triangle construction 4th r.a. bill for township ii

183
Doc. No.: TC/CGPL/11-12/RA-4 RA Bill Summary SITE ADDRESS : MUNDRA R A Bill No. : 4th Project : Township For CGPL At Mundra. Bill date : 31/08/2011 CLIENT : COASTAL GUJARAT POWER LIMTED (CGPL) - MUNDRA Period - 23/07/2011 TO 31/08/ Local Sales Tax No. : 24011005673 CST No. : WO No :6300001044 S. No. Description A Value of Work done i Tender items ### 2,043,057.64 Net value of Tender items ### 2,043,057.64 B Value of Non Tendered / Extra items - - C ### 2,043,057.64 D Value of other bills i Escalation - - ii Extra items iii Reimbursement - - Sub total ( D ) - - E Gross value of Work done ( C + D ) ### 2,043,057.64 F Service Tax 10.30% on 33% of Total Amount 279,972.72 69,443.53 G Gross Value After Service Tax (E + F) ### 2,112,501.16 H Recoveries i Reinf. Steel Recovery ii Cement Recovery iii Str. Steel Recovery - - iv Water Charges - - v Electricity Charges - - vi Other Recoveries - - Total recoveries - - I Net value of Work done ( G-H) ### 2,112,501.16 J Deductions of Advances / Retention i Retention @ 5% on ( E ) 411,845.72 102,152.88 Performance bond @ 5% ii Others - ( To be specified) - - TOTAL DEDUCTIONS - J 411,845.72 102,152.88 K GROSS AMOUNT RECEIVABLE ( I - J ) ### 2,010,348.28 L - - M - - N TOTAL AMOUNT RECEIVABLE TILL DATE ( K+L-M) ### 2,010,348.28 O - - P NET AMOUNT RECEIVABLE TILL DATE (N-O) ### 2,010,348.00 For TRIANGLE CONSTRUCTION Triangle Construction Previous bill amount This bill amount Value of Work done including Client Supplied Materials (A+B) ADD Material advance for the current month LESS Material advance recieved last month TOTAL AMOUNT ( INCLUDING TDS) RECIEVED AGAINST BILL TILL DATE

Upload: triangle269

Post on 02-Dec-2014

59 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Triangle Construction 4th R.a. Bill for Township II

Doc. No.: TC/CGPL/11-12/RA-4

RA Bill SummarySITE ADDRESS : MUNDRA R A Bill No. : 4th Project : Township For CGPL At Mundra. Bill date : 31/08/2011

Period - 23/07/2011 TO 31/08/2011

Local Sales Tax No. : 24011005673 CST No. : WO No :6300001044

S. No. Description

A Value of Work donei Tender items 8,236,914.44 2,043,057.64 10,279,972.08

Net value of Tender items 8,236,914.44 2,043,057.64 ###B Value of Non Tendered / Extra items - - - C 8,236,914.44 2,043,057.64 10,279,972.08

D Value of other billsi Escalation - - - ii Extra itemsiii Reimbursement - - -

Sub total ( D ) - - - E Gross value of Work done ( C + D ) 8,236,914.44 2,043,057.64 10,279,972.08 F Service Tax 10.30% on 33% of Total Amount 279,972.72 69,443.53 69,443.53 G Gross Value After Service Tax (E + F) 8,516,887.17 2,112,501.16 10,629,388.33 H Recoveries

i Reinf. Steel Recovery

ii Cement Recovery

iii Str. Steel Recovery - - -

iv Water Charges - - -

v Electricity Charges - - -

vi Other Recoveries - - - Total recoveries - - -

I Net value of Work done ( G-H) 8,516,887.17 2,112,501.16 10,629,388.33 J Deductions of Advances / Retentioni Retention @ 5% on ( E ) 411,845.72 102,152.88 513,998.60

Performance bond @ 5%ii Others - ( To be specified) - - -

TOTAL DEDUCTIONS - J 411,845.72 102,152.88 513,998.60 K GROSS AMOUNT RECEIVABLE ( I - J ) 8,105,041.44 2,010,348.28 10,115,389.73 L - - - M - - - N TOTAL AMOUNT RECEIVABLE TILL DATE ( K+L-M) 8,105,041.44 2,010,348.28 10,115,389.73 O

- - - P NET AMOUNT RECEIVABLE TILL DATE (N-O) 8,105,041.00 2,010,348.00 10,115,389.00

For TRIANGLE CONSTRUCTION

Triangle Construction T.D.X. - 108, Barwadi, Adipur, Kutch, Gujarat.

CLIENT : COASTAL GUJARAT POWER LIMTED (CGPL) - MUNDRA

Previous bill amount

This bill amount

Cumulative bill amount

Value of Work done including Client Supplied Materials (A+B)

ADD Material advance for the current monthLESS Material advance recieved last month

