unclassified ad number limitation changesconstruction necessary to restore the project flood control...

41
UNCLASSIFIED AD NUMBER LIMITATION CHANGES TO: FROM: AUTHORITY THIS PAGE IS UNCLASSIFIED ADB344261 Approved for public release; distribution is unlimited. Distribution: Further dissemination only as directed by US Army Corps of Engineers, Sacramento District, 1325 J Street, Room 1480, Sacramento, CA 95814, MAR 1993, or higher DoD authority. COE/CA/SD ltr dtd 22 Oct 2008

Upload: others

Post on 16-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

UNCLASSIFIED

AD NUMBER

LIMITATION CHANGESTO:

FROM:

AUTHORITY

THIS PAGE IS UNCLASSIFIED

ADB344261

Approved for public release; distribution isunlimited.

Distribution: Further dissemination only asdirected by US Army Corps of Engineers,Sacramento District, 1325 J Street, Room 1480,Sacramento, CA 95814, MAR 1993, or higher DoDauthority.

COE/CA/SD ltr dtd 22 Oct 2008

Page 2: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

OFFICE REPORT SACRAMENTO RIVER FLOOD CONTROL PROJECT COLUSA TROUGH DRAINAGE CANAL CALIFORNIA

IK. ***PI*- ^ T?

US Army Corps of Engineers Sacramento District

• *#§

«**«•;

MARCH 1993

20081029157

Page 3: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

81

DEFENSE TECHNICAL INFORMATION CENTER

Inp>rm*Uw*hr the. Def&tie> C»mtmouty

Month Day Year

DTIC has determined on I \i \j\3A \Q\o\o\% that this Technical Document has the Distribution Statement checked below. The current distribution for this document can be found in the DTIC® Technical Report Database.

I | DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.

] © COPYRIGHTED. U.S. Government or Federal Rights License. All other rights and uses except those permitted by copyright law are reserved by the copyright owner.

• DISTRIBUTION STATEMENT B. Distribution authorized to U.S. Government agencies only. Other requests for this document shall be referred to controlling office.

] DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and their contractors. Other requests for this document shall be referred to controlling office.

• DISTRIBUTION STATEMENT D. Distribution authorized to the Department of Defense and U.S. DoD contractors only. Other requests shall be referred to controlling office.

I~~l DISTRIBUTION STATEMENT E. Distribution authorized to DoD Components only. Other requests shall be referred to controlling office.

|2| DISTRIBUTION STATEMENT F. Further dissemination only as directed by controlling office or higher DoD authority.

Distribution Statement F is also used when a document does not contain a distribution statement and no distribution statement can be determined.

] DISTRIBUTION STATEMENT X. Distribution authorized to U.S. Government Agencies and private individuals or enterprises eligible to obtain export-controlled technical data in accordance with DoDD 5230.25.

Page 4: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

.)

OFFICE REPORT

SACRAMENTO RIVER FLOOD CONTROL PROJECT COLUSA TROUGH DRAINAGE CANAL CALIFORNIA

March 1993

Page 5: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

EXECUTIVE SUMMARY

The Water Resources Development Act of 17 November 1986 authorized remedial construction

necessary to restore the Sacramento River Flood Control Project levees along the Colusa Trough Drainage

Canal and the Knights Landing Ridge Cut, subject to review and comment of the project work by the

Secretary of the Army and the submittal of report findings to Congress. The Act stated that if the

Secretary did not comment before the end of a 3-year period beginning on the date of the Act, the project

work would be deemed to have been approved by the Secretary.

Construction General funds were appropriated in FY 90 under the Sacramento River Flood Control

Project to initiate advanced engineering and design studies for the project levees within the study area.

Additional funds were made available in FY 91 and FY 92 to determine the extent and scope of

reconstruction work required to restore the levees to the congressionally authorized and approved design

levels.

The study area includes about 13 miles of project levees on the Knights Landing Ridge Cut and

about 36 miles of project levee on Colusa Trough Drainage Canal. Engineering and geotechnical

evaluations indicate about 11 miles of levees require remedial construction to correct for stability and

seepage problems inherent in the design and construction of the original project. Although there is always

the question of adequate maintenance by the local agencies, it is concluded that the stability and

seepage problems are the result of internal soil conditions (within the levee embankment and subsurface

foundation) and not inadequate maintenance.

8.5 miles of the reconstruction work (located on the Colusa Trough Drainage Canal levee and the

west levee of the Knights Landing Ridge Cut; see Figure 7) is not economically justified incrementally.

The remainder of the work, 2.5 miles along the east levee of Knights Landing Ridge Cut, appears

economically feasible when combined with reconstruction work proposed in the Mid-Valley Area Initial

Appraisal Report (lAR) for that flood hazard area encompassing the community of Knights Landing. The

first cost of the 2.5 miles of levee reconstruction on Knights Landing Ridge Cut is estimated to be about $2

million.

In addition to the above, there are localized depressed areas of the levee crown that do not have the

minimum congressionally approved 3 feet of freeboard above the design water surface. The depressed

areas of the levee crown are outside the limits of the remedial reconstruction work cited above and are

generally located at railroad and road crossings. It is proposed that the local entities responsible for

levee maintenance in these areas be required to install flood barriers or permanenUy fill such locations

under existing maintenance and operation agreements to insure that the design flood stages can be safely

conveyed within the project levees. This work is also within the financial capabilities of the local sponsor,

The Reclamation Board.

The potentially feasible work (2.5 miles of levee reconstruction along the east levee of the Knights

Landing Ridge Cut) will be considered in conjunction with the Mid-Valley Area levee reconstruction plan.

The purpose of this office report is to present findings regarding work performed under Colusa Trough

remedial construction authority. This office report includes a summary of geotechnical analysis, required

levee reconstruction work, design, costs, and economic evaluation.

Page 6: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

Considering Colusa Drain/Knights Landing Ridge Cut work in conjunction with the Mid-Valley Area is

in accord with the recommendations presented in the Sacramento River Flood Control System Evaluation, Mid-Valley Area IAR. The east levee of the Knights Landing Ridge Cut in that report was assumed to

provide the congressionally approved design level of flood protection, but it was recognized that

additional detailed geotechnical studies were being done under the subject investigation. The

construction of all work proposed around an independent flood hazard area as one unit will insure that the

design level of flood protection for that area, including the community of Knights Landing, would be met at

one point in time. Geotechnical and design information developed under the Colusa Trough authority will

be incorporated into the Mid-Valley Area design memorandum. In addition, this will minimize engineering

and institutional efforts since only one Project Cooperation Agreement (PCA), one set of plans and

specifications, and one construction contract would be required for the Knights Landing area.

Other areas shown to be incrementally unjustified will be addressed as part of the Total Systems

Costs and Benefits Evaluation pursuant to instructions regarding WRDA-92 and FY-93 work allowance

instructions, and as elements within Phase IV, Lower Sacramento, or Phase V, Upper Sacramento, of the

Sacramento River Flood Control System Evaluation.

