unit 1 primary containment vessel internal investigation · 2017-07-27 · legend:measurement...
TRANSCRIPT
Unit 1 Primary Containment Vessel Internal Investigation〜 Analysis of image data and dose data 〜
Tokyo Electric Power Company Holdings, Inc
July 27, 2017
1
1.Outline of analysis
Measurement points Purpose of measurementD0①〜③ Diffusion of fuel debris from the drain sumpBG Background levels against D0〜D3 measurementD1①②,D2①〜③ Diffusion of fuel debris from pedestal opening
D3 Possibility of fuel debris reaching to the PCV shell
Primary Containment Vessel (PCV)
Cross section of 1st floor PCV
Pedestal opening
CRD railPedestal
BG
D3D2
D1
X-100Bpenetration
We sharpened the images took in March, 2017 and re-analyzed, while examined the possibility of debris diffusion from the pedestal opening using dose data gathered in the investigation.
Positions of image and dose data are as follows:
Drain sump
D0
Extended figure
Extended figure
Legend:measurement date(MM/DD)
Pedestal
Pedestal Drain sump
X-100Bpenetration
Opening
2
Image data of the measurement points were sharpened. Sharpened image of the point D0② shows no extensive deformity and damage of existing structures
including valves, pipes and steels. The checker plate of drain sump was not found due to deposits.original
Valve
SteelPipe elbow
valvevalve
SteelSteel
Near point D0② before disaster
Pipe elbowPipe elbow
Checker plate of drain sump
2.Analysis result of image data(1/2)
sharpened
Position and direction of D0②Drain sump pump
Pedestal side
Pedestal side
Pedestal side
3
Point D0③ Point D1② Point D2③
Obtained
images
Sharpenedim
ages
Fallen object
2.Analysis result of image data(2/2) Image data other than D0② were sharpened too. Fallen object was found at the point D2③. No new information at the points D0 and D1.
4
3.Analysis result of dose data3.1 Estimation of possibility of fuel debris diffusion(1/2)
【Before investigation】 In the case that fuel debris exist at the PCV bottom※ and there are deposits of less than 0.1
m (assuming concrete as deposit in analysis) on the debris, we found it possible to estimate the possibility of fuel debris under deposits.
Distance from floor of the basement [m]
Deposit (approx.0.1m)
Accumulated water
Fuel debrisDo
se r
ate
in w
ater
[Gy/
h]
Dose distribution image
Deposits of approx. 0.1m on the fuel debrisNo fuel debris, only deposit(No dose from deposit)
※ It is assumed that fuel melted the structures in thereactor at the accident and fused with Co-60 in thestructures.
PCV bottom
5
Possibility of fuel debris under deposits was estimated in the following steps:
Main dose source (nuclide) on the deposit surface at point BG where is less affected by fuel debris is determined.
Analysis result at BG and D0③ where are considered to be less affected with fuel debris assuming there is no fuel debris and there is Cs-137 on the deposit surface as main source is to be compared with the measured dose data.
Analysis result at D1 and D2 where there are possibly fuel debris assuming there are main source and fuel debris on the deposit surface is to be compared with the measured dose data, and the possibility of fuel debris diffusion is to be estimated.
Possibility of fuel debris diffusion is estimated.
3.Analysis result of dose data3.1 Estimation of possibility of fuel debris diffusion(2/2)
6
【 Point BG 】
Distance from deposit surface [m]
正規
化し
た⽔
中線
量率
[―]
As dose rate measured from the deposit surface※1 is almost equal to Cs-137 decay curve in decay rate by distance, main dose source (nuclide) is considered to be Cs-137.
※1:Impacts of accumulated water and structures are subtracted from the measurement.※2:It is assumed that fuel debris fused with Co-60 in the melted structures in the reactor
at the accident. ※3:Dose rate is normalized by treating dose rate nearest the deposit surface as “1”.
0.1
1
0 0.05 0.1 0.15 0.2
Dose rate measured from deposit surfaceCs-137Approximated curve for measurementFuel debris supposed in analysis※2
△
Norm
aliz
ed※
3 dos
e ra
te in
wat
er[―
]
3.Analysis result of dose data3.2 Analysis of dose distribution – BG: main source on the deposit surface
77
We analyzed BG and D0③ assuming Cs-137 is main source on the deposit surface. It is assumed that there is no fuel debris at BG and D0③, because these points have thin deposits
and enough distance from the pedestal opening. Analysis based on above assumption well-matches with measurement. Therefore, it is considered
that there is no fuel debris under deposits at BG and D0③ or very little even if exist.