TOTAL AMOUNT ( INCLUDING TDS) RECIEVED AGAINST BILL TILL DATE

Page 2: Triangle Construction 4th R.a. Bill for Township II

PROJECT MANAGER

Page 3: Triangle Construction 4th R.a. Bill for Township II
Page 4: Triangle Construction 4th R.a. Bill for Township II
Page 5: Triangle Construction 4th R.a. Bill for Township II
Page 6: Triangle Construction 4th R.a. Bill for Township II
Page 7: Triangle Construction 4th R.a. Bill for Township II
Page 8: Triangle Construction 4th R.a. Bill for Township II
Page 9: Triangle Construction 4th R.a. Bill for Township II
Page 10: Triangle Construction 4th R.a. Bill for Township II
Page 11: Triangle Construction 4th R.a. Bill for Township II
Page 12: Triangle Construction 4th R.a. Bill for Township II
Page 13: Triangle Construction 4th R.a. Bill for Township II
Page 14: Triangle Construction 4th R.a. Bill for Township II
Page 15: Triangle Construction 4th R.a. Bill for Township II
Page 16: Triangle Construction 4th R.a. Bill for Township II
Page 17: Triangle Construction 4th R.a. Bill for Township II
Page 18: Triangle Construction 4th R.a. Bill for Township II
Page 19: Triangle Construction 4th R.a. Bill for Township II
Page 20: Triangle Construction 4th R.a. Bill for Township II
Page 21: Triangle Construction 4th R.a. Bill for Township II
Page 22: Triangle Construction 4th R.a. Bill for Township II
Page 23: Triangle Construction 4th R.a. Bill for Township II
Page 24: Triangle Construction 4th R.a. Bill for Township II
Page 25: Triangle Construction 4th R.a. Bill for Township II
Page 26: Triangle Construction 4th R.a. Bill for Township II
Page 27: Triangle Construction 4th R.a. Bill for Township II
Page 28: Triangle Construction 4th R.a. Bill for Township II
Page 29: Triangle Construction 4th R.a. Bill for Township II
Page 30: Triangle Construction 4th R.a. Bill for Township II
Page 31: Triangle Construction 4th R.a. Bill for Township II
Page 32: Triangle Construction 4th R.a. Bill for Township II
Page 33: Triangle Construction 4th R.a. Bill for Township II
Page 34: Triangle Construction 4th R.a. Bill for Township II
Page 35: Triangle Construction 4th R.a. Bill for Township II
Page 36: Triangle Construction 4th R.a. Bill for Township II
Page 37: Triangle Construction 4th R.a. Bill for Township II
Page 38: Triangle Construction 4th R.a. Bill for Township II
Page 39: Triangle Construction 4th R.a. Bill for Township II
Page 40: Triangle Construction 4th R.a. Bill for Township II
Page 41: Triangle Construction 4th R.a. Bill for Township II
Page 42: Triangle Construction 4th R.a. Bill for Township II
Page 43: Triangle Construction 4th R.a. Bill for Township II
Page 44: Triangle Construction 4th R.a. Bill for Township II
Page 45: Triangle Construction 4th R.a. Bill for Township II
Page 46: Triangle Construction 4th R.a. Bill for Township II
Page 47: Triangle Construction 4th R.a. Bill for Township II
Page 48: Triangle Construction 4th R.a. Bill for Township II
Page 49: Triangle Construction 4th R.a. Bill for Township II
Page 50: Triangle Construction 4th R.a. Bill for Township II
Page 51: Triangle Construction 4th R.a. Bill for Township II
Page 52: Triangle Construction 4th R.a. Bill for Township II
Page 53: Triangle Construction 4th R.a. Bill for Township II
Page 54: Triangle Construction 4th R.a. Bill for Township II
Page 55: Triangle Construction 4th R.a. Bill for Township II
Page 56: Triangle Construction 4th R.a. Bill for Township II
Page 57: Triangle Construction 4th R.a. Bill for Township II
Page 58: Triangle Construction 4th R.a. Bill for Township II
Page 59: Triangle Construction 4th R.a. Bill for Township II
Page 60: Triangle Construction 4th R.a. Bill for Township II
Page 61: Triangle Construction 4th R.a. Bill for Township II
Page 62: Triangle Construction 4th R.a. Bill for Township II
Page 63: Triangle Construction 4th R.a. Bill for Township II
Page 64: Triangle Construction 4th R.a. Bill for Township II
Page 65: Triangle Construction 4th R.a. Bill for Township II
Page 66: Triangle Construction 4th R.a. Bill for Township II
Page 67: Triangle Construction 4th R.a. Bill for Township II
Page 68: Triangle Construction 4th R.a. Bill for Township II
Page 69: Triangle Construction 4th R.a. Bill for Township II
Page 70: Triangle Construction 4th R.a. Bill for Township II
Page 71: Triangle Construction 4th R.a. Bill for Township II
Page 72: Triangle Construction 4th R.a. Bill for Township II
Page 73: Triangle Construction 4th R.a. Bill for Township II
Page 74: Triangle Construction 4th R.a. Bill for Township II
Page 75: Triangle Construction 4th R.a. Bill for Township II
Page 76: Triangle Construction 4th R.a. Bill for Township II
Page 77: Triangle Construction 4th R.a. Bill for Township II
Page 78: Triangle Construction 4th R.a. Bill for Township II
Page 79: Triangle Construction 4th R.a. Bill for Township II
Page 80: Triangle Construction 4th R.a. Bill for Township II
Page 81: Triangle Construction 4th R.a. Bill for Township II
Page 82: Triangle Construction 4th R.a. Bill for Township II
Page 83: Triangle Construction 4th R.a. Bill for Township II
Page 84: Triangle Construction 4th R.a. Bill for Township II
Page 85: Triangle Construction 4th R.a. Bill for Township II
Page 86: Triangle Construction 4th R.a. Bill for Township II
Page 87: Triangle Construction 4th R.a. Bill for Township II
Page 88: Triangle Construction 4th R.a. Bill for Township II
Page 89: Triangle Construction 4th R.a. Bill for Township II
Page 90: Triangle Construction 4th R.a. Bill for Township II
Page 91: Triangle Construction 4th R.a. Bill for Township II
Page 92: Triangle Construction 4th R.a. Bill for Township II
Page 93: Triangle Construction 4th R.a. Bill for Township II
Page 94: Triangle Construction 4th R.a. Bill for Township II
Page 95: Triangle Construction 4th R.a. Bill for Township II
Page 96: Triangle Construction 4th R.a. Bill for Township II
Page 97: Triangle Construction 4th R.a. Bill for Township II
Page 98: Triangle Construction 4th R.a. Bill for Township II
Page 99: Triangle Construction 4th R.a. Bill for Township II
Page 100: Triangle Construction 4th R.a. Bill for Township II
Page 101: Triangle Construction 4th R.a. Bill for Township II
Page 102: Triangle Construction 4th R.a. Bill for Township II
Page 103: Triangle Construction 4th R.a. Bill for Township II
Page 104: Triangle Construction 4th R.a. Bill for Township II
Page 105: Triangle Construction 4th R.a. Bill for Township II
Page 106: Triangle Construction 4th R.a. Bill for Township II
Page 107: Triangle Construction 4th R.a. Bill for Township II
Page 108: Triangle Construction 4th R.a. Bill for Township II
Page 109: Triangle Construction 4th R.a. Bill for Township II
Page 110: Triangle Construction 4th R.a. Bill for Township II
Page 111: Triangle Construction 4th R.a. Bill for Township II
Page 112: Triangle Construction 4th R.a. Bill for Township II
Page 113: Triangle Construction 4th R.a. Bill for Township II
Page 114: Triangle Construction 4th R.a. Bill for Township II
Page 115: Triangle Construction 4th R.a. Bill for Township II
Page 116: Triangle Construction 4th R.a. Bill for Township II
Page 117: Triangle Construction 4th R.a. Bill for Township II
Page 118: Triangle Construction 4th R.a. Bill for Township II
Page 119: Triangle Construction 4th R.a. Bill for Township II
Page 120: Triangle Construction 4th R.a. Bill for Township II
Page 121: Triangle Construction 4th R.a. Bill for Township II
Page 122: Triangle Construction 4th R.a. Bill for Township II
Page 123: Triangle Construction 4th R.a. Bill for Township II
Page 124: Triangle Construction 4th R.a. Bill for Township II
Page 125: Triangle Construction 4th R.a. Bill for Township II
Page 126: Triangle Construction 4th R.a. Bill for Township II
Page 127: Triangle Construction 4th R.a. Bill for Township II
Page 128: Triangle Construction 4th R.a. Bill for Township II
Page 129: Triangle Construction 4th R.a. Bill for Township II
Page 130: Triangle Construction 4th R.a. Bill for Township II
Page 131: Triangle Construction 4th R.a. Bill for Township II
Page 132: Triangle Construction 4th R.a. Bill for Township II
Page 133: Triangle Construction 4th R.a. Bill for Township II
Page 134: Triangle Construction 4th R.a. Bill for Township II
Page 135: Triangle Construction 4th R.a. Bill for Township II
Page 136: Triangle Construction 4th R.a. Bill for Township II
Page 137: Triangle Construction 4th R.a. Bill for Township II
Page 138: Triangle Construction 4th R.a. Bill for Township II
Page 139: Triangle Construction 4th R.a. Bill for Township II
Page 140: Triangle Construction 4th R.a. Bill for Township II
Page 141: Triangle Construction 4th R.a. Bill for Township II
Page 142: Triangle Construction 4th R.a. Bill for Township II
Page 143: Triangle Construction 4th R.a. Bill for Township II
Page 144: Triangle Construction 4th R.a. Bill for Township II
Page 145: Triangle Construction 4th R.a. Bill for Township II
Page 146: Triangle Construction 4th R.a. Bill for Township II
Page 147: Triangle Construction 4th R.a. Bill for Township II
Page 148: Triangle Construction 4th R.a. Bill for Township II
Page 149: Triangle Construction 4th R.a. Bill for Township II
Page 150: Triangle Construction 4th R.a. Bill for Township II
Page 151: Triangle Construction 4th R.a. Bill for Township II
Page 152: Triangle Construction 4th R.a. Bill for Township II
Page 153: Triangle Construction 4th R.a. Bill for Township II
Page 154: Triangle Construction 4th R.a. Bill for Township II
Page 155: Triangle Construction 4th R.a. Bill for Township II
Page 156: Triangle Construction 4th R.a. Bill for Township II
Page 157: Triangle Construction 4th R.a. Bill for Township II
Page 158: Triangle Construction 4th R.a. Bill for Township II
Page 159: Triangle Construction 4th R.a. Bill for Township II
Page 160: Triangle Construction 4th R.a. Bill for Township II
Page 161: Triangle Construction 4th R.a. Bill for Township II
Page 162: Triangle Construction 4th R.a. Bill for Township II
Page 163: Triangle Construction 4th R.a. Bill for Township II
Page 164: Triangle Construction 4th R.a. Bill for Township II
Page 165: Triangle Construction 4th R.a. Bill for Township II
Page 166: Triangle Construction 4th R.a. Bill for Township II
Page 167: Triangle Construction 4th R.a. Bill for Township II
Page 168: Triangle Construction 4th R.a. Bill for Township II
Page 169: Triangle Construction 4th R.a. Bill for Township II
Page 170: Triangle Construction 4th R.a. Bill for Township II
Page 171: Triangle Construction 4th R.a. Bill for Township II
Page 172: Triangle Construction 4th R.a. Bill for Township II
Page 173: Triangle Construction 4th R.a. Bill for Township II
Page 174: Triangle Construction 4th R.a. Bill for Township II
Page 175: Triangle Construction 4th R.a. Bill for Township II
Page 176: Triangle Construction 4th R.a. Bill for Township II
Page 177: Triangle Construction 4th R.a. Bill for Township II
Page 178: Triangle Construction 4th R.a. Bill for Township II
Page 179: Triangle Construction 4th R.a. Bill for Township II
Page 180: Triangle Construction 4th R.a. Bill for Township II
Page 181: Triangle Construction 4th R.a. Bill for Township II
Page 182: Triangle Construction 4th R.a. Bill for Township II
Page 183: Triangle Construction 4th R.a. Bill for Township II
Page 184: Triangle Construction 4th R.a. Bill for Township II
Page 185: Triangle Construction 4th R.a. Bill for Township II
Page 186: Triangle Construction 4th R.a. Bill for Township II
Page 187: Triangle Construction 4th R.a. Bill for Township II
Page 188: Triangle Construction 4th R.a. Bill for Township II
Page 189: Triangle Construction 4th R.a. Bill for Township II
Page 190: Triangle Construction 4th R.a. Bill for Township II
Page 191: Triangle Construction 4th R.a. Bill for Township II
Page 192: Triangle Construction 4th R.a. Bill for Township II
Page 193: Triangle Construction 4th R.a. Bill for Township II
Page 194: Triangle Construction 4th R.a. Bill for Township II
Page 195: Triangle Construction 4th R.a. Bill for Township II
Page 196: Triangle Construction 4th R.a. Bill for Township II
Page 197: Triangle Construction 4th R.a. Bill for Township II
Page 198: Triangle Construction 4th R.a. Bill for Township II
Page 199: Triangle Construction 4th R.a. Bill for Township II
Page 200: Triangle Construction 4th R.a. Bill for Township II
Page 201: Triangle Construction 4th R.a. Bill for Township II
Page 202: Triangle Construction 4th R.a. Bill for Township II
Page 203: Triangle Construction 4th R.a. Bill for Township II
Page 204: Triangle Construction 4th R.a. Bill for Township II
Page 205: Triangle Construction 4th R.a. Bill for Township II
Page 206: Triangle Construction 4th R.a. Bill for Township II
Page 207: Triangle Construction 4th R.a. Bill for Township II
Page 208: Triangle Construction 4th R.a. Bill for Township II
Page 209: Triangle Construction 4th R.a. Bill for Township II
Page 210: Triangle Construction 4th R.a. Bill for Township II
Page 211: Triangle Construction 4th R.a. Bill for Township II
Page 212: Triangle Construction 4th R.a. Bill for Township II
Page 213: Triangle Construction 4th R.a. Bill for Township II
Page 214: Triangle Construction 4th R.a. Bill for Township II
Page 215: Triangle Construction 4th R.a. Bill for Township II
Page 216: Triangle Construction 4th R.a. Bill for Township II
Page 217: Triangle Construction 4th R.a. Bill for Township II
Page 218: Triangle Construction 4th R.a. Bill for Township II
Page 219: Triangle Construction 4th R.a. Bill for Township II
Page 220: Triangle Construction 4th R.a. Bill for Township II
Page 221: Triangle Construction 4th R.a. Bill for Township II
Page 222: Triangle Construction 4th R.a. Bill for Township II
Page 223: Triangle Construction 4th R.a. Bill for Township II
Page 224: Triangle Construction 4th R.a. Bill for Township II
Page 225: Triangle Construction 4th R.a. Bill for Township II
Page 226: Triangle Construction 4th R.a. Bill for Township II
Page 227: Triangle Construction 4th R.a. Bill for Township II
Page 228: Triangle Construction 4th R.a. Bill for Township II
Page 229: Triangle Construction 4th R.a. Bill for Township II
Page 230: Triangle Construction 4th R.a. Bill for Township II
Page 231: Triangle Construction 4th R.a. Bill for Township II
Page 232: Triangle Construction 4th R.a. Bill for Township II
Page 233: Triangle Construction 4th R.a. Bill for Township II
Page 234: Triangle Construction 4th R.a. Bill for Township II
Page 235: Triangle Construction 4th R.a. Bill for Township II
Page 236: Triangle Construction 4th R.a. Bill for Township II
Page 237: Triangle Construction 4th R.a. Bill for Township II
Page 238: Triangle Construction 4th R.a. Bill for Township II
Page 239: Triangle Construction 4th R.a. Bill for Township II
Page 240: Triangle Construction 4th R.a. Bill for Township II
Page 241: Triangle Construction 4th R.a. Bill for Township II
Page 242: Triangle Construction 4th R.a. Bill for Township II
Page 243: Triangle Construction 4th R.a. Bill for Township II
Page 244: Triangle Construction 4th R.a. Bill for Township II
Page 245: Triangle Construction 4th R.a. Bill for Township II
Page 246: Triangle Construction 4th R.a. Bill for Township II
Page 247: Triangle Construction 4th R.a. Bill for Township II
Page 248: Triangle Construction 4th R.a. Bill for Township II
Page 249: Triangle Construction 4th R.a. Bill for Township II
Page 250: Triangle Construction 4th R.a. Bill for Township II
Page 251: Triangle Construction 4th R.a. Bill for Township II
Page 252: Triangle Construction 4th R.a. Bill for Township II
Page 253: Triangle Construction 4th R.a. Bill for Township II
Page 254: Triangle Construction 4th R.a. Bill for Township II
Page 255: Triangle Construction 4th R.a. Bill for Township II
Page 256: Triangle Construction 4th R.a. Bill for Township II
Page 257: Triangle Construction 4th R.a. Bill for Township II
Page 258: Triangle Construction 4th R.a. Bill for Township II
Page 259: Triangle Construction 4th R.a. Bill for Township II
Page 260: Triangle Construction 4th R.a. Bill for Township II
Page 261: Triangle Construction 4th R.a. Bill for Township II
Page 262: Triangle Construction 4th R.a. Bill for Township II
Page 263: Triangle Construction 4th R.a. Bill for Township II
Page 264: Triangle Construction 4th R.a. Bill for Township II
Page 265: Triangle Construction 4th R.a. Bill for Township II
Page 266: Triangle Construction 4th R.a. Bill for Township II
Page 267: Triangle Construction 4th R.a. Bill for Township II
Page 268: Triangle Construction 4th R.a. Bill for Township II
Page 269: Triangle Construction 4th R.a. Bill for Township II
Page 270: Triangle Construction 4th R.a. Bill for Township II
Page 271: Triangle Construction 4th R.a. Bill for Township II
Page 272: Triangle Construction 4th R.a. Bill for Township II
Page 273: Triangle Construction 4th R.a. Bill for Township II
Page 274: Triangle Construction 4th R.a. Bill for Township II
Page 275: Triangle Construction 4th R.a. Bill for Township II
Page 276: Triangle Construction 4th R.a. Bill for Township II
Page 277: Triangle Construction 4th R.a. Bill for Township II
Page 278: Triangle Construction 4th R.a. Bill for Township II
Page 279: Triangle Construction 4th R.a. Bill for Township II
Page 280: Triangle Construction 4th R.a. Bill for Township II
Page 281: Triangle Construction 4th R.a. Bill for Township II
Page 282: Triangle Construction 4th R.a. Bill for Township II
Page 283: Triangle Construction 4th R.a. Bill for Township II
Page 284: Triangle Construction 4th R.a. Bill for Township II
Page 285: Triangle Construction 4th R.a. Bill for Township II
Page 286: Triangle Construction 4th R.a. Bill for Township II
Page 287: Triangle Construction 4th R.a. Bill for Township II
Page 288: Triangle Construction 4th R.a. Bill for Township II
Page 289: Triangle Construction 4th R.a. Bill for Township II
Page 290: Triangle Construction 4th R.a. Bill for Township II
Page 291: Triangle Construction 4th R.a. Bill for Township II
Page 292: Triangle Construction 4th R.a. Bill for Township II
Page 293: Triangle Construction 4th R.a. Bill for Township II
Page 294: Triangle Construction 4th R.a. Bill for Township II
Page 295: Triangle Construction 4th R.a. Bill for Township II
Page 296: Triangle Construction 4th R.a. Bill for Township II
Page 297: Triangle Construction 4th R.a. Bill for Township II
Page 298: Triangle Construction 4th R.a. Bill for Township II
Page 299: Triangle Construction 4th R.a. Bill for Township II
Page 300: Triangle Construction 4th R.a. Bill for Township II
Page 301: Triangle Construction 4th R.a. Bill for Township II
Page 302: Triangle Construction 4th R.a. Bill for Township II
Page 303: Triangle Construction 4th R.a. Bill for Township II
Page 304: Triangle Construction 4th R.a. Bill for Township II
Page 305: Triangle Construction 4th R.a. Bill for Township II
Page 306: Triangle Construction 4th R.a. Bill for Township II
Page 307: Triangle Construction 4th R.a. Bill for Township II
Page 308: Triangle Construction 4th R.a. Bill for Township II
Page 309: Triangle Construction 4th R.a. Bill for Township II
Page 310: Triangle Construction 4th R.a. Bill for Township II
Page 311: Triangle Construction 4th R.a. Bill for Township II
Page 312: Triangle Construction 4th R.a. Bill for Township II
Page 313: Triangle Construction 4th R.a. Bill for Township II
Page 314: Triangle Construction 4th R.a. Bill for Township II
Page 315: Triangle Construction 4th R.a. Bill for Township II
Page 316: Triangle Construction 4th R.a. Bill for Township II
Page 317: Triangle Construction 4th R.a. Bill for Township II
Page 318: Triangle Construction 4th R.a. Bill for Township II
Page 319: Triangle Construction 4th R.a. Bill for Township II
Page 320: Triangle Construction 4th R.a. Bill for Township II
Page 321: Triangle Construction 4th R.a. Bill for Township II
Page 322: Triangle Construction 4th R.a. Bill for Township II
Page 323: Triangle Construction 4th R.a. Bill for Township II
Page 324: Triangle Construction 4th R.a. Bill for Township II
Page 325: Triangle Construction 4th R.a. Bill for Township II
Page 326: Triangle Construction 4th R.a. Bill for Township II
Page 327: Triangle Construction 4th R.a. Bill for Township II
Page 328: Triangle Construction 4th R.a. Bill for Township II
Page 329: Triangle Construction 4th R.a. Bill for Township II
Page 330: Triangle Construction 4th R.a. Bill for Township II
Page 331: Triangle Construction 4th R.a. Bill for Township II
Page 332: Triangle Construction 4th R.a. Bill for Township II
Page 333: Triangle Construction 4th R.a. Bill for Township II
Page 334: Triangle Construction 4th R.a. Bill for Township II
Page 335: Triangle Construction 4th R.a. Bill for Township II
Page 336: Triangle Construction 4th R.a. Bill for Township II
Page 337: Triangle Construction 4th R.a. Bill for Township II
Page 338: Triangle Construction 4th R.a. Bill for Township II
Page 339: Triangle Construction 4th R.a. Bill for Township II
Page 340: Triangle Construction 4th R.a. Bill for Township II
Page 341: Triangle Construction 4th R.a. Bill for Township II
Page 342: Triangle Construction 4th R.a. Bill for Township II
Page 343: Triangle Construction 4th R.a. Bill for Township II
Page 344: Triangle Construction 4th R.a. Bill for Township II
Page 345: Triangle Construction 4th R.a. Bill for Township II
Page 346: Triangle Construction 4th R.a. Bill for Township II
Page 347: Triangle Construction 4th R.a. Bill for Township II
Page 348: Triangle Construction 4th R.a. Bill for Township II
Page 349: Triangle Construction 4th R.a. Bill for Township II
Page 350: Triangle Construction 4th R.a. Bill for Township II
Page 351: Triangle Construction 4th R.a. Bill for Township II
Page 352: Triangle Construction 4th R.a. Bill for Township II
Page 353: Triangle Construction 4th R.a. Bill for Township II
Page 354: Triangle Construction 4th R.a. Bill for Township II
Page 355: Triangle Construction 4th R.a. Bill for Township II
Page 356: Triangle Construction 4th R.a. Bill for Township II
Page 357: Triangle Construction 4th R.a. Bill for Township II
Page 358: Triangle Construction 4th R.a. Bill for Township II
Page 359: Triangle Construction 4th R.a. Bill for Township II
Page 360: Triangle Construction 4th R.a. Bill for Township II
Page 361: Triangle Construction 4th R.a. Bill for Township II
Page 362: Triangle Construction 4th R.a. Bill for Township II
Page 363: Triangle Construction 4th R.a. Bill for Township II
Page 364: Triangle Construction 4th R.a. Bill for Township II
Page 365: Triangle Construction 4th R.a. Bill for Township II
Page 366: Triangle Construction 4th R.a. Bill for Township II
Page 367: Triangle Construction 4th R.a. Bill for Township II
Page 368: Triangle Construction 4th R.a. Bill for Township II
Page 369: Triangle Construction 4th R.a. Bill for Township II
Page 370: Triangle Construction 4th R.a. Bill for Township II
Page 371: Triangle Construction 4th R.a. Bill for Township II
Page 372: Triangle Construction 4th R.a. Bill for Township II
Page 373: Triangle Construction 4th R.a. Bill for Township II
Page 374: Triangle Construction 4th R.a. Bill for Township II
Page 375: Triangle Construction 4th R.a. Bill for Township II
Page 376: Triangle Construction 4th R.a. Bill for Township II
Page 377: Triangle Construction 4th R.a. Bill for Township II
Page 378: Triangle Construction 4th R.a. Bill for Township II
Page 379: Triangle Construction 4th R.a. Bill for Township II
Page 380: Triangle Construction 4th R.a. Bill for Township II
Page 381: Triangle Construction 4th R.a. Bill for Township II
Page 382: Triangle Construction 4th R.a. Bill for Township II
Page 383: Triangle Construction 4th R.a. Bill for Township II
Page 384: Triangle Construction 4th R.a. Bill for Township II
Page 385: Triangle Construction 4th R.a. Bill for Township II
Page 386: Triangle Construction 4th R.a. Bill for Township II
Page 387: Triangle Construction 4th R.a. Bill for Township II
Page 388: Triangle Construction 4th R.a. Bill for Township II
Page 389: Triangle Construction 4th R.a. Bill for Township II
Page 390: Triangle Construction 4th R.a. Bill for Township II
Page 391: Triangle Construction 4th R.a. Bill for Township II
Page 392: Triangle Construction 4th R.a. Bill for Township II
Page 393: Triangle Construction 4th R.a. Bill for Township II
Page 394: Triangle Construction 4th R.a. Bill for Township II
Page 395: Triangle Construction 4th R.a. Bill for Township II
Page 396: Triangle Construction 4th R.a. Bill for Township II
Page 397: Triangle Construction 4th R.a. Bill for Township II
Page 398: Triangle Construction 4th R.a. Bill for Township II
Page 399: Triangle Construction 4th R.a. Bill for Township II
Page 400: Triangle Construction 4th R.a. Bill for Township II
Page 401: Triangle Construction 4th R.a. Bill for Township II
Page 402: Triangle Construction 4th R.a. Bill for Township II
Page 403: Triangle Construction 4th R.a. Bill for Township II
Page 404: Triangle Construction 4th R.a. Bill for Township II
Page 405: Triangle Construction 4th R.a. Bill for Township II
Page 406: Triangle Construction 4th R.a. Bill for Township II
Page 407: Triangle Construction 4th R.a. Bill for Township II
Page 408: Triangle Construction 4th R.a. Bill for Township II
Page 409: Triangle Construction 4th R.a. Bill for Township II
Page 410: Triangle Construction 4th R.a. Bill for Township II
Page 411: Triangle Construction 4th R.a. Bill for Township II
Page 412: Triangle Construction 4th R.a. Bill for Township II
Page 413: Triangle Construction 4th R.a. Bill for Township II
Page 414: Triangle Construction 4th R.a. Bill for Township II
Page 415: Triangle Construction 4th R.a. Bill for Township II
Page 416: Triangle Construction 4th R.a. Bill for Township II
Page 417: Triangle Construction 4th R.a. Bill for Township II
Page 418: Triangle Construction 4th R.a. Bill for Township II
Page 419: Triangle Construction 4th R.a. Bill for Township II
Page 420: Triangle Construction 4th R.a. Bill for Township II
Page 421: Triangle Construction 4th R.a. Bill for Township II
Page 422: Triangle Construction 4th R.a. Bill for Township II
Page 423: Triangle Construction 4th R.a. Bill for Township II
Page 424: Triangle Construction 4th R.a. Bill for Township II
Page 425: Triangle Construction 4th R.a. Bill for Township II
Page 426: Triangle Construction 4th R.a. Bill for Township II
Page 427: Triangle Construction 4th R.a. Bill for Township II
Page 428: Triangle Construction 4th R.a. Bill for Township II
Page 429: Triangle Construction 4th R.a. Bill for Township II
Page 430: Triangle Construction 4th R.a. Bill for Township II
Page 431: Triangle Construction 4th R.a. Bill for Township II
Page 432: Triangle Construction 4th R.a. Bill for Township II
Page 433: Triangle Construction 4th R.a. Bill for Township II
Page 434: Triangle Construction 4th R.a. Bill for Township II
Page 435: Triangle Construction 4th R.a. Bill for Township II
Page 436: Triangle Construction 4th R.a. Bill for Township II
Page 437: Triangle Construction 4th R.a. Bill for Township II
Page 438: Triangle Construction 4th R.a. Bill for Township II
Page 439: Triangle Construction 4th R.a. Bill for Township II
Page 440: Triangle Construction 4th R.a. Bill for Township II
Page 441: Triangle Construction 4th R.a. Bill for Township II
Page 442: Triangle Construction 4th R.a. Bill for Township II
Page 443: Triangle Construction 4th R.a. Bill for Township II
Page 444: Triangle Construction 4th R.a. Bill for Township II
Page 445: Triangle Construction 4th R.a. Bill for Township II
Page 446: Triangle Construction 4th R.a. Bill for Township II
Page 447: Triangle Construction 4th R.a. Bill for Township II
Page 448: Triangle Construction 4th R.a. Bill for Township II
Page 449: Triangle Construction 4th R.a. Bill for Township II
Page 450: Triangle Construction 4th R.a. Bill for Township II
Page 451: Triangle Construction 4th R.a. Bill for Township II
Page 452: Triangle Construction 4th R.a. Bill for Township II
Page 453: Triangle Construction 4th R.a. Bill for Township II
Page 454: Triangle Construction 4th R.a. Bill for Township II
Page 455: Triangle Construction 4th R.a. Bill for Township II
Page 456: Triangle Construction 4th R.a. Bill for Township II
Page 457: Triangle Construction 4th R.a. Bill for Township II
Page 458: Triangle Construction 4th R.a. Bill for Township II
Page 459: Triangle Construction 4th R.a. Bill for Township II
Page 460: Triangle Construction 4th R.a. Bill for Township II
Page 461: Triangle Construction 4th R.a. Bill for Township II
Page 462: Triangle Construction 4th R.a. Bill for Township II
Page 463: Triangle Construction 4th R.a. Bill for Township II
Page 464: Triangle Construction 4th R.a. Bill for Township II
Page 465: Triangle Construction 4th R.a. Bill for Township II
Page 466: Triangle Construction 4th R.a. Bill for Township II
Page 467: Triangle Construction 4th R.a. Bill for Township II
Page 468: Triangle Construction 4th R.a. Bill for Township II
Page 469: Triangle Construction 4th R.a. Bill for Township II
Page 470: Triangle Construction 4th R.a. Bill for Township II
Page 471: Triangle Construction 4th R.a. Bill for Township II
Page 472: Triangle Construction 4th R.a. Bill for Township II
Page 473: Triangle Construction 4th R.a. Bill for Township II
Page 474: Triangle Construction 4th R.a. Bill for Township II
Page 475: Triangle Construction 4th R.a. Bill for Township II
Page 476: Triangle Construction 4th R.a. Bill for Township II
Page 477: Triangle Construction 4th R.a. Bill for Township II
Page 478: Triangle Construction 4th R.a. Bill for Township II
Page 479: Triangle Construction 4th R.a. Bill for Township II
Page 480: Triangle Construction 4th R.a. Bill for Township II
Page 481: Triangle Construction 4th R.a. Bill for Township II
Page 482: Triangle Construction 4th R.a. Bill for Township II
Page 483: Triangle Construction 4th R.a. Bill for Township II
Page 484: Triangle Construction 4th R.a. Bill for Township II
Page 485: Triangle Construction 4th R.a. Bill for Township II
Page 486: Triangle Construction 4th R.a. Bill for Township II
Page 487: Triangle Construction 4th R.a. Bill for Township II
Page 488: Triangle Construction 4th R.a. Bill for Township II
Page 489: Triangle Construction 4th R.a. Bill for Township II
Page 490: Triangle Construction 4th R.a. Bill for Township II
Page 491: Triangle Construction 4th R.a. Bill for Township II
Page 492: Triangle Construction 4th R.a. Bill for Township II
Page 493: Triangle Construction 4th R.a. Bill for Township II
Page 494: Triangle Construction 4th R.a. Bill for Township II
Page 495: Triangle Construction 4th R.a. Bill for Township II
Page 496: Triangle Construction 4th R.a. Bill for Township II
Page 497: Triangle Construction 4th R.a. Bill for Township II
Page 498: Triangle Construction 4th R.a. Bill for Township II
Page 499: Triangle Construction 4th R.a. Bill for Township II
Page 500: Triangle Construction 4th R.a. Bill for Township II
Page 501: Triangle Construction 4th R.a. Bill for Township II
Page 502: Triangle Construction 4th R.a. Bill for Township II
Page 503: Triangle Construction 4th R.a. Bill for Township II
Page 504: Triangle Construction 4th R.a. Bill for Township II
Page 505: Triangle Construction 4th R.a. Bill for Township II
Page 506: Triangle Construction 4th R.a. Bill for Township II
Page 507: Triangle Construction 4th R.a. Bill for Township II
Page 508: Triangle Construction 4th R.a. Bill for Township II
Page 509: Triangle Construction 4th R.a. Bill for Township II
Page 510: Triangle Construction 4th R.a. Bill for Township II
Page 511: Triangle Construction 4th R.a. Bill for Township II
Page 512: Triangle Construction 4th R.a. Bill for Township II
Page 513: Triangle Construction 4th R.a. Bill for Township II
Page 514: Triangle Construction 4th R.a. Bill for Township II
Page 515: Triangle Construction 4th R.a. Bill for Township II
Page 516: Triangle Construction 4th R.a. Bill for Township II
Page 517: Triangle Construction 4th R.a. Bill for Township II
Page 518: Triangle Construction 4th R.a. Bill for Township II
Page 519: Triangle Construction 4th R.a. Bill for Township II
Page 520: Triangle Construction 4th R.a. Bill for Township II
Page 521: Triangle Construction 4th R.a. Bill for Township II
Page 522: Triangle Construction 4th R.a. Bill for Township II
Page 523: Triangle Construction 4th R.a. Bill for Township II
Page 524: Triangle Construction 4th R.a. Bill for Township II
Page 525: Triangle Construction 4th R.a. Bill for Township II
Page 526: Triangle Construction 4th R.a. Bill for Township II
Page 527: Triangle Construction 4th R.a. Bill for Township II
Page 528: Triangle Construction 4th R.a. Bill for Township II
Page 529: Triangle Construction 4th R.a. Bill for Township II
Page 530: Triangle Construction 4th R.a. Bill for Township II
Page 531: Triangle Construction 4th R.a. Bill for Township II
Page 532: Triangle Construction 4th R.a. Bill for Township II
Page 533: Triangle Construction 4th R.a. Bill for Township II
Page 534: Triangle Construction 4th R.a. Bill for Township II
Page 535: Triangle Construction 4th R.a. Bill for Township II
Page 536: Triangle Construction 4th R.a. Bill for Township II
Page 537: Triangle Construction 4th R.a. Bill for Township II
Page 538: Triangle Construction 4th R.a. Bill for Township II
Page 539: Triangle Construction 4th R.a. Bill for Township II
Page 540: Triangle Construction 4th R.a. Bill for Township II
Page 541: Triangle Construction 4th R.a. Bill for Township II
Page 542: Triangle Construction 4th R.a. Bill for Township II
Page 543: Triangle Construction 4th R.a. Bill for Township II
Page 544: Triangle Construction 4th R.a. Bill for Township II
Page 545: Triangle Construction 4th R.a. Bill for Township II
Page 546: Triangle Construction 4th R.a. Bill for Township II
Page 547: Triangle Construction 4th R.a. Bill for Township II
Page 548: Triangle Construction 4th R.a. Bill for Township II
Page 549: Triangle Construction 4th R.a. Bill for Township II
Page 550: Triangle Construction 4th R.a. Bill for Township II
Page 551: Triangle Construction 4th R.a. Bill for Township II
Page 552: Triangle Construction 4th R.a. Bill for Township II
Page 553: Triangle Construction 4th R.a. Bill for Township II
Page 554: Triangle Construction 4th R.a. Bill for Township II
Page 555: Triangle Construction 4th R.a. Bill for Township II
Page 556: Triangle Construction 4th R.a. Bill for Township II
Page 557: Triangle Construction 4th R.a. Bill for Township II
Page 558: Triangle Construction 4th R.a. Bill for Township II
Page 559: Triangle Construction 4th R.a. Bill for Township II
Page 560: Triangle Construction 4th R.a. Bill for Township II
Page 561: Triangle Construction 4th R.a. Bill for Township II
Page 562: Triangle Construction 4th R.a. Bill for Township II
Page 563: Triangle Construction 4th R.a. Bill for Township II
Page 564: Triangle Construction 4th R.a. Bill for Township II
Page 565: Triangle Construction 4th R.a. Bill for Township II
Page 566: Triangle Construction 4th R.a. Bill for Township II
Page 567: Triangle Construction 4th R.a. Bill for Township II
Page 568: Triangle Construction 4th R.a. Bill for Township II
Page 569: Triangle Construction 4th R.a. Bill for Township II
Page 570: Triangle Construction 4th R.a. Bill for Township II
Page 571: Triangle Construction 4th R.a. Bill for Township II
Page 572: Triangle Construction 4th R.a. Bill for Township II
Page 573: Triangle Construction 4th R.a. Bill for Township II
Page 574: Triangle Construction 4th R.a. Bill for Township II
Page 575: Triangle Construction 4th R.a. Bill for Township II
Page 576: Triangle Construction 4th R.a. Bill for Township II
Page 577: Triangle Construction 4th R.a. Bill for Township II
Page 578: Triangle Construction 4th R.a. Bill for Township II
Page 579: Triangle Construction 4th R.a. Bill for Township II
Page 580: Triangle Construction 4th R.a. Bill for Township II
Page 581: Triangle Construction 4th R.a. Bill for Township II
Page 582: Triangle Construction 4th R.a. Bill for Township II
Page 583: Triangle Construction 4th R.a. Bill for Township II
Page 584: Triangle Construction 4th R.a. Bill for Township II
Page 585: Triangle Construction 4th R.a. Bill for Township II
Page 586: Triangle Construction 4th R.a. Bill for Township II
Page 587: Triangle Construction 4th R.a. Bill for Township II
Page 588: Triangle Construction 4th R.a. Bill for Township II
Page 589: Triangle Construction 4th R.a. Bill for Township II
Page 590: Triangle Construction 4th R.a. Bill for Township II
Page 591: Triangle Construction 4th R.a. Bill for Township II
Page 592: Triangle Construction 4th R.a. Bill for Township II
Page 593: Triangle Construction 4th R.a. Bill for Township II
Page 594: Triangle Construction 4th R.a. Bill for Township II
Page 595: Triangle Construction 4th R.a. Bill for Township II
Page 596: Triangle Construction 4th R.a. Bill for Township II
Page 597: Triangle Construction 4th R.a. Bill for Township II
Page 598: Triangle Construction 4th R.a. Bill for Township II
Page 599: Triangle Construction 4th R.a. Bill for Township II
Page 600: Triangle Construction 4th R.a. Bill for Township II
Page 601: Triangle Construction 4th R.a. Bill for Township II
Page 602: Triangle Construction 4th R.a. Bill for Township II
Page 603: Triangle Construction 4th R.a. Bill for Township II
Page 604: Triangle Construction 4th R.a. Bill for Township II
Page 605: Triangle Construction 4th R.a. Bill for Township II
Page 606: Triangle Construction 4th R.a. Bill for Township II
Page 607: Triangle Construction 4th R.a. Bill for Township II
