6
c Copper terminal for conductor M120mm2 Piece 120
d
Exothermic Welds
weld
joint
54
e Bolt, nut, ring (M12x40mm) Set 136
f Clamp earthing wire into supporting
tower
Piece 50
4 Earthing system cabinet
a Ceiling copper conductor M70mm2
(612kg/km)-08m kg 4,9
b Copper terminal for conductor M70mm2 Piece 8
c Bolt, nut, ring (M12x40mm) Set 8
5 Conduit-powered cable and control
cable
a Pipe PVC 100
b Pipe PVC 60
c Pipe joint L shape for pipe 100
d Pipe joint L shape for pipe 60
6 Force cable and control cable
a Force cable with copper core insulator
PVC, with protection of steel belt, nti-
jamming metal coated and anti-fire spread
m 2.800
b Accessories connecting cable Batch 1
(Source: Technical design prepared by PECC4 in January 2014)
3.5 Volume of main works
3.5.1. Volume of main works pre- and construction phase.
Pre- construction phase
- Land acquisition for tower foundation construction;
- Improving or earthing for house/structure under the ROW;
- Cut down tree, crops on permanent land acquisition;
- Cut down tree under the ROW for construction;
- Reduce the posibility of land use/house/structure under the ROW.
Construction phase:
- Excavation, embankment;
- Transporting marterial and construction euqipment;
- Preparing mortar, reinforced concrete form;
- Installing steel tower;
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 19
- Installing electric equipment and conductor;
- Test and operation of the subproject.
3.5.2 Transportation
Supply source of marterial, equipment and transport distance:
- Construction materials such as ciment, sand, stone, brick…. are bought from
Quang Ngai and transported to construction location by truck, distance of 25km.
- Electric equipments, materials are imported to the Da Nang port, transported to
construction location by truck, distance of 85km.
- Loading machines, equipment up and down at the ports, susbstation construction
location by lifting crane, winch and pulley system.
3.5.3 Manpower for the subproject contruction
- 220kV Quang Ngai – Quy Nhon (Phuoc An) transmision line:
Construction and erection forces, including construction teams specilized in line are
07 teams (each team is responsible for constructing a transmission line section).
Workforce for erection team specialized in line incluyes:
+ Direct manpower : 80 persons.
+ Indirect manpower : 05 persons.
+ Site management board : 03 persons.
Remark: The specilized erection team is construction team specilized in each work,
depending on the actual manpower of construction unit, number of manpowers could be
decreased (each worker can hold more than a job).
- 220kV feeder bay at the 220kV Quang Ngai Substation:
Construction of the 220kV feeder bay implemented by the specialzed erection team.
Total manpower on site is 40 persons as expected, in which:
+ Teachical officer, manager : 6 persons.
+ Erection worker : 30 persons.
+ Cleaner : 4 persons.
The above manpower is arranged in compliance with construction units as follows:
+ Mechanical tranportation unit: transporting equipments, materials
+ Mechanical construction unit: executing construction items like erecting
distribution system such as supporting tower and equipments...
+ Prosessing unit: Proceed steel hot dip gavanized structures
+ Machine installation unit: installing primary and secondary electrical part,
troughing system and cabinet in control house completing under this subproject.
+ Communication system installation unit: installing communication
system/SCADA.
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 20
+ Testing Unit: Testing custom relay, test specifications of all equipments in the
station.
3.6 Subproject Implementation Schedule and Total Investment
3.6.1 Subproject Implementation Schedule
- 220kV feeder bay at the 220kV QuangNgai substation:
Pursuant to power supply requirement, construction schedule and time to put the
subproject into operation are expected as:
- Preparation work : 0.5 month.
- Time of implementing construction part : 1 month
- Time of implementing power part: 1 month
- Time of testing and finalization: 1 month
Total time of the subproject construction: 3.5 – 4 months
- 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line:
Subproject construction time is anticipated to be 20 months, not include site
clearance and compensation implementation time.
+ Prepare and approve technical design and total cost estimate: Sept. 2014
+ Prepare bidding document, bidding, and purchase equipment and materials: Oct.
2014
+ Prepare detailed drawing, estimate installation and construction bidding backage:
Mar. 2015
+ Installation and construction: Apr. 2015
+ Testing, adjustment, acceptance and hand over: Dec. 2016.
