tw@esi 26th june 2016

20
TW@ESI 26 th June 2016 Hope all of you had a happy weekend The following is a record of what was done during the past week and a forecast of the next week.....

Upload: simon-abela

Post on 20-Feb-2017

57 views

Category:

Business


2 download

TRANSCRIPT

Page 1: TW@ESI 26th June 2016

TW@ESI26th June 2016

Hope all of you had a happy weekend

The following is a record of what was done during the past week and a forecast of the next week.....

Page 2: TW@ESI 26th June 2016

A General Note before we start- New premisesThe new premises.... Most works have now been completed- well done to all for their efforts done. The following is to be done before we can say we are really ready! a) Air Conditioning controls with JACEb) Re installation of all wall mounted items in tech area.

This area is to be made a show case and it is to reflect organisation and technology

c) Automation system integrated with lighting and the other systems installed

d) Snag list is pending which is with Dennis to implement- this too is nearly done.

Page 3: TW@ESI 26th June 2016

A General Note before we start- Some General Notes•Clifton and Claudio are now done with the NIAGARA4 on line training- Prosit•To all of you who helped organise John’s surprise party in the office- Well Done... Great occasion •There will be another activity on Friday 8th July- sailing club and a taster on MoonDance Sailing yacht... Can all people coming confirm their presence •A new intern Dalma Eszenyi – will be joining CVA and CCI team as of 27th June 2016 till 2nd August 2016•CCI/CVA ask Andrew to use Linkedin to allow him to follow our group and team updates•Happy holidays to Christian, Giljan and also Karolina

Page 4: TW@ESI 26th June 2016

Projects and deadlines• 15_044_Hilton_Restaurant_Kitchen_AHU and

15_034_Hilton_Calorifier_Monitoring. We have managed to commission basic closed loop controls ... Next would be the full commissioning of the CVA can you confirm when this will be completed. We will have the VSD built as of tomorrow 20th June and DSH should co ordinate to install this permanently on site- we have a new PO for the construction of a further drive EF48... We will now start ordering and design for this

• 15_033_Westin_7-AHU- Most of the T&C should by now be completed. Pending is documentation CCI I would like a target date on the completion here

• 15_008 - Aurobindo PH02 BMS- We have made progress on commissioning here- we are stuck on a lot of issues by the client – We must do all we can to close items which are our control- we will soon be under pressure to conclude what we can here

Page 5: TW@ESI 26th June 2016

Projects and deadlines• 12_027- Parliament We now need to proceed on

all pending issues down to ESI (Original contract- Server software, Intruder alarm mainly)

• 13_070- SCM Lagoona Plant room – DSH we need to identify which is the date when we can conclude all installations possible here

• 15_041- has been concluded and we now have to close off all as fitted and O&M as well as assist in creating a VPN with site- A very very well done to all who made this a successful overseas endeavour.

Page 6: TW@ESI 26th June 2016

DesignLast week• OVT & AAP – Concluded Rittal Parts list• OVT & AAP – met CCI for Field Devices Part Nos• OVT – Released Helvar & Tridium Panel Parts• AAP - Released Helvar & Tridium Panel Parts• OVT – updated UFH details on P&ID & Plans, &

re-submitted to all• Siggiewi – O&M CDs for MPA

Page 7: TW@ESI 26th June 2016

DesignNext Week:• Conclude My Fadlallah update for CVA• Life Sciences DDC-LS4-B Panel Drawing update

as per CCI feedback• Hilton Kitchen AHUs - get As Built feedback

from DSH, implement. Then distribute to Alex & Mark Picc.

• OTM – SAS000770 update by 1/7/2016• GGY Residence – BMS Panel Sizing as per

available space

Page 8: TW@ESI 26th June 2016

InstallationPast week:

• Fitted new intercom and doorbell in offices• Sterling Chemicals panels inspection and

cleaning• Completed electrical, plumbing, tiling and most

of the plastering and painting in garage• Reconnected power supply for panel testing in

workshop• Painted garage doors

Page 9: TW@ESI 26th June 2016

InstallationNext week:

• New VSD panel at Hilton• Modification on MCC-N1 at Hilton• Commissioning with Claudio at Hilton• CCTV repairs at SCM• Complete garage painting

