UNIT - VI

PROJECT MANAGEMENT

Page 2: Unit  vi

HRM In A Dynamic Environment

What is a project?

“A project is a series of activities or tasks or operations directed to accomplishment of a desired objective.”

“A project is a temporary endeavour undertaken to create a "unique" product or service.”

Page 3: Unit  vi

HRM In A Dynamic Environment

EARLY TECHNIQUES OF PROJECT MANAGEMENT

1. Gantt’s Bar Chart

2. Milestone Chart

Page 4: Unit  vi

HRM In A Dynamic Environment

NETWORK ANALYSIS

Network Analysis refers to a number of techniques for the planning and control of complex projects.

The two most frequently used forms of network planning are:

1. Programme Evaluation and Review Technique (PERT)

2. Critical Path Method (CPM)

Page 5: Unit  vi

HRM In A Dynamic Environment

WHAT IS A NETWORK?

A network is a graphical diagram consisting of certain configuration of “Arrows” () and “Nodes” () for showing the logical sequence of various tasks to be performed to achieve the project objective.

Page 6: Unit  vi

HRM In A Dynamic Environment

PERT / CPM TECHNIQUES

The initial step in PERT/CPM project scheduling process is the determination of all specific activities that comprise the project and their relationships.

Page 7: Unit  vi

HRM In A Dynamic Environment

EXAMPLE

Activity Description Duration (in weeks)

Immediate predecessor

A Obtain the budget approval

2 -

B Obtain the machine

5 A

C Hire the operator 1 A

D Install the machine 1 B

E Train the operator 6 C

F Produce the goods 1 D,E

Page 8: Unit  vi

HRM In A Dynamic Environment

TERMS USED IN A NETWORK

1. Activity: An effort that is required to complete a part of the project. It is represented by “”.

2. Node: It represents the beginning or completion of an activity. It is represented by “”

Page 9: Unit  vi

HRM In A Dynamic Environment

RULES OF NETWORK CONSTRUCTION

1. Each defined activity is represented by one and only one arrow in the network.

2. Before an activity can be undertaken, all activities preceding it must be completed.

3. The arrows depicting various activities are indicative of logical procedure only. The length and bearing of the arrows are of no significance.

Page 10: Unit  vi

HRM In A Dynamic Environment

RULES OF NETWORK CONSTRUCTION

4. The arrow direction indicates the general progression in time. Head events and Tail events.

5. When a number of activities terminate at one event, it indicates that no activity emanating from that event may start unless all activities terminating there have been completed.

6. Events are identified by numbers.

7. The activities are identified by the numbers of their starting and ending events or by alphabets.

Page 11: Unit  vi

HRM In A Dynamic Environment

RULES OF NETWORK CONSTRUCTION

8. A network should have only one initial and terminal node.

9. Merge Event

Burst Event

A

B

C

AB

C

Page 12: Unit  vi

HRM In A Dynamic Environment

RULES OF NETWORK CONSTRUCTION

10. Parallel activities between two events, without intervening events, are prohibited. When two or more parallel activities in a project have the same head and tail events, dummy activities are needed in constructing the network.

Dummy activities do not consume time or resources. An efficient network contains a minimum number of dummy activities required to portray the correct precedence relationships.

11. Looping is not permitted in a network.

Page 13: Unit  vi

HRM In A Dynamic Environment

Network analysis

3-2

It is a Planning project Management

It means construction of Variances

It is process Technique

It is outsourcing analysis

Page 14: Unit  vi

HRM In A Dynamic Environment

What is Network

3-2

Network analysis is a system which plans projects both large

and small by analyzing the project activities

Projects are broken down to individual tasks or activities,

which are arranged in logical sequential order

A network diagram is constructed which presents the

Relationship b/w all the activities are involved

Page 15: Unit  vi

HRM In A Dynamic Environment

Meaning and Definition

3-2

According to author – “Network analysis helps to designing, Planning, Coordinating and decision making in order to accomplish the project economically in the minimum available time with the limited available resources.”

