Transmission Planning Annual Stakeholder Outreach Meeting

10.17.11

Page 2: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Purpose of This Meeting To allow stakeholders the opportunity to

participate in Tri-State’s transmission planning process consistent with:

Development of Tri-State’s long-term

transmission plans Attachment L of Tri-State’s OATT CPUC 3627 Generator Interconnection Procedures

Page 3: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Blane Taylor Senior Manager, Power Systems Planning 303-254-3659 [email protected]

Page 4: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Agenda

Overview of Tri-State Tri-State Planning Process 2011-2020 L&R Resource Assumptions Transmission Capital Construction Plan Generation Interconnections OATT update

Page 5: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Background Tri-State is a member owned, not-for-profit, generation

and transmission cooperative

44 member owners across NM (12), CO (18), NE (6), WY (8) Members serve approximately 1.4 million 200,000 square miles of service territory

Mission Statement:

“Provide our member owners a reliable, cost-based supply of electricity while maintaining a sound financial position through effective utilization of human, capital and physical resources in accordance with cooperative principles.”

Page 6: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Tri-State G&T Member Cooperative Systems

Page 7: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Basic Statistics Peak Member Load (Summer 2011) ~ 2834 MW

5 meters / line mile average Load by State

New Mexico 471 MW ~ 17% Colorado 1729 MW ~ 61% Nebraska 357 MW ~ 12% Wyoming 277 MW ~ 10%

Diverse Membership

United Power– Brighton, CO – 65,000 meters – 300 MW Garland L&P- Powell, WY – 1,900 meters – 6 MW

Page 8: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Tri-State’s Transmission System

Tri-State wholly or jointly owns 5,177 miles of transmission 1220 miles - 345 kV 984 miles - 230 kV 184 miles - 138 kV 2740 miles - 115 kV 49 miles - 69 kV

~ 220 Stations ~ 400 Communication Sites DC Tie (Stegall, NE) Operations Center / Backup Control Center

Page 9: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder
Page 10: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder
Page 11: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder
Page 12: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder
Page 13: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Tri-State Generation Resources

1,408 MW coal 797 MW gas 30 MW solar (PPA) 51 MW wind (PPA) Additional co-op member renewable projects Contracts

~ 600 MW federal hydroelectric allocation Basin Electric purchase

Page 14: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder
Page 15: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Tri-State Planning Process

Page 16: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

About WestConnect WestConnect is composed of utility companies

providing transmission of electricity in the United States.

The members work collaboratively to assess stakeholder and market needs and to develop cost-effective enhancements to the western wholesale electricty market.

WestConnect is committed to coordinating its work with other regional industry efforts to achieve as much consistency as possible in the Western Interconnection.

Page 17: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

WestConnect Footprint

Page 18: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Tri-State Planning Process Tri-State performs and participates in transmission

planning consistent with FERC 890 principles for coordinated, open and transparent planning.

Tri-State coordinates its planning with other

transmission providers and stakeholders at the regional and sub regional levels of the Western Interconnection.

CCPG SWAT WestConnect WECC

Page 19: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Tri-State Planning Process Tri-State performs and participates in transmission

planning consistent with FERC 890 principles for coordinated, open and transparent planning.

Tri-State coordinates its planning with other

transmission providers and stakeholders at the regional and sub regional levels of the Western Interconnection.

CCPG SWAT WestConnect WECC

Page 20: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

2011-2020 L&R Resource Assumptions

Page 21: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

2011-2020 L&R Resource Assumptions Resource additions: 50 MW wind, Lamar, CO 2015 50 MW wind Archer, WY 2015 588 MW combined cycle, Lamar, CO 2017 100 MW wind Archer, WY 2018 200 MW wind Lamar, CO 2020

Page 22: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Transmission Capital Construction Plan

Page 23: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Gladstone 230 kV Phase Shifting Transformer