堆積物 滞留⽔
【 Point BG 】 【 Point D0③ 】
0
5
10
15
20
25
0 0.5 1 1.5Do
se ra
te in
wat
er [
Gy/h
]Distance from floor of the basement [m]
測定結果測定結果(参考値)D0③解析値Analysis result
0
5
10
15
20
25
0 0.5 1 1.5
Dose
rate
in w
ater
[Gy
/h]
Distance from floor of the basement [m]
測定結果測定結果(参考値)BG解析値
堆積物 Accumulatedwater
Analysis result
Deposit
PCV bottomPCV bottom
3.Analysis result of dose data3.3 Analysis of dose distribution – Possibility of fuel debris in the deposits(1/2)
Note)◆Measurement:Measured by halting censor◇Measurement(Reference):Measured by moving censor
(average dose rate)
Measurement (reference)
Measurement MeasurementMeasurement (reference)
Accumulatedwater
Deposit
We have analyzed dose rate in the case of fuel debris exist under deposits of about 0.9m height, in range of deposit height measured at D1 and D2.
Analysis result for point D2③ near pedestal opening is as the figure bellow. Existence of fuel debris cannot be examined in the case of thick deposits due to their shield. The cause examination cannot be done is considered to be that there is no fuel debris, or
that thick deposits and structures have profound shield effect. As the deposit thickness is currently unknown, we cannot determine it.
※ The structures might exist under the deposits.
D2③ Analysis condition( Height of deposits is 0.9m)① Deposit thickness:0.9m② Deposit thickness:0.3m③ Deposit thickness:0.1m
80 0.5 1 1.5
地下階床⾯からの距離 [m]
滞留⽔燃料デブリ
⽔中線量率
[Sv/
h]
0.9m
堆積物※
0
5
10
15
20
25
30
35
40
0
5
10
15
20
25
30
35
40
Deposit※
AccumulatedwaterFuel debris
◆ Measurement◇ Measurement (Reference)
Analysis①(deposits of 0.9m)Analysis②(deposits of 0.3m)Analysis③(deposits of 0.1m)
Note)◆Measurement:Measured by halting censor◇Measurement(Reference):Measured by moving censor
(average dose rate)
Dose
rate
in w
ater
[Gy/
h]
PCV bottom
3.Analysis result of dose data3.3 Analysis of dose distribution – Possibility of fuel debris in the deposits(2/2)
Distance from basement floor [m]
9
4.Conclusion<Analysis result of image data> Analysis of image data at the point D0 near the drain sump shows no extensive
damage and collapse of visible structures (steel, valve) near the drain sump (X-100B side).
<Analysis result of dose data> Main source on the deposit surface is considered to be Cs-137 from analysis. As analysis result at the point BG and D0③ assuming that deposit thickness is
thin and there is Cs-137 on the deposit surface is almost equal to measured dose rate, it is considered that there is no fuel debris or very little even if exist.
Analysis of dose rate at the point D1 and D2 near the pedestal open did not lead any meaningful result about the possibility of fuel debris in the deposits due to high location of deposit surface.
<Future policy> We will discuss the range and the method of the next investigation considering
this analysis result and the characteristics of deposits collected just bellow X-100 penetration.
Reference: Analysis of image dataEstimation of deposit surface height
※1 Height of the deposit surface is calculated from the distance between censor and deposit surfaceobtained by SFM(Structure from Motion) and the dropping length of censor.
・Value in yellow box is estimated height of deposit surface calculated from image analysis.・Value in () is lowest height of hanged censor.・Deposit thickness bellow the deposit surface is unknown.
10
D2①
D2②③
D1②
D1①
約1.5m
1.0m(1.0m)
0.9m(0.9m※)
0.9m(0.9m)
0.8m(0.9m)
約3.3m
D0③
0.3m(0.3m)
0.2m(0.3m)
Estimation of deposit surface height from image※1
1st floor grating
Water surface
Approx. 3.3m
PRL pipe
PRL pipe
Pedestal opening
A-A cross section B-B cross section
Basement floor
Approx. 1.5m
※ Height measured by closing censor
11
Analysis for various thickness of fuel debris and deposits were carried out.