Funds programmed for Colusa Trough after FY 92 are not required. Engineering and design costs

expended in the evaluation of the east levee of the Knights Landing Ridge Cut will be transferred to the

Mid-Valley Area design effort and would be cost shared by the local sponsor. Additional funds would

need to be programmed in subsequent years for the Mid-Valley Area engineering and design effort.

Page 7: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

TABLE OF CONTENTS

Page

I. Introduction

a) Study Authority 1

b) Study Purpose and Scope 1

c) Other Studies and Reports 1

II. Study Area Description

a) Study Location 2

b) Area Description 3

c) History of Study Area Project Levees 3

III. Problems

a) General 3

b) Levee Embankment Problems 4

c) Flood Problems 6

IV. Engineering and Design

a) General 6 b) Levee Crown and Design Water Surface Profiles 6

c) Geotechnical Analyses 8

d) Designs 10

e) Hydraulics and Hydrology 11

f) Reconstruction Costs 12

g) Economic Justification 16

V. Conclusions 19

Page 8: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

TABLE OF CONTENTS (cont'd)

LIST OF TABLES

Page

1 Knights Landing Ridge Cut and Colusa Trough Drainage Canal,

Public Law 84-99 Work - Costs 5

2 Knights Landing Ridge Cut (West Levee) Construction Costs,

Reconstruction Plan - Costs 13

3 Knights Landing Ridge Cut (East Levee) Construction Costs,

Reconstruction Plan - Costs 14

4 Colusa Trough Drainage Canal Construction Costs, Reconstruction Plan - Costs 15

5 Knights Landing Ridge Cut and Colusa Trough Drainage Canal,

Summary of Permanent and Temporary Right-of-Way, Staging Areas,

and Land Acquisition Costs 17

LIST OF FIGURES

1 Location Map, Colusa Basin

2 Vicinity Map .

3 Levee Crown and Water Surface Profiles, Knights Landing Ridge Cut

4 Levee Crown and Water Surface Profiles, Colusa Trough Drain

5 Levee Crown and Water Surface Profiles, Colusa Trough Drain

6 Levee Crown and Water Surface Profiles, Colusa Trough Drain

7 General Location, Levee Reconstruction

8 Levee Breaching, Potential Flooded Areas

9 Reconstruction Design, Landside Ditch Relocation

10 Reconstruction Design, Landside Berm Construction

11 Reconstruction Design, Landside Berm Construction and Ditch Relocation

Page 9: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

I. INTRODUCTION

a) Study Authority - The levees of the Coiusa Trough Drainage Canal and the Knights Landing

Ridge Cut have had significant problems over the years. Their integrity has been maintained by local

entities and supplemented by State and Federal aid, Public Laws 84-99 and 93-288, when applicable.

A reconnaissance report was prepared in July 1981 to support the repair of potential project deficiencies.

Resolution of this request was never finalized. With the passage of the Water Resources Development Act

of 1986, repair of these levees was authorized in Section 830 subject to the provisions of Section 903(a).

The authorization reads:

Subject to Section 903(a) of this Act, the project for flood protection along the

Sacramento River and its tributaries, California, authorized by the Flood Control Act of

1917, is modified to authorize and direct the Secretary to accomplish remedial

construction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut, in accordance with such

report, at a total cost of $11,000,000, with an estimated first Federal cost of $8,250,000

and an estimated first non-Federal cost of $2,750,000.

Section 903(a) required that, prior to commencing construction, the Secretary of the Army review and

comment on the project and report to Congress. If such comment is not made before the end of the

3-year period beginning on the date of enactment of the Water Resources Development Act, the project

will be considered approved by the Secretary of the Army.

b) Study Purpose and Scope - This study was conducted to evaluate the integrity of the existing

levees of the Coiusa Trough Drainage Canal and Knights Landing Ridge Cut, to determine whether the

levees function as designed; to determine whether the levees have the minimum congressionally

approved 3 feet of freeboard above the design water surface; and, if levee reconstruction is needed, to

determine the economic justification for proceeding with construction. The existing levee embankments of

the Coiusa Trough Drainage Canal and Knights Landing Ridge Cut were constructed based on (1) a

design water surface profile, (2) a discharge associated with the design water surface profile, and (3) a

minimum freeboard requirement above the design water surface profile. In general, the study objective

was to develop reconstruction plans to insure that the project levees could safely pass the design flood

stages.

c) Other Studies and Reports - Detailed explorations, soil testing, and analyses of the levees

and foundations within the project area are described in the following reports:

1) "Basis For Design, Levee Construction, Back Levee, RD 108, Sycamore Slough to SPRR

Bridge, Sacramento River Flood Control Project," Corps of Engineers, September 1955.

2) "Design Memorandum No. 2, Sacramento River Flood Control Project, California, Back

Levees of Reclamation District No. 108, Levee Construction General Design," Corps of Engineers,

August 1957.

-1-

Page 10: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

3) "Design Memorandum No. 3, Sacramento River Flood Control Project, California, Back

Levees of Reclamation District 108, Levee Construction General Design," Corps of Engineers, August

1957.

4) "Colusa Basin Drainage Canal Levee, Engineering Study," Converse Ward Davis Dixon Inc.,

March 1981.

5) "Office Report, Sacramento River Flood Control Project, California, Engineering and

Economic Evaluation, Colusa Basin Drain and Knights Landing Ridge Cut, Units 127 and 132, Colusa and

Yolo Counties, California," Corps of Engineers, April 1986.

6) "Decision Document, Sacramento River Flood Control Project, California, Engineering and

Economic Evaluation, Colusa Basin Drain and Knights Landing Ridge Cut, Units 132 and 127, Colusa and

Yolo Counties," Corps of Engineers, May 1988.

7) "Geotechnical Assessment of Levees in the Mid-Valley Area, Sacramento River Flood

Control System Evaluation," Corps of Engineers, December 1989.

8) "Plan of Action, Sacramento River Flood Control Project, Colusa Basin Drain and Knights

Landing Ridge Cut," Corps of Engineers, February 1990.

9) "Colusa Basin Appraisal," State of California, The Resources Agency, Department of Water

Resources, May 1990.

10) "Sacramento River Flood Control System Evaluation, Mid-Valley Area, Initial Appraisal

Report," Corps of Engineers, December 1991

11) "Cultural Resources Inventory for the Colusa Basin/Knights Landing Ridge Cut Levees

Project, Colusa and Yolo Counties, California," PAR Environmental Services, April 1992.

12) "Baseline Resources Inventory, Colusa Basin and Knights Landing Ridge Cut," Beak

Consultants Incorporated, May 1992.

II. STUDY AREA DESCRIPTION

a) Study Location - The Colusa Basin is an area northwest of the city of Sacramento. The basin

extends from the Sacramento River on the east to the crest of the foothills on the west, with Stony Creek

and Cache Creek the approximate northern and southern boundaries, respectively. (See Figure 1.) The

basin has a drainage area of approximately 1,700 square miles, a length of about 70 miles, and a

maximum width of about 25 miles. The lands of the basin are used primarily for agriculture, with about

100,000 acres devoted to rice production. Waterfowl hunting at private clubs and on public preserves is

also a major industry in the northern part of the basin. The population of Colusa Basin is mostly contained

within the cities and towns of Willows, Maxwell, Colusa, Williams, Arbuckle, Dunnigan, and Knights

Landing; smaller communities are in the outlying areas. The population of Colusa Basin is increasing at a

rate of about 1.4 percent annually. The January 1987 population estimate was 21,800.

