Transportation Improvement Program (TIP) for Fiscal Years 2017-2020 Presentation to Chittenden County Regional Planning Commission July 20, 2016

Upload: others

Post on 12-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

Transportation Improvement Program (TIP)for Fiscal Years 2017-2020

Presentation to Chittenden County Regional Planning Commission

July 20, 2016

Page 2: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

Transportation Planning and Project Implementation

Metropolitan Transportation Plan/ECOS Plan Broad Vision/Goals for Chittenden County

20 year vision developed by CCRPC

Planning Studies/Corridor StudiesComprehensive assessment of current and future transportation and land

use conditions

Scoping StudiesEvaluate existing and future conditions and develop a locally accepted

preferred alternative

FundingTIP/STIP/Capital Program

DesignRight-of WayConstruction

Page 3: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

What is the Transportation Improvement Program (TIP)?

The TIP is a prioritized, fiscally-constrained, multi-year list of federally-funded, multimodal transportation projects and operations in the MPO region • Must be fiscally-constrained

• Must cover at least 4-years

• Must be updated at least every 4 years

• Authorizes obligation of federal funds

Page 4: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

How do Projects Get on the TIP?• The TIP is based on a continuing, comprehensive

transportation planning process carried out cooperatively by the State, the MPO, and transit operators

• Projects must have completed, or nearly completed, the planning process and be ready for design

• Projects must have funding

• In order to spend funds, projects must be listed in VTrans Capital Program

Page 5: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

Capital Program vs. TIP/STIPCapital Program

• State Document

• Developed by VTrans and VT Legislature

• Budget Document

• All transportation projects

• Federal and state dollars to be spent on transportation projects

• Selection based on VTrans and RPC priorities

• Projects cannot spend Federal or State dollars unless they are listed in the Capital Program

TIP/STIP• Federal Document

• Developed by VTrans and CCPRC, Required by FHWA

• Planning Document

• Federally funded transportation projects

• Federal funds to be obligated

• Must conform with CCRPC’s MTP

• Projects cannot spend Federaldollars unless they are listed in the TIP/STIP

Page 6: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

How to Read the TIPThe TIP contains the following three sections:

Section I: Introduction• What the TIP is• Adoption Resolution• Glossary of Acronyms• TIP Map

Section II: Projects by Municipality• Chittenden County projects

that CCRPC authorizes for obligation of federal funds

Page 7: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation
Page 8: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

How to Read the TIP

Section III: Summary of Financial Statistics• Figures and tables showing federal funds by

CCRPC Project Use Categories and federal funding sources

Page 9: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

TIP Funding Levels

Amount of Federal Funds in each year:

• FY2017 -- $93.7 million

• FY2018 -- $56.7 million

• FY2019 -- $54.2 million

• FY2020 -- $46.7 million

Page 10: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

100.0

FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20

Chittenden County TIP AmountsFY2006 - FY2020

BIA Projects

All Other Projects

Page 11: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

Paving6.3%Roadway System 

Management12.8%

Roadway Corridor Improvements

7.9%

Bridge Preservation7.0%

New Facility/Major Roadway Upgrade

15.6%

Bike/ Pedestrian2.1%

Transit 25.6%

Intermodal1.1%

Aviation21.4%

CCRPC FY2017‐2020 TIP Funding by Project Use Category

Page 12: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

TIP Projects by Use CategoriesAviation -- $53.9 Million

Bicycle/Pedestrian -- 13 Projects -- $5.3 Million

Bridge Preservation -- 8 Projects -- $17.7 Million

Intermodal -- 3 Projects -- $2.7 Million

New Facility/Major Roadway Upgrade -- 4 Projects -- $39.1 Million

Paving -- 4 Projects -- $15.8 Million

Roadway Corridor Improvements -- 6 Projects -- $19.9 Million

Roadway System Management -- 17 Projects -- $32.1 Million

Transit -- $64.4 Million

Other – 4 Projects -- $0.6 Million

Page 13: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

CIRC Alternative Projects Listed in FY2016-2019 TIPPhase I• Colchester - Exit 16 Improvements $8.3 M (FY18/19/20)

• Essex - VT2A/VT289 Interchange $1.5 M (FY17)

• Essex Junction - Crescent Connector $5.4 M (FY16/17/18)

• Williston - VT2A/James Brown Drive $1.9 M (FY17/18)

• Adaptive Signal Control $1 M (FY17)

Phase I Total $18.1 M

Phase II• Colchester - Severance Corners Intersection $4.8 M (FY20)

• Colchester-Essex - VT15 Multiuse Path $1.1 M (FY19)

• Essex - VT15/Sand Hill Road Intersection $1.1 M (FY19)

• Essex Junction - Pearl Street Improvements $1.5 M (FY17/18)

• Williston - US2/Trader Lane Traffic Signal $0.85 (State funds)

Phase II Total $9.3 M

Page 14: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

CIRC Alternative Projects Listed in FY2016-2019 TIP

Transit – FY17 is third and final year of CMAQ funding• CCTA Service – Jeffersonville Commuter $86,000• CCTA Service - Milton/Colchester to Burlington $29,838• CCTA Service - Williston Mid-Day $15,335Transit Total $131,173

Page 15: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

CIRC Alternative Projects Listed in FY2016-2019 TIPPhase III Projects in Design• Colchester - Blakely Road/Laker Lane Intersection • Colchester - Prim Road/West Lakeshore Drive Intersection • Colchester - VT2A Improvements• Essex - Susie Wilson Road Corridor and Intersections• Essex - VT117/North Williston Road Intersection (PE to begin in

FY17)

• Williston - I-89 Exit 12 Improvements - Stage 1

• Williston - VT2A/Industrial Avenue/Mountain View Road Intersection

Page 16: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

CIRC Alternative Projects Listed in FY2016-2019 TIPPhase III Projects not Started