Page 608: Triangle Construction 4th R.a. Bill for Township II
Page 609: Triangle Construction 4th R.a. Bill for Township II
Page 610: Triangle Construction 4th R.a. Bill for Township II
Page 611: Triangle Construction 4th R.a. Bill for Township II
Page 612: Triangle Construction 4th R.a. Bill for Township II
Page 613: Triangle Construction 4th R.a. Bill for Township II
Page 614: Triangle Construction 4th R.a. Bill for Township II
Page 615: Triangle Construction 4th R.a. Bill for Township II
Page 616: Triangle Construction 4th R.a. Bill for Township II
Page 617: Triangle Construction 4th R.a. Bill for Township II
Page 618: Triangle Construction 4th R.a. Bill for Township II
Page 619: Triangle Construction 4th R.a. Bill for Township II
Page 620: Triangle Construction 4th R.a. Bill for Township II
Page 621: Triangle Construction 4th R.a. Bill for Township II
Page 622: Triangle Construction 4th R.a. Bill for Township II
Page 623: Triangle Construction 4th R.a. Bill for Township II
Page 624: Triangle Construction 4th R.a. Bill for Township II
Page 625: Triangle Construction 4th R.a. Bill for Township II
Page 626: Triangle Construction 4th R.a. Bill for Township II
Page 627: Triangle Construction 4th R.a. Bill for Township II
Page 628: Triangle Construction 4th R.a. Bill for Township II
Page 629: Triangle Construction 4th R.a. Bill for Township II
Page 630: Triangle Construction 4th R.a. Bill for Township II
Page 631: Triangle Construction 4th R.a. Bill for Township II
Page 632: Triangle Construction 4th R.a. Bill for Township II
Page 633: Triangle Construction 4th R.a. Bill for Township II
Page 634: Triangle Construction 4th R.a. Bill for Township II
Page 635: Triangle Construction 4th R.a. Bill for Township II
Page 636: Triangle Construction 4th R.a. Bill for Township II
Page 637: Triangle Construction 4th R.a. Bill for Township II
Page 638: Triangle Construction 4th R.a. Bill for Township II
Page 639: Triangle Construction 4th R.a. Bill for Township II
Page 640: Triangle Construction 4th R.a. Bill for Township II
Page 641: Triangle Construction 4th R.a. Bill for Township II
Page 642: Triangle Construction 4th R.a. Bill for Township II
Page 643: Triangle Construction 4th R.a. Bill for Township II
Page 644: Triangle Construction 4th R.a. Bill for Township II
Page 645: Triangle Construction 4th R.a. Bill for Township II
Page 646: Triangle Construction 4th R.a. Bill for Township II
Page 647: Triangle Construction 4th R.a. Bill for Township II
Page 648: Triangle Construction 4th R.a. Bill for Township II
Page 649: Triangle Construction 4th R.a. Bill for Township II
Page 650: Triangle Construction 4th R.a. Bill for Township II
Page 651: Triangle Construction 4th R.a. Bill for Township II
Page 652: Triangle Construction 4th R.a. Bill for Township II
Page 653: Triangle Construction 4th R.a. Bill for Township II
Page 654: Triangle Construction 4th R.a. Bill for Township II
Page 655: Triangle Construction 4th R.a. Bill for Township II
Page 656: Triangle Construction 4th R.a. Bill for Township II
Page 657: Triangle Construction 4th R.a. Bill for Township II
Page 658: Triangle Construction 4th R.a. Bill for Township II
Page 659: Triangle Construction 4th R.a. Bill for Township II
Page 660: Triangle Construction 4th R.a. Bill for Township II
Page 661: Triangle Construction 4th R.a. Bill for Township II
Page 662: Triangle Construction 4th R.a. Bill for Township II
Page 663: Triangle Construction 4th R.a. Bill for Township II
Page 664: Triangle Construction 4th R.a. Bill for Township II
Page 665: Triangle Construction 4th R.a. Bill for Township II
Page 666: Triangle Construction 4th R.a. Bill for Township II
Page 667: Triangle Construction 4th R.a. Bill for Township II
Page 668: Triangle Construction 4th R.a. Bill for Township II
Page 669: Triangle Construction 4th R.a. Bill for Township II
Page 670: Triangle Construction 4th R.a. Bill for Township II
Page 671: Triangle Construction 4th R.a. Bill for Township II
Page 672: Triangle Construction 4th R.a. Bill for Township II
Page 673: Triangle Construction 4th R.a. Bill for Township II
Page 674: Triangle Construction 4th R.a. Bill for Township II
Page 675: Triangle Construction 4th R.a. Bill for Township II
Page 676: Triangle Construction 4th R.a. Bill for Township II
Page 677: Triangle Construction 4th R.a. Bill for Township II
Page 678: Triangle Construction 4th R.a. Bill for Township II
Page 679: Triangle Construction 4th R.a. Bill for Township II
Page 680: Triangle Construction 4th R.a. Bill for Township II
Page 681: Triangle Construction 4th R.a. Bill for Township II
Page 682: Triangle Construction 4th R.a. Bill for Township II
Page 683: Triangle Construction 4th R.a. Bill for Township II
Page 684: Triangle Construction 4th R.a. Bill for Township II
Page 685: Triangle Construction 4th R.a. Bill for Township II
Page 686: Triangle Construction 4th R.a. Bill for Township II
Page 687: Triangle Construction 4th R.a. Bill for Township II
Page 688: Triangle Construction 4th R.a. Bill for Township II
Page 689: Triangle Construction 4th R.a. Bill for Township II
Page 690: Triangle Construction 4th R.a. Bill for Township II
Page 691: Triangle Construction 4th R.a. Bill for Township II
Page 692: Triangle Construction 4th R.a. Bill for Township II
Page 693: Triangle Construction 4th R.a. Bill for Township II
Page 694: Triangle Construction 4th R.a. Bill for Township II
Page 695: Triangle Construction 4th R.a. Bill for Township II
Page 696: Triangle Construction 4th R.a. Bill for Township II
Page 697: Triangle Construction 4th R.a. Bill for Township II
Page 698: Triangle Construction 4th R.a. Bill for Township II
Page 699: Triangle Construction 4th R.a. Bill for Township II
Page 700: Triangle Construction 4th R.a. Bill for Township II
Page 701: Triangle Construction 4th R.a. Bill for Township II
Page 702: Triangle Construction 4th R.a. Bill for Township II
Page 703: Triangle Construction 4th R.a. Bill for Township II
Page 704: Triangle Construction 4th R.a. Bill for Township II
Page 705: Triangle Construction 4th R.a. Bill for Township II
Page 706: Triangle Construction 4th R.a. Bill for Township II
Page 707: Triangle Construction 4th R.a. Bill for Township II
Page 708: Triangle Construction 4th R.a. Bill for Township II
Page 709: Triangle Construction 4th R.a. Bill for Township II
Page 710: Triangle Construction 4th R.a. Bill for Township II
Page 711: Triangle Construction 4th R.a. Bill for Township II
Page 712: Triangle Construction 4th R.a. Bill for Township II
Page 713: Triangle Construction 4th R.a. Bill for Township II
Page 714: Triangle Construction 4th R.a. Bill for Township II
Page 715: Triangle Construction 4th R.a. Bill for Township II
Page 716: Triangle Construction 4th R.a. Bill for Township II
Page 717: Triangle Construction 4th R.a. Bill for Township II
Page 718: Triangle Construction 4th R.a. Bill for Township II
Page 719: Triangle Construction 4th R.a. Bill for Township II
Page 720: Triangle Construction 4th R.a. Bill for Township II
Page 721: Triangle Construction 4th R.a. Bill for Township II
Page 722: Triangle Construction 4th R.a. Bill for Township II
Page 723: Triangle Construction 4th R.a. Bill for Township II
Page 724: Triangle Construction 4th R.a. Bill for Township II
Page 725: Triangle Construction 4th R.a. Bill for Township II
Page 726: Triangle Construction 4th R.a. Bill for Township II
Page 727: Triangle Construction 4th R.a. Bill for Township II
Page 728: Triangle Construction 4th R.a. Bill for Township II
Page 729: Triangle Construction 4th R.a. Bill for Township II
Page 730: Triangle Construction 4th R.a. Bill for Township II
Page 731: Triangle Construction 4th R.a. Bill for Township II
Page 732: Triangle Construction 4th R.a. Bill for Township II
Page 733: Triangle Construction 4th R.a. Bill for Township II
Page 734: Triangle Construction 4th R.a. Bill for Township II
Page 735: Triangle Construction 4th R.a. Bill for Township II
Page 736: Triangle Construction 4th R.a. Bill for Township II
Page 737: Triangle Construction 4th R.a. Bill for Township II
Page 738: Triangle Construction 4th R.a. Bill for Township II
Page 739: Triangle Construction 4th R.a. Bill for Township II
Page 740: Triangle Construction 4th R.a. Bill for Township II
Page 741: Triangle Construction 4th R.a. Bill for Township II
Page 742: Triangle Construction 4th R.a. Bill for Township II
Page 743: Triangle Construction 4th R.a. Bill for Township II
Page 744: Triangle Construction 4th R.a. Bill for Township II
Page 745: Triangle Construction 4th R.a. Bill for Township II
Page 746: Triangle Construction 4th R.a. Bill for Township II
Page 747: Triangle Construction 4th R.a. Bill for Township II
Page 748: Triangle Construction 4th R.a. Bill for Township II
Page 749: Triangle Construction 4th R.a. Bill for Township II
Page 750: Triangle Construction 4th R.a. Bill for Township II
Page 751: Triangle Construction 4th R.a. Bill for Township II
Page 752: Triangle Construction 4th R.a. Bill for Township II
Page 753: Triangle Construction 4th R.a. Bill for Township II
Page 754: Triangle Construction 4th R.a. Bill for Township II
Page 755: Triangle Construction 4th R.a. Bill for Township II
Page 756: Triangle Construction 4th R.a. Bill for Township II
Page 757: Triangle Construction 4th R.a. Bill for Township II
Page 758: Triangle Construction 4th R.a. Bill for Township II
Page 759: Triangle Construction 4th R.a. Bill for Township II
Page 760: Triangle Construction 4th R.a. Bill for Township II
Page 761: Triangle Construction 4th R.a. Bill for Township II
Page 762: Triangle Construction 4th R.a. Bill for Township II
Page 763: Triangle Construction 4th R.a. Bill for Township II
Page 764: Triangle Construction 4th R.a. Bill for Township II
Page 765: Triangle Construction 4th R.a. Bill for Township II
Page 766: Triangle Construction 4th R.a. Bill for Township II
Page 767: Triangle Construction 4th R.a. Bill for Township II
Page 768: Triangle Construction 4th R.a. Bill for Township II
Page 769: Triangle Construction 4th R.a. Bill for Township II
Page 770: Triangle Construction 4th R.a. Bill for Township II
Page 771: Triangle Construction 4th R.a. Bill for Township II
Page 772: Triangle Construction 4th R.a. Bill for Township II
Page 773: Triangle Construction 4th R.a. Bill for Township II
Page 774: Triangle Construction 4th R.a. Bill for Township II
Page 775: Triangle Construction 4th R.a. Bill for Township II
Page 776: Triangle Construction 4th R.a. Bill for Township II
Page 777: Triangle Construction 4th R.a. Bill for Township II
Page 778: Triangle Construction 4th R.a. Bill for Township II
Page 779: Triangle Construction 4th R.a. Bill for Township II
Page 780: Triangle Construction 4th R.a. Bill for Township II
Page 781: Triangle Construction 4th R.a. Bill for Township II
Page 782: Triangle Construction 4th R.a. Bill for Township II
Page 783: Triangle Construction 4th R.a. Bill for Township II
Page 784: Triangle Construction 4th R.a. Bill for Township II
Page 785: Triangle Construction 4th R.a. Bill for Township II
Page 786: Triangle Construction 4th R.a. Bill for Township II
Page 787: Triangle Construction 4th R.a. Bill for Township II
Page 788: Triangle Construction 4th R.a. Bill for Township II
Page 789: Triangle Construction 4th R.a. Bill for Township II
Page 790: Triangle Construction 4th R.a. Bill for Township II
Page 791: Triangle Construction 4th R.a. Bill for Township II
Page 792: Triangle Construction 4th R.a. Bill for Township II
Page 793: Triangle Construction 4th R.a. Bill for Township II
Page 794: Triangle Construction 4th R.a. Bill for Township II
Page 795: Triangle Construction 4th R.a. Bill for Township II
Page 796: Triangle Construction 4th R.a. Bill for Township II
Page 797: Triangle Construction 4th R.a. Bill for Township II
Page 798: Triangle Construction 4th R.a. Bill for Township II
Page 799: Triangle Construction 4th R.a. Bill for Township II
Page 800: Triangle Construction 4th R.a. Bill for Township II
Page 801: Triangle Construction 4th R.a. Bill for Township II
Page 802: Triangle Construction 4th R.a. Bill for Township II
Page 803: Triangle Construction 4th R.a. Bill for Township II
Page 804: Triangle Construction 4th R.a. Bill for Township II
Page 805: Triangle Construction 4th R.a. Bill for Township II
Page 806: Triangle Construction 4th R.a. Bill for Township II
Page 807: Triangle Construction 4th R.a. Bill for Township II
Page 808: Triangle Construction 4th R.a. Bill for Township II
Page 809: Triangle Construction 4th R.a. Bill for Township II
Page 810: Triangle Construction 4th R.a. Bill for Township II
Page 811: Triangle Construction 4th R.a. Bill for Township II
Page 812: Triangle Construction 4th R.a. Bill for Township II
Page 813: Triangle Construction 4th R.a. Bill for Township II
Page 814: Triangle Construction 4th R.a. Bill for Township II
Page 815: Triangle Construction 4th R.a. Bill for Township II
Page 816: Triangle Construction 4th R.a. Bill for Township II
Page 817: Triangle Construction 4th R.a. Bill for Township II
Page 818: Triangle Construction 4th R.a. Bill for Township II
Page 819: Triangle Construction 4th R.a. Bill for Township II
Page 820: Triangle Construction 4th R.a. Bill for Township II
Page 821: Triangle Construction 4th R.a. Bill for Township II
Page 822: Triangle Construction 4th R.a. Bill for Township II
Page 823: Triangle Construction 4th R.a. Bill for Township II
Page 824: Triangle Construction 4th R.a. Bill for Township II
Page 825: Triangle Construction 4th R.a. Bill for Township II
Page 826: Triangle Construction 4th R.a. Bill for Township II
Page 827: Triangle Construction 4th R.a. Bill for Township II
Page 828: Triangle Construction 4th R.a. Bill for Township II
Page 829: Triangle Construction 4th R.a. Bill for Township II
Page 830: Triangle Construction 4th R.a. Bill for Township II
Page 831: Triangle Construction 4th R.a. Bill for Township II
Page 832: Triangle Construction 4th R.a. Bill for Township II
Page 833: Triangle Construction 4th R.a. Bill for Township II
Page 834: Triangle Construction 4th R.a. Bill for Township II
Page 835: Triangle Construction 4th R.a. Bill for Township II
Page 836: Triangle Construction 4th R.a. Bill for Township II
Page 837: Triangle Construction 4th R.a. Bill for Township II
Page 838: Triangle Construction 4th R.a. Bill for Township II
Page 839: Triangle Construction 4th R.a. Bill for Township II
Page 840: Triangle Construction 4th R.a. Bill for Township II
Page 841: Triangle Construction 4th R.a. Bill for Township II
Page 842: Triangle Construction 4th R.a. Bill for Township II
Page 843: Triangle Construction 4th R.a. Bill for Township II
Page 844: Triangle Construction 4th R.a. Bill for Township II
Page 845: Triangle Construction 4th R.a. Bill for Township II
Page 846: Triangle Construction 4th R.a. Bill for Township II
Page 847: Triangle Construction 4th R.a. Bill for Township II
Page 848: Triangle Construction 4th R.a. Bill for Township II
Page 849: Triangle Construction 4th R.a. Bill for Township II
Page 850: Triangle Construction 4th R.a. Bill for Township II
Page 851: Triangle Construction 4th R.a. Bill for Township II
Page 852: Triangle Construction 4th R.a. Bill for Township II
Page 853: Triangle Construction 4th R.a. Bill for Township II
Page 854: Triangle Construction 4th R.a. Bill for Township II
Page 855: Triangle Construction 4th R.a. Bill for Township II
Page 856: Triangle Construction 4th R.a. Bill for Township II
Page 857: Triangle Construction 4th R.a. Bill for Township II
Page 858: Triangle Construction 4th R.a. Bill for Township II
Page 859: Triangle Construction 4th R.a. Bill for Township II
Page 860: Triangle Construction 4th R.a. Bill for Township II
Page 861: Triangle Construction 4th R.a. Bill for Township II
Page 862: Triangle Construction 4th R.a. Bill for Township II
Page 863: Triangle Construction 4th R.a. Bill for Township II
Page 864: Triangle Construction 4th R.a. Bill for Township II
Page 865: Triangle Construction 4th R.a. Bill for Township II
Page 866: Triangle Construction 4th R.a. Bill for Township II
Page 867: Triangle Construction 4th R.a. Bill for Township II
Page 868: Triangle Construction 4th R.a. Bill for Township II
Page 869: Triangle Construction 4th R.a. Bill for Township II
Page 870: Triangle Construction 4th R.a. Bill for Township II
Page 871: Triangle Construction 4th R.a. Bill for Township II
Page 872: Triangle Construction 4th R.a. Bill for Township II
Page 873: Triangle Construction 4th R.a. Bill for Township II
Page 874: Triangle Construction 4th R.a. Bill for Township II
Page 875: Triangle Construction 4th R.a. Bill for Township II
Page 876: Triangle Construction 4th R.a. Bill for Township II
Page 877: Triangle Construction 4th R.a. Bill for Township II
Page 878: Triangle Construction 4th R.a. Bill for Township II
Page 879: Triangle Construction 4th R.a. Bill for Township II
Page 880: Triangle Construction 4th R.a. Bill for Township II
Page 881: Triangle Construction 4th R.a. Bill for Township II
Page 882: Triangle Construction 4th R.a. Bill for Township II
Page 883: Triangle Construction 4th R.a. Bill for Township II
Page 884: Triangle Construction 4th R.a. Bill for Township II
Page 885: Triangle Construction 4th R.a. Bill for Township II
Page 886: Triangle Construction 4th R.a. Bill for Township II
Page 887: Triangle Construction 4th R.a. Bill for Township II
Page 888: Triangle Construction 4th R.a. Bill for Township II
Page 889: Triangle Construction 4th R.a. Bill for Township II
Page 890: Triangle Construction 4th R.a. Bill for Township II
Page 891: Triangle Construction 4th R.a. Bill for Township II
Page 892: Triangle Construction 4th R.a. Bill for Township II
Page 893: Triangle Construction 4th R.a. Bill for Township II
Page 894: Triangle Construction 4th R.a. Bill for Township II
Page 895: Triangle Construction 4th R.a. Bill for Township II
Page 896: Triangle Construction 4th R.a. Bill for Township II
Page 897: Triangle Construction 4th R.a. Bill for Township II
Page 898: Triangle Construction 4th R.a. Bill for Township II
Page 899: Triangle Construction 4th R.a. Bill for Township II
Page 900: Triangle Construction 4th R.a. Bill for Township II
Page 901: Triangle Construction 4th R.a. Bill for Township II
Page 902: Triangle Construction 4th R.a. Bill for Township II
Page 903: Triangle Construction 4th R.a. Bill for Township II
Page 904: Triangle Construction 4th R.a. Bill for Township II
Page 905: Triangle Construction 4th R.a. Bill for Township II
Page 906: Triangle Construction 4th R.a. Bill for Township II
Page 907: Triangle Construction 4th R.a. Bill for Township II
Page 908: Triangle Construction 4th R.a. Bill for Township II
Page 909: Triangle Construction 4th R.a. Bill for Township II
Page 910: Triangle Construction 4th R.a. Bill for Township II
Page 911: Triangle Construction 4th R.a. Bill for Township II
Page 912: Triangle Construction 4th R.a. Bill for Township II
Page 913: Triangle Construction 4th R.a. Bill for Township II
Page 914: Triangle Construction 4th R.a. Bill for Township II
Page 915: Triangle Construction 4th R.a. Bill for Township II
Page 916: Triangle Construction 4th R.a. Bill for Township II
Page 917: Triangle Construction 4th R.a. Bill for Township II
Page 918: Triangle Construction 4th R.a. Bill for Township II
Page 919: Triangle Construction 4th R.a. Bill for Township II
Page 920: Triangle Construction 4th R.a. Bill for Township II
Page 921: Triangle Construction 4th R.a. Bill for Township II
Page 922: Triangle Construction 4th R.a. Bill for Township II
Page 923: Triangle Construction 4th R.a. Bill for Township II
Page 924: Triangle Construction 4th R.a. Bill for Township II
Page 925: Triangle Construction 4th R.a. Bill for Township II
Page 926: Triangle Construction 4th R.a. Bill for Township II
Page 927: Triangle Construction 4th R.a. Bill for Township II
Page 928: Triangle Construction 4th R.a. Bill for Township II
Page 929: Triangle Construction 4th R.a. Bill for Township II
Page 930: Triangle Construction 4th R.a. Bill for Township II
Page 931: Triangle Construction 4th R.a. Bill for Township II
Page 932: Triangle Construction 4th R.a. Bill for Township II
Page 933: Triangle Construction 4th R.a. Bill for Township II
Page 934: Triangle Construction 4th R.a. Bill for Township II
Page 935: Triangle Construction 4th R.a. Bill for Township II
Page 936: Triangle Construction 4th R.a. Bill for Township II
Page 937: Triangle Construction 4th R.a. Bill for Township II
Page 938: Triangle Construction 4th R.a. Bill for Township II
Page 939: Triangle Construction 4th R.a. Bill for Township II
Page 940: Triangle Construction 4th R.a. Bill for Township II
Page 941: Triangle Construction 4th R.a. Bill for Township II
Page 942: Triangle Construction 4th R.a. Bill for Township II
Page 943: Triangle Construction 4th R.a. Bill for Township II
Page 944: Triangle Construction 4th R.a. Bill for Township II
Page 945: Triangle Construction 4th R.a. Bill for Township II
Page 946: Triangle Construction 4th R.a. Bill for Township II
Page 947: Triangle Construction 4th R.a. Bill for Township II
Page 948: Triangle Construction 4th R.a. Bill for Township II
Page 949: Triangle Construction 4th R.a. Bill for Township II
Page 950: Triangle Construction 4th R.a. Bill for Township II
Page 951: Triangle Construction 4th R.a. Bill for Township II
Page 952: Triangle Construction 4th R.a. Bill for Township II
Page 953: Triangle Construction 4th R.a. Bill for Township II
Page 954: Triangle Construction 4th R.a. Bill for Township II
Page 955: Triangle Construction 4th R.a. Bill for Township II
Page 956: Triangle Construction 4th R.a. Bill for Township II
Page 957: Triangle Construction 4th R.a. Bill for Township II
Page 958: Triangle Construction 4th R.a. Bill for Township II
Page 959: Triangle Construction 4th R.a. Bill for Township II
Page 960: Triangle Construction 4th R.a. Bill for Township II
Page 961: Triangle Construction 4th R.a. Bill for Township II
Page 962: Triangle Construction 4th R.a. Bill for Township II
Page 963: Triangle Construction 4th R.a. Bill for Township II
Page 964: Triangle Construction 4th R.a. Bill for Township II
Page 965: Triangle Construction 4th R.a. Bill for Township II
Page 966: Triangle Construction 4th R.a. Bill for Township II
Page 967: Triangle Construction 4th R.a. Bill for Township II
Page 968: Triangle Construction 4th R.a. Bill for Township II
Page 969: Triangle Construction 4th R.a. Bill for Township II
Page 970: Triangle Construction 4th R.a. Bill for Township II
Page 971: Triangle Construction 4th R.a. Bill for Township II
Page 972: Triangle Construction 4th R.a. Bill for Township II
Page 973: Triangle Construction 4th R.a. Bill for Township II
Page 974: Triangle Construction 4th R.a. Bill for Township II
Page 975: Triangle Construction 4th R.a. Bill for Township II
Page 976: Triangle Construction 4th R.a. Bill for Township II
Page 977: Triangle Construction 4th R.a. Bill for Township II
Page 978: Triangle Construction 4th R.a. Bill for Township II
Page 979: Triangle Construction 4th R.a. Bill for Township II
Page 980: Triangle Construction 4th R.a. Bill for Township II
Page 981: Triangle Construction 4th R.a. Bill for Township II
Page 982: Triangle Construction 4th R.a. Bill for Township II
Page 983: Triangle Construction 4th R.a. Bill for Township II
Page 984: Triangle Construction 4th R.a. Bill for Township II
Page 985: Triangle Construction 4th R.a. Bill for Township II
Page 986: Triangle Construction 4th R.a. Bill for Township II
Page 987: Triangle Construction 4th R.a. Bill for Township II
Page 988: Triangle Construction 4th R.a. Bill for Township II
Page 989: Triangle Construction 4th R.a. Bill for Township II
Page 990: Triangle Construction 4th R.a. Bill for Township II
Page 991: Triangle Construction 4th R.a. Bill for Township II
Page 992: Triangle Construction 4th R.a. Bill for Township II
Page 993: Triangle Construction 4th R.a. Bill for Township II
Page 994: Triangle Construction 4th R.a. Bill for Township II
Page 995: Triangle Construction 4th R.a. Bill for Township II
Page 996: Triangle Construction 4th R.a. Bill for Township II
Page 997: Triangle Construction 4th R.a. Bill for Township II
Page 998: Triangle Construction 4th R.a. Bill for Township II
Page 999: Triangle Construction 4th R.a. Bill for Township II
Page 1000: Triangle Construction 4th R.a. Bill for Township II
Page 1001: Triangle Construction 4th R.a. Bill for Township II
Page 1002: Triangle Construction 4th R.a. Bill for Township II
Page 1003: Triangle Construction 4th R.a. Bill for Township II
Page 1004: Triangle Construction 4th R.a. Bill for Township II
Page 1005: Triangle Construction 4th R.a. Bill for Township II
Page 1006: Triangle Construction 4th R.a. Bill for Township II
Page 1007: Triangle Construction 4th R.a. Bill for Township II
Page 1008: Triangle Construction 4th R.a. Bill for Township II
Page 1009: Triangle Construction 4th R.a. Bill for Township II
Page 1010: Triangle Construction 4th R.a. Bill for Township II
Page 1011: Triangle Construction 4th R.a. Bill for Township II
Page 1012: Triangle Construction 4th R.a. Bill for Township II
Page 1013: Triangle Construction 4th R.a. Bill for Township II
Page 1014: Triangle Construction 4th R.a. Bill for Township II
Page 1015: Triangle Construction 4th R.a. Bill for Township II
Page 1016: Triangle Construction 4th R.a. Bill for Township II
Page 1017: Triangle Construction 4th R.a. Bill for Township II
Page 1018: Triangle Construction 4th R.a. Bill for Township II
Page 1019: Triangle Construction 4th R.a. Bill for Township II
Page 1020: Triangle Construction 4th R.a. Bill for Township II
Page 1021: Triangle Construction 4th R.a. Bill for Township II
Page 1022: Triangle Construction 4th R.a. Bill for Township II
Page 1023: Triangle Construction 4th R.a. Bill for Township II
Page 1024: Triangle Construction 4th R.a. Bill for Township II
Page 1025: Triangle Construction 4th R.a. Bill for Township II
Page 1026: Triangle Construction 4th R.a. Bill for Township II
Page 1027: Triangle Construction 4th R.a. Bill for Township II
Page 1028: Triangle Construction 4th R.a. Bill for Township II
Page 1029: Triangle Construction 4th R.a. Bill for Township II
Page 1030: Triangle Construction 4th R.a. Bill for Township II
Page 1031: Triangle Construction 4th R.a. Bill for Township II
Page 1032: Triangle Construction 4th R.a. Bill for Township II
Page 1033: Triangle Construction 4th R.a. Bill for Township II
Page 1034: Triangle Construction 4th R.a. Bill for Township II
Page 1035: Triangle Construction 4th R.a. Bill for Township II
Page 1036: Triangle Construction 4th R.a. Bill for Township II
Page 1037: Triangle Construction 4th R.a. Bill for Township II
Page 1038: Triangle Construction 4th R.a. Bill for Township II
Page 1039: Triangle Construction 4th R.a. Bill for Township II
Page 1040: Triangle Construction 4th R.a. Bill for Township II
Page 1041: Triangle Construction 4th R.a. Bill for Township II
Page 1042: Triangle Construction 4th R.a. Bill for Township II
Page 1043: Triangle Construction 4th R.a. Bill for Township II
Page 1044: Triangle Construction 4th R.a. Bill for Township II
Page 1045: Triangle Construction 4th R.a. Bill for Township II
Page 1046: Triangle Construction 4th R.a. Bill for Township II
Page 1047: Triangle Construction 4th R.a. Bill for Township II
Page 1048: Triangle Construction 4th R.a. Bill for Township II
Page 1049: Triangle Construction 4th R.a. Bill for Township II
Page 1050: Triangle Construction 4th R.a. Bill for Township II
Page 1051: Triangle Construction 4th R.a. Bill for Township II
Page 1052: Triangle Construction 4th R.a. Bill for Township II
Page 1053: Triangle Construction 4th R.a. Bill for Township II
Page 1054: Triangle Construction 4th R.a. Bill for Township II
Page 1055: Triangle Construction 4th R.a. Bill for Township II
Page 1056: Triangle Construction 4th R.a. Bill for Township II
Page 1057: Triangle Construction 4th R.a. Bill for Township II
Page 1058: Triangle Construction 4th R.a. Bill for Township II
Page 1059: Triangle Construction 4th R.a. Bill for Township II
Page 1060: Triangle Construction 4th R.a. Bill for Township II
Page 1061: Triangle Construction 4th R.a. Bill for Township II
Page 1062: Triangle Construction 4th R.a. Bill for Township II
Page 1063: Triangle Construction 4th R.a. Bill for Township II
Page 1064: Triangle Construction 4th R.a. Bill for Township II
Page 1065: Triangle Construction 4th R.a. Bill for Township II
Page 1066: Triangle Construction 4th R.a. Bill for Township II
Page 1067: Triangle Construction 4th R.a. Bill for Township II
Page 1068: Triangle Construction 4th R.a. Bill for Township II
Page 1069: Triangle Construction 4th R.a. Bill for Township II
Page 1070: Triangle Construction 4th R.a. Bill for Township II
Page 1071: Triangle Construction 4th R.a. Bill for Township II
Page 1072: Triangle Construction 4th R.a. Bill for Township II
Page 1073: Triangle Construction 4th R.a. Bill for Township II
Page 1074: Triangle Construction 4th R.a. Bill for Township II
Page 1075: Triangle Construction 4th R.a. Bill for Township II
Page 1076: Triangle Construction 4th R.a. Bill for Township II
Page 1077: Triangle Construction 4th R.a. Bill for Township II
Page 1078: Triangle Construction 4th R.a. Bill for Township II
Page 1079: Triangle Construction 4th R.a. Bill for Township II
Page 1080: Triangle Construction 4th R.a. Bill for Township II
Page 1081: Triangle Construction 4th R.a. Bill for Township II
Page 1082: Triangle Construction 4th R.a. Bill for Township II
Page 1083: Triangle Construction 4th R.a. Bill for Township II
Page 1084: Triangle Construction 4th R.a. Bill for Township II
Page 1085: Triangle Construction 4th R.a. Bill for Township II
Page 1086: Triangle Construction 4th R.a. Bill for Township II
Page 1087: Triangle Construction 4th R.a. Bill for Township II
Page 1088: Triangle Construction 4th R.a. Bill for Township II
Page 1089: Triangle Construction 4th R.a. Bill for Township II
Page 1090: Triangle Construction 4th R.a. Bill for Township II
Page 1091: Triangle Construction 4th R.a. Bill for Township II
Page 1092: Triangle Construction 4th R.a. Bill for Township II
Page 1093: Triangle Construction 4th R.a. Bill for Township II
Page 1094: Triangle Construction 4th R.a. Bill for Township II
Page 1095: Triangle Construction 4th R.a. Bill for Township II
Page 1096: Triangle Construction 4th R.a. Bill for Township II
Page 1097: Triangle Construction 4th R.a. Bill for Township II
Page 1098: Triangle Construction 4th R.a. Bill for Township II
Page 1099: Triangle Construction 4th R.a. Bill for Township II
Page 1100: Triangle Construction 4th R.a. Bill for Township II
Page 1101: Triangle Construction 4th R.a. Bill for Township II
Page 1102: Triangle Construction 4th R.a. Bill for Township II
Page 1103: Triangle Construction 4th R.a. Bill for Township II
Page 1104: Triangle Construction 4th R.a. Bill for Township II
Page 1105: Triangle Construction 4th R.a. Bill for Township II
Page 1106: Triangle Construction 4th R.a. Bill for Township II
Page 1107: Triangle Construction 4th R.a. Bill for Township II
Page 1108: Triangle Construction 4th R.a. Bill for Township II
Page 1109: Triangle Construction 4th R.a. Bill for Township II
Page 1110: Triangle Construction 4th R.a. Bill for Township II
Page 1111: Triangle Construction 4th R.a. Bill for Township II
Page 1112: Triangle Construction 4th R.a. Bill for Township II
Page 1113: Triangle Construction 4th R.a. Bill for Township II
Page 1114: Triangle Construction 4th R.a. Bill for Township II
Page 1115: Triangle Construction 4th R.a. Bill for Township II
Page 1116: Triangle Construction 4th R.a. Bill for Township II
Page 1117: Triangle Construction 4th R.a. Bill for Township II
Page 1118: Triangle Construction 4th R.a. Bill for Township II
Page 1119: Triangle Construction 4th R.a. Bill for Township II
Page 1120: Triangle Construction 4th R.a. Bill for Township II
Page 1121: Triangle Construction 4th R.a. Bill for Township II
Page 1122: Triangle Construction 4th R.a. Bill for Township II
Page 1123: Triangle Construction 4th R.a. Bill for Township II
Page 1124: Triangle Construction 4th R.a. Bill for Township II
Page 1125: Triangle Construction 4th R.a. Bill for Township II
Page 1126: Triangle Construction 4th R.a. Bill for Township II
Page 1127: Triangle Construction 4th R.a. Bill for Township II
Page 1128: Triangle Construction 4th R.a. Bill for Township II
Page 1129: Triangle Construction 4th R.a. Bill for Township II
Page 1130: Triangle Construction 4th R.a. Bill for Township II
Page 1131: Triangle Construction 4th R.a. Bill for Township II
Page 1132: Triangle Construction 4th R.a. Bill for Township II
Page 1133: Triangle Construction 4th R.a. Bill for Township II
Page 1134: Triangle Construction 4th R.a. Bill for Township II
Page 1135: Triangle Construction 4th R.a. Bill for Township II
Page 1136: Triangle Construction 4th R.a. Bill for Township II
Page 1137: Triangle Construction 4th R.a. Bill for Township II
Page 1138: Triangle Construction 4th R.a. Bill for Township II
Page 1139: Triangle Construction 4th R.a. Bill for Township II
Page 1140: Triangle Construction 4th R.a. Bill for Township II
Page 1141: Triangle Construction 4th R.a. Bill for Township II
Page 1142: Triangle Construction 4th R.a. Bill for Township II
Page 1143: Triangle Construction 4th R.a. Bill for Township II
Page 1144: Triangle Construction 4th R.a. Bill for Township II
Page 1145: Triangle Construction 4th R.a. Bill for Township II
Page 1146: Triangle Construction 4th R.a. Bill for Township II
Page 1147: Triangle Construction 4th R.a. Bill for Township II
Page 1148: Triangle Construction 4th R.a. Bill for Township II
Page 1149: Triangle Construction 4th R.a. Bill for Township II
Page 1150: Triangle Construction 4th R.a. Bill for Township II
Page 1151: Triangle Construction 4th R.a. Bill for Township II
Page 1152: Triangle Construction 4th R.a. Bill for Township II
Page 1153: Triangle Construction 4th R.a. Bill for Township II
Page 1154: Triangle Construction 4th R.a. Bill for Township II
Page 1155: Triangle Construction 4th R.a. Bill for Township II
Page 1156: Triangle Construction 4th R.a. Bill for Township II
Page 1157: Triangle Construction 4th R.a. Bill for Township II
Page 1158: Triangle Construction 4th R.a. Bill for Township II
Page 1159: Triangle Construction 4th R.a. Bill for Township II
Page 1160: Triangle Construction 4th R.a. Bill for Township II
Page 1161: Triangle Construction 4th R.a. Bill for Township II
Page 1162: Triangle Construction 4th R.a. Bill for Township II
Page 1163: Triangle Construction 4th R.a. Bill for Township II
Page 1164: Triangle Construction 4th R.a. Bill for Township II
Page 1165: Triangle Construction 4th R.a. Bill for Township II
Page 1166: Triangle Construction 4th R.a. Bill for Township II
Page 1167: Triangle Construction 4th R.a. Bill for Township II
Page 1168: Triangle Construction 4th R.a. Bill for Township II
Page 1169: Triangle Construction 4th R.a. Bill for Township II
Page 1170: Triangle Construction 4th R.a. Bill for Township II
Page 1171: Triangle Construction 4th R.a. Bill for Township II
Page 1172: Triangle Construction 4th R.a. Bill for Township II
Page 1173: Triangle Construction 4th R.a. Bill for Township II
Page 1174: Triangle Construction 4th R.a. Bill for Township II
Page 1175: Triangle Construction 4th R.a. Bill for Township II
Page 1176: Triangle Construction 4th R.a. Bill for Township II
Page 1177: Triangle Construction 4th R.a. Bill for Township II
Page 1178: Triangle Construction 4th R.a. Bill for Township II
Page 1179: Triangle Construction 4th R.a. Bill for Township II
Page 1180: Triangle Construction 4th R.a. Bill for Township II
Page 1181: Triangle Construction 4th R.a. Bill for Township II
Page 1182: Triangle Construction 4th R.a. Bill for Township II
Page 1183: Triangle Construction 4th R.a. Bill for Township II
Page 1184: Triangle Construction 4th R.a. Bill for Township II
Page 1185: Triangle Construction 4th R.a. Bill for Township II
Page 1186: Triangle Construction 4th R.a. Bill for Township II
Page 1187: Triangle Construction 4th R.a. Bill for Township II
Page 1188: Triangle Construction 4th R.a. Bill for Township II
Page 1189: Triangle Construction 4th R.a. Bill for Township II
Page 1190: Triangle Construction 4th R.a. Bill for Township II
Page 1191: Triangle Construction 4th R.a. Bill for Township II
Page 1192: Triangle Construction 4th R.a. Bill for Township II
Page 1193: Triangle Construction 4th R.a. Bill for Township II
Page 1194: Triangle Construction 4th R.a. Bill for Township II
Page 1195: Triangle Construction 4th R.a. Bill for Township II
Page 1196: Triangle Construction 4th R.a. Bill for Township II
Page 1197: Triangle Construction 4th R.a. Bill for Township II
Page 1198: Triangle Construction 4th R.a. Bill for Township II
Page 1199: Triangle Construction 4th R.a. Bill for Township II
Page 1200: Triangle Construction 4th R.a. Bill for Township II
Page 1201: Triangle Construction 4th R.a. Bill for Township II
Page 1202: Triangle Construction 4th R.a. Bill for Township II
Page 1203: Triangle Construction 4th R.a. Bill for Township II
Page 1204: Triangle Construction 4th R.a. Bill for Township II
Page 1205: Triangle Construction 4th R.a. Bill for Township II
Page 1206: Triangle Construction 4th R.a. Bill for Township II
Page 1207: Triangle Construction 4th R.a. Bill for Township II
Page 1208: Triangle Construction 4th R.a. Bill for Township II
Page 1209: Triangle Construction 4th R.a. Bill for Township II