Construction schedule of main items are as below:
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 21
Table 7: Construction Schedule of transmission line part in the 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line
Subproject
No. Work items Compensation Construction phase is expected to be 20 months
1 2 3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
I. Preparation works
I.1 Prepare Site Clearance
Dossier
I.2 Compensation works
II. Foundation excavation
and Casting
II.1 Excavation and elevation
works
II.2 Foundatin casting
II.3 Foundation filling
III. Tower manufacture
and installation
III.1
Manufacture and
acceptance of sample
tower
III.2 Mass manufacture
III.3 Tower installation
IV. Construct embankment
to protect foundation
V. Pull and stretch
conductor
VI. Finalization
-
TEP – 220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line Feasibility Study
Environmental Management Plan 22
VII. Sub-acceptance
VIII. Clear remaining issues
IX. Acceptance and hand
over
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 23
3.6.2. Total cost investment
Total investment capital of subproject is 999,248,472,316 VND
Table 8: Total investment capital of subproject
No. Cost Items
220kV
transmission
line
220kV feeder
bay
Costs under
the subproject Total
1 Construction cost 695,069,138,119 2,297,686,964 697,366,825,083
2 Equipment cost 292,612,526 9,908,042,290 10,200,654,816
3 Project
Management cost 8,080,103,542 - 8,080,103,542
4 Engineering
costs 19,720,081,158 595,286,966 13,910,308,060 34,225,676,185
5 Other costs 8,922,481,244 622,273,728 56,156,867,413 65,701,622,385
6 Provision costs 174,653,379,266 2,013,493,492 7,006,717,547 183,673,590,305
TOTAL 906,737,795,856 15,436,783,440 77,073,893,020 999,248,472,316
4. BASIC DATA
4.1 Geographical location and populations
Geographical location:
220kV Quang Ngai- Quy Nhon (Phuoc An) transmission line starts from the 220kV
Quang Ngai substation (under construction) to the ending point of the 220kV Phuoc An
substation (under construction). The transmission line will go through 34 communes, wards in
Binh Dinh and Quang Ngai provinces. Details are as below:
- Section through Quang Ngai province (from the starting point- G16) includes Mo
Duc district (Duc Lan commune), Duc Pho district (Pho Phong, Pho Nhon, Pho Ninh, Pho
Hoa, Pho Cuong and Pho Khanh communes)
- Section through Binh Dinh province (from G16 to ending point) includes Hoai
Nhon district (Hoai Son, Hoai Chau Bac, Hoai Chau, Hoai Phu, Hoai Hao, Hoai Tan
commune, Bong Son and Hoai Duc town), Hoai An district (An My, An Thanh, Anh Phong,
An Tuong Dong communes), Phu My district (My Trinh, My Hoa, My Hiep communes),
Phu Cat district (Cat Lam, Cat Son, Cat Hiep communes), Tay Son district (Binh Thuan,
Tay An, Tay Vinh communes), An Nhon town (Nhon Phuc, Nhon Loc, Nhon Tho, Nhon
Hoa communes), Tuy Phuoc district (Phuoc An commune).
Population:
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 24
220kV Quang Ngai - Quy Nhon (Phuoc An) transmission line goes through Binh
Dinh and Quang Ngai provinces.
- Section through Quang Ngai province: Mo Duc and Duc Pho districts.
- Section through Binh Dinh province: Hoai Nhon, Hoai An, Phu My, Phu Cat, Tay
Son and Tuy Phuoc districst, An Nhon Town.
Communes that the subproject goes through mainly are midland and delta, local
people mainly are the Kinh.
Population density in comunes is not uniform, people mainly live in two side of
inter-communal/inter-village roads.
Table 9: Data of area, population, density, number of villages in communes of the
subproject
No. Commune Area (km2)
Population
(person)
Density
(person/km2)
Number
of hamlets
and
villages
1 Duc Lan 29.62 13,533 457 4
2 Pho Phong 54.07 9,652 179 7
3 Pho Nhon 40 7,201 180 9
4 Pho Ninh 22.25 10,475 471 5
5 Pho Hoà 17 4,406 259 4
6 Pho Cuong 48.5 15,450 319 7
7 Pho Khonh 55.6 14,300 257 7
8 Hoai Son 57 11,514 202 12
9 Hoài Chou Bac 21.25 10,637 501 8
10 Hoài Chou 23 9,770 425 9
11 Hoài Phy 39.66 10,173 256 9
12 Hoài Hao 37.93 13,842 365 6
13 Hoài Ton 27.03 19,594 725 7
14 thi tran Bong Son 17.04 21,529 1,263 11
15 Hoai Duc 63 15,779 250 10
16 Ân My 32.58 7,602 233 5
17 Ân Thanh 17.11 9,674 565 6
18 An Phong 30.62 7,514 245 6
19 An Tuong Dong 47.59 5,169 109 7
20 My Trinh 51.44 7,404 144 8
21 My Hoà 42.98 10,923 254 7
22 My Hiep 55.65 15,569 280 17
23 Cot Lom 69.42 7,399 107 5
24 Cat Son 113.4 4,994 44 3
25 Cot Hiep 41.02 7,715 188 3
26 Phuoc An 33.69 19,740 585.9 8
(Source: Report on socio- economic situation in communes in the subproject area in 2012)
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 25
4.2 Topography
The transmission line will go on complicated topographical area.
+ Route sections G11-G12, G15-G22, G33-G35, G60-ĐC go on transitional area
from mountain and midland to lowland with average slope from 100-25
0, mountains with
height over 300m. Route sections mainly cross thorugh crop land, planted forest alternated
with natural forest.
+ Remaining route sections mainly go on flat land areas and field of delta. Those
route sections cross thorugh rice fields, crop lands and some acacia planting forest and
residentail areas.
The whole subproject area will not affect badly to construction and activities of
infrastructure works in general and the transmission line in particular. Details are as below:
* Route section in Quang Ngai province:
- Route section from starting point – G9 mainly goes on flat land, crosses through
rice and crop fields of delta area in Duc Lan, Pho Phong, Pho Nhon commune. Position of
G2 locates on hill side planting acacia with elevation of about 100m.