Page 16: Unit  vi

HRM In A Dynamic Environment

Techniques of Network3-2

PERT

CPM

RAMS

DEP

COPAC

MAP

RPSM

LCS

MOSS

PCS

GERT

Project analysis

Page 17: Unit  vi

HRM In A Dynamic Environment

Key concepts of Network3-2

Activity

Event

Predecessor Event

Successor Event

Net work

Dummy activity

Construction of Project network

Page 18: Unit  vi

HRM In A Dynamic Environment

Key concepts of Network3-2

ACTIVITY

Activity means a work. A project consists of several activities. An activity takes time. It is represented by an arrow in a diagram of the network. Eg. An activity in house construction can be flooring.

Flooring

Page 19: Unit  vi

HRM In A Dynamic Environment

Key concepts of Network3-2

Event

It is the beginning or the End of an activity. Events are represented by circles in a project network diagram. The events in a network are called the nodes.

Punching

Start Stop

Page 20: Unit  vi

HRM In A Dynamic Environment

Key concepts of Network3-2

Predecessor Event

The event just before another event is called the predecessor event

Page 21: Unit  vi

HRM In A Dynamic Environment

Key concepts of Network3-2

Successor Event

The event just following another event is called the successor event

1 22

3

4

5

6

Page 22: Unit  vi

HRM In A Dynamic Environment

Key concepts of Network3-2

Successor Event

In this diagrams

Event 1 is predecessor for the event 2

Event 2 is successor to event 1

Event 2 is predecessor for the events 3,4 and 5

Event 4 is predecessor for the event 6

Event 6 is successor to events 3, 4 and 5

Page 23: Unit  vi

HRM In A Dynamic Environment

Key concepts of Network3-2

Network

A network is series of related activities and events which

result in an end product or service.

The activities shall follow a prescribed sequence.

It is construction area of network path

Page 24: Unit  vi

HRM In A Dynamic Environment

Key concepts of Network3-2

Dummy activity

A dummy activity is an activity which does not consume any

time.

sometimes it may be necessary to introduce a dummy

activity in order to provide connectivity to a network only.

Page 25: Unit  vi

HRM In A Dynamic Environment

Key concepts of Network3-2

Construction of a project network

A project network consists of a finite number of events and

activity by adhering to a certain sequential order.

It is a path way of network

Page 26: Unit  vi

HRM In A Dynamic Environment

Problem 13-2

Construct the network diagram for a project with the following activities

ActivityEvent-Event

Number of Activity

PredecessorActivity

1-21-31-42-53-64-65-6

ABCDEFG

---ABCD

Page 27: Unit  vi

HRM In A Dynamic Environment

3-2

Solution

1

2

3

4

A

B

C

Page 28: Unit  vi

HRM In A Dynamic Environment

3-2

Solution

1 2 5A D

Page 29: Unit  vi

HRM In A Dynamic Environment

3-2

Solution

1 3 6B E

Page 30: Unit  vi

HRM In A Dynamic Environment

3-2

Solution

2 5 6G G

Page 31: Unit  vi

HRM In A Dynamic Environment

3-2

Solution

5

3

4

6

G

E

F

Page 32: Unit  vi

HRM In A Dynamic Environment

Solution3-2

1

2

3

4

6

5A

D

B

C

E

F

G

Page 33: Unit  vi

HRM In A Dynamic Environment

CRITICAL PATH METHOD (CPM)3-2

The critical path method (CPM) aims at the determination of the time to complete a project and the important activities on which a manager shall focus attention.

Page 34: Unit  vi

HRM In A Dynamic Environment

Problem 13-2

The following details are available reading a project

ActivityEvent-Event

PredecessorActivity

ABCDEF

357

1054

Duration(Weeks)

-AABC

D,E

First let us construct the network diagram for the given project. We mark the time estimates along the arrows representing the activities

Page 35: Unit  vi

HRM In A Dynamic Environment

Solution3-2

1 22

3

4

5 6

Start Event End Event

A

B

C

D

E

F

3

5

7

10

5

4

Page 36: Unit  vi

HRM In A Dynamic Environment

Solution3-2

Path I

1 22 5 63A B D F

3 5 10 4

with a time of 3+5+10+4 =22 weeks

Page 37: Unit  vi

HRM In A Dynamic Environment

Solution3-2

Path II

1 22 5 64A C E F

3 7 5 4

with a time of 3+7+5+4 =19 weeks

Page 38: Unit  vi

HRM In A Dynamic Environment

Solution3-2

Compare the times for the two paths. Maximum of {22,19} = 22. we see that path I has maximum time of 22 weeks. The critical activities are A,B,C,D and F, finally the project completion time is 22 weeks.