Page 1209 of 1288 ABSTRACT SHEET

TRIANGLE CONSTRUCTIONDoc.No.- TC/CGPL/11-12/RA-4

Abstract SheetClient:COASTAL GUJARAT POWER LIMITED(CGPL), MUNDRA

RA Bill No. : 4thDate: 31/08/2011

Description Unit

Contract Quantity(Package-7) Amount

Rate Amount This Bill Total This Bill Total

A - Civil WorkSection:1 Earth works

1.01

Cu.Mt. 4810.09 88.78 427039.79 1738.00 0.00 1738.00 154299.64 0.00 154299.64

1.10

Cu.Mt 2142.11 168.88 361759.54 2128.43 0.00 2128.43 359449.26 0.00 359449.26

1.11.a

Cu.Mt 405.95 173.70 70513.52 167.36 0.00 167.36 29070.43 0.00 29070.43

Work Order No. : 6300001044 Triangle Construction T.D.X. - 108, Barwadi,

Tender Item

No.BOQ QTY.

Upto Previous

Bill

Up to Previous

Bill

Earth work in excavation in all kind of soil by mechanical means / manual means in foundation trenches, drains, etc. lead up to 100mt

a) Depth up to 2.0 m

Filling, in foundations, plinths and other areas as directed with murrum or selected cohesive non swelling soil obtained from outside (Contractor's earth) in layers of 15 cm. thickness, including watering to optimum moisture content, ramming and compacting

Filling, in foundation and plinth (under floors), with good quality coarse river sand , obtained from outside, including watering, ramming well, consolidating and dressing etc. complete, as directed (For all civil, plumbing & electrical works).

Page 1210: Triangle Construction 4th R.a. Bill for Township II

Page 1210 of 1288 ABSTRACT SHEET

Description Unit

Contract Quantity(Package-7) Amount

Rate Amount This Bill Total This Bill Total

Tender Item

No.BOQ QTY.

Upto Previous

Bill

Up to Previous

Bill

1.14

Cu.Mt 1379.90 53.08 73245.09 1738.00 0.00 1738.00 92253.04 0.00 92253.04

1.15

Sq.Mt. 3316.38 48.25 160015.34 777.99 401.72 1179.71 37538.02 19382.99 56921.01

Section:2 PCC & RCC works

2.01

c) PCC 1:4:8 Cu.Mt 814.90 1375.13 1120593.44 207.44 13.18 220.62 285256.97 18124.21 303381.18

2.09

Disposing of the surplus excavated earth and/or debris etc. including loading at site, transporting & disposal as per designated place by EIC, unloading, spreading and dressing etc. complete (For all civil, plumbing & electrical works).

a) Beyond initial lead of 100m to 1km.

Carrying out pre construction anti-termite treatment for all types of structure without basement with RCC foundation/RCC wall or with load bearing wall foundation. The chemical used shall be confirming to IS : 6313 part-II like chloropyriphos 20EC etc. as

Providing and laying Cement Concrete including compaction, finishing top surface to the level curing but excluding the cost of formwork etc. complete as per specifications and directions as per Engineer-in-charge. In foundations, plinth, sub base of floor

Supplying, fabricating and placing in position reinforcement bars of all diameter confirming to IS-1786 reinforcement for RCC structure / items as per design including transporting steel to the work site, handling wastage, decoiling, cutting, bending, cra

Page 1211: Triangle Construction 4th R.a. Bill for Township II

Page 1211 of 1288 ABSTRACT SHEET

Description Unit

Contract Quantity(Package-7) Amount

Rate Amount This Bill Total This Bill Total

Tender Item

No.BOQ QTY.

Upto Previous

Bill

Up to Previous

Bill

The reinforcement shall be

MT 218.74 5452.25 1192625.17 158.21 23.98 182.19 862600.47 130771.76 993372.23

2.12

2.12.1Cu.Mt 1679.63 1635.68 2747337.20 1158.88 160.48 1319.36 1895556.84 262493.93 2158050.76

Section:3 Centering & Form works

3.01

3.01a

Sq.Mt. 12066.09 285.64 3446557.95 7887.92 1296.01 9183.93 2253105.47 370190.95 2623296.42Sectoin:4 Masonry works

4.09

a) TMT bars- CRS Fe- 500, yield stress not less than 500 N/mm2

Providing and laying in position machine batched, machine mixed and machine vibrated design mix fair finish / smooth finish cement concrete of M30 grade with minimum cement content 400 Kg per cum of concrete for reinforced cement concrete work for all wor

Excluding the cost of centering, shuttering and reinforcement

Providing ordinary formwork with shuttering plywood/ steel sheathing and steel supporting system so as to give fair finish, including centering, shuttering and propping, etc. complete, height of propping and centering below supporting floor to ceiling not

As per item no 3.01 but for all heights, levels, shapes and locations. The rate shall be inclusive of cost of staging, if at all required (For all civil, plumbing and electrical works).

Providing and laying Solid cement concrete block masonry in cement mortar 1:5 (1 part cement and 5 part of sand) using factory made/precast (made out of 1:4:8 concrete), load bearing, approved quality, Density of blocks not less than 1800 kg/cum. Minimum

Page 1212: Triangle Construction 4th R.a. Bill for Township II

Page 1212 of 1288 ABSTRACT SHEET

Description Unit

Contract Quantity(Package-7) Amount

Rate Amount This Bill Total This Bill Total

Tender Item

No.BOQ QTY.

Upto Previous

Bill

Up to Previous

Bill

Cu.Mt 1121.98 1737.00 1948879.26 295.13 52.92 348.05 512640.81 91915.09 604555.90

Sq.Mt. 5406.97 386.00 2087090.42 2611.10 507.86 3118.96 1007884.60 196033.96 1203918.56

Sq.Mt. 1,180 265.38 313153.71 99.84 114.24 214.08 26495.54 30317.01 56812.55Sectoin:5 Doors and Windows work

5.01

Cum 9.17 86391.63 792,211.25 2.80 2.80 0.00 241896.56 241896.56

7.01c

Sq.Mt. 3,642 106.15 386605.73 526.12 0.00 526.12 55847.64 0.00 55847.64

Sq.Mt. 9,172 135.10 1239179.08 979.56 0.00 979.56 132338.56 0.00 132338.56

a) For 300 mm thick wall

b) For 200 mm thick wall

c) For 100 mm thick wall

Providing & fixing in position door and window frame, including grooves on both sides and 2 rebates for on frame, made from best quality selected well seasoned Sal wood including smoothening, sand papering, making the edges rounded fixing the same using a

Sectoin:7 Plaster and Pointing worksProviding and laying average 6 mm thick single coat mala finish plaster in CM 1:4, on RCC surfaces viz. ceilings and stair soffits etc. at all floors, all shapes and all heights with necessary scaffolding, curing, making grooves, forming pattas, hacking p

7.02b.1

Providing and laying average 12 mm thick single coat mala finish plaster in CM 1:6, on sides of brickwork/ blocks at all floors, all shapes and all heights with necessary scaffolding, curing, making grooves, forming pattas, hacking properly RCC surface etc.

Page 1213: Triangle Construction 4th R.a. Bill for Township II

Page 1213 of 1288 ABSTRACT SHEET

Description Unit

Contract Quantity(Package-7) Amount

Rate Amount This Bill Total This Bill Total

Tender Item

No.BOQ QTY.

Upto Previous

Bill

Up to Previous

Bill

7.04.a

Sq.Mt. 9,006 202.65 1825013.21 1498.60 2068.06 3566.66 303691.29 419092.64 722783.93Sectoin:8 Waterproofing works

8.09.b

Sq.Mt. 2819.11 190.00 535630.90 580.68 412.51 993.19 110329.20 78377.28 188706.48

9.44

Rmt 76.84 4926.33 378,539.20 21.40 21.40 105423.46 105423.46

B - Plumbing WorksSection:1 Water supply

1.01.a

8) 25 mm rmt 283 328.10 92,823 59.52 39.68 99.20 19528.51 13019.01 32547.52

Providing and laying average 18-20 mm. thick Sand face cement plaster on walls upto any height above ground level and for all shapes consisting of average 12-15 mm. thick backing coat of CM 1:6 (1 cement: 6 coarse sand) and average 6 mm. thick uniform gra

Providing and laying 60 mm. thick water proof cement concrete flooring for IPS in 1:2:4 (1 Cement : 2 Sand : 4 Graded Aggregate 20mm nominal size) on RCC floors / slab / sloping slabs / swimming pool floor, including vata, etc as directed by EIC, at all hProviding & laying sandwich platform of maximum 700mm width a) Sandwich type platform of top stone as 18 mm thick Granite of approved shade and sample and bottom stone as 25 mm thick single side polished kota with 25 mm thick screed of cement mortar

Providing and fixing galvanized iron (GI) mild steel tube (Medium grade Class B) of Tata or equivalent approved make conforming to IS: 1239, including tube fittings of ‘R’ brand or equivalent approved make such as sockets, unions, reducers, long or short

Page 1214: Triangle Construction 4th R.a. Bill for Township II

Page 1214 of 1288 ABSTRACT SHEET

Description Unit

Contract Quantity(Package-7) Amount

Rate Amount This Bill Total This Bill Total

Tender Item

No.BOQ QTY.

Upto Previous

Bill

Up to Previous

Bill

10) 15 mm. rmt 622 264.41 164,569 215.64 143.76 359.40 57017.37 38011.58 95028.95

3.08.b

1) 110mm, rmt 485 337.75 163,805 87.15 58.10 145.25 29434.91 19623.27 49058.19

3.09.a

nos 192 349.33 67,071 36.00 24.00 60.00 12575.88 8383.92 20959.80Total Amount 8236914.44 2043057.64 10279972.08

For TRIANGLE CONSTRUCTION

PROJECT MANAGER

Providing and fixing uPVC pressure pipes of Supreme or equivalent make as approved by EIC concealed laid having 6kg /cm² working pressure for Soil and Waste water, complete jointing with suitable grade of good quality solvent cement (supplied by the man

Providing and fixing an SWR quality, heavy duty, uPVC ‘P’ trap of Supreme or equivalent make as approved by EIC Including cutting the floor and making them good with surrounding M15 CC, masonry /block supports, MS brackets etc. testing, etc complete to th

Page 1215: Triangle Construction 4th R.a. Bill for Township II

Page 1215 of 1288 IPS 8.09 b

TRIANGLE CONSTRUCTION

Measurement SheetProject Name: Township For CGPL at Mundra Running Bill No. 4thLocation: Mundra Period 23/07/2011 to 31/08/2011

Date of Submission 31/08/2011Name of Contractor: TRTIANGLE CONSTRUCTIONWork Order No.: 6300001044

Type B10

Description of Item Unit No. Length Breadth Depth Quantity

8.09.b

Sq.Mt.Sloping slab at G5Grid H-L / 14A-12A 2 1 4.350 2.310 20.10Grid H-C / 14A-12A 2 1 4.650 2.310 21.48Grid K-A / 13A-16A 2 1 6.700 2.760 36.98Grid K-E / 13A-12A 2 1 1.000 2.760 5.52

Total of G5 84.08G1, G2, G8, G9 & G12 same as G5 84.08 6.00 504.50Sloping slab at F5Grid H-L / 6A-4A 2 1 4.350 2.310 20.10Grid H-C / 6A-4A 2 1 4.650 2.310 21.48Grid K-A / 8A-5A 2 1 6.700 2.760 36.98Grid K-E / 5A-1 2 1 7.900 2.760 43.61

Total of F5 122.17F3, F4, F6 same as F5 122.17 4.00 488.69

Total Sq.Mt. 993.19Less Paid in 3rd R.A. Bill Item No.- 8.09 in Cu.Mt. 580.68

Net Balance Qut. In this Bill Cu.Mt. 412.51

For TRIANGLE CONSTRUCTION

PROJECT MANAGER

Doc. No. : TC/CGPL/11-12 /RA-4 Date: 31/08/2011

Name of Owner: M/s Coastal Gujarat Power Limited

Item No

Total Quantity

Providing and laying 60 mm. thick water proof cement concrete flooring for IPS in 1:2:4 (1 Cement : 2 Sand : 4 Graded Aggregate 20mm nominal size) on RCC floors / slab / sloping slabs / swimming pool floor, including vata, etc as directed by EIC, at all h

Page 1216: Triangle Construction 4th R.a. Bill for Township II

Page 1216 of 1288 Anti-termite 1.15

TRIANGLE CONSTRUCTION

Measurement SheetProject Name: Township For CGPL at Mundra Running Bill No. 4thLocation: Mundra Period 23/07/2011 to 31/08/2011

Date of Submission 31/08/2011Name of Contractor: TRTIANGLE CONSTRUCTIONWork Order No.: 6300001044

Type B10

Description of Item Unit No. Length Breadth Depth Quantity

1.15

14A-12A/C-F Bed room-2 1 1 4.000 3.850 15.4014A-12A/J-L Bed room-1 1 1 4.000 3.550 14.2015A-14A/D-E Verandah 1 1 4.000 1.500 6.00Living Room 1 1 4.000 5.000 20.00Dinning 1 1 5.500 3.700 20.3511A-10A/K-E - Study/Kitchen 1 1 3.150 5.000 15.75

Total qty of G5 Cumt. 91.70

91.70 7.00 641.90

14A-12A/C-F Bed room-1 1 1 4.000 3.550 14.2014A-12A/J-L Bed room-2 1 1 4.000 3.850 15.4015A-14A/D-E Verandah 1 1 4.000 1.400 5.60Dinning 1 1 5.050 3.700 18.69Living Room 1 1 4.000 5.000 20.0011A-10A/K-E - Study/Kitchen 1 1 3.150 5.000 15.75

Doc. No. : TC/CGPL/11-12 /RA-4 Date: 31/08/2011

Name of Owner: M/s Coastal Gujarat Power Limited

Item No

Total Quantity

Carrying out pre construction anti-termite treatment for all types of structure without basement with RCC foundation/RCC wall or with load bearing wall foundation. The chemical used shall be confirming to IS : 6313 part-II like chloropyriphos 20EC etc. as

House Type B10 anti termite treatment at -G5

B10 Type G1, G4, G8, G9, G12 & G13 is same to G5

House Type B10 anti termite treatment at -G6

Page 1217: Triangle Construction 4th R.a. Bill for Township II

Page 1217 of 1288 Anti-termite 1.15

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Total qty of G6 Cumt. 89.64

89.64 6.00 537.81

Total Sq. Mt. 1179.71

Less Paid in 3rd R.A. Bill Item No.- 1.15 in Cu.Mt. 777.99Net Balance Qut. In this Bill Cu.Mt. 401.72

For TRIANGLE CONSTRUCTION

PROJECT MANAGER

B10 Type G2, G3, G7, G10 & G11is same is G6

Page 1218: Triangle Construction 4th R.a. Bill for Township II

Page 1218 of 1288 PCC 2.01

TRIANGLE CONSTRUCTION

Measurement SheetProject Name: Township For CGPL at Mundra Running Bill No. 4thLocation: Mundra Period 23/07/2011 to 31/08/2011

Date of Submission 31/08/2011Name of Contractor: TRTIANGLE CONSTRUCTIONWork Order No.: 6300001044

Type B10

Description of Item Unit No. Length Breadth Depth Quantity

2.01

Avg.NGL=3.950,Avg.Exc.lvl=2.250 mt.G5C1 4 1 1.400 1.400 0.075 0.59C2 4 1 1.550 1.550 0.075 0.72C3 1 1 1.550 1.550 0.075 0.18C4 5 1 1.800 1.800 0.075 1.22C5 2 1 1.550 2.200 0.075 0.51C9A 1 1 1.400 1.400 0.075 0.15

Total qty of G5 Cumt. 3.37

3.17 8.00 25.36G6C1A 1 1 1.400 1.400 0.075 0.15C6 4 1 2.050 2.050 0.075 1.26C6A 2 1 2.050 2.050 0.075 0.63C7 4 1 1.800 1.800 0.075 0.97C7A 2 1 1.800 1.800 0.075 0.49C8 4 1 1.550 1.700 0.075 0.79C9 4 1 1.400 1.400 0.075 0.59C9A 1 1 1.400 1.400 0.075 0.15C10 1 1 1.200 2.500 0.075 0.23

Doc. No. : TC/CGPL/11-12 /RA-4 Date: 31/08/2011

Name of Owner: M/s Coastal Gujarat Power Limited

Item No

Total Quantity

Providing and laying Cement Concrete including compaction, finishing top surface to the level curing but excluding the cost of formwork etc. complete as per specifications and directions as per Engineer-in-charge. In foundations, plinth, sub base of floors etc. (For all civil, plumbing and electrical works.)

c) PCC 1:4:8

B10 Type G1, G4, G8, G9, G12, G13 & G16 is same to G5

Page 1219: Triangle Construction 4th R.a. Bill for Township II

Page 1219 of 1288 PCC 2.01

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

C11 1 1 1.400 1.400 0.075 0.15Total qty of G6 Cumt. 5.41

5.41 8.00 43.28House Type B10 - G5 PCC for Plinth Beam Cumt.

TB1 2 1 1.80 0.35 0.075 0.09TB3 2 1 4.00 0.35 0.075 0.21TB4A 2 1 1.35 0.45 0.075 0.09TB4B 2 1 3.10 0.45 0.075 0.21TB5A 1 1 3.90 0.45 0.075 0.13TB5B 1 1 1.40 0.45 0.075 0.05TB8 2 1 4.00 0.35 0.075 0.21TB13 1 1 4.00 0.35 0.075 0.11TB14 1 1 4.00 0.35 0.075 0.11TB18A 1 1 1.00 0.35 0.075 0.03TB18B 1 1 4.05 0.55 0.075 0.17TB19A 1 1 1.70 0.35 0.075 0.04TB19B 1 1 4.90 0.35 0.075 0.13TB20A 2 1 3.00 0.45 0.075 0.20TB20A 2 1 2.70 0.45 0.075 0.18TB20B 4 1 0.40 0.45 0.075 0.05TB21 2 1 2.90 0.35 0.075 0.15TB22 2 1 2.90 0.35 0.075 0.15TB25 1 1 5.00 0.35 0.075 0.13TB26 2 1 5.00 0.35 0.075 0.26

Total Qty of G5 Cumt. 2.70G1, G4, G8, G9, G12 & G13 same as G5 2.70 8.00 21.60PCC below Plinth beam G6TB1 2 1 1.800 0.35 0.075 0.09TB3 2 1 4.000 0.35 0.075 0.21TB5A 1 1 4.000 0.45 0.075 0.14TB5A 1 1 3.900 0.45 0.075 0.13TB5B 1 1 1.400 0.45 0.075 0.05TB5B 1 1 1.300 0.45 0.075 0.04TB6A 1 1 0.900 0.35 0.075 0.02TB6B 1 1 2.400 0.55 0.075 0.10TB7A 2 1 3.700 0.45 0.075 0.25

B10 Type G3, G2, G7, G10, G11, G14 & G 15 is same is G6

Page 1220: Triangle Construction 4th R.a. Bill for Township II

Page 1220 of 1288 PCC 2.01

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

TB7B 1 1 2.800 0.45 0.075 0.09TB8 2 1 4.000 0.35 0.075 0.21TB10A 1 1 3.150 0.35 0.075 0.08TB10B 0.5 1 2.800 0.35 0.075 0.04TB11 1 1 2.600 0.35 0.075 0.07TB12 1 1 2.600 0.35 0.075 0.07TB14 1 1 4.000 0.35 0.075 0.11TB15A 1 1 1.535 0.35 0.075 0.04TB15B 1 1 3.765 0.35 0.075 0.10TB16 1 1 3.765 0.35 0.075 0.10TB19A 1 1 1.800 0.35 0.075 0.05TB19B 1 1 5.000 0.35 0.075 0.13TB20A 2 1 2.700 0.45 0.075 0.18

2 1 3.000 0.45 0.075 0.20TB20B 4 1 0.400 0.45 0.075 0.05TB21 2 1 2.900 0.35 0.075 0.15TB22 2 1 2.900 0.35 0.075 0.15TB23A 1 1 1.200 0.35 0.075 0.03TB23B 1 1 1.800 0.35 0.075 0.05TB23C 1 1 1.800 0.35 0.075 0.05TB24A 1 1 2.300 0.35 0.075 0.06TB24B 1 1 2.300 0.35 0.075 0.06TB14 0.5 1 2.800 0.35 0.075 0.04

Total Qty of G6 3.14G2, G3, G7, G10, G11 & G14 same as G6 3.14 8.00 25.12House Type B10 Floor PCC-G514A-12A/C-F Bed room-2 1 1 4.000 3.850 0.075 1.1614A-12A/J-L Bed room-1 1 1 4.000 3.550 0.075 1.0715A-14A/D-E Verandah 1 1 4.000 1.500 0.075 0.45Living Room 1 1 4.000 5.000 0.075 1.50Dinning 1 1 5.050 3.700 0.075 1.4011A-10A/K-E - Study/Kitchen 1 1 3.150 5.000 0.075 1.18Toilet 1 & 2 2 1 2.200 1.800 0.075 0.59Toilet 3 & Utility 1 1 1.350 5.000 0.075 0.51Entrench 1 1 4.300 1.000 0.075 0.32

Total qty of G5 Cumt. 8.188.18 7.00 57.26B10 Type G1, G4, G8, G9, G12 & G13 is same to G5

Page 1221: Triangle Construction 4th R.a. Bill for Township II

Page 1221 of 1288 PCC 2.01

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

House Type B10 Floor PCC-G614A-12A/C-F Bed room-1 1 1 4.000 3.550 0.075 1.0714A-12A/J-L Bed room-2 1 1 4.000 3.850 0.075 1.1615A-14A/D-E Verandah 1 1 4.000 1.400 0.075 0.42Dinning 1 1 5.050 3.700 0.075 1.40Living Room 1 1 4.000 5.000 0.075 1.5011A-10A/K-E - Study/Kitchen 1 1 3.150 5.000 0.075 1.18Toilet 1 & 2 2 1 2.200 1.800 0.075 0.59Toilet 3 & Utility 1 1 1.350 5.000 0.075 0.51Entrench 1 1 2.250 1.000 0.075 0.17

Total qty of G6 Cumt. 8.008.00 6.00 48.00

Total Cu.Mt. 220.62Less Paid in 3rd R.A. Bill Item No.- 2.01 in Cu.Mt. 207.44

Net Balance Qut. In this Bill Cu.Mt. 13.18

For TRIANGLE CONSTRUCTION

PROJECT MANAGER

B10 Type G7, G10 & G11is same is G6

Page 1222: Triangle Construction 4th R.a. Bill for Township II

Page 1222 of 1288 RCC and Shuttering

TRIANGLE CONSTRUCTION

Measurement SheetProject Name: Township For CGPL at Mundra Running Bill No. 4th

Location: Mundra Period 23/07/2011 to 31/08/2011

Date of Submission 31/08/2011

Name of Contractor: TRTIANGLE CONSTRUCTION

Work Order No.: 6300001044

Type B10

Description of Item Unit No. Length Breadth Depth Quantity

2.12.1

House Type B10 (R.C.C. For Footing) G2 Cumt.

1 1 0.41 1.00 0.41

4 1 1.32 1.00 5.28

2 1 1.29 1.00 2.58

4 1 0.89 1.00 3.56

2 1 0.89 1.00 1.78

4 1 0.67 1.00 2.66

4 1 0.41 1.00 1.65

1 1 0.41 1.00 0.41

Doc. No. : TC/CGPL/11-12 /RA-4 Date: 31/08/2011

Name of Owner: M/s Coastal Gujarat Power Limited

Item No

Total Quantity

Providing and laying in position machine batched, machine mixed and machine vibrated design mix fair finish / smooth finish cement concrete of M30 grade with minimum cement content 400

C1A = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=1.44 Sqmt.,A2=0.15 Sqmt.D=350mm,d=230mm,h=120mm.C6 = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=3.42 Sqmt.,A2=0.16 Sqmt.D=600mm,d=230mm,h=370mm.C6A = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=3.42 Sqmt.,A2=0.09 Sqmt.D=600mm,d=230mm,h=370mm.C7 = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=2.56 Sqmt.,A2=0.16 Sqmt.D=500mm,d=230mm,h=270mm.C7A = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=2.56 Sqmt.,A2=0.16 Sqmt.D=500mm,d=230mm,h=270mm.C8 = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=2.025 Sqmt.,A2=0.15 Sqmt.D=450mm,d=230mm,h=220mm.C9 = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=1.44 Sqmt.,A2=0.15 Sqmt.D=350mm,d=230mm,h=120mm.C9 = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=1.44 Sqmt.,A2=0.15 Sqmt.D=350mm,d=230mm,h=120mm.