- Route section G9 – G11 has the first half of the section go on flat land, the
remainimg half and position G9 go on acacia planting hill side with elevation of 30m.
- Route section from G11 - G16 mainly go on acacia and Azadizacta indica tree
planting hill side of local people, slope of 10-200, and elevation of 60-230m.
* Route section in Binh Dinh province:
- Route section from G16 - G19, G20-G21 mainly goes on acacia planting hill side,
slope varies from 100 to 25
0, elevation of 140-230m.
- Route section from G19 – G20, G21 – G22 mainly goes on acacia palnting hill side
alternated with valley, slope varies from 50 to 20
0, elevation of 20-230m.
- Route section from G22 - G27 mainly goes on flat filed land, sometimes alternated
with residential area, slope varies from 30 to 10
0, elevation of 10-30m.
- Route section from G27 - G31 mainly goes on hill side alternated with valley, slope
varies from 30 to 20
0, elevation of 10-110m.
- Route section from G31- G33 mainly goes on hill side alternated with valley, slope
varies from 30 to 20
0, elevation of 10-110m.
- Route section from G27- G28, G33-G35 mainly goes on hill side, slope varies from
100 to 25
0, elevation of 100-300m.
- Route section from G35- G41mainly goes on hill side, slope varies from 100 to 25
0,
elevation of 100-300m.
- Route section from G41-G60 goes on flat land, crosses through fields alternated with
residential area (as section G45-G47), slope varies from 10 to 5
0, elevation of 5-10m.
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 26
- Route section from G60- G62 mainly go on hill side, slope varies from 50 to 20
0,
elevation of 40-120m.
- Route section from G62- to end point mainly goes on hill side crosses through fields
alternated with residential area, slope varies from 10 to 5
0, elevation of 5-10m
Description sensitive features within/along the ROW in each section are presented in the
below table:
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 27
Table 10: Description sensitive features within the ROW
No Section
Sensitive features within the ROW (21.2m)
Forest cemeteries/
graveyards
(in route’s
length)
Highway/
railway River/ waterway
Number of
houses/ structures
Forest owner
affected area
(ha) The status of forest
Produc
tion
Protect
ion
House structures
1 Starting
point – G2
Once passing
through North –
Sought railway
2 G2 – G7 Phổ Phong CPC 1.61
2-4 year Acacia
forest
100m
(G6–G7)
Once passing
through
Highway No 24
Trà Câu River in
G6-G7 7 11
3 G7 – G11 Phổ Nhơn CPC 2.65 1-5 year Acacia
forest
150m
(G7–G9) 4 2
4 G11 – G12 Phổ Ninh, Phổ Hòa
CPC 8.50
1-5 year Acacia
forest
5 G12 – G16 Phổ Cường, Phổ
Khanh CPC 14.95
2-4 year Acacia
forest
Hốc Cây Lake
in G12-G13
6 G16 - G24
Hoai Nhon
Protection forest
management Board
17.4
Acacia and Hopea
odorata Roxb forest
with the reserve
estimated at 959.4
m3. The average
diameter is from 5-
15cm, the average
height is from 7-12m
350m
(G19–G21)
Hố Giang Lake in
G18-G19 10 13
7 G20 – G22 Hoài Hảo CPC 2.44 1-5 year Acacia
forest
8 G24 – G35
Phù Mỹ Protection
forest management
Board
6.3 5-7 year Acacia
forest 110m
(G26– G27;
G29–G30)
- Once passing
through
provincial road
(G24-G25)
- Once passing
An Lão River
(G25-G26)
Đá Bàn River
(G30-G31)
11 23
1.8 Natural forest, type
IIB
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 28
No Section
Sensitive features within the ROW (21.2m)
Forest cemeteries/
graveyards
(in route’s
length)
Highway/
railway River/ waterway
Number of
houses/ structures
Forest owner
affected area
(ha) The status of forest
Produc
tion
Protect
ion
House structures
through
provincial road
(G31-G32)
Kim Sơn River
(G26-G27)
Liên Chiều Lake
(G29-G30)
9 G35 – G42
Chí Hòa Lake
(G40-G41)
La Tinh River
(G41-G42)
Đại Sơn River
(G39-G40)
3 2
10 G42 – G44 Cát Hiệp CPC 2.31 2-5 year Acacia
forest
- Once passing
through
provincial road
(G42-G43)
9 18
11 G44 – G45 Bình Thuận CPC 1.27 1-5 year Acacia
forest
12
G45 – G62
– Ending
point
500m
(G46–G47;
G48–G49;
G50–G52;
G53–G54)
Once passing
through
Highway No 19
(G54-G55)
Côn River (G49-
G50)
Đồng Lợi Lake
(G50-G51)
1 6
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 29
4.3 Climate
The transmission line locates on Quang Ngai and Binh Dinh provinces which have
general characteristics of South-East tropical monsoon climate, in addition, climate and
weather regime of the route area also have characteristics of coastal Central region with
typical characteristics as below:
Because of wind stop effect of Truong Son mountain range which is closed to the
sea at Hai Van mountain pass, tropical air at the south of Hai Van pass denature fully,
therefore it is less cold in winter, the lowest monthly average temperature is 18.8oC
(January), the absolute lowest air temperature is 10.2oC, average temperature difference
between the hottest and coldest months is about 6-7oC.
