tynagh ccgt power station · the site consists of a 400 megawatt combined cycle gas turbine power...
TRANSCRIPT
1
TYNAGH CCGT ANNUAL ENVIRONMENTAL REPORT 2011
Tynagh CCGT Power Station
Annual Environmental Report
2011
Reference Number: TYN\ENV\2011\01
Date: 31/03/2012
Issue: Rev. 01
Authors: Donal Fanning, Plant Manager – GE Energy
Eoin O’Sullivan, EHS Specialist – GE Energy
Colin D’Arcy, Technical Manager - Tynagh Energy Ltd.
Approved: Colin D’Arcy, Technical Manager - Tynagh Energy Ltd.
2
TYNAGH CCGT ANNUAL ENVIRONMENTAL REPORT 2011
Table of Contents
Executive Summary 3
Facility Summary Information 4
Air Emissions 6
Waste Water 9
Complaints & Incidents 12
Bund testing 14
Groundwater /Contaminated Land summary report 17
ELRA & CRAMP 19
Environmental Management Programme 21
Noise 24
Resource Usage/ Energy Efficiency 26
Waste - PRTR 29
3
TYNAGH CCGT ANNUAL ENVIRONMENTAL REPORT 2011
Executive Summary
2011 was an excellent year from an environmental compliance perspective. There were
no breaches, exceedances or non-compliances and there was only one complaint
recorded.
The power plant running regime in 2011 was significantly different from previous years.
The plant run hours were down and plant starts were up; this shift was due to market
conditions and record wind generation levels and it had a considerable impact on our
emissions and energy usage.
Another major change during the year was the re-commissioning of the Gas Turbine
secondary fuel (Gasoil) system. For security of supply reasons and at the direction of the
CER Tynagh re-commissioned the system and underwent Eirgrid testing. In addition to
ongoing Eirgrid testing requirements (up to twice a year) the unit must regularly operate
on its secondary fuel to ensure continued operability of the system.
Some high-level environmental projects and operational milestones for 2011 are as
follows:
• ISO 14001 and 9001 re-accreditation was achieved.
• Achieved no non-compliances with the IPPC license in 2011 as confirmed via the independent sampling reports, various EPA site audits and inspections and internal monitoring and reporting.
• New hazardous waste storage area was built.
• An assessment of risk of catastrophic tank failure and overtopping of bund wall of the main diesel storage tank was completed by external consultant.
• Plant operator, GE Energy received a Global Star Award – GE’s highest internal award for health and safety.
• Completed internal IPPC permit review day to ensure on-going compliance with IPPC license and GHG permit requirements.
• A 25% reduction in off-line electricity usage was achieved.
The format of this year’s AER is significantly different from previous years. The
operations team previously took great pride in producing a very detailed AER of highest
quality. This year we were requested to utilise EPA templates and minimise additional
detail; as a result, this report is very concise and to the point and much of the information
previously supplied is no longer included. Full reports and supporting data etc. is
available on site and maintained on file for viewing and/or inspection
4
Facility Summary Information
Additional comments / supplemental information:
None.
Facility Manager , GE Energy (Ltd)
Date
Technical Manager, Tynagh Energy (Ltd)
Date
B3
National Grid Reference (6E, 6 N)
P0700-01
Tynagh Energy Limited
Derryfrench, Tynagh, Loughrea, Co. Galway
3511NACE Code
The operation of combustion installations with a rated thermal input equal to or greater than 50MW
30-Mar-12Colin D'Arcy
Facility Information Summary
Licence Register Number
Name of site
Class of Activity
RBME risk category
1745E, 21293N
Site Location
Donal Fanning
A brief description of the activities/process
at the site for the reporting year. This should
include information such as production
increases or decreases on site, any
infrastructural changes, environmental
performance improvements which were
measured during the reporting year;
All the data and information presented in this report has been checked and certified as being accurate. The
quality of the information is assured to meet license requirements.
Reviewed and approved by
30-Mar-12
The site consists of a 400 Megawatt combined cycle gas turbine power plant that has been built on the former
Tynagh Mines site, Loughrea, Co. Galway. Tynagh Energy Limited is the site licensee. The site IPPC license was
issued in 2004 and became operational in March 2006. This report covers the fifth full commercial year of
licensed activity.
Tynagh is an advanced combined cycle gas turbine (CCGT) power plant. CCGT technology is a highly efficient
energy conversion process whereby electricity is generated by burning natural gas in a gas turbine (GT)
generator. The waste GT exhaust gas energy is subsequently recovered in a heat recovery steam generator
(HRSG) to produce additional electricity in a separate steam turbine (ST) generator. This dual process ensures the
maximum energy is extracted from every unit of natural gas consumed. The power plant was built under a
turnkey contract by a consortium of General Electric Company/General Electric International Inc. and Gama
Power Systems Inc. The plant is operated and maintained by GE Energy (Ireland) Limited on behalf of Tynagh
Energy Ltd.
Declaration:
6
Air
Additional comments / supplemental information:
The fugitive emissions from the power plant due to natural gas venting to atmosphere for
operations and maintenance activities have been included in gas consumption calculations.
As per EPA guide note only licensed emissions are included in this template. Other PRTR
reported emissions include N20, CH4, NMVOC, CO2 and SF6.
AER summary template-AIR emissions
Parameter
/Substance
Annual fugitive
emission (kg/annum)
Quantificaton
method M/C/E
N/A
2
No
3Basic air
monitoring
checklist AGN2 Yes
Table 2: Licensed Mass Emissions/Ambient data-periodic monitoring (non-continuous)
Emission
reference no: Parameter/ Substance
Date of
Monitoring
ELV in licence
or any revision
thereof Licence Compliance criteria Measured value
Unit of
measurement
Compliant with
licence limit Method of analysis
Annual mass
load (kg)
% change in mass load
from previous year +/- Comments
N/A
Note 1: Volumetric flow shall be included as a reportable parameter
4 Yes
5Yes
6
No
7
No
Table 3: Summary of average emissions -continuous monitoring
Emission
reference no: Parameter/ Substance
ELV in licence or
any revision
thereof
Averaging
Period Compliance Criteria
Units of
measurement Annual Emission Annual maximum
Monitoring
Equipment
downtime (hours)
% compliance
current
reporting year Comments
A2-1Nitrogen oxides
(NOx/NO2)
50 mg/m3 on
Gas
120 mg/m3 on
Gasoil (Diesel)
1 hour All 1-hour averages < 2 x ELV mg/Nm3 142913.37 Kg
949000 Kg On Gas
2689320 Kg On
Gasoil Diesel
1 Hour 100%
Dual fuel site Corrected
to 15% Oxygen. No day
Invalid. Plant not online
during downtime
Do you have a proactive service agreement for each piece of continuous monitoring equipment?
Trained and qualified technicians maintain and calibrate
monitoring equipment on site. If additional expertise is
required this is obtained as required. Back-up spare
equipment is also kept and maintained on site.
Did your site experience any abatement system bypasses? If yes please detail them in table 4 below
Continuous Monitoring Does your site carry out continuous air emissions monitoring?
If yes please review your continuous monitoring data and report the required fields below in Table 3 and
compare it to its relevant Emission Limit Value (ELV)
Did continuous monitoring equipment experience downtime? If yes please record downtime in table 3 below.
Periodic/Non-Continuous Monitoring
Are there any results in breach of licence requirements? If yes please provide brief details in the comment
section of Table 2 below.
Was all monitoring carried out in accordance with EPA
guidance note AG2 and using the basic air monitoring
checklist?
Additional information
1
Does your site have licensed air emissions? If yes please complete table 1, 2 and 3 below for the
current reporting year and answer further questions. If you do not have licenced emissions and do not
complete a solvent management plan (table 5 and 6) you only need to complete table 1 fugitive
emissions on site belowYes IPPC licence P0700-01
Table 1: Fugitive emissions
A2-1 Carbon monoxide (CO)
25 mg/m3 on
Gas
40 mg/m3 on
Gasoil (Diesel)
1 hour All 1-hour averages < 2 x ELV mg/Nm3 106014.1 Kg
474500 Kg On Gas
896440 Kg On
Gasoil Diesel
3 Hours 100%
Dual fuel site Corrected
to 15% Oxygen. No day
Invalid.
A2-1Sulphur oxides
(SOx/SO2)
120 mg/m3 on
Gasoil (Diesel)1 hour All 1-hour averages < 2 x ELV mg/Nm3 8492.88 Kg
2689320 Kg On
Gasoil Diesel1 Hour 100%
Dual fuel site Corrected
to 15% Oxygen
A2-1 Volumetric flow 5.2E+7 m3 1 Day Daily average < ELV m3 5.5E+09
1.9E+10 m3
Natural Gas
2.24E+10 m3 on
Gasoil Diesel
Calculated Value 100%Flow is calculated based
on mass exhaust flow
note 1: Volumetric flow shall be included as a reportable parameter.
