7/17/2019 TxSelf-BuildProcedure http://slidepdf.com/reader/full/txself-buildprocedure 1/71 CONTROLLED DISCLOSURE When downloaded from the EDS database, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the database. Procedure Transmission Division Title: Procedure for Self-Build Customer Projects in Transmission Unique Identifier: 240-61713594 Alternative Reference Number: N/A Area of Applicability: Transmission Documentation Type: Procedure Revision: 1 Total Pages: 71 Next Review Date: September 2015 Disclosure Classification: CONTROLLED DISCLOSURE Compiled by Functional Responsibility Authorized by ………………………………….. ………………………………….. ………………………………….. Roy Estment Corporate Consultant Mbulelo Kibido GM Grid Planning Mongezi Ntsokolo Group Executive Transmission Date: …………………………… Date: …………………………… Date: ……………………………

Upload: mansoor-mohammed

Post on 08-Jan-2016

224 views

Category:

Documents


0 download

DESCRIPTION

build procedure

TRANSCRIPT

  • CONTROLLED DISCLOSURE When downloaded from the EDS database, this document is uncontrolled and the responsibility rests with the user to ensure it

    is in line with the authorized version on the database.

    Procedure

    Transmission Division

    Title: Procedure for Self-Build Customer Projects in Transmission

    Unique Identifier: 240-61713594

    Alternative Reference Number: N/A

    Area of Applicability: Transmission

    Documentation Type: Procedure

    Revision: 1

    Total Pages: 71

    Next Review Date: September 2015

    Disclosure Classification: CONTROLLED DISCLOSURE

    Compiled by Functional Responsibility Authorized by

    .. .. ..

    Roy Estment Corporate Consultant

    Mbulelo Kibido GM Grid Planning

    Mongezi Ntsokolo Group Executive Transmission

    Date: Date: Date:

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 2 of 71

    CONTENTS PAGE 1. INTRODUCTION ...................................................................................................................................................... 4 2. SUPPORTING CLAUSES ........................................................................................................................................ 4

    2.1 SCOPE .............................................................................................................................................................. 4 2.1.1 Purpose ..................................................................................................................................................... 4 2.1.2 Applicability................................................................................................................................................ 4

    2.2 NORMATIVE/INFORMATIVE REFERENCES .................................................................................................. 4 2.2.1 Normative .................................................................................................................................................. 4 2.2.2 Informative ................................................................................................................................................. 5

    2.3 DEFINITIONS .................................................................................................................................................... 5 2.3.1 Classification ...............................................................................................................................................

    2.4 ABBREVIATIONS .............................................................................................................................................. 8 2.5 ROLES AND RESPONSIBILITIES .................................................................................................................. 10 2.6 PROCESS FOR MONITORING ...................................................................................................................... 10 2.7 RELATED/SUPPORTING DOCUMENTS ...........................................................................................................

    3. GENERAL CONDITIONS AND GUIDELINES FOR SELF-BUID PROJECTS ..................................................... 10 3.1 KEY PRINCIPLES AND CONDITIONS ........................................................................................................... 12 3.2 APPLICATION FOR SELF-BUILD .................................................................................................................. 13

    3.3 THE SELF-BUILD PROCESS AND ITS LINKAGES WITH THE ESKOM QUOTATION AND EIA PROCESSES. 3.4 ALLOCATION OF RESPONSIBILITIES BETWEEN ESKOM AND THE CUSTOMER IN A SELF- BUILD PROJECT. 3.5 CONNECTION CHARGES APPLICABLE TO SELF BUILD PROJECTS 3.6 HOLDING POINTS TO ASSURE COMPLIANCE TO ESKOM STANDARDS AND SPECIFICATIONS 4. AUTHORIZATION .................................................................................................................................................. 18 5. REVISIONS ............................................................................................................................................................ 19 6. DEVELOPMENT TEAM ......................................................................................................................................... 19 7. ACKNOWLEDGEMENTS ...................................................................................................................................... 20 APPENDIX A : ESKOMS CONDITIONS AND REQUIREMENTS FOR SELF-BUILD PROJECTS ....................... 20 APPENDIX B : CHECKLIST OF ESKOMS HOLDING POINTS..21 APPENDIX C : APPLICABLE STANDARDS, SPECIFICATIONS, GUIDELINES, ETC .25 APPENDIX D : UNDERTAKING BY THE CUSTOMER TO USE INFORMATION PROVIDED SOLELY FOR

    THE PURPOSE FOR WHICH IT IS INTENDED ....26 APPENDIX E : DETAILS OF CUSTOMERS AND ESKOMS RESPONSIBILITIES....27 APPENDIX F : ESKOM SUBSTATION DESIGN REQUIREMENTS FOR SELF-BUILD PROJECTS ..44 APPENDIX G: ESKOM SUBSTATION DESIGN GUIDELINES45 APPENDIX H: TX SELF-BUILD CONNECTION AGREEMENT PRO FORMA ...........................................49 APPENDIX I: TYPICAL ESKOM STANDARD EQUIPMENT RATINGS..50 APPENDIX J: GUIDELINES ON COST ALLOCATION AND TRANSMISSION ASSET CLASSES..52 APPENDIX K: ESKOM TRANSMISSION LINE DESIGN REQUIREMENTS FOR SELF BUILD PROJECTS64

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 3 of 71

    FIGURES Figure 1: Customer Application Process (From initial application up to BQ stage).................................................... 13 Figure 2: Customer Application Process ( showing touch points between the various Parties in the Project

    Lifecycle).14

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 4 of 71

    1. INTRODUCTION

    The Transmission Executive Committee (TEXCO) decided to permit Customers to self-build their network connection assets or infrastructure in order to afford them the opportunity to seek efficiencies on cost and/or connection timelines. This TEXCO decision has been a response to the Customers perception that Eskoms quoted connection costs are high and also that the quoted grid connection timelines are inordinately long.

    2. SUPPORTING CLAUSES

    2.1 SCOPE

    This procedure outlines the requirements, conditions, mechanisms, rules and process to be followed by Customers electing to self-build their connection infrastructure to the Transmission network. The procedure applies to both load and generation Customers wishing to connect to the Transmission network. The procedure is limited to the Transmission scope-of-works of the Customer connection projects.

    2.1.1 Purpose

    To provide a detailed procedure to direct load and generation Customers electing to self-build their connection-infrastructure to connect to the Eskom Transmission System.

    Note: For connections to the Eskom Distribution System, the Eskom Distribution Procedure for HV Self-Build Projects (ref: 240-43874056) shall apply.

    2.1.2 Applicability

    This document shall apply to all Transmission Business Units.

    2.2 NORMATIVE/INFORMATIVE REFERENCES

    Parties using this document shall apply the most recent edition of the documents listed in the following paragraphs.

    2.2.1 Normative

    [1] South African Grid Code [2] Environmental Impact Assessment Regulations 2010 (or latest amendment) [3] Expropriation Act [4] Eskom Consideration and Compensation Standard (EST 32-844) [5] National Environmental Management Act, (as amended)

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 5 of 71

    [6] NERSA Guidelines on Transmission Connection Charges [7] Quotation policy and process for generator connections 32-978 [8] Cost estimate pro forma letter (to be revised) [9] Budget quotation pro forma letter (to be revised) [10] Self-build connection agreement (to be developed) [11] Substation Layout Design Guide. [12] WGL001 Outage Planning Guideline [13] Occupational Health and Safety Act (OHS Act) [14] Eskoms Operating Regulations for High Voltage Systems (ORHVS) [15] Eskom Practice Note for Implementation of Substation Layouts for Transmission

    Substations: 240-61713594 [16] TRMSCAAC1: The Design and Construction of Overhead Power Lines [17] SANS10280: Overhead Lines for Conditions Prevailing in South Africa [18] Transmission Line Specifications Template

    2.2.2 Informative

    [1] The Electricity Regulation Act as amended [2] The Transmission Licence [3] Grid connection code for renewable power plants [4] Eskom Distribution Procedure for HV Self-Build Projects (unique number 240-43874056)

    2.3 DEFINITIONS

    2.3.1 Definitions

    a. Concept design: as per Table 3 in Annexure E b. Connection assets or connection works: means the work which shall be carried out by

    Eskom and the Customer to connect the Customers asset to the Eskom Transmission System.