Rainy season starts from August and ends on January, the highest rainfall months
are October and November with average rainfall of 500-600 mm. Total rainfall in rainy
season account for 80-90% total annual rainfall, dry season is from February to July,
account for 10-20% total annual rainfall.
Remarkable weather phenomena in this region are storm, thunder and hot and dry
westerly wind. Storm season lasts from September to November, annualy there are 1-2
storms in this region with strong effects.
Thunder is little, thunder season coincide with summer monsoon, from April to
October, an average number of thundering days are 50-80.
Hot and dry westerly wind in the first half of summer, from April to August which is
rather strong is the reason of extreme air temperature over 40oC and low humidity
under 25-30%.
* Wind:
+ Prevailing wind direction
From October to March (winter monsoon): N, NW (North, North West)
From April to September (summer monsoon): E, W, SE (East, West, South
East).
+ Average wind speed: from1.6 m/s
+ Wind Pressure: According to wind pressure division map in National Technical
Regulation of natural condition data in construction QCVN 02:2009/BXD, wind pressure in
the route area is defined as below:
Table 10: Standard wind pressure with repetition cycle of wind in ten years and in 20
years.
Route Section Pressure
area
Wo (kN/m2)
3s, 10 years
Wo (kN/m2)
3s, 20 years
- G25-G33: Hoai An district IIB 0.83 0.95
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 30
(Binh Dinh province)
- G44-G49: Tay Son district
(Binh Dinh province) IIB 0.83 0.95
- The remaining sections IIIB 1.09 1.25
(Source: Investigation Report issued by PECC4 in 2014)
* Air Temperature
Annual average temperature: 26 (oC)
Highest Temperature: 42 (oC)
Lowest Temperature: 13 (oC)
* Rainfall
Annual average rainfall: 2,100 (mm)
Highest daily rainfall: 525 (mm)
It is noted that heavy rain normally is long in a large area due to storm in East sea or
tropical low pressure.
* Air relative humidity (%)
Annual average relative humidity: 82 (%)
Lowest relative humidity: 18 (%)
Highest relative humidity of 100% normally apprears in rainy season.
* Thunderstorm
Average number of thundering days in year: 44.8 (days)
Lightning density: 8.2 (times/km2/year)
4.4 Existing condition of environment quality in the subproject area
Air quality in the subproject area
Results of measurement and analysis of air quality in the subproject area are shown
in the table below.
Table 11: Results of ambient air quality analysis and noise in the subproject area
No. Parameters Unit
Test results
QCVN
26:2010/
BTNMT
QCVN
05:2009/B
TNMT
KK1 KK2 KK3 KK4 KK5 KK6 (From 6-
21h)
(average
in 01hour)
1
Air
temperatu
re
0C 26.5 27.5 26.5 27.5 28.5 26.5 - -
2 Humidity % 78.6 77.2 78.0 78.6 76.2 78.0 - -
3
Wind
speed m/s 1.8 1.4 1.9 1.8 1.7 1.8 - -
4 Noise dBA 51.3 56.4 54.5 52.9 58.7 53.2 70 -
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 31
5
Suspende
d dust mg/m
3 0.2 0.37 0.32 0.28 0.45 0.33 - 0.30
6 SO2 mg/m3 0.006 0.016 0.009 0.004 0.012 0.007 - 0.35
7 NOx mg/m
3 0.003 0.011 0.06 0.004 0.012 0.007 - 0.2
8 CO mg/m3 1.64 2.60 1.60 1.13 2.80 1.54 - 30
9 Pb mg/m3
Not-
detect 0.0013
Not-
detect
Not-
detect 0.0014
Not-
detect - 0.5
(Source: Environment Impact Assessement Report of the 220kV QuangNgai-Quy Nhon (Phuoc An),
April 2014)
Remarks:
- Sampling at the height of 1.5m compared with the ground.
- Coordinates of measurement and sampling locations according to Coordinate system
VN2000, central longitude 111000, zone 6:
KK1 X: 1649600 Y: 273750 Starting point
KK2 X: 1643801 Y: 272424 Near G6 (near Pho Phong industrial zone)
KK3 X: 1590109 Y: 281834 Provincial road No. 630 near G29 at Tang
Bat Ho town.
KK4 X: 1543583 Y: 285292 Provincial road No. 636 near G46 and
new rural planning zone of Tay An
commune
KK5 X: 1532433 Y: 292323 Near Nhon Hoa Industrial zone
KK6 X: 1528508 Y: 294374 Near the ending point
* Comments: From above results, it can be seen that air quality in the subproject area
is normal; results of measurement and analysis show that except suspended dust in KK5,
KK6 locations is higher than the allowable limit, corresponding to 15 and 1.1 times, other
analysis parameters are in the allowable limits of QCVN 05:2009/BTNMT (average in 1
hour) and QCVN 26:2010/BTNMT (from 6-21h).