Table 4: Abatement system bypass reporting table Bypass protocol
Date* Duration** (hours) Location
N/A
8 Do you have a total Emission Limit Value of direct and fugitive emissions on site? if yes please fill out table 5No
Solvent
regulations
Reporting year Total solvent input on
site (kg)
Total VOC
emissions to Air
from entire site
(direct and
fugitive)
Total VOC
emissions as
%of solvent
input Total Emission Limit Value
(ELV) in licence or any revision
thereof
Compliance
N/ASELECT
(I) Inputs (kg)
Solvent
(I) Inputs (kg)
Organic solvent
emission in
waste gases(kg)
Solvents lost in
water (kg)
Collected waste solvent (kg) Fugitive Organic
Solvent (kg)
Solvent released in
other ways e.g. by-
passes (kg)
Solvents destroyed
onsite through
physical reaction
e.g.
incineration(kg)
Total emission of
Solvent to air (kg)
N/A
Total
Table 6: Solvent Mass Balance summary
(O) Outputs (kg)
* this should include all dates that an abatement system bypass occurred
** an accurate record of time bypass beginning and end should be logged on site and maintained for future
Agency inspections please refer to bypass protocol link
Table 5: Solvent Management Plan Summary
Total VOC Emission limit value
Please refer to linked solvent regulations to
complete table 5 and 6
Reason for bypass Corrective action
9
Waste Water
Additional comments / supplemental information:
As per EPA guide note only licensed emissions are included in this template. Other PRTR
reported emissions include total nitrogen, TOC and Chlorides
AER Monitoring returns summary template-WATER/WASTEWATER(SEWER)
2
Yes
Location
reference
Location
relative to site
activities
PRTR ParameterLicenced
Parameter
Monitoring
date
ELV or trigger
level in licence
or any revision
thereof*
Licence
Compliance criteria Measured value
Unit of
measurement
Compliant with
licence Comments
N/A
*trigger values may be agreed by the Agency outside of licence conditions
Location
Reference
Date of
inspectionSource of
contamination
N/A SELECT
3No
4
External /Internal
Lab Quality
checklist
Assessment of
results checklist Yes
Table 3: Licensed Emissions to water and /or wastewater (sewer)-periodic monitoring (non-continuous)
Emission
reference no:
Emission
released to
Parameter/ Substance
Note 1 Type of sample
Date of
Monitoring Averaging period
ELV or trigger
values in licence or
any revision
thereof Note 2
Licence Compliance
criteria Measured value
Unit of
measurement
Compliant with
licence Method of analysis
Procedural
reference source
Procedural
reference
standard number
Annual mass load
(kg)
% change in mass
load from
previous year +/- Comments
SW1 Water Total Dissolved Solids composite weekly Weekly 5000
All results < 1.2 times
ELV, plus 8 from ten
results must be < ELV
1324 mg/L yes Gravimetric analysis
APHA / AWWA
"Standard
Methods"
2540-C
45576.9 -28.1measure weekly
average used here
SW1 Water Suspended Solids composite weekly Weekly 30
All results < 1.2 times
ELV, plus 8 from ten
results must be < ELV
10 mg/L yes Gravimetric analysis
APHA / AWWA
"Standard
Methods" 2540-D
338 -40.0measure weekly
average used here
SW1 Water Ammonia (as N) composite weekly Weekly 1.5
All results < 1.2 times
ELV, plus 8 from ten
results must be < ELV
0.22 mg/L yes Nessler method
APHA / AWWA
"Standard
Methods"
4500-NH3 and
ASTM d1426-08
9.8 -46.7measure weekly
average used here
SW1 Water Total phosphorus composite weekly Weekly 0.1
All results < 1.2 times
ELV, plus 8 from ten
results must be < ELV
<0.05 mg/L yesDigestion +
Spectrophotometry
APHA / AWWA
"Standard
Methods" 4500-P-E
1.7 -37.0measured weekly
average used here
SW1 Water BOD composite monthly Monthly 20
All results < 1.2 times
ELV, plus 8 from ten
results must be < ELV
1.8 mg/L yesDissolved Oxygen Meter
(Electrode)
APHA / AWWA
"Standard
Methods"
TM045, MEWAM
bod5 2nd
ed.hmso 1988
62.4 0.8
measured
monthly- average
given here
SW2 water pH discrete weekly Weekly 6-9*
*not specified in
licence site follows
EQS
7.9 pH units yes pH Meter (Electrode)
APHA / AWWA
"Standard
Methods" 4500-H-B
Not applicable Not applicablemeasured weekly
average used here
SW2 Water COD discrete weekly Weekly 30*
*not specified in
licence site follows
EQS
16.9 mg/L yesSpectrophotometry
(Colorimetry) ISO
IS0 6060-1989
determination of
COD using Dr.
Not applicable Not applicablemeasured weekly
average used here
Was all monitoring carried out in accordance with EPA
guidance and checklists for Quality of Aqueous Monitoring
Data Reported to the EPA? If no please detail what areas
require improvement in additional information box
Site lab has developed a quality manual and attended EPA conferences on Lab assurance quality control.
Operation of these requirements is an on-going project. Where necessary an accredited lab is also used
for analysis.
Comments
Licensed Emissions to water and /or wastewater(sewer)-periodic monitoring (non-continuous)
Was there any result in breach of licence requirements? If yes please provide brief details in the
comment section of Table 3 below
Was it a requirement of your licence to carry out visual inspections on any surface water
discharges or watercourses on or near your site? If yes please complete table 2 below
summarising only any evidence of contamination noted during visual inspectionsDaily visual inspections at surface water discharge location sw2.
No contamination observed 2011
Table 1: Ambient monitoring
Table 2: Visual inspections-Please only enter details where contamination was observed.
Description of contamination Corrective action
Additional information
1
Does your site have licensed emissions direct to surface water or direct to sewer? If yes
please complete table 3 and 4 below for the current reporting year and answer further
questions. If you do not have licenced emissions you only need to complete table 1 and
/table 2 below for ambient monitoring and visual inspectionsYes
Trained and qualified technicians maintain and calibrate
monitoring equipment on site. If additional expertise is required
this is obtained as required.
SW2 WaterTotal petroleum
hydrocarbonsdiscrete weekly Weekly
*not specified in
licence site follows
EQS
<1 mg/L yesGC (Gas
Chromatography)US EPA
Method for EPH,
Massachusetts
dept of ep, 1998
Not applicable Not applicablemeasured weekly
average used here
Note 1: Volumetric flow shall be included as a reportable parameter
5 Yes
6
No
7
No
8No
Table 4: Summary of average emissions -continuous monitoring
Emission
reference no:
Emission
released to Parameter/ Substance
ELV or trigger
values in license
or any revision
thereof
Averaging
Period
Compliance
Criteria
Units of
measurement
Annual Emission for
current reporting year
(kg)
% change +/- from
previous reporting
year
Monitoring
Equipment
downtime (hours)
% compliance
current reporting
year
SW1 Water Volumetric flow 1128 1 hour
No flow value
shall exceed the
specific limit
m3/day 35326910 -62% 0 100
SW1 Water Temperature 25 30 minutes
No
temperature
value shall
exceed the limit
value
degrees C not applicable not applicable 0 100
SW1 Water pH between 6-9 1 hour
No pH value
shall deviate
from the
specified range
pH units not applicable not applicable 0 100
SW1 Water Dissolved Oxygen none 30 minutes None specified mg/L not applicable not applicable 0 100
SW1 Water Conductivity none 30 minutes All values < ELV µS/cm @20oC not applicable not applicable 0 100
note 1: Volumetric flow shall be included as a reportable parameter.
Table 5: Abatement system bypass reporting tableDate Duration (hours) Location Resultant
emissions
Reason for
bypass
Corrective
action*
Was a report
submitted to the
EPA?
When was this report
submitted?
N/A SELECT
*Measures taken or proposed to reduce or limit bypass frequency
Site follows best practice and sets limit for conductivity based on TDS limit
Trained and qualified technicians maintain and calibrate
monitoring equipment on site. If additional expertise is required
this is obtained as required.
Calibrations and maintenance were carried out when plant was not discharging
No limits specified but site follows best practice guidelines
Calibrations and maintenance were carried out when plant was not discharging
Did continuous monitoring equipment experience downtime? If yes please record downtime in
table 4 below
Calibration and maintenance is only carried out when plant is
not discharging. The WWTP also has triple redundant
instrumentation.
Do you have a proactive service contract for each piece of continuous monitoring equipment on
site?
Did abatement system bypass occur during the reporting year? If yes please complete table 5
below
Comments
Calibrations and maintenance were carried out when plant was not discharging
Note 2: Where Emission Limit Values (ELV) do not apply to your licence please compare results against EQS for Surface water or relevant receptor quality standards
Continuous monitoring Additional Information
Does your site carry out continuous emissions to water/sewer monitoring?
Online monitoring and daily inspections. In-house lab testing.
