unique design concrete preheater tower - ppc ltd. · pdf fileunique design concrete preheater...
TRANSCRIPT
1
Unique Design Concrete Preheater Tower
Preheater tower constructed of concrete with steel floorsConcrete section 105m high (35 storey building)
Additional 10m cyclone structureFootprint 25.3m by 20.4m
1 720 tons steel reinforcing & 9 540 m³ concrete
1 270 tons structural steel for floorsImportant to have ‘vertical’ aspect of preheater constructed when preheater parts started arriving at site
Time savingOnly achieved by utilising concrete & sliding to a special design
Cost effective (+7% saving compared to steel) Aesthetically pleasing Used our product
2
In-Line Calciner Plus Six-Stage Preheater
Kiln 4.55m diameter x 54m Calciner 6.6m diameter x 27m
268oC
Cyclones 1-2: 6.9m diameter
Cyclones 3-6: 7.2m diameter
3 Air 2.5m diameter
3
Pre-Heater H2
4
Pre-Heater H2
5
Pre-Heater H3
6
Pre-Heater H4
7
Pre-Heater H5
8
Pre-Heater H6
9
Pre-Heater H7
10
Pre-Heater H8
11
Pre-Heater H9
12
Pre-Heater H9
13
1200 Metres of Piling Installed
March 2007
1.2metre diameter piles
14
Constructed Using 80 ton Slide Platform
15
16
Around the Clock Construction
17
18
19
20
Preheater Topped-Out After 58 Days
May 2007
21
Preheater Structure Dominates the Skyline
22
Mechanical Installation Began Immediately
June 2007
23
Kiln Drive Installation Kiln Pier 2
Preheater Steelwork: Level H3
Structural Steel Floor H3
24Steel Fixing in Preheater: Level H3
25MMC Clinker Cooler Frame
26
Kiln Shell Arriving on Site
27
Kiln 2 LT Substation
New Clinker Return System
Kiln 2 Cooler ESP
Burners Platform
Coal Mill Building
Clinker CoolerKiln Pier 1
New Kiln Shell Sections
August 2007
28
Riding Ring Hoisted into Position
29August 2007
30
31
32
33
34
35
36Raw Mill Building: Sept 2007
37
‘Kopanelang’ Contractors Village
Feb 2006
38
Contractors Camp Catering Facilities
39
28 New Staff Houses Built
Nov 2006
Existing Village
New Houses
40
2 Lost Time Injuries Recorded to Date
More than 2 million man
hours worked to dateMore than 2 million man
hours worked to date
41
One of PPC’s core values: ‘We assist with up-liftment in communities in which we operate’
Dwaalboom situated near three (very rural) communities Rate of unemployment in area >50%
Important to ensure maximum economic spin-off from the project into the disadvantaged Dwaalboom communities‘Labour’ component comes from these areas only
>40% of staff at site from local communityRecruitment centre built
Daily transport to & from home provided
One good meal per day at site for every worker
Focus on Local Community Involvement
Excellent labour relations between contractors & local community employeesExcellent labour relations between contractors & local community employees
Opening of Holfontein Pension Payout & Recruitment Centre (June 2006)
Batsweledi in the Community
43
Jupiter Clinker Milling Facility Upgraded
Jupiter plant commissioned 1970
Mothballed in 1998 (eight years)
Used as bag/bulk cement depot
44
Upgrade Programme at Jupiter
Environmental Issues AddressedEnclosed & de-dusted clinker storeEnclosed all dust-generating beltsOverhaul/addition of dust collectorsAutomatic doors to tippler enclosure
Improvements AffectedNew Haver & Boecker packer & Beumer palletiser All spillage eliminated Upgrade of extender-blending facility
Major RefurbishmentsAll electric motors/gearboxes overhauledOverhauled overhead crane, tippler, cement transport system etc.Plant clean up & extensive painting
45
Clinker Storage Facility Enclosed
46
Raw MillClinker Store
Kiln ESPTippler
Dust Collectors Upgraded
47
Other Projects in the Pipeline
Batsweledi project first phase of 20 year modernisation programmeBased on combination of capacity replacement & expansion
New cement milling complex under construction at Hercules plant1Mt/yr capacity Loesche vertical roller mill (3150kW)35kt clinker silo, 10kt cement silo, tippler upgrade Cost~€61mCommissioning planned for July 2009Replace two old mills, maximise product extension (~0.3Mt/yr) &balance clinker/milling capacity in Inland Region
Planned new 1.25Mt/yr factory at Riebeeck (Western Cape) Greenfields projectIn feasibility stage (in middle of EIA approval process)Capital cost estimated at ~€340mCommissioning planned for 2010/2011
Studies underway for next Inland Region expansion
48
Summary
Batsweledi PPC’s first new factory in over 20 yearsPart of PPC’s 20 year modernisation programmeMost modern South African cement factory Utilises latest technology Lowest cost producing factoryEnvironmentally friendly & energy efficientProject within budget & on timeSafety is not negotiableCommunity involvement keyOther projects planned to meet country’s future cement demandOnly 6 months to commissioning date & counting!
For ongoing project update refer PPC website: www.ppccement.co.zaFor ongoing project update refer PPC website: www.ppccement.co.za
Thank You
Port Elizabeth Cement Silo