    c. Connection charges: mean the charges recouped or to be recouped by Eskom from the Customer for the cost of construction of the works and connecting the connection works to the Transmission System, which shall be either (a) a Distribution and/or Transmission Standard Connection Charge if the connection is a Standard Connection or (b) a Distribution and/or Transmission Premium Connection Charge, if the connection is a Premium Connection.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 6 of 71

    d. Connection Charge Guarantee: means a guarantee from the Customer to cover the risk of non-payment where a schedule for the payment of connection charges has been agreed to between Eskom and the Customer.

    e. Connection works: means the works required to be constructed to connect the Customers plant to the Eskom Transmission System.

    f. Consultant: means the Customer-appointed agent assuming technical accountability for the self-build project.

    g. Contestable works: refers to the activities and connection-works allocated to the Customer in a self-build agreement.

    h. Contracting party: the contracting parties shall be Eskom and the Customer. i. Contractor: means an Eskom-accepted contractor undertaking contestable construction

    works. j. Control Plant: means all equipment which is used in the detection of fault conditions in the

    network in order that the faulty parts of the network are promptly disconnected from the power system, thereby ensuring optimal quality of supply to customers, minimal damage to primary plant, and sustained stability and integrity of the power system. Control plant encompasses all Protection, Telecommunications, DC Supplies, and Measurements equipment in a substation.

    k. Customer: means generators and/or load applicants that will be connected to the Eskom network.

    l. Dedicated connection assets: mean that portion of the network which is dedicated to a specific Customer; Customer-dedicated assets are assets created for the sole use of a Customer to meet the Customers technical specifications, and are unlikely to be shared in the Eskoms planning horizon by any other Customer.

    m. Design Review Team: an Eskom Technical Governance Committee that evaluates any proposed designs for a project in order to provide assurance that the designs conform to Eskom Standards and specifications.

    n. Environmental Impact Assessment (EIA): means the process of examining the environmental effects of a development and obtaining an environmental authorisation to proceed with the development from the relevant authorities in accordance with applicable legislation. It is normally a detailed study or a specialist study of significant issues that have been identified.

    o. Environmental Management Programme (EMPr): means an environmental management plan that guarantees the end state of the affected areas and describes how activities that could have a negative impact on the environment will be managed and monitored. It also describes how the impacted areas will be rehabilitated.

    p. Eskom Distribution System: means all Eskom power networks from the voltage level of 132kV and below that are not owned by the Eskom Transmission Division.

    q. Eskom Standards: the term standard means all related policies, procedures, work instructions and standards in Eskom.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 7 of 71

    r. Eskom Transmission System: means all Eskom networks with voltage level above 132kV but includes also any voltage-level plant or equipment that is owned and operated by the Eskom Transmission Division.

    s. Final design package: means the Eskom accepted technical document detailing the design in line with the Eskom Standards and specifications in accordance with which the asset is to be constructed.

    t. Handover: means a point where all self-build network construction is complete, ownership of all such network has been transferred to Eskom and the Contractors permission to work on them has been removed.

    u. Heads of Agreement: refers to a non-binding document outlining the main issues relevant to a tentative agreement.

    v. HV (High Voltage): means networks with nominal voltage exceeding 33kV w. HV Plant Equipment: means HV equipment in a substation used in the transmission of

    electrical energy. This includes all the equipment used to insulate electrical conductors from earth and/or from one another. HV plant encompasses high-voltage switchgear, power transformers, isolators, current and voltage transformers, capacitor banks, copper and/or aluminium busbars, overhead conductors, HV cables, reactors, surge arrestors and insulators, and earthing systems.

    x. Monopoly works: means those works which are Eskoms responsibility that are required to ensure a standard of work that meets quality of supply, reliability and safety standards.

    y. National Network Integration Forum: means an Eskom committee charged with ensuring that the network planning solution selected for a project is agreed to by Distribution and Transmission as being appropriate to customer requirements, in alignment with other developments, and operable in a safe and secure manner.

    z. National Transmission Company: means the Eskom Transmission Division in its capacity as the holder of the Transmission Licence issued by the National Energy Regulator of South Africa.

    aa. Point of supply: a point of supply or POS is a physical point on the electrical network from which electricity is delivered to or by a Customer.

    bb. Point to point: means the electrical infrastructure directly from the existing Eskom network to the Customers self-build asset, where no other Eskom customers or electrical infrastructure can be affected.

    cc. Primary Plant Equipment: has the same meaning as the HV Plant equipment. dd. Route plan: means a plan detailing the geographic path along which the asset will be

    constructed. ee. Schedule of owners: means a listing of the names, addresses and contact numbers of all

    landowners along the route of the new about-to-be-constructed asset. ff. Secondary Plant Equipment: has the same meaning as control plant gg. Self Build: refers to a right granted to a third party, other than the designated Transmission

    Licensee, to plan, design, and build their own infrastructure to connect to the transmission grid (or the shared transmission system)

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 8 of 71

    hh. Self-Build Connection Agreement: means the contract concluded between Eskom and the Customer defining, inter alia, the terms, rights and obligations of these parties, and specifically including the conditions under which the self-build option requested by the Customer will be allowed and exercised.

    ii. Self-Build Assets: refers to the Customer connection assets built through the self-build option.

    jj. Self-Build Customer: refers to the generators and/or load applicants that will be connected to the Eskom network using the self-build option

    kk. Technical Evaluation Forum: means a forum applicable to the Distribution Division of Eskom which looks at various project solution proposals and which recommends the best technical option to meet the Customers demand and ensure that designs are executed in line with the Eskom Standards and specifications.

    2.3.2 Classification

    a. Controlled disclosure: controlled disclosure to external parties (either enforced by law, or discretionary).

    2.4 ABBREVIATIONS

    2.4.1 Abbreviated Terms

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 9 of 71

    Abbreviation Description BOM BQ CBEAPSA COW CRA CRM DEA PDEA DRA DRT DWA EA ECSA ED EIA EMP EMPr ENS ERA FDD FRA GCIMC HOA

    HWC HV ICE IPP IQ LES LUPO MTO MV NERSA NNIF NTC OHS Act ORHVS PCC POC POD PTM&DC QOS SACNASP SAHRA

    Bill of Materials Budget Quote Certification Board for Environmental Assessment Practitioners South Africa Site Supervisor Concept Release Approval Customer Relationship Management Department of Environmental Affairs Provincial Department of Environmental Affairs Definition Release Approval Design Review Team Department of Water Affairs Environmental Authorisation Engineering Council of South Africa Electricity Delivery Environmental Impact Assessment Environmental Management Plan Environmental Management Programme Electrical Network Schematic Execution Release Approval Final Design Document Finalisation Release Approval Group Capital Investment Monitoring Committee Heads of Agreement(a non-binding document outlining the main issues relevant to a tentative agreement) Heritage Western Cape High Voltage Indicative Cost Estimate Independent Power Producer Indicative Quote Eskom Line Engineering Services Land Use Planning Ordinance Mountain to Forest Medium Voltage National Energy Regulator of South Africa National Network Integration Forum National Transmission Company Occupational Health and Safety Act Operating Regulations for High Voltage Systems Point of Common Coupling Point of Connection Point of Delivery Protection, Telecommunications, Metering, and Direct Current Quality of Supply South African Council for Natural Scientific Professions South African Heritage Resources Agency

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 10 of 71

    Abbreviation Description

    SHE SNC TEF TEXCO TIC Tx WBS

    Safety Health and Environment Shared Network Cost Technical Evaluation Forum Transmission Executive Committee Transmission Investment Committee Eskom Transmission Division Work Breakdown Structure

    2.4.2 Implementation Date

    The implementation date for this procedure is the date on which this document is authorised

    2.5 ROLES AND RESPONSIBILITIES

    The implementation responsibilities of this procedure are outlined in Section 3 below. However, the details of the allocation of responsibilities between Eskom and the Self-Build Customer are explained in Annexure E.

    2.6 PROCESS FOR MONITORING

    The monitoring of effectiveness of this procedure will be the accountability of the Grid Connections Oversight Committee which comprises members from Transmission Grid Planning, the Group Customer Service Grid Access Unit, Group Technology Power Delivery Engineering, and Group Capital. Moreover, self-Assessment audits and Customer feedback would be used to ensure effective implementation of this procedure.

    Any gaps or opportunities for improvement that are identified will be incorporated in the next review.

    3. GENERAL CONDITIONS AND GUIDELINES FOR SELF-BUILD IN TRANSMISSION

    The Transmission Division of Eskom has decided to allow Customers to build their dedicated and directly related connection assets. This is meant to respond to the increasing need for self-build which has been expressed by Customers.