If yes please summarise your continuous monitoring data below in Table 4 and compare it to
its relevant Emission Limit Value (ELV)
12
Complaints – incidents.
Additional comments / supplemental information.
Compliance with the conditions of our IPPC Licence is of the highest priority for Tynagh
Energy Limited and the Plant Operator and all environmental concerns / complaints are
thoroughly investigated.
Noise Complaints:
Historically the vast majority of the complaints received by the plant since commercial
operation have been noise related. All complaints have been fully investigated and these
investigations along with annual noise surveys have shown the plant to be operating within
the conditions of its license.
The 2011 annual noise survey showed the plant to be below license limits 45.8 dB (day) &
43.5 dB (night) versus limits of 55 dB and 45 dB respectively. See noise section for further
information.
Notwithstanding the ongoing noise compliance detailed above and in response to a
resident’s continued concern, Tynagh Energy Limited has engaged a noise consultant to
carry out a focused study, including development of an environmental noise model (currently
underway), aimed at reducing noise levels at the residence in question. The complainant has
been kept informed with regard to progress on this matter.
Additional information
Yes
Date Category Other type (please specify)
Brief description of
complaint (Free txt <20
words)
Corrective action< 20
words Resolution status Resolution date
Further
information
5th Jan 2011 Noise
Verbal complaint of
noise at residence at
night.
Plant was off-line at
some of the times.
Contacted complainant.
Investigated with ops
team. Reviewed noise
sources with noise
consultant under
different operating
conditions.
Ongoing Annual noise
surveys have
showed in
compliance with
licence
conditions.
Working with
noise consultants
and engineering
team to resolve.
Total complaints
open at start of
reporting year 0
Total new
complaints
received during
reporting year 1
Total complaints
closed during
reporting year 0
Balance of
complaints end of
reporting year 1
Additional information
No
What is an incident
Table 2 Incidents summary
Date of occurrence Incident nature Location of occurrence
Incident category*please
refer to guidance Receptor Cause of incident
Other
cause(please
specify)
Activity in
progress at
time of incident Communication Occurrence
Corrective
action<20
words
Preventative
action <20
words Resolution status
Resolution
date
Likelihood of
reoccurrence
N/A SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT
Total number of
incidents current
year 0
Total number of
incidents previous
year 0
% reduction/
increase N/A
Complaints
Have you received any environmental complaints in the current reporting year? If yes please complete summary
details of complaints received on site in table 1 below
Table 1 Complaints summary
Incidents
Have any incidents occurred on site in the current reporting year? Please list all incidents for current reporting
year in Table 2 below
*For information on how to report and what constitutes
an incident
14
Bund testing
Additional comments / supplemental information:
As per EPA guidance note table 1 & 2 only list failure of bunds in the previous year and are
therefore blank as there were no failures in 2011.
Bund testing schedules and results were communicated in previous years AERs. Full bund
testing reports and pipeline inspections are required under IPPC licence and are available
for inspection on site.
Bund testing Additional information
1 Yes
As per EPA guide note only
failures are reported -
there were none in 2011.
2 Please provide integrity testing frequency period 3 years
3 Yes
This is available on site and
was attached in previous
years AERs including the
last full pipeline inspection
report.
Bund/Containment
structure ID Type Specify Other type Product containment Actual capacity Capacity required* Type of integrity test
N/A
* Capacity required should comply with 25% or 110% containment rule as detailed in your licence
Commentary
4 Yes
Site testing procedures
follows this guidance.
5 Are channels/transfer systems to remote containment systems tested? Yes
6 Are channels/transfer systems compliant in both integrity and available volume? Yes
7 Yes
All outside bunds have
high level liquid alarms.
Inside bunds do not.
8 Yes
Part of site maintenance
programme
Bund/pipe testing report summary ALL IPPC/WASTE licensed facilities Intensive agriculture facilities please use alternative template
dropdown menu click to see options
Are you required by your licence to undertake integrity testing on bunds and containment structures ? if yes
please fill out table 1 below listing all bunds and containment structures on site
Table 1: Summary details of bund integrity test
Has integrity testing been carried out in accordance with licence requirements and are all structures tested in
line with BS8007/EPA Guidance?
Do all sumps and chambers have high level liquid alarms?
If yes to Q7 are these failsafe systems included in a maintenance and testing programme?
Does the site maintain a register of bunds, underground pipelines (including stormwater and foul), Tanks,
sumps and containers? (containers refers to "Chemstore" type units and mobile bunds)
1 Yes
2 Please provide integrity testing frequency period Other (please specify) 5 Years
Structure ID Type system Material of construction:
Does this structure have
Secondary containment?
Type of secondary
containment
Type integrity testing
Integrity reports
maintained on site?
N/A
Are you required by your licence to undertake integrity testing on underground structures e.g. pipelines or
sumps etc ? if yes please fill out table 2 below listing all underground structures and pipelines on site
Table 2: Summary details of underground structures/pipeline integrity test
Pipeline/underground structure testing
17
Groundwater /Contaminated land summary report
Additional comments / supplemental information:
The site is built on an historic mining site with contamination issues from previous activities.
This is not due to any activities the current operator undertakes.
The licensee advised the Agency during a previous site inspection that the enforcement
category for the facility, as determined by the annual risk rating assessment is increased as
a result of contaminated land within the assessment. The licensee was unsure whether this
should apply to the facility.
The Agency noted that the issue of historical contamination in the Tynagh area is not related
to any current and/or previous activities at the licensed facility. It was considered appropriate
that the licensee could omit the contaminated land issue from future risk classification
assessments. (EPA inspection report: Reference number 700-0110SI04KR, 15/09/2010)
Note: Sampling at AGW2 is no longer required (ref: (700)07S104KR)
1 yes
2 no
3 yes
4 no
5 no
6
7
8
9
10
11 Have potential receptors been identified on and off site?
12 Is there evidence that contamination is migrating offsite?
Table 1: Upgradient Groundwater monitoring results
Date of
sampling
Sample
location
reference
Parameter/
Substance Methodology
Monitoring
frequency
Maximum
Concentration++
Average
Concentration+ unit GTV's* SELECT**
% change in average
concentration previous
year +/-
Upward trend in pollutant
concentration over last 5 years of
monitoring data
2011 AGW1 pH pH electrode bi-annual Not applicable 7.15 pH units SW EQS Not applicable No
2011 AGW1
Diesel range
organics
Standard
method bi-annual Not applicable <0.01 mg/L SW EQS No change No
.+ where average indicates arithmetic mean
.++ maximum concentration indicates the maximum measured concentration from all monitoring results produced during the reporting year
Table 2: Downgradient Groundwater monitoring results
Date of
sampling
Sample
location
reference
Parameter/
Substance Methodology
Monitoring
frequency
Maximum
Concentration
Average
Concentration unit GTV's* SELECT**
% change in average
concentration previous
year +/-
Upward trend in yearly average
pollutant concentration over last 5
years of monitoring data
2011 AGW3 pH pH electrode bi-annual Not applicable 7.03 pH units SW EQS Not applicable No
2011 AGW3
Diesel range
organics
Standard
method bi-annual Not applicable <0.01 mg/L SW EQS No change No
2011 AGW4 pH pH electrode bi-annual Not applicable 7.2 pH units SW EQS Not applicable No
2011 AGW4
Diesel range
organics
Standard
method bi-annual Not applicable <0.01 mg/L SW EQS No change No
Table 3: Soil results
Date of
sampling
Sample
location
reference
Parameter/
Substance Methodology
Monitoring
frequency
Maximum
Concentration
Average
Concentration unit
N/A SELECT
Comments
Schedule 5(ii)
Raw water and service water use
see note on previous pageIs there contaminated land and /or groundwater on site? If yes please answer q's 5-12
Is the contamination related to operations at the facility (either current and/or historic)
Have actions been taken to address contamination issues?If yes please summarise remediation strategies
Is there a licence condition to carry out/update ELRA for the site?
Has any type of risk assessment been carried out for the site?
Has a Conceptual Site Model been developed for the site?
Please specify the proposed time frame for the remediation strategy
Groundwater /Contaminated land summary report
Are you required to carry out groundwater monitoring as part of your licence requirements?
Are you required to carry out soil monitoring as part of your licence requirements?
Do you extract groundwater for use on site? If yes please specify use in comment section
19
ELRA & CRAMP
Additional comments / supplemental information:
None.
Commentary
1 Yes
2 Yes
No specific approval issued, but
assume it has been approved.
3 31/03/2009 Submitted in 2009 AER
4 31/03/2009 Mar-09
5 Insurance €3,000,000
6 Yes No.
7 TBC
8 01/03/2013 Annual review in-line with AER
9 Please list the top 10 risks assessed on your site in table 1 below
Table 1 ELRA summary information
Click here to access EPA
guidance on ELRA Operational Risk Assessment Category SELECT
Action
Date of
implementation of
mitigation measures Comment
Revised Risk score for
current reporting year ELRA costing
e.g
29 Decommissioning activities - incorrect waste disposal Significant volumes of waste will be
disposed of in the event of
decommissioning - risk of improper
disposal of waste streams that are not
usually handled in large volumes as
part of normal operation.