Page 11: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

b) Area Description - The development of Colusa Basin into a productive agricultural area has

depended upon the progressive reclamation of the area to prevent flooding, improve drainage, and

provide irrigation. Individuals, local districts, the State, and Federal agencies through the years have

constructed various flood control works necessary to the farming of the fertile areas located within the

basin. Local reclamation districts were the first agencies to develop the area for agriculture.

Investigations and proposals by State and Federal Governments in the early 1900's concerning flood

protection of the Sacramento Valley greatly influenced the subsequent developments within the basin.

c) History of Study Area Project Levees - The levee of Reclamation Districts 108 and 787 and

Maintenance Area 12 extends from the vicinity of Colusa along the eastern side of the Colusa Trough

Drainage Canal through Knights Landing. (See Figure 2.) This levee was originally constructed to

protect lands to the east of the Colusa Trough Drainage Canal from flood runoff originating from the

western foothills. Local interests constructed the Colusa Trough Drainage Canal, which flows south from

its junction with Willow Creek above the town of Colusa and then along the alignments of the levee of

Reclamation Districts 108 and 787. Excavated material was used to build the levee of this channel, and in

some reaches excavation was necessary to provide a continuous drainage channel of the desired

capacity. The levee was originally constructed by local interests between 1911 and 1918 using a

clamshell dredge. The levee was gradually improved and final modifications were completed in 1958 to

meet the design specifications for the Sacramento River Flocd Control Project and to provide flood

protection for lands to the east against flows up to 20,000 cubic feet per second (cfs). However,

floodflows that exceed the Trough's in-channel capacity of 1,500 cfs have caused and will continue to

cause extensive flooding of lands west of the levee.

During low stages on the river, flows from the Colusa Trougr. Drainage Canal are discharged through a

concrete structure, the Knights Landing Outfall Gates, into the Sacramento River. When the stage of the

Sacramento River is high, the gates are closed, and flows frcrn Colusa Trough Drainage Canal are

conveyed through Knights Landing Ridge Cut into the Yolo Bypass. The Knights Landing Ridge Cut, which

has a bottom width of 400 feet, was constructed by excavating two parallel channels and using the

excavated material to construct two levees on the outside of each channel. The leveed cut was designed

to convey 20,000 cfs. The two combined excavated channels act as low flow outlet channels for the

Colusa Trough Drainage Canal.

III. PROBLEMS

a) General - The levees in the Colusa Trough Drainage Canal and Knights Landing Ridge Cut

have experienced subsidence, slippage, and partial collapse over the years. Historic records, dating to

1915, indicate failures have occurred on both sides of the levees and repairs have been made throughout

their existence. Records dating to 1959 show subsidence and slumping of many short levee reaches (200

feet or less). In some cases, levees were repaired by excavating and recompacting as much as one-half

-3-

Page 12: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

of the levee cross section. These failures have been extensive and threaten the integrity of the levee

system.

The cost of such work has frequently exceeded the financial capabilities of the local districts to repair the

levees, and the assistance of the Corps of Engineers has been provided under Public Law 84-99.

Previous Public Law 84-99 work is shown in Table 1. However, continuous intensive maintenance

programs and prompt and effective emergency actions have been necessary to prevent levee breaches

and flooding of the protected areas.

b) Levee Embankment Problems - Corps documents dating to 1951 have described levee

deformation, slippage, and partial collapse. Levee damage has resulted from the following: (1) loss of

strength and cracking of the near surface soils, (2) precipitation and flood stage water forces, (3) a weak

layer of foundation clay and/or organic material, and (4) over steepened levee geometry. Many of the

failures have been on the landside of the levees. Slope failures are often shallow surficial slides involving

the upper 5 feet or so of material and do not extend into the crown. Deeper slides manifest themselves as

longitudinal cracks extending into the crown. The landside or waterside slope gradually deforms several

inches to several feet per day until equilibrium of the sliding mass is reached. The typical result is a 4- to

7-foot vertical escarpment in the crown which may extend for 200 to 1,000 feet. Material in the levee

foundation moves laterally along a weak layer of soft clay and organic debris (tule reeds, grasses, carbon

chunks, and decayed matter) and comes to rest 20 to 30 feet beyond the levee toe. Deformation

problems have been described as several feet of subsidence in the crown accompanied by bulging of the

sides between the toe and crown.

During 8 of the past 34 years (1958, 1959, 1969, 1974, 1975, 1980, 1983, and 1986), damages to the

levees of the Colusa Trough Drainage Canal, RD 108/787, warranted Public Law 84-99 assistance.

Repairs in 1959 consisted of reconstructing small portions of the levees at various locations. In 1974,

1980, and 1984 (1983 damages), repairs consisted of reconstructing approximately 5,200 feet of the levee.

During the same 34-year period, Knights Landing Ridge Cut levees required assistance under Public Law

84-99 in 4 years (1956,1963, 1975, and 1986). In 1963, repairs consisted of reconstructing approximately

1,600 feet of levees on both sides of the channel. In addition, in 1983 non-Federal interests received

assistance from the Federal Emergency Management Agency for damages not subject to Public Law

84-99 assistance.

Repairs have included removal and compaction of the failed material to flatten slopes with the inclusion of

a berm to counterbalance tbe rotational failure of the levee fill. A total of 67 levee repair and

reconstruction sites have been noted in Corps documents since 1956. In many other instances,

non-Federal interests have repaired the levees when Federal aid was not available as levee failures

occurred in years when no flood emergency was declared.

Page 13: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

TABLE 1 KNIGHTS LANDING RIDGE CUT AND COLUSA TROUGH DRAINAGE CANAL

PUBLIC LAW 84-99 WORK

Year Reclamation District

Levee Mile Length Damage Actual Cost (S) Cost ($) Oct91

Price Level

1956 KLRC 2.5 1,600 Slip, Subsidence

50,000 290,358

1963 KLRC 0.7, 0.85 1,850 Slip, Subsidence

60,000 300,344

1969 108 787

2.4 Combined 350

Slip 22,000 88,808

1974 108 0.0,2.1-3.7 Combined Structural Combined 787 2.2, 4.2 2,250 Failure 69,000 191,380

1975 108 14.9, 15.4 400 Landside Slip 37,000 86,975 787 1.98, 2.73 200 Slip 23,500 55,241

1980 108 0.15, 1.8,2.25 3,150 Slip, Subsidence

304,000 466,470

1983 108 0.22-17.4 10,300 Slips 509,000 618,557

1986 KLRC 2.25, 2.4, 2.6 900 Slip, Subsidence

TOTAL COST

60,000 70,110

1,134,500 2,168,243

KLRC = Knights Landing Ridge Cut

5-

Page 14: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

c) Rood Problems - Under existing conditions, land on the west side of the Colusa Trough

Drainage Canal levee is flooded during peak floodflows. This situation has existed since the early part of

the century when the levee was first constructed by non-Federal interests. During an event such as the

100-year (1983) flood, the peak flood stage would be reduced about 3 feet by a levee breach. Peak

stages are of short duration when compared with periods of inundation generally experienced by the

westside lands (peak stage periods generally last about 1 to 2 weeks on the average). The primary

problem is that flow in the Yolo Bypass produces prolonged periods of backwater inundation in the Colusa

Trough Drainage Canal. Flood records indicate that westside lands may be inundated for several months

and that the inundation may extend into May.