    The Transmission Division recognises that there may be cases where it would be beneficial to both Eskom and the Customer to opt for Self-Build. For example, there may be circumstances

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 11 of 71

    where a Customer is in a more advantageous position than Eskom to build his/her connection assets and thus achieve efficiencies in the capital cost and/or connection timelines.

    The detailed conditions governing self-build option are listed in Annexure A.

    3.1 KEY PRINCIPLES

    The principal reason for allowing Self-Build at the Transmission network level is to afford the Customer the opportunity to seek efficiencies in capital costs and timelines in connecting their plants or load to the grid.

    The following principles shall apply in a self-build project: The Customer may apply to exercise the self-build option; The right of the Customer to opt for the self-build option must be balanced against the

    inalienable right of the National Transmission Company to protect the integrity and security of the shared Transmission System.

    The National Transmission Company shall determine the connection method and the point of connection for any generation or load project. While an IPP or load customer can request a modification to their connection method, the modification will only be allowable where it is technically and financially justifiable and adheres to the Grid Code, Eskom specifications and standards.

    The National Transmission Company shall take over the ownership of the self-built assets.

    In cases where the self-built assets do not comply to the applicable standards, the National Transmission Company reserves the right to refuse the energisation and connection of those assets to the shared network. Eskom shall in such cases request the Customer to rectify the identified defects in the self-built assets at the Customers expense. The Customer may request Eskom to correct the defects, in which case the scope of works to correct the defects shall be treated by Eskom as a recoverable project and the full cost thereof shall be recovered from the Customer in accordance with Eskoms procedure for recoverable projects.

    The Self-Build option shall apply only to the dedicated Customer connection assets.

    The Self-Build option is intended for single-Customer projects and may not be used for groups of Customers.

    Any associated reinforcements required elsewhere on the Transmission system will not be eligible for self-build.

    The self-build assets shall be built to Eskoms standards and specifications. This is

    intended to protect the safety, integrity, and security of the Transmission system.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 12 of 71

    Eskom will recover from the self-build Customer any inspection, testing, and supervision costs incurred in ensuring that the self-built assets are built to Eskom standards and specifications.

    The self-build Customer must ensure that the use of scarce national resources such as line routes are well-thought through such that no barrier is placed on the future development of the network.

    To facilitate maintainability and compatibility with the existing Eskom plant, Customers are required to source their primary plant and secondary plant equipment from existing Eskom contract suppliers. The items of plant selected must be those on existing Eskom contracts.

    The Self-Build Customer takes full accountability for its own and its agents Safety, Health and Environmental (SHE) incidents during the duration of the self-build project.

    3.2 APPLICATION FOR SELF-BUILD

    A Customer electing to make use of the self-build option to construct his/her own connection-infrastructure to connect to the transmission grid for the purposes of an electricity supply connection (load customer) or to export electricity to the grid (as a generator), or both MUST do so in writing. The application for the self-build option will be managed in accordance with the Eskom Project Life Cycle Model (PLCM) via the Direct Customer Process.

    The Customer will have two opportunities to apply for the self-build option: 1. At the time of the Customers initial application, the Customer may indicate a preference for the self- build option which will then be provided-for in the scope outlined in the cost estimate letter; or 2. After the cost estimate letter has been issued by Eskom, at the cost-estimate acceptance stage, the Customer also has an opportunity to indicate his/her preference for self-build.

    In the latter case above (i.e. option 2) a revised cost estimate will have to be issued to the Customer detailing a revised scope of works excluding the self-build scope of works, a revised cost estimate and a revised project schedule. This cost-estimate will now be referred to as the Self-Build Cost Estimate and it will only reflect the portion of the works that will still be executed by Eskom.

    NB: The Customers request to exercise the self-build option has to be in writing (in both instances).

    If the Customer indicates his/her Self-Build preference only at the budget quotation stage (BQ stage) then all negotiations with Eskom will have to start afresh.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 13 of 71

    3.3 THE SELF-BUILD PROCESS AND ITS LINKAGES WITH THE ESKOM QUOTATION AND ENVIRONMENTAL AUTHORISATION PROCESSES

    The linkages of the self-build process with the established Eskom processes of Customer Quotations and Environmental Authorisation are depicted in the flow-diagrams below:

    Figure 1: Customer Application Process (From initial application up to BQ stage)

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 14 of 71

    Figure 2: Customer Application Process (showing touch points between the various Parties in the Project Lifecycle)

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 15 of 71

    3.4 ALLOCATION OF RESPONSIBILITIES BETWEEN THE CUSTOMER AND ESKOM IN A SELF-BUILD PROJECT

    3.4.1 Customers Responsibilities (Contestable works) The following activities are considered contestable works and may be allocated to the Customer for self-build:

    Route and site selection. Environmental Impact Assessment (EIA). Environmental Authorisation (EA). Route and site acquisition All other land development assessments required; applications, permits and statutory

    approvals. Land rights:

    o Servitude and Title Deeds for HV lines and substations. o Only land rights registered against the title deed of a property will be accepted. o Servitude and Title Deeds for access roads and Control Plant cabling and repeater

    stations. o The statutory approvals, permits and licenses required.

    Concept designs (subject to Eskom design requirements as explained in Annexures F, G, and K).

    Detailed design (subject to Eskom design requirements as explained in Annexures F, G, and K).

    Transmission line specifications for all line components Construction profiles for the Transmission line Construction method statements Equipment/material purchasing. Construction. Works and assets that are required by Eskom for system protection, communication and

    metering. Pre-commissioning tests. Site clean-up, disposal of waste, and anti-erosion works in accordance with the EIMP. The Customer is responsible to provide all the documentary proof to the Eskom Project

    Manager confirming that all the holding points tests (as specified in Annexure B) have been successfully passed

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 16 of 71

    3.4.2 Eskoms Responsibilities (Monopoly Works) The following activities are considered monopoly works and will be carried out by Eskom:

    Network Planning Report and/or Business Case Report, motivating the need for an asset to be created

    Network Planning shall influence and approve the preferred network concept solutions and decisions.

    The determination of the point of connection and the connection method (Network Planning Solution) subject to the Customer providing the load or generation information as requested by Eskom.

    All work related to upstream, shared, or existing assets and any associated upstream system reinforcements.

    Works and assets that cannot be safely and efficiently separated from the existing live system.

    Network operational control and switching activities. The outline specifications and requirements relating to sites, routes and

    wayleaves/servitudes. The Eskom standards to be used for High Voltage lines and substations. The verification of compliance with Eskom Standards for the concept and detailed design of

    the self-build connection assets. The verification of compliance with Eskom Standards during the construction phase at the

    holding points determined by Eskom. Leading Customers Control Plant contractors during the inspection, testing and

    commissioning of the newly constructed asset with final sign-off and acceptance as objective. Maintenance of the self-built assets after they have been successfully commissioned and

    their ownership having been transferred to Eskom.

    3.5 CONNECTION CHARGES APPLICABLE TO SELF-BUILD CUSTOMER PROJECTS

    3.5.1 Costs Payable

    The Self-Build Customer will be required to pay a Connection Charge that comprises the costs of the Eskom component of the works (i.e. the monopoly works) to be performed and all Eskom costs associated with the connection works.

    The charges that make up the connection charge will be calculated in accordance with the principles set out below:

    The Eskom costs associated with the connection works. These costs include the Eskom component of the works (i.e. the monopoly works), project development costs, the cost of supervision and inspection of the self-built assets to ensure compliance with technical and safety standards and procedures, plus, where applicable, the premium-supply charges.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 17 of 71

    The premium-supply charges are only applicable in cases where the Customer has elected to apply for a connection that requires infrastructure that is more than that of a standard connection.

    All costs associated with the monopoly works shall be payable upfront. These will be provided through the quotation process (i.e. cost estimate and budget quotation letters) and will be based on estimated costs. A final reconciliation of costs will be done upon the completion of the project.

    The final cost will be based on the actual costs incurred. Any shortfall will be payable by the Customer and any over-charging by Eskom will be refunded to the Customer by Eskom. However, any over-recovery by Eskom will only be refunded to the Customer after Eskom has taken over the self-built assets and after there has been a final reconciliation of costs.

    The connection charges associated with the monopoly works will be required to be paid at the time of accepting the budget quotation, unless a written and signed payment schedule has been agreed with Eskom.

    In the cases where Eskom needs to purchase long lead-time material for its component of the works, the Customer shall be obliged to pay the cost of such long lead-time material before Eskom can proceed with the monopoly works. This is meant to prevent Eskom from incurring any liability for such long-lead items costs.