Surface water quality in the subproject area
Table 12: Results of surface water quality in the subproject area
No. Parameters Unit Test results
QCVN
08:2008/BTNM
T
NM1 NM2 NM3 NM4 NM5 NM6 Column B2
1 pH - 6.68 5.91 7.10 6.71 5.25 7.01 5.5-9
3 DO mg/L 6.3 5.3 6.9 6.2 2
Total suspended
solid (TSS) mg/L 12.1 24.5 18.3 14.6 100
5 COD mg/L 7.5 9.6 7.7 7.4 9.7 7.4 50
BOD5 (20oC) mg/L 4.5 6.3 4.7 4.5 6.1 3.5 25
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 32
6 NH4+ mg/L 0.0015 0.0035 0.0024 0.0022 0.0033 0.0018 -
7 NO3- mg/L 0.116 0.237 0.127 0.147 0.227 0.135 15
8 NO2- mg/L 0.0034 0.0097 0.0041 0.0049 0.0081 0.0052 0.05
9 PO43-
mg/L 0.0037 0.0072 0.0058 0.0052 0.0072 0.0062 0.5
10 Cu mg/L 0.0051 0.0083 0.0067 0.0053 0.0082 0.0063 1
11 Fe mg/L 1.26 2.34 1.32 1.15 2.32 1.32 2
12 Niken mg/L 0.0008 0.0031 0.0021 0.0019 0.0029 0.0016 0.1
13 Zn mg/L 0.017 0.024 0.017 0.016 0.022 0.014 2
14 Pb mg/L 0.008 0.017 0.009 0.007 0.0016 0.0008 0.05
15 Cr III mg/L 0.00031 0.00017 0.00015 0.00013 0.00026 0.00016 1
16 Coliform
MPN/10
0mL 135 380 489 225 423 125 10,000
(Source: Environment Impact Assessement Report of the 220kV QuangNgai-Quy Nhon (Phuoc An),
April 2014)
Remarks:
- Coordinates of measurement and sampling locatiosn according to Coordinate system
VN2000, central longitude 111000, Zone 6:
NM1 X: 1649609 Y: 273606 In Song Ve south channel
NM2 X: 1643321 Y: 272407 In Tra Cau river
NM3 X: 1595307 Y: 282517 In An Lao river near G25
NM4 X: 1593510 Y: 282212 In Kim Son river near G27
NM5 X: 1558183 Y: 283160 In La Tinh river near G45
NM6 X: 1538537 Y: 284475 In Con river near G42
* Comments: From the above results, it can be seen that the quality of surface water
in the subproject area is good, analyzed parameters are in the allowable limits according to
QCVN 08:2008, column B2.
Soil environment quality of the subproject area
Table 13: Results of soil sample analysis in the subproject area
No. Parameters Unit
Test results QCVN
03:2008/BTNMT
MĐ1 MĐ2 MĐ3 (Agricultural
land)
1 As mg/Kg 0.005 0.016 0.007 12
2 Cd mg/Kg 0.004 0.007 0.003 2
3 Cu mg/Kg 0.46 0.32 0.21 50
4 Pb mg/Kg 0.003 0.007 0.003 70
5 Zn mg/Kg 2.16 4.21 2.72 200
(Source: Environment Impact Assessement Report of 220kV QuangNgai-Quy Nhon (Phuoc An),
April 2014)
Remarks:
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 33
Coordinates of measurement and sampling locations according to Coordinate system
VN2000, central longitude 111000, Zone 6:
MĐ1 X: 1649600 Y: 273750 Starting point
MĐ2 X: 1590063 Y: 281987 G29
MĐ3 X: 1528508 Y: 294374 Near the ending
point
* Comments: From the above results, it can be seen that parameters of soil sample
meet requirements in QCVN 03:2008/BTNMT about the allowable limit of heavy metals in
soil (column of agricultural land).
4.5 Socio-economic Features
4.5.1 Economic
a) Agriculture – Forestry - Fishery
* Quang Ngai province:
Agriculture, forestry and fishery production in 2012 reached 3,061.1 billion VND
(1994 constant price), an increased of 5.9% compared to the 2011. Agricultural productivity
was high, and agricultural production value grew higher.
Regarding farming, food production reached 461,706 tonnes, an increase of 6.6%
compared to 2011, and an decrease of 0.56% compared with 2011. Planted food crop area
was estimated at 84,085ha, an increase of 1.7% compared to 2011. Paddy field area was
estimated at 73,489ha, an increase of 1.4% compared to 2011, the productivity reached 55.3
kg/ha, an increase of 2.8 hectogram/ha compared to 2011, the output reached 406.4
thousand tons, an increase of 6.8% compared to 2011; cassava production reached 390.9
thousand tons, an increase of 6.4% compared to 2011. Sugarcane area reached 5,700
hectares, up 2.1% compared with 2011, production reached 306.6 thousand tons, an increase
of 6% compared to 2011.
Regarding livestock, there are 63,596 buffalo, an increase of 7.9% compared to the
same phasein 2011, the are 273,126 cows, an increase of 1.3%, the proportion of crossbred
cows is 48.1% which is up 0.8% compared with 2011, there are 487,182 pigs which is
approximately the same as in 2011.
