university of alberta energy efficiency lighting project€¦ · prepared by: blue source canada...
TRANSCRIPT
Prepared By: Blue Source Canada ULC (Authorized Project Contact)
Suite 1605, 840-7th Avenue SW
Calgary, AB T2P 3G2
T: (403) 262-3026
F: (403) 269-3024
www.bluesource.com
University of Alberta Energy Efficient Lighting Project
April 2018
DRAFT GHG REPORT v1.3
Jan 1, 2017-Dec 31, 2017
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 1
Contents List of Tables .................................................................................................................................. 2
List of Figures ................................................................................................................................. 2
List of Abbreviations ...................................................................................................................... 3
1 Project Description and Summary ................................................................................... 4
2 Introduction ......................................................................................................................... 6
2.1 Emission Claim .............................................................................................................. 7
2.2 Project Implementation and Variances ....................................................................... 7
3 Review of Project Consistency with ISO-14064 Principles ......................................... 9
3.1 Relevance ....................................................................................................................... 9
3.2 Completeness ................................................................................................................ 9
3.3 Consistency .................................................................................................................... 9
3.4 Accuracy ........................................................................................................................ 10
3.5 Transparency ................................................................................................................ 10
3.6 Conservativeness ........................................................................................................ 10
4 Project Scope ................................................................................................................... 10
4.1 Assertion of GHG Emission Reductions .................................................................. 10
4.2 Roles and Responsibilities ......................................................................................... 10
4.3 Project Eligibility ........................................................................................................... 11
4.4 Additionality .................................................................................................................. 12
4.5 Environmental Impact Assessments and Stakeholder Consultations ................. 13
4.6 Project History .............................................................................................................. 13
5 Selection and Justification of the Baseline Scenario .................................................. 13
6 Inventory of Sources, Sinks and Reservoirs................................................................ 16
6.1 Project Condition .......................................................................................................... 16
6.2 Baseline Condition ....................................................................................................... 21
6.3 Comparison of Project and Baseline SSRs ............................................................. 25
6.4 Quantification and Calculation of GHG Emissions and Reductions .................... 27
7 Data Quantification and Adjustments ........................................................................... 28
7.1 Calibration ..................................................................................................................... 28
7.2 Functional Equivalence ............................................................................................... 29
7.3 Interactive Effects ........................................................................................................ 29
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 2
7.4 Adjustment for ECO Canada Funding ...................................................................... 30
7.5 Sample Calculations .................................................................................................... 30
7.6 GHG Assertion Consistency ...................................................................................... 31
8 Data Management, Monitoring and Control ................................................................. 32
8.1 Quantification and Monitoring .................................................................................... 32
8.2 Data Management and QA/QC at Blue Source ...................................................... 34
7.2.1 Blue Source Standards ....................................................................................... 34
7.2.2 Back-up Procedures at Blue Source ....................................................................... 34
7.2.3 Document Retention Policy at Blue Source ........................................................... 34
9 Statement of Senior Review ........................................................................................... 35
10 References ........................................................................................................................ 36
Appendix A: List of University of Alberta Facilities that Underwent Energy Efficiency
Retrofits ......................................................................................................................................... 37
Appendix B: Back-up Procedures at Blue Source .................................................................. 40
Appendix C: Data Retention Policy at Blue Source................................................................ 42
Appendix D: Relumen Quantification Procedure .................................................................... 44
List of Tables Table 1. T12 and T8 Baseline Date Ranges for Re-Modeled Buildings during this
Reporting Period ........................................................................................................................... 8
Table 2. Barriers Assessment of Baseline Alternative Scenarios ....................................... 14
Table 3. Project Condition Sources, Sinks, and Reservoirs ................................................ 16
Table 4. Baseline Condition Sources, Sinks, and Reservoirs ............................................. 21
Table 5. Project and Baseline SSRs and Justification for Exclusion of SSRs .................. 25
Table 6. Data Quality Management Procedures for the Project .......................................... 33
List of Figures Figure 1: Project Element Lift Cycle Chart .............................................................................. 19
Figure 2: Process Flow Diagram for Project Condition ......................................................... 20
Figure 3: Baseline Element Life Cycle Chart .......................................................................... 23
Figure 4: Process Flow Diagram for Baseline Condition ...................................................... 24
Figure 5: GHG Reductions vs. Number of Retrofits .............................................................. 32
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 3
List of Abbreviations ACCO Alberta Climate Change Office
Blue Source Blue Source Canada ULC
CH4 Methane
CO2 Carbon Dioxide
CO2e Carbon Dioxide-equivalent
CSA Canadian Standards Association
GHG Greenhouse Gas
GWP Global Warming Potential
HDD Heating Degree Day
HVAC Heating, Ventilation and Air-Conditioning
HFC Hydrofluorocarbon(s)
IPMVP International Performance Measurement and Verification Protocol
IESNA Illuminating Engineering Society of North America
LED Light-emitting Diode
N2O Nitrous Oxide
PFC Perfluorocarbon(s)
SF6 Sulphur Hexafluoride
SGER Specified Gas Emitters Regulation
SSR Sources, Sinks and Reservoirs
U of A University of Alberta
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 4
1 Project Description and Summary
Project Title University of Alberta Energy Efficient Lighting Project
(‘the Project’).