Page 39: Unit  vi

HRM In A Dynamic Environment

Problem 23-2

Find out the completion time and the critical activities for the following project.

1

2

3

4

6

5

8 10

9

A

DG

KK

L

7JF

C

B E H

I

820 8

611

1610

725 10

5

Page 40: Unit  vi

HRM In A Dynamic Environment

Problem 33-2

Draw a network diagram and determine the critical path for the following project.

ActivityEvent-Event

1-21-31-42-53-63-74-75-86-87-98-9

56357

1042564

Duration(Weeks)

Page 41: Unit  vi

HRM In A Dynamic Environment

Solution3-2

We have the following network diagram for the project.

1

2

4

3 6 89

5

7

A

B

C

D

E

FG

H

I

J

K5

3

6

5

4

10

7 5

6

4

2

Page 42: Unit  vi

HRM In A Dynamic Environment

Problem 43-2

The following details are available reading a project

Activity PredecessorActivity

ABCDEFGHIJK

4736476

10342

Time estimates (Weeks)

---ABBCED

F,GH,I

Draw a project network diagram

Page 43: Unit  vi

HRM In A Dynamic Environment

PERT analysis3-2

INTRODUCTION

Programme Evaluation and Review Technique (PERT) is a tool that would help a project manager in project planning and control. It would enable him in continuously monitoring a project and taking corrective measures wherever necessary. This technique involves statistical methods.

Page 44: Unit  vi

HRM In A Dynamic Environment

PERT analysis3-2

The PERT analysis includes 3 Aspects

1. Pessimistic time estimate (tp)

2. Optimistic time estimate (to)

3. Most likely time estimate (tm)

Formulae te = to + 4tm + tp

6

Page 45: Unit  vi

HRM In A Dynamic Environment

Problem 13-2

ActivityPredecessor

ActivityOptimistic Time

estimate (to days)Most likely time

estimate (tm days)Pessimistic time

estimate (tp days)

A - 2 4 6

B A 3 6 9

C A 8 10 12

D B 9 12 15

E C 8 9 10

F D,E 16 21 26

G D,E 19 22 25

H F 2 5 8

I G 1 3 5

Page 46: Unit  vi

HRM In A Dynamic Environment

Solution 3-2

ActivityOptimistic Time

estimate (to days)

4 *Most likely time estimate (tm days)

Pessimistic timeestimate (tp

days)to + 4tm +tp

Time estimateTe = to+4tm+tp

6

A 2 16 6 24 4

B 3 24 9 36 6

C 8 40 12 60 10

D 9 48 15 72 12

E 8 36 10 54 9

F 16 84 26 126 21

G 19 88 25 132 22

H 2 20 8 30 5

I 1 12 5 18 3

From the three time estimates tp, tm, to calculate te for each activity.

Page 47: Unit  vi

HRM In A Dynamic Environment

Solution (contd..)3-2

1 2

3

4

5

6

7

8A

4

B

6

C10

D

12

E9

F21

G

22

H

5

3

I

Page 48: Unit  vi

HRM In A Dynamic Environment

Path I3-2

1 2 3 5 6 8

A

4

B

6

D

12

F

21

H

5

Time for the path : 4+6+12+21+5=48 days

Page 49: Unit  vi

HRM In A Dynamic Environment

Path II3-2

1 2 3 5 7 8

A

4

B

6

D

12

G

6

I

3

Time for the path : 4+6+12+6+3=31 days

Page 50: Unit  vi

HRM In A Dynamic Environment

Path III3-2

1 2 4 5 6 8

A

4

C

10

E

9

F

21

H

5

Time for the path : 4+10+9+21+5=49 days

Page 51: Unit  vi

HRM In A Dynamic Environment

Path IV3-2

1 2 4 5 7 8

A

4

C

10

E

9

G

6

I

3

Time for the path : 4+10+9+6+3=32 days

Page 52: Unit  vi

HRM In A Dynamic Environment

Final3-2

Compare the times for the four paths.Maximum of { 48,31,49,32} = 49

Page 53: Unit  vi

HRM In A Dynamic Environment

Problem 23-2

Activity Optimistic Timeestimate (to days)

Most likely time estimate (tm days)

Pessimistic timeestimate (tp days)

1-2 3 6 9

1-6 2 5 8

2-3 6 12 18

2-4 4 5 6

3-5 8 11 14

4-5 3 7 11

6-7 3 9 15

5-8 2 4 6

7-8 8 16 18

Page 54: Unit  vi

HRM In A Dynamic Environment

Solution 3-2

Activity

Optimistic Timeestimate (to days)

4 *Most likely time estimate (tm days)

Pessimistic timeestimate (tp

days)to + 4tm +tp

Time estimateTe = to+4tm+tp

6

1-2 3 24 9 36 6

1-6 2 20 8 30 5

2-3 6 48 18 72 12

2-4 4 20 6 30 5

3-5 8 44 14 66 11

4-5 3 28 11 42 7

6-7 3 36 15 54 9

5-8 2 16 6 24 4

7-8 8 64 18 90 15

From the three time estimates tp, tm, to calculate te for each activity.

Page 55: Unit  vi

HRM In A Dynamic Environment

Solution (contd..) 3-2

1

2

3

1

6

4

5

7

8

A

B

6

5

C

12

D

5

E

9

F

11

7

G

I

4

15

H

Page 56: Unit  vi

HRM In A Dynamic Environment

Problem 33-2

ActivityPredecessor

Activity

Optimistic Timeestimate (to

days)

Most likely time estimate (tm

days)

Pessimistic timeestimate (tp

days)

A - 2 5 8

B A 2 3 4

C A 6 8 10

D A 2 4 6

E B 2 6 10

F C 6 7 8

G D,E,F 6 8 10

Page 57: Unit  vi

HRM In A Dynamic Environment

Solution 3-2

Activity

Optimistic Timeestimate (to days)

4 *Most likely time estimate (tm days)

Pessimistic timeestimate (tp

days)to + 4tm +tp

Time estimateTe = to+4tm+tp

6

A 2 20 8 30 5

B 2 12 4 18 3

C 6 32 10 48 8

D 2 16 6 24 4

E 2 24 10 36 6

F 6 28 8 42 7

G 6 32 10 48 8

From the three time estimates tp, tm, to calculate te for each activity.

Page 58: Unit  vi

HRM In A Dynamic Environment

Solution (Network)3-2

1 2 5 6

4

3

A

5

D

4

G

8

B

3

C

8

E6

F7

Page 59: Unit  vi

HRM In A Dynamic Environment

Problem 43-2

ActivityPredecessor

Activity

Optimistic Timeestimate (to

days)

Most likely time estimate (tm

days)

Pessimistic timeestimate (tp

days)

A - 12 14 22

B - 16 17 24

C A 14 15 16

D A 13 18 23

E B 16 18 20

F D,E 13 14 21

G C,F 6 8 10

Page 60: Unit  vi

HRM In A Dynamic Environment

Problem 53-2

ActivityPredecessor

Activity

Optimistic Timeestimate (to

days)

Most likely time estimate (tm

days)

Pessimistic timeestimate (tp

days)

A - 2 4 6

B - 3 5 7

C A 5 6 13

D A 4 8 12

E B,C 5 6 13

F D,E 6 8 14

Page 61: Unit  vi

HRM In A Dynamic Environment

3-2

1.The process of shortening the time to complete a project is called crashing

and is usually achieved by putting into service additional labor or machines

to one activity or more activities.

2. Crashing involves more costs. A project manager would like to speed up a

project by spending as minimum extra cost as possible.

INTRODUCTION TO PROJECT CRASHING

Page 62: Unit  vi

HRM In A Dynamic Environment

3-2

Step:1

Find the critical path with the normal times and normal costs for the activities and identify the critical activities.

Step:2

Find out the crash cost per unit time for each activity in the network. This is calculated by means of the following formulae

STEPS IN PROJECT CRASHING

Activity Time

Normal Time

Crash Time

Crash Time

Normal Time

Activity Cost

Normal Time & Cost

Crash Time & Cost

Page 63: Unit  vi

HRM In A Dynamic Environment

3-2

Crash cost/Time period = Crash cost-Normal cost/Normal time-Crash time

Step:3

Select an activity for crashing

STEPS IN PROJECT CRASHING