transmittal of meeting handout materials for … · - present licensing actions, and other reviews...

28
NRC FORM 658 U.S. NUCLEAR REGULATORY COMMISSION (9-1999) TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR IMMEDIATE PLACEMENT IN THE PUBLIC DOMAIN This form is to be filled out (typed or hand-printed) by the person who announced the meeting (i.e., the person who issued the meeting notice). The completed form, and the attached copy of meeting handout materials, will be sent to the Document Control Desk on the same day of the meeting; under no circumstances will this be done later than the working day after the meeting. Do not include proprietary materials. DATE OF MEETING The attached document(s), which was/were handed out in this meeting, is/are to be placed 06/12/2002 in the public domain as soon as possible. The minutes of the meeting will be issued in the near future. Following are administrative details regarding this meeting: Docket Number(s) 50-259 Plant/Facility Name Browns Ferry Nuclear Plant, Unit 1 TAO Number(s) (if available) Reference Meeting Notice 05/30/2002 Purpose of Meeting (copy from meeting notice) Management meeting to discuss an overview of the actions required for Browns Ferry Unit 1 restart NAME OF PERSON WHO ISSUED MEETING NOTICE TITLE Kahtan N. Jabbour Senior Project Manager OFFICE Office of Nuclear Reactor Regulation DIVISION Division of Licensing Project Management BRANCH Project Directorate II, Section 2 Distribution of this form and attachments: Docket File/Central File PUBLIC PRINTED ON RECYCLED PAPER This form was designed using InForms NRC FORM 65B (9-1999)

Upload: others

Post on 27-Sep-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

NRC FORM 658 U.S. NUCLEAR REGULATORY COMMISSION (9-1999)

TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR IMMEDIATE PLACEMENT IN THE PUBLIC DOMAIN

This form is to be filled out (typed or hand-printed) by the person who announced the meeting (i.e., the person who issued the meeting notice). The completed form, and the attached copy of meeting handout materials, will be sent to the Document Control Desk on the same day of the meeting; under no circumstances will this be done later than the working day after the meeting. Do not include proprietary materials.

DATE OF MEETING

The attached document(s), which was/were handed out in this meeting, is/are to be placed

06/12/2002 in the public domain as soon as possible. The minutes of the meeting will be issued in the near future. Following are administrative details regarding this meeting:

Docket Number(s) 50-259

Plant/Facility Name Browns Ferry Nuclear Plant, Unit 1

TAO Number(s) (if available)

Reference Meeting Notice 05/30/2002

Purpose of Meeting (copy from meeting notice) Management meeting to discuss an overview of the

actions required for Browns Ferry Unit 1 restart

NAME OF PERSON WHO ISSUED MEETING NOTICE TITLE

Kahtan N. Jabbour Senior Project Manager OFFICE

Office of Nuclear Reactor Regulation

DIVISION

Division of Licensing Project Management

BRANCH

Project Directorate II, Section 2

Distribution of this form and attachments: Docket File/Central File PUBLIC

PRINTED ON RECYCLED PAPER This form was designed using InFormsNRC FORM 65B (9-1999)

Page 2: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Tennessee Valley Authority Browns Ferry Nuclear Plant

Unit 1 Restart

L

TVA/NRC Meeting

Nuclear Reactor Regulation - Rockville, MD

June 12, 2002

I�I

.�

|

Page 3: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Agenda

• Introduction/Meeting Objectives

* Regulatory History

* Overview and Schedule

* Methodology for Special Programs

* Licensing Actions

* Generic Communications

* Licensing Actions of Special Interest

• Commitment Closure

• Unit 1 Regulatory Framework

* Summary and Open Discussion

- Jon Rupert - Tim Abney

- Jon Rupert/Joe Valente

- Joe Valente

- Tim Abney

- Tim Abney

- Tim Abney

- Tim Abney

- Tim Abney

- Jon Rupert

I

Page 4: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Unit 1 Restart - Introduction/Meeting Objectives

Objectives of this meeting are: - Provide overview of Unit 1 Restart Project

- Discuss regulatory history of Units 2 and 3 restarts

- Present licensing actions, and other reviews that will be needed from NRR

- Initiate dialogue on Regulatory Framework for Unit 1 restart

Jon Rupert 2

Page 5: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Regulatory History

Unit 2 Restart - All 3 BFN units voluntarily shutdown by TVA in March, 1985 because of safety,

regulatory and management issues

- TVA committed to obtain NRC approval prior to restart of any BFN unit

- NRC issued a "show cause" letter for all TVA nuclear plants in September, 1985, under 10 CFR 50.54 (f), and requested TVA to specify corrective actions