Regarding forestry, the total forest area in the province is 260,368 ha, an increase of
1.8% compared to the same phasein 2011, the forest coverage rate reached 46.3%, up 2.2%
compared with 2011
Regarding fishery, the production reached 126.96 thousand tons, up 12% compared
with 2011. Total fishery area is estimated at 1,406 hectares, up 0.3% compared with 2011;
in which there is 615 ha of shrimp farming area, down 1.4% compared with 2011. The
output reached 6,638 tons, and is the same as 2011, in which shrimp farming reached 5,293
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 34
tons, down 1.1%. Salt production area is 135 ha; its production reached 9,720 tons, up 2.9%
compared with 2011
* Binh Đinh province:
Agriculture, forestry and fishery develops comprehensively and effectively. The
production value in 2012 (1994 constant price) was estimated at 5,531.5 billion, an increase
of 5.41% compared to 2011. In which, agriculture accounts for 3590.1 billion, which
increased 4.02%; forestry accounts for 267 billion, which increased 14.2%; and fishery
accounts for 1674.4 billion, which increased 7.16%.
Regarding farming, production value was estimated at 2,037.4 billion, down 0.56%
compared with 2011. Total annual tree planted area is estimated at 165,920 ha, down 0.4%
compared with 2011; in which, there is 119,505 hectares of food crop, down 0.6%, reaching
697,681 tonnes in output which is up 0.7%; and there is 111,242 ha area of paddy field
which is down 1% compared to 2011 (caused by season converting), but the average yield is
estimated at 58.6 hectogram/ha (the highest yield so far), which is up 1.4 % and is estimated
at 651,828 tonnes of output, an increase of 0.4%.
Regarding livestock, the production value was estimated at 1,430.6 billion, an
increase of 11.5% compared to 2011. Livestock has gradually been restored. The prevention
of foot and mouth disease, blue ear disease, swine flu, and animal quarantine continue to be
strengthened, so there are no major epidemics. Survey result of livestock on Oct. 1st, 2012,
there were 20,997 buffalo, an increase of 2.1%; there were 246,253 cows, down 2.2%; there
were 711,065 pigs (excluding shoats), which increases 7.7%; poultry had 6.6 millions units,
up 6.7% compared to Oct. 01st, 2011.
Regarding forestry, reforestation projects were focused to properly implement, area
of contracted management and protection service of forest was 102,693 ha, reaching 100%
of the plan; forest regeneration area was 7,539 hectares, reaching 100% of the plan; newly
planted area was 8010 hectares, reaching 200.3% of the plan. The management and
protection of forest and the fire prevention and forest firefighting continue to be
strengthened
Regarding fishery, the expolitation and farming capacity is estimated at 173,186
tonnes, up 7.4% compared with 2011, in which the expolitation capacity is estimated at
164,479 tonnes, up 8.1%. In 2012, policies to support fishermen fishing in distant waters
were implemented, which approved 11 fuel supports to 4,228 fishing vessels, with a total of
nearly 151 billion VND. Besides, the funding of 522 long range HF communication
systems, which is integrated with satellite positioning device (GPS) in each fishery boat,
were also supported with a total of 14.6 billion VND.
* Communes in the subproject area:
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 35
Agroforestry industry is a major contribution to the economy of communes where the
220kV Quang Ngai - Quy Nhon (Phuoc An) line goes through, accounting for 70-75% of
GDP. In the subproject area, agricultural crops are mainly rice and vegetables (beans,
peanuts, sesame, melon,...); forestry crops are mainly acacia, eucalyptus (paper material).
In addition to farming, farmers in the region also focuses on development of
livestock (buffaloes, cows,...) for traction, and poultry to provide nutrients and increase
revenue.
The area of agricultural land in the communes in 2012 is presented in Table 10:
Table 14: Area of productive land of communes in the subproject area (2012)
No. District/Commune Natural area
(km2)
Agricultural
land
(ha)
Non-
agricultural
land
(ha)
Unused
land
(ha)
I District Mo Duc
1 commune Duc Lan 29.62 1,462.25 651 522.6
II District Duc Pho
2 Pho Phong commune 54.07 4,363 460.2 584.1
3 Pho Nhon commune 40.00 3,043 309.0 647.9
4 Pho Ninh commune 22.25 1,844.3 343.5 37.1
5 Pho Hoa commune 17.00 1,054.4 225.8 419.8
6 Pho Cuong
commune 48.50 2,595.3 521.0 1,734.6
7 Pho Khanh
commune 55.60 2,123.7 1,145.1 2,291.2
III District Hoai Nhon
8 Hoai Son commune 57.00 1,748
9 Hoai Chau Bac
commune 21.25 978.5
10 Hoai Chau commune 23.00 1,262
11 Hoai Phu commune 39.66 1,521
12 Hoai Hao commune 37.93 975.5
13 Hoai Tan commune 27.03 1,434.6
14 Bong Son town 17.04 682
15 Hoai Duc commune 63.00 1,903
IV Hoai An District
16 An My commune 32.58 1,950 293 1,016
17 An Thanh commune 17.11 1,286 198 226
18 An Phong commune 30.62 1,699 259 1.004
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 36
No. District/Commune Natural area
(km2)
Agricultural
land
(ha)
Non-
agricultural
land
(ha)
Unused
land
(ha)
19 An Tuong Dong
commune 47.59 3,204 296 1,259
V District Phu My
20 My Trinh commune 51.44 3,389.49 630.88 1,123.42
21 My Hoa commune 42.98 2,818.97 422.49 1,056.67
22 My Hiep commune 55.65 2,794.76 891.64 1,878.61
VI District Phu Cat
23 Cat Lam commune 69.42 5,130.66 420.26 1,391.08
24 Cat Son commune 113.4 8,476.87 880.08 1,983.05
25 Cat Hiep commune 41.02 3,299.13 436.86 336.01
VII District Tuy Phuoc
26 Phuoc An commune 33.60 2,366 902 92
(Source: Report on socio-economic the subproject area in 2012)
b) Industry:
* Quang Ngai province:
The value of industrial production, service, and trade is estimated at 120,000 billion
VND, accounting for 102% of the target, the value of port cargo throughput is estimated at
12 million tons, reaching 160% of the plan. Creating new jobs for 600 workers, reaching
60% of the plan
In Quang Ngai industrial zones, there have been 80 projects attracted with a total
registered capital of nearly 5,000 billions VND, of which 44 projects are now actively
operational, creating frequent jobs for more than 8,000 workers
* Binh Dinh province:
The industrial production value is estimated at 8,056.2 billion (1994 constant price),
accounting for 93% of the plan, but increasing 8.1% compared with 2011; in which, most
economic sectors grow, such as the state enterprise sector increased by 12.7%; non-state
enterprises sector increased by 6.2%; individual household sector increased by 12.6%;
foreign investment sector increased by 14.2% compared with 2011. In 30 major industrial
products of the province, there are 21 products, of which theirs production ouput increased
over the same phase. Some other products increased significantly such as: titanium ore
increased by 36.7%, titanium ore concentrate increased by 23.4%, bottled beer by 23.4%,
fish fillet and chilled fresh fish increased by 21.5%, cattle feed increased by 16%, solution
of serum protein increased by 22.4%. The products that decrease are: Refined Standar sugar,
stone exploited for construction, tiles etc.
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 37
Overall, the value of industrial production continued to grow despite not reaching its
target which represents a great effort by all levels and branches of goverment in directing and
resolving difficulties for enterprises. Regarding enterprises, they have also attempted to
overcome difficulties in the difficult conditions of the domestic economy. In 2012, the
enterprises of garment industry had organized production and business activities efficiently,
and had signed many orders directly with foreign countries like America, Japan, Korea,
Canada, etc. contributing to improve exports and stablize livelihood, employment for
workers. However, there were still many enterprises processing product, which were the
strength of the province, such as seafood processing and exporting, wood, rocks, minerals and
titanium, etc. were moderately active due to lack of raw materials or price input is too high,
narrow markets, low competitiveness.
* Communes in the subproject area:
The communes in the subproject area are rural agricultural communes, therefore, the
industry virtually undeveloped. There are 2 communes: Pho Phong commune - Duc Pho
district - Quang Ngai province and Nhon Hoa Ward - An Nhon town - Binh Dinh Province
that had industrial zone. These industrial zones also had created works for local labors. The
major industries in the industrial zone were wood processing, granite, cattle feed processing,
garment.
c) People’s income
According to the socio-economic survey of the mission team of the PECC4 in March
2014, most of the income of households where the route passes through mainly came from
agriculture. Per capita income was from 450,000-550,000 VND/person/month, especially
there were households that only reached 300,000 VND/person/month
d) Transportation
The subproject mainly passes through communes with flat terrain (plain), therefore
the transportation in the area is well-developed. In addition to the Highway No. 1A,
Highway No. 24, Highway No. 19, transport system of provincial road, and inter-communal
road are also well-developed as well, which meet the needs of communication between the
subproject area and other areas
100% inter-communal roads are asphalted; inter-village roads are expanded,
concreted or bricked in accordance to the program of the state and people working together.
4.5.2 Public Health:
100% communes in the subproject area have medical personnel and clinics.
However, some clinics still lack of facilities, equipment and manpower, but generally has
met the medical needs of people.
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 38
4.5.3 Education:
100% communes in the subproject area have primary schools, junior secondary
schools. 100% communes in the subproject area has eliminated illiteracy.
The social situation of the communes in the recent years was relatively stable
4.6 Ecology.
According to the result of field survey conducted by PECC4 in March and April
2014, the entire 220kV Quang Ngai - Qui Nhon (Phuoc An) transmission line goes mainly
through flat land, paddy fields, crops; plantations of acacia, eucalyptus, Azadizacta indica
tree (raw material for paper production) of local people; a small portion of the route goes
through natural forests with poor resources that are assigned to local people to take care and
protect. The route is divided into the following major sections:
+ Sections: G11-G16, G16-G24, G24-G35, G39-G41, G60-G62 mainly go over
hillsides, low mountains, fragmented terrains with average slope of 1500-200
0, terrain altitude
varying from 20-200m. Vegetation cover is mainly acacia plantations (paper material) and a
few Ib, Ic, IIB productive natural forests. The planted productive forest area (mostly plantations
of acacia from 1-8 years old) is in the ROW. Productive forest area has been assigned to people
by the CPCs (FLA format) to take care and protect. For protective forest, the route has 11,700m
in length going through protective forest and 850m in length going through natural protective
forest that is under management of Hoai Nhon protective forest management board (managing
from G16 to G24) and Phu My protective forest management board (managing from G24 -
G35).