Gladstone

Page 24: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

230 kV Santa Rosa-Gladstone Line

Santa Rosa

Gladstone

Page 25: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Dulce Chama

Chama-Dulce 69 to 115 kV Line Upgrade Project

Santa Rosa

Gladstone

Page 26: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Dulce

Chama

Dulce-Navajo Dam 115 kV Line

Santa Rosa

Gladstone Navajo

Dam

Page 27: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Nucla

Nucla-Telluride 115 kV Line

Telluride

Sunshine

Page 28: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Plaza

Waverly

Nucla

Plaza-Waverly 115 kV Loop Project

Telluride

Sunshine

Page 29: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Plaza

Waverly

Nucla

San Juan Project

Telluride

Sunshine

Shiprock

Iron Horse

Page 30: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Big Sandy

Midway

Lincoln

230 kV Big Sandy-Lincoln-Midway Line Uprate

Page 31: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Big Sandy

Midway

Lincoln

230 kV Big Sandy-Calhan Line

Calhan

Page 32: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Big Sandy

Midway

Lincoln Calhan

Falcon Paddock

115 kV Midway-Falcon Line Uprate Falcon-Paddock 69>115 kV Line Upgrade

115 kV Paddock-Calhan Line

Page 33: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Comanche

Calumet

To San Luis Valley Sub

Big Sandy

Midway

Lincoln Calhan

Falcon Paddock

San Luis Valley-Calumet-Comanche Transmission Project

Page 34: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Comanche

Calumet

To San Luis Valley Sub

Big Sandy

Midway

Lincoln Calhan

Falcon Paddock

Wayne Child-Cheyenne Project

Wayne Child

Cheyenne

Page 35: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Comanche

Calumet

To San Luis Valley Sub

Big Sandy

Midway

Lincoln Calhan

Falcon Paddock

230 kV Burlington-Wray Line

Wayne Child

Cheyenne

Burlington

Wray

Page 36: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Comanche

Calumet

To San Luis Valley Sub

Big Sandy

Midway

Lincoln Calhan

Falcon Paddock

Ogallala-Roscoe 115 kV Line Rebuild

Wayne Child

Cheyenne

Burlington

Wray

Ogallala Roscoe

Page 37: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder
Page 38: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Questions?

38

Page 39: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Ray A. LaPanse, P.E. Transmission Interconnection Administrator (303) 254-3154 [email protected]

Page 40: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Generator Interconnection Procedures

Summary of GIP Basics & GIR Queues

Page 41: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

41

Generator Interconnection Procedures - Reform & Basics GIP reform process began in November 2008. Final Generator Interconnection Procedures (GIP) went

into effect July 1, 2010, and continues to be updated periodically as necessary (next Rev. planned for 12/1/2011).

Covers all sizes of generation projects connected to Tri-State’s transmission system.

Does not cover interconnections to Tri-State member cooperative systems.

NOTE – The GIP does not discuss or address Tri-State Transmission Service or Generation Network Resource issues (Energy Resources - Merchant Group).

Page 42: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

First Ready-First Served

Option A) First Come-First Served Option B) Fast track

(expedited SIS, sec. 7.1.1) with confirmed customer

Review Published

Load & Resource

Trans-mission Study

Two month windows to

submit application.

IR Applications reviewed on semi-annual

basis.

Attend Information Session at

Beginning of IR

Application Window

Customer may have access to Base Case Data (with

confidentiality agreement)

and may perform own

Studies

Facilities Study

Customer submits deposit

of 25% of Facility Cost &

TSR or proceeds at own risk

Defer FacSA up to

18 months

Submit IR

Network Upgrade Studies

Customer

TSR Path

At Risk or non-

designated Network

Resource Path

Detailed Modeling data + Deposit: > 75 MW--$250,000;

21 to 75 MW--$75,000 11-20 MW--$50,000; <= 10 MW--

$25,000 (Includes non-refundable portion)

Proof of 25% Site Control at time of application

SIS Scoping Meeting

Three levels of generation

allowed and specified for

study at time of meeting:

1.Network Upgrades for IR MW Request;

2.Max MW with no internal NUs;

3.Alt. MW level, if agreed to, up to 60% less than MW of IR.

SIS After power flow portion

of SIS, meet with Customer, customer

must select one

generation level & POI

SIS Review (with cost estimates)

and FS Scoping Meeting

and Agreement

Shows Designation as Network Resource &

submits deposit of

25% of Facility

Cost, 50% Site Control,

signs FacSA.

LGIA 100% Site Control + 100% of Facility

Cost

Page 43: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

GIP Process Implementation

43

• Update on recent efforts and progress made in the Generation Interconnection Study process: • Major work completed in developing power flow “TSGT GIP base

case” models (2012 & 2015, HS & LA, PSSE-V32 & PSLF-V17) that have been reviewed and included input from regional entities (TSGT, XE/PSCo, BHC, CSU, WAPA, BEPC, etc.).

• Tracking of study costs and implementing quarterly cost account summary reports to be issued to Interconnection Customers.

• Improved review of IR filings , customer facilities model data, clarification of TSGT interconnection and operational criteria (voltage regulation, dynamics, etc.) to minimize need for re-study.

• Pre-GIR Application Information: • Phone call and single meeting discussion of Tri-State’s GIP process

/ requirements, and Queue & completed reports on OASIS; • Tri-State Transmission Map with GIR locations, and GIP Base

Cases available upon request, once NDA signed with Tri-State (and WECC).

Page 44: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Major Changes in the GIP

44

Sec. Topic Interim LGIP (2/2009 – 7/2010) GIP (7/2010)

3.3, 3.4 IR Filing Deposits

3.3 - $125k Dep (<75MW) $250k Dep (>75MW) (plus model data, 50% Site

Control)

3.4 – (New) $25k Dep (<10MW) (New) $50k Dep (10 - 20MW) (New) $75k Dep (20 – 75MW) $250k Dep (>75MW) (plus model data, (new) 25% Site

Control)

5.1 Study

Deposits (add’l info.)

IR filed before 2/2009 requires additional $$ required as needed to bring total dep to $125k.

IR filed before 7/2010 (*8/2010) requires additional $$ required as needed to bring total dep to (new) $250k.