- TVA submitted the Nuclear Performance Plan, Volume 3, in August, 1986 outlining the steps needed to recover the BFN units, specifically directed to Unit 2

- TVA and NRC conducted several meetings and TVA made several submittals to fully define the regulatory actions needed to restart BFN Unit 2

- NRC issued NUREG 1232, Volume 3, Supplement 2 in January, 1991, concluding that TVA's actions acceptably addressed deficiencies in BFN

- NRC approved Unit 2 restart on May 23, 1991

- Unit 2 restarted on May 24, 1991

Tim Abney 3

Page 6: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Regulatory History LLAJ

Unit 3 Restart - TVA proposed regulatory framework for restart of Units 1 and 3 in July, 1991,

outlining improvements from the Unit 2 precedent

- NRC approved framework proposed by TVA in April, 1992

- Unit 3 restart effort dealt primarily with resolving Special Programs, as the

management issues had been resolved for Unit 2 restart

- NRC staff issued SECY-95-264 recommending restart of Unit 3 on November 1, 1995

- NRC approved Unit 3 restart on November 15, 1995

- Unit 3 restarted on November 19, 1995

Tim Abney 4

Page 7: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Regulatory History

Unit 1 - Based on Energy Vision 2020 recommendations, TVA decided to delay decision on

Unit 1 restart

- Unit 1 was removed from the NRC's problem plant list on June 21,1996 based on commitments from an April 16, 1996 TVA letter to:

"* Implement same special programs on Unit 1 that were done for Unit 3 "* Not restart Unit 1 without prior approval of NRC

Tim Abney 5

Page 8: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Overview and Schedule Egg.

Detailed Scoping, Estimate and Planning (DSEP)

- Extensive effort to support Unit 1 restart decision

- Utilized key TVA personnel with both discipline expertise and experience on restart

of units 2 and 3

- Results in organizational structure and strong team in place for recovery effort

* Unit 1 Restart Principles - BFN units will be operationally the same at completion of Unit 1 Restart

- Unit 1 Restart activities will use plant processes and procedures when available

6J Oil 12upt L

Page 9: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Overview and Schedule

Workscope Required for Unit 1 Restart - Special Programs using criteria consistent with Unit 3 Restart

- Design changes since Units 2/3 restart

- Future design changes in 5 year BFN Project Plan

- Corrective/Preventive Maintenance

- Regulatory Issues

- Licensing Actions

- Inservice Inspection

Joe Valente 7

Page 10: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Methodology for Special Programs

Special Program Differences in Unit 1 vs. Unit 3 Approach

Configuration Managenmt None

Design Calculations None

Equipment Qualification None

Seisnic Design None

Fire Protection Improvement None

Instrnrt Sensing Lines None

Wall Thinning None

PRA Not Required

Compnent & Piece Part Qualification None

Electrical Issues None

Q-List None

MELB None

Platfonrm Thermal Growth None

IGSCC Complete replacement of recirculation piping

Coa•ings None

Restart Test None

Plant Welding Not Required

Heat Code Traceability Not Required

8Joe Valente

Page 11: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

2 0 22 0 32 0 42 0 0 5 2.0 8 2 0 0 7 2 0 00RD APPROVAL $

ýRD MAJOR CONTRACTS

o.........lMnC.l

ýNEERING PROGRAMS REO'D FOR MOOS. .:.:.... " .... .. .. '.:. .xy: . :.XN. .:..:.*:N. .c.JENC

'V.,,'R

BRIEF

IOBILIZE MODI.CATIONS SUPPORT TEAM

,ONG LEAD MATERIAL - ORDER

MODIFICATIONS - DEMOLITION & NON DCN ACTIVITIES

PREPARE & ISSUE BULK MATERIAL ORDER

LONG LEAD MATERIAL - DELIVER

ENGINEERING ISSUE REACTOR BUILDING DCN°S ............ .. ..NG .NE... ..N......U.. O

DESIGN ENGINEERING SUPPORT. 1. -- -- - -- - -------------.... ' . . . . . . .

ENGINEERING ISSUE CONTROL BUILDING DCN'S .. x s .. ........

