transportation_master_plan_2007_web_version_-_chapter_3_part_2 (1).pdf

Upload: ramadan-duraku

Post on 15-Feb-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/23/2019 transportation_master_plan_2007_web_version_-_chapter_3_part_2 (1).pdf

    1/10

    3.0 Roadway Infrastructure

    as part of the 2006 TMP scope of work, it is recognized that this corridor is in need of

    improvement. It is therefore recommended that the Town consider reconstructing this

    section of roadway as either (a) a two lane, two way roadway with separate parking lane

    and consolidation of access where possible (similar to the treatment implemented in

    Golden, BC), or (b) development of the roadway as a two lane one way operation, alsowith a separate parking lane and consolidation of access (similar to the treatment

    implemented in Airdrie, AB). There may be merit to retaining two way operation, or

    converting it to one way operation, though this would require further study prior to

    developing a recommended plan. As such, the necessary exercise would entail the

    undertaking of an Access Management Plan and Conceptual Design Study. It is

    recommended that the Town seek to undertake this study in the near term.

    3.3.9 Summary of Short Term (Immediate) Traffic Improvements

    The analysis outlined in Section 3.3 identified a series of Short Term improvements for

    immediate implementation. Most of these were identified previously in the 20012 TMP.

    A summary of the Short Term improvements are illustrated on Exhibit 3.4.

    3.4 LONG-TERM TRAFFIC VOLUME PROJECTIONS

    3.4.1 Background

    The 1993 Town of Canmore Transportation Studyprepared by IMC Consulting Group,

    Inc (IMC study) contained some specific recommendations for the long-term roadwaynetwork for a 20,000 population horizon. The forecasting undertaken in the 2001

    Transportation Master Plan involved a manual adjustment and linear extrapolation of the

    IMC forecasts based on changes in road network and other factors. Specific changes

    included in the 2001 analysis included the following:

    The proposed Spine Road that was recommended to connect the Three

    Sisters area to the Trans Canada Highway via a new bridge over the Bow River

    is not included in the long term road network. Instead, the Mid-point

    Interchange will be used as the primary route between the Three Sisters area

    and the Trans Canada Highway.

    The loop roadway from Silvertip to Eagle Terrace has been modified such that

    no direct travel between these two areas is currently permitted.

    47

    N:\Project Files\1009 Town of Canmore\07 2006 TMP Update\C\Report\Draft and Final Reports\Final Report\3-Final Report.doc07/09/2007

  • 7/23/2019 transportation_master_plan_2007_web_version_-_chapter_3_part_2 (1).pdf

    2/10

    C:\h_drive\projects\Bunt\1009 07\1009 07_Exhibits_3 7_3 8.cdr 13/04/07 WOZ

    IMPROVE MID BLOCK CROSSINGS

    - TRIM AND MAINTAIN VEGETATION

    - INSTALL ADVANCE WARNING SIGNS

    - BAN NORTH SIDE PEDESTRIAN CROSSING

    - APPLY CHIP SEAL TO SOUTHBOUND APPROACH

    - PROVIDE PEDESTRIAN SIGNAL PHASES

    - INSTALL SIGNAGE

    - INSTALL PEDESTRIAN BUMP-OUT

    IMPROVE PEDESTRIAN CROSSING SAFETY BY

    PROVIDING IMPROVED SIGHT LINES AND

    ADVANCE WARNING SIGNAGE

    INSTALL REDUCED SIGHT DISTANCE SIGNS

    REPLACE EXISTING 3-WAY STOP WITH

    A 2-WAY OR 4-WAY STOP CONTROL

    INSTALL LANE STRIPING

    POSSIBLE FUTURE ROUNDABOUT LOCATION

    PROVIDE PEDESTRIAN SIGNAL PHASES

    IMPROVE INTERSECTION GEOMETRY

    OTHERRECOMMENDATIONS

    UNDERTAKE ACCESS MANAGEMENT STUDY

    CONSTRUCT AT GRADE

    TRAIL CROSSING OVER RAIL

    - CONSTRUCT A REGIONAL MULTI-USE TRAIL

    - CONSTRUCT A PEDESTRIAN BARRIER

    ALONG TRANSCANADA HIGHWAY

    CONSTRUCT SIDEWALK TO PROVIDE

    CONTINUOUS PEDESTRIAN LINK

    CONSTRUCT SIDEWALK

    MONITOR TOWN

    CENTRE INTERSECTIONS

  • 7/23/2019 transportation_master_plan_2007_web_version_-_chapter_3_part_2 (1).pdf

    3/10

    3.0 Roadway Infrastructure

    The future traffic volume projections developed in 2001 were coarse, and were intended

    for a high level review of possible infrastructure improvements. The RFP issued by the

    Town for the 2006 update included consideration of a full re-working of the forecasts for

    the 30,000 population horizon to specifically consider new land use, population and

    employment data, approved ASPs developed in the time since the 2001 TMP, and theuse of a computer based tool to provide the Town with a means to re-assess the adequacy

    of the road network and associated infrastructure improvements in the future.