7.1.1 System Impact

Study (SIS)

Expedited study option for projects with LOI / PPA. Same

Page 45: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

45

Sec. Topic Interim LGIP (2/2009 – 7/2010) GIP (7/2010)

8.1

Facilities Study

(FacS) – Items

required from IC to

begin study.

For IR designated as a Network Resource (NR):

a) Site Control - 50%. b) Ltr Of Intent / PPA for

NR.

For IR designated as an Energy Resource (ER):

a) Site Control 50%. b) No LOI / PPA necessary.

180 days (6 months) allowed for signing FacSA and supplying documentation of Site Control and LOI / PPA.

a) Site Control – 50%. b) (New) Dep or Ltr Of Credit

for 25% of cost of Interconnection Facilities and Network Upgrades.

c) (New) Either: • Designation as a NR or; • TSR with TSGT or; • A written statement

acknowledging IC’s acceptance of risk of TP system operating limits.

(New) 18 months allowed for supplying evidence of site control and LOI / PPA, and (new) 25% of Intercon. Facilities & Network Upgrade costs, followed by signing GIR Facilities Study Agreement (FacSA).

Major Changes in the GIP

Page 46: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

46

Sec. Topic Interim LGIP (2/2009 – 7/2010) GIP (7/2010)

11.3

Gen. Intercon.

Agreement (GIA)

11.3 – Once final LGIA tendered to IC, it must be signed and returned to TP (TSG&T) within 21 days, along with:

a) Site Control 100%. b) Evidence of project

milestones achieved, such as either: • Fuel supply contract (if

applicable); • Cooling water supply

contract (if applicable); • Contract signed for E&P

of major equipment / construction of IC facilities;

• Contract signed for air / land / water use permit.

11.3 – Once final GIA tendered to IC, it must be signed and returned to TP (TSG&T) within 21 days, along with:

a) Site Control 100%. b) (New) Deposit or LOC for

balance of the 100% cost of Interconnection facilities and Network Upgrades as identified in the final FacS.

Major Changes in the GIP

Page 47: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

47

Generation Interconnection Requests (GIR) Queues & Applications

• Total # of IRs in Queue as of 10/12/11: 21 • (13 in CO, 3 in NM, 5 in WY, 0 in NB)

• Total MW of IRs in Queue as of 10/12/11: 2,683 MW • (1,888 MW in CO, 145 MW in NM, 650 MW in WY, 0 MW in NB)

• Last Semiannual GIR Application Window closed: Aug. 31, 2011

• Only 2 new GIRs received in each of the last 2 GIR Application Windows;

• Next semi-annual GIR Application Window opens: Jan. 1, 2012

Page 48: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Questions?

48

Page 49: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Ron Steinbach Senior Manager, Transmission, Contracts, Rates & Policy (303) 254-3355 [email protected]

Page 50: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

OATT Update

Page 51: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Open Access Transmission Tariff In place since 2001 Formula Rate—updated annually

2011 Point-to-Point Rate:

$3.48 per kW month

Non-firm rates currently discounted up to 70%

WestConnect Pricing Experiment Non-pancaked hourly non-firm transmission

Page 52: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Tri-State Open Access Transmission Tariff

Tri-State is not FERC jurisdictional, but uses FERC pro forma tariff model

Reviewed annually and revised when needed Formula Rate—updated annually Non-firm rates currently discounted up to 70% WestConnect Pricing Experiment

Non-pancaked hourly non-firm transmission

Page 53: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Recent Changes to OATT and GIP OATT

Added Hourly Firm product Eliminated deposit for sales of three months or less Modified Billing procedures

Default Distribution of penalty revenue

Updated Attachment C—ATC methodology Updated Attachment L—Transmission Planning

GIP Clarified method for reimbursement of network credits

when Tri-State is an Affected System

Page 54: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Historical Transmission Usage (12 month average)

Sum of Point-to-Point reservations and coincident peak network load

2007: 2,442 MW 2008: 2,543 MW 2009: 2,509 MW 2010: 2,587 MW 2011: 2,626 MW (through August) 2011 System peak in August = 3,105 MW

54

Page 55: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

55

Rate Design Monthly Network Service Charge =

ATRR / 12 * Load Ratio Share Load Ratio Share = Customer 12 CP/Total 12 CP

Point to Point Transmission Rate = ATRR / Total Load

On-Peak Non-Firm Point to Point Rate = Annual Transmission rate / 4160 hours

Off-Peak Non-Firm Point-to-Point Rate Annual Transmission rate / 8760 hours

Page 56: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

56

2012 Transmission Rates Annual Transmission Revenue Requirement

$109,992,813

Point-to-Point Transmission Rates - $ / MW-Month $3,570.53

Schedule 1--Scheduling and Dispatch $ / MW-Month $328.99

Schedule 2--VAR Support $ / MW-Month $87.82

Page 57: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

OASIS Information Go to:

www.tristategt.org/Operations

OATT Queues and Studies

Interconnection requests Transmission Service requests Study Reports

Page 58: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder

Questions?

58

Page 59: Transmission Planning Annual Stakeholder Outreach Meeting ...€¦ · Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 . Purpose of This Meeting ... stakeholder