Treasure Island Development Authority
Treasure Island Development Program
Item 6: 2017 – The Year Ahead
February 7, 2017
Treasure Island Development Authority
• TIDA Board welcomed Sam Moss
• Transferred development parcels in the first subphase areas to TICD
• Secured BCDC Major Permit Approval
• Accepted second Navy land transfer
• Completed demolition of structures on Yerba Buena Island & initiated demolition on Treasure Island
• New westbound Bay Briddge on/off ramps opened
• Initiated formation of public financing districts
• Caltrans opened bike path to YBI
2016 – Events & Milestones
Treasure Island Development Authority
• Anticipate three property
transfers in 2017
• Field work complete in Site 24
• Completion of Site 12 TCRA and
Stage III Removal Actions
• Stage IV work to begin late 2017
or early 2018
Navy Property Transfers
Parcel FOST Date
Parcels Building 233, UC 1 & UC 2 6 Pending
Parcels 30, 30N, 30S, 30W & 31 7 01/31/2017
Parcels 6 & 32 8 07/31/2017
Parcel 24 9 01/30/2018
Parcel 2 10 12/31/2020
Parcels 12A, 12B & Navy
Retained Sites11 12/31/2021
3
Treasure Island Development Authority
• Secure Secure permit approvals for infrastructure improvements
• Secure tentative and final subdivision map approvals
• Draft Public Improvement Agreements
• Prepare design construction documents for open space projects
2017 – Design
Treasure Island Development Authority
Construction Activity – 2017
• Complete demolition in initial Treasure Island sub-phase area
• Initial infrastructure contracts awarded, bid, or advertised• Water reservoir design/build
• Yerba Buena utility/right-of-way infrastructure
• Geotechnical & causeway reconstruction
• Treasure Island utility/right-of-way infrastructure
• Tree removal/relocation/preservation
5
Mobilizing in March
Treasure Island Development Authority
Construction Activity
6
Treasure Island Development Authority
2017 – Planning
• Initiate preparation of Subphase Applications for the balance of Major Phase 1
Treasure Island Development Authority
• Continue planning for congestion management implementation
• Negotiate operating MOUs with AC Transit & WETA
• Begin construction of Southgate/Hillcrest interchange
• Advance design for the westside viaducts
• With SFMTA study/develop parking policies
2017 – TIMMA
Treasure Island Development Authority
• Finalize long-term leases with Treasure Island Enterprises and Treasure Island Sailing Center
• Begin BCDC application process with TIE
2017 – Clipper Cove