12 Operational controls
Prior to
Decommissioning
Assumed a fully documented
decommissioning procedure and
specific risk assessments will be
created prior to the event. 12 €540,000 Yes
1 Fire / explosion in production Firewater run-off and/or smoke
reaching the local environment 9 Operational controls 31/03/2009
All mitigation measures detailed in
full ELRA. 9 €99,000 Yes
27 Closure / Decommissioning - Fire at facility Introduction of abnormal ignition
sources during decommissioning e.g.
Cutting equipment or generation of
flammable fuel vapours during
drainage of excess / waste liquids.
9 Operational controls
Prior to
Decommissioning
Assumed a fully documented
decommissioning procedure and
specific risk assessments will be
created prior to the event. 9 €99,000 Yes
30 Closure / Decommissioning - IPPCL emission
exceedance
Under abnormal conditions of
decommissioning there is a risk of
IPPCL exceedances to waster water /
air.
9 Operational controls
Prior to
Decommissioning
Assumed a fully documented
decommissioning procedure and
specific risk assessments will be
created prior to the event. 9 €99,000 Yes
6 Fire / Explosion in transformer Firewater and/or smoke reaching the
local environment 6 Operational controls 31/03/2009
All mitigation measures detailed in
full ELRA. 6 €49,500 Yes
8 Fire / explosion from Natural Gas supply Release to atmosphere, Firewater
and/or smoke reaching the local
environment 6 Operational controls 31/03/2009
All mitigation measures detailed in
full ELRA. 6 €49,500 Yes
10 Leak from foul treatment system Contamination of soil , surface or
groundwater 6 Operational controls 31/03/2009
All mitigation measures detailed in
full ELRA. 6 €4,950 Yes
12 Spill to surface drainage from tanker (fuel, oil or
chemical)
Contamination of soil , surface or
groundwater 6 Operational controls 31/03/2009
All mitigation measures detailed in
full ELRA. 6 €9,900 Yes
28 Closure / Decommissioning - leaks & spills Potential spills of oils, lubricants and
chemicals associated with equipment &
pipework decommissioning.6 Operational controls 31/03/2009
All mitigation measures detailed in
full ELRA. 6 €9,900 Yes
5 Emission to air exceedance Emissions exceedance
5 Operational controls 31/03/2009
All mitigation measures detailed in
full ELRA. 5 €4,500 Yes
Total SELECT SELECT €965,250 Yes
1 Yes
2 Yes
No specific approval issued, but
assume it has been approved.
3 N/A Completed
4 Letter of Credit
5 05/04/2013
6
Outline - full plan to be
developed prior to
decommissioning.
Table 2 CRAMP summary information (NON Landfill)
Date of submission of plan Risk category Closure plan in place Clean closure
Restoration Aftercare
Management Plan
Change in Risk
category since
previous year Increase in risk category
Does the current
financial provision
cover the risk score?
Value of current
financial provision
for site
31/03/2009 3 Yes Yes Yes No SELECT Yes €500,000.00
Has a closure plan submission been approved by the Agency?
What is the timescale for submission?
What financial instrument do you have in place to cover known liabilities?
What is the date of expiry of this financial instrument?
What is the status of implementation of the plan?
Previous risk score
Mitigation measures to reduce risk ELRA
Does the current
financial provision
(FP) cover the risk
score?
Closure Restoration Aftercare Management Plan/ Restoration plan (CRAMP/RP)Was a closure or restoration plan a requirement of the licence?
Has this financial instrument/s been verified by the Agency?
What is the date of expiry of this financial instrument?
Date of next required review of the ELRA?
Risk ID Potential hazards Environmental effect
Environmental Liability Risk Assessment
Is it a requirement of your licence to complete an ELRA?
Has an initial ELRA been submitted to and approved by the Agency?
Please enter the date of submission of the initial ELRA
Date of most recent substantial ELRA update
What financial instrument/s do you have in place to cover unknown liabilities?
21
Environmental Management Programme
Additional comments / supplemental information:
None.
Additional Information
1 Yes
2 Yes
3 Yes
4 Yes
Environmental Management Programme (EMP) report
Objective Category Target
Status (%
completed) How target was progressed Responsibility Intermediate outcomes
Waste reduction/Raw material
usage efficiency
Challenging the site team to Reduce,
Recycle, Reuse by ongoing awareness
campaign
100 Ideas discussed at waste meeting. Presentation given at EHS
day (June 29) . Display stand completed in turbine hall. Waste
awareness emails distributed. Waste team member attended
council waste workshop. Team came up with award scheme
for best waste saving idea for 2012.
Waste Team Increased waste
segregation on site
Waste reduction/Raw material
usage efficiency
Review and implement site bin thrasher
in some site waste storage areas.
100 Led by site waste team. Installed at stores area for mixed
recyclable waste containers
Waste Team Improved
Environmental
Management Practices
Waste reduction/Raw material
usage efficiency
Label all underground tanks 100 Led by site waste team. Identified all underground tanks,
assigned unique ID and labelled.
Waste Team Improved
Environmental
Management Practices
Waste reduction/Raw material
usage efficiency
Investigating possibility of reducing our
Haz-Waste generation of blade wash
50 The operations team has led this investigation. Sampling is
ongoing and still being reviewed. Ongoing review of
classification of material (i.e. hazardous). Waiting on new set
of results.
Waste team Lead Potential reduction in
waste
Energy Efficiency/Utility
conservation
Continue to monitor plant to ensure
ongoing thermal performance
optimization
50 The major outage is planned for the Steam Turbine in 2012. As
part of this outage a significant amount of the gland packing
will be upgraded to a new design which will significantly
improve thermal efficiency of the Steam Turbine by up to 5%.
Some minor packing replacement was carried out in 2011.
Maintenance Manager Improved plant
efficiency
Energy Efficiency/Utility
conservation
Complete project survey to identify &
switch off all unnecessary electrical
loads when plant is shutdown for
extended periods.
100 Electricity import has been reduced by circa 25% through a
detailed review of all offline loads.
Operations Engineer Reduction in energy
usage
Waste reduction/Raw material
usage efficiency
Loading of waste documents to site
online document management system
(info-router)
60 Stores officer identifying relevant remaining documents and
loading to Info-router.
Stores Officer Increased compliance
with licence conditions
Waste reduction/Raw material
usage efficiency
Benchmarking our monthly waste
production against run-rates from 2009,
2010 and 2011
50 Ongoing project Waste Team Increased compliance
with licence conditions
Reduction of emissions to
Wastewater
Review maintenance of water system
PM checks to ensure optimum leak
prevention.
20 O&M team have identified areas of high leakage and has
organised a project to reduce leaking blow down valves.
Maintenance Manager Reduced emissions
Environmental Management Programme (EMP)/Continuous Improvement Programme
Does the EMS maintain an Environmental Management Programme (EMP) as required in
accordance with the licence requirements
Do you maintain an environmental documentation/communication system to inform the
public on environmental performance of the facility, as required by the licence
Documented in site procedures
Do you maintain an Environmental Management System for the site. If yes, please detail
in additional information
ISO 14001 and GE Energy EMS system in place.
Does the EMS reference the most significant environmental aspects and associated
impacts on-site
Yes, site has developed an Impacts and aspects
database
Reduction of emissions to
Wastewater
Regarding being a phosphate free site,
review the site procedures to ensure
that all relevant areas are addressed.
100 Site purchasing procedures updated Nov 2011 to ensure that
no phosphorous is included in products supplied to site. On-
going vendor evaluations of performance on site EHS
requirements.
Commercial Manager Improved
Environmental
Management Practices
Reduction of emissions to
Wastewater
Improve quality of analytical monitoring
of emissions from the Waste Water
Treatment Plant in line with EPA and
quality requirements.
80 The guidelines on quality assurance from EPA have been
implemented and quality manual and procedures improved.
Site is IS014001 and ISO9000 quality approved. Further actions
with new GE water representative to improve.
EHS Specialist Improved
Environmental
Management Practices
Reduction of emissions to
Wastewater
Update lab management records,
training program, quality control of
methods, method validation, lab
auditing, testing procedures, method
validation, instrument calibration
programme, (q3)
80 Lab quality manual has been developed and recently reviewed
as part of ISO14001. Further improvements with GE water
planned.
EHS Specialist Improved
Environmental
Management Practices
Additional improvements Continue refresher training of the
operations team on installation of
portable CEMS analyser.
100 Training complete by site CEMS specialist to operations team
in Q1 2012
Maintenance Manager Increased compliance
with licence conditions
Energy Efficiency/Utility
conservation
Major Inspection of Gas Turbine which
will improve plant efficiency
10 Planning complete, work to take place in April 2012. This will
be an upgrade to Turbine, Combustion and Compressor
sections. (0.5% - 0.75% efficiency gains)
Maintenance Manager Improved plant
efficiency
Reduction of emissions to Water Implement mechanical seals on demin
pumps
10 Identified pumps where glands could be replaced by
mechanical seals to save water usage.