Project
Purpose/Objective
The Proponent has undertaken this Project as part of a
conservation program designed to increase electricity
savings and reduce greenhouse gas emissions from the
campus’ various buildings. This Project is part of a
district-wide initiative administered by the U of A’s
Operations and Energy Management team.
Reporting period January 1, 2017 – December 31, 2017
GHG Assertion for
Reporting Period
11,686 tonnes CO2e
Protocol Alberta’s Quantification Protocol for Energy Efficiency in
Commercial and Institutional Buildings (Version 1.0,
October 2010)
Expected Lifetime of
Project
Energy efficient lighting retrofits began crediting May 1,
2004. Lighting retrofit projects are ongoing and have
continued into 2017; however, no additional retrofits
were completed for this reporting period.
There is no specified end date for this project. All
retrofits that have reached their 10-year expected
lifetime have been remodeled to demonstrate the T12
phase-out and change in baseline scenario to T8 linear
fluorescent bulbs.
Project Type This is an energy efficiency project. Energy Efficiency is a
valid category under the Alberta-based Offset Credit
System and under the Canadian Standards Association
(CSA) GHG CleanProjectsTM Registry
Project Location This is an aggregation project of 41 facilities located at
the U of A Campus which is situated at 11487 89 Ave,
Edmonton, Alberta, T6G 2M7. A list of the facilities that
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 5
underwent an energy efficiency retrofit can be found in
Appendix A.
Conditions Prior to
Project Prior to the implementation of the project, original
lighting was utilized at the various U of A facilities. The
specific lighting varied depending on the facility.
Description of how GHG
Reductions are Achieved
Emission reductions are achieved through energy
efficiency retrofits undertaken across U of A facilities.
This is an indirect emission reduction activity as
electricity is produced offsite and purchased by the U of
A from the Alberta electrical utility grid. In the absence of
the project activity GHG emissions resulting from
electricity would not be reduced.
Project Technologies Energy efficiency retrofits consisted of lighting retrofits.
Retrofits were dependent on the pre-existing
infrastructure that was in place at the various facilities
before any energy efficiency retrofits were undertaken.
For this reason, the project retrofits are described below
in section 2 in a generic fashion.
Project Risks There are no material risks that have been identified for
this Project that would impact the quantification of GHG
emissions. The lighting retrofits completed by the
Proponent result in a permanent GHG emission reduction
since the displacement of the fossil fuels cannot be
reversed. This project type does not involve biological or
geological sequestration-related risks.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 6
2 Introduction This report provides details on the lighting efficiency retrofit projects undertaken by the
University of Alberta (U of A) (‘the Proponent’). The university has been located in Edmonton,
Alberta, for over 100 years and is now one of the top five universities in Canada and is included in
the top 100 universities in the world. The Proponent maintains a large inventory of buildings to
provide over 39,000 students with a world class learning environment.
U of A began the lighting retrofit projects in May of 2004, with new buildings being added to the
retrofit project on an ongoing basis. The lighting retrofit project, administered by the U of A’s
Operations and Energy Management team, was undertaken as part of a conservation program
designed to increase electricity savings and reduce greenhouse gas (GHG) emissions at the
university. The retrofits were completed in such a way to achieve maximum energy savings and
involved replacing older lighting technologies such as T12 fluorescent and incandescent lighting,
with newer, more efficient technologies including T5, T8 and/or LED lights, as well as redesigning
the lighting layout/fixtures and including advanced lighting controls such as occupancy and
daylight sensors.