    Bunt & Associates chose to utilize the VISUM software package, a traffic forecasting

    model developed by the PTV Group. Bunt & Associates initially recommended using T-

    model for this purpose, but it was found that this model was no longer being supported

    and that it had been integrated into the VISUM framework. Bunt & Associates therefore

    included PTV on the project team to participate in the development of a VISUM model

    for the Town of Canmore for the 30,000 population horizon.

    3.4.2 Development of Traffic Forecasting Model

    This document is intended as a guide for those using the City of Canmore model, to

    understand in a general sense how the model was crafted and implemented. The model is

    a four-step model process containing: trip generation, trip distribution, mode choice, and

    assignment. The first part will review the data provided and network assumptions.

    Following, the model validation will be described.

    3.4.2.1 Data and Network

    Road and Intersection Coding

    The VISUM software platform was used, specifically, version 9.44-4. Base network

    information was imported from NAVTEQ tiles. Roadway classification, speeds and

    capacity were provided to PTV and modified to best fit the vehicle counts provided. In

    select cases the speed was modified on arterial links to 70 km/hr (kph). A table of the

    link coding is below:

    49

    N:\Project Files\1009 Town of Canmore\07 2006 TMP Update\C\Report\Draft and Final Reports\Final Report\3-Final Report.doc07/09/2007

  • 7/23/2019 transportation_master_plan_2007_web_version_-_chapter_3_part_2 (1).pdf

    4/10

    3.0 Roadway Infrastructure

    Table 3.2: Assumed Link Volumes and Speeds

    Link TypePer Lane per Hour Capacity

    (vehicles)Speed (kph)

    Freeway 2000 110

    Provincial Highway 1700 70

    Ramps 1500 50

    Arterials 1500 60

    Secondary Highway 1500 60

    Collectors 1400 50

    Local 1200 varies

    Intersection control was coded based on data provided to PTV for the project. Table 3.3

    describes the control type.

    Table 3.3: Intersection Control Modeling

    Node Type Type Number K4

    Uncontrolled 1 1

    Two-Way Stop 2 0.35

    Signal 3 0.45

    Ramp Diverge 4 1

    Ramp Merge 5 1

    All-way Stop Roundabout 6 0.30

    K4 is the coefficient for node capacity calculation. Junction capacity in the Canmore

    model is calculated as the capacity of the inbound roads multiplied by K4. Intersection

    control information was provided to PTV by Bunt Engineering and Associates. Two-way

    stop control had special delay links coded. Special delay links assign the delay to the

    approaches that must stop and wait for the opposing movement to clear in order to pass.

    Roundabouts are coded as if they were an all-way stop. Roundabouts and all-way stops

    share the delay for each approach leg.

    Turning movements at intersections were also coded. Table 3.4 summarizes the input

    parameters showing single-lane capacity, delay, and allowed movements for each turn

    type in the Canmore transportation model network. U-turns were not allowed. Other

    movements may not be allowed based on information received by PTV from the Bunt

    Engineering & Associates.

    50

    N:\Project Files\1009 Town of Canmore\07 2006 TMP Update\C\Report\Draft and Final Reports\Final Report\3-Final Report.doc07/09/2007

  • 7/23/2019 transportation_master_plan_2007_web_version_-_chapter_3_part_2 (1).pdf

    5/10

    3.0 Roadway Infrastructure

    Table 3.4: Intersection Delay and Capacity

    Turn Type Delay (seconds)Per Hour Capacity

    (turning vehicles)

    Through 0 no restriction

    Left 10 180

    Right 6 400

    U-turn 0 not allowed

    Link and node delay are defined in the model stream. Exhibits 3.5 and 3.6demonstrate

    an example of the link and node delay function used in the Canmore model. Delay

    functions serve to define how much impedance one experiences by using a specific road

    or passing through an intersection. The same function with coefficients specific to each

    network type is used for all links and nodes except uncontrolled local street intersections

    which are a coded with a constant amount of delay.

    Exhibit 3.5: Node Delay Function

    51

    N:\Project Files\1009 Town of Canmore\07 2006 TMP Update\C\Report\Draft and Final Reports\Final Report\3-Final Report.doc07/09/2007

  • 7/23/2019 transportation_master_plan_2007_web_version_-_chapter_3_part_2 (1).pdf

    6/10

    3.0 Roadway Infrastructure

    Exhibit 3.6: Link Delay Function

    Exhibit 3.7shows a plot of the model domain.

    Exhibit 3.7: Model Domain

    52

    N:\Project Files\1009 Town of Canmore\07 2006 TMP Update\C\Report\Draft and Final Reports\Final Report\3-Final Report.doc07/09/2007

  • 7/23/2019 transportation_master_plan_2007_web_version_-_chapter_3_part_2 (1).pdf

    7/10

    3.0 Roadway Infrastructure

    Land Use and Transportation Analysis Zones (TAZ)

    Canadian census geography defined the structure for the Canmore model. Census

    information provided to PTV was the basis for TAZ boundaries and provided the

    activities for trip generation. In TAZ 25 and 27 the commercial land uses were updatedbased on field information provided to PTV. Connectors were coded in multiple

    locations to provide access points to the zones. Land use types are listed in Table 3.5.