If levees along the Colusa Trough Drainage Canal are breached, there will be a reduction in the extent of

westside lands inundated. This reduction in flooded areas around the perimeter is not really significant.

The duration of flooding of the westside lands would also change because of a levee break but is

dependent on how floodwaters are removed from flooded areas east of the Colusa Trough and

reintroduced into the system. There will be no change to westside flooding levels, assuming the Colusa

Trough Drainage Canal levee provides the design level of protection.

Flood stages in the Colusa Trough Drainage Canal and Knights Landing Ridge Cut are a function of runoff

upstream from the town of Colusa, local runoff, and backwater effects from the Yolo Bypass. Antecedent

weather conditions prior to floods are characterized by extensive and frequent rainy periods. During these

periods, rainfall which averages more than one-third of an inch per day occurs more than 50 percent of

the time, with only shea periods of clearing (less than 10 days) for periods up to 4 months. These wet

weather conditions result in saturation of the levees and corresponding softening of the levee fill adjacent

to cracks or fissure surfaces. As noted in the geotechnical analyses (Section IV-c), the fissure orientation,

intrusion of water, and associated softening of the fissure surfaces may cause slope failures.

Levee damages usually consist of partial slope failures or subsidence, with the majority of damages

occurring on the landward side of the levee. Repair of these damages often requires excavation and

reconstruction of the entire levee cross section. During reconstruction it has been observed that the

levees contain fissured clay and that the underlying foundation contains organic clays with local layers of

vegetation that has not decomposed.

IV. ENGINEERING AND DESIGN

a) General - This study was conducted to evaluate the integrity of the existing project levees of

the Colusa Trough Drainage Canal and Knights Landing Ridge Cut; to determine whether the levees

function as designed; to determine whether the levees have the minimum congressionally approved 3 feet

of freeboard above the design water surface; and, if levee reconstruction is needed, to determine the

economic justification for proceeding with reconstruction. If levee reconstruction is needed, reconstruction

plans would be developed to insure that the project levees can safely pass the design flood stages.

b) Levee Crown and Design Water Surface Profiles - Levee crown surveys were completed on

the Colusa Trough Drainage Canal and the Knights Landing Ridge Cut in September and December of

-6-

Page 15: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

1990, respectively. Levee crown elevations are referenced to mean sea level datum. Levee crown

stationing (and the design water surface profile) was based on "Levee and Channel Profiles," Corps of

Engineers, March 1957, as revised.

Survey points were taken on the centerline of the levee crown about every 1,000 feet and at breaks in the

levee crown profile. Additional survey points were taken at railroad crossings, road crossings, and at

other significant physical features. Levee crown profiles developed from the survey data are shown in

Figures 3 through 6.

The profile plots indicate the non-uniformity in the levee crown surfaces in the study area. In addition, the

plots indicate that some road crossings cut through the levee embankments at elevations 1 to 3 feet

below the adjacent levee crown elevations.

Design water surface profiles were developed for Colusa Trough Drainage Canal and Knights Landing

Ridge Cut as part of the Sacramento River Flood Control Project, as indicated by "Levees and Channel

Profiles," Corps of Engineers, March 1957. Design water surface elevations were based on a specified

design discharge (no recurrence interval or frequency was attached to that design discharge) and adopted concurrent conditions at the confluences of study area streams and bypasses.

Project flood plains were originally adopted by the March 1917 Flood Control Act as taken from House

Document No. 81,1st Session, dated 1910. In 1923 , House Document No. 81 was modified to show

changes to the recommended project because of significant cost increases, local desires, and to

incorporate work which had already been done by locals in the interim. Revised values for project design

flows and flood plains were established and included in the report "Flood Control in the Sacramento and

San Joaquin Basins," printed as Senate Document No. 23, 69th congress, 1st Session, 1926. This is the

basic document authorizing the 1928 revision of the project. Since 1928, project design flows and water

surface profiles have been reevaluated and modified based on available hydrologic information and more

detailed hydraulic studies, and as various segments of the project were constructed. These revisions

have been agreed to by The Reclamation Board, State of California, and the Corps of Engineers and

published as "Levee and Channel Profiles, Sacramento River Flood Control Project," 15 March 1957.

The agreed-to 1957 design water surface profiles are shown on Figures 3 through 6 and can be compared

to the levee crown profile plots.

Three feet is the minimum freeboard on the Colusa Trough Drainage Canal and Knights Landing Ridge Cut

project levees to meet design requirements for the flood control project levees and to provide for a uniform

level of protection from overtopping. An inspection of the profile plots indicates that freeboard is

inadequate on Knights Landing Ridge Cut at the Road 16 crossing and in the vicinity of channel mile 12,

and on Colusa Trough Drainage Canal at the Road 99E crossing, in the vicinity of channel mile 4, between

channel miles 12 and 14, at the County Line Road crossing, and in the vicinity of channel mile 17.

Although road crossings do not meet minimum design freeboard requirements, local levee maintaining

agencies should have operational procedures for sandbagging or for installing flood gates at these

locations during high flood stages. In addition, other localized depressed areas of the levee crown have

Page 16: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

deficient freeboard ranging up to about a maximum of 1 foot. Because these areas are very localized,

because the magnitude of the freeboard deficiency is small, and because the reasons for the deficiencies

cannot be positively associated with design or construction deficiencies, the depressed areas should be

raised under existing maintenance and operation agreements.

c) Geotechnical Analyses - Geotechnical analyses were conducted on the Colusa Trough

Drainage Canal and Knights Landing Ridge Cut project levee embankments and levee foundations to

evaluate levee stability and provide reconstruction designs for levees with inherent design and

construction deficiencies. Reconstruction designs were selected on the basis of current explorations and

testing and a review of previous investigations and information.

The current geotechnical investigation included a total of 88 borings drilled in June and July of 1990 for

the purpose of determining the properties and characteristics of the levee embankment and foundation

soils. A 6-inch diameter hollow-stem auger was used to drill to depths of 40 feet from the levee crown

and 20 feet from the levee toe (generally two borings per site). Additional borings were drilled to

investigate slumping. Standard penetration tests (SPT's) were conducted continuously from the surface to

a depth of 20 feet and then at 5-foot intervals thereafter except in alternating borings where undisturbed

and bulk samples were taken. In addition, in November 1990, a total of five exploration trenches were

excavated in the levee embankment at selected sites within the project area for the purpose of evaluating

levee crackage. Two trenches were excavated on the landside of the Knights Landing Ridge Cut, and 3

trenches were excavated along the Colusa Trough Drainage Canal levee at known levee problem areas.

