typical procedure & report development process flow

11
1 Pipeline (WPS & WQT) Sample of Process Flow pWPS WPQT WPS WQT 21d 7d 14d Commence 3d Total Duration = 45 days *subject to how many test is required. Resources 1 Welding Engineer: 360hrs 1 Welder Foreman: 280hrs 1 Fitter Foreman: 280hrs 1 QC Supervisor: 336hrs 1 QC Inspector: 1344hrs 1 Production manager: 40hrs

Upload: yusfarisyam-fauzi

Post on 04-Oct-2015

215 views

Category:

Documents


1 download

DESCRIPTION

process flow

TRANSCRIPT

  • *Pipeline (WPS & WQT) Sample of Process FlowpWPSWPQTWPSWQT21d7d14dCommence3dTotal Duration = 45 days*subject to how many test is required.Resources1 Welding Engineer: 360hrs1 Welder Foreman: 280hrs1 Fitter Foreman: 280hrs1 QC Supervisor: 336hrs1 QC Inspector: 1344hrs1 Production manager: 40hrs

    Proposed Disposal of Sarku Utama

  • *Pipeline (Transportation Study) Sample of Process FlowAFC DrawingsConsultant ReportGeneral ArrangementSea StateTransportation StudyAnalysis/Report8d2dResources1 Marine Engineer: 80hrs1 Lead Engineer: 8hrs1 Drafter: 80hrs1 Lead Drafter: 8hrs1 Clerk/QA: 8hrsBarge ConfirmationLoad-out InfoDocumentation/ First Rev. SubmissionIssued for ApprovalReviewed by Company10d7dTotal Duration for first submission = 10 days

    Proposed Disposal of Sarku Utama

  • *Pipeline (Pipelay Analysis) Sample of Process FlowAFC DrawingsConsultant ReportDL Barge DetailsPipelay AnalysisAnalysis/Report21d3dResources1 Marine Engineer: 168hrs1 Lead Engineer:24hrs1 Clerk/QA: 8hrsDocumentation/ First Rev. SubmissionIssued for ApprovalReviewed by Company10d7dTotal Duration for first submission = 24 days

    Proposed Disposal of Sarku Utama

  • *Pipeline (Pipelay Procedure) Sample of Process FlowAFC DrawingsConsultant ReportPipelay AnalysispWPSPipelay ProcedureAnalysis/Report21d3dResources2 Field Engineer: 336hrs1 Lead Engineer: 24hrs1 Drafter: 80hrs1 Clerk/QA: 8hrsBarge ConfirmationPre-lay Survey ReportDocumentation/ First Rev. SubmissionIssued for ApprovalReviewed by Company10d7dTotal Duration for first submission = 24 days

    Constructability ReviewHAZIDReadiness ReviewPipelay Commence

    Proposed Disposal of Sarku Utama

  • *Structure (On-Bottom Analysis) Sample of Process FlowAFC DrawingsConsultant ReportSoil ReportFabrication WCRSpecificationOn-Bottom AnalysisJacket ModelAnalysis/Report7d21d3dResources1 Structure Engineer: 248 hrs1 Lead Engineer: 16hrs1 Clerk/QA: 8hrsDocumentation/ First Rev. SubmissionIssued for ApprovalReviewed by Company10d3.5dTotal Duration for first submission = 31 days

    Proposed Disposal of Sarku Utama

  • *Structure (Upending) Sample of Process FlowAFC DrawingsConsultant ReportSling ConfirmationWCRCrane Barge ConfirmationJacket UpendingSingle BlockAnalysis5d8dResources1 Structure Engineer: 128hrs1 Lead Engineer: 24hrs1 Drafter: 40hrs1 Clerk/QA: 8hrsJacket Main modelDouble BlockDocumentation/ First Rev. SubmissionIssued for ApprovalReviewed by Company10d7d3dTotal Duration for first submission = 16 days

    Proposed Disposal of Sarku Utama

  • *Structure (Transportation Study) Sample of Process FlowAFC DrawingsConsultant ReportGeneral ArrangementFabrication WCRSea StateTransportation StudyJacket/TopsideAnalysis/Report15d3dResources1 Marine Engineer: 144hrs1 Lead Engineer: 24hrs1 Drafter: 144hrs1 Lead Drafter: 24hrs1 Clerk/QA: 8hrsBarge ConfirmationLoad-out InfoPilesAnalysis/Report2d10dDocumentation/ First Rev. SubmissionIssued for ApprovalReviewed by Company10d7dTotal Duration for first submission = 18 days

    Proposed Disposal of Sarku Utama

  • *Structure (Conductor Hang-off) Sample of Process FlowAFC DrawingsConsultant ReportConductor Make-upHanger SelectionSpecificationConductor Hang-off AnalysisReport/Analysis15d2dResources1 Structure Engineer: 136hrs1 Lead Engineer: 24hrs1 Clerk/QA: 8hrsDocumentation/ First Rev. SubmissionIssued for ApprovalReviewed by Company10d7dTotal Duration for first submission = 17 days

    Proposed Disposal of Sarku Utama

  • *Structure (Pile Drivability Study) Sample of Process FlowPile make-upHammer DetailsSoil reportSea state Criteria (underwater Piles)Piles Drivability AnalysisReport/AnalysisDocumentation/ First Rev. Submission7d2dResources1 Structure Engineer: 72hrs1 Lead Engineer: 16hrs1 Clerk/QA: 8hrsIssued for ApprovalReviewed by Company10d3.5dTotal Duration for first submission = 9 days

    Proposed Disposal of Sarku Utama

  • *Structure (Pile Upending) Sample of Process FlowPile Make-upBarge InfoGeneral ArrangementSea state CriteriaCrane Lift ChartPiles UpendingReport/AnalysisDocumentation/ First Rev. Submission15d3dResources1 Marine Engineer: 144hrs1 Lead Engineer: 24hrs1 Clerk/QA: 8hrsClamp DetailsIssued for ApprovalReviewed by Company10d7dTotal Duration for first submission = 18 days

    Proposed Disposal of Sarku Utama

  • *Structure ( Jacket/Topside Installation Procedure) Sample of Process FlowAFC DrawingFinal WCRConsultant Design ReportInfo From FabricatorLoadout Coordination ManualRigging CalculationDocumentation/ First Rev. Submission3dResources2 Field Engineer: 448hrs1 Lead Engineer: 24hrs1 Drafter: 112hrs1 Clerk/QA: 16hrs Issued for ApprovalReviewed by Company10d7dRigging CalculationInstallation Procedure14d14dTotal Duration for first submission = 31 days

    Installation CommenceConstructability ReviewHAZIDReadiness Review

    Proposed Disposal of Sarku Utama

    ***********