    In the cases where construction will be carried out over an extended period of time, the Customer may be required to make part-payments for the phases of the construction before Eskom proceeds with the various phases.

    In cases where a payment schedule has been agreed with Eskom, the Customer may be required to provide an acceptable connection-charge guarantee at the time of accepting the budget quotation.

    The NTC may, for the purposes of providing for its future requirements, request the Self-Build Customer to build assets with greater capacity than it needs for its own purposes. In such cases, the NTC shall refund the Customer all the costs related to the greater capacity. The quantum of the refund will be based on a written agreement between the Customer and the NTC.

    3.5.2 Sharing of the Dedicated Customer Assets

    In the event when, at some point in the future, the self-built assets that were constructed in accordance with this procedure, become shared (i.e. in cases where, at some future point, other unrelated Customers utilise or benefit from the self-built assets or a portion of the self-built assets), the original Self-Build Customer will be refunded all or a portion of the capital costs incurred less accumulated depreciation.

    The NTC and the Customer shall, at the time of concluding the connection and the use-of-system agreements, agree on the value of the self-built connection assets. In the event where an agreement is not reached between the two parties, the value of the connection assets shall be based on the lower of the actual costs and the NTCs reasonable cost to do the same work (i.e. the least life cycle costs as determined by the NTC).

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 18 of 71

    Any rebate to the Customer shall take into consideration the following principles: The original cost, straight line depreciation, and remaining useful life of the assets.

    The NERSA Guidelines on Transmission connection charges.

    3.5.3 Transfer of Ownership

    The Customer shall, after successful commissioning, transfer full ownership of the self-built connection assets to the NTC, including all environmental authorisations, approvals and approved permits.

    The assets shall be transferred to Eskom at cost and in accordance with the guideline in Annexure J.

    The Self-Build Customer retains the defects liability for the transferred assets.

    3.6 HOLDING POINTS APPLICABLE TO SELF-BUILD PROJECTS TO ASSURE COMPLIANCE WITH ESKOM STANDARDS AND SPECIFICATIONS

    It is important to note that, in a self-build Customer project, the Customer assumes all the project risk and associated liabilities from the beginning of the project up until successful commissioning and handover of the constructed asset to Eskom. The holding points specified in this section are intended to provide assurance to Eskom that the prevailing Eskom Standards and specifications are adhered-to during the self-build project execution.

    The holding points provide a mechanism for Eskom to inspect and test the works during the construction phase. This has the benefit of ensuring that any non-conformances are resolved as early as possible in the project life cycle.

    A detailed checklist of holding points required by Eskom is specified in Annexure B.

    4. AUTHORIZATION

    This document has been seen and accepted by: Designation / Stakeholder Division

    Group Executive Transmission Group Executive Group Customer Services TEXCO Members Transmission Grid Managers Transmission The Head of the Grid Access Unit Group Customer Service Key Customer Executives Group Customer Service General Manager Group Technology Power Delivery Engineering Senior General Manager Group Technology Engineering

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 19 of 71

    Designation / Stakeholder Division General Managers Group Capital

    5. REVISIONS

    Date Rev. Compiler Remarks 26-March-2013 0.00 Mbulelo Kibido New Number and the Draft Procedure for Tx Self Build

    Projects 05-July-2013 0.16 Roy Estment. Version accepted by the Development Team 08-August-2013 0.17 Mbulelo Kibido Version influenced by TEXCO, GAU, and Group Technology 15-August-2013 1 Mbulelo Kibido Authorised Version

    6. DEVELOPMENT TEAM

    The following people were involved in the development of this document: Archibold Mogokonyane - Group Capital Land Development, Asanda Taylor, Transmission, Bernard Magoro, Transmission System Operator, Bheki Ntshangase, Transmission Grids, Braam Groenewald, Group Technology, Caswell Ndlhovu, Transmission Grid Planning; Charles Kalima, Group Commercial, Elliot Vilakazi, Group Commercial Land & Related Services, Eric Shunmagum, Transmission AME, Ernest Grunewald, Group Commercial Land & Related Services, Harish Mohabir, Transmission AME, Johan Bornman, Group Capital PDP, John Geeringh, Eskom Real Estate ( ERE): Land Development,, Juan La Grange, Transmission Office of the GE, Jurie Groenewald, Group Capital PDD, Leslie Naidoo, Transmission Grid Planning, Malesela Sekhasimbe, Group Commercial,

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 20 of 71

    Mansoor Barday, Distribution Division, Mmamie Kodisang, Eskom Transmission, Mutenda Tshipala, Group Customer Service,

    Philip Wahl, Distribution Western Cape OU, Phineas Tlhatlhetji, Group Technology Substation Design, Prince Kara, Group Technology, PTM&C, Ray Asalan, Distribution Division, Riaz Vajeth, Group Technology Line Design, Richard Chinzvende, Transmission Grids, Roger Cormack, Group Technology HV Plant, Roy Estment, Transmission Grid Planning, Solly Matlala, Transmission BIPM, Thys Bower, Group Technology PTM&C, Wolfgang Bohmer, Group Customer Services Grid Access Unit,

    7. ACKNOWLEDGEMENTS

    The contribution of the development team and their generosity in dedicating their time to this project is acknowledged and greatly appreciated.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 21 of 71

    ANNEXURE A:

    Eskoms conditions and requirements for Self-Build projects:

    1. The Customer has to confirm in writing their request for the self-build option. 2. The Customer has to accept and pay Eskoms cost estimate/re-quoted cost estimate. 3. The Customer has to conclude a contract with Eskom, detailing the conditions under which

    the self-build option will be undertaken. 4. The Customer has to appoint only Eskom-accepted consultants to manage and prepare the

    concept design as well as the final designs. 5. Only Consultant-approved designs will be accepted by Eskom for further consideration and

    verification purposes. 6. The Customer has to appoint only professionally-registered engineering surveyors/land

    surveyors to handle all surveying functions and obtain other approvals. 7. The Customer has to appoint only RSA government-approved environmental consultants to

    handle all environmental functions and obtain other approvals. 8. The Customer has to appoint only Eskom-accepted construction contractors to manage and

    execute the construction works as per the detailed project scope of works as outlined in the final design package.

    9. The Customer has to ensure that only Eskom-accepted suppliers are used to source the items of material and equipment needed for the execution of self-build projects.

    10. The Customer has to use only new material for the self-build asset creation project. No reconditioned or pre-used material or equipment will be allowed.

    11. The Customer has to apply the Eskom Standards and specifications to the designs and construction.

    Note: In order to ensure adherence to Eskom requirements 4, 6, 7 and 8, the Customer has to obtain

    written acceptance from the various Eskom functional departments for the use of these

    contractors prior to contracting. This will serve as a compliance check.

    In order to ensure adherence to requirement 9, the Customer has to ensure that the contractor

    provides Eskoms Site Supervisor with a detailed listing of all material items and equipment

    purchases as well as the source from which these items and equipment have been purchased.

    To adhere to requirement 11: the responsible project engineer or specialist from Eskom Group

    Technology must be consulted to obtain a copy of the national or regional preferred standards

    and drawings. The applicable Eskom Standards, specifications, and Guidelines appear in

    Appendices C, F, G, and K.

    The above documents must be contained in the Eskom Project Managers project file.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 22 of 71

    ANNEXURE B:

    Checklist of Eskoms holding points

    The following holding points during the project life cycle will apply to the self-build projects: The Eskom Project Manager will be responsible for physically gathering written proof that all these holding points have been successfully passed and that they have been adhered to. All the written proofs must be filed in the correct Eskom project file or any other approved project-data repository.

    Note: the project should not proceed if these requirements are not met.

    Description of phase and activity Responsible

    Pre-project planning

    1. Proof of the written request from the Customer to execute the project by utilising the self-build option.

    Eskom Customer Executive

    2. Written confirmation from Customer Executive that all Eskoms requirements for self-build projects have been provided to the Customer and that the Customer has accepted them (see Annexure A for a full listing of the Eskom requirements).

    Eskom Customer Executive

    3. Confirmation of proposed technical solution. Eskom Senior Planning Engineer

    4. Confirmation of Customers acceptance and payment of the cost estimate

    Eskom Customer Executive

    Confirmation of all four of the above conditions will result in CRA approval.