MODIFICATINSInkcMPLEMET DRrno LL nr,

CRDR ENGINEERING COMPLETE

MODIFICATIONS IMPLEMENT REACTOR BUILDING DCN'S

ENGINEERING ISSUE TURBINE BUILDING DCN'S

OPERATIONS PROGRAMS

LICENSE RENEWAL SUBMITTAL

MODIFICATIONS IMPLEMENT CONTROL BUILDING DCN'S

MODIFICATIONS IMPLEMENT TURBINEP RIlINfGlDC Nru-.. " .... . " ' ' . `:N:: : : : : : ::..N.. 'N .. . . . . ''..."..-NN....':.¼*:.N::.:.:.:c5.......tA........

RESTART TEST PROGRAM

MAINTENANCE CM's & PM's ..................................................................................................................................................................................................-.............-...............'...'•.??N...<$.<.:.:..:<.......'N.::<N N .:..-NN.'NN.<:&

EPU SUBMITTAL

RISK INFORMED ISI SUBMITTAL

OPERATOR TRAINING

SPAE/SPOC TURNOVER

AREA TURNOVER

PLANT ACCEPTANCE .....................................................................................................................................................................................5.5'.5..S:.::s.: .

OPERATIONAL READINESS REVIEW

NRC TESTING NOTIFICATION

LICENSING TO NOTIFY NRC OF FUEL LOAD

FUEL LOAD

TURBINE GENERATOR ON TURNING GEAR

NCR APPROVAL FOR RESTART

POWER ASCENSION TESTING

TVA BFN UNIT-1 MAJOR MILESTONES

S© Primavera Systems, Inc.

NEERING ISSUE DRYWELL DCN'S

........ .. ... ........ ........... .

9

ENGINEERING

ISSUE

CONTROL

BUILDING

DCN'S

Ut•f•l•l•&l'inMR

lug! ¢U¢• nDvuu=t I RP=le

Page 12: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Licensing Actions

Technical Specifications Changes/License Amendments - High Range Primary Containment Radiation Monitors

- Power Range Neutron Monitor (PRNM) Upgrade With Implementation of Average Power Range Monitor

(APRM) and Rod Block Monitor (RBM) TS ARTS/MELLL

- 14 Day Allowable Outage Time for Emergency Diesel Generators

- Extended Power Uprate Operation

- 24 Month Fuel Cycle

- Crediting of Containment Overpressure for Net Positive Suction Head Calculations for Emergency Core

Cooling Pumps

- Change Setpoint of Scram Discharge Volume

- PT Curves

- Safety Limit Minimum Critical Power Ratio (SLMCPR)

- Allowable Value for Reactor Vessel Water Level - Low, Level 3

Oscillation Power Range Monitor (OPRM)

- Main Steam Isolation Valve (MSIV) Leakage Rate Limits and Exemption from 10 CFR 50 Appendix J

- Excess Flow Check Valve Surveillance Intervals

- Containment Air Dilution (CAD) AOT

- Alternative Source Term

- Miscellaneous I & C Changes

10Tim Abney

Page 13: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Licensing Actions

Relief Requests - Inservice Inspection Program - 11 requests for relief including one which provides

for permanent deferral of examinations for circumferential shell welds of the RPV

- Containment Inspection Program - 5 requests for relief

- System Pressure Test (SPT) Program - 6 requests for relief

- Programmatic Relief Requests - 5 requests for relief

- Risk-Informed ISI Program - 1 request for relief

• ..A. ...,111111 / muii1j

Page 14: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Generic Communications L"i

Bulletins - 88-03 Inadequate Latch Engagement in HFA Type Relays Manufactured by GE

- 88-04 Potential Safety Related Pump Loss

- 90-01 Loss of Fill Oil in Rosemount Transmitters

- 93-02 Debris Plugging of Emergency Core Cooling Suction Strainers

- 95-02 Unexpected Clogging of a RHR Pump Strainer While Operating in Suppression Pool Cooling Mode

12Tim Abney

Page 15: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Generic Communications

Generic Letters 88-01 NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping

- 88-20, S4 Individual Plant Examination of External Events for Severe Accident Vulnerabilities

- 89-13 Service Water System Problems Affecting Safety Related Equipment

- 92-01 Reactor Vessel Structural Integrity

- 94-02 Long Term Solutions and Upgrade of Interim Operating Recommendations for Thermal-Hydraulic

Instabilities in BWRs

- 94-03 Intergranular Stress Corrosion Cracking of Core Shrouds in BWRs

- 95-07 Pressure Locking and Thermal Binding of Safety Related and Power-Operated Gate Valves

- 96-06 Assurance of Equipment Operability and Containment Integrity During Design Basis Accident