Page 1223: Triangle Construction 4th R.a. Bill for Township II

Page 1223 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

1 1 0.81 1.00 0.81

11 0.41 1.00 0.41

Total qty of G2 Cumt. 19.55

19.55 8.00 156.40

House Type B10 (R.C.C. For Footing) G1 Cumt.

4 1 0.41 1.00 1.65

4 1 0.56 1.00 2.25

1 1 0.56 1.00 0.56

5 1 0.89 1.00 4.46

2 1 0.99 1.00 1.99

1 1 0.41 1.00 0.41Total qty of G1 Cumt. 11.32

11.32 8.00 90.56

G5

C1 4 1 0.20 0.40 1.26 0.40C2 4 1 0.30 0.30 1.21 0.44C3 1 1 0.20 0.40 1.21 0.10C4 5 1 0.30 0.30 1.11 0.50

C10 = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=2.30 Sqmt.,A2=0.45 Sqmt.D=450mm,d=230mm,h=220mm.C11 = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=1.44 Sqmt.,A2=0.15 Sqmt.D=350mm,d=230mm,h=120mm.G3, G6, G7, G10, G11, G14 & G15 is same is G2

C1 = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=1.44 Sqmt.,A2=0.15 Sqmt.D=350mm,d=230mm,h=120mm.C2 = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=1.82 Sqmt.,A2=0.16 Sqmt.D=400mm,d=230mm,h=170mm.C3 = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=1.82 Sqmt.,A2=0.16 Sqmt.D=400mm,d=230mm,h=170mm.C4 = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=2.56 Sqmt.,A2=0.16 Sqmt.D=500mm,d=230mm,h=270mm.C5 = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=2.70 Sqmt.,A2=0.40 Sqmt.D=500mm,d=230mm,h=270mm.C9A = [{h/3(A1+A2+SQRT(A1*A2))} + (A1*d)] A1=1.44 Sqmt.,A2=0.16 Sqmt.D=350mm,d=230mm,h=120mm.G4, G5, G8, G9, G12 G13 & G16 is same to G1

B10-Concrete for pedestal up to Plinth beam bottom

Avg.NGL=3.950,Avg.Exc.lvl=2.250 mt. & P.L. 4.60 mt.

Page 1224: Triangle Construction 4th R.a. Bill for Township II

Page 1224 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

C5 2 1 0.30 0.90 1.11 0.60C9A 1 1 0.20 0.40 1.26 0.10

Total qty of G5 Cumt. 2.14

2.14 4.00 8.56G6

C1A 1 1 0.200 0.400 1.26 0.10C6 4 1 0.300 0.300 1.01 0.36C6A 2 1 0.300 0.300 1.01 0.18C7 4 1 0.300 0.300 1.11 0.40C7A 2 1 0.300 0.300 1.11 0.20C8 4 1 0.200 0.400 1.16 0.37C9 4 1 0.200 0.400 1.26 0.40C9A 1 1 0.200 0.400 1.26 0.10C10 1 1 0.200 1.400 1.16 0.32

C11 1 1 0.200 0.400 1.26 0.10Total qty of G6 Cumt. 2.53

2.53 4.00 10.12

G1

C1 4 1 0.20 0.40 1.36 0.44C2 4 1 0.30 0.30 1.31 0.47C3 1 1 0.20 0.40 1.31 0.10C4 5 1 0.30 0.30 1.21 0.54C5 2 1 0.30 0.90 1.21 0.65C9A 1 1 0.20 0.40 1.36 0.11

Total qty of G1 Cumt. 2.31

B10 Type G8, G9 & G12 is same to G5

B10 Type G7, G10 & G11is same is G6

B10-Concrete for pedestal up to Plinth beam bottom

Avg.NGL=3.950,Avg.Exc.lvl=2.250 mt. & P.L. 4.70 mt.

Page 1225: Triangle Construction 4th R.a. Bill for Township II

Page 1225 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

2.31 4.00 9.24G2

C1A 1 1 0.200 0.400 1.36 0.11C6 4 1 0.300 0.300 1.11 0.40C6A 2 1 0.300 0.300 1.11 0.20C7 4 1 0.300 0.300 1.21 0.44C7A 2 1 0.300 0.300 1.21 0.22C8 4 1 0.200 0.400 1.26 0.40C9 4 1 0.200 0.400 1.36 0.44C9A 1 1 0.200 0.400 1.36 0.11C10 1 1 0.200 1.400 1.26 0.35

C11 1 1 0.200 0.400 1.36 0.11Total qty of G2 Cumt. 2.78

2.78 4.00 11.12House Type B10 - G1 Plinth Beam Cumt.

TB1 2 1.80 0.20 0.60 0.43TB2 2 2.20 0.20 0.30 0.26TB3 2 4.00 0.20 0.60 0.96TB4A 2 1.35 0.30 0.60 0.49TB4B 2 3.10 0.30 0.60 1.12TB5A 1 3.90 0.30 0.60 0.70TB5B 1 1.40 0.30 0.60 0.25TB8 2 4.00 0.20 0.60 0.96TB13 1 4.00 0.20 0.60 0.48TB14 1 4.00 0.20 0.60 0.48TB18A 1 1.00 0.20 0.60 0.12TB18B 1 4.05 0.40 0.60 0.97TB19A 1 1.70 0.20 0.60 0.20

B10 Type G4, G13 & G16 is same to G1

B10 Type G3, G14 & G15 is same is G2

Page 1226: Triangle Construction 4th R.a. Bill for Township II

Page 1226 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

TB19B 1 4.90 0.20 0.60 0.59TB20A 2 3.00 0.30 0.60 1.08TB20A 2 2.70 0.30 0.60 0.97TB20B 4 0.40 0.30 0.60 0.29TB21 2 2.90 0.20 0.60 0.70TB22 2 2.90 0.20 0.60 0.70TB25 1 5.00 0.20 0.60 0.60TB26 2 5.00 0.20 0.60 1.20Column Concrete with Plinth beam -G1

C1 4 0.20 0.40 0.60 0.19C2 4 0.30 0.30 0.60 0.22C3 1 0.20 0.40 0.60 0.05C4 5 0.30 0.30 0.60 0.27C5 2 0.30 0.90 0.60 0.32C9A 1 0.20 0.40 0.60 0.05

Total qty of G1 Cumt. 14.65

14.65 8.00 117.20House Type B10 - G2 Plinth Beam Cumt.

TB1 2 1 1.800 0.20 0.600 0.43TB2 2 1 2.200 0.20 0.300 0.26TB3 2 1 4.000 0.20 0.600 0.96TB5A 1 1 4.000 0.30 0.600 0.72TB5A 1 1 3.900 0.30 0.600 0.70TB5B 1 1 1.400 0.30 0.600 0.25TB5B 1 1 1.300 0.30 0.600 0.23TB6A 1 1 0.900 0.20 0.600 0.11TB6B 1 1 2.400 0.40 0.600 0.58

B10 Type G4, G5, G8, G9, G12, G16 & G13 is same to G1

Page 1227: Triangle Construction 4th R.a. Bill for Township II

Page 1227 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

TB7A 2 1 3.700 0.30 0.600 1.33TB7B 1 1 2.800 0.30 0.600 0.50TB8 2 1 4.000 0.20 0.600 0.96TB10A 1 1 3.150 0.20 0.600 0.38TB10B 0.5 1 2.800 0.20 0.600 0.17TB11 1 1 2.600 0.20 0.600 0.31TB12 1 1 2.600 0.20 0.300 0.16TB14 1 1 4.000 0.20 0.600 0.48TB15A 1 1 1.535 0.20 0.600 0.18TB15B 1 1 3.765 0.20 0.600 0.45TB16 1 1 3.765 0.20 0.600 0.45TB19A 1 1 1.800 0.20 0.600 0.22TB19B 1 1 5.000 0.20 0.600 0.60TB20A 2 1 2.700 0.30 0.600 0.97

2 1 3.000 0.30 0.600 1.08TB20B 4 1 0.400 0.30 0.600 0.29TB21 2 1 2.90 0.20 0.600 0.70TB22 2 1 2.90 0.20 0.600 0.70TB23A 1 1 1.20 0.20 0.600 0.14TB23B 1 1 1.80 0.20 0.600 0.22TB23C 1 1 1.80 0.20 0.600 0.22TB24A 1 1 2.30 0.20 0.600 0.28TB24B 1 1 2.30 0.20 0.600 0.28TB14 0.5 1 2.80 0.20 0.600 0.17Concrete for column with plinth beam G2

C1A 1 1 0.200 0.400 0.600 0.05C6 4 1 0.300 0.300 0.600 0.22C6A 2 1 0.300 0.300 0.600 0.11

Page 1228: Triangle Construction 4th R.a. Bill for Township II

Page 1228 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

C7 4 1 0.300 0.300 0.600 0.22C7A 2 1 0.300 0.300 0.600 0.11C8 4 1 0.200 0.400 0.600 0.19C9 4 1 0.200 0.400 0.600 0.19C9A 1 1 0.200 0.400 0.600 0.05C10 1 1 0.200 1.400 0.600 0.17

C11 1 1 0.200 0.400 0.600 0.05Total qty of G2 Cumt. 16.84

16.84 8.00 134.72Concrete for column up to Lintel level G5

C1 4 1 0.200 0.400 2.165 0.69C2 4 1 0.300 0.300 2.165 0.78C3 1 1 0.200 0.400 2.165 0.17C4 5 1 0.300 0.300 2.165 0.97C5 2 1 0.300 0.900 2.165 1.17

Total qty of G5 Cumt. 3.78

3.78 8.00 30.24Concrete for column up to Lintel level G6

C1A 1 1 0.200 0.400 2.165 0.17C6 4 1 0.300 0.300 2.165 0.78C6A 2 1 0.300 0.300 2.165 0.39C7 4 1 0.300 0.300 2.165 0.78C7A 2 1 0.300 0.300 2.165 0.39C8 4 1 0.200 0.400 2.165 0.69C9 3 1 0.200 0.400 1.010 0.24C9 1 1 0.200 0.400 2.165 0.17C10 1 1 0.200 1.400 2.165 0.61

B10 Type G3, G6, G7, G10, G11, G15 & G14 is same is G2

B10 Type G1, G4, G8, G9, G12, G13 & G16 is same to G5

Page 1229: Triangle Construction 4th R.a. Bill for Township II

Page 1229 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

C11 1 1 0.200 0.400 2.165 0.17Total qty of G6 Cumt. 4.39

4.39 8.00 35.12Concrete for Lintel G5

Grid K & 15 to 16 L1 1 1 1.200 0.300 0.200 0.07Grid 16 & E to KL10 1 1 5.100 0.200 0.200 0.20Grid 15 & E to K L5 1 1 4.900 0.200 0.200 0.20Grid E & 15 to 16 L3 1 1 1.200 0.300 0.400 0.14Ent. Down slab 1 1 5.000 1.200 0.100 0.60Grid 15 & E to D L5 1 1 1.750 0.200 0.200 0.07Grid D to C & 14 to 15 L4 1 1 4.000 0.300 0.200 0.24Grid E & 14 to 15 L3 1 1 4.000 0.300 0.400 0.48

Ver. Down slab 1 1 1.450 4.000 0.100 0.58

Grid 13 & A to C , L to N L11 4 1 2.900 0.200 0.400 0.93

Grid B,M & 12 to 13 L11 2 1 2.200 0.200 0.400 0.35

Grid A, N & 12 to 13 L11A 2 1 1.800 0.200 0.200 0.14

Grid C, L & 12 to 14 L12 2 1 4.000 0.200 0.400 0.64

Toilet 1 & 2 Down slab 2 1 2.200 1.800 0.100 0.79

Grid 12, 14 & C to E L1 2 1 3.000 0.300 0.200 0.36

Chhaja 2 1 1.125 0.600 0.113 0.15

Grid E, K & 10 to 12 ( L7+ L1 ) 2 1 3.100 0.300 0.200 0.37

Chhaja 2 1 1.125 0.600 0.113 0.15

Grid 10 & E to KL6 2 1 1.350 0.200 0.200 0.11

Grid 9 & E to KL6 1 1 1.050 0.200 0.200 0.04

Grid 12, 14 & K to L L1 2 1 2.700 0.300 0.200 0.32

2 1 1.125 0.600 0.113 0.15

Grid K 14 to 15 L1 1 1 3.900 0.300 0.200 0.23

B10 Type G2, G3, G7, G10, G11, G14 & G15 is same is G6

Chhaja

Page 1230: Triangle Construction 4th R.a. Bill for Township II

Page 1230 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

1 1 1.125 0.600 0.200 0.14

Grid K & 9 to 10 L8 1 1 1.550 0.300 0.200 0.09

1 1 1.550 0.600 0.100 0.09

Grid C, I & 12 to 14 L15 2 1 4.300 0.200 0.400 0.69

2 1 4.300 0.625 0.100 0.54

Grid 12 & E to K L9 1 1 5.000 0.300 0.400 0.60

1 1 5.000 0.600 0.100 0.30Total qty of G5 Cumt. 9.76

9.76 7.00 68.32Concrete for Lintel G10

Grid k & 7 to 8 L1 1 1 1.400 0.300 0.200 0.08Grid 7 and 8 & K to H L5 2 1 2.500 0.200 0.200 0.20Grid 7 to 8 and K to H L5 1 1 1.600 0.200 0.200 0.06Entrance Down slab 1 1 1.200 2.050 0.100 0.25Grid 7 & D to G L5 1 1 1.750 0.200 0.200 0.07Grid D & 6 to 7 L4 1 1 4.000 0.300 0.200 0.24Grid E & 6 to 7 L3 1 1 4.000 0.300 0.400 0.48Grid 6 & C to G L1 1 1 3.000 0.300 0.200 0.18

Chhaja 1 1 1.125 0.600 0.113 0.08

Ver. Down slab 1 1 1.450 4.000 0.100 0.58

Toilet 2 L6 2 1 1.050 0.200 0.200 0.08

Toilet 2 L6 2 1 1.250 0.200 0.200 0.10

Grid 4 & C to G L1 1 1 3.000 0.300 0.200 0.18

Chhaja 1 1 1.125 0.600 0.113 0.08

Grid E & 2 to 4 L1 / L7 1 1 3.700 0.300 0.200 0.22

Grid K & 2 to 4 L1 / L7 1 1 3.700 0.300 0.200 0.22

Chhaja 2 1 1.125 0.600 0.113 0.15

Chhaja

Chhaja

Chhaja

Chhaja

B10 Type G1, G4, G8, G9, G12 & G13 is same to G5

Page 1231: Triangle Construction 4th R.a. Bill for Township II

Page 1231 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Grid G & 4 to 6 L2 1 1 4.300 0.200 0.400 0.34

Chhaja 1 1 4.300 0.600 0.100 0.26

Grid I & 4 to 6 L2 1 1 4.300 0.200 0.400 0.34

Chhaja 1 1 4.300 0.625 0.100 0.27

Grid 4 & E to K L9 1 1 5.000 0.300 0.400 0.60

Chhaja 1 1 5.000 0.600 0.100 0.30

Grid 4, 5 & K to L L1 2 1 2.700 0.300 0.200 0.32

1 1 1.125 0.600 0.113 0.08

Grid K & 6 to 7 L1 1 1 3.900 0.300 0.200 0.23

1 1 1.200 0.600 0.100 0.07

Grid K 1 to 2 L13 1 1 1.600 0.300 0.200 0.10

1 1 1.600 0.600 0.100 0.10

Grid E & 1 to 2 L7 1 1 0.900 0.300 0.200 0.05

Toilet 3 & Utility L6 2 1 1.350 0.200 0.200 0.11Total qty of G10 Cumt. 6.42

6.42 6.00 38.52

RCC for Ground floor Slab - G6

For slabBed room-1 1 1 4.000 3.550 0.125 1.78Bed room-2 1 1 4.000 3.850 0.125 1.93Living Room 1 1 4.000 5.000 0.175 3.50Dinning 1 1 4.600 3.700 0.175 2.98Offset 1 1 0.450 5.000 0.175 0.39Toilet 1 & 2 2 1 2.200 1.800 0.125 0.99Kitchen/Study 1 2 3.150 2.450 0.125 1.93Utility/Toilet 03 1 1 1.400 4.900 0.125 0.86For slab beam

Chhaja

Chhaja

Chhaja

B10 Type G2, G3, G6, G7 & G11 is same to G10

Page 1232: Triangle Construction 4th R.a. Bill for Township II

Page 1232 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

B1 2 1 1.800 0.200 0.450 0.32B2 2 1 2.200 0.200 0.325 0.29

B2 - Duct 1 1 1.400 0.200 0.325 0.09B3 2 1 4.000 0.200 0.450 0.72

B4A 2 1 3.700 0.300 0.450 1.00B4B 2 1 1.400 0.300 0.450 0.38

B5 2 1 4.000 0.200 0.450 0.72B6A 1 1 4.000 0.300 0.450 0.54B6A 1 2 3.900 0.300 0.450 1.05B6B 1 2 1.400 0.300 0.450 0.38B8A 1 1 3.150 0.150 0.450 0.21B8B 1 1 1.400 0.100 0.450 0.06B9A 1 1 1.400 0.200 0.450 0.13

B9B/9C 2 1 1.800 0.200 0.450 0.32B11A/11B 2 1 2.300 0.200 0.450 0.41

B12A 2 1 2.900 0.200 0.450 0.52B12B 1 1 2.700 0.300 0.450 0.36

1 1 3.000 0.300 0.450 0.41B12C 2 1 0.650 0.300 0.450 0.18

B13 2 1 2.900 0.200 0.450 0.52B14A 1 1 2.700 0.300 0.450 0.36

1 1 3.000 0.300 0.450 0.41B14B 2 1 0.650 0.300 0.450 0.18

B15 1 1 5.000 0.200 0.450 0.45B16 1 1 5.000 0.200 0.450 0.45B21 2 1 1.200 0.200 0.450 0.22

For Column with slab

C1A 1 1 0.200 0.400 1.200 0.10

Page 1233: Triangle Construction 4th R.a. Bill for Township II

Page 1233 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

C6 4 1 0.300 0.300 1.200 0.43C6A 2 1 0.300 0.300 1.200 0.22C7 4 1 0.300 0.300 1.200 0.43C7A 2 1 0.300 0.300 1.200 0.22C8 4 1 0.200 0.400 1.200 0.38C9 3 1 0.200 0.400 1.200 0.29C9 1 1 0.200 0.400 1.200 0.10C10 1 1 0.200 1.400 1.200 0.34C11 1 1 0.200 0.400 1.200 0.10

Total qty of G6 Cumt. 27.11

27.11 6.00 162.66

Steps 10 0.5 1.200 0.275 0.159 0.261st Step 1 1 1.200 0.275 0.159 0.05

West slab 1 1 1.200 3.180 0.150 0.57Landing 1 1 1.340 2.600 0.211 0.74

10 1 1.000 0.275 0.159 0.44West slab 1 1 1.000 3.205 0.150 0.48

Landing 1 1 1.400 1.535 0.150 0.32LB1A 1 1 1.535 0.200 0.450 0.14LB1B 1 1 3.765 0.200 0.450 0.34

LB2 1 1 2.600 0.200 0.450 0.23LB3 1 1 4.745 0.200 0.450 0.43

LB4A 1 1 1.535 0.200 0.450 0.14LB4B 1 1 4.745 0.200 0.450 0.43B22 1 1 1.200 0.200 0.300 0.07

Column C9 3 1 0.200 0.400 0.450 0.11

B10 Type G2, G3, G7, G10 & G11 is same is G6

Staircase B10-G6 1st Flight

2nd Flight Steps

Page 1234: Triangle Construction 4th R.a. Bill for Township II

Page 1234 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Column 1A 1 1 0.200 0.400 0.190 0.02Column C9 1 1 0.200 0.400 0.900 0.07

Total Qty of G6 4.84G2, G3, G7, G10 & G11 same as G6 4.84 6.00 29.04

RCC for Ground floor Slab - G8

For slabGrid H-L / 14A-12A 2 1 4.350 2.310 0.135 2.71Grid H-C / 14A-12A 2 1 4.650 2.310 0.135 2.90Grid K-A / 13A-16A 2 1 6.700 2.760 0.135 4.99Grid K-E / 13A-12A 2 1 1.000 2.760 0.135 0.75Flat Slab at Kitchen/Study 1 1 3.800 5.000 0.125 2.38Utility/Toilet 03 1 1 3.550 5.000 0.125 2.22For slab beam

Grid 14A-12A / L-K ( B19/ 18C ) 2 1 2.750 0.300 0.450 0.74Projection 2 1 2.850 0.150 0.150 0.13

Grid 14A-12A / E-C ( B19/ 18A ) 2 1 3.050 0.300 0.450 0.82Projection 2 1 3.150 0.150 0.150 0.14

K / 15A-14A ( B7A-B7B ) 1 1 5.100 0.300 0.450 0.69Projection 1 1 5.250 0.150 0.150 0.12

E / 15A-14A ( B7A-B7B ) 1 1 5.200 0.300 0.450 0.70Projection 1 1 5.250 0.150 0.150 0.12

B18B 1 1 5.000 0.300 0.450 0.68B3A 2 1 4.000 0.200 0.450 0.72B20 1 1 5.600 0.200 0.450 0.50

UB20 1 2 2.910 0.200 0.335 0.39UB3 2 2 2.310 0.200 0.335 0.62

UB18 1 2 2.760 0.200 0.335 0.37B6B 2 1 3.550 0.300 0.450 0.96

Page 1235: Triangle Construction 4th R.a. Bill for Township II

Page 1235 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

B6C 2 1 3.100 0.300 0.450 0.84B17 1 1 5.000 0.200 0.450 0.45

For Column with slab

C1 4 1 0.200 0.400 0.200 0.06C2 4 1 0.300 0.300 1.200 0.43C3 1 1 0.200 0.400 1.200 0.10C4 5 1 0.300 0.300 1.200 0.54C5 2 1 0.300 0.900 1.200 0.65

Total Qty of G8 26.72G1, G4, G5, G9, G13 & G12 same as G8 26.72 7.00 187.04Grad Slab Floor -G5

14A-12A/C-F Bed room-2 1 1 4.000 3.850 0.100 1.5414A-12A/J-L Bed room-1 1 1 4.000 3.550 0.100 1.4215A-14A/D-E Verandah 1 1 4.000 1.500 0.100 0.60Living Room 1 1 4.000 5.000 0.100 2.00Dinning 1 1 5.050 3.700 0.100 1.8711A-10A/K-E - Study/Kitchen 1 1 3.150 5.000 0.100 1.58Toilet 1 & 2 2 1 2.200 1.800 0.100 0.79Toilet 3 & Utility 1 1 1.350 5.000 0.100 0.68Entrench 1 1 4.300 1.000 0.100 0.43

Total qty of G5 Cumt. 10.91

10.91 4.00 43.64Grad Slab Floor -G6

14A-12A/C-F Bed room-1 1 1 4.000 3.550 0.100 1.4214A-12A/J-L Bed room-2 1 1 4.000 3.850 0.100 1.5415A-14A/D-E Verandah 1 1 4.000 1.400 0.100 0.56Dinning 1 1 5.050 3.700 0.100 1.87Living Room 1 1 4.000 5.000 0.100 2.00

B10 Type G8, G9 & G12 is same to G5

Page 1236: Triangle Construction 4th R.a. Bill for Township II

Page 1236 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

11A-10A/K-E - Study/Kitchen 1 1 3.150 5.000 0.100 1.58Toilet 1 & 2 2 1 2.200 1.800 0.100 0.79Toilet 3 & Utility 1 1 1.350 5.000 0.100 0.68Entrench 1 1 2.250 1.000 0.100 0.23

Total qty of G6 Cumt. 10.67

10.67 4.00 42.68

C6 4 1 0.300 0.300 2.165 0.78C6A 2 1 0.300 0.300 2.165 0.39C7 4 1 0.300 0.300 2.165 0.78C7A 2 1 0.300 0.300 2.165 0.39C8 4 1 0.200 0.400 2.165 0.69

Total Qty of F3 3.03F1, F2, F4, F5, & F6 same as F3 3.03 6.00 18.18Concrete for Lintel F3

L5 (Grid 8 & K to E ) 2 1 5.000 0.200 0.200 0.40L5 ( Grid 7 & K to E ) 1 1 5.000 0.200 0.200 0.20L1( Grid K & 6 to 7 ) 1 1 3.900 0.300 0.200 0.23L1 ( Grid E & 6 to 8 ) 1 1 5.300 0.300 0.200 0.32L3 ( Grid K & 7 to 8 ) 1 1 1.400 0.300 0.200 0.08Down slab at Entrance 1 1 5.000 1.200 0.100 0.60L7A ( Grid N & 4 to 5 ) 1 1 1.800 0.200 0.200 0.07L7 ( Grid M & 4 to 5 ) 1 1 2.200 0.200 0.200 0.09L7 ( Grid 4 & N to L ) 1 1 2.900 0.200 0.200 0.12L7 ( Grid 5 & N to L ) 1 1 2.900 0.200 0.200 0.12Toilet 2 Down Slab 1 1 2.200 1.800 0.100 0.40

L8 ( Grid L & 4 to 6 ) 1 1 4.000 0.200 0.400 0.32

B10 Type G7, G10 & G11 is same is G6

Concrete for column Above First floor up to Lintel level F3

Page 1237: Triangle Construction 4th R.a. Bill for Township II

Page 1237 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

L2 ( Grid j & 4 to 6 ) 1 1 4.300 0.200 0.400 0.34

L1 ( Grid 4 & L to K ) 1 1 3.000 0.200 0.200 0.12

L1 ( Grid 6 & L to J ) 1 1 3.450 0.200 0.200 0.14

Chajja at Bed Room 2 1 1 4.300 0.625 0.100 0.27L7A ( Grid A & 4 to 5 ) 1 1 1.800 0.200 0.200 0.07L7 ( Grid B & 4 to 5 ) 1 1 2.200 0.200 0.200 0.09L7 ( Grid 4 & A to C ) 1 1 2.900 0.200 0.200 0.12L7 ( Grid 5 & A to C ) 1 1 2.900 0.200 0.200 0.12Toilet 1 Down Slab 1 1 2.200 1.800 0.100 0.40

L8 ( Grid C & 4 to 6 ) 1 1 4.000 0.200 0.200 0.16

L2 ( Grid E & 4 to 6 ) 1 1 4.300 0.200 0.400 0.34

L1 ( Grid 4 & E to C ) 1 1 3.000 0.300 0.200 0.18

L1 ( Grid 6 & F to C ) 1 1 3.450 0.300 0.200 0.21

Chajja at Bed Room 1 1 1 4.300 0.625 0.100 0.27

L4 ( Grid 4 & I to J) 1 1 3.950 0.300 0.400 0.47

Chajja 1 1 5.600 0.600 0.100 0.34

L1 ( Grid K & 2 to 4 ) 1 1 3.550 0.300 0.200 0.21

L1 ( Grid E & 2 to 4 ) 1 1 3.550 0.300 0.200 0.21

8 1 1.125 0.600 0.113 0.61

7.62

7.62 4.00 30.48

RCC for First Floor Slab - F3

For slabGrid H-L / 6A-4A 2 1 4.350 2.310 0.135 2.71Grid H-C / 6A-4A 2 1 4.650 2.310 0.135 2.90Grid K-A / 8A-5A 2 1 6.550 2.760 0.135 4.88Grid K-E / 5A-1 2 1 6.550 2.760 0.135 4.88For slab beam

Chhaja at L1

B10 Type F4, F5 & F6 is same to F3

Page 1238: Triangle Construction 4th R.a. Bill for Township II

Page 1238 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Grid E / 8A to 6A ( B3A-3B ) 1 1 5.100 0.300 0.450 0.69Projection 1 1 5.100 0.150 0.150 0.11

Grid K / 8A to 6A ( B3A-3B ) 1 1 5.100 0.300 0.450 0.69Projection 1 1 5.100 0.150 0.150 0.11

Grid 8A / E to K ( B6 ) 1 1 5.600 0.200 0.450 0.50Grid L / 6A to 4A ( B1 ) 1 1 4.000 0.200 0.450 0.36Grid C / 6A to 4A ( B1 ) 1 1 4.000 0.200 0.450 0.36

Grid 6A / L to K ( B5 ) 1 1 2.700 0.300 0.450 0.36Projection 1 1 2.700 0.150 0.150 0.06

Grid 4A / L to K ( B5 ) 1 1 2.700 0.300 0.450 0.36Projection 1 1 2.700 0.150 0.150 0.06

Grid 6A / C to E ( B5 ) 1 1 3.000 0.300 0.450 0.41Projection 1 1 3.000 0.150 0.150 0.07

Grid 4A / C to E ( B5 ) 1 1 3.000 0.300 0.450 0.41Projection 1 1 3.000 0.150 0.150 0.07

Grid K / 4A to 1 ( B2A-2B ) 1 1 5.050 0.300 0.450 0.68Projection 1 1 5.050 0.150 0.150 0.11

Grid E / 4A to 1 ( B2A-2B ) 1 1 5.050 0.300 0.450 0.68Projection 1 1 5.050 0.150 0.150 0.11

UB6 1 2 2.910 0.200 0.335 0.39UB18 2 2 2.310 0.200 0.335 0.62

For Column with slab

C6 4 1 0.300 0.300 1.200 0.43C6A 2 1 0.300 0.300 1.200 0.22C7 4 1 0.300 0.300 1.200 0.43C7A 2 1 0.300 0.300 1.200 0.22

Total Qty of F3 23.88F4, F5 & F6 same as F3 23.88 4.00 95.52

Page 1239: Triangle Construction 4th R.a. Bill for Township II

Page 1239 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Total Cu.Mt. 1319.36

Less Paid in 3rd R.A. Bill Item No.- 2.12 in Cu.Mt. 1158.88

Net Balance Qut. In this Bill Cu.Mt. 160.483.01a

House B10 - G2 (Formwork for Footings) Sqmt.