The purpose of the trenches was to trace the depth of the larger cracks and to view the zone of drying and

cracking. The above information was supplemented with boring logs from previous investigations by the

Corps of Engineers, other geotechnical firms, and with data from past levee repairs.

Levee embankment cross section surveys indicated levee slopes ranging from 1.5 horizontal to 1 vertical

(1.5H:1V) to 4.0H:1Von the waterside and 2.0H:lVto 5.5H:1V on the landside. The crown width varies

from 12 to 60 feet on the Knights Landing Ridge Cut and 18 to 80 feet on the Colusa Trough Drainage

Canal. The predominant crown width is 25 feet for the Colusa Trough Drainage Canal and 15 feet for the

Knights Landing Ridge Cut. The typical levee height above the natural ground surface is 15 feet for the

levee reaches. However, the levee in some reaches is as high as 20 feet. A landside ditch 10 feet deep

and 30 feet wide parallels the landside toe for much of the project.

The laboratory testing program indicated that the soil samples obtained from the levee embankments and

foundations were primarily clays. There were 15 samples selected to represent the embankment and

foundation and 8 samples chosen as representative of the clay-organic layer. Testing indicated that a

well defined peak strength was not reached by 10 of the 23 samples tested. The descriptions of past

failures indicated a gradual remolding and loss of strength of material prior to failure; however, creep as a

mode of failure was not established.

Soil-lime testing consisted of using matenal from three sites that were selected as representative of the

levee embankment and foundation soils. Clay-organic material was not tested because acid from

decaying organic matter inhibits the interaction of lime with clay. Soils with an organic content greater

Page 17: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

than 20 percent are considered nonreactive with lime. Soils tested had an organic content of about 6

percent. Laboratory test results indicated that cracking and shallow sloughing may be prevented with the

addition of 4 percent lime to the clay and that the soils of the project levees are conducive to lime

treatment. Potential reconstruction work on the Colusa Trough Drainage Canal, about 8,000 lineal feet of

levee between roads 99E and 98A, would use a lime treatment to prevent cracking of the near-surface

levee material. Lime at a rate of 4 percent by weight would be mixed in place to a depth of 2 to 3 feet.

Any organic matter encountered would be removed.

The slope stability analyses determined that the critical condition for landside slope stability occurs at the design flood stage with uplift pressure transmitted through trie shallow foundation organic layer. Waterside

slope stability is most critical at low-flow conditions at locations where the freeboard is greatest.

All levee reaches have shallow stability problems regardless of slope geometry or flood stage. The

expansion characteristics of the clay materials and the long periods of seasonal wetting and drying result

in progressive loss of strength. The shallow slides are confined to the upper few feet of material and

typically daylight at the levee toe, channel bank, or ditch bank. Deeper slides fall along the plane of the

clay-organic layer. In general, the more stable reaches have (1) slopes flatter than 3H:1 V, (2) a landside

height less than 15 feet, (3) no channel or ditch bank within 50 feet of the levee toe, and (4) no underlying

clay-organic layer. The analyses did not consider the dense growth of large trees along the waterside

bank of the Colusa Trough Drainage Canal. Based on the height of these trees, the root system is

estimated to extend to a depth of 30 feet into the foundation soil. The roots could increase the resistive

force of the available shear strength along the failure plane.

Based on the results of the geotechnical evaluation, engineering judgement, and past performance, the

following reconstruction plans are recommended to insure that the project levees can safely convey the

design flood stages:

Colusa Trough Drainage Canal *

15,500 lineal feet landside irrigation ditch relocation and intermittent toe berm construction

(with 8,000 lineal feet of lime treatment) up to Road 98A. Upstream of Road 98A plan consists

of 29,000 lineal feet of landside irrigation ditch relocation and toe berm construction.

Knights Landing Ridge Cut *

West Levee - Reconstruction plan consists of 500 lineal feet of landside irrigation ditch

relocation.

East Levee - Reconstruction plan consists of 13,500 lineal feet of landside irrigation ditch

relocation and 11,500 lineal feet of toe berm construction.

* See Figure 7

9-

Page 18: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

d) Designs - Designs for reconstruction of levees along the Colusa Trough Drainage Canal and

Knights Landing Ridge Cut were based on results from the current geotechnical analyses and a review of

test results and previous designs presented in "Colusa Basin Drainage Canal, Engineering Study"

(reference 4).

The test results presented in the consultant's report indicated that the fissured structure of the uppermost

foundation material significantly affects the strength of the material. The stability analysis showed that

failure surfaces passing through this fissured layer could cause the Colusa Trough Drainage Canal levee

to fail. Thus, the presence of this fissured layer suggests that the levee should be reshaped. The report

indicates the following three solutions (reconstruction designs) based on their testing results:

1) Reconstruction design 1 - The levee would be excavated to foundation level and then reconstructed. The results of a number of soils tests indicated that excavating the levee to the

foundation material and recompacting the soil such that the fissured structure is eliminated would be a

viable solution. Previous repairs of the levee used this method with the provision that highly organic

layers of materials be removed and inspections made to insure that such layers were not present when the

levee was replaced. Most of the repaired sections have been performing satisfactorily; however, a

previously repaired section in RD 108 reportedly failed. The failure could be due to inadequate depth of

excavation or width of the key (remolding of fissured clay).

2) Reconstruction design 2 - The driving force would be reduced by removing material from the top

of the slope and placing it near the toe. This measure involves excavating a portion of the landside slope

and decreasing the crest width and placing and compacting the excess material into a berm near the toe

of the slope. The geometric configuration would be a 16-foot crown width with a 2H:1V landside slope

and a 27-foot wide berm at the landside toe. The waterside slope would remain unchanged. In this

method, the final levee would have a split section, and the factor of safety would be higher due to an

improved geometric configuration. This plan would not remove the fissured structure or organic layers in

the unexcavated portions of the levees.

3) Reconstruction design 3 - The basic designs of the first two alternatives would be used. This

•design consists of excavating the levee and the upper few feet of foundation soils and compacting the

material into the split-level geometric configuration described in design 2. This method would give the

highest factor of safety.

Based on analysis of the designs presented in the consultant's report, geotechnical analyses done for the

current investigation, and basic engineering judgement, the following designs have been recommended:

a) Berms will be added to provide a differential of 15 feet between the levee crest and the top

of berm to stabilize the levee slope from potential deep failures. The berm is to extend horizontally a

minimum of 20 feet from the levee slope with a minimum thickness of 2 feet. (See Figure 10.) Ditches

are to be relocated a minimum distance of 50 feet from the levee toe . (See Figure 11.)

b) The upper 2 to 3 feet of material from the levee crown to the toe will be treated with lime to

prevent cracking and to stabilize the levee slopes from potential shallow slides and deformation. The

treatment area will extend between roads 99E and 98A.

-10-

Page 19: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

c) Landside ditches near the levee toe will be relocated a minimum distance of 50 feet from

the levee toe to improve slope stability. (See Figure 9.)

e) Hydraulics and Hydrology - Within the study area, the Colusa Trough Drainage Canal is

leveed only on the left bank for about 36 miles. The upstream limit of the levee is south of the city of

Colusa and just south of Highway 20. The Knights Landing Ridge Cut is leveed on both the left and right

banks for about 13 miles.

