Treasure Island Development Authority Treasure Island Development Program Item 6: 2017 The Year Ahead February 7, 2017

Upload: others

Post on 06-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Treasure Island Development Program...Stage III Removal Actions •Stage IV work to begin late 2017 or early 2018 Navy Property Transfers Parcel FOST Date Parcels Building 233, UC

Treasure Island Development Authority

Treasure Island Development Program

Item 6: 2017 – The Year Ahead

February 7, 2017

Page 2: Treasure Island Development Program...Stage III Removal Actions •Stage IV work to begin late 2017 or early 2018 Navy Property Transfers Parcel FOST Date Parcels Building 233, UC

Treasure Island Development Authority

• TIDA Board welcomed Sam Moss

• Transferred development parcels in the first subphase areas to TICD

• Secured BCDC Major Permit Approval

• Accepted second Navy land transfer

• Completed demolition of structures on Yerba Buena Island & initiated demolition on Treasure Island

• New westbound Bay Briddge on/off ramps opened

• Initiated formation of public financing districts

• Caltrans opened bike path to YBI

2016 – Events & Milestones

Page 3: Treasure Island Development Program...Stage III Removal Actions •Stage IV work to begin late 2017 or early 2018 Navy Property Transfers Parcel FOST Date Parcels Building 233, UC

Treasure Island Development Authority

• Anticipate three property

transfers in 2017

• Field work complete in Site 24

• Completion of Site 12 TCRA and

Stage III Removal Actions

• Stage IV work to begin late 2017

or early 2018

Navy Property Transfers

Parcel FOST Date

Parcels Building 233, UC 1 & UC 2 6 Pending

Parcels 30, 30N, 30S, 30W & 31 7 01/31/2017

Parcels 6 & 32 8 07/31/2017

Parcel 24 9 01/30/2018

Parcel 2 10 12/31/2020

Parcels 12A, 12B & Navy

Retained Sites11 12/31/2021

3

Page 4: Treasure Island Development Program...Stage III Removal Actions •Stage IV work to begin late 2017 or early 2018 Navy Property Transfers Parcel FOST Date Parcels Building 233, UC

Treasure Island Development Authority

• Secure Secure permit approvals for infrastructure improvements

• Secure tentative and final subdivision map approvals

• Draft Public Improvement Agreements

• Prepare design construction documents for open space projects

2017 – Design

Page 5: Treasure Island Development Program...Stage III Removal Actions •Stage IV work to begin late 2017 or early 2018 Navy Property Transfers Parcel FOST Date Parcels Building 233, UC

Treasure Island Development Authority

Construction Activity – 2017

• Complete demolition in initial Treasure Island sub-phase area

• Initial infrastructure contracts awarded, bid, or advertised• Water reservoir design/build

• Yerba Buena utility/right-of-way infrastructure

• Geotechnical & causeway reconstruction

• Treasure Island utility/right-of-way infrastructure

• Tree removal/relocation/preservation

5

Mobilizing in March

Page 6: Treasure Island Development Program...Stage III Removal Actions •Stage IV work to begin late 2017 or early 2018 Navy Property Transfers Parcel FOST Date Parcels Building 233, UC

Treasure Island Development Authority

Construction Activity

6

Page 7: Treasure Island Development Program...Stage III Removal Actions •Stage IV work to begin late 2017 or early 2018 Navy Property Transfers Parcel FOST Date Parcels Building 233, UC

Treasure Island Development Authority

2017 – Planning

• Initiate preparation of Subphase Applications for the balance of Major Phase 1

Page 8: Treasure Island Development Program...Stage III Removal Actions •Stage IV work to begin late 2017 or early 2018 Navy Property Transfers Parcel FOST Date Parcels Building 233, UC

Treasure Island Development Authority

• Continue planning for congestion management implementation

• Negotiate operating MOUs with AC Transit & WETA

• Begin construction of Southgate/Hillcrest interchange

• Advance design for the westside viaducts

• With SFMTA study/develop parking policies

2017 – TIMMA

Page 9: Treasure Island Development Program...Stage III Removal Actions •Stage IV work to begin late 2017 or early 2018 Navy Property Transfers Parcel FOST Date Parcels Building 233, UC

Treasure Island Development Authority

• Finalize long-term leases with Treasure Island Enterprises and Treasure Island Sailing Center

• Begin BCDC application process with TIE

2017 – Clipper Cove

Page 10: Treasure Island Development Program...Stage III Removal Actions •Stage IV work to begin late 2017 or early 2018 Navy Property Transfers Parcel FOST Date Parcels Building 233, UC

Treasure Island Development Authority

Discussion