C1A 2 1 1.200 0.230 0.55

2 1 1.200 0.230 0.55C6 2 4 1.850 0.230 3.40

2 4 1.850 0.230 3.40C6A 2 2 1.850 0.230 1.70

2 2 1.850 0.230 1.70C7 2 4 1.600 0.300 3.84

2 4 1.600 0.300 3.84C7A 2 2 1.600 0.300 1.92

2 2 1.600 0.300 1.92C8 2 4 1.350 0.230 2.48

2 4 1.500 0.230 2.76C9 2 4 1.200 0.230 2.21

2 4 1.200 0.230 2.21C9A 2 1 1.200 0.230 0.55

2 1 1.200 0.230 0.55C10 2 1 1.000 0.230 0.46

2 1 2.300 0.230 1.06C11 2 1 1.200 0.230 0.55

2 1 1.200 0.230 0.55

Providing ordinary formwork with shuttering plywood/ steel sheathing and steel supporting system so as to give fair finish, including centering, shuttering and propping, etc. complete, height of

Page 1240: Triangle Construction 4th R.a. Bill for Township II

Page 1240 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Total qty of G2 36.20

36.20 8.00 289.60

House B6 - G1 (Formwork for Footings) Sqmt.

2 4 1.200 0.230 2.21

2 4 1.200 0.230 2.21C2 2 4 1.350 0.230 2.48

2 4 1.350 0.230 2.48C3 2 1 1.350 0.230 0.62

2 1 1.350 0.230 0.62C4 2 5 1.600 0.300 4.80

2 5 1.600 0.300 4.80C5 2 2 1.350 0.230 1.24

2 2 2.000 0.230 1.84C9A 2 1 1.200 0.230 0.55

2 1 1.200 0.230 0.55Total qty of G5 24.40

24.40 8.00 195.20

G5

C1 4 2 0.200 1.260 2.024 2 0.400 1.260 4.03

C2 4 2 0.300 1.210 2.904 2 0.300 1.210 2.90

C3 1 2 0.200 1.210 0.481 2 0.400 1.210 0.97

C4 5 2 0.300 1.110 3.33

B10 Type G3, G6, G7, G10, G11, G14 & G15 is same is G2

C1

B10 Type G4, G5, G8, G9, G12, G13 & G16 is same to G1

B10-Shuttering for pedestal up to Plinth beam bottom P.L. 4.60 Mt.

Page 1241: Triangle Construction 4th R.a. Bill for Township II

Page 1241 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

5 2 0.300 1.110 3.33C5 2 2 0.300 1.110 1.33

2 2 0.900 1.110 4.00C9A 1 2 0.200 1.260 0.50

1 2 0.400 1.260 1.01Total qty of G5 26.80

26.80 4.00 107.20G6

C1A 1 2 0.200 1.260 0.501 2 0.400 1.260 1.01

C6 4 2 0.300 1.010 2.424 2 0.300 1.010 2.42

C6A 2 2 0.300 1.010 1.212 2 0.300 1.010 1.21

C7 4 2 0.300 1.110 2.664 2 0.300 1.110 2.66

C7A 2 2 0.300 1.110 1.332 2 0.300 1.110 1.33

C8 4 2 0.200 1.160 1.864 2 0.400 1.160 3.71

C9 4 2 0.200 1.260 2.024 2 0.400 1.260 4.03

C9A 1 2 0.200 1.260 0.501 2 0.400 1.260 1.01

C10 1 2 0.200 1.160 0.461 2 1.400 1.160 3.25

C11 1 2 0.200 1.260 0.501 2 0.400 1.260 1.01

B10 Type G8, G9 & G12 is same to G5

Page 1242: Triangle Construction 4th R.a. Bill for Township II

Page 1242 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Total qty of G6 35.10

35.10 4.00 140.40

G1

C1 4 2 0.200 1.360 2.184 2 0.400 1.360 4.35

C2 4 2 0.300 1.310 3.144 2 0.300 1.310 3.14

C3 1 2 0.200 1.310 0.521 2 0.400 1.310 1.05

C4 5 2 0.300 1.210 3.635 2 0.300 1.210 3.63

C5 2 2 0.300 1.210 1.452 2 0.900 1.210 4.36

C9A 1 2 0.200 1.360 0.541 2 0.400 1.360 1.09

Total qty of G1 29.08

29.08 4.00 116.32G2

C1A 1 2 0.200 1.260 0.501 2 0.400 1.260 1.01

C6 4 2 0.300 1.010 2.424 2 0.300 1.010 2.42

C6A 2 2 0.300 1.010 1.212 2 0.300 1.010 1.21

C7 4 2 0.300 1.110 2.664 2 0.300 1.110 2.66

B10 Type G7, G10 & G11 is same is G6

B10-Shuttering for pedestal up to Plinth beam bottom P.L. 4.70 Mt.

B10 Type G4, G13 & G16 is same to G1

Page 1243: Triangle Construction 4th R.a. Bill for Township II

Page 1243 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

C7A 2 2 0.300 1.110 1.332 2 0.300 1.110 1.33

C8 4 2 0.200 1.160 1.864 2 0.400 1.160 3.71

C9 4 2 0.200 1.260 2.024 2 0.400 1.260 4.03

C9A 1 2 0.200 1.260 0.501 2 0.400 1.260 1.01

C10 1 2 0.200 1.160 0.461 2 1.400 1.160 3.25

C11 1 2 0.200 1.260 0.501 2 0.400 1.260 1.01

Total qty of G2 35.10

35.10 4.00 140.40Shuttering for Plinth Beam G1

TB1 2 2 1.800 0.600 4.32TB2 2 2 2.200 0.300 2.64Bottom 2 1 2.200 0.200 0.88TB3 2 2 4.000 0.600 9.60TB4A 1 2 1.450 0.600 1.74

1 2 1.350 0.600 1.62TB4B 2 2 3.100 0.600 7.44TB5A 2 1 3.900 0.600 4.68TB5B 1 1 1.000 0.600 0.60

1 1 1.400 0.600 0.84TB8 1 2 4.000 0.600 4.80

1 2 4.600 0.600 5.52TB13 2 1 4.000 0.600 4.80

B10 Type G3, G14 & G15 is same is G2

Page 1244: Triangle Construction 4th R.a. Bill for Township II

Page 1244 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

TB14 1 1 4.000 0.600 2.40

1 1 4.200 0.600 2.52TB18A 2 1 1.000 0.600 1.20TB18B 1 1 4.050 0.600 2.43

1 1 4.350 0.600 2.61TB19A 1 1 1.700 0.600 1.02

1 1 1.500 0.600 0.90TB19B 2 1 4.900 0.600 5.88TB20A 2 4 2.700 0.600 12.96TB20B 1 4 0.400 0.600 0.96

1 4 0.200 0.600 0.48TB21 2 2 2.900 0.600 6.96TB22 2 2 2.900 0.600 6.96TB25 2 1 5.000 0.600 6.00TB26 2 2 5.000 0.600 12.00

1 1 5.000 0.600 3.00

1 1 5.600 0.600 3.36Shuttering for column with Plinth beam G1

C1 2 4 0.200 0.600 0.962 4 0.400 0.600 1.92

C2 2 4 0.300 0.600 1.442 4 0.300 0.600 1.44

C3 2 1 0.200 0.600 0.242 1 0.400 0.600 0.48

C4 2 5 0.300 0.600 1.802 5 0.300 0.600 1.80

C5 2 2 0.300 0.600 0.722 2 0.900 0.600 2.16

Page 1245: Triangle Construction 4th R.a. Bill for Township II

Page 1245 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

C9A 2 1 0.200 0.600 0.242 1 0.400 0.600 0.48

Total qty of G1 134.80

134.80 8.00 1078.40Shuttering for Plinth beam G2

TB1 2 2 1.800 0.600 4.32TB2 2 2 2.200 0.300 2.64Bottom 2 1 2.200 0.200 0.88TB3 2 2 4.000 0.600 9.60TB5A 1 2 4.000 0.600 4.80TB5A 1 2 3.900 0.600 4.68TB5B 1 1 1.400 0.600 0.84

1 1 1.100 0.600 0.66TB5B 1 2 1.300 0.600 1.56TB6A 1 2 0.900 0.600 1.08TB6B 1 1 2.400 0.600 1.44

1 1 2.700 0.600 1.62TB7A 2 2 3.700 0.600 8.88TB7B 1 2 2.800 0.600 3.36TB8 2 1 4.600 0.600 5.52

2 1 4.000 0.600 4.80TB10A 1 2 3.150 0.600 3.78TB10B 0.5 2 2.800 0.600 1.68TB11 1 2 2.600 0.600 3.12TB12 1 2 2.600 0.300 1.56TB14 1 1 4.000 0.600 2.40

1 1 4.200 0.600 2.52

B10 Type G4, G5, G8, G9, G12,G16, & G13 is same to G1

Page 1246: Triangle Construction 4th R.a. Bill for Township II

Page 1246 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

TB15A 1 2 1.535 0.600 1.84TB15B 1 2 3.765 0.600 4.52TB16 1 2 3.765 0.600 4.52TB19A 1 1 1.800 0.600 1.08

1 1 1.600 0.600 0.96TB19B 1 2 5.000 0.600 6.00TB20A 4 2 2.700 0.600 12.96TB20B 4 1 0.400 0.600 0.96

4 1 0.200 0.600 0.48TB21 2 2 2.900 0.600 6.96TB22 2 2 2.900 0.600 6.96TB23A 1 1 1.400 0.600 0.84

1 1 1.200 0.600 0.72TB23B 1 2 1.800 0.600 2.16TB23C 1 2 1.800 0.600 2.16TB24A 1 2 2.300 0.600 2.76TB24B 1 2 2.300 0.600 2.76TB14 0.5 1 2.600 0.600 0.78

0.5 1 2.200 0.600 0.66Shuttering for Column with Plinth beam-G2

C1A 1 2 0.200 0.600 0.241 2 0.400 0.600 0.48

C6 4 2 0.300 0.600 1.444 2 0.300 0.600 1.44

C6A 2 2 0.300 0.600 0.722 2 0.300 0.600 0.72

C7 4 2 0.300 0.600 1.44

Page 1247: Triangle Construction 4th R.a. Bill for Township II

Page 1247 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

4 2 0.300 0.600 1.44C7A 2 2 0.300 0.600 0.72

2 2 0.300 0.600 0.72C8 4 2 0.200 0.600 0.96

4 2 0.400 0.600 1.92C9 4 2 0.200 0.600 0.96

4 2 0.400 0.600 1.92C9A 1 2 0.200 0.600 0.24

1 2 0.400 0.600 0.48C10 1 2 0.200 0.600 0.24

1 2 1.400 0.600 1.68

C11 1 2 0.200 0.600 0.241 2 0.400 0.600 0.48

Total qty of G2 150.30

150.30 8.00 1202.40Shuttering for column up toLintel level G5

C1 4 2 0.200 2.165 3.464 2 0.400 2.165 6.93

C2 4 2 0.300 2.165 5.204 2 0.300 2.165 5.20

C3 1 2 0.200 2.165 0.871 2 0.400 2.165 1.73

C4 5 2 0.300 2.165 6.505 2 0.300 2.165 6.50

C5 2 2 0.300 2.165 2.602 2 0.900 2.165 7.79

Total qty of G5 46.78

B10 Type G3, G6, G7, G10, G11,G15 & G14 is same is G2

Page 1248: Triangle Construction 4th R.a. Bill for Township II

Page 1248 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

46.78 8.00 374.24Shuttering for column up to Lintel level G6

C1A 1 2 0.200 2.165 0.871 2 0.400 2.165 1.73

C6 4 2 0.300 2.165 5.204 2 0.300 2.165 5.20

C6A 2 2 0.300 2.165 2.602 2 0.300 2.165 2.60

C7 4 2 0.300 2.165 5.204 2 0.300 2.165 5.20

C7A 2 2 0.300 2.165 2.602 2 0.300 2.165 2.60

C8 4 2 0.200 2.165 3.464 2 0.400 2.165 6.93

C9 3 2 0.200 1.010 1.213 2 0.400 1.010 2.42

C9 1 2 0.200 2.165 0.871 2 0.400 2.165 1.73

C10 1 2 0.200 2.165 0.871 2 1.400 2.165 6.06

C11 1 2 0.200 2.165 0.871 2 0.400 2.165 1.73

Total qty of G6 59.95

59.95 8.00 479.60

Shuttering for Ground floor Slab - G6

B10 Type G1, G4, G8, G9, G12, G13 & G16 is same to G5

B10 Type G2, G3, G7, G10, G11, G14 & G15 is same is G6

Page 1249: Triangle Construction 4th R.a. Bill for Township II

Page 1249 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

For slabBed room-1 1 1 4.000 3.300 13.20Bed room-2 1 1 4.000 3.600 14.40Living Room 1 1 4.000 5.000 20.00Dinning 1 1 4.600 4.200 19.32Offset 1 1 0.450 5.000 2.25Toilet 1 & 2 2 1 2.200 1.500 6.60Kitchen/Study 1 1 3.150 5.000 15.75Utility/Toilet 03 1 1 1.400 5.100 7.14For slab beam

B1 2 2 1.800 0.450 3.24B2 2 1 2.200 0.325 1.43

2 1 2.200 0.400 1.76B2 - Duct 1 1 1.400 0.450 0.63

B3 2 1 4.000 0.325 2.602 1 2.100 0.325 1.372 1 1.900 0.450 1.71

B4A 2 1 3.700 0.450 3.332 1 3.700 0.325 2.41

B4B 2 1 1.400 0.450 1.262 1 1.400 0.325 0.91

B5 2 1 4.600 0.275 2.532 1 4.000 0.325 2.60

B6A 1 1 4.000 0.450 1.801 1 4.000 0.275 1.10

B6A 1 1 3.900 0.450 1.761 1 3.900 0.275 1.07

B6B 1 1 1.400 0.450 0.63

Page 1250: Triangle Construction 4th R.a. Bill for Township II

Page 1250 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

1 1 1.400 0.325 0.46B8A 1 2 3.150 0.325 2.05B8B 1 2 1.400 0.325 0.91B9A 1 1 1.400 0.450 0.63

1 1 1.200 0.450 0.54B9B/9C 2 2 1.800 0.325 2.34

B11A/11B 2 2 2.300 0.325 2.99B12A 2 1 2.900 0.450 2.61

2 1 1.200 0.450 1.082 1 1.500 0.325 0.98

B12B 1 1 2.700 0.450 1.221 1 2.700 0.325 0.88

B12B 1 1 3.000 0.450 1.351 1 3.000 0.325 0.98

B12C 2 1 0.400 0.325 0.262 1 0.200 0.325 0.13

B13 2 1 2.900 0.450 2.61B14A 1 1 2.700 0.450 1.22

1 1 2.700 0.325 0.88B14A 1 1 3.000 0.450 1.35

1 1 3.000 0.325 0.98B14B 2 1 0.200 0.325 0.13

2 1 0.400 0.325 0.26B15 1 1 5.000 0.275 1.38

1 1 5.000 0.450 2.25B16 1 1 5.000 0.275 1.38

1 1 5.000 0.450 2.25B21 1 2 1.200 0.450 1.08

Page 1251: Triangle Construction 4th R.a. Bill for Township II

Page 1251 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

For Column Lintel to slab

C6 4 2 0.300 0.750 1.804 2 0.300 0.750 1.80

C6A 2 2 0.300 0.750 0.902 2 0.300 0.750 0.90

C7 4 2 0.300 0.750 1.804 2 0.300 0.750 1.80

C7A 2 2 0.300 0.750 0.902 2 0.300 0.750 0.90

C8 4 2 0.200 0.750 1.204 2 0.400 0.750 2.40

C10 1 2 0.200 0.750 0.301 2 1.400 0.750 2.10

C11 1 2 0.200 0.750 0.301 2 0.400 0.750 0.60

For Column with slab

C6 4 2 0.300 0.450 1.084 2 0.300 0.450 1.08

C6A 2 2 0.300 0.450 0.542 2 0.300 0.450 0.54

C7 4 2 0.300 0.450 1.084 2 0.300 0.450 1.08

C7A 2 2 0.300 0.450 0.542 2 0.300 0.450 0.54

C8 4 2 0.200 0.450 0.724 2 0.400 0.450 1.44

C10 1 2 0.200 0.450 0.181 2 1.400 0.450 1.26

Page 1252: Triangle Construction 4th R.a. Bill for Township II

Page 1252 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

C11 1 2 0.200 0.450 0.181 2 0.400 0.450 0.36

Total qty of G6 194.30

194.30 6.00 1165.80Staircase B6-G6 - 1st Flight

Steps 10 1 1.200 0.159 1.911st Step 1 2 0.275 0.159 0.09

West slab 1 2 3.180 0.150 0.95West slab Bottom 1 1 2.880 1.200 3.46

Landing 1 1 1.340 2.600 3.4810 0.5 0.275 0.159 0.22

West slab 1 2 3.210 0.150 0.96West slab Bottom 1 1 2.910 1.000 2.91

Landing Bottom 1 1 1.400 1.540 2.16Side 1 2 1.534 0.150 0.46

LB1A 1 2 1.535 0.150 0.46LB1B 1 2 3.765 0.200 1.51

LB2 1 1 2.600 0.450 1.171 1 2.600 0.239 0.62

LB3 1 2 4.745 0.450 4.27LB4A 1 2 1.535 0.200 0.61LB4B 1 2 4.745 0.200 1.90B22 1 2 1.200 0.150 0.36

Column C9 3 2 0.200 0.450 0.543 2 0.400 0.450 1.08

Column 1A 1 2 0.200 0.190 0.081 2 0.400 0.190 0.15

B10 Type G2, G3, G7, G10 & G11 is same is G6

2nd Flight Steps

Page 1253: Triangle Construction 4th R.a. Bill for Township II

Page 1253 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Column C9 1 2 0.200 0.900 0.361 2 0.400 0.900 0.72

Total qty of G6 30.43

30.43 6.00 182.58B10 Type G6 Slab Beam Bottom

For slab beam

B1 2 1 1.800 0.20 0.72B2 2 1 2.200 0.20 0.88

B2 - Duct 1 1 1.400 0.20 0.28B3 2 1 4.000 0.20 1.60

B4A 2 1 3.700 0.30 2.22B4B 2 1 1.400 0.30 0.84

B5 2 1 4.600 0.20 1.84B6A 1 1 4.000 0.30 1.20B6A 1 1 3.900 0.30 1.17B6B 1 1 1.400 0.30 0.42B8A 1 2 3.150 0.20 1.26B8B 1 2 1.400 0.20 0.56B9A 1 1 1.400 0.20 0.28

B9B/9C 2 2 1.800 0.20 1.44B11A/11B 2 2 2.300 0.20 1.84

B12A 2 1 2.900 0.20 1.16B12B 2 1 2.700 0.30 1.62B12B 2 1 3.000 0.30 1.80B12C 2 2 0.400 0.30 0.48

B13 2 1 2.900 0.20 1.16B14A 1 1 2.700 0.30 0.81

B10 Type G2, G3, G7, G10 & G11 is same is G6

Page 1254: Triangle Construction 4th R.a. Bill for Township II

Page 1254 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

B14A 1 1 3.000 0.30 0.90B14B 2 1 0.200 0.30 0.12

B15 1 1 5.000 0.20 1.00B16 1 1 5.000 0.20 1.00B21 1 2 1.200 0.20 0.48

Total qty of G6 27.08

27.08 2.00 54.16

RCC for Ground floor Slab - G8Grid H-L / 14A-12A 2 1 4.350 2.310 20.10Grid H-C / 14A-12A 2 1 4.650 2.310 21.48Grid K-A / 13A-16A 2 1 6.700 2.760 36.98Grid K-E / 13A-12A 2 1 1.000 2.760 2.00Flat Slab at Kitchen/Study 1 1 3.800 5.000 3.80Utility/Toilet 03 1 1 3.550 5.000 17.75For slab beam

Grid 14A-12A / L-K ( B19/ 18C ) 2 1 2.750 0.450 2.482 1 2.750 0.315 1.73

Projection 2 1 2.850 0.150 0.86Grid 14A-12A / E-C ( B19/ 18A ) 2 1 3.050 0.450 2.75

2 1 3.050 0.315 1.92Projection 2 1 3.150 0.150 0.95

K / 15A-14A ( B7A-B7B ) 1 1 5.100 0.450 2.301 1 5.100 0.315 1.61

Projection 1 1 5.250 0.150 0.79E / 15A-14A ( B7A-B7B ) 1 1 5.200 0.450 2.34

1 1 5.200 0.315 1.64Projection 1 1 5.250 0.150 0.79

B18B 1 2 5.000 0.450 4.50

B10 Type G7 is same is G6

Page 1255: Triangle Construction 4th R.a. Bill for Township II

Page 1255 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

B3A 2 2 4.000 0.450 7.20B20 1 2 5.600 0.450 5.04

UB20 1 2 2.910 0.335 1.951 2 2.910 0.200 1.16

UB3 2 2 2.310 0.335 3.102 2 2.310 0.200 1.85

UB18 1 2 2.760 0.335 1.851 2 2.760 0.200 1.10

B6B 2 1 3.550 0.450 3.202 1 3.550 0.325 2.31

B6C 2 1 3.100 0.450 2.792 1 3.100 0.325 2.02

B17 1 1 5.000 0.450 2.251 1 5.000 0.325 1.63

For Column with slab

C1 4 2 0.200 0.500 0.804 2 0.400 0.500 1.60

C2 4 4 0.300 1.200 5.76C3 1 2 0.200 1.200 0.48

1 2 0.400 1.200 0.96C4 5 4 0.300 1.200 7.20C5 2 2 0.300 1.200 1.44

2 2 0.900 1.200 4.32Total qty of G8 186.78

186.78 7.00 1307.49

C6 4 2 0.300 2.165 5.20

B10 Type G1, G4, G5, G9, G13 & G12 is same is G8

Shuttering for column Above First floor up to Lintel level F3

Page 1256: Triangle Construction 4th R.a. Bill for Township II

Page 1256 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

4 2 0.300 2.165 5.20C6A 2 2 0.300 2.165 2.60

2 2 0.300 2.165 2.60C7 4 2 0.300 2.165 5.20

4 2 0.300 2.165 5.20C7A 2 2 0.300 2.165 2.60

2 2 0.300 2.165 2.60C8 4 2 0.200 2.165 3.46

4 2 0.400 2.165 6.93Total Qty of F3 41.59

F1, F2, F4, F5 & F6 same as F3 41.59 6.00 249.54Shuttering for Lintel G5

Grid K & 15 to 16 L1 1 1 1.200 0.200 0.24

1 1 1.200 0.100 0.12Grid 16 & E to KL10 1 1 5.100 0.200 1.02

1 1 5.100 0.100 0.51Bottom 1 1 2.700 0.200 0.54Grid 15 & E to K L5 1 1 4.900 0.200 0.98

1 1 4.900 0.100 0.49Bottom 1 1 1.000 0.200 0.20Grid E & 15 to 16 L3 1 1 1.200 0.400 0.48

1 1 1.200 0.300 0.36Bottom 1 1 1.200 0.30 0.36Ent. Down slab 1 1 5.000 1.20 6.00Grid 15 & E to D L5 1 1 1.750 0.200 0.35

1 1 1.750 0.100 0.18Grid D to C & 14 to 15 L4 1 1 4.000 0.200 0.80

1 1 4.000 0.100 0.40

Page 1257: Triangle Construction 4th R.a. Bill for Township II

Page 1257 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Bottom 1 1 4.000 0.30 1.20Grid E & 14 to 15 L3 1 1 4.000 0.400 1.60