Maintenance Manager Improved plant
efficiency
Reduction of emissions to Water Review water usage in relation to boiler
preservation during unit downtime
events
100 Meeting held with GE Water and recommendations
implemented resulting in significant water savings.
Operations Manager Water usage reduction
Reduction of emissions to Air Upgrade CEMS server 100 Server upgraded in 2011 giving increased reliability and
durability of data.
Maintenance Manager Increased compliance
with licence conditions
Reduction of emissions to Air Update CEMS quality procedures to
include training requirements, how to
deal with deviations, analyser
certifications, maintenance calibration
schedules, reporting uncertainties,
standards used for analysis, contractor
quality assurance, reference to AG3 and
EPA guidance documents.
50 Project ongoing. Site team have attended EPA conferences
and are following requirements. Further improvements in
documentation are planned.
Maintenance Manager Increased compliance
with licence conditions
Additional improvements Complete annual refresher training on
all environmental training courses.
100 Complete EHS Specialist Improved
Environmental
Management Practices
Reduction of emissions to
Wastewater
Implement lighting at wastewater inlet
chambers.
100 An upgrade has been made to the lighting at the Waste Water
Treatment Plant. It is best practice for the operations team to
visually check the Waste Water Treatment Plant chambers
before a discharge so the additional lighting greatly enhances
these visual checks during the winter months.
Maintenance Manager Increased compliance
with licence conditions
Additional improvements Detailed audit of all environmental
scorecards for ISO 14001 recertification
and cross business environmental
audits.
10 Develop auditing teams to review all scorecards. EHS Specialist Increased compliance
with licence conditions
Additional improvements Continue development of community
awareness and outreach in Power Plant
Operations and Environmental
Management activities on site.
100 Ongoing visits from local schools and universities and provision
of work experience to local students.
Plant Manager Public Awareness
24
Noise
Additional comments / supplemental information:
Based on the new AER guidance the full noise report has not been submitted as part of the
AER. There are some points from the report that do need to be communicated alongside the
noise monitoring results reported in this section.
The relevance of using the LA90, 30 min as opposed to LAeq, 30 min for comparison with
the EPA emission limits is discussed in the report.
“In the case of the Tynagh CCGT Power Station, the LA90 statistical indicator was deemed
to represent the noise impact specifically from the power station. The reason being that the
noise from power station was a constant background noise and the LA90 statistical indicator
is defined as:
The noise level that is equalled or exceeded for 90% of the time – the L90 statistical noise
indicator is an indicator of the constant background noise level at any location.”
It should also be noted that the Agency agreed to the use of LA 90 measurements in the
annual noise surveys as documented in a previous inspection report in 2007 (Ref: (700)
(07SI04KR))
Tonality: with reference to guidance set out in ISO 1996 (Reference 2 in the report available
on site), the measured noise at NSL1 and NSL2 during day and night time is not deemed
tonal in character – full details in report.
The following template states that “Please ensure that a tonal analysis has been carried out
as per guidance note NG4.”
The noise survey was largely carried out in accordance with the procedures and
methodologies outlined in Guidance Note for Noise (NG4) including the items listed in Table
6; Checklist for Noise Measurement Reports. It should be noted that NG4, at the time of
report writing, is still in consultation form and the first draft was published after the annual
noise survey was conducted.
Monitoring was carried out according to the existing EPA Environmental Noise Survey
Guidance document (2003) and associated referenced documents such as ISO 1996.
1 Yes
2 Yes
3 No
4 N/A
5 No
Date of
monitoring Time period Noise location (on site)
Noise sensitive location -NSL (if
applicable) LAeq LA90 LA10 LAmax
Tonal or Impulsive
noise* (Y/N)
If tonal /impulsive noise was
identified was 5dB penalty
applied?
Comments (ex. main
noise sources on site,
& extraneous noise ex.
road traffic)
Is site compliant with
noise limits
(day/evening/night)?
28/07/2011 Day Southwest of site approx 600m NSL1 Residence 59.2 45.8 52.9 88.9No No Ref. Noise Survey
ReportYes
26/09/2011 Day Northeast of site approx 500m NSL2 Milchem Equestrian Centre 34.8 29.5 35.7 58.9No No
Ref. Noise Survey
ReportYes
28/07/2011 Night Southwest of site approx 600m NSL1 Residence 54.3 43.5 48.1 83.3No No
Ref. Noise Survey
ReportYes
28/07/2011 Night Northeast of site approx 500m NSL2 Milchem Equestrian Centre 36.5 29.2 37.5 64.4No No
Ref. Noise Survey
ReportYes
*Please ensure that a tonal analysis has been carried out as per guidance note NG4. These records must be maintained onsite for future inspection
N/A
Have there been changes relevant to site noise emissions (e.g. plant or operational changes) since the last noise survey?
Table 1: Noise monitoring summary
If noise limits exceeded as a result of noise attributed to site activities, please choose the corrective action from the following options?
Noise Monitoring Report Summary
Was noise monitoring a licence requirement for the AER period?
If yes please fill in table 1 noise summary below
Was noise monitoring carried out using the EPA Guidance note including completion of the "Checklist for noise measurement report"
included in the guidance note as table 6?
Does your site have a noise reduction plan
When was the noise reduction plan last updated?
26
Resource Usage / Energy Efficiency
Additional comments / supplemental information:
The power plant running regime in 2011 was significantly different from previous years. The
plant run hours were down and plant starts were up; this shift was due to market conditions
and record wind generation levels. This change has resulted in considerable year on year
changes to our resource usage etc. Natural gas consumption and energy production are
both down by 57%, but electricity usage versus production shows a very large jump. This
anomaly is due to the fact that for the extended downtime periods the plant still has
significant power requirements. This was identified and action has been taken and typical
off-line electricity usage has been reduced by circa 25%.
Another major change during the year was the re-commissioning of the Gas Turbine
secondary fuel (Gasoil) system. For security of supply reasons and at the direction of the
CER Tynagh re-commissioned the system and underwent Eirgrid testing. In addition to
ongoing Eirgrid testing requirements (up to twice a year) the unit must regularly operate on
its secondary fuel to ensure continued operability of the system thereby considerably
increasing our consumption year on year.
The IPPC licence requirement to complete a full energy audit was completed in 2007. The
full report of this and implementation of recommendations from this energy audit were
reported in previous Annual environmental reports.Each year the site has a pro-active
energy efficiency team and complete a number of energy efficiency projects on site. These
also have been reported in previous AERs and projects to date have included:
• Improvements for the site aux equipment and lighting circuit modification kits ,
• Completed several plant condenser vacuum integrity leak checks to improve thermal
performance of the ST turbine plant and reduce overall ACC power consumption.
• Site has implemented a system of regular online and offline GT Blades washes to
maintain the power plant at its maximum energy efficiency level.
• Completed the installation of the GT Bellow cross-fire tube upgrade again increasing
overall GT thermal performance.
• Carried out a very significant GT cooling optimization upgrade (reported in 2009
AER) delivering significant fuel efficiency improvements.
Additional information
1 2007
Site has an energy efficiency team as
part of Environmental Objectives and
targets each year. The site completes
a number of energy projects on site
each year.
2
SEAI - Large
Industry Energy
Network (LIEN) yes
Site is member of government led
Greenbusiness.ie imitative and has
had independent resource efficiency
audits on site.
3 yes 0.1
Energy Use Previous year kWh Current year kWh
Change in Energy use
+/- %
Production +/- %
compared to
previous reporting
year**
Energy
Consumption +/- %
vs overall site
production*
Total 4,438,047,992 1,928,396,798 -56.5%
Electricity 50,503,000 37,874,049 -25.0%
Fossil Fuels: - -
Heavy Fuel Oil - -
Light Fuel Oil 44,992 1,911,638 4149%
Natural gas 4,387,500,000 1,888,611,111 -57.0% -57% 2%
Coal/Solid fuel - -
Renewable energy generated on site - -
Water use Previous year m3/yr. Current year m3/yr.
Change in Water use
+/- %
Production +/- %
compared to
previous reporting
year**
Water Consumption
+/- % vs overall site
production*
Groundwater 84,297 58496 -31% 65%
Surface water 14,024 9908 -29%
Public supply - -
Total 98,321 68,404 -30% -57%
Date of audit Recommendations
Description of
Measures proposed Origin of measures
Predicted energy
savings %
Implementation
date Responsibility Completion date Status and comments
Table 2 Water usage on site
* where consumption of energy can be compared to overall site production please enter this information as percentage increase or decrease compared to
the previous reporting year.
** where site production information is available please enter percentage increase or decrease compared to previous year
* where consumption of water can be compared to overall site production please enter this information as percentage increase or decrease compared to
the previous reporting year.
