transportation investment act meeting...95. tia projects let to construction in 2018. 66. tia...

21
Transportation Investment Act Program Delivery Committee Kenneth Franks, State TIA Administrator

Upload: others

Post on 19-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

Transportation Investment ActProgram Delivery Committee

Kenneth Franks, State TIA Administrator

Page 2: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

TIA Regions

River Valley HOGA

CSRA

Southern Georgia

Page 3: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

TIA Timeline

Page 4: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

First 6 Years of TIA

521 Projects Advanced to Construction

Page 5: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

Revenue Collections by RegionRegion Total Approved

Investment List (75%)Local Discretionary

(25%)

CSRA $376,616,735* $282,462,551* $94,154,184*

River Valley $262,398,229* $196,798,671* $65,599,557*

HOGA $166,376,723* $124,782,542* $41,594,181*

Southern Ga $0.00 $0.00 $0.00

Totals(*rounded amounts)

$805,391,687 $604,043,764 $201,347,922

Page 6: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

TIA 2018 Highlights

95TIA Projects Let to Construction in 2018

66TIA Projects Completed 2018

$75,459,582TIA Program Expenditures in 2018

Page 7: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

CSRA Project Overview84

Total Projects

$538,965,884Final Investment List

Project Total

16In Construction

40Projects Completed

$160,234,172Total Expenditure to Date

(as of 11.13.18)

Wilkes Lincoln

Richmond

Columbia

BurkeJefferson

Jenkins

Hancock

Washington

Warren

Page 8: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

Lewiston Road at I-20 Interim Improvement

Page 9: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

Lewiston Road at I-20 Interim Improvement

Page 10: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

HOGA Project Overview

764Total Projects

$255,524,067Final Investment List

Project Total

12In Construction

439Projects Completed

$89,634,894Total Expenditure to Date

(as of 11.13.18)

Johnson

Emanuel

Wayne

Evans

Tattnall

Candler

ApplingJeff

Davis

Telfair

Dodge

Wilcox

Laurens

Page 11: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

HOGA Project Status

Page 12: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

Vidalia Projects

Page 13: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

River Valley Project Overview

Harris Talbot

Taylor

Macon

Dooly

Crisp

Sumter

Randolph

Stewart

Marion

Schley

23Total Projects

$380,828,512Final Investment List

Project Total

7In Construction

7Projects Completed

$117,177,263Total Expenditure to Date

(as of 11.13.18)

Page 14: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

Lake Blackshear

Page 15: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

Southern GA Project Overview151

Total Projects

$408,763,452Final Investment List

Project Total

Band 184 ProjectsBand 2

34 ProjectsBand 3

33 Projects

ATKINSON

BENHILL

BERRIEN

CHARLTONCLINCH

COFFEE

COOK

ECHOLS

IRWIN

PIERCETIFT

WARE

Page 16: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

Southern GA Timeline

Page 17: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

Southern GA Citizen’s Review Panel

Mr. Walter HudsonIrwin County

Mr. Patrick JonesWare County

Mr. D.W. HarperIrwin County(CRP Vice-Chair)

CommissionerRobert GrinerBerrien County

Chairman Bill SlaughterLowndes County

(CRP Chairman)

Page 18: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

Southern GA ProjectsProject Type # of Projects

Resurfacing/ Paving 94Bridge 14Safety/ Operations 13Sidewalks 13Widening/ Passing Lanes 10Airport 4Interchange 2New Roadway 1

Page 19: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

TIA 2019 Highlighted Projects• CSRA-Flowing Wells Road widening in Columbia Co. ($20M)• CSRA-SR4/15th St. Widening in Richmond Co. ($21M)• HOGA-Hillcrest Parkway widening in Laurens Co. ($17.5M)• HOGA-SR 135 over the Altamaha River Montgomery and Jeff Davis

($7M)• RV-SR 1/US 27 Harris Co. NB Passing Lane ($2.9M)• RV-Buena Vista Road Interchange Muscogee Co. ($47M) • RV-Buena Vista Road Intersection(Spider Web) ($40M)• SG-I-75 @ SR 31 (Exit 11) Interchange Recon. Lowndes Co.

($19.5M)• SG-Ware Street Resurface & Minor Widening Pierce Co. ($2.6M)• SG-Clinch Co. Resurfacing Bundle ($2.5M)

Page 20: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

The TIA Office

Kenneth FranksTIA Administrator

(404) [email protected]

Brent MoseleyTIA Regional Coordinator

SG & HOGA(912) 661-7157

[email protected]

William EastinTIA Regional Coordinator

River Valley & SG(404) 631-1810

[email protected]

Eric WilkinsonTIA Regional Coordinator

CSRA, HOGA, & SG(478) 538-8522

[email protected]

www.ga-tia.com

Page 21: Transportation Investment Act Meeting...95. TIA Projects Let to Construction in 2018. 66. TIA Projects Completed 2018. $75,459,582. TIA Program Expenditures in 2018

Questions?

SUMMER 2019