    Table 3.5: Land Use Modeling

    Land Use Category Units

    Permanent Resident Residents

    Non-Permanent Resident Residents

    Office Employees

    Commercial (including retail) Employees

    Education Employees

    Hotel Employees

    Manufacturing Employees

    Trip Generation, Distribution, and Assignment

    The Canmore model is a land use based evening peak hour simulation. Trips were

    generated based on data provided from a recent travel survey conducted in Canmore.

    The survey was especially helpful in estimating external trip activities (i-x, x-i, and x-xtrips). The travel survey also helped define the number of trips by purpose. In the future

    additional survey data would help refine travel characteristics used in model

    development.

    Trips are created in the Canmore model simply by factoring land use activities by a trip

    generation factor specific for each activity. The subsequent trips need to then be

    distributed to develop an origin-destination matrix. A modified gravity type formula is

    used for each trip purpose. An example of the function is included in Exhibit 3.8.

    53

    N:\Project Files\1009 Town of Canmore\07 2006 TMP Update\C\Report\Draft and Final Reports\Final Report\3-Final Report.doc07/09/2007

  • 7/23/2019 transportation_master_plan_2007_web_version_-_chapter_3_part_2 (1).pdf

    8/10

    3.0 Roadway Infrastructure

    Exhibit 3.8: Trip Distribution Function for Home-Work Trip Purpose

    The travel survey conducted in Canmore was also helpful in setting the parameters for the

    trip distribution step. These parameters defined the frequency distribution of trips by

    time interval. The trip distribution parameters are listed in Table 3.6by trip purpose.

    Table 3.6: Trip Distribution Modeling

    ParametersTrip Purpose

    a b c

    Home-Work -2.5 2 100

    Work-Home -2.5 2 100

    Home-Other -2 3 200

    Other-Home -2 3 200

    Non-Home -2.5 2.5 100

    The only mode in the Canmore model was the automobile mode. Other modes can be

    built into the model in the future as data and analysis needs support these enhancements.

    54

    N:\Project Files\1009 Town of Canmore\07 2006 TMP Update\C\Report\Draft and Final Reports\Final Report\3-Final Report.doc07/09/2007

  • 7/23/2019 transportation_master_plan_2007_web_version_-_chapter_3_part_2 (1).pdf

    9/10

    3.0 Roadway Infrastructure

    Assignment is a multi-equilibrium procedure. Equilibrium assignment is an optimal

    strategy method where as all paths are assigned in the system aggregate routing reaches a

    minimum time, distance, or combination of the two. In the Canmore model equilibrium

    assignment routing is based on optimal time strategies. The initial impedance is defined

    as the average of the free-flow and constrained routing in the network. The processiterates until the assignment reaches its solution. The assignment process of trips gives

    us what many people first look at in a modeling system: roadway volumes and the

    subsequent operational characteristics. The parameters of the assignment are listed in

    Exhibit 3.9.

    55

    N:\Project Files\1009 Town of Canmore\07 2006 TMP Update\C\Report\Draft and Final Reports\Final Report\3-Final Report.doc07/09/2007

    Exhibit 3.9: Equilibrium Assignment Parameters for the Canmore Model

  • 7/23/2019 transportation_master_plan_2007_web_version_-_chapter_3_part_2 (1).pdf

    10/10

    3.0 Roadway Infrastructure

    Multi-point assignment (MPA) was used in the Canmore model. MPA allows discrete

    shares to be assigned to the network at logical locations for transportation analysis zone

    ingress and egress. VISUM allows shares and connectors to be modified as access and

    land use changes in a zone using multi-point assignment.

    Model Validation

    PTV received vehicle ground data for the evening peak hour. Turning movement, daily

    volume, and evening peak hour counts were used to validate the model set for Canmore.

    To accept a model, an evaluation of model roadway volumes are compared to observed

    counts. A corresponding plot of this comparison is generated and statistical outcomes are

    measured. Generally accepted practice is an R-squared value of 0.88 or greater, a slope

    near 1.0, the percent (In) greater than 75, and an RMSE less than 35 percent. An R-

    squared value above 0.9 is considered well calibrated. The model assignment analysis is

    illustrated below in Exhibit 3.10. The Canmore model is well within the prescribedthresholds for acceptable practice having an R-squared value greater than 0.9, a percent

    in of greater than 90, and the RMSE less than 32.

    56

    N:\Project Files\1009 Town of Canmore\07 2006 TMP Update\C\Report\Draft and Final Reports\Final Report\3-Final Report.doc07/09/2007

    Exhibit 3.10: PM Peak Hour Assignment Analysis