    Concept phase

    5. Acceptance by Eskom Land Development of the route and/or site selection as indicated by the Customer.

    Eskom Survey Manager

    6. Confirmation from Eskom that EIA, EMPr and any other approvals/permit conditions undertaken by the Customer have been reviewed prior to submission to the authorities.

    Eskom Environmental Officer and/or

    Eskom Land & Rights Officer

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 23 of 71

    Description of phase and activity Responsible

    7. Copy of written acceptance from applicable Eskom functional departments of the Customer-appointed consultants to manage and prepare the concept design as well as the final designs. Ensure that the copy of written acceptance to the Customer is filed as well.

    (See Condition 4 in Annexure A).

    Eskom Project Manager

    8. Copy to the Customer of Eskoms written acceptance of the Customer-appointed engineering surveyors/land surveyors to handle all surveying functions and other approvals.

    (See Condition 6 in Annexure A.)

    Eskom Survey Manager

    9. Copy to the Customer of Eskoms written acceptance of the Customer-appointed environmental consultants to handle all environmental functions and other approvals.

    (See Condition 7 in Annexure A.)

    Eskom Environmental Officer

    10. Confirmation that the Customers concept design has been accepted/supported by the relevant DRT.

    Eskom Project Manager

    Confirmation of all above conditions will result in DRA approval.

    Definition phase

    11. Confirmation that the Customers Final Design Package is accepted / supported.

    Eskom Project Manager

    12. Copy to the Customer of Eskom Project Managements written acceptance of the Customer-appointed construction contractors (power and control plant contractors).

    (See Condition 8 in Annexure A.)

    Eskom Project Manager

    Confirmation of above condition will result in ERA approval.

    Execution Phase 1 (prior to commencement of construction)

    13. Review by Eskom of the approval / permit conditions prior to and during the construction phase checking that all legal requirements

    Eskom Acquisition Advisor

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 24 of 71

    Description of phase and activity Responsible

    to commence construction have been adhered to, which may include all or some of the following but are not limited to:

    Landowners contracts / registration in Deeds Office

    Environmental Authorisations DEA

    DEA (Province)

    Local and Provincial Authorities

    SAHRA and any provincial Heritage Authorities such as HWC

    Telkom, Neotel

    Roads national (SANRAL), provincial and local road agencies

    DWA

    Transnet

    ESKOM, TELKOM & Municipalities crossings of other power lines and services

    Pipeline authorities: crossings or close proximity to pipelines

    Mining authorities: underground and open cast mining activities

    Wind farms: proximity to these

    Aviation/Airport authority: proximity to aircraft approaches

    Other approvals / permits as may be required by legislation such as water use licences, tree-cutting permits, borrow pits, etc.

    AND

    Eskom Environmental Advisor

    14. Confirmation that the project kick-off meeting has taken place and all Eskom pre-construction requirements have been adhered to

    Eskom Project Manager

    Confirmation of all the above requirements will allow the Customers contractor to commence construction. Where the contractor has commenced work without satisfying the above

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 25 of 71

    Description of phase and activity Responsible

    requirements, all such work shall be undertaken at the Customers risk and expense in the event that the Contractor fails to meet Eskoms requirements.

    Execution Phase 2 (during construction)

    15. Verification that all the material purchases listed in the Final Design Package were procured from Eskom-Accepted suppliers.

    Eskom Site Supervisor

    16. Adherence to outlined Eskom Quality Control hold points during construction including ESKOM SHEQ processes and procedures.

    Eskom Site Supervisor

    17. After completion of construction BUT prior to commencement of testing and commissioning. (Verification activity: As-Built drawings and all equipment data sheets submitted in a format that is acceptable to Eskom.)

    Eskom Site Supervisor

    18. Ensure that the Self-Build agreement has been signed by both parties before energising.

    Eskom Customer Executive

    Confirmation of all the above requirements will result HOA approval.

    Finalisation Phase

    19. All Quality Control check sheets as per the Final Design Package and

    all handover documents duly completed and signed by all parties.

    Eskom Site Supervisor

    20. All warranties and guarantees in respect of all items purchased by the Customer are handed over to Eskom.

    Eskom Project Manager

    21. Compliance with EMP.

    Eskom Site Supervisor and / or Eskom Environmental

    Advisor

    22. Obtain sign-off from the Landowner(s) and deliver release forms to Eskom confirming that the landowner(s) agree that their properties have been rehabilitated after construction activities and that the property is in at least the same condition as it was before construction started

    Eskom Project Manager

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 26 of 71

    Description of phase and activity Responsible

    23. Receipt of the As-Built design package from the Customer Eskom Project Manager

    Confirmation of all the above requirements will result in FRA approval.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 27 of 71

    ANNEXURE C: Applicable standards, specifications, guidelines, and requirements

    The Customer shall liaise with the Eskom Project Manager to obtain the latest versions of the Eskom standards, specifications, and procedures applicable to the self-build works. The Eskom Project Manager shall facilitate contact between the Customer and the relevant Eskom technical specialists to address any queries relating to Eskoms standards, specifications, and procedures, or other matters relating to the self-build works.

    The following Eskom technical specialists are authorised to determine the standards, specifications, and procedures applicable to the self-build works:

    1. Line Designs and Specifications: The Head of Group Technology Line Design,

    2. Substation Designs and Specifications: The Head of Group Technology Substation Design,

    3. HV Plant Specifications: The Head of Group Technology HV Plant,

    4. PTM&C Specifications and Requirements: The Head of Group Technology, PTM&C,

    5. Network Planning Specifications and Requirements: The Corporate Specialist - Transmission Grid Planning

    6. Lands & Rights Requirements and Specifications: Land & Rights Specialist Eskom Group Commercial Commodities

    7. Environmental Requirements: The Environmental Specialist for Eskom Real Estate ( ERE): Land Development,

    8. Customer Application Requirements: The Head of Group Customer Services Grid Access unit

    9. Safety Requirements: The Transmission Safety Executive

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 28 of 71

    ANNEXURE D:

    Undertaking by the Customer to use information provided to him/her solely for the purpose for which it is intended

    USE OF ESKOM STANDARDS AND SPECIFICATIONS, GUIDELINES, AND COPYRIGHTED MATERIAL

    ACCEPT CONDITIONS

    Signed at ____________________________ on this _______ day of ______________________ 20____

    ______________________________________ _________________________________________

    (Signature) (Print Name) (on behalf of company)

    Company Name

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 29 of 71

    ANNEXURE E:

    Details of Customers and Eskoms Responsibilities during a Transmission Self-Build Project

    1 General Customers Responsibilities: The Customer or his/her Agent must ensure the following:

    1.1 The completion of the Eskom application form, detailing the requirements.

    1.2 The provision for PTM&C and energy metering requirements in the scope of works 1.3 The appointment of design engineers who will be responsible for the design and the presentation of the concept and detailed design documents. These designers must be Eskom-Accepted consultants, as they will be responsible for design and construction management. To protect Eskoms interests in a Transmission self- build scheme agreement, the design to be used must be accepted/supported by the Design Review Team prior to the commencement of any construction work. This is intended to ensure that the network is constructed to Eskoms standards and specifications in order that the new assets can be maintained satisfactorily by Eskom after construction.

    1.4 The appointment of a negotiator or negotiation consultant to assist with the route acquisition process.

    1.5 The appointment of an engineering surveyor / land surveyor who is responsible for the cadastral/registration survey. The surveyor must be registered with Plato.

    1.6 The appointment of an environmental consultant to conduct the environmental process. This consultant must be formally registered and/or accepted by Government to conduct EIAs.

    1.7 The appointment of relevant Town and Regional Planners for relevant municipal approvals. 1.8 The appointment of the contractor that will do the construction. The construction contractor must be an Eskom-accepted/accredited contractor. Such a contractor will therefore be well versed and knowledgeable in the construction of Transmission assets.

    1.9 The preparation of a tax invoice for submission to Eskom in order to effect any capital allowance payment (if applicable). 1.10 The development of Health & Safety specifications and the approval of the contractors Health & Safety Plan.

    1.11 Prepare the power and control plant for testing and commissioning.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 30 of 71

    1.12 Assist Eskom with the testing and commissioning activities. 1.13 Timely completion of the project Eskom absolves itself from any liability for the late delivery of any assets being constructed by the Customer.

    1.14 The Customer must provide a oneyear warranty against poor workmanship to Eskom.

    The responsibilities of the resources/Consultants/Contractors/agents as appointed by the Customer are as detailed in section 2 below:

    2 Land Surveying, Land Acquisition and Environmental Customer

    Responsibilities: The Customer must appoint the following parties for land development activities:

    A professionally-registered surveyor who is responsible for lands and rights, the engineering survey and geographic mapping and obtaining of statutory approvals.

