united states environmental protection agency in the matter of · poulenc currently uses the newer...
TRANSCRIPT
SFUND RECORDS CTR1652-04013
United States Environmental Protection AgencyRegion 9 AR0088
In the Matter of :
Iron Mountain Mine
Iron Mountain Mines, Inc.,T.W. Arman,Rhone-Poulenc Basic Chemicals Co.
First Amendment toOrder No. 94-12
Respondents
Proceeding under Section 106 of theComprehensive Environmental Response,Compensation and Liability Act of 1980,as amended by the Superfund Amendmentsand Reauthorization Act of 1986,(42 U.S.C. § 9606)
FIRST AMENDMENT TO ORDER NO. 94-12
1. This First Amendment to Order No. 94-12 is issued to
Respondents by the United States Environmental Protection Agency
("EPA") under the authority of section 106 (a) of the Comprehensive
Environmental Response, Compensation, and Liability Act of 1980,
as amended ("CERCLA"). This authority was delegated to the
Administrator of EPA on January 23, 1987, by Executive Order 12580
(52 Fed. Reg. 2926, January 29, 1987), and was further delegated
to EPA Regional Administrators on September 13, 1987 by EPA
Delegation No. 14-14-B. The Regional Administrator redelegated
this authority to the Director, Superfund Division. Except as
specified herein, this action does not alter any of the deadlines
or obligations in Order 94-12 or any other order issued by EPA in
connection with the Iron Mountain Mine Superfund Site.
2. Unless otherwise specified, defined terms in this First
Amendment shall be the same as the terms as defined in
Order 94-12.
I. FINDINGS OF FACT AND CONCLUSIONS OF LAW
3. Except as modified herein, this Amendment is based upon the
Findings of Fact contained in Order Nos. 93-01 (as amended) and
94-12 and the Conclusions of Law of contained in Order 94-12.
4. On September 30, 1992, EPA signed a Record of
Decision ("ROD2") that selected, among other things, treatment of
the Acid Mine Drainage ("AMD") discharges from the Richmond and
Lawson adits utilizing the lime/sulfide High Density Sludge
("HDS") treatment method.
5. On September 24, 1993, EPA signed a Record of
Decision ("ROD3") that selected, among other things, treatment of
the AMD flows from the Old/No. 8 Mine Seep utilizing the lime HDS
treatment method.
6. EPA selected HDS treatment as the method of treatment for
several reasons, including but not limited to:
a. EPA studies and research indicated that HDS sludge would
be chemically and physically more stable than simple mix sludge.
EPA tests on treated sludge showed that, compared to sludge
generated by simple mix, HDS sludge is more effective in binding
the metals in the sludge.
b. EPA studies and research indicated that HDS sludge would
have drainage characteristics that are superior to simple mix
sludge. Improved drainage characteristics will enable sludge to
dewater more effectively in the sludge drying beds at the
treatment plant and improve plant reliability.
c. EPA studies and research indicated that HDS sludge would
have superior physical and handling characteristics and would be
more manageable than simple mix sludge. These superior physical
characteristics would allow for adequate long term management of
the sludge disposal area, Brick Flat Pit ("BFP") .
d. EPA studies and research indicated that HDS sludge would
be more dense and would take up less volume than simple mix
sludge. This greater bulk density would extend the useful life of
the sludge disposal site at BFP significantly. EPA estimated that
compared to simple mix, treatment using the HDS method would
double the useful life of BFP.
e. EPA also determined that HDS treatment would be more
cost effective than simple mix treatment at the Minnesota Flats
plant site.
7. On November 3, 1993,- EPA issued Order 93-01 to Respondents
which required Respondents to, among other things, design and
construct an HDS treatment plant.
8. Rhone-Poulenc resisted construction of an HDS plant on the
ground that the aerated simple mix ("ASM") treatment method was
comparable to the HDS treatment method with respect to sludge
reduction, physical/handling characteristics and compliance with
other CERCLA requirements. EPA disagreed with Rhone-Poulenc's
technical position, but in order to expedite completion of a
treatment plant at Minnesota Flats, EPA agreed to take
responsibility for designing and constructing the HDS components
at the Site, provided that Rhone-Poulenc expeditiously design and
construct the simple mix components that complement the HDS
components to be constructed by EPA. EPA reserved all its rights
to seek recovery of its costs. On October 8, 1993, EPA amended
Order 93-01 to suspend the obligation of Rhone-Poulenc to
construct the HDS treatment components under Order 93-01.