** where site production information is available please enter percentage increase or decrease compared to previous year
Table 3: Energy Audit finding recommendations
Resource usage/ Energy Efficiency
When did the site carry out the most recent energy efficiency audit? Please list the recommendations in table 3 below
Is the site a member of any accredited programmes for reducing energy usage/water conservation such as the SEAI programme
linked to the right? If yes please list them in additional information
Where Fuel Oil is used in boilers on site is the sulphur content compliant with licence conditions? Please state percentage in additional information
Table 1 Energy usage on site
17-Feb-10 Review and removal of
lighting in some areas.
Review suitability of
lighting levels in all
plant areas to support
rationalise/reduction.e.
g Workshop lighting
upgrade.
energy audit 200 euros/year Feb-10 Site maintenance
manager
Sep-11 Greenbusiness energy audit
recommendation. Completed
a full review was completed of
site lighting levels and using
lux readings. Several changes
were made to reduce
unnecessary lighting where
possible.
04/01/2011 Improve site energy
efficiency
Continue review and
implement other
feasible energy
efficiency projects
other initiative
(Environmental
Improvement plan
target)
25% reduction in
houseload energy
use
01-Nov Site maintenance
manager
30/01/2012 Project completed with the
plant offline we identified
opportunities to switch off
certain items of plant at
different times based on plant
condition in order to reduce
the amount of KW's we are
using.
04/01/2011 Improve site energy
efficiency
Continue to monitor
plant to ensure
ongoing thermal
performance
optimization.
other initiative
(Environmental
Improvement plan
target)
09-Apr-12 Operations manager
and shift support
engineer
on-going on-going: thermal plant
efficiency measured with
operations manager as part of
monthly customer report.
Operations manager gives
update on thermal efficiency
performance to customer
monthly report.
04/01/2011 Improve site energy
efficiency
Implement a site
energy conservation
awareness programme.
To reduce
photocopying,
powering down etc
other initiative
(Environmental
Improvement plan
target)
Aug-11 Maintenance manager
and commercial
manager
on-going on-going: Commercial
manager has raised awareness
on photocopying. Waste team
led incentives to reduce waste
water on site. An energy
efficiency procedure has also
been developed.
29
Waste - PRTR
Additional comments / supplemental information:
None.
��������������� ��� ����������
���������������������������� �������������� �����
� ��
� ��
� ��
�������������� ����������������� �� �� �������� ����� ���������� ��� �������������� �� ����������������������������� ��������������������������������� ��������� �������� ��� ���������� ���������������������
���������������������������
���������������
��������������������
��������� �� �������
������������������
��������������������
����������������������
!����������
���������"���������
��� ����#�����
��������������
$��%���������������& '�
���������������(��
������(��������%������
�� ������
����������������������������
�����
���������������
������������������
�"�
�������"!���#��������
����� ����������������������
�����������������������(��
����������������(������������
������������
������
�� ����������
���������(������
�������������
������������
�� �����'��
��������������(�#��������)������������� ������������������(������������������������*���������������#����+������,�������������(����������������� ������
�����������������������������������(��������������������������(��!���+�����������*��������������������(��-������������������������������������ �����
.��������������
��������� ������������
�����������
������"����
/������������������������ ������������������������������
���#��������������������������� �
!��������"���
������#���
���#����������
0"�'�&�
!"#�$%&�' �����('!�"���'&!)"�!��'* ��%�*"�#%+�,"�"��*-�',,�$��#�'&��('!�"�)'#$,$�$"!
!"#�$%&�* �('!�"�'##"��"��%&�%�!$�" �%�*"�#%+�,"�"��*-�',,�$��#�'&��('!�"�)'#$,$�$"!
������������������������������������������������#����������������������� �����������������#������������������(����(��+��������������������������*1���������������������(��������
+����������������+������������(����(�$!2!����������
�������������������������������+����+���
Sheet : Facility ID Activities AER Returns Workbook 31/3/2012 15:32
| PRTR# : P0700 | Facility Name : Tynagh Energy Limited | Filename : P0700_2011.xls | Return Year : 2011 |
Guidance to completing the PRTR workbook
Version 1.1.13
REFERENCE YEAR 2011
1. FACILITY IDENTIFICATION
Parent Company Name Tynagh Energy Limited
Facility Name Tynagh Energy Limited
PRTR Identification Number P0700
Licence Number P0700-01
Waste or IPPC Classes of Activity
No. class_name
2.1
The operation of combustion installations with a rated thermal input equal to or greater than
50MW
Address 1 PM Group
Address 2 Killakee House
Address 3 Belgard Square, Tallaght
Address 4 Dublin 24
Galway
Country Ireland
Coordinates of Location -8.38215 53.1666
River Basin District IEGBNISH
NACE Code 3511
Main Economic Activity Production of electricity
AER Returns Contact Name Colin Darcy
AER Returns Contact Email Address [email protected]
AER Returns Contact Position Technical Manager
AER Returns Contact Telephone Number 0909 745670
AER Returns Contact Mobile Phone Number 0870501639
AER Returns Contact Fax Number 0909 745752
Production Volume 1002635.0
AER Returns Workbook
| PRTR# : P0700 | Facility Name : Tynagh Energy Limited | Filename : P0700_2011.xls | Return Year : 2011 | Page 1 of 1
Production Volume 1002635.0
Production Volume Units Megawatt hours generated by powerplant
Number of Installations 1
Number of Operating Hours in Year 8760
Number of Employees 32
User Feedback/Comments
Web Address http:www.tynaghenergy.ie/
2. PRTR CLASS ACTIVITIES
Activity Number Activity Name
1(c) Thermal power stations and other combustion installations
3. SOLVENTS REGULATIONS (S.I. No. 543 of 2002)
Is it applicable? No
Have you been granted an exemption ?
If applicable which activity class applies (as per
Schedule 2 of the regulations) ?
Is the reduction scheme compliance route being
used ?
| PRTR# : P0700 | Facility Name : Tynagh Energy Limited | Filename : P0700_2011.xls | Return Year : 2011 | Page 1 of 1
������������������ � ������������������� ���������������
���������������� � ���������� ��������� ��� � !�"�#�$���"�%���!�&' � ���(�����#��)������)��� � �� �!�& ��������"�%��*����+,��!��������-����������! ����������������
. �� �� �� �� �� / % / /
� ��������� ����� ��� ������������
����������������������������������������������� !�
"����#
(�+�����,�00 (�� 1�2�� 1���� �2� � 3� )�� ������3�'� �� �� �� ���"� ���� �� ���"� ���� #�4#���5�67�-��
��4�'' ����5�
67�-��
&�4&�) � ��5�
67�-��
�� 2����� �, ��428�5 2 �#� �.9�9����+� ��.%�+� �.9������+� �+� �+�
�� 2���������, ��4285 1 �(�����.����: ��/��:+� �+� ��/��:+� �+� �+�
�� 1������42;:5 � ��#01�#�
7� �'��<���'����� ���
'� � � ����������� ���
��������������� �)=�
��� ���������)��'��4��5=�
��� ����=�3�'����� ����.+� �+� ����.+� �+� �+�
�% (��>����������� �����)� '�'������ �4(1?825 � ��#01�#�
7� �'��<���'����� ���
'� � � ����������� ���
��������������� �)=�
��� ���������)��'��4��5=�
��� ����=�3�'����� /��9+� �+� /��9+� �+� �+�
�� ����������,<���� ��4�&/5 � ��#01�#�
7� �'��<���'����� ���
'� � � ����������� ���
��������������� �)=�
��� ���������)��'��4��5=�
��� ����=�3�'����� �+/� �+� �+/� �+� �+�
�� ���������, ��4�8,��8�5 1 0�8�%9�����99� .:9�+� �+� .:9�+� �+� �+�
�. ( ���)����, ��4(8,�(8�5 1 �(��:%9������ �:�9��+� �+� �:�9��+� �+� �+�
$% ���������&�'��(�)�* � ��#01�#�
7� �'��<���'����� ���
'� � � ����������� ���
��������������� �)=�
��� ���������)��'��4��5=�
��� ����=�3�'����� ��99+. �+� ��99+. �+� �+�
@�����'�����A���� �����>'� '� �)��������"��������(���42������B5������'� '������ ������������
� ����+�����,�����!������������
����������������������������������������������� !�
"����#
(�+�����,�00 (�� 1�2�� 1���� �2� � 3� )�� ������3�'� �� �� �� ���"� ���� #�4#���5�67�-�� ��4�'' ����5�67�-�� &�4&�) � ��5�67�-��
�+� �+� �+� �+�
@�����'�����A���� �����>'� '� �)��������"��������(���42������B5������'� '������ ������������
� ���� �����,�����!����������,�����(����������'����-�����������*
������������
������� ,�.�/
1���� �C�
������������
������� ,�.�/
1���� �C�
!�"�#�$���"�%���!�&' � ���(�����#��)������)��� � �� �!�& ��������"�%��*����+,��!��������-����������! ")�����<��
� ���� �����,�����!����������,�����(����������'����-�����������*
����������������������������������������������� !�
"����#
"��������(�+ (�� 1�2�� 1���� �2� � 3� )�� ������3�'� �� �� �� ���"� ���� #�4#���5�67�-�� ��4�'' ����5�67�-�� &�4&�) � ��5�67�-��
�+� �+� �+� �+�
@�����'�����A���� �����>'� '� �)��������"��������(���42������B5������'� '������ ������������
�''��������/������������'�0��1����'0�����2�������
���'0���� #��)������)��� � �� ���������������11��-�'�����������
������������0�1�������0����'���'�3����
�������'�
� ���*��������*�� �(����*�453#��� ,3 3� ,����'� �'�
/���5����������
/�����2����
�������-������ �2����-�
16�2�������
#������ ��� ��������)����� ���4�����
����� ��5 �+� (��
1������<��� �+� �+� 4#����&�� �)�2�' ��5
1�������� � � � ����) ��� �+� �+� 4#����C� � �)�2�' ��5
(������������ ���4�������� � ����'� ���
������5 �+� (��
,����'����'
1���� �C�
�������
������������
,�.�/
��������2��2������0����������������7�����-����!����������!����8����'0�����2��������������������'����2��7�'����11��-�'����������'0����5���(,������*�0����'�
����������'����������0�����������������12��-�����0�5�����0���������1�������5�������'����2�������������'����-���2��������������1�������( .�*��1��������������
��7����1������'���(�����*� !3-��0��������������������2���0�������2�����������9�7�������������12�����������9���9���:�
!�"�#�$���"�%���!�&' � ���(�����#��)������)��� � �� �!�& ��������"�%��*����+,��!��������-����������! ")�����<��
�������������������� �������� ���� ����� ���������������
����������������� ��������� �������� �������� � !�"�#�$���"�%���!�&'������(�����#��)����� )�������� �!�&���������"�%��*����+,��!����� ��-� ��������! ����������������
. �� �/ �/ �% �% 0 0 0
� ��������� ����� ��� ������������ ������������������������������ ����! "���#��$�����������"�%$����&�#��%"#��%�� �'�������(�"��)�#��#����*"������� &� +�")%������� "������%�"�%�������!�������'�������� ��+� ���)(�#��#��� ���)�� � �����
�)�� ���������))�*"������� �����+� � �#��������,-
.����/
(�+�����,�11 (�� 2�3�� 2���� �3� � 4��)������� �4�' ������ �������"������ #�5#���6�78�-� ��5�''� ����6�78�-� &�5&�)�����6�78�-�
�� #������� �)�� 2 9#:
;� ����1�9�%����
�� ����� ������ �
<� ���������(�� �)�� /+. /+. �+� �+�
01 ���)�'+� '+��" 2 9#:
�":���������=��� �
2���� =�>?���@"@� �+% �+% �+� �+�
%0 #����� )��'�' ����5#936�5������3�� �394��6 2 9#:
������":�>������� +>�
�///>����������� �
?��+� �?/+� �?/+� �+� �+�
%/ 3��� � ��5�3�6 2 9#:
A���"������� ����+��
� ����+��4��� ��������
�<���������B�����
���)������
��'� �������� + �%�/+/ �%�/+/ �+� �+�
C�����'��� �D���� �����@'��'���)��������"��������(���53������;6������'��'������ ������������
� ����2�����3�����-������������
�)�� ���������))�*"������� �����+� � �#��������,-
.����/
(�+�����,�11 (�� 2�3�� 2���� �3� � 4��)������� �4�' ������ �������"������ #�5#���6�78�-� ��5�''� ����6�78�-� &�5&�)�����6�78�-�
�+� �+� �+� �+�
C�����'��� �D���� �����@'��'���)��������"��������(���53������;6������'��'������ ������������
� ���� �����3�����-����������3�����4� ���*"���%����(�"����#��#�5
�)�� ���������))�*"������� �����+� � �#��������,-
.����/
"��������(�+ (�� 2�3�� 2���� �3� � 4��)������� �4�' ������ �������"������ #�5#���6�78�-� ��5�''� ����6�78�-� &�5&�)�����6�78�-�
�+� �+� �+� �+�
C�����'��� �D���� �����@'��'���)��������"��������(���53������;6������'��'������ ������������
�������������
2���� �A�
�������������
�������������
2���� �A�
�������
2���� �A�
�������
�������
!�"�#�$���"�%���!�&'������(�����#��)����� )�������� �!�&���������"�%��*����+,��!����� ��-� ��������! ")�����<��
�������������������� ����� ����� �������������������� ���������������
���������������� ���������������������� ������������������ !"#"�$�%�����$�&������&$�'""��(��� "#�����������)����*+#�����������,����������� ����������������
� �- ��������������������������������������������������� �.
/���"�$�
0�������1���
,��2
34��������%���(�
'"!��!�����"��%��� �%�+��
5���"��"��� !"#"�$���������������������%���
34�������%���(�
'"!��!�����"��%��� �
��!�6���5"�1����
34���������((������ �%�+��
5���"��"��� !"#"�$����������������������������
%���34��������((������ �
��!�6���5"�1����
%���(�'"!����������"��%�*��(�
�((������ � "�#���!�6�������
5"�1�����03�7��589��������
8%',2
�!��#��((������ � "�#�5���"��"���
"*�*� "�#���!�6��$���5"�1��#��"���
03�7��589��������8%',2
���� ���5���"��"��
����1��������
:�(� 34�(��� /���"�$���,�� 5��!�"1�"���� �����
�����
��������
81���"�� ;�:�� ;����(�9��(
'�!�"���� �
������� %���(�'"!��!�������"��%�*�� ���!�6�������5"�1�������<����� �((������ ���!�6�������5"�1�������<����� %���(��((������ � "�#�5���"��"���"*�*� "�#���!�6��$���5"�1��#��"���03�7��589��������8%',2 '"!��!�������"��%�*�� � "�#�5���"��"���"*�*� "�#���!�6��$���5"�1��#��"���03�7��589��������8%',2
�"��"������:�����$ �������� %� �*=� >��(���1!�&"�& �� ; ��"&��( 8 �"���"��?��#�( �#��������'�(�@����AB
C"#!������@*@'��&���@*@?��#�
(
�"��"������:�����$ �������. %� �*-� "+�(�1!�&"�& �� : D�#���:#!�#�"�� 8 �"���"��?��#�( �#��������'�(�@����AB
C"#!������@*@'��&���@*@?��#�
(
�"��"������:�����$ �.������ ,�� �=*B
E������#"E�"(�>�����!���"�"�&�
(�&������������!�� 5- ; ��"&��( 8 �"���"��?��#�( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
��6�?��#�(�'�(@���B�A
��@�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
�"��"������:�����$ ����B��� %� �*�� "+�(���#� �B ; ��"&��( 8 �"���"��?��#�( �#��������'�(�@����AB
C"#!������@*@'��&���@*@?��#�
(
�"��"������:�����$ ����-��B %� ��*�.