Floodflows accumulating upstream of the project levee on Colusa Trough Drainage Canal are conveyed

downstream past Highway 20 and down the drain to the Knights Landing Ridge Cut. Additional local

inflows are intercepted at various points along the drain. During low stages, flows do not enter the

Knights Landing Ridge Cut but are discharged through the outfall gates into the Sacramento River just

north of the community of Knights Landing. During high stages, the outfall gates are closed and

floodflows are conveyed through the Knights Landing Ridge Cut into the Yolo Bypass.

The study area has a gaging station at Highway 20 (flow and stage) and at Knights Landing (stage only).

The gage at Knights Landing is upstream of the entrance to the Knights Landing Ridge Cut and west of the outfall gates to the Sacramento River.

The Corps of Engineers modified the levee embankments of the Knights Landing Ridge Cut in 1952 and

the Colusa Trough Drainage Canal in 1956 and 1958 to meet design criteria authorized for the Sacramento

River Flood Control Project. The minimum design freeboard was specified as 3 feet. The approved

design water surface profiles are shown on Figures 3 through 6. Since modification of the existing levees

by the Corps, no breaching of the levee embankments has occurred to date, although areas of significant

levee distress have been observed (see photo, front cover) during and after flood events.

A design overflow location exists immediately upstream of the entrance to the Knights Landing Ridge Cut

on the right bank. Overflow is initiated at about the design water surface elevation at this location. If

overflow occurs, excess flows would be conveyed around the project levee and downstream on the

landward side of the west levee of the Knights Landing Ridge Cut.

During the 1986 flood event, overflow did not occur to the west of the Knights Landing Ridge Cut for an

observed peak flood stage of 35.94 feet (msl datum) at Knights Landing (see 1986 high water mark profile

of Figure 3). During the 1983 flood event, when the observed peak flood stage was 37.35 feet at this

same location, overflow did occur and floodflows traveled southerly along the landward side of the west

levee of the Knights Landing Ridge Cut.

The peak stage for the 1986 flood in the Yolo Bypass at the confluence with the Knights Landing Ridge Cut

was about 34.0 feet. (See Figure 3.) The peak stage exceeded the design water surface by about 0.3

feet. Based on the following stage-frequency data, which was developed for Yolo Bypass at this location

(Yolo Bypass at the confluence with Knights Landing Ridge Cut), the peak stage represented a recurrence

interval of 50 to 55 years.

-11-

Page 20: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

Recurrence interval (years) 50 40 30 20 10

Yolo Bypass stage (feet) ** 33.7 33.1 32.7 32.0 30.4

** Yolo Bypass at the confluence with Knights Landing Ridge Cut

For the 1983 flood, the peak flow rate observed at Highway 20 was 15,700 cfs. According to the

Department of Water Resources (State of California), the 1983 recorded flow did not include overbank flow. Total flow has been estimated as 22,400 cfs. Using the following discharge-frequency data

supplied by Hydrology Section, the 1983 peak flow, 22,400 cfs, at this location corresponds to a

recurrence interval of about 40 years. The peak flow rate for the 1986 flood was 11,600 cfs and

corresponds to a recurrence interval of about 10 years.

Recurrence interval (years) 100 50 25 10

Peak flow (cfs) ** 34500 26000 19000 11800

** Colusa Trough Drainage Canal at Highway 20

Since peak flood stages in the Knights Landing Ridge Cut and Colusa Trough Drainage Canal are

influenced by the flood stages in Yolo Bypass (backwater condition), a one-dimensional unsteady flow

model was developed for the study area. Water surface profiles were developed for various flow rates

and downstream stage-boundary conditions. The maximum peak flood stages during the 1983 and 1986

floods were estimated to have recurrence intervals of 40 to 55 years based on the hydraulic modeling and

hydrologic inputs.

f) Reconstruction Costs - Since previous studies have never identified an economically feasible

project for the subject study area, costs in the current investigation were only developed to that extent

necessary to determine whether the work was potentially feasible.

•The geotechnical evaluations, limits of reconstruction, reconstruction designs, costs of levee

modifications and drainage facilities, and costs of relocations were done to that detail necessary for

incorporation into a design memorandum. This was done such that if the reconstruction was shown to be

infeasible, the information would be available to local entities and would permit those entities to make

decisions and implement the necessary work without significant additional engineering and design efforts.

The reconstruction costs were developed for three separate reconstruction plans, the west levee of the

Knights Landing Ridge Cut, the east levee of the Knights Landing Ridge Cut, and the levee on the Colusa

Trough Drainage Canal. Each of these plans was associated with a potential flood hazard area (see

Figure 8 for the general location of the flood hazard areas) for economic purposes.

Reconstruction costs are shown for each plan in Tables 2, 3, and 4. A general description of each

applicable plan is contained in the first footnote of each table. Costs for relocations, levee modifications

and drainage facilities were done in sufficient detail for incorporation into a design memorandum. Costs

for real estate were estimated based on work previously accomplished by Real Estate Division for the

Mid-Valley Area cost estimates, which include similar land types for value purposes. This work was

12-

Page 21: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

TABLE 2 KNIGHTS LANDING RIDGE CUT (WEST LEVEE)^

CONSTRUCTION COSTS RECONSTRUCTION PLAN

Item First Cost

Lands and Damages $50,000 2/

Relocations $33,000

Fish and Wildlife Facilities $20,000 2/

Levee Modifications and Drainage Facilities $76,000

Cultural Resources Preservation $5,000 2/

Planning, Engineering, and Design $190,000 ZJ It

Construction Management $10,000 2/

TOTAL $384,000

1/ Reconstruction plan consists of 500 lineal feet of landside irrigation ditch relocation.

li Estimated using amounts for similar work shown in the Sacramento River Flood Control System Evaluation - Initial Appraisal Report - Mid-Valley Area, December 1991.

h Includes costs expended during current investigation.

-13-

Page 22: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

TABLE 3 KNIGHTS LANDING RIDGE CUT (EAST LEVEE)17

CONSTRUCTION COSTS RECONSTRUCTION PLAN

Item First Cost

Lands and Damages $400,000 2/

Relocations $78,000

Fish and Wildlife Facilities $200,000 ll

Levee Modifications and Drainage Facilities $803,000

Cultural Resources Preservation $20,000 ll

Planning, Engineering, and Design $400,000 %l h

Construction Management $70,000 li

TOTAL $1,971,000

y Reconstruction plan consists of 13,500 lineal feet of landside irrigation ditch relocation and 11,500 lineal feet of toe berm construction.

h Estimated using amounts for similar work shown in the Sacramento River Flood Control System Evaluation - Initial Appraisal Report - Mid-Valley Area, December 1991.

h Includes costs expended during current investigation.

