UNIVERSITY DRIVE PEDESTRIAN SAFETY IMPROVEMENTS PHASE II Project Status October 9, 2014

Upload: city-of-college-station

Post on 25-May-2015

756 views

Category:

Government & Nonprofit


0 download

TRANSCRIPT

Page 1: University Drive Pedestrian Safety Improvements Phase II

UNIVERSITY DRIVE

PEDESTRIAN SAFETY

IMPROVEMENTSPHASE II

Project StatusOctober 9, 2014

Page 2: University Drive Pedestrian Safety Improvements Phase II

BACKGROUND• RFQ No. 12-020 for PER due November

2011• Contract No. 12-206 awarded to HDR May

2012• Scope of Work• Survey• Traffic Data Collection• Traffic Modeling• Public Meetings• Deliverables

• Conceptual Design w/ graphics• Preliminary engineering report• Corridor signal timings (Boyett to Texas)

Page 3: University Drive Pedestrian Safety Improvements Phase II

PROJECT MEETINGS• Public Meeting in November 2012• Public and stakeholder input

• Met with local merchants on site• November 2012• February 2013

• CoCS, TxDOT, and TAMU met in October 2013

Page 4: University Drive Pedestrian Safety Improvements Phase II

EXISTING TRAFFIC

Page 5: University Drive Pedestrian Safety Improvements Phase II

EXISTING TRAFFIC

Page 6: University Drive Pedestrian Safety Improvements Phase II

CONCEPTUAL DESIGN• College Main to Tauber• Extend median from Phase I

Page 7: University Drive Pedestrian Safety Improvements Phase II

CONCEPTUAL DESIGN• Tauber to Nagle• Reestablish the raised median• Left turns prohibited into TAMU garage

Page 8: University Drive Pedestrian Safety Improvements Phase II

CONCEPTUAL DESIGN• Nagle to South College • Staff continues working with TxDOT and TAMU• Possible Spence to Church signal relocation• Discussing potential impacts from TAMU

developments along University Drive

Page 9: University Drive Pedestrian Safety Improvements Phase II

NEXT STEPS• Meeting with CoCS, TxDOT and TAMU to

discuss the impacts of the Midway development and the engineering complex

• Hold a public meeting

• Conceptual design will be finalized based on information gathered at these meetings

Page 10: University Drive Pedestrian Safety Improvements Phase II

QUESTIONS ?