"+�(�!������!�"����(�(��#"�"���>�����
�������������������"���(�"������-���@����
�-�����(�����-��� �� ; ��"&��( 8 �"���"��?��#�( �#��������'�(�@����AB
C"#!������@*@'��&���@*@?��#�
(
�"��"������:�����$ �������. %� ��*� >���� �����>&��!#��"�& �� ; D�#���:#!�#�"�� 8 �"���"��?��#�( �#��������'�(�@����AB
C"#!������@*@'��&���@*@?��#�
(
�"��"������:�����$ ������-- %� B*=� ��"!"1#�>��������������>"����1�!" "�( 5� ; ��"&��( 8 �"���"��?��#�( �#��������'�(�@����AB
C"#!������@*@'��&���@*@?��#�
(
�"��"������:�����$ ������-- %� �*�� ��"!"1#�>��������������>"����1�!" "�( �� ; ��"&��( 8 �"���"��?��#�( �#��������'�(�@����AB
C"#!������@*@'��&���@*@?��#�
(
�"��"������:�����$ �������� %� �*��� �"�(�&�(�#��>��� �� ; ��"&��( 8 �"���"��?��#�( �#��������'�(�@����AB
C"#!������@*@'��&���@*@?��#�
(
�"��"������:�����$ �������� ,�� �B*�B
"���#A���(����A!�#��"���(���&"��@�&���
�(�#���"!�"�&��"#� �- : D�#���:#!�#�"�� 8 �"���"��?��#�(
�"#����6"������#�
'�(@���-�A�
<#�!��B���F�����
5�"6�@F�����&���<��"�����
���@���!��#�@:�*�
5��#"�@?��#�(
�"#����6"������#�
'�(@���-�A�@<#�!��B���
F�����5�"6�@F�����&���
<��"�����
���@���!��#�@:�*�
5��#"�@?��#�(
<#�!��B���F�����
5�"6�@F�����&���<��"�����
���@���!��#�@:�*�
5��#"�@?��#�(
�"��"������:�����$ �������= ,�� �*� ��������&"��@�&����(�#���"!�"�&��"#� �- : D�#���:#!�#�"�� 8 �"���"��?��#�( ��6�?��#�(�'�(@�=BA�
:#��"��?�(����"#�
�����@*@����#�"��@:�*�
'�"�@?��#�(
��6�?��#�(�'�(@�=BA
�@:#��"��?�(����"#�
�����@*@����#�"��@:�*�
'�"�@?��#�(
:#��"��?�(����"#�
�����@*@����#�"��@:�*�
'�"�@?��#�(
;����(�9��(
�"��"������:�����$ �������= ,�� �*� ��������&"��@�&����(�#���"!�"�&��"#� �- : D�#���:#!�#�"�� 8 �"���"��?��#�( ��6�?��#�(�'�(@�=BA� '�"�@?��#�( '�"�@?��#�( '�"�@?��#�(
���8�����:�����"�� �=������ ,�� �*���
>����1"����(�6��"���!���"�"�&���&�"!�
��#6��������������(�&������������!�� �� ; ��"&��( ����( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
'"�(���!�"(��CF�
9>�#����6"!�@B��B-=�=-@C
���!����������@B�A
B.@C���4�#@�����@F���$
C���!����������@B�A
B.@C���4�#@�����@F���$
���8�����:�����"�� �=��B��- ,�� �*���
>����(���"6����(���#����!���"�"�&�
��&�"!���#6��������������(�&������
������!�� �� ; ��"&��( ����( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
'"�(���!�"(��CF�
9>�#����6"!�@B��B-=�=-@C
���!����������@B�A
B.@C���4�#@�����@F���$
C���!����������@B�A
B.@C���4�#@�����@F���$
�"��"������:�����$ �������� ,�� �*��
1!�&"�&�!���"�"�&����"(����� ����
!���"���(��$�(�&������������!�� �B ; ��"&��( 8 �"���"��?��#�( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
C;C�;��#����!$!#"�&�'�(�
@�����A��@5"�&���
��(@:11"�!���?�(����"#�
�����@��##���@:�*�
8 #$@?��#�(
5"�&�����(@:11"�!���
?�(����"#�
�����@��##���@:�*�
8 #$@?��#�(
�"��"������:�����$ �������� ,�� �*��-
1!�&"�&�!���"�"�&����"(����� ����
!���"���(��$�(�&������������!�� �� ; ��"&��( 8 �"���"��?��#�( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
���������@� �AFA�-A
����A��@��"����(�
<��"��������@*@��@:�*�
F#>$@?��#�(
��"����(�<��"�����
���@*@��@:�*�
F#>$@?��#�(
�"��"������:�����$ �������� ,�� �*���
1!�&"�&�!���"�"�&����"(����� ����
!���"���(��$�(�&������������!�� �B ; ��"&��( 8 �"���"��?��#�( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
;�;���!$!#"�&@�-A
�@:������>��?�(����"#�
�����@9�"��
B�@�##&��@5��#"���B@?��#�(
:������>��?�(����"#�
�����@9�"��
B�@�##&��@5��#"���B@?��#�(
������������������ !"#"�$�%�����$�&������&$�'""��(��� "#�����������)����*+#�����������,����������� �&����� ��
�������������������� ����� ����� �������������������� ���������������
/���"�$�
0�������1���
,��2
34��������%���(�
'"!��!�����"��%��� �%�+��
5���"��"��� !"#"�$���������������������%���
34�������%���(�
'"!��!�����"��%��� �
��!�6���5"�1����
34���������((������ �%�+��
5���"��"��� !"#"�$����������������������������
%���34��������((������ �
��!�6���5"�1����
%���(�'"!����������"��%�*��(�
�((������ � "�#���!�6�������
5"�1�����03�7��589��������
8%',2
�!��#��((������ � "�#�5���"��"���
"*�*� "�#���!�6��$���5"�1��#��"���
03�7��589��������8%',2
���� ���5���"��"��
����1��������
:�(� 34�(��� /���"�$���,�� 5��!�"1�"���� �����
�����
��������
81���"�� ;�:�� ;����(�9��(
'�!�"���� �
������� %���(�'"!��!�������"��%�*�� ���!�6�������5"�1�������<����� �((������ ���!�6�������5"�1�������<����� %���(��((������ � "�#�5���"��"���"*�*� "�#���!�6��$���5"�1��#��"���03�7��589��������8%',2 '"!��!�������"��%�*�� � "�#�5���"��"���"*�*� "�#���!�6��$���5"�1��#��"���03�7��589��������8%',2
;����(�9��(
���8�����:�����"�� �������� ,�� �*�-�
���������@� "#�������"#��0"�!#�("�&��"#�
"#��������������>"����1�!" "�(2@�>"1"�&�
!#����@�1����!�"6��!#���"�&�!���"���(��$�
(�&������������!�� �� ; ��"&��( ����( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
'"�(���!�"(��CF�
9>�#����6"!�@B��B-=�=-@C
���!����������@B�A
B.@C���4�#@�����@F���$
C���!����������@B�A
B.@C���4�#@�����@F���$
�"��"������:�����$ �.������ ,�� �*�-.
("�!�(�(��E�"1����!���"�"�&��4�(����
!�1�������0�.2�����������������
���"���(�"���.�����-�����.������ �B ; ��"&��( 8 �"���"��?��#�( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
C;C�;��#����!$!#"�&�'�(�
@�����A��@5"�&���
��(@:11"�!���?�(����"#�
�����@��##���@:�*�
8 #$@?��#�(
5"�&�����(@:11"�!���
?�(����"#�
�����@��##���@:�*�
8 #$@?��#�(
���8�����:�����"�� �.�����B ,�� �*�=�
&����"��1��������!���"�����0"�!#�("�&�
�#���2�!���"�"�&�(�&������������!�� �B ; ��"&��( ����( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
����("��?�(����"�����6"!��
F�3�G�:��
CF@��3�8�����@%"�(��#��
��&�C�����"@���������
�@C�����"@�B��=@F���$
%"�(��#����&�
C�����"@���������
�@C�����"@�B��=@F���$
���8�����:�����"�� �.�����. ,�� �*��-
#������$�!��"!#�@�!���"��"�&�� ����
!���"�"�&�(�&������������!��@�"�!#�("�&�
"+������� �#������$�!��"!#� �� ; ��"&��( ����( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
'"�(���!�"(��CF�
9>�#����6"!�@B��B-=�=-@C
���!����������@B�A
B.@C���4�#@�����@F���$
C���!����������@B�A
B.@C���4�#@�����@F���$
�"��"������:�����$ �.�����. ,�� �*��=
#������$�!��"!#�@�!���"��"�&�� ����
!���"�"�&�(�&������������!��@�"�!#�("�&�
"+������� �#������$�!��"!#� 5- ; ��"&��( 8 �"���"��?��#�( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
��6�?��#�(�'�(@���B�A
��@�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
������������������ ��� �� � �� �*��� ������(�����1����"����+!��&�����"�� �� ; ��"&��( ����( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
���8�����:�����"�� �������� ,�� �*��B
1"��@�"���@�(���"6����(����"���!���"�"�&�
(�&������������!�� �� ; ��"&��( ����( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
'"�(���!�"(��CF�
9>�#����6"!�@B��B-=�=-@C
���!����������@B�A
B.@C���4�#@�����@F���$
C���!����������@B�A
B.@C���4�#@�����@F���$���8�����:�����"�� �������� ,�� �*��B (�&������������!�� �� ; ��"&��( ����( ��6�?��#�(�'�(@���B�A�� :#��@?��#�( B.@C���4�#@�����@F���$ B.@C���4�#@�����@F���$
�"��"������:�����$ �������� ,�� �*.B �"#$�>���� ����"#�>������1����� �� ; ��"&��( 8 �"���"��?��#�( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
��6�?��#�(�'�(@�=BA
�@:#��"��?�(����"#�
�����@*@����#�"��@:�*�
'�"�@?��#�(
:#��"��?�(����"#�
�����@*@����#�"��@:�*�
'�"�@?��#�(
�"��"������:�����$ �������� ,�� �*��
#�����!�����������(���������!��$A
!���"�"�&�>��� �� ; ��"&��( 8 �"���"��?��#�( ��6�?��#�(�'�(@���B�A��
�"�����>��?�(����"#�
�����@*@������@:�*�
:#��@?��#�(
?�"���'1���!$!#"�&@� �A
C�A�=A��B=A��@���(���!��
?�(����"#������@*@���$@:�*�
C"#(��@?��#�(
���(���!��?�(����"#�
�����@*@���$@:�*�
C"#(��@?��#�(
H���#�!�����>��$�(���#�A!#"!�"�&�����5��!�"1�"���� �����������!#"!������(�#����������
������������������ !"#"�$�%�����$�&������&$�'""��(��� "#�����������)����*+#�����������,����������� �&����� ��