14-

Page 23: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

TABLE 4 COLUSA TROUGH DRAINAGE CANAL17

CONSTRUCTION COSTS RECONSTRUCTION PLAN

Item First Cost

Lands and Damages $700,000 2/

Relocations $8,000

Fish and Wildlife Facilities $400,000 ll

Levee Modifications and Drainage Facilities $2,664,000

Cultural Resources Preservation $40,000 li

Planning, Engineering, and Design $1,200,000 till

Construction Management $190,000 2/

TOTAL $5,202,000

1/ Reconstruction plan consists of 15,500 lineal feet landside irrigation ditch relocation and intermittent toe berm construction (with 8,000 lineal feet of lime treatment) between Knights Landing and Road 98A. Upstream of Road 98A plan consists of 29,000 lineal feet of landside irrigation ditch relocation and toe berm construction.

li Estimated using amounts for similar work shown in the Sacramento River Flood Control System Evaluation - Initial Appraisal Report - Mid-Valley Area, December 1991.

li Includes costs expended during current investigation.

-15-

Page 24: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

coordinated with District Real Estate Division, and a breakdown of cost for each plan is presented in Table

5. Other costs were also estimated using amounts for similar work shown in the Sacramento River Flood

Control System Evaluation, Initial Appraisal Report, Mid-Valley Area, December 1991. Since, as indicated

below in the Economic Justification, the reconstruction work was shown to be infeasible based on existing

conditions and an incremental resource analysis, no further refinement of quantities and cost was

considered necessary.

g) Economic Justification - Based on past performance and the geotechnical evaluation, the

levee reconstruction shown in Figure 7 is necessary to insure that the design flood stages can be safely

conveyed by the project levees. The geotechnical evaluation also indicated a high potential for levee

failure at flood stages equal to or greater than the higher of the peak flood stages that occurred during the

1983 and 1986 floods.

Potential flooded areas (see Figure 8) were developed assuming various breach scenarios and different

without project condition levels of flood protection. Without project damages were computed for the

various scenarios in an effort to determine whether the levee reconstruction was incrementally justified at a

reconnaissance level.

During high flood stages a levee break on the west side of the Knights Landing Ridge Cut (at the site

where ditch relocation is the recommended repair, see Figure 7) would result in flooding to an area

bounded by the Cache Creek and Yolo Bypass project levees. (See Figure 8.) The potential flooded

area is predominantly agriculture with farmsteads. Even if the recommended levee repair is made at this

time, higher levels of flood protection for this area are probably not possible. As indicated previously,

floodwaters circumvented the upstream limit of the west levee of the Knights Landing Ridge Cut during the

1983 flood and caused flood damages to areas landward of that levee. In addition, during the 1983 flood

the north levee of Cache Creek just downstream of the community of Yolo was sandbagged to prevent

overflow of the levee. If overflow or levee breaching would occur at this location, floodwaters would be

conveyed downstream into the same general area shown flooded in Figure 8 (the estimated design level

of flood protection for Cache Creek in the vicinity of Yolo is probably between a 10- and 20-year

recurrence interval). Based on the above, higher levels of flood protection could not be achieved for that

flood hazard area west of the Knights Landing Ridge Cut by relocating the ditch adjacent to the landward

toe of the west levee. Since higher levels of flood protection cannot be attributed to the recommended

repair for the west levee of the Knights Landing Ridge Cut, this work is not economically justified on an

incremental basis.

Although the reconstruction proposed for the west levee of the Knights Landing Ridge Cut cannot be

justified, the local maintaining agency or the State should consider doing the necessary work. If

economic justification were shown and if Federal participation were approved, the cost of relocating ditch

facilities would have been a local responsibility under current cost sharing policies.

-16-

Page 25: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

1 s 8 8 I I 3 »

8 S

I CO

CO o O c o

4->

"55 3 CT O <

CO c CO c O CO

S CO c

c CO

CO CO la CO Q CD

k_ .C < 3 TO O c la 1- 'en

CO co *-> to CO

. 3 ^ w o UjO

> CO

m "2 1

o *-> £

3 D) o ir 0) D) ET

T3

be CO V-

o D) Q. C E C

CD 1-

CO •o _l c tn CO

J= <-> c

D) CD 'E c * CO

E i- o

Q. •*— O

E? CO

E E 3 (/)

<D CM

8

9 s| CO CO

CO 1 v>

E* CO "c7r m CO en

CO 1 I

8 8

2 g 5 <D T—

S 3

o o *-* c\i

8 8 in r* CTT *~

a

a

O O o O CM CM

8 § CNJ 25 8

8

S §

^ CM

•2 «

LU _2 > 3 LU CT

Si O o

1£ •

m "• c sfil Si i w 8 S O T> -o "I "" c _i w- <o *: •

8 £ I Q

s s. £

a cu

2 ra to CO c c/> a>

cz E CD

g I £ CT3

CD

ra QJ ra Er ra re | 8* E en

fa

-17-

Page 26: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

For the Colusa Trough Drainage Canal, about 8.5 miles of levee reconstruction is proposed just upstream

of the Knights Landing Ridge Cut. (See Figure 7.) Based on the geotechnical and hydraulic analyses,

the most probable levee breach location is in the uppermost levee reach of the recommended repair. If a

levee were to break at an upstream location, another break downstream on Colusa Trough Drainage

Canal is not expected. The potential flooded area for the above condition is shown in Figure 8.

The potential flooded area is bounded by a local levee to the south, the Sacramento River levee to the

east, and the Colusa Trough Drainage Canal levee on the west. The area is predominantly agriculture with

scattered farmsteads. The economic evaluation indicated that the average annual without project

damages for existing conditions, a 21-day duration of flooding, and a 50-year nondamaging level of

flood protection is about $115,000. Even if all the foregoing damages could be eliminated by the

proposed reconstruction, the potential benefits would only support about $1.4 million of repair work. As

shown in Table 4, the cost of levee modifications is in excess of $2 million which would indicate that the

work on Colusa Trough Drainage Canal is economically infeasible on an incremental basis.

In addition to the above, the Sacramento River side of the Colusa Basin has levee reaches with design

levels of flood protection between 30-year and 40-year recurrence intervals. The 1983 peak flood stages

in the Colusa Trough Drainage Canal had estimated recurrence intervals of 40 to 60 years (there were

reaches of observable levee distress during the 1983 flood but no levee failures, although emergency

repairs were subsequently required as indicated in Table 1). Based on past records, infrequent storm

events generally produce high flood stages in the Colusa Trough Drainage Canal at about the same time

as high flood stages are occurring in the Sacramento River opposite the Canal. Because of the above,

higher levels of flood protection for that area east of the Colusa Trough Drainage Canal probably cannot

be achieved by the recommended repairs.

The reconstruction work proposed for the east levee of the Knights Landing Ridge Cut (see Figure 7)

would insure that this project levee could safely convey the design conditions. A levee break at either of

the repair sites shown would inundate an area confined by project levees on all sides. (See Figure 8.) In

the "Mid-Valley Area, Initial Appraisal Report", Corps of Engineers, December 1991, reconstruction work

was also recommended for the west levee of the Sacramento River opposite the community of Knights

Landing. The estimated existing (without project condition) levels of flood protection for the Knights

Landing area were estimated at a 40-year recurrence interval on the Knights Landing Ridge Cut side and

a 60-year recurrence interval on the Sacramento River side.