Page 10: TW@ESI 26th June 2016

Panel BuildWe have the Hilton VSD design and material list ready

we will be sub contracting this as a Trial

Next panels planned are for

a) OVT panelsb) APP panels

Page 11: TW@ESI 26th June 2016

Mater DeiThe following are the tasks being worked on and planned for the next weeks• MCC Panel Checks/UPS in BMS Panel E01-CC1, E02-CC1, EP1-CC1, F01-CC1,

F02-CC1, F05-CC4, F05-CC5, F03-CC1, F04-CC1, F05-CC1• MCC PANEL CHECKS/UPS IN BMS PANEL D00-CC1, D01-CC1, DP1-CC1, D02-

CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D02-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3

• Field Device PPm D08-CC1, DP5-CC1 / D08-CC2, D08-CC3 / D09-CC1, D09-CC2• COORDINATED CHECKS OF ALARMS FROM 3RD PARTY DEVICES D08-CC1, DP5-

CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2• WEEKLY UPDATE OF ANTI-VIRUS ON ALL BMS STATIONS• Handling of reactive work orders• Quotation works new angiography project• Cont WinCC Upgrade HMIs- which are now all on line- well done all!!• To Add 2 new Alarms from volt free contacts of medical fridges in rooms

D113051 and D113052• New Medical gas alarm in B212005

Page 12: TW@ESI 26th June 2016

Development and Commissioning• Parliament project - NEXT IS TO TACKLE SNAGS ON

PARLIAMENT so as to close off the whole job • The last issues on the DAC for SCM PH2- IT IS NOW A

PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION

• 12_043_Life Sciences – Collecting the KWhr monthly data and finishing off what we can is a huge urgency- we need to start on water meter commissioning

• SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

• The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission

Page 13: TW@ESI 26th June 2016

Development and Commissioning• OTM urgent jobs and snags – P12/ Tank Field 3• CCA Villa - AC snags and ILPS. • Oncology 14_066- We have done most of the

work here and are waiting from Panta on this• Aurobindo we are proceeding with software

development and we have done quite some progress –we need to conclude whatever we can here

Page 14: TW@ESI 26th June 2016

Development and Commissioning• 16_004_Microbiz_PW_Otis_Interface- is now urgent and

must meet our deadlines- we have fixed the commissioning dates in the US here- Flights out on 11th July 2016

• 14_081_Siggiewi School- Lets move on concluding issues related to Data acquisition and analysis.... We need good data to prove our systems- CCI we need to assess the data requirements of the client and report back

• 16_017_BMIT_DAC- We have done first and second fix and now need to proceed to commission

• 16_011_Intruder_UOM- We have started installation on this project and we need to plan on completion dates

Page 15: TW@ESI 26th June 2016

Data, data and more data• We have a lot of projects which are giving us a lot

of data and I would like to start telling “stories” by data

• I have received Data from MDH and need the data from CCI (for siggiewi) and what type of data we can get from SCM (From CVA) – Once I have these I will start writing our stories with the data

• I should have had this data by 13th June- I need feedback from CCI and CVA- or tell me by when I can get this data

Page 16: TW@ESI 26th June 2016

Sales and Business Development• We have been working on a quote for Actavis,

2 other Home automation projects and a quote for OTM for the change over of their PLC/Operating system and re writing of their core software

• New projects won Nestle - 15_039, Hilton VSD for EF48

Page 17: TW@ESI 26th June 2016

Birthday wishes go to

I Forgot to wish Silvan Scerri Happy Birthday last 23rd July- Happy

Belated Birthday Silvan

Page 18: TW@ESI 26th June 2016

Team ESI- Reminders

• I sent out some e mails to some of you to give me feedback on what tools and instruments you have so as to have a log of everyone- I need your feedback by 30th June 2016

• Quality questions for new employees – I sent these out and need them returned by 13th July 2016

• Strengths, Weaknesses, Opportunities and Threats... I would like all your feedback by end of June 2016.... This is what I came up with so far

Page 19: TW@ESI 26th June 2016

Team ESI• I urge you all to follow this blog and keep up to date with

what is happening at ESI • I await all your feedback on all the ESI discussions –

without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

Page 20: TW@ESI 26th June 2016

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable

• I have been seeing a lot of encouraging actions showing teamwork- people working and helping each other as a team – this needs to go on and we must work to achieve what we persist for- success!!!

• Have a good week- and well done Poland for your qualification