Reference: Analysis of dose dataDose distribution analysis – possibility of fuel debris in deposit
■Point D1①Analysis condition (Deposit height is 0.8m)① Deposit thickness:0.8m② Deposit thickness:0.3m
■Point D1②Analysis condition (Deposit height is 0.9m)① Deposit thickness:0.9m② Deposit thickness:0.3m
0.8m
堆積物燃料デブリ 滞留⽔
0.9m
堆積物燃料デブリ 滞留⽔
0
5
10
15
20
25
0 0.5 1 1.5
Dos
e ra
te in
wat
er[G
y/h]
Distance from basement floor [m]
測定結果測定結果(参考値)解析結果①(燃料デブリ無し)解析結果②(燃料デブリ0.5m)
0
5
10
15
20
25
0 0.5 1 1.5
Dos
e ra
te in
wat
er[G
y/h]
Distance from basement floor [m]
測定結果測定結果(参考値)解析結果①(燃料デブリ無し)解析結果②(燃料デブリ0.6m)
注)◆測定結果:センサを⽌めて測定した値◇測定結果(参考値):センサ吊下げ動作中の線量率の平均値
Analysis ①(0.8m thick deposit)Analysis ②(0.3m thick deposit)
Analysis ①(0.9m thick deposit)Analysis ②(0.3m thick deposit)
PCV bottomPCV bottom
Accumulatedwater
AccumulatedwaterFuel debris
Fuel debrisDeposit Deposit
MeasurementMeasurement (reference)
MeasurementMeasurement (reference)
Note)◆Measurement:Measured by halting censor◇Measurement(Reference):Measured by moving censor
(average dose rate)
12
Analysis for various thickness of fuel debris and deposits were carried out.
■Point D2①Analysis condition (deposit height is 1.0m)① Deposit thickness:1.0m② Deposit thickness:0.3m
■Point D2②Analysis condition (deposit height is 0.9m)① Deposit thickness:0.9m② Deposit thickness:0.3m
1.0m
堆積物燃料デブリ 滞留⽔
0.9m
堆積物燃料デブリ 滞留⽔
0
5
10
15
20
25
0 0.5 1 1.5
Dos
e ra
te in
wat
er[G
y/h]
Distance from basement floor [m]
測定結果測定結果(参考値)解析結果①(燃料デブリ無し)解析結果②(燃料デブリ0.7m)
0
5
10
15
20
25
0 0.5 1 1.5
Dos
e ra
te in
wat
er[G
y/h]
Distance from basement floor [m]
測定結果測定結果(参考値)解析結果①(燃料デブリ無し)解析結果②(燃料デブリ0.6m)
Analysis ①(1.0m thick deposit)Analysis ②(0.3m thick deposit)
Analysis ①(0.9m thick deposit)Analysis ②(0.3m thick deposit)
PCV bottomPCV bottom
Reference: Analysis of dose dataDose distribution analysis – possibility of fuel debris in deposit
Note)◆Measurement:Measured by halting censor◇Measurement(Reference):Measured by moving censor
(average dose rate)
DepositDeposit
Accumulatedwater
AccumulatedwaterFuel debris Fuel debris
MeasurementMeasurement (reference)
MeasurementMeasurement (reference)
13
【 Point D2③ 】
正規
化し
た⽔
中線
量率
[―]
0.01
0.1
1
0 0.1 0.2 0.3 0.4
堆積物表⾯からの線量率測定結果Cs-137測定値近似曲線燃料デブリ※1
△
解析で想定した燃料デブリ※1
【 Point D0③ 】
正規
化し
た⽔
中線
量率
[―]
堆積物表⾯からの線量率測定結果Cs-137測定値近似曲線燃料デブリ※2
△
0.01
0.1
1
0 0.1 0.2 0.3 0.4
正規
化し
た⽔
中線
量率
[―]
解析で想定した燃料デブリ※1
Reference: Analysis of dose dataMain source on the deposit surface-D0③,D2③
Distance from deposit surface [m] Distance from deposit surface [m]
Dose rate measurementCs-137Approximated for measurementAssumed fuel debris ※1No
rmal
ized
dos
e ra
te in
wat
er[―
]
Norm
aliz
ed d
ose
rate
in w
ater
[―]
Dose rate measurementCs-137Approximated for measurementAssumed fuel debris ※1
※1 It is assumed that fuel melted the structures in thereactor at the accident and fused with Co-60 in thestructures.