Richard Thorne P.E. CXA, Axiom Engineers Tunnel Commissioning 21 st National Conference on Building Commissioning

Upload: lythuy

Post on 07-Feb-2018

222 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

Richard Thorne P.E. CXA, Axiom Engineers

Tunnel Commissioning

21st National Conference on Building Commissioning

Page 2: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

AIA Quality Assurance

The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.

This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.

Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

21st NCBC Conference

Page 3: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

Presentation Description

This presentation will cover project experience in applying basic commissioning principals and procedures to an uncommon commissioning environment – tunnel systems.

The presentation will cover:•Tunnel commissioning scope of work and growth•Experience with commissioning unique systems such as:

• Medium voltage electrical equipment• Radio communications• Complex Fire Protection (wet and dry)

•Scenario driven integrated test

21st NCBC Conference

Page 4: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

Presentation Description

21st NCBC Conference

Yesterdays Tunnel Projects

Page 5: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

Presentation Description

21st NCBC Conference

Page 6: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

Presentation Description

21st NCBC Conference

Page 7: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

At the end of this session, participants will be able to:

1. Apply basic commissioning processes to atypical systems2. Recognize project growth opportunities3. Understand importance of including manufacturers in commissioning

process4. Include operators and multiple organizations in integrated testing

Learning Objectives

21st NCBC Conference

Page 8: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Project Background• Commissioning Scope• Commissioned Systems• Commissioning Process• Integrated Test• Questions?

21st NCBC Conference

West End of Southbound Tunnel

Experience in Tunnel CommissioningOutline

Page 9: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Replace southbound access to and from Golden Gate bridge –Doyle Dr

• Original overpass no longer seismically safe

• Increase green scape –parkway not a freeway

21st NCBC Conference

Project BackgroundProject Goals

Doyle Dr Transition

Page 10: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Got the call• Tunnel or Electrical Commissioning

Experience?• Apply basic commissioning

principals to new systems• BSEE – Basic Understanding in

electrical systems• Attended 1 yr PG&E

Commissioning Course• Construction Site Experience• 20 years Naval experience

21st NCBC Conference

Project BackgroundGetting Project

Page 11: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Schedule of Commissioning Events• Integrate schedule with Construction

Schedule• Commissioning Plan

• Readiness, start-ups, functional tests, & acceptance criteria

• Training• Cx report contents• Schedule

• Provide checklists and test procedures

• Commissioning Checklist Log• Training – videotaping,

schedule and coordination with contractor

• Final systems integration test• Final report

21st NCBC Conference

Commissioning ScopeFrom Specifications and Drawings

Page 12: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Electrical• Medium Voltage

Switchgear• DC Battery Charger and

Power Supply• One for protective relays

and PLC controllers• One for emerg tunnel

lighting• Circuit Breakers• Uninterruptable Power

Supplies• 12-20KVA for traffic

operations and SCADA• 30KVA for tunnel lighting

• Protective Relays

21st NCBC Conference

Commissioned Systems

Page 13: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Electrical (cont)• Motor Control Centers• Lighting Systems (Tunnel,

street area at portals, and Substation)

• Grounding• Surge Arrestors• Transformers• Panelboards

21st NCBC Conference

Commissioned SystemsCONT

Page 14: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Mechanical• Substation fans• Hydrogen detection (added)• Carbon Monoxide System• Jet fans are future scope!

21st NCBC Conference

Commissioned SystemsCONT

Page 15: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Special Systems• Radio Rebroadcast• Call Boxes

21st NCBC Conference

Commissioned SystemsCONT

Page 16: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Special Systems• SCADA (Supervisory Control

And Data Acquisition)• Electrical Distribution• Lighting• Fire Protection (info only)• Carbon Monoxide Monitoring• Future Jet Fans• Substation HVAC• Call Boxes• Hydrogen Detection

21st NCBC Conference

Commissioned SystemsCONT

Page 17: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Commissioned Systems:• Fire Protection

• Deluge Tunnel System• Standpipe Tunnel System• Linear Heat Detectors• Fire Alarm Control Units• Fire Alarm Remote

Annunciators• Smoke Detectors• Manual Pull Boxes• Remote Fire Alarm and

control from central control station

21st NCBC Conference

Commissioned SystemsCONT

Page 18: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Drawing Review (growth opportunity)• Submittal Review• Commissioning Plan• Start-Up Plans (Prefunctional Checklists)

Development/Execution• Functional Tests Development/Execution• Training (growth opportunity)• Integrated Test Development/Execution• Report

21st NCBC Conference

West End of Tunnel, digging to bottom level

Commissioning ProcessGeneral Process

• Many Parties Involved• CALTRANS (Numerous

Branches)• State Fire Marshall• Inspector of Record• Facilitator

Page 19: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Understanding the project beyond the drawings themselves

• More emphasis on tracing power

21st NCBC Conference

Commissioning ProcessDrawing Review Alternate power

supply not to be installed during

this phase

Page 20: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Under-developed single line• Growth opportunity

21st NCBC Conference

Commissioning ProcessDrawing Review

200 sheets of drawingsto filter what is on each panels, if anything

Page 21: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Lessons Learned:• Updating process did not show clouds or revision marks.

21st NCBC Conference

Commissioning ProcessDrawing Review

Page 22: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Lessons Learned:• Updating process did not show clouds or

revision marks. • Understanding Ladder Logic and

controls

21st NCBC Conference

Commissioning ProcessDrawing Review

Page 23: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Standard process and comments for HVAC type systems

Equipment capabilities match design?Is equipment going to fit?Access?

• Difference from HVAC system – more capability issues between equipment contacts and SCADA inputs.