    A negotiator to assist with the negotiations associated with the acquisition of a servitude.

    A Government-approved environmental consultant who is responsible for obtaining environmental authorisations.

    A professional land surveyor who is responsible for the cadastral survey.

    A Conveyancer who is responsible for the registration of servitudes or the transfer of land.

    The responsibilities related to each of these environmental activities will be further described in the following sections.

    3 Lands and Rights - Customer Responsibilities: Route selection

    o Approval of route by Eskom Land Development and Senior Project Engineer.

    o Ensuring that the route plan adheres to the Eskom Standards.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 31 of 71

    o The route plan must include the final route and substation site, as well as any switching station site if required, all access roads, all road / rail crossings with the kilometre reading, cadastral boundaries and property descriptions, a co-ordinated list of all the bend points on the route and affected servitudes.

    Note: the access road, from the main tar road up to the Eskom yard, has to be accepted/supported by Eskom Project Manager. This access road to the site must be suitable for a sedan two-wheel drive vehicle, and must be wide enough and have the correct carrying capacity to accommodate construction vehicles/low-bed trucks (including those used for transporting transformers). The access road must also be surveyed as a servitude and registered in the Deeds Office as an access road in favour of Eskom, and the cost of this registration is for the Customer's account.

    o The route must follow the shortest possible distance and use minimal bends to minimise cost and be done under the guidance of the Eskom Standards.

    o The route has to take into account that dams and wetlands must be avoided where possible and feasible

    The EIA has to include the soil resistivity tests for part of the substation and switching site selection process as well as the proposed bend points to ensure the sites suitability

    Eskom must approve any changes required to its networks (e.g. line deviations) to accommodate the Customer line or substation.

    All statutory approvals and licences must be obtained that are required for the complete life cycle of the asset. Specific caution should be taken where limited approval is granted, such as instances where Eskom could be liable for relocation costs at any stage.

    Obtaining the schedule of owners:

    o This list must include the property description, registered owner, contact person, postal address, telephone/fax number and special requests/conditions.

    o All communication with property owners must be recorded and listed per property owner.

    Schedule of mineral rights holders the Mineral and Petroleum Resources Development Act, 2002. The Customer has to give Eskom all the details surrounding mineral rights and mineral rights holders. The Customer has to negotiate and supply land rights to Eskom that are void

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 32 of 71

    of the cost risk for the relocation of services at any stage. These conditions have to be contained in the notarial deed of servitude.

    Consideration and compensation for land rights the consideration payable for the land rights acquired must be based on the principles set out in the Expropriation Act and must furthermore be in accordance with the Eskom Consideration and Compensation Standard (EST 32-844). Any additional payments or sweeteners paid to landowners must be made through separate agreement and may not be reflected in the Deed of Servitude as part of the price.

    The option has to be included in the agreement to register the servitude/s in favour of Eskom with Eskom servitude conditions of access, construction and maintenance at the time of registration and the option to cede to Eskom with Eskoms servitude conditions of maintenance.

    Exercise options / transfer of ownership to Eskom

    o Ensure that the Eskom ceding clause and Eskom conditions are included see note below.

    o It must be noted that the Customer is liable for all costs, damages and rework should any land parcel be missed in the process of obtaining rights for Eskom.

    o The registration process in general terms must occur for the route and in general or specific terms for the substation, and within 6 months of construction the route must be defined in specific terms in the Deeds Office.

    o Note: although it is a fairly simple notarial process to cede a servitude from one entity to another entity, one item which should be considered is the fact the Eskom is exempt from some of the Regulations of Act 70 of 1970, section 6 (1) (a) and 6(1)(a). This in effect means that Eskom need not acquire approval from the Minister of Agriculture for the registration of a servitude exceeding a width of 15 metres or an area exceeding 225 square metres, if a private person acquires a servitude in a right which exceeds the width and area mentioned. Therefore a site exceeding 15 m x 15 m or a line servitude required for an area wider than 7.5 m on either side of the centre line, does require Ministerial approval. Therefore there is not much which they could do as far as HV sites and HV line servitudes are concerned. They will need Ministerial approval for most servitudes. Accordingly, it could be in the interests of all concerned that the servitude should include the option of being registered on behalf of Eskom from the outset as obtaining approval from the Minister could take an extremely long time.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 33 of 71

    4 Environmental Authorisation Process Customer Responsibilities: A procedurally sound environmental impact assessment must be conducted for the HV power line and substation, which must comply with the requirements of the National Environmental Management Act, 1998 (Act No. 107 of 1998), as amended, and the Environmental Impact Assessment Regulations, 2010, addressing the project as a whole and meeting all relevant legal and procedural requirements.

    a) Submit the Basic Assessment Report/ Environmental Impact Assessment Report to the relevant competent environmental authority for authorisation.

    b) Consult Eskom (Land Development) as an interested and affected party during the BAR/ EIA phase.

    c) Forward the original submission, Environmental Authorisation (EA), Construction Environmental Management Plan (EMP), Maintenance EMP and Decommissioning EMP to Eskom.

    Eskom has to be consulted regarding the Maintenance and Decommissioning EMP prior to their submission to DEA prior to initial submission or to finalisation after EA.

    d) Eskom can request all other correspondence concerning the project. e) A list of all interested and affected parties (electronic format) should be made available to Eskom

    on completion of the project.

    f) All legal conditions, including EA conditions and conditions contained in the approvals granted by the relevant authorities (DEA, SAHRA (HWC), local and provincial authorities, DWA, etc.) must be adhered to.

    g) All environmental legal liabilities and claims arising from the activities of the Customer and any of the Customers subcontractors shall be for the Customers expense.

    5 Engineering survey or design consultant where applicable (Customer-appointed) a) Submits all records to Eskom including the following:

    Profiles, tower positions, line and pegging information in ASCII format and CAD diagrams.

    All field surveying and calculations necessary to complete the work.

    Any wayleave documentation that was required in any changes to 11kV, 22kV, or other affected power lines, and all the survey work relating to such changes.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 34 of 71

    Profiles and drawings (scale as per Eskom specifications) with the necessary topography indicated (refer to the standard listed in Annexure C).

    All templated profiles have to be submitted in PLSCAD format for soft copy and as hard copy.

    All co-ordinate data, including as-pegged data, setting out data, etc. Adherence to the as-built template requirements

    b) Civil engineering plans and designs that need approval at municipal level in terms of the municipal building plan submissions have to be part of the responsibility of the Customers consultant.

    c) Labelling of the line has to be done both in the field and on the poles, and this labelling must be reflected on the plans.

    d) No handover may take place until all statutory approvals and legal requirements for the project have been obtained and checked by Eskom; and no construction may start until all the legal requirements are met and have been checked by Eskom.

    Soft and hard copies of all statutory approvals have to be submitted.

    All hard copies of plans must have the approval stamp on them.

    Relevant approvals include but are not restricted to: the local authority, Telkom, Neotel, Roads, Rail, Water Affairs, etc.

    6 Cadastral / registration survey Customer Responsibilities a) Registration surveys shall be conducted for the subdivision of the substation site (either by

    subdivision or registration of a servitude), all as per the Land Survey Act No. 8 of 1997. Registration surveys, including the accepted/supported diagrams, must be completed.

    Registration copies of accepted/supported diagrams from the Surveyor-General and title deeds for the line and substation have to be delivered to Eskom Land Development by registered post or by hand.

    b) The language used in the diagrams and title deeds must be English or Afrikaans, as specified by the individual landowners.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 35 of 71

    c) Eskom will require an abbreviated hard copy x 1 and a digital copy of the survey records co-ordinate list, working plan and report, together with a digital copy of each diagram for our GIS data base. One photocopy each of statutory approvals and local authority endorsements required for the registration process must accompany the hard copies of the survey record.

    d) Insurance / Claim Event contravention of any provision of the Land Survey Act 8/1997 in connection with a cadastral survey period following the completion of the whole of the services or earlier termination: as specified in the Land Survey Act No. 8 of 1997.

