tusd facilities update november 8, 2010. deferred maintenance
TRANSCRIPT
![Page 1: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/1.jpg)
TUSD Facilities Update
November 8, 2010
![Page 2: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/2.jpg)
Deferred Maintenance
![Page 3: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/3.jpg)
What is Deferred Maintenance?TUSD – “Planned Maintenance”
• Major repair or replacement of existing school building components so that the educational process may safely continue.
![Page 4: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/4.jpg)
Deferred Maintenance Eligible Repairs
• Floor Covering
• Painting
• Electrical
• Classroom Lighting
• Roofing
• Plumbing
• HVAC
• Wall Systems
• Paving
• Underground Toxic Tank
• Asbestos
• Lead
![Page 5: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/5.jpg)
Typical Facilities Component Life Spans
Component Timeframe Repair/Replacement
Carpet 15 Years Rotation
Interior Paint 10 Years * As Needed
Exterior Paint 15 Years * As Needed
HVAC 15 Years * As Needed
Roofing 20 Years * As Needed
* Function and condition assessed annually
![Page 6: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/6.jpg)
09/10 Deferred Maintenance Projects:
Project School Expenditure
Carpet Replacement Utt MS $135,825
Walkway Roof Replacement Beswick ES $114,640
Exterior PaintingHeideman ES
Tustin HS$39,407
Slurry/Striping Various Sites (12) $119,459
$409,331
![Page 7: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/7.jpg)
Proposed 10/11 Deferred Maintenance Repairs:
Project School Preliminary Budget
Carpet Replacement Tustin Ranch ES $250,000
Exterior Painting (2) Sites – TBD $300,000
Roof Replacement (2) Sites – TBD $200,000
Slurry/Striping Various Sites – TBD $100,000
HVAC Controls Various Sites – TBD $100,000
Replace HVAC Units Various Sites – TBD $250,000
$1,200,000
![Page 8: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/8.jpg)
Building Program
* This presentation includes construction projects that are funded from a number of sources including: CFD’s, General Obligation Bonds (Measure G & L), and Statewide school construction bonds.
![Page 9: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/9.jpg)
Completed Projects 2010:
Project Budget Status
Orchard Hills K-8 $56,000,000 Complete
FHS Pool Replacement $ 3,900,000 Complete
BHS Field Replacement $ 200,000 Complete
* THS Summer Modernization $ 5,600,000 98% Complete
* Math/Special Education Remodel and Building 230 HVAC
$65,700,000
![Page 10: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/10.jpg)
Orchard Hills K-8 - Adminstration
![Page 11: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/11.jpg)
Orchard Hills K-8 - Library
![Page 12: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/12.jpg)
Orchard Hills K-8 - Gymnasium
![Page 13: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/13.jpg)
FHS Pool Replacement
![Page 14: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/14.jpg)
FHS Pool Replacement
![Page 15: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/15.jpg)
BHS Field Replacement – Progress Photo
![Page 16: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/16.jpg)
BHS Field Replacement - Completion
![Page 17: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/17.jpg)
BHS Field Replacement - Completion
![Page 18: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/18.jpg)
THS Summer Modernization - Courtyard
![Page 19: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/19.jpg)
THS Summer Modernization - Exterior
![Page 20: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/20.jpg)
THS Summer Modernization – Special Ed.
![Page 21: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/21.jpg)
THS Summer Modernization – Math
![Page 22: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/22.jpg)
Projects in Construction
Project Budget Status
Heritage School $12,000,000 70% Complete
THS Science Center $ 11,800,000 60% Complete
FHS Locker Room Remodel $ 4,500,000 95% Complete
$28,300,000
![Page 23: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/23.jpg)
Heritage School - Administration
![Page 24: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/24.jpg)
Heritage School - Multipurpose
![Page 25: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/25.jpg)
Heritage School – Storm Drain Filtration
![Page 26: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/26.jpg)
Heritage School – Classroom Building C
![Page 27: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/27.jpg)
THS Science Center - Exterior
![Page 28: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/28.jpg)
THS Science Center - Exterior
![Page 29: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/29.jpg)
THS Science Center – Interior Stairs
![Page 30: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/30.jpg)
THS Science Center - Classroom
![Page 31: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/31.jpg)
FHS Locker Room Remodel - Exterior
![Page 32: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/32.jpg)
FHS Locker Room Remodel - Restrooms
![Page 33: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/33.jpg)
FHS Locker Room Remodel - Showers
![Page 34: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/34.jpg)
FHS Locker Room Remodel – Lockers
![Page 35: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/35.jpg)
Proposed Future Projects 2010/11
Project Cost Estimate Status
BHS Snack Bar/Restrooms $600,000 DSA Review
THS Gymnasium $ 9,000,000 DSA Approved
FHS Events Center $10,500,000 DSA Approved
MS Multipurpose Facilities $20,000,000 DSA Review
* Currie Modernization $ 4,100,000 In Design
* Building 400, 500 & 600$44,200,000
![Page 36: TUSD Facilities Update November 8, 2010. Deferred Maintenance](https://reader038.vdocument.in/reader038/viewer/2022102923/55167df3550346a25b8b4789/html5/thumbnails/36.jpg)
Building Program Summary
Category Budget
Completed Projects 2010 $65,700,000
Projects in Construction $28,300,000
Proposed Future Projects 2010/11 $44,200,000
$138,200,000
* The referenced construction projects are funded from a number of sources including: CFD’s, General Obligation Bonds (Measure G & L), and Statewide school construction bonds.