Existing indoor lighting was retrofitted with approved energy efficient lighting sources to minimize
energy costs and to enhance the quality of lighting in each facility. Rather than obtaining only the
minimum energy savings achievable by implementing simple and straightforward methods, the
project aim was to harvest optimal savings by using a combination of methods and technologies
to maximize electricity savings:
• Older lighting technologies, such as T12 fluorescent and incandescent, are upgraded with
more modern, efficient technologies, such as T5, T8 and LED lights;
• Low watt lamps and under drive ballasts are also used to further reduce the energy used
by the luminaires;
• The efficiency of the luminaire itself is improved by using specular reflectors, prismatic
lenses and re-positioning the lamp holders, allowing the same (functionally equivalent)
level of illumination to be achieved using fewer luminaires;
• The operating hours of the luminaire are reduced by using lighting controls such as motion
sensors, photo sensors, multi-level switching or time clocks;
• The way the luminaire is installed within the space may be modified, so that fewer
luminaires are needed in a layout to achieve the same (functionally equivalent) level of
illumination in task areas.
These upgrades yield the most energy savings while improving the quality of the lighting and
decreasing the energy intensity of the space. Therefore, the project did not simply change the
bulb type, rather the U of A employed a combination of lighting technologies, improvements, and
design in the buildings.
The last quantification of emission reductions from the U of A Lighting Efficiency project took
place in 2017, and quantified emission reductions from 41 retrofits for the period of January 1,
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 7
2015 to December 31, 2016. The Quantification methodology followed was Option D - Calibrated
Simulation model under Alberta’s Quantification Protocol for Energy Efficiency in Commercial and
Institutional Buildings (Version 1.0, October 2010). Blue Source worked with ReLumen Engineering
to produce the calibrated simulation model and details on the methodology used for this can be
found in the following report: CO2 Offset Quantification Procedure, Lighting Upgrade Projects
2002-2014, University of Alberta, Revision 5. As no other building retrofits took place during the
2016 vintage year, Revision 5 is still applicable to this reporting period.
2.1 Emission Claim
The emission reductions quantified in this report are for the period January 1, 2017 to December
31, 2017 and include the same 41 building retrofits from previous years.
Emission reductions quantified in this reporting period are: 11,686 tonnes CO2e1.
2.2 Project Implementation and Variances
The Government of Alberta is in the process of releasing a revised Energy Efficiency protocol,
whereby the existing two energy efficiency protocols will be combined into one over-arching
protocol. Starting January 1, 2019, projects must be updated to the new protocol. Therefore,
the 2019 vintage year of this project will be adjusted to meet the new protocol requirements.
i) Adjusted T8 Baseline Approach
Commencing with the 2015 project delivery (covering the period July 1, 2013 to December 31,
2014) the baseline approach for this project was altered so that any building that had retrofit
projects completed more than ten years ago is remodeled to reflect a new T8 baseline, instead of
the previous T12 baseline. This has been done to represent the gradual phase out of T12s from
the US and Canada lighting sector, while maintaining the savings from other upgrades made to
those buildings (advanced lighting controls, lighting space design, de-lamping etc.). The current
quantification period includes five new buildings that have been remodeled and are shown below
in Table 12.
To increase the accuracy of calculated emissions, the five buildings that are over this ten-year
threshold have been quantified using a combined T12/T8 baseline approach. The original T12
baseline is used from the start of the quantification period (January 1, 2017) up to the original
project completion date, plus an additional ten years. After this date, the new T8 baseline has
been used until the end of the quantification period (December 31, 2017). Therefore, the date
the T12 baseline range ends, is the date the project was completed less ten years ago. Even
1 Note that a 2.5% discount to the emission claim was applied to subprojects implemented before July 1, 2011, as
they received funding from Eco-Canada. This application is discussed below in proceeding sections.
2 Note that there are additional buildings, from previous reporting periods, which were previously remodelled to use
a combined T12/T8 baseline and that now use a wholly T8 baseline. See Appendix A for more details.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 8
though the Agricultural Greenhouses and the Agricultural Growth Chambers have surpassed their
10-year lifetime, they were not included in the adjusted baseline group as they were retrofitted
to high pressure sodium (HPS) and T12VHO bulbs rather than T8s. Table 1 below outlines the
buildings and the date ranges applicable to the separate baselines.