9. On April 19, 1994, EPA issued Order 94-12 which required
5
Respondents to, among other things, collect, convey and treat all
acid mine drainage from the Richmond and Lawson Portals and the
Old Mine/No. 8 Seep and dispose of the treatment residue in BFP in
accordance the EPA approved Operation & Maintenance Plan.
10. Pursuant to Order 93-01, as amended, and Order 94-12 Rhone-
Poulenc constructed AMD collection and conveyance facilities,and
the ASM treatment plant components at Minnesota Flats.
11. Since approximately October 1994, Rhone-Poulenc has operated
the ASM treatment plant pursuant to Order 94-12.
12. Information obtained by EPA since it issued ROD2 and RODS,
including but not limited to design studies, actual data from the
existing treatment plant, and investigation of ASM plant
operations, has reinforced the superiority of the HDS system and
the deficiencies of using an ASM system to address the release and
threat of release hazardous substances at the Site.
13. The ASM plant has failed to produce a sludge that is
comparable to the sludge EPA anticipates the HDS method would
produce. The sludge produced by the ASM process has a high water
content, low density, and extremely poor handling characteristics.
Data provided by Rhone-Poulenc show that ASM sludge hauled from
the sludge drying beds to Brick Flat Pit has an average solids
content of less than 40%. EPA anticipates that a properly
6
operated HDS plant will generate a sludge with a solids content
between 60% and 65%. EPA estimates that an increase in solids
content from 40% to 60% would correspond to a volume reduction of
50%.
14. The ASM plant is replete with inherent operational
difficulties and other deficiencies. These problems make the
existing plant an unreliable and potentially unsafe manner to
respond to the releases or threats of releases from the Site that
may pose an imminent and substantial endangerment to public
health, welfare or the environment. The HDS treatment method
would eliminate or substantially reduce these difficulties and
deficiencies.
15. The HDS treatment method would also be more cost effective
than the existing ASM treatment method.
16. EPA's selection of the HDS treatment method was fully
consistent with the National Contingency Plan, 40 CFR § 300 et
seq.
17. The existing sludge drying beds were designed for HDS and are
too small to store all of the ASM sludge generated in a major
storm event. During the January 1995 storm event, the sludge
drying beds became full. A spill of untreated AMD from the
treatment plant was avoided only through the combination of
significant effort, considerable extra cost, and the fortuitous
presence of a large construction cadre on-site at the time.
18. Although Rhone-Poulenc has constructed one additional drying
bed since the 1994-1995 wet season, that bed is currently
unavailable to store ASM sludge. Due to the poor drainage
characteristics of the ASM sludge, the ASM sludge blinds off the
sand filters in the drying beds. As a result, unfiltered leachate
ponds at the top of the drying beds. Because the leachate must be
filtered prior to being discharged into Spring Creek, Rhone-
Poulenc currently uses the newer drying bed solely to filter the
leachate that ponds in the other three drying beds.
19. Rhone-Poulenc has regularly ripped the geotextile liner and
the geotextile grid when Rhone-Poulenc is removing the ASM sludge
from the drying beds. Destruction of or damage to the geotextile
liner increases the risk that unfiltered leachate will be released
into Spring Creek and Flat Creek. These rips threatened to cause,
or may have caused, the release of leachate into the environment.
20. Contaminated water has been detected adjacent to and
downgradient from the drying beds. The constituents and location
of the contamination indicate that the contamination may have been
caused in whole or in part by a leak in the liner. The
contaminated water flows into Flat Creek, upstream of residents
who use the water of Flat Creek for agricultural irrigation.
21. Future operation of the ASM treatment plant threatens to
cause similar rips and similar threatened or actual releases of
leachate because the ASM treatment method can require winter
sludge hauls due to the large volume that is generated. These
winter hauls threaten the integrity of the sludge drying bed
liners. Poor weather creates difficult working conditions.
Hauling in the winter does not permit sufficient drying time for
dewatering. The poor handling characteristics of the dewatered
ASM sludges, and the difficult working conditions in the drying
beds significantly increases the likelihood that sludge excavation
operations would damage the drying bed filter and lining system.