    7 Geographic mapping Customer Responsibilities a) The standards for the submission for any drawings or spatial data are listed under the Geographic

    Mapping Standards in Annexure D, and must be adhered to.

    b) Both the hard copy and electronic format must be provided for all submissions. c) All co-ordinates have to be in WGS 84 and in the correct Lo. d) The acceptable formats are CAD format i.e. Microstation to AutoCAD. Shape files will also be

    required (.dwd, .dgn, shape formats). The conductor types, tower types and numbering of towers in field are required too.

    e) Route plans have to be at the largest sensible scale. 1:5 000, 1:10000 or 1:25 000 (maximum) or whichever larger scale is suitable for the plans. Odd scales will not be accepted.

    f) An aerial photography backdrop has to be provided if available. g) Raster / topographic backdrop has to be provided, i.e. any additional information which assists

    with the readability of the plans.

    h) All templated profiles (design drawings) have to be submitted in PLSCAD (.bak) format as well as three hard copy plans, of which at least one must be a Sepia copy signed off by the design engineer.

    i) Besides the design drawings, the As-Built drawings and GPS co-ordinates of all support structures must be submitted once the project has been constructed.

    j) The proposed schematic layout (single line diagram) has to be provided. k) Commissioning dates or time lines should be supplied. l) Assist with updating the electrical diagrams.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 36 of 71

    8 Lands & Rights Conveyance Customer Responsibilities a) A Conveyancer must be appointed to handle the conveyance work.

    b) It should be noted that no delegation of authority is possible for the assigning of Eskoms rights to a third party. Therefore all draft deeds must be submitted to Eskom for scrutiny and signing in general and in specific terms.

    c) If the landowner specifies the requirement that his/her attorney is to be used, in such cases both Eskoms and the landowners attorneys will handle the conveyance of that land parcel.

    d) Registration in general terms, or in specific terms for the substation where the accepted diagrams are obtained from the Surveyor Generals office, has to begin as soon as possible and the deeds transfer must be completed within 8 months of exercising the options (barring unforeseen circumstances with landowners, which must be substantiated and documented).

    e) All costs have to be borne by the Customer.

    9 Design Engineer / Consultant Customer Responsibilities The Customers design engineer / Consultant is responsible for the following:

    To ensure that the scope of the works covers all the assets required to make the Customer connection complete; including energy metering requirements.

    Presenting the concept design, final design, and execution plan at the Design Review Team (DRT) as arranged by the responsible Eskom project engineer. Should there be any action items following the DRT meeting, the consultant shall be required to make the suggested changes and present the project again. The concept design report must be made available two weeks prior to the DRT. An outline of the required content of this report for substation and lines projects respectively is shown in Table 3.

    Providing costing for the project.

    Submitting the final design document (FDD) to Eskom DRT for review. The following must be submitted: 1 printed A4 FDD, 1 copy of all drawings printed to scale, CD containing electronic copies of all documents in the original format, not in a *pdf format.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 37 of 71

    Eskom DRT only accepts the FDD, it does not approve it. The Eskom Project Engineer merely accepts and confirms that the design has been done in line with the Eskom Standards as listed in Annexure A. Eskom expects the FDD to be approved by the consultants professional engineer, resting the final professional responsibility for the design with the consultant. The consultant will be liable for the soundness of the design for the entire lifetime of the designed asset. After reviewing, if there are no changes to be made, the FDD will be made available by Eskom DRT to the Eskom Project Manager. Note that all drawings must be established by using the Microstation Software package [*.dgn format] or latest Eskom-compatible software.

    The required content of final design documents for substation and line projects respectively is shown in Table 4.

    Any design changes made during construction must be communicated to ESKOM and reflected in the as-built documents.

    Arranging to have the final constructed assets as-built drawings signed-off before handing them over to Eskom.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 38 of 71

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 39 of 71

    10 Table 3: Concept design report requirements Substations and Lines

    Concept design for HV substation projects Concept design for HV lines projects

    Conducted assessments: o Environmental Impact o All national, applicable provincial and local bodies, including but not limited to the

    DEA; DEA&PDEA (Province); SAHRA (South African Heritage Resources Agency); Provincial Heritage e.g. HWC (Western Cape); DAFF (Department of Forestry and Fisheries); MTO (Mountain to Ocean Western Cape forestry) and others; Provincial Parks, e.g. Cape Nature (Western Cape); DWAF (Department of Water Affairs); Local authorities, including Aviation and Rail authorities Specialist studies as required by the DEA such as for avifauna; Others as required.

    o Soil resistivity o Other assessments as deemed fit / factors influencing the overall design; including wind,

    pollution monitoring, geotechnical investigations, vandalism, bird, fire, lightning and icing studies.

    Bill of materials (highlighting long lead-time equipment)

    Conducted assessments: o Air-wave communications /

    reception availability o Security o Pollution level

    Design philosophy covering the following:

    o Station electric diagrams / operating diagrams

    o Conceptual layout drawings o Earthing requirements o Surge / lightning protection o Equipment and conductor

    ratings considering loading and future fault levels

    Other supporting documentation

    Design philosophy covering the following: o Executive summary o Scope o Power line route o Conductor and insulators o Wind loading used on structure

    designs o Structure designs o Foundation designs o Earthing and shielding design o Measures to reduce environmental

    impact o Other assessments as deemed fit /

    factors influencing the overall design; including wind, pollution monitoring, geotechnical studies, vandalism, bird, fire, lightning and icing studies.

    Structure drawings Foundation drawings Other supporting documentation

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 40 of 71

    11 Table 4: Final design document requirements HV substations and HV lines

    Final design for HV substation projects Final design for HV lines projects

    Project details

    Civil

    Architectural

    Power and control plant

    o Bill of quantities

    o Bill of materials

    o All applicable design drawings

    Temporary arrangements

    MV Lines

    HV Cable

    Urban MV cable

    Quality assurance

    o Substation quality-checking document

    o Environmental checklist

    o SHE report

    Geotechnical investigation and foundation information

    Note: design drawings must include Long Sections, Contour plans, GPS co-ordinates, Oil management systems, drainage plans, engineering calculations and topographical plans.

    Design philosophy

    Templated profile

    Staking table

    Bill of materials and quantities

    Structure drawings

    Hardware assembly drawings

    Stringing charts

    Buy-out specifications

    Buyers guide specifications

    OPGW and fibre specifications

    Health & Safety specification

    Geotechnical investigation and foundation Information

    Project Form (DRA)

    Project schedule

    Contact persons

    Standards Specialist studies, including but not limited to;

    transposition, unbalance, Ferranti effect, reactor sizing and insulation co-ordination studies.

    Note: design drawings must include Long Sections, GPS co-ordinates, engineering calculations and topographical plans. The submission must conform to the design pack format available from Group Technology Line Design

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 41 of 71

    11.1 Contractors responsibilities (Customer-appointed) The contractor should not commence any construction work unless he/she is in possession of

    and Eskom-accepted final design document (FDD). The contractor must provide to the Eskom Site Supervisor a list of all material to be used and the

    suppliers from which these materials have been procured.

    The contractor must provide to the Eskom Site Supervisor a detailed construction programme, clearly indicating all quality control hold points as specified by Eskom.

    The contractor is responsible for safety checks and acceptance, and the development of a Health & Safety Plan to be accepted by the Customer/consultant.

    The contractor is responsible for the installation of control plant panels with associated cabling and the termination of the cables.

    Submission of as-built drawings after construction, which will contain at least but are not limited to the following:

    - Support structure labels numbers. - Final co-ordinates of all support structures and in the case of a cable, the position of the

    cable at 10-m intervals. - Structure types used. - Cable or conductor type and size. - Transformer specifications. - Transformer label. - Confirmation of feeder name, as well as the official from and to points. - Final soil-type information and drawings of foundations. - Any deviation from the design, together with associated distances (changes must be

    clearly indicated). - Conductor attachment heights per structure. - Clearances above crossings of services such as road, rail or telecommunication

    infrastructure. - Points where gates have been installed. - Confirmation of adherence to the special conditions of the statutory authorities and

    landowners. - Certificate of Inspection from roads agencies. - Indication of any damage to property and/or crops, with the extent of such damage. - Any other information which is deemed necessary. - Signature of responsible construction person.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 42 of 71

    All materials must be Eskom-accepted products and must be procured by the Customer from an Eskom-accepted supplier. The Customer is responsible for planning and securing the rest of the Customers material.

    As the responsibilities of the Customer have now been defined, the following sections focus on outlining the responsibilities of different Eskom departments for Transmission self-build projects.

    12 Eskoms Responsibilities (during self-build projects) 12.1 Eskom Group Customer Services Responsibilities

    Customer Services will serve as the interface between Eskom and the Customer until Project Management takes over this role, after which they should assist. It is also Customer Services responsibility to make sure that the Project Manager appointed on the Customer's side is integrated in the Eskom Project Management Team.