Conditions

- 97-04 Assurance of Sufficent Net Positive Suction for Emergency Core Cooling and Containment Heat

Removal Pumps

- 98-04 Potential for Degradation of the Emergency Core Cooling System and the Containment Spray

System After a Loss of Coolant Accident Because of Construction and Protective Coating

Deficiencies and Foreign Material in Containment

13Tim Abney

Page 16: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Generic Communications

* NUREG-0737 (TMI Action Plan) Action Items

I.D.1 I.D.2 II.B. 2 II.B.3 II.E.4.2.1-4

II.F.1.2.C II.F.1.2.D II.F. 1.2.E II.F.2.4

II.K.3.13 II.K.3.18 II.K.3.28

Control Room Design Review Safety Parameter Display Console Plant Shielding Post-Accident Sampling System

Containment Isolation Dependability - Implement Diverse Isolation Accident - Monitoring - Containment High Range Radiation

Accident - Monitoring - Containment Pressure

Accident - Monitoring - Containment Water Level

(Generic Letter 84-23) - Instrumentation for Detection of

Inadequate Core Cooling HPCI/RCIC Initiation Levels ADS Actuation Modifications Qualification of ADS Accumulators

14Tim Abney

Page 17: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Licensing Actions of Special Interest Emu

• License Renewal

"• Extended Power Uprate

"• Unit 1 license condition to provide analysis for Technical Specifications changes since 1985

Tim Abney 15

Page 18: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Commitment Closure

• 268 total open Unit 1 commitments • 68 associated with Generic Communications * 70 from LERs, violations and inspections 9 130 from other miscellaneous sources • These will be evaluated in accordance with NEI 99-04 for potential decommitments

Tim Abney 16

Page 19: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Unit 1 Regulatory Framework

"Regulatory Framework will include:

- Summary of Special Programs

- Submittals required

- Concurrent licensing actions for all 3 units, where applicable

- Commitment closure process

- Actions needed for NRC restart approval

"* TVA intends to submit proposed Regulatory Framework document by December 31, 2002

Tim Abney 17

Page 20: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Summary and Conclusions

18Jon Rupert

Page 21: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

BFN UNIT 1 PROJECT PLAN

PRIORITY ISSUES ............................................................................................................................................................... 2

INSPECTIONS .. .................................................................................................................................................................... 2

M EETINGS IVISITS ............................................................................................................................................................... 2

PENDING NRC ACTIONS .................................................................................................................................................... 2

TECHNICAL SPECIFICATIONS .......................................................................................................................................... 3

SUBMITTALS ....................................................................................................................................................................... 4

NRC COMMITMENTS ................................................................................................................................... 8

Page 22: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

BFN UNIT 1 PROJECT PLAN Page 2

PRIORITY ISSUES TVA SUB NRC ISSUE DATE NRC RESP TVA

DATE APPROVAL MGR DATE

INSPECTIONS INSPECTION INSPECTION NRC CONTACT TVA DATE PROCEDURE CONTACT

MEETINGSNISITS MILESTONE DATE CONTACT (NRC, TVA CONTACT INPO, NEIL, ANI)

NRR - Unit 1 Restart Overview @ Rockville 6/12/02 K. Jabbour T. Abney

NRR - License Renewal @ Rockville 7/24/02 K. Jabbour M. Morrison

2

Page 23: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Page 3BFN UNIT 1 PROJECT PLAN

TECHNICAL SPECIFICATIONS TVA CONTACT SUBMITTAL FED REG TVA NEED DATE DATE DATE

Containment Air Dilution (CAD) AOT 3Q/03

Excess Flow Cljeck Valve Surveillance 3Q/03 Intervals

High Range Primary Containment Radiation 4Q/03 Monitors

PT Curves 4Q/03

Crediting of Containment Overpressure for Net 1 Q/04 Positive Suction Head Calculations for Emergency Core Cooling Pumps

Allowable Value For Reactor Vessel Water 1 Q/04 Level - Low Level 3

Oscillation Power Range Monitor (OPRM) 2Q/04

Main Steam Isolation Valve (MSIV) Leakage 2Q/04 Rate Limits and Exemption From 10 CFR 50 Appendix J

SDIV Setpoint Change 2Q/04

14-Day Allowed Outage Time for Emergency 2Q/04 Diesel Generators Power Range Neutron Monitor (PRNM) 3Q/04 Upgrade with Implementation of Average Power Range Monitor (APRM) and Rod Block Monitor (RBM) TS ARTS/MELLL