• Colchester - Severance Road Path and Mill Pond Road Intersection

• Essex - VT117/North Williston Road Hazard Mitigation Improvements

• Essex - VT15 Sidewalk - Old Stage Road to Essex Way• Williston - I-89 Exit 12 Improvements - Stage 2, Stage 3 and

Stage 4

• Williston - Mountain View Road Shoulder Improvements• Williston - US2 Shared Use Path - Taft Corners to Williston

Village• Williston - VT2A Taft Corners Area Sidewalk/Shared Use

Path

Page 17: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

Federal Funding Sources

• FHWA Constrained Funds - $77.4 Million

• FHWA Non-Constrained Funds - $35.8 Million─ Includes $18.3 M for Circ Alternatives projects

• FHWA Transfer to FTA - $25.3 Million

• Federal Earmark or Grant Funds - $17.2 Million

• Federal Transit Administration - $41.8 Million(FTA) Funds

• Airport Improvement Program- $53.8 Million

Page 18: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

• Seguin Covered Bridge, Charlotte• US7 Reconstruction, Charlotte• US2/Clay Point Road, Colchester• Multi-Use Safety Path, Essex Junction• Essex Junction Paving – VT15,

VT117, VT2A• Bridge 30 on Camels Hump Road,

Huntington• I-89 Culvert, Colchester (75-1N)• I-89 Culverts, South Burlington (63 &

64)• McMullen Road Sidewalk, Milton• US2/Bear Trap Road, Milton• Harvest Lane Sidewalk, Williston• Winooski Circulator

Projects to be Constructed in FY16 – this year

US2/Bear Trap Road, Milton

BR30 on Camels Hump Road, Huntington

Winooski Circulator

Page 19: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

• VT117 Paving, Essex, Jericho, Richmond (FY17/18)

• VT15/Browns Trace Intersection, Jericho (FY17)

• US2 Paving, South Burlington/Williston (FY17)

• VT2A Paving, Williston (FY17)

Projects that will not be Constructed in FY16 – this year

Page 20: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

Projects to be Constructed in FY17 – next yearBike/Ped• Champlain Elementary Pedestrian Crossing, Burlington• Colchester Avenue Sidepath, Burlington• North Avenue Crosswalks, Burlington• Fort Ethan Allen Sidewalk Improvements, Colchester• Mountain View Drive Sidewalks• Towers Road Sidewalk, Essex• Village North Sidewalk, Hinesburg• Browns River Middle School and Union ID School

Crossing Improvements, Jericho• Village Sidewalks and Crosswalks, Shelburne• VT116 Sidewalk to Tilley Drive, South Burlington• VT15/Underhill Flats Sidewalk, Underhill• VT2A Infill Sidewalk South of Taft Corners, Williston

Page 21: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

Projects to be Constructed in FY17 – next yearBridge• Bridge 8 on Main Road, Huntington (south of Moody Road)• Bridge 32 on US2 over Snipe Island Brook, Richmond• VT116 Potash Brook Culvert, South BurlingtonIntermodal• Exit 16 Park and Ride• Williston Park and RideNew Facility/Major Roadway Upgrade• Crescent ConnectorPaving• US2 Paving, South Burlington-Williston• VT2A Paving, Williston

Page 22: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

Projects to be Constructed in FY17 – next yearRoadway Corridor Improvement• Pearl Street Improvements, Essex Junction• Market Street Construction, South BurlingtonRoadway System Management• VT2A/US7/Creek Road/Bay Road, Colchester• VT2A/VT289 Intersection Phase II, Essex• Signal Upgrades on VT2A and VT15, Essex, Williston• VT116/CVU Road, Hinesburg• VT15/Browns Trace Intersection Improvements, Jericho• VT2A/James Brown Drive, Williston

Page 23: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

Proposed Changes

Crescent Connector, Essex Junction Project HC014

• Increase funding in FY16 from $1,000,000 to $1,600,000

• Reduce funding in FY18 from $3,800,000 to $3,700,000

Cost Escalation• Increase funds in FY18, FY19, FY20 by 1.5% per year

Page 24: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

Annual Listing of Projects Receiving Federal Funds

FY99 FY00 FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15

Page 25: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation
Page 26: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

Projects Constructed in FY15

• Mill Pond Road Bridge, Colchester• Vt128 Slope Stability System, Essex• VT2A Bike Path, Old Colchester

Road to Pinecrest, Essex• Browns Trace Multi-modal

Connection, Jericho• Plains Road to Jericho Center• US2/Exit 14, South Burlington• Meadow Run to Alliance Church,

Williston

Meadow Run to Alliance Church Path, Williston Browns Trace Multi-modal Connection, Jericho

VT128 Slope Stability System, Essex

Mill Pond Road Bridge, Colchester

Page 27: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

$0

$5

$10

$15

$20

$25

$30

$35

$40

$45

$50

FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15

Millions

Federal Funds Obligated in Chittenden County by Use CategoryFY2006 ‐ FY2015

Bike/Pedestrian

Bridge

Intermodal

New Facility/MajorRoadway UpgradePaving

Roadway CorridorImprovementsRoadway SystemManagementTransit Service

Transit Capital

Other

Page 28: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

Questions?Comments?

Page 29: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

Next Steps

• Recommend that the Board approve the FY17-20 TIP with changes

Page 30: Transportation Improvement Program (TIP) for Fiscal Years ... · Presentation to Chittenden County Regional Planning Commission July 20, 2016. ... •Budget Document •All transportation

$0.0

$10.0

$20.0

$30.0

$40.0

$50.0

$60.0

$70.0

FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20

Chittenden County TIP As Adopted and Obligation AmountsFY2006 - FY2020

Obligation Amount TIP Amount