• Education on how protective relay logic works

21st NCBC Conference

Commissioning ProcessSubmittal Review

Page 24: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Lessons Learned:• Panel board number and type

of circuit breakers not matching design

• Lighting controller O&M sequence backwards

• Finding terminal blocks on submittal drawings that were not installed

• Points not terminated at controller

• Learn from manufacturer

21st NCBC Conference

Commissioning ProcessSubmittal Review

Page 25: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Lessons Learned:• Learn from manufacturer

21st NCBC Conference

Commissioning ProcessSubmittal Review

Page 26: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Standard process and comments for HVAC type systems

• Installed equipment does not match submittal

• Missing items from design• Maintenance Access

21st NCBC Conference

Commissioning ProcessInstallation Verification

Page 27: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Lessons Learned:• Circuit breakers not matching

design• CO monitor cover could not

open• Missing insulation on

condensate drain

21st NCBC Conference

Commissioning ProcessInstallation Verification

On East Side of Tunnel looking West – 1 month to opening

Page 28: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Additional sections normally not found in HVAC type projects

• System Testing Details• Specific system start-up plan

responsibilities• Specific functional test plan

responsibilities• Phased commissioning sequence

21st NCBC Conference

Commissioning ProcessCommissioning Plan

Deluge Control Valve in Niche

Page 29: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Direct application of building commissioning• Proceed from components to systems• Composed of specification checks• Refer to items in the installation manual

• Review start-up plans provided by installers/manufactures.

• Radio rebroadcast• Fire protection system (alarms)• SCADA

• Basic common checks• Connected correctly?• Initial settings (Protective Relay)

21st NCBC Conference

Commissioning ProcessStart-up Plans

Medium Voltage Circuit Breaker

Page 30: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Lessons Learned• Big difference with HVAC – most of

team was NOT familiar with commissioning process

• What start-ups really need to happen• Risk of not completing:

• Safety – lack of eyewash stations• Makes functional testing go MUCH

slower• Need to use unfamiliar publications on

unfamiliar projects

21st NCBC Conference

Commissioning ProcessStart-up Plans

Medium Voltage Circuit Breaker

US Army Commissioning of Electrical Systems for Command, Control, Communications, Computer, Intelligence, Surveillance, and Reconnaissance Facilities Technical Manual is a great resource for commissioning power distribution systems

Page 31: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Direct application of building commissioning• Start from component and work up to

systems and then integration• Need to confirm component functions

based on controlling inputs• Major difference than HVAC – not all

components need functional tests• Electrical equipment (transformer, panel

boards)

21st NCBC Conference

Commissioning ProcessFunctional Tests

Page 32: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Lessons Learned:• Found issues that could have been caught

earlier• Contacts not present to provide

feedback to SCADA• Lack of pre-recorded messages• Further slows functional test process

• Still catches issues that everyone misses – spray blockage

21st NCBC Conference

Commissioning ProcessFunctional Tests

Page 33: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Similar to building commissioning except:• Training had to cover all three

maintenance shifts• Training plans reviewed by State Fire

Marshall• State Fire Marshall witness some

training• Great opportunity to increase scope

• Who else has a grasp on all of the systems and how the training should be organized?

• Developed detailed class schedule

• Collected and submitted training plans

• Even provided some training (expert in radio rebroadcast system????)

21st NCBC Conference

Commissioning ProcessTraining

Page 34: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Integrated Test:• Goal is to show how tunnel systems

work together in a major tunnel incident

• Demonstration for State Fire Marshall for ALL systems

• Electrical• Fire Protection• Mechanical• Operators• Special Systems

21st NCBC Conference

Commissioning ProcessIntegrated Test

Completion of Integrated Test

• Scenario driven (plan)• Start with simulated car

wreck• Driver uses call box to report

accident• Smoke bomb lit off to

simulate smoke to cameras• Activation of LHD (triggered

at FACU)• Operators respond

Page 35: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Plan was just a plan, a guide

21st NCBC Conference

Commissioning ProcessIntegrated Test

Completion of Integrated Test

• What really happened• Continued testing and

troubleshooting of the fire alarm system.

• Conducted functional tested on systems not ready before this point

• Battery Charger, street lighting, CO system

• Actual scenario testing happened on Friday after heat testing on Thur

Page 36: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Lessons Learned:• Be Flexible!!!!

• Correct deluge reaction• LHD detects heat• Operator has 30sec to

acknowledge• Once acknowledged, 90sec delay• End of 90sec, water will release

• What actually happened during scenario

• Call box activation successful• LHD zone (6) that was switched ON

different than location of smoke bomb (8)

• Operators shut down tunnel, acknowledged LHD zone 6

• Vendor entered control center and manually activated zone 7 and 8

21st NCBC Conference

Commissioning ProcessIntegrated Test

Page 37: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• The primary focus during integrated testing –open the tunnel

• Numerous tests had to be done latter• Substation external lighting/SCADA• Security system (door sensors)• Substation fan operation with regards to

high hydrogen• Tunnel lighting• Troubleshooting

21st NCBC Conference

Commissioning ProcessFollow On Testing

West Bore, After Tunnel Opening

Page 38: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Similar to building commissioning report, except:

• Specifications description of report is more like systems manual

• Major component of systems manual –Narratives!

• Include ALL factory tests, start-up reports, functional tests, and training documentation

21st NCBC Conference

Commissioning ProcessFinal Report

Page 39: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

• Try to always say YES to opportunities• Look for growth opportunities and ways to help

project• Apply standard commissioning processes to

new systems with base knowledge• Include all parties and manufactures in

process

21st NCBC Conference

Summary

Tunnel Of Today

Tunnel Of Yesterday

Page 40: Tunnel Commissioning -  · PDF fileWest End of Southbound Tunnel Experience in Tunnel Commissioning Outline ... • Future Jet Fans

THANK YOU

Richard Thorne, P.E., [email protected]