1 1 4.000 0.300 1.20

Ver. Down slab 1 1 1.450 4.000 5.80

Grid 13 & A to C , L to N L11 4 1 2.900 0.400 4.644 1 2.900 0.300 3.48

Grid B,M & 12 to 13 L11 2 1 2.200 0.400 1.762 1 2.200 0.300 1.32

Grid A, N & 12 to 13 L11A 2 2 1.800 0.200 1.44

Grid C, L & 12 to 14 L12 2 1 4.000 0.400 3.202 1 4.000 0.300 2.40

Toilet 1 & 2 Down slab 2 1 2.200 1.800 1.800 7.92

Grid 12, 14 & C to E L1 2 2 3.000 0.200 2.40

Chhaja 2 1 1.125 0.600 1.352 2 0.600 0.113 0.27

Grid E, K & 10 to 12 ( L7+ L1 ) 2 2 3.100 0.200 2.48

Chhaja 2 1 1.125 0.600 1.352 2 0.600 0.113 0.27

Grid 10 & E to KL6 2 2 1.350 0.200 1.08

Grid 9 & E to KL6 1 2 1.050 0.200 0.42

Grid 12, 14 & K to L L1 2 2 2.700 0.200 2.16

2 1 1.125 0.600 1.35

2 2 0.600 0.113 0.27

Grid K 14 to 15 L1 1 2 3.900 0.200 1.56

1 1 1.125 0.600 0.67

1 2 0.600 0.113 0.14

Grid K & 9 to 10 L8 1 2 1.550 0.200 0.62

1 1 1.550 0.600 0.93

Chhaja

Chhaja

Chhaja

Page 1258: Triangle Construction 4th R.a. Bill for Township II

Page 1258 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Grid C, I & 12 to 14 L15 2 2 4.300 0.400 6.88

1 2 4.300 0.625 5.38

Grid 12 & E to K L9 1 2 5.000 0.400 4.00

1 1 5.000 0.600 3.00

Opening bottom

D2 1 4 0.900 0.200 0.72

D3 1 4 0.750 0.200 0.60

D4 1 1 1.800 0.300 0.54

GD1 1 1 1.000 0.300 0.30

W1 1 5 1.125 0.300 1.69

W2 1 2 1.125 0.300 0.67

W3 1 1 0.900 0.300 0.27

W4 1 2 0.900 0.200 0.36

W5 1 2 0.450 0.200 0.18

W7 1 1 0.450 0.200 0.09

FG1 1 2 1.125 0.300 0.67Total qty of G5 Sq.Mt. 91.66

91.66 7.00 641.63Shuttering for Lintel G10

Grid k & 7 to 8 L1 1 1 1.400 0.200 0.28

1 1 1.400 0.100 0.14Grid 7 and 8 & K to H L5 2 1 2.500 0.200 1.00

2 1 2.500 0.100 0.50Bottom 1 1 1.200 0.200 0.24

1 1 1.000 0.200 0.20Grid 7 to 8 and K to H L5 1 1 1.600 0.200 0.32

1 1 1.600 0.100 0.16

Chhaja

Chhaja

B10 Type G1, G4, G8, G9, G12 & G13 is same to G5

Page 1259: Triangle Construction 4th R.a. Bill for Township II

Page 1259 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Entrance Down slab 1 1 1.200 2.05 2.46Grid 7 & D to G L5 1 1 1.750 0.200 0.35

1 1 1.750 0.100 0.18Bottom 1 1 1.250 0.200 0.25Grid D & 6 to 7 L4 1 1 4.000 0.200 0.80

1 1 4.000 0.100 0.40Bottom 1 1 4.000 0.300 0.00Grid E & 6 to 7 L3 1 1 4.000 0.400 0.00

1 1 4.000 0.300 1.20Grid 6 & C to G L1 1 1 3.000 0.200 0.60

1 1 3.000 0.100 0.30

Chajja 1 1 1.200 0.600 0.72

Ver. Down slab 1 1 1.450 4.000 5.80

Toilet 2 L6 2 2 1.050 0.200 0.84

Toilet 2 L6 2 2 1.250 0.200 1.00

Grid 4 & C to G L1 1 2 3.000 0.200 1.20

Chhaja 1 1 1.125 0.600 0.671 2 0.600 0.113 0.14

Grid E & 2 to 4 L1 / L7 1 2 3.700 0.200 1.48

Grid K & 2 to 4 L1 / L7 1 2 3.700 0.200 1.48

Chhaja 2 1 1.125 0.600 1.352 2 0.600 0.113 0.27

Grid G & 4 to 6 L2 2 2 4.300 0.400 6.88

Chhaja 2 1 4.300 0.625 5.38

Grid 4 & E to K L9 1 2 5.000 0.400 4.00

Chhaja 1 1 5.000 0.600 3.00

Grid 4, 5 & K to L L1 2 2 2.700 0.200 2.16

2 1 1.125 0.600 1.35Chhaja

Page 1260: Triangle Construction 4th R.a. Bill for Township II

Page 1260 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

2 2 0.600 0.113 0.27

Grid K & 6 to 7 L1 1 2 3.900 0.200 1.56

1 1 1.125 0.600 0.67

1 2 0.600 0.113 0.14

Grid K 1 to 2 L13 1 2 1.600 0.200 0.64

1 1 1.600 0.600 0.96

Grid E & 1 to 2 L7 1 2 0.900 0.200 0.36

Toilet 3 & Utility L6 2 2 1.350 0.200 1.08

Opening bottom

D2 1 4 0.900 0.200 0.72

D3 1 4 0.750 0.200 0.60

D4 1 1 1.800 0.300 0.54

GD1 1 1 1.000 0.300 0.30

W1 1 5 1.125 0.300 1.69

W2 1 2 1.125 0.300 0.67

W3 1 1 0.900 0.300 0.27

W4 1 2 0.900 0.200 0.36

W5 1 2 0.450 0.200 0.18

W6 1 1 0.600 0.300 0.18

FG1 1 2 1.125 0.300 0.67Total qty of G10 Sq.Mt. 58.96

58.96 6.00 353.77Shuttering for Lintel F3

L5 (Grid 8 & K to E ) 1 1 5.000 0.200 1.00

1 1 5.000 0.100 0.50L5 ( Grid 7 & K to E ) 1 1 5.000 0.200 1.00

1 1 5.000 0.100 0.50L1( Grid E & 6 to 7 ) 1 2 3.900 0.200 1.56

Chhaja

Chhaja

B10 Type G2, G3, G6, G7 & G11 is same to G10

Page 1261: Triangle Construction 4th R.a. Bill for Township II

Page 1261 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

L1 ( Grid E & 6 to 8 ) 2 1 5.300 0.200 2.12L3 ( Grid K & 7 to 8 ) 1 1 1.400 0.200 0.28

1 1 1.400 0.100 0.14Down slab at Entrance 1 1 5.000 1.200 6.00L7A ( Grid N & 4 to 5 ) 2 1 1.800 0.200 0.72L7 ( Grid M & 4 to 5 ) 1 1 2.200 0.400 0.88

1 1 2.200 0.300 0.66L7 ( Grid 4 & N to L ) 1 1 2.900 0.400 1.16

1 1 2.900 0.300 0.87L7 ( Grid 5 & N to L ) 1 1 2.900 0.400 1.16

1 1 2.900 0.300 0.87Toilet 2 Down Slab 1 1 2.200 1.800 3.96

L8 ( Grid L & 4 to 6 ) 1 1 4.000 0.400 1.601 1 4.000 0.300 1.20

L2 ( Grid j & 4 to 6 ) 1 1 4.300 0.400 1.721 1 4.300 0.300 1.29

L1 ( Grid 4 & L to K ) 2 1 3.000 0.200 1.20

L1 ( Grid 6 & L to J ) 2 1 3.450 0.300 2.07

Chajja at Bed Room 2 1 1 4.300 0.625 2.69L7A ( Grid A & 4 to 5 ) 2 1 1.800 0.200 0.72L7 ( Grid B & 4 to 5 ) 1 1 2.200 0.400 0.88

1 1 2.200 0.300 0.66L7 ( Grid 4 & A to C ) 1 1 2.900 0.400 1.16

1 1 2.900 0.300 0.87L7 ( Grid 5 & A to C ) 1 1 2.900 0.400 1.16

1 1 2.900 0.300 0.87Toilet 1 Down Slab 1 1 2.200 1.800 3.96

L8 ( Grid C & 4 to 6 ) 1 1 4.000 0.200 0.80

Page 1262: Triangle Construction 4th R.a. Bill for Township II

Page 1262 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

1 1 4.000 0.100 0.40

L2 ( Grid E & 4 to 6 ) 1 1 4.300 0.400 1.721 1 4.300 0.300 1.29

L1 ( Grid 4 & E to C ) 1 1 3.000 0.200 0.601 1 3.000 0.100 0.30

L1 ( Grid 6 & F to C ) 1 1 3.450 0.200 0.691 1 3.450 0.100 0.35

Chajja at Bed Room 1 1 1 4.300 0.625 2.69

L4 ( Grid 4 & I to J) 1 1 3.950 0.400 1.58

1 1 3.950 0.300 1.19

Chajja 1 1 5.600 0.600 3.36

L1 ( Grid K & 2 to 4 ) 2 1 3.550 0.200 1.42

L1 ( Grid E & 2 to 4 ) 2 1 3.550 0.200 1.42

8 1 1.125 0.600 5.40

Chhaja 18 1 0.600 0.113 1.22

Opening bottom

D2 1 4 0.900 0.200 0.72

D3 1 4 0.750 0.200 0.60

D4 1 1 1.800 0.300 0.54

W1 1 5 1.125 0.300 1.69

W2 1 2 1.125 0.300 0.67

W3 1 1 0.900 0.300 0.27

W4 1 2 0.900 0.200 0.36

W5 1 2 0.450 0.200 0.18

W6 1 1 0.600 0.300 0.18

FG1 1 2 1.125 0.300 0.67Total qty of F3 Sq.Mt. 75.73

75.73 4.00 302.93

Chhaja at L1

B10 Type F4,F5 & F6 is same to F3

Page 1263: Triangle Construction 4th R.a. Bill for Township II

Page 1263 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

RCC for Ground floor Slab - F3

For slabGrid H-L / 6A-4A 2 1 4.350 2.310 20.10Grid H-C / 6A-4A 2 1 4.650 2.310 21.48Grid K-A / 8A-5A 2 1 6.700 2.760 36.98Grid K-E / 5A-1 2 1 7.900 2.760 43.61For slab beam

Grid E / 8A to 6A ( B3A-3B ) 2 1 5.100 0.450 4.59Projection 2 1 5.100 0.150 1.53

Grid K / 8A to 6A ( B3A-3B ) 2 1 5.100 0.450 4.59Projection 2 1 5.100 0.150 1.53

Grid 8A / E to K ( B6 ) 2 1 5.600 0.450 5.04Grid L / 6A to 4A ( B1 ) 2 1 4.000 0.450 3.60Grid C / 6A to 4A ( B1 ) 2 1 4.000 0.450 3.60

Grid 6A / L to K ( B5 ) 2 1 2.700 0.450 2.43Projection 2 1 2.700 0.150 0.81

Grid 4A / L to K ( B5 ) 2 1 2.700 0.450 2.43Projection 2 1 2.700 0.150 0.81

Grid 6A / C to E ( B5 ) 2 1 3.000 0.450 2.70Projection 2 1 3.000 0.150 0.90

Grid 4A / C to E ( B5 ) 2 1 3.000 0.450 2.70Projection 2 1 3.000 0.150 0.90

Grid K / 4A to 1 ( B2A-2B ) 2 1 5.050 0.450 4.55Projection 2 1 5.050 0.150 1.52

Grid E / 4A to 1 ( B2A-2B ) 2 1 5.050 0.450 4.55Projection 2 1 5.050 0.150 1.52

UB6 2 2 2.910 0.335 3.90UB18 2 2 2.310 0.335 3.10

Page 1264: Triangle Construction 4th R.a. Bill for Township II

Page 1264 of 1288 RCC and Shuttering

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

For Column with slab

C1 4 2 0.200 0.200 0.324 2 0.400 0.200 0.64

C2 4 4 0.300 1.200 5.76C3 1 2 0.200 1.200 0.48

1 2 0.400 1.200 0.96C4 5 4 0.300 1.200 7.20C5 2 2 0.300 1.200 1.44

2 2 0.900 1.200 4.32Total qty of F3 Sq.Mt. 200.57

200.57 4.00 802.27Total Sq.Mt. 9183.93

Less Paid in 3rd R.A. Bill Item No.- 3.01a in Sq.Mt. 7887.92Net Balance Qut. In this Bill Sq.Mt. 1296.01

For TRIANGLE CONSTRUCTION

PROJECT MANAGER

B10 Type F4 is same to F3

Page 1265: Triangle Construction 4th R.a. Bill for Township II

Page 1265 of 1288 Block Masonry

TRIANGLE CONSTRUCTION

Measurement SheetProject Name: Township For CGPL at Mundra Running Bill No. 4thLocation: Mundra Period 23/07/2011 to 31/08/2011

Date of Submission 31/08/2011Name of Contractor: TRTIANGLE CONSTRUCTIONWork Order No.: 6300001044

Type B10

Description of Item Unit No. Length Breadth Depth Quantity

4.09

G5 block masonary up to Slab level - B10

Grid 16 & I to H Entrance 1 1 1.000 0.400 2.165 0.87Grid K & 14 to 15 Living Room 1 1 3.900 0.300 2.715 3.18Grid K & 15 to 16 at Entrance 1 1 1.400 0.300 2.715 1.14Grid E & 14 to 15 Lintel to slab at Living Room 1 1 4.000 0.300 0.550 0.66Grid E & 15 to 16 Lintel to slab at Entrance 1 1 1.400 0.300 0.550 0.23Grid 12 & K to L Bed Room 1 1 1 2.700 0.300 2.715 2.20Grid 14 & K to L Bed Room 1 1 1 2.700 0.300 2.715 2.20Grid 12 & K to I Bed Room 1 1 1 0.450 0.300 2.715 0.37Grid 14 & K to I Bed Room 1 1 1 0.450 0.300 2.715 0.37Grid 12 & C to E Bed Room 2 1 1 3.000 0.300 2.715 2.44Grid 14 & C to E Bed Room 2 1 1 3.000 0.300 2.715 2.44Grid 12 & E to G Bed Room 2 1 1 0.450 0.300 2.715 0.37Grid 14 & E to G Bed Room 2 1 1 0.450 0.300 2.715 0.37

1 1 1.760 0.300 0.53Grid E & 9 to 12 Study 1 1 4.200 0.300 2.715 3.42Grid K & 9 to 12 Kitchen 1 1 4.200 0.300 2.715 3.42

Doc. No. : TC/CGPL/11-12 /RA-4 Date: 31/08/2011

Name of Owner: M/s Coastal Gujarat Power Limited

Item No

Total Quantity

Providing and laying Solid cement concrete block masonry in cement mortar 1:5 (1 part cement and 5 part of sand) using factory made/precast (made out of 1:4:8 concrete), load bearing, approved quality,

a) For 300 mm thick wall

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=1.73mt., Height=1.02mt.

Page 1266: Triangle Construction 4th R.a. Bill for Township II

Page 1266 of 1288 Block Masonry

Ded for W1 -5 1 1.125 0.300 2.165 -3.65Ded for W2 -2 1 1.125 0.300 2.165 -1.46Ded for GD1 -1 1 1.100 0.300 2.165 -0.71Ded for FG1 -2 1 1.125 0.300 0.550 -0.37Total of G5 18.02

18.02 7.00 126.13G7 block masonary up to slab

Grid 8 Entrance 1 1 0.300 0.300 2.165 0.19Grid K & 6 to 7 Living Room 1 1 3.900 0.300 2.715 3.18Grid K & 7 to 8 at Entrance 1 1 1.400 0.300 2.715 1.14Grid E & 6 to 7 Lintel to slab at Living Room 1 1 4.000 0.300 0.550 0.66Grid E & 7 to 8 at Entrance 1 1 1.400 0.300 2.715 1.14Grid 4 & K to L Bed Room 1 1 1 2.700 0.300 2.715 2.20Grid 6 & K to L Bed Room 1 1 1 2.700 0.300 2.715 2.20Grid 4 & K to I Bed Room 1 1 1 0.450 0.300 2.715 0.37Grid 6 & K to I Bed Room 1 1 1 0.450 0.300 2.715 0.37Grid 4 & C to E Bed Room 2 1 1 3.000 0.300 2.715 2.44Grid 6 & C to E Bed Room 2 1 1 3.000 0.300 2.715 2.44Grid 4 & E to G Bed Room 2 1 1 0.450 0.300 2.715 0.37Grid 6 & E to G Bed Room 2 1 1 0.450 0.300 2.715 0.37Grid 4 & E to K Dining area 1 1 4.360 0.300 0.400 0.52Grid E & 1 to 2 Study 1 1 4.200 0.300 2.715 3.42Grid K & 1 to 2 Kitchen 1 1 4.200 0.300 2.715 3.42Ded for W1 -5 1 1.125 0.300 2.165 -3.65Ded for W2 -2 1 1.125 0.300 2.165 -1.46Ded for W6 -1 1 0.600 0.300 0.900 -0.16Ded for GD1 -1 1 1.100 0.300 2.165 -0.71Ded for FG1 -2 1 1.125 0.300 0.550 -0.37Total of G7 18.08G2, G3, G6, G10 & G11 of B10 same as G7 18.08 6.00 108.48F3 block masonary up to Slab level - B10

Grid E & 7 to 8 Entrance 1 1 1.400 0.300 2.715 1.14

G1, G4, G8, G9, G12 & G13 of B10 same as G5

Page 1267: Triangle Construction 4th R.a. Bill for Township II

Page 1267 of 1288 Block Masonry

Grid K & 6 to 7 Living Room 1 1 3.900 0.300 2.715 3.18Grid K & 7 to 8 at Entrance 1 1 1.400 0.300 2.715 1.14Grid E & 6 to 7 Lintel to slab at Living Room 1 1 4.000 0.300 0.550 0.66Grid E & 7 to 8 at Entrance 1 1 1.400 0.300 2.715 1.14Grid 4 & K to L Bed Room 1 1 1 2.700 0.300 2.715 2.20Grid 6 & K to L Bed Room 1 1 1 2.700 0.300 2.715 2.20Grid 4 & K to I Bed Room 1 1 1 0.450 0.300 2.715 0.37Grid 6 & K to I Bed Room 1 1 1 0.450 0.300 2.715 0.37Grid 4 & C to E Bed Room 2 1 1 3.000 0.300 2.715 2.44Grid 6 & C to E Bed Room 2 1 1 3.000 0.300 2.715 2.44Grid 4 & E to G Bed Room 2 1 1 0.450 0.300 2.715 0.37Grid 6 & E to G Bed Room 2 1 1 0.450 0.300 2.715 0.37Grid 4 & E to K Dining area 1 1 4.360 0.300 0.400 0.52Grid E & 1 to 2 Study 1 1 4.200 0.300 2.715 3.42Grid K & 1 to 2 Kitchen 1 1 4.200 0.300 2.715 3.42Ded for W1 -5 1 1.125 0.300 2.165 -3.65Ded for W2 -2 1 1.125 0.300 2.165 -1.46Ded for W6 -1 1 0.600 0.300 0.900 -0.16Ded for FG1 -2 1 1.125 0.300 0.550 -0.37Total of F3 19.74F4, F5 & GF6 of B10 same as F3 19.74 4.00 78.96G5 block masonary Compound wall

Foundation 600mm Wall

Grid 16 & A to E 1 1 6.450 0.600 0.200 0.77Grid A &13 to 16 1 1 6.700 0.600 0.200 0.80Grid L & 9 to 12 1 1 5.600 0.600 0.200 0.67Grid 9 & K to L 1 1 2.400 0.600 0.200 0.29Foundation 450mm Wall

Grid 16 & A to E 1 1 6.400 0.450 0.200 0.58Grid A &13 to 16 1 1 6.800 0.450 0.200 0.61Grid L & 9 to 12 1 1 5.550 0.450 0.200 0.50Grid 9 & K to L 1 1 2.500 0.450 0.200 0.23Foundation 300mm Wall

Page 1268: Triangle Construction 4th R.a. Bill for Township II

Page 1268 of 1288 Block Masonry

Grid 16 & A to E 1 1 6.500 0.300 1.175 2.29Grid A &13 to 16 1 1 6.900 0.300 1.175 2.43Grid L & 9 to 12 1 1 5.600 0.300 1.175 1.97Grid 9 & K to L 1 1 2.600 0.300 1.175 0.92

Total of G5 12.06G8 of B10 same as G5 12.06 2.00 24.12G6 block masonary Compound wall

Foundation 600mm Wall

Grid A & 5 to 8 1 1 6.900 0.600 0.200 0.83Grid 8 & A to E 1 1 6.450 0.600 0.200 0.77Grid L & 1 to 4 1 1 5.750 0.600 0.200 0.69Foundation 450mm Wall

1 1 6.850 0.450 0.200 0.621 1 6.500 0.450 0.200 0.591 1 5.750 0.450 0.200 0.52

Foundation 300mm Wall

1 1 6.950 0.300 0.200 0.421 1 6.550 0.300 0.200 0.391 1 5.750 0.300 0.200 0.35

Total of G6 5.18G7 of B10 same as G6 5.18 2.00 10.36

Total Cu.Mt. 348.05Less Paid in 3rd R.A. Bill Item No.- 4.09 a in Cu.Mt. 295.13

Net Balance Qut. In this Bill Cu.Mt. 52.92b) For 200 mm thick wall

G5 block masonary up to Slab level - B10 Smt.

Grid 16 & K to H Entrance 1 1 1.000 2.165 2.17Above Lintel 1 1 4.360 0.550 2.40

1 1 2.220 2.22Grid 15 & E to K Living Room 1 1 4.900 2.715 13.30

1 1 2.220 2.22Grid E & 14 to 15 Living Room 1 1 4.000 2.165 8.66

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=2.18mt., Height=1.02mt.

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=2.18mt., Height=1.02mt.

Page 1269: Triangle Construction 4th R.a. Bill for Township II

Page 1269 of 1288 Block Masonry

Grid 15 & E to B Verandah 1 1 1.600 2.165 3.46Grid 12 & A to C Toilet 2 1 1 2.900 2.365 6.86Grid13 & A to C Toilet 2 1 1 2.900 2.365 6.86Grid A & 12 to 13 Toilet 2 1 1 1.800 2.165 3.90Grid B & 12 to 13 Toilet 2 1 1 2.200 2.365 5.20Grid C & 12 to 14 Bed Room 2 1 1 4.000 2.715 10.86

1 1 1.760 1.76Grid G & 12 to 14 Bed Room 2 1 1 4.600 2.515 11.57

1 1 1.760 1.761 1 0.625 2.165 1.35

Grid 12 & L to N Toilet 1 1 1 2.900 2.365 6.86Grid13 & L to N Toilet 1 1 1 2.900 2.365 6.86Grid N & 12 to 13 Toilet 1 1 1 1.800 2.165 3.90Grid M & 12 to 13 Toilet 1 1 1 2.200 2.365 5.20Grid L& 12 to 14 Bed Room 1 1 1 4.000 2.715 10.86

1 1 1.760 1.76Grid I & 12 to 14 Bed Room 1 1 1 4.600 2.525 11.62

1 1 1.760 1.761 1 0.625 2.165 1.35

Grid E & 11 to 12 Dining 1 1 0.450 2.715 1.22Grid K & 11 to 12 Dining 1 1 0.450 2.715 1.22Grid 11 E to K Kitchen/ Studay 1 1 5.000 2.715 13.58Grid 10 & E to K Kitchen / Studay 1 1 5.000 2.715 13.58Grid H & 10 to 11 Kitchen / Studay 1 1 3.150 2.715 8.55Grid 9 & E to K Toilet 3 & Uitiley 1 1 5.300 2.715 14.39Grid 16 & G to E Enteerince 1 1 0.700 2.165 1.52Sill W1 5 1 1.125 0.500 2.81Sill W2 2 1 1.125 0.900 2.03Ded for W3 -1 1 0.900 1.600 -1.44Ded for W4 -2 1 0.800 1.200 -1.92

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=1.73mt., Height=1.02mt.

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=1.73mt., Height=1.02mt.

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=1.73mt., Height=1.02mt.

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=1.73mt., Height=1.02mt.

Page 1270: Triangle Construction 4th R.a. Bill for Township II

Page 1270 of 1288 Block Masonry

Ded for W7 -1 1 0.450 0.900 -0.41Ded for D2 -4 1 0.900 2.165 -7.79Ded for D3 -4 1 0.750 2.165 -6.50Ded for D4 -1 1 1.800 2.165 -3.90Total of G5 175.56G1, G4, G8, G9, G12 & G13 same as G5 175.56 7.00 1228.92G7 block masonary up to ground floor slab Smt.

Grid 8 & K to H Entrance 1 1 2.125 2.165 4.60Above Lintel 1 1 5.000 0.550 2.75Grid 7 & E to K Living Room 1 1 4.900 2.715 13.30Grid E & 6 to 7 Living Room 1 1 4.000 2.165 8.66Grid 7 & E to B Verandah 1 1 0.500 2.165 1.08Grid 4 & A to C Toilet 2 1 1 2.900 2.715 7.87Grid 5 & A to C Toilet 2 1 1 2.900 2.715 7.87Grid A & 4 to 5 Toilet 2 1 1 1.800 2.715 4.89Grid B & 4 to 5 Toilet 2 1 1 2.200 2.715 5.97Grid C & 4 to 6 Bed Room 2 1 1 4.600 2.715 12.49Grid G & 4 to 6 Bed Room 2 1 1 4.600 2.715 12.49

1 1 0.625 2.715 1.70Grid 4 & L to N Toilet 1 1 1 2.900 2.715 7.87Grid 5 & L to N Toilet 1 1 1 2.900 2.715 7.87Grid N & 4 to 5 Toilet 1 1 1 1.800 2.715 4.89Grid M & 4 to 5 Toilet 1 1 1 2.200 2.715 5.97Grid L& 4 to 6 Bed Room 1 1 1 4.600 2.715 12.49Grid I & 4 to 6 Bed Room 1 1 1 4.600 2.715 12.49

1 1 0.625 2.715 1.70Grid E & 2 to 3 Dining 1 1 0.450 2.715 1.22Grid K & 3 to 4 Dining 1 1 0.450 2.715 1.22Grid 3 E to K Kitchen/ Studay 1 1 5.000 2.715 13.58Grid 2 & E to K Kitchen / Studay 1 1 5.000 2.715 13.58Grid H & 2 to 3 Kitchen / Studay 1 1 3.150 2.715 8.55Grid 1 & E to K Toilet 3 & Uitiley 1 1 5.300 2.715 14.39Sill W1 5 1 1.125 0.500 2.81

Page 1271: Triangle Construction 4th R.a. Bill for Township II

Page 1271 of 1288 Block Masonry

Sill W2 2 1 1.125 0.900 2.03 Duct 1 1 1.200 2.965 3.56

1 1 1.600 2.965 4.74Ded for W3 -1 1 0.900 1.600 -1.44Ded for W4 -2 1 0.800 1.200 -1.92Ded for W7 -1 1 0.450 0.900 -0.41Ded for D2 -4 1 0.900 2.165 -7.79Ded for D3 -4 1 0.750 2.165 -6.50Ded for D4 -1 1 1.800 2.165 -3.90Total of G7 180.67G2, G3, G6, G10 & G11 same as G7 180.67 6.00 1084.02F3 block masonary up to ground floor slab Smt.