Table 1. T12 and T8 Baseline Date Ranges for Re-Modeled Buildings during this Reporting Period
Building T12 Baseline date range T8 Baseline date range
Agricultural Forestry Jan 1, 2017 - January 15, 2017 Jan 16, 2017 - Dec 31, 2017
Medical Sciences Jan 1, 2017 - April 4, 2017 April 5, 2017 - Dec 31, 2017
Arts Building & Convocation
Hall
Jan 1, 2017 – May 15, 2017 May 16, 2017 - Dec 31, 2017
Tory Jan 1, 2017 - June 28, 2017 June 29, 2017 - Dec 31, 2017
Physical Education East/West
(Van Vliet)
Jan 1, 2017 – Aug 23, 2017 Aug 24, 2017 - Dec 31, 2017
Since the last quantification, no new buildings retrofits or upgrades have been performed and
added to this quantification. See Appendix A for a full list of buildings included for this
quantification period.
ii) Removal of Reduction Targets applied to Electricity Grid Emission Factors
In previous reporting periods, the electricity grid emission factor for the province of Alberta was
increased by 15% and 20% to reflect the anticipated impact of the provincial government’s
Climate Leadership Plan (2015), and those values were applied to the 2015 and 2016
quantification years respectively. This adjustment has been removed for the current reporting
period, as it deviates from the application of the grid intensity factor in all other offset projects.
This change is accurate, conservative and consistent with standard quantification methodologies
in Alberta.
The adjustment methodology is also noted in the “CO2 Offset Quantification Procedure Lighting
Upgrade Projects 2004-2014” report provided by Relumen Engineering to quantify offsets,
however this methodology has been excluded from the project.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 9
3 Review of Project Consistency with ISO-14064 Principles
3.1 Relevance
The methodology referenced in quantifying GHG emission reductions from the U of A Energy
Efficient Lighting Project was developed and approved under the Alberta Offset System, regulated
under the Specified Gas Emitters Regulation (SGER). The Alberta Quantification Protocol for
Energy Efficiency in Commercial and Institutional Buildings (Version 1.0, October 2010) ('the
Protocol') was developed following the ISO 14064-2 standard as required under the Alberta Offset
System protocol development process. Additionally, the protocol development process included
a multi-step stakeholder review process consisting of a technical expert review, a broader
stakeholder review process and a public posting period, all of which were managed by the
Government of Alberta. At the time this quantification project commenced, the Protocol was the
only government-approved quantification protocol applicable to energy efficiency projects for
commercial and institutional buildings in Canada and was therefore considered to be the best
available quantification protocol to apply for this project. The Protocol is currently under review,
and the Project will be re-evaluated for necessary revisions following the release of the new
Protocol.
Sources, Sinks and Reservoirs (SSRs) considered to be relevant and included for quantification
under the protocol are defined in Section 4 of this document, including justification for the
exclusion of SSRs identified in the life cycle elements of the project and baseline condition under
ISO 14064-2. SSRs for the project condition are summarized in Table 3 and Figure 1 and Figure 2.
SSRs under the baseline condition are summarized in Table 4and Figure 3 and Figure 4.
3.2 Completeness
The specific scope of this project has been limited to GHG emission reductions achieved through
the reduction in use of electricity through the implementation of energy efficient lighting retrofits.
This involves indirect GHG emissions associated with the consumption of grid electricity
generated in Alberta.
Data collection, monitoring, and quantification approaches are summarized in Table 9 of this
report.
3.3 Consistency
The Protocol used in the quantification of GHG reductions is consistent in its application of
functional equivalence between the baseline and project condition. The lighting in each of the
retrofitted buildings at the U of A operates in a functionally equivalent condition in the project
and baseline condition.
The use of a calibrated simulation to quantify energy savings is an approach that is recognized by
the International Performance Measurement and Verification Protocol (IPMVP) guidance of
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 10
energy savings quantification3. This approach is consistent with the definition of functional
equivalence under ISO-14064-2.
3.4 Accuracy
Bias and uncertainties in quantification were limited using a Simulated Lighting Systems Model. A
calibration adjustment derived from data logging activities is applied to the kilowatt-hour energy
savings for each simulated project model. Data collection, monitoring, and quantification
approaches are summarized in Table 8 of this report.
3.5 Transparency
Data collection, monitoring, and quantification approaches are summarized in Section 6 of this
report. The annual emission reduction claims are also summarized in this document to support