The average annual without project damages for existing conditions, a 21-day duration of flooding, and a

40-year nondamaging level of flood protection is about $530,000 for the Knights Landing area. The

combined cost of levee repairs for this area is about $3.7 million (the cost of reconstruction of the west

levee of the Sacramento River is about $1.7 million based on the Mid-Valley Area, Initial Appraisal

Report, and the cost of reconstruction of the east levee of the Knights Landing Ridge Cut is about $2

million as shown in Table 3). If half the benefits within the freeboard range are attributed to the

reconstruction proposed, the benefits exceed the costs (a benefit to cost ratio that could range from 1.1 to

-18-

Page 27: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

1.5 depending on upstream levee breaching), The cost of doing the combined work could be less than

that shown above if only one contract for construction is necessary (combining the reconstruction work will

minimize engineering and institutional efforts since only one Project Cooperation Agreement, one set of

plans and specifications, and one construction contract would be required for the Knights Landing area).

Based on the economic evaluation (results summarized above), reconstruction work for the levees

surrounding the community of Knights Landing is economically justified based on an incremental analysis

and assuming that the Mid-Valley Area work is combined with this work as one contract. Reconstruction

work for the west levee of the Knights Landing Ridge Cut and the Colusa Trough Drainage Canal is not

justified incrementally

Because public safety is a primary concern, there is also potential justification for Federal participation in

reconstruction work for the levees around Knights Landing. This potential flood hazard area includes

about 500 structures, primarily residences, and about 850 people. A major adverse impact resulting from

a levee failure in this area is the potential for loss of human life. Depths of flooding resulting from levee

failure could range up to a maximum of 15 feet. Because of the depths of flooding possible and the

potential for unexpected levee failures, loss of life could result.

V. CONCLUSIONS

Based on a comparison of with and without project conditions, reconstruction work proposed for the

Colusa Trough Drainage Canal levee and the west levee of the Knights Landing Ridge Cut is not

economically justified incrementally. Reconstruction work proposed for the east levee of the Knights

Landing Ridge Cut is incrementally justified when combined with repairs recommended for the west levee

of the Sacramento River (as presented in the "Mid-Valley Area, Initial Appraisal Report", Corps of

Engineers, December, 1991) opposite Knights Landing.

Further development of plans for reconstruction of the east levee of Knights Landing Ridge Cut will be

accomplished in conjunction with the Mid-Valley Area design effort. The construction of all work

proposed around an independent flood hazard area as one unit will insure that the design level of flood

protection for that area, which includes the community of Knights Landing, will be met at one point in time.

Geotechnical and design information developed under the Colusa Trough Drainage Canal investigation

can easily be incorporated in the Mid-Valley Area design memorandum. In addition, this will minimize engineering and institutional efforts because only one Project Cooperation Agreement, one set of plans

and specifications, and one construction contract would be required for the Knights Landing area.

Reconstruction work which has been shown to be incrementally infeasible in this investigation will be

considered in other phases of the Sacramento River Flood Control System Evaluation. That work

proposed for the Colusa Trough Drainage Canal levee (which is incrementally infeasible) will be

considered along with the west levee of the Sacramento River opposite the canal. These two levees

provide flood protection for the same potential flood hazard area and, as such, it would be appropriate to

19-

Page 28: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

evaluate these levees concurrently. Based on the above, repair work for the Colusa Trough Drainage

Canal levee will be addressed in the Initial Appraisal Report for the Upper Sacramento Area, Phase V, of

the Sacramento River Flood Control System Evaluation. This same reasoning also applies to work

proposed for the west levee of the Knights Landing Ridge Cut (which is also incrementally infeasible).

This work will be addressed in the Initial Appraisal Report for Lower Sacramento Area, Phase IV, of the

Sacramento River Flood Control System Evaluation.

-20-

Page 29: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

TEHAMA g$* CO LAKE

GLENN STONY GORGE RESERVO/I

lUKIAH

LAKEPORT

NAPA CO

• SANTA ROSA

COLUSA TROUGH DRAINAGE CANAL CALIFORNIA

LOCATION MAP COLUSA BASIN

SACRAMENTO DISTRICT. CORPS OF ENGINEERS SEPTEMBER 1992

FIGURE 1

Page 30: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,
Page 31: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

N/Wa N/SV9 vsmop

LHl AVMHSIH

('X9 2H> 91 QVOU

CM9 'iv 9i> avoid

SSVdAd 010A 33A11 1S3M

o 1^

o CO

(1SW) 133J Nl N0I1VA313

Page 32: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

(1SW) 1333 Nl NOLLVA313

Page 33: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

avou urn

QVOci 31IHM

QVOV 3NI1 MNDOO

CN

CN CN

o CN

fr

CO

9

o

oo 0-

CO

1 X e>

o a:

ft 3 _l o o

CN

o o CD

o $

o

(1SW) 133J Nl NOI1VA313

Page 34: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

CO

O Ld

3 Q.

O

X o 3 O

< 00 => _l o o

(iSfl) I33J Nl N0I1VA313

Page 35: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

-A-

COLUSA TROUGH DRAINAGE CANAL CAUFORNIA

GENERAL LOCATION LEVEE RECONSTRUCTION

SACRAMENTO DISTRICT. CORPS Of ENGINEERS SEPTEMBER 1992

FIGURE 7

Page 36: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

LEVEE BREACHING POTENTIAL FLOODED AREAS

SACRAMENTO DISTRICT. CORPS OF ENGINEERS SEPTEMBER 1992

FIGURE 8

Page 37: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

i it!

D>

^v*

|

o

.

< o o _J Ul

'

V' i i 1 i

o 1— Q

Ul Q CO Q

<

1 I Is 1

Is Is

k r I I

L

i i B •« fy %> § COLUSA TROUGH DRAINAGE CANAL

1 i r

1

CALIFORNIA

RECONSTRUCTION DESIGN LANDSIDE DITCH

RELOCATION

SACRAMENTO DISTRICT, CORPS OF ENGINEERS SEPTEMBER 1992

FIGURE 9

Page 38: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

Sa

I

i u OH I— (/)

o o

LU 00.

Ld Q

</) Q

I I §l

f •9 i

if <3 o

COLUSA TROUGH DRAINAGE CANAL CALIFORNIA

RECONSTRUCTION DESIGN LANDSIDE BERM CONSTRUCTION

SACRAMENTO DISTRICT. CORPS Of ENGINEERS SEPTEMBER 1992

FIGURE 10

Page 39: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,

i^

o i— o Z> en \— CO z; o o

UJ m

to

< o o _l UJ Ql

X o Q

Q z: <

I I Pi

C *> Q. £ **"

•S I

c Q

£

»

J COLUSA TROUGH DRAINAGE CANAL

CALIFORNIA

RECONSTRUCTION DESIGN LANDSIDE BERM CONSTRUCTION

AND DITCH RELOCATION

SACRAMENTO DtSTWCT. CORPS OF ENGINEERS SEPTEMBER 1992

FIGURE 11

Page 40: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,
Page 41: UNCLASSIFIED AD NUMBER LIMITATION CHANGESconstruction necessary to restore the project flood control levees along the Coiusa Trough Drainage Canal and the Knights Landing Ridge Cut,