As discussed above, this damage may result in the release of
contaminants into the environment.
22. Using the HDS treatment method would reduce substantially the
likelihood of a liner tear and a release of leachate. Since HDS
will create a higher density sludge, sludge hauling will, in all
but the most extreme years, be required only once a year -- in the
summer. In the event of a liner tear during HDS operation, the
leachate from HDS sludge would pose less of a threat to public
health and the environment than leachate from ASM sludge because
the HDS leachate will be less voluminous than the ASM leachate.
23. The ASM sludge is thixotropic and does not allow for an
engineered and stable fill. The continued dumping of ASM sludge
threatens to make BFP unsafe and potentially unusable without
expensive corrective measures. The ASM sludge has blinded off and
clogged the bed-drainage system in BFP and threatens to clog the
few remaining column filter drains in BFP. Without adequate
drainage, BFP will become unmanageable and may have to be
abandoned well before its full capacity is realized.
24. Due to the poor handling characteristics of the ASM sludge,
there are very few options for managing the sludge. None of the
available options allow for the creation of a stable landfill.
Because the ASM sludges could not be placed as an engineered fill
in BFP, until recently, Rhone-Poulenc transported the ASM sludge
to a bluff above the eastern side of BFP and then dumped the ASM
sludge down a slope and into BFP. The bluff, and slope below the
bluff, have failed, so that this procedure can no longer be used.
Because ASM sludge is difficult to handle, Rhone-Poulenc is now
dumping the ASM sludge directly onto the edge of the BFP liner at
the west end of the pit. EPA is unaware of any engineering work
that demonstrates that the anchors for the liners were adequately
engineered for this purpose. If the liner is not properly
engineered, repeatedly dumping the sludge directly onto the edge
10
of the liner would threaten to rip the liner and cause a release
of leachate into the environment.
25. EPA studies indicate that the HDS sludge will have a
granular, soil-like consistency. This improved consistency will
allow for the management of BFP as an engineered landfill. This
improved consistency will also result in a sludge that will have
drainage characteristics that are superior to the ASM sludge. The
improved drainage characteristics will enable the landfill to
drain properly and allow BFP to be managed as a dry landfill.
26. Experience with the ASM treatment plant also confirms EPA's
conclusion that the HDS treatment method is more cost effective
than the ASM treatment method. The ASM treatment method generates
a much larger volume of sludge than the HDS treatment method, so
the cost of hauling sludge generated by the ASM method is
proportionally much greater than the cost of hauling sludge
generated by the HDS method. In addition, the unit cost of
hauling HDS sludge will be lower than ASM sludge. First, due to
its lower volume, HDS sludge will only need to be hauled in the
summer, when haul rates will be lower. Second, HDS has superior
handling characteristics so it will be easier (and less expensive)
to haul. While HDS could have slightly higher utility and
maintenance costs, those costs will generally be more than offset
11
by the lower haul costs associated with the HDS process.
27. EPA has designed and constructed improvements to the
treatment plant that will enable the treatment plant to treat AMD
using the HDS treatment method. Throughout the design and
construction of these improvements, EPA has kept Rhone-Poulenc
fully informed of its activities and has sought input from Rhone-
Poulenc on the project. During the tie-in of the HDS improvements
to the existing treatment facility, EPA carefully coordinated its
construction activities with Rhone-Poulenc representatives. EPA
has also provided early drafts of operation and maintenance
manuals to Rhone-Poulenc and requested comments on these drafts.
EPA understands that Rhone-Poulenc representatives are currently
using the manuals provided by EPA to train the operators of the
ASM treatment plant for HDS operation. EPA has coordinated and
sponsored training of Rhone-Poulenc personnel on the start-up,
operation and maintenance of the HDS improvements.
28. The HDS treatment plant is scheduled to begin operation on
January 7, 1997.
29. The actions required by this First Amendment to Order No. 94-
12 are necessary to protect the public health or the environment.
The response action was selected in ROD2 and ROD3 and were based
on the Administrative Records for those RODs. The actions
12
required by this First Amendment to Order No. 94-12 are based upon
all previous administrative records for the Site and the
administrative records for this First Amendment to Order No. 94-
12.
II. NOTICE TO THE STATE
30. Prior to issuing this First Amendment to Order No. 94-12, EPA
notified the State of California Department of Toxic Substances
Control, that EPA would be issuing this Amendment to Order No. 94-
12.