Entrance 1 1 3.250 2.165 7.041 1 2.600 2.165 5.63

Above Lintel 1 1 5.000 0.550 2.75

1 1 2.220 2.22Grid 7 & E to K Living Room above Lintel 1 1 4.900 0.550 2.70

1 1 2.220 2.22Grid E & 6 to 7 Living Room 1 1 4.000 2.165 8.66Grid 4 & A to C Toilet 2 1 1 2.900 2.715 7.87Grid 5 & A to C Toilet 2 1 1 2.900 2.715 7.87Grid A & 4 to 5 Toilet 2 1 1 1.800 2.715 4.89Grid B & 4 to 5 Toilet 2 1 1 2.200 2.715 5.97Grid C & 4 to 6 Bed Room 2 1 1 4.000 2.715 10.86

1 1 1.760 1.76Grid G & 4 to 6 Bed Room 2 1 1 4.600 2.715 12.49

1 1 1.760 1.761 1 0.625 2.715 1.70

Grid 4 & L to N Toilet 1 1 1 2.900 2.715 7.87Grid 5 & L to N Toilet 1 1 1 2.900 2.715 7.87

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=2.18mt., Height=1.02mt.

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=2.18mt., Height=1.02mt.

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=1.73mt., Height=1.02mt.

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=1.73mt., Height=1.02mt.

Page 1272: Triangle Construction 4th R.a. Bill for Township II

Page 1272 of 1288 Block Masonry

Grid N & 4 to 5 Toilet 1 1 1 1.800 2.715 4.89Grid M & 4 to 5 Toilet 1 1 1 2.200 2.715 5.97Grid L& 4 to 6 Bed Room 1 1 1 4.600 2.715 12.49

1 1 1.760 1.76Grid I & 4 to 6 Bed Room 1 1 1 4.600 2.715 12.49

1 1 1.760 1.761 1 0.625 2.715 1.70

Grid E & 2 to 3 Dining 1 1 0.450 2.715 1.22Grid K & 3 to 4 Dining 1 1 0.450 2.715 1.22Grid 3 E to K Kitchen/ Studay 1 1 5.000 2.715 13.58Grid 2 & E to K Kitchen / Studay 1 1 5.000 2.715 13.58Grid H & 2 to 3 Kitchen / Studay 1 1 2.450 2.715 6.65Sill W1 5 1 1.125 0.500 2.81Sill W2 2 1 1.125 0.900 2.03 Duct 1 1 1.200 2.965 3.56

1 1 1.600 2.965 4.74Ded for W3 -1 1 0.900 1.600 -1.44Ded for W4 -2 1 0.800 1.200 -1.92Ded for W7 -1 1 0.450 0.900 -0.41Ded for D2 -4 1 0.900 2.165 -7.79Ded for D3 -4 1 0.750 2.165 -6.50

Total of F3 174.52F4,F5 & F6 same as G7 174.52 4.00 698.08G6 block masonary for Stair Case

Grid 7A & N to L1 1 1 3.765 1.260 4.74Grid 7A & L1 to K 1 1 1.535 1.260 1.93Grid 8 & N to L1 1 1 3.765 1.260 4.74Grid 7 & M1 to L1 1 1 2.550 1.560 3.98Grid N & 7A to 8 1 1 2.600 1.000 2.60

Total of G6 17.99G2, G3, G7, G10 & G11 same as G6 17.99 6.00 107.94

Total Sq.Mt. 3118.96

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=1.73mt., Height=1.02mt.

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=1.73mt., Height=1.02mt.

Page 1273: Triangle Construction 4th R.a. Bill for Township II

Page 1273 of 1288 Block Masonry

Less Paid in 3rd R.A. Bill Item No.- 4.09 b in Sq.Mt. 2611.10Net Balance Qut. In this Bill Sq.Mt. 507.86

b) For 100 mm thick wallG5 block masonary up to lintel level Sq.Mt.Grid H & 10 to 11 Kitchen / Studay ( 150mm wall ) 1 1 3.150 2.165 6.82Grid H & 9 to 10 Toile 3 / Utiliy 1 1 1.350 2.165 2.92Bead room 1 & 2

2 1 1.760 3.522 1 4.000 0.600 4.80

Total of G5 18.06G1, G4, G8, G9 & G12 same as G5 18.06 6.00 108.36G6 block masonary up to lintel level

Grid H & 10 to 11 Kitchen / Studay ( 150mm wall ) 1 1 3.150 2.165 6.82Grid H & 9 to 10 Toile 3 / Utiliy 1 1 1.350 2.165 2.92Bead room 1 & 2 2 1 4.000 0.985 7.88

Total of G6 17.62G2, G3, G7, G10 & G11 same as G6 17.62 6.00 105.72

Total Sq.Mt. 214.08Less Paid in 3rd R.A. Bill Item No.- 4.09 c in Sq.Mt. 99.84

Net Balance Qut. In this Bill Sq.Mt. 114.24

For TRIANGLE CONSTRUCTION

PROJECT MANAGER

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=1.73mt., Height=1.02mt.

Page 1274: Triangle Construction 4th R.a. Bill for Township II

Page 1274 of 1288 Plastring

TRIANGLE CONSTRUCTION

Measurement SheetProject Name: Township For CGPL at Mundra Running Bill No. 4thLocation: Mundra Period 23/07/2011 to 31/08/2011

Date of Submission 31/08/2011Name of Contractor: TRTIANGLE CONSTRUCTIONWork Order No.: 6300001044

Type B10

Description of Item Unit No. Length Breadth Depth Quantity

7.04.a

B10 - G8 Outside wall Plaster Sqmt.Right side Building Entrance out side wall 1 1 5.60 3.950 22.12

1 1 3.034 3.03Top of beam 1 2 3.11 0.400 2.49

1 1 1.60 2.815 4.501 1 1.70 3.600 6.121 1 0.79 1.600 1.26

Projection O/s 1 1 3.10 0.300 0.93

Doc. No. : TC/CGPL/11-12 /RA-4 Date: 31/08/2011

Name of Owner: M/s Coastal Gujarat Power Limited

Item No

Total Quantity

Providing and laying average 18-20 mm. thick Sand face cement plaster on walls upto any height above ground level and for all shapes consisting of average 12-15 mm. thick backing coat of CM 1:6 (1 cement: 6 coarse sand) and average 6 mm. thick uniform grained textured finish coat using wooden Gutka, in CM 1:4 (1 cement: 4 sand), including scaffolding, forming grooves, drip moulds, pattas, hacking RCC surface, curing etc. complete (for all civil, plumbing & electrical works). (The rate shall be inclusive providing and fixing of chicken wire mesh having openings 20 mm. x 20 mm. of 22 gauge and 150mm wide at all vertical and horizontal junctions of RCC and masonry works as directed by EIC)

Area of Triangle = [ { ( base x perpendicular height)/2)x2}] Base=5.1mt., Height=1.19mt.

Page 1275: Triangle Construction 4th R.a. Bill for Township II

Page 1275 of 1288 Plastring

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Toilet 2 wall 1 1 3.10 3.215 9.97Bed Room 1 wall 1 1 3.00 3.600 10.80Projection O/s 1 1 2.80 0.300 0.84Toilet 1 wall 1 1 3.10 3.215 9.97Entrance in side wall 1 1 3.30 2.165 7.14

1 1 0.80 2.165 1.73Ver. Inside 1 2 1.60 2.165 6.93Fount side Building

1 1 2.445 2.451 1 4.60 0.735 3.381 1 2.00 3.215 6.43

Top of beam 1 2 2.68 0.400 2.14Toilet 2 wall 1 1 2.60 3.215 8.36Studay out side wall 1 1 5.50 3.300 18.15Passage + Staday above beam bottom 1 1 7.55 0.781 5.90

1 1 7.55 0.150 1.13Above Ver. 1 1 5.60 0.985 5.52Projection O/s 1 1 5.40 0.300 1.62Ver 1 1 0.20 2.615 0.52Ent. Columns 1 1 0.20 2.615 0.52Ent. Inside 1 1 0.40 2.165 0.87Ver. Inside 1 1 4.00 2.165 8.66

1 1 4.00 0.200 0.801 1 4.00 0.450 1.80

Back side Building

1 1 2.445 2.451 1 4.60 0.735 3.38

Top of beam 1 2 2.68 0.400 2.141 1 2.00 3.215 6.431 1 2.60 3.215 8.36

Living b/s wall 1 1 5.60 3.600 20.16Projection O/s 1 1 5.40 0.300 1.62Kitchen out side wall 1 1 5.50 3.300 18.15

1 1 7.55 0.750 5.66

Area of Triangle = [ { ( base x perpendicular height)/2)x2}] Base=4.11mt., Height=1.19mt.

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=4.11mt., Height=1.19mt.

Page 1276: Triangle Construction 4th R.a. Bill for Township II

Page 1276 of 1288 Plastring

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Passage + Kitchen above beam bottom 1 1 7.55 0.150 1.131 1 5.60 3.300 18.48

Left side Building Bed Room 1 wall 1 1 5.60 1.500 8.40Projection O/s 1 1 2.80 0.300 0.84Bed Room 2 wall 1 1 3.00 3.600 10.80Projection O/s 1 1 3.10 0.300 0.93

1 1 3.30 3.600 11.88Toilet 1 Wall 1 1 3.10 3.215 9.97Duct in side 2 2 2.20 3.215 28.29

2 2 0.90 3.215 11.57W1 -5 0.5 1.13 1.600 -4.50Jambs 5 2 0.30 1.600 4.80

5 2 0.30 1.200 3.60W2 -2 0.5 1.13 1.200 -1.35Jambs 2 2 0.30 1.200 1.44

2 2 0.30 1.200 1.44W5 -2 0.5 0.45 1.600 -0.72Jambs 2 2 0.20 1.600 1.28

2 2 0.20 0.450 0.36GD1 -1 0.5 1.10 2.100 -1.16Jambs 1 2 0.20 2.100 0.84

1 1 0.20 1.100 0.22FG1 -2 0.5 1.20 0.550 -0.66Jambs 2 2 0.30 1.200 1.44

2 2 0.30 0.550 0.66Enternce -1 1 2.70 2.100 -5.67W3 -1 0.5 0.90 1.600 -0.72Jambs 1 2 0.20 1.600 0.64

1 2 0.20 0.900 0.36D4 -1 0.5 1.80 2.100 -1.89Jambs 1 2 0.20 2.100 0.84

1 1 0.20 1.800 0.36W4 -2 1.0 0.90 1.200 -2.160Jambs 2 2.0 0.20 0.900 0.720

2 2.0 0.20 1.200 0.960

Page 1277: Triangle Construction 4th R.a. Bill for Township II

Page 1277 of 1288 Plastring

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Total Qty. G8 327.86G5, G9 & G12 same as G8 327.86 4 1311.4338B10 - G7 ( F4 ) Outside Wall Plaster Sqmt.Fount side Building

1 1 2.445 2.445Fournt side plaster 1 1 4.60 0.735 3.381Top of beam 1 2 2.68 0.400 2.144Bed Room 2 out side wall 1 1 2.00 6.450 12.900Toilet 2 wall 1 1 2.60 6.450 16.770Studay out side wall 1 1 3.80 6.450 24.510Above Ver. 1 1 5.40 0.450 2.430Projection O/s 1 1 5.40 0.300 1.620Duct wall 1 1 1.60 6.450 10.320Ver. Inside 1 1 4.00 2.165 8.660

1 1 4.00 0.450 1.8001 1 4.00 0.200 0.8001 1 0.20 2.815 0.563

Projection O/s 1 1 5.40 0.300 1.6201 1 5.60 4.150 23.2401 1 2.60 1.400 3.640

Back side Building

1 1 2.445 2.4451 1 4.60 0.735 3.3811 2 2.68 0.400 2.1441 1 2.000 6.450 12.9001 1 2.600 6.450 16.770

Kitchen out side wall 1 1 5.600 6.965 39.004Projection O/s 1 1 5.400 0.300 1.620

1 1 5.400 6.965 37.611Projection O/s 1 1 5.400 0.300 1.620Right side Building

1 1 3.034 3.034

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=4.11mt., Height=1.19mt.

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=4.11mt., Height=1.19mt.

Area of Triangle = [ { ( base x perpendicualr height)/2)x2}] Base=5.1mt., Height=1.19mt.

Page 1278: Triangle Construction 4th R.a. Bill for Township II

Page 1278 of 1288 Plastring

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

F4 Ent. 1 1 5.600 3.500 19.600inside wall 1 2 1.600 2.100 6.720GF 1 1 0.300 3.300 0.990

1 1 1.400 3.300 4.6201 1 2.770 3.300 9.1411 1 0.400 2.100 0.840

GF Ent. 1 1 2.525 3.300 8.3331 1 1.400 0.450 0.6301 2 0.200 2.100 0.8401 2 0.200 1.000 0.400

Bed Room 2 wall 1 1 3.300 4.150 13.6951 1 1.700 2.815 4.786

Projection O/s 1 1 3.100 0.300 0.930Toilet 2 wall 1 1 3.100 6.450 19.995Ver. Inside 1 1 1.600 2.100 3.360Columns side 1 1 1.200 2.100 2.520

1 1 1.100 0.200 0.2201 1 1.100 0.450 0.495

Bed Room 1 wall 1 1 3.000 6.965 20.895Projection O/s 1 1 2.800 0.300 0.840Toilet 1 1 3.100 6.450 19.995Left side Building G7 & G6 Center Bed Room 1 Wall 1 1 3.000 6.965 20.895Projection O/s 1 1 2.800 0.300 0.840Toilet 1 Wall 1 1 3.100 6.450 19.995Projection O/s 1 1 3.100 0.300 0.930Bed Room 2 wall 1 1 3.300 6.965 22.984Toilet 2 wall 1 1 3.100 6.450 19.995Duct in side 2 2 2.200 6.450 56.760

2 2 0.900 6.450 23.2201 1 1.200 6.450 7.7401 2 1.400 6.450 18.060

Less -1 1 1.800 2.100 -3.780W1 -11 1 1.125 1.600 -19.800Jambs 11 2 0.300 1.600 10.560

11 2 0.300 1.125 7.425

Page 1279: Triangle Construction 4th R.a. Bill for Township II

Page 1279 of 1288 Plastring

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

W2 -4 1 1.125 1.200 -5.400Jambs 4 2 0.300 1.125 2.700

4 2 0.300 1.200 2.880FG1 -4 1 1.125 0.550 -2.475Jambs 4 2 0.300 1.125 2.700

4 2 0.300 0.550 1.320W4 -4 1 0.900 1.200 -4.320Jambs 4 2 0.200 0.900 1.440

4 2 0.200 1.200 1.920Total Qty. G7 563.81

G6, F3, F4, G10 , F5, F6 & G11 same as G7 563.81 4.0 2255.2276Total Sq.Mt. 3566.66

Less Paid in 3rd R.A. Bill Item No.- 7.04 a in Sq.Mt. 1498.60Net Balance Qut. In this Bill Cu.Mt. 2068.06

For TRIANGLE CONSTRUCTION

PROJECT MANAGER

Page 1280: Triangle Construction 4th R.a. Bill for Township II

Page 1280 of 1288 Water supply

TRIANGLE CONSTRUCTION

Measurement SheetProject Name: Township For CGPL at Mundra Running Bill No. 4thLocation: Mundra Period

Date of Submission 31/08/2011Name of Contractor: TRTIANGLE CONSTRUCTIONWork Order No.: 6300001044

Type B10

Description of Item Unit No. Length Breadth Depth Quantity

Section:1 Water supply

1.01.a

8) 25 mm R.Mt.

G8 Water supply Line fitting

Toilet 1 & 2

Water Supply Line 2 1 1.700 3.40

2 1 0.550 1.10

2 1 0.600 1.20Toilet 3

Water Supply Line 1 1 0.900 0.901 1 0.300 0.301 1 0.950 0.951 1 0.570 0.571 1 0.850 0.851 1 0.650 0.65

Total of G5 9.92

9.92 10 99.20Less Paid in 3rd R.A. Bill Item No.- 1.01a 8 in R.Mt. 59.52

Net Balance Qut. In this Bill R.Mt. 39.68

Doc. No. : TC/CGPL/11-12 /RA-4 Date: 31/08/2011

23/07/2011 to 31/08/2011

Name of Owner: M/s Coastal Gujarat Power Limited

Item No

Total Quantity

Providing and fixing galvanized iron (GI) mild steel tube (Medium grade Class B) of Tata or equivalent approved make conforming to IS: 1239, including tube fittings of ‘R’ brand or equivalent approved make such as sockets, unions, reducers, long or short

G6, G7, G8, F3, F4, G9, G10, G11 & G12 same as G5

Page 1281: Triangle Construction 4th R.a. Bill for Township II

Page 1281 of 1288 Water supply

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

10) 15 mm. R.Mt.

Toilet 1 & 2

Hot Water Line 2 1 0.770 1.54

2 1 0.550 1.10

2 1 1.850 3.70

2 1 1.700 3.40

2 1 0.200 0.40Toilet 3

Hot Water Line 1 1 1.940 1.94

1 1 0.350 0.35

1 1 0.330 0.33

1 1 0.100 0.10

1 1 0.140 0.14

1 1 1.210 1.21

1 1 0.760 0.76

1 1 1.370 1.37Toilet 1 & 2

Water Supply Line 2 1 0.500 1.00

2 1 1.400 2.80

2 1 0.720 1.44

2 1 1.850 3.70

2 1 0.200 0.40

2 1 0.320 0.64

2 1 0.100 0.20

2 1 0.770 1.54Toilet 3

1 1 1.350 1.35

1 1 0.330 0.33

1 1 1.230 1.23

1 1 0.410 0.41

1 1 0.130 0.13

Page 1282: Triangle Construction 4th R.a. Bill for Township II

Page 1282 of 1288 Water supply

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

1 1 0.330 0.33Kitchen 1 1 0.100 0.10

1 1 0.300 0.30

1 1 0.180 0.18

1 1 0.720 0.72

1 1 1.470 1.47

1 1 0.180 0.18

1 1 0.630 0.63

1 1 0.190 0.19

1 1 0.330 0.33Total of G5 35.94

35.94 10 359.40Less Paid in 3rd R.A. Bill Item No.- 1.01a 10 in R.Mt. 215.64

Net Balance Qut. In this Bill R.Mt. 143.76Section:3 Internal Drainage works

3.08.b

G8 Internal Drainage Line Fitting1) 110mm, R.Mt.

Toilet 1 & 2

Drainage line 2 1 2.100 4.20

2 1 1.500 3.00

2 1 0.600 1.20

2 2 0.300 1.20Toilet 3

Drainage line 1 1 3.025 3.03

1 1 1.000 1.00

1 2 0.450 0.90

G6, G7, G8, F3, F4, G9, G10, G11 & G12 same as G5

Providing and fixing uPVC pressure pipes of Supreme or equivalent make as approved by EIC concealed laid having 6kg /cm² working pressure for Soil and Waste water, complete jointing with suitable grade of good quality solvent cement (supplied by the man

Page 1283: Triangle Construction 4th R.a. Bill for Township II

Page 1283 of 1288 Water supply

Description of Item Unit No. Length Breadth Depth Quantity Item No

Total Quantity

Total of G8 14.53G8,G6,G7,F3 & F4 same as G5 14.53 10 145.25

Less Paid in 3rd R.A. Bill Item No.- 3.08 b in R.Mt. 87.15Net Balance Qut. In this Bill R.Mt. 58.10

3.09.a Nos

G8 Internal Drainage Line FittingToilet 1 & 2 2 1 2.000 4.00Toilet 3 1 1 2.000 2.00

Total of G8 6.00G8,G6,G7,F3 & F4 same as G5 6.00 10 60.00

Less Paid in 3rd R.A. Bill Item No.- 3.09 a in Nos. 36.00Net Balance Qut. In this Bill Nos 24.00

For TRIANGLE CONSTRUCTION

PROJECT MANAGER

Providing and fixing an SWR quality, heavy duty, uPVC ‘P’ trap of Supreme or equivalent make as approved by EIC Including cutting the floor and making them good with surrounding M15 CC, masonry /block supports, MS brackets etc. testing, etc complete to th

Page 1284: Triangle Construction 4th R.a. Bill for Township II

TRIANGLE CONSTRUCTION

Measurement Sheet

Project Name: Township For CGPL at Mundra 4th

Location: Mundra Period 22/07/2011 to 31/08/2011

Date of Subm1/9/2011

Name of Contractor: TRTIANGLE CONSTRUCTION

Work Order No.: 6300001044

Type B10

Work Order No.: 6300001044

CEMENT CONSUMPTION STATEMENT

SR. NO. DESCRIPTION UNIT CO-EFFICIENT QTY CEMENT BAG CONSUMPTION

1 RCC M30 Concrete Bag/Cum 8.12 1319.36 10713

2 PCC 1:4:8 Bag/Cum 3.40 220.62 750

3 300mm Block Masonary Bag/Cum 4.65 348.046 1618

4 200mm Block Masonary Bag/Sqmt 0.93 3118.960 2901

5 100mm Block Masonary Bag/Sqmt 0.10 214.080 22

6 6mm Plaster (1:4) Bag/Sqmt 0.06 526.120 29

7 12mm Plaster (1:6) Bag/Sqmt 0.07 979.560 71

8 18-20mm Plaster (1:6) Bag/Sqmt 0.11 3566.661 399

9 IPS 60mm th. In 1:2:4 Bag/Sqmt 0.48 993.192 477

10 Polished Kotah Stone (1:6) 40mm Bedding Bag/Sqmt 0.40 0

11 Block Making Bag/Sqmt 0.40 0

Total Qty Bags 16980

For TRIANGLE CONSTRUCTION

PROJECT MANAGER

Doc. No. : TC/CGPL/11-12 /RA-4 Date: 31/08/2011

Running Bill No.

Name of Owner: M/s Coastal Gujarat Power Limited

Page 1285: Triangle Construction 4th R.a. Bill for Township II

Project Name: Township For CGPL at Mundra Running Bill No.- 3rd

Location: Mundra Period - 23/07/2011 to 31/08/2011

Date of Submission- 31/08/2011

Name of Contractor: TRTIANGLE CONSTRUCTION

Work Order No.: 6300001044

For Reconcillation

Dia of bar {A } { B } { C } D= {B+C} E F G={E+F} H = A-D-G

8 76.35 49.826 7.379 57.205 0.000 0.000 19.14510 18.82 9.118 0.978 10.096 0.000 0.000 8.72412 5.9 2.812 0.264 3.076 0.000 0.000 2.82416 34.56 22.172 1.738 23.910 0.000 0.000 10.65020 31.59 23.864 3.895 27.759 0.000 0.000 3.83125 72.735 47.962 9.104 57.066 0.000 0.000 15.66928 4.92 2.434 0.629 3.063 0.000 0.000 1.857

Total qty 244.875 158.188 23.987 182.175 0.000 0.000 0.000 62.700For TRIANGLE CONSTRUCTION

PROJECT MANAGER

Name of Owner: M/s Coastal Gujarat Power Limited

Total qty received up to 31.03.11( MT)

Total qty consumed

up to previous bill

( in MT ) Qty this bill

( in MT )

Cumalative qty consumed up to this bill

( in MT )

Total qty consumed up to previous bill ( in MT )

Qty this bill ( in MT )

Cumalative qty

consumed up to this bill ( in

MT ) Balance qty in Stock ( in MT)

Page 1286: Triangle Construction 4th R.a. Bill for Township II

Page 1286 of 1288 Door Farm

TRIANGLE CONSTRUCTION

Measurement SheetProject Name: Township For CGPL at Mundra Running Bill No. 4th

Location: Mundra Period 23/07/2011 to 31/08/2011

Date of Submission 31/08/2011

Name of Contractor: TRTIANGLE CONSTRUCTION

Work Order No.: 6300001044

Type B10

Item No Description of Item Unit No. Length Breadth Depth Quantity

5.01

Door Frame B10/G5

D1-Nr.Main Entry 1 2 2.100 0.125 0.050 0.031 1 1.000 0.125 0.050 0.01

D2-Bed,Kitchen,Study 4 2 2.100 0.125 0.050 0.114 1 0.900 0.125 0.050 0.02

D3-Toilet,Utility 4 2 2.100 0.125 0.050 0.114 1 0.750 0.125 0.050 0.02

D4-Living room 1 3 2.100 0.125 0.050 0.041 1 1.800 0.125 0.050 0.011 1 0.400 0.125 0.050 0.00

Total Qty. G5 0.35G8, G9 & G12 same as G5 0.35 4 1.4Door Frame B10/G5

D1-Nr.Main Entry 1 2 2.100 0.125 0.050 0.03

Doc. No. : TC/CGPL/11-12 /RA-4 Date: 31/08/2011

Name of Owner: M/s Coastal Gujarat Power Limited

Total Quantity

Providing & fixing in position door and window frame, including grooves on both sides and 2 rebates for on frame, made from best quality selected well seasoned Sal wood including smoothening, sand papering, making the edges rounded fixing the same using a

Page 1287: Triangle Construction 4th R.a. Bill for Township II

Page 1287 of 1288 Door Farm

Item No Description of Item Unit No. Length Breadth Depth Quantity Total

Quantity 1 1 1.000 0.125 0.050 0.01

D2-Bed,Kitchen,Study 4 2 2.100 0.125 0.050 0.114 1 0.900 0.125 0.050 0.02

D3-Toilet,Utility 4 2 2.100 0.125 0.050 0.114 1 0.750 0.125 0.050 0.02

D4-Living room 1 3 2.100 0.125 0.050 0.041 1 1.800 0.125 0.050 0.011 1 0.400 0.125 0.050 0.00

Total Qty. G5 0.35G6, G10 & G11 same as G12 0.35 4 1.4

Total Cu.Mt. 2.80

For TRIANGLE CONSTRUCTION

PROJECT MANAGER

Page 1288: Triangle Construction 4th R.a. Bill for Township II

Page 1288 of 1288 Platform

TRIANGLE CONSTRUCTION

Measurement SheetProject Name: Township For CGPL at Mundra Running Bill No. 4thLocation: Mundra Period

Date of Submission 31/08/2011Name of Contractor: TRTIANGLE CONSTRUCTIONWork Order No.: 6300001044

Type B10

Description of Item Unit No. Length Breadth Depth Quantity

9.44

Kitchen Plat form at G8 1 1 3.150 3.15

1 1 2.200 2.20

Total of G8 R.Mt. 5.35G6, G7 & G5 same as G8 5.35 4 21.40

For TRIANGLE CONSTRUCTION

PROJECT MANAGER

Doc. No. : TC/CGPL/11-12 /RA-4 Date: 31/08/2011

23/07/2011 to 31/08/2011

Name of Owner: M/s Coastal Gujarat Power Limited

Item No

Total Quantity

Providing & laying sandwich platform of maximum 700mm width a) Sandwich type platform of top stone as 18 mm thick Granite of approved shade and sample and bottom stone as 25 mm thick single side polished kota with 25 mm thick screed of cement mortar