    Customer Services responsibilities are summarised as follows:

    When the Customers application has been received, ensure that it is registered in the CRM system. Provide the relevant reference number to the Customer for use in future communication and status queries.

    Arrange the project scope clarification meeting with the Customer. Invite all project stakeholders and if necessary also the Project Manager.

    Initiate the cost estimation process in the pre-project planning phase. The Customer must receive a cost estimate letter, detailing what works are contestable and what works will be a monopoly service. This must include the relevant conditions and the charges payable. The target of 60 days (2 months) is set in order to provide the cost estimate letter (to be in line with the load Customer process).

    If the Customer accepts the conditions and fees as set out in the cost estimate and requests that the project should proceed, ensure that the Customer pays the quotation fee as set out in the cost estimate letter. Manage the original documentation and acceptance letters.

    Ensure that the project obtains the required concept release approval (CRA) from the delegated manager(s) or investment committee.

    Be involved in the concept phase. The Design Review Team should approve the concept design on which costs will be based so that the Customer can be given a budget quotation.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 43 of 71

    Serve as interface between the Customer and Eskom for any queries about the budget quotation and conditions specified in the accompanying letter.

    Ensure that the necessary Customer acceptance and payments are received prior to releasing the project to the definition phase.

    Be involved in the definition phase:

    o The final design package should be accepted as the basis on which tenders will refine the project costs. A final letter should be sent to the Customer indicating the refined conditions and final payments, and may include a final quotation (or revised budget quotation) if costs fall beyond the accuracy ranges of the budget quotation. Manage the original documentation and acceptance letters.

    Manage the contracting process between Eskom and the Customer.

    o Ensure the management of the signing of all Eskom contracts as well as the self-build project contract between Eskom and the Customer, setting out the terms and conditions.

    Assist as interface between The Eskom Project Manager and the Customer during the execution phase.

    Attend all relevant project meetings

    Activate the Customer on the billing system after commissioning.

    During project finalisation, Customer Services will be responsible for reconciling the Customers payments versus final project costs, according to the accepted quotations and contracts.

    Note: the cost allocation and final reconciliation (Eskom vs. Customer) will be in accordance with the accepted principles for the recovery of capital.

    12.2 Eskom Network Planning - Responsibilities Network Planning is responsible for the following:

    Obtain from the Customer its high-level requirements, expected reliability and future requirements (load forecast and phasing plan).

    Details of technology of load/generation, and any special requirements e.g. starting large motors.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 44 of 71

    Discuss the network configuration with the Customer (including voltage levels, alternative solutions) and agree with the Customer what connection method is to be used.

    Determine ownership and boundaries.

    Specify the requirements for assets owned, operated and maintained by Eskom. Network planning must inform the Customer that Eskom-owned plant under the self-build project has

    to be done by Eskom-accepted consultants, vendors and service providers, and only using Eskom standard equipment (to be confirmed by Eskom DRT).

    Interface with Land Development on the route selection and EIA input.

    Network Planning has to ensure that the network performance issues, quality of supply data and studies (e.g. harmonics, flicker, voltage dips, motor-starting studies, etc) have been addressed.

    Perform load flow simulation studies to ensure that the proposed network configuration caters optimally for the Customers needs as well as meeting all upstream and adjacent network requirements.

    Define the high-level scope of the self-build project, which shall include the following:

    o Main power plant requirements.

    o Demarcation between Customers responsibility and Eskoms responsibility.

    o Acceptable level of network reliability and quality of supply.

    o Location of metering point and point of common coupling (PCC). o Customers expected completion date.

    Network Planning will provide the following information to enable adequate design:

    o Network data (e.g. single line diagram and transformer/line modelling data). o Fault levels (3-phase and single line-to-ground) of present and future network at

    PCC.

    Where the project entails any generation, the following will also be specified by Network Planning to supplement the grid codes and the relevant NRS standards:

    o Power factor/ reactive power requirements.

    o Voltage limits and voltage control requirements.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 45 of 71

    Network Planning will provide final confirmation of connectability at the budget quote stage. At this stage, any outstanding specialist such as quality of supply impacts, power transfer capability studies (P-V, P-Q and Q-V curves, etc) where the project entails generation must have been completed.

    Obtaining the necessary concept release approval (CRA) in order to make the necessary budget available to the project.

    Network Planning will participate at DRT with the technical evaluation of self-build projects.

    12.3 Eskom Land Development Responsibilities: Eskom Land Developments responsibilities are outlined in the following subsections in terms of Lands and Rights, Environmental Approvals, Engineering Survey, Cadastral/Registration Survey, Geographic Mapping and Conveyancing.

    Eskom Land Development should take responsibility for:

    Checking of route as supplied by the Customer-appointed surveyor.

    Checking statutory / environmental and other approvals (e.g. Municipality, District Municipality, LUPO, Roads, Telkom, Neotel, etc.) as supplied by the Customer.

    Ensuring that no construction may take place until all statutory approvals for the project have been obtained and checked by Eskom for completeness and onerous conditions.

    Receiving the survey records (co-ordinate list, working plan and report).

    Receiving the SurveyorGenerals approved diagrams for substation and servitudes.

    Verification of correctness of cadastral surveys, in specific, framed SG diagrams. It is suggested that these should be verified by Eskom prior to submitting them to the Surveyor-General for approval.

    Scrutinising and signing documents for the registration of servitudes in favour of Eskom.

    Capturing information and updating LARGIS / TxIS.

    12.3.1 Environmental Authorisation Process Eskom Responsibilities

    Ensuring that EA and EMPrs for construction, maintenance and decommission are in place, as well as all related legal approvals / permits, such as SAHRA, Cape Nature, DWA, etc. Specific care must be taken in terms of licences for water use, borrow pits, and tree-cutting and herbicide permits.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 46 of 71

    Checking that the maintenance and decommissioning requirements set out in the EMPrs are feasible.

    Receiving the list of all interested and affected parties consulted by the Customers EIA consultant.

    12.4 Engineering Line Design Eskom Responsibilities

    To interact with the Self-Build Customer and provide guidance on line design matters.

    To issue the Customer with the ESKOM line specifications, standards, designs, and practices notes where applicable.

    On completion of the services or part of services, the Eskom Line Design Department will assess the work for compliance with the Eskom Standards.

    Receive the Transmission Lines checklist.

    Checking the spanning sheets as supplied by the Customer-appointed surveyor.

    Profiles and templates.

    12.5 Geographic Mapping Eskom Responsibilities

    Create the geographically referenced network elements in the Geographical Information System (GIS) and ensure spatial reference with the correct connectivity.

    Publish the geographically referenced network design as schematic operating diagrams (substation, feeder or network operating diagrams (SOD, FOD or NOD)).

    Assist with creating the spanning sheets, adding tops and bottoms.

    12.6 Eskom Substation Design Responsibilities: The substation engineer is responsible for the following:

    Ensuring that all the consultant designs are done according to Eskom's specifications and standards.

    Utilising / ensuring the utilisation of the self-build specification document as a design guideline.

  • Transmission Self-Build Procedure

    Unique Identifier: 240-61713594 Revision: 0 Page: 47 of 71

    Ensuring that the consultant enlists the acceptance of spanning sheets from Land Development and Line Design prior to the meeting of the applicable Design Review Team (DRT).

    Ensuring that the consultant presents a concept design document (Volume 2) to the DRT.

    Receiving the costing of the DRT-accepted design: This will be submitted by the consultant to the Eskom-appointed project engineer in preparation for the design release approval (DRA) for submission to the Investment Committee for approval.

    Checking that all changes to the concept design suggested at the DRT are made.

    Verifying that the final design document (Volume 3) for power and control plant as provided by the consultant is in accordance with the Eskom specifications and compliance.

    Making the final design document available to The Eskom Project Manager.

    12.7 Eskom Project Management Responsibilities: The Project Manager/Project Co-ordinator is responsible for the following:

    Obtaining the necessary execution release approval (ERA) in order to make the necessary budget available for the project.

    Interfacing and procuring materials have to be purchased by Eskom.

    Appointing a dedicated Eskom Site Supervisor (COW) who will be responsible for all inspections of the contestable works and who will perform quality inspections based on the accepted FDD.

    Taking over the asset from the contracting party after the completion of testing and commissioning work.

    Attend all project meetings as requested by the Customer/consultant.

    Closin