+ The remaining sections pass through flat terrain with mostly rice fields and crops. A
few sectios cut through some small decentralized residential areas. Vegetation cover on these
route sections are mainly rice and vegetables (peas, corn, sugar cane,...), fruit trees (of which
sections cutting through residential areas).
a) Vegetation
Overall, the vegetation cover in the line route area is poor due to strong impact
caused by human
* Natural flora:
Some sections of the line in the G9-G18, G33-G35, G39-G42 goes through terrain
which is mostly hills, low mountains (300m in altitude), with an average slope of 100-30
0,
and is not much difficult when approaching. On the other hand, traffic in the subproject
areas is developed in natural forest which have been strongly affected by human
- The total length of the route going through the natural forest land is 9,576 m. Based
on the assessment report on environmental impact of the subproject, the followings have
been identified:
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 39
+ 8,726m section is low-value forest with no reserves and grassland, shrub which
was assigned to local people to reforest and take care
The forest status is mostly low-value secondary forest with no existed valuable large
trees, and with vacant land or bushes. The species in this area are less diversed in
composition and are species with wide ecological amplitude, and distributed in the
surrounding areas such as bamboo species, Fagaceae, Meliaceae, Clusiaceae, Annonaceae,
Melastomaceae, Urticaceae, Araceae, etc.
Forest land is scattered in the subproject area into small parts mixed with agricultural
land and acacia plantations. The common species in this type of flora are walnut
(Juglandaceae), areca (Asteraceae), grass species of Poaceae familia, etc.
There are 850m of G34 - G35 section at Ho Voi lake’s upstream having natural forest
with IIB status, which is a form of restored young forest that has the reserves of 30m3/ha
and was assigned to Phu My Protective forest Management Board for protection purpose.
* Artificial vegetation:
Rice fields, vegetable gardens
They are distributed in areas with flat terrain, river, and canals; areas that are near the
residential area; areas that have good soil with little floods, and being favorable of water in
dry season; and areas with high plant restructuring. This part of vegetation cover accounts
for the majority of land in the ROW.
Mixed garden, fruit trees, cashew trees
This landscape appears in the residential areas. Mixed gardens provide food, fruit,
reduction in temperature and air purification, keeping the balance of the ecosystem, shelters
for birds, and reptiles which are the natural enemies of many orchard pests for, etc. Mixed
gardens offer fruits like banana, guava, orange, plum, coconut,... and provide a portion of
fuel daily.
Forest plantation
- Forest plantation is mainly hybrid acacia plantations (paper materials) that are on the
hillside, sloping land allocated for the local households.
- Protective forest plantations are mainly hybrid acacia plantations which are under the
management of two units: Hoai Nhon Protective forest Management Board and Phu My
Protective forest Management Board.
- Acacia, Azadizacta indica trees have average height of 5-12m, average diameter of
100-700mm, and density of 0.11trees / m2.
- Agarwood has the average height of 1-4m, average diameter of 30-70mm, density of
0.25 plants/m2.
-
TEP - 220kV Quang Ngai – Quy Nhơn (Phuoc An) transmission line Feasibility Study
Enviromental Management Plan 40
- In the ROW, there are 557 hopea odorata trees with a diameter of 5-15cm, height of
7-15m which belongs to Phu My Protective forest Management Board
The total length and area of the route passing through forest, and functions of the
forests the route passing through as shown in table 2.7.
Table 15: Length, and area of forest that the transmission line crosses through
No. Management agency
Length of
sites that
are cut
through by
the route
(m)
Area in
the ROW
(ha)
Functions
Forest status Produ
ctive
forest
Protec
tive
forest
1 Hoai Nhon Protective
forest MB 7,880 17.4 17.4
Reserve of acacia,
hopea odorata
plantations are
estimated at 959.4
m3, with diameter of
5-15cm, height of 7-
12 m)
2 Phu My Protective
forest MB 2,970 6.3 6.3
5-7 years of age
acacia Plantations
850 1.8 1.8 Natural forest with
IIB status
3 Pho Nhon PC 1,250 2.65 2.65
Acacia Plantations
from 1-5 years old
4 Pho Ninh PC 2,510 5.32 5.32
Acacia Plantations
from 1-5 years old
5 Pho Cuong PC 3,890 8.25 8.25
Acacia Plantations
from 2-4 years old
6 Pho Phong PC 760 1.61 1.61
Acacia Plantations
from 2-4 years old
7 Phổ Hòa PC 1,500 3.18 3.18
Acacia Plantations
from 1-5 years old
8 Pho Khanh PC 3,301 6.7 6.7
Acacia Plantations
from 2-5 years old
9 Hoai Hao PC 1,150 2.44 2.44
Acacia Plantations
from 1-5 years old
10 Binh Thuan PC 600 1.27 1.27
Acacia Plantations
from 1-5 years old
11 Cat Hiep PC
1,090 2.31 2.31 Acacia Plantations
from 1-5 years old
12 Agricultural land of
local residents
25,849 54.8 54.8 Acacia Plantations
from 1-5 years old
8,726 18.5 18.5 Grassland, shrub: Ib,
Ic
13 Total
52,924 112.2 88.5 23.7 Forest plantations
9,576 20.3 18.5 1.8
Natural forest with
IIB stat