Miscellaneous I & C Changes 3Q/04

24 Month Fuel Cycle 3Q/04

Alternative Source Term 4Q/04

Extended Power Uprate Operation 3Q/05

Safety Limit Minimum Critical Power Ratio 4Q/05 (SLMCPR)

Page 24: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Page 4BFN UNIT 1 PROJECT PLAN

SUBMITTALS - LOOK AHEAD DUE DATE AND INPUT DUE ___ _

Description Input Resp Org Input Rec'd Sch'd Actual Sch'd Actual Due Comment I ic Due Date to Date to Date to Date to Date Eng

Concur Concur Signature Signature

1 Regulatory 4Q/02 Framework

2 GL 88-01 NRC 1 Q/03 Position on IGSCC in BWR Austenitic Stainless Steel Piping

3 GL 94-03 Part 1 Intergranular Stress 1Q/03 Corrosion Cracking Part 2 of Core Shrouds in 3Q/03 BWRs

4 Inservice Inspection 2Q/03 (ISI) Program Relief Requests

5 Containment 3Q/03 Inspection Program Relief Requests

6 System Pressure 3Q/03 Test (SPT) Program Relief Requests

7 Programmatic Relief 4Q/03 Requests

8 BL 93-02 Debris 1 Q/04 Plugging of Emergency Core Cooling Suction Strainers

Page 25: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Page 5BFN UNIT 1 PROJECT PLAN

SUBMITTALS - LOOK AHEAD DUE DATE AND INPUT DUE

E DAT AN INPUT DUE

Description Resp Org Input Rec'd Sch'd Date to Concur

Actual Date to Concur

Sch'd Date to

Signature

Actual Date to Signature

Due

Date

Comment Lic

Eng

- - __________________________________ I _________________ ________________________ __________________________ £ _________________ J _________________ _____________________ 4. _____________________ ______________________

BL 95-02 Unexpected Clogging of a RHR Pump Strainer While Operating in Suppression Pool

BL 88-03 Inadequate Latch Engagement in HFA Type Relays Manufactured by GE

I Q/04

-4 1 I -

2Q/04

11 BL 88-04 Potential 2Q/04 Safety Related Pump Loss

12 GL 89-13 Service 2Q/04 Water System Problems Affecting Safety Related Equipment

13 GL 94-02 Long 2Q/04 Term Solutions Thermal-Hydraulic Instabilities in BWRs

14 BL 90-01 Loss of Fill 3Q/04 Oil in Rosemount Transmitters

Input Due

-� 4 4- 4 + +

Page 26: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Page 6BFN UNIT I PROJECT PLAN

SUBMITTALS - LOOK AHEAD DUE DATE AND INPUT DUE

Description Input Resp Org Input Rec'd Sch'd Actual Sch'd Actual Due Comment Lic Due Date to Date to Date to Date to Date Eng

Concur Concur Signature Signature

15 GL 95-07 Pressure 3Q/04 Locking and Thermal Binding of Safety-Related and Power-Operated Gate Valves

16 GL 96-06 Assurance 3Q/04 of Equipment Operability and Containment Integrity During Design Basis Accident Conditions

17 GL 97-04 Assurance 3Q/04 of Sufficient Net Positive Suction for Emergency Core Cooling and Containment Heat Removal Pumps

18 GL 98-04 Potential 4Q/04 for Degradation of the Emergency Core Cooling Systems Because of Construction and Protective Coating Deficiencies and Foreign Material in Containment

Page 27: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Page 7BFN UNIT 1 PROJECT PLAN

SUBMITTALS - LOOK AHEAD DUE DATE AND INPUT DUE

Description Input Resp Org Input Rec'd Sch'd Actual Sch'd Actual Due Comment Lic

Due Date to Date to Date to Date to Date Eng Concur Concur Signature Signature

19 Risk-Informed 3Q/05

Inservice Inspection Program

20 GL 88-20, S4 4Q/05 Individual Plant Examination of External Events for Severe Accident Vulnerabilities

21 GL 92-01 Reactor 4Q/05

Vessel Structural Integrity

Page 28: TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR … · - Present licensing actions, and other reviews that will be needed from NRR - Initiate dialogue on Regulatory Framework for Unit

Page 8

NRC COMMITMENTS - TOTAL OPEN (14) - FOUR-WEEK LOOK AHEAD

None _

CCTS Number Originating Lead Coord. Closure TVA Due Commitment Description Lic

Document Pkg Due to Date Eng. Lic

1None

s:lic/everyone/Project Plan Unit 1/020614 Unit 1 .doc