III. ORDER
31. The following provisions modify requirements contained in
Order 94-12:
HDS Treatment of AMD Flows
32. Starting January 7, 1997, Respondents shall treat, using the
high density sludge treatment process, acid mine drainage from the
Richmond and Lawson Portals and the Old Mine/No. 8 Seep.
33. Respondents shall operate the HDS plant in a manner that
conforms with the Operations and Maintenance Manual attached as
Attachment A and that conforms with the Long-Term Performance
Requirements contained in Table 2-2 of Attachment B.
13
34. Respondents shall operate the HDS plant in a manner that
optimizes sludge density and shall use their best efforts to meet
or exceed the sludge densities contained in Table 2-3 of
Attachment B.
35. Respondents shall permit EPA and EPA representatives to
monitor plant operations and plant performance in whatever manner
EPA and its representatives deem appropriate. This paragraph does
not supersede or affect any rights of inspection or other rights
that EPA has under this Order, as amended, or any other order or
any other statutory authority. Upon oral request by EPA or an EPA
representative, Respondents shall provide immediate access to AMD
flow data, and all other analytical data that is currently
available, in hard copy and electronic format. In conducing its
monitoring activities, EPA and its representatives will endeavor
to minimize interference with Respondents' operation and
maintenance of the treatment plant.
EPA Performance Test
36. EPA will conduct one or more 14-day performance tests of the
HDS system. EPA anticipates that the performance test(s) will
occur between January 7, 1997 and June 30, 1997. Respondents
shall cooperate with EPA and EPA representatives in performing
these tests, by among other things, permitting EPA and its
14
representatives access to the plant site, plant equipment, process
flows, plant data and plant laboratory equipment. The 14-day
performance test is described in Attachment B. During these 14-
day performance tests, EPA and its representatives will endeavor
to minimize interference with Respondents' operation and
maintenance of the treatment plant.
Sludge Disposal
37. Respondents shall dispose of the treatment sludges in Brick
Flat Pit in a manner consistent with the dry landfill operations
practices concept contained in Attachment D of Unilateral Order
93-01 (the "Dry Landfill Concept"). Brick Flat Pit shall be
managed in accordance with the EPA approved Landfill Management
Report and Plan ("LMRP").
38. Within 90 days of the date of this First Amendment to Order
No. 94-12, Respondents shall submit to EPA a Brick Flat Pit
Baseline Status Report which shall describe the current condition
of Brick Flat Pit and provide an engineering evaluation of the
status of simple mix sludges deposited within the landfill. The
Baseline Status Report shall provide an evaluation of historic
sludge management practices associated with treatment plant
operations, sludge dewatering, excavation, hauling and placement
in BFP. The Brick Flat Pit Baseline Status Report shall contain,
15
at a minimum, the following information:
a. An as-built drawing of the Brick Flat Pit Landfill
showing the final as-built topography prior to sludge placement
both in hard copy and electronic file format;
b. The location of all sludge disposed of at the landfill
to date both in hard copy and electronic file format;
c. Computed estimates of the volume of sludge placed in
Brick Flat Pit to date, including hard copy calculations and
electronic file format;
d. A complete listing of all analytical and geotechnical
data that has been produced or obtained to date by the Respondents
pertaining to sludge production at the treatment plant at
Minnesota Flats;
e. A complete listing of computed sludge haulage data
including volume, unit and total costs for sludge excavation and
haulage, repair and O&M of sludge drying beds, repair and O&M of
the haulage roads; and repair and O&M associated with the Brick
Flat Pit landfill operations and facilities;
f. A complete listing of the records and data pertaining to
filtrate contamination of sludge drying bed underdrain systems and
repair records for geotextile protective layers;
g. A complete listing (including detailed acvtivity
16
descriptions, engineering analyses and drawings) of any and all
changes to the EPA approved plans and specifications for the
sludge drying beds and Brick Flat Pit landfill facilities that
have been implemented without EPA approval. Examples of such
changes include, but are not limited to, removal of the sludge
drying bed geogrid protective layer, the removal of the protective
drainage rock from the filtrate riser pipes at Brick Flat Pit, and
the constructed dumping location at the west end of Brick Flat
Pit.
h. The current configuration of all drainage and erosion
control features in use;
i. A complete engineering evaluation of the
operability/functionality of the BFP filtrate collection system;
j. A discussion of any areas of concern or non-compliance.
The discussion shall include detailed illustrations of the area of
concern or non-compliance and the plans to correct any
deficiencies.
k. Compaction test reports;
1. Location of all access points including the point
currently being used for sludge dumping into the fill; and
m. Discussion of any changes in landfill management
practices or failures in BFP features or constructed facilities
17
and the sludge fill since commencement of placement operations.
39. By November 30th of each year, Respondents shall provide to
EPA, for EPA review and approval, an annual report on landfill
management practices (the Landfill Management Report and Plan)
that addresses landfill management for the 12-month period ending
on October 31 of that year and planned operations for the 12-month
period beginning on November 1 of that year. In the event that a
sludge haul occurs during the month of November, Respondents shall
provide data related to that sludge haul as a supplement to the
annual report. Respondents shall provide such supplement by
December 31 of the year in which the November sludge haul occurs.
40. Within 120 days of the effective date of this First Amendment
to Order No. 94-12 Respondents shall submit to EPA for EPA review
and approval a workplan that specifies the proposed contents of
the annual Landfill Management Report and Plan ("LMRP") and
documents the enginering studies to be performed in support of the
LMRP. The LMRP shall contain sufficient information to enable EPA
to effectively evaluate whether the landfill was properly managed,
consistent with the concept design for a dry landfill, over the
preceding 12 month period, and that the BFP landfill would be
properly managed as a dry landfill over the upcoming 12 month
period.
18
41. With respect to operations from the preceding 12-month period
ending on October 31 of that year, the Landfill Management Report
and Plan shall contain at a minimum the following information:
a. An updated as-built drawing of the BFP landfill, with
updated topography;
b. A discussion of the manner in which sludge was
dewatered, excavated, hauled and placed in the BFP landfill,
landfill operations practices, and any problems encountered during
sludge dewatering, excavation, haulage and placement, or landfill
operations;
c. A discussion of areas of non-compliance;
d. A discussion of repairs that were made to sludge
dewatering or BFP landfill facilities, or construction activities
that were undertaken modify sludge dewatering and BFP landfill
facilities;
e. As a minimum, the following flow, analytical and
geotechnical data shall be included in the LMRP:
i. Sludge influent flow rates to sludge drying beds
(to be reported as a daily average);
ii. Filtrate flow rates from sludge drying beds and
Brick Flat Pit (to be reported as a daily average);
iii. Filtrate water quality from sludge drying beds (to
19
be reported as a composite daily average) and
Brick Flat Pit (to be reported as a daily average);
iv. Sludge volume, specific gravity, solids contents
of sludge hauled to Brick Flat Pit (to be reported in
a manner consistent with the Operations and Maintenance Plan for
at least six locations from each sludge dewatering bed);
v. Total volume of Sludge in Brick Flat Pit and
stage/elevation curves;
vi. Results of routine analytical testing conducted on
Brick Flat filtrate and seepage discharge. This testing
shall include, as a minimum , flowrate, pH, total and
dissolved cooper, zinc, cadmium, and lead; and total iron and
ferrous iron. Respondents shall conduct this testing at
least every 2-weeks. In conducting this analysis,
Respondents shall comply with the procedures and standards
set forth in Sections 4,5,6,7 and 8 of Attachment B; and
f. Any inconsistencies between the activities or operations
projected in the previous LMRP and the activities or operations
actually undertaken during the projected period.
42. With respect to future operations for the 12-month period
beginning on November 1 of the year, the Landfill Management
Report and Plan shall contain at a minimum the following
20
information:
a. Identification of the area of the landfill to be used
for the placement of seasonal sludge production; a description of
sludge placement and landfill operations practices to be
employed;
b. Specifically identify each planned construction activity
to repair or modify sludge dewatering or landfill facilities and
any changes to sludge dewatering or landfill operations
practices; and
c. A discussion of any areas of concern;
d. A complete listing of the analytic and geotechnical
testing and methods that will be completed
i. prior to sludge haulage;
ii. during the sludge haulage; and
iii. On a routine basis.
Equipment Failure
43. In the event of equipment failure at the Site, Respondents
shall follow the following procedures:
a. In the case of equipment failure that causes or
threatens to (1) cause the release of AMD from the treatment
plant that is not fully treated in compliance with Table 2-2 of
Attachment B or (2) require Respondents to operate the plant in
21
aerated simple mix mode, Respondents shall:
i. Take all steps necessary to avoid and minimize the
release or threatened release from the treatment plant of AMD
that is not fully treated in compliance with Table 2-2 of the
Attachment B;
ii. Take all steps necessary to cure the problem that
causes or threatens to cause Respondents to operate the plant in
aerated simple mix mode and to cure the equipment failure as soon
as possible; and
iii. Notify EPA within eight hours of discovering the
failure by contacting the RPM by telephone.
b. In the case of any and all other equipment failures,
Respondents shall:
i. Take all steps necessary to repair or replace the
equipment as soon as necessary and
ii. Notify EPA within 48 hours of discovering the
failure by contacting the RPM via telephone.
c. Respondents shall report all equipment failures in the
appropriate monthly report.
44. EPA has equipped the treatment plant with certain essential
and long lead-time spare parts. However, Respondents are solely
responsible for:
22
a. Determining which spare parts are necessary or
appropriate to maintain on-site and
b. Maintaining necessary and appropriate spare parts at
the plant site.
Monitoring and Reporting Requirements
45. Respondents shall provide a monthly report to EPA and such
other persons as EPA identifies that describes the monthly
operation of the treatment plant.
46. Respondents shall monitor and report HDS plant performance
and AMD flow in accordance with the requirements set forth in
Section 3 of the Performance Standards and Verification Plan
("PSVP"), attached hereto as Attachment B. Respondents shall
conduct such monitoring and reporting in accordance with the
procedures and standards set forth in Sections 4,5,6,7 and 8 of
Attachment B. Respondents shall submit the information in a
monthly report to EPA and to such other persons as EPA
identifies. i. Respondents shall also include in the monthly
report results of analytical testing conducted on Brick Flat Pit
filtrate and seepage discharges that are called for in the
Landfill Management Report and Plan. Until EPA approves the data
to be included in the Landfill Management Report and Plan
pursuant to paragraph 39, Respondents shall include in the
23
monthly report the following analytical data conducted on Brick
Flat Pit filtrate and seepage discharge: flowrate; pH; total and
dissolved copper, zinc, cadmium, and lead; total iron and ferrous
iron. In conducting this analysis, Respondents shall comply with
the procedures and standards set forth in Sections 4,5,6,7 and 8
of Attachment B.
47. Respondents shall also include in the monthly report a
detailed description of equipment failures that occurred during
the preceding month, all steps taken to respond to the failure,
whether a release of untreated AMD or other impact occurred as a
result of the failure, and all steps that were or will be taken
to avoid the risk of such failure in the future. The report
shall also include a detailed description of all maintenance
activities that occurred during the month and a description of
significant activities planned for future months.
48. Respondents shall submit the monthly report required by this
Order, as amended, by the twenty-first (21st) of each month.
Unless otherwise specified by EPA, Respondents shall submit the
report by overnight delivery service.
49. These monitoring and reporting requirements supersede the
monitoring and reporting obligations contained in paragraph 29 of
Order 94-12. Other than the obligations contained in paragraph
24
29 of Order 94-12, these new reporting and monitoring
requirements do not superseded or change any other requirement
contained in Order 94-12 or other previous orders issued in
connection with the Site. (i) Within 48 hours of receiving a
request for such information from EPA, Respondents shall provide
to EPA, and to such other persons as EPA identifies, AMD flow
data from the Richmond and Lawson Portals and the Old Mine/No. 8
Seep.
50. Unless otherwise specified by EPA, Respondents shall provide
all data (in the monthly report and otherwise) in hard copy and
electronic format.
51. The effective date for the requirements contained in
paragraphs 44 to 51 is January 7, 1997.
Modification of Operation, Reporting, Monitoring or Performance
Standards.
52. The performance standards for the treatment plant are
technology based. If, as a result of experience gained from plant
operation, Respondents come to believe that the performance
standards or monitoring procedures should be modified, Respondents
may submit a request to EPA to approve a change in the standards
or procedures. The request shall contain sufficient information
to allow EPA to determine the appropriateness of the requested
25
changes. Either at the request of Respondents or on EPA's own
initiative, EPA may modify the performance standards or monitoring
procedures as it deems appropriate. Unless otherwise stated by
EPA, a change in such standard or procedures shall become
effective 30 days after EPA notifies Respondents of the change.
53. Respondents are responsible for ensuring that the Operations
and Maintenance Manual is current and reflects the experience
gained during plant operation. Either at the request of EPA or on
a regular basis as determined by Respondents, Respondents shall
review and propose appropriate revisions to the Operations and
Maintenance Manual for the treatment plant. Respondents shall
submit any proposed changes to EPA for review and approval by EPA.
EPA may at its discretion revise the Operations and Maintenance
Manual or the Performance Standards Verification Plan.
Other
54. Although EPA may, at its discretion, provide technical
assistance to Respondents on HDS plant operation, Respondents are
fully responsible for complying with the requirements of this
Order, as amended.
55. The attachments to this order amendment are hereby
incorporated by reference as if set forth herein in full.
26
IV. NOTICE OF INTENT TO COMPLY
56. Not later than fifteen calendar days after this Amendment to
Order No. 94-12 is signed by the Director, Superfund Division,
Respondents shall provide written notice to EPA's Remedial Project
Manager ("RPM") stating whether they will comply with the terms of
this Order, as amended. If Respondents do not unequivocally
commit to perform the work as provided by this Order, as amended,
they shall be deemed to have violated this Order and to have
failed or refused to comply with this Order. Respondent's
written notice shall describe, using facts that exist on or prior
to the effective date of this Order, any "sufficient cause"
defenses asserted by Respondents under sections 106(b) and
107 (c) (3) of CERCLA. The absence of a response by EPA to the
notice required by this paragraph shall not be deemed to be
acceptance of Respondent's assertions.
V. UNITED STATES NOT LIABLE
57. The United States, by issuance of this Order, as amended,
assumes no liability for any injuries or damages to persons or
property resulting from acts or omissions by Respondents, or
its (their) directors, officers, employees, agents,
27
representatives, successors, assigns, contractors, or consultants
in carrying out any action or activity pursuant to this Order, as
amended. Neither EPA nor the United States may be deemed to be a
party to any contract entered into by Respondents or its (their)
directors, officers, employees, agents, successors, assigns,
contractors, or consultants in carrying out any action or
activity pursuant to this Order, as amended.
VI. EFFECTIVE DATE AND COMPUTATION OF TIME
58. This Order Amendment shall be effective fifteen (15)
calendar days after the Order Amendment is signed by the
Director, Superfund Division. All times for performance of
ordered activities shall be calculated from this effective date.
VII. OPPORTUNITY TO CONFER
59. Respondents may, within seven (7) calendar days after the
date this Order is signed, request a conference with EPA's
Director, Superfund Division, to discuss this Order. If
requested, the conference shall occur no later than seven (7)
days after the request is made and shall be held at EPA Region 9,
75 Hawthorne Street, San Francisco, CA. The Director may
designate an alternate to meet with Respondents in the event of a
schedule conflict.
60. The purpose and scope of the conference shall be limited to
28
issues involving the implementation of the response actions
required by this Order and the extent to which Respondents
intends to comply with this Order. This conference is not an
evidentiary hearing, and does not constitute a proceeding to
challenge this Order. It does not give Respondents a right to
seek review of this Order, or to seek resolution of potential
liability, and no official stenographic record of the conference
will be made. At any conference held pursuant to Respondent's
request, Respondents may appear in person or by an attorney or
other representative.
61. Requests for a conference must be by (1) telefacsimile or
(2) telephone followed by written confirmation mailed that day to
Rick SugarekUnited States Environmental Protection Agency
Region 975 Hawthorne Street
San Francisco, California 94105(415) 744-2226 (ph)(415) 744-2180 (fax)
VIII. EFFECT ON PREVIOUS ORDERS
62. Nothing in this order shall be construed to excuse any non-
compliance with any previous order issued to Respondents,
including Order Nos. 89-18, 90-08 and 91-18, 93-01, 94-12.
63. Except as expressly provided herein, nothing in this order
29
shall be construed as amending any previous order issued to
Respondents.
So Ordered, this 27th day of November, 1996.
BY:Keith A. TakataDirector, Superfund DivisionU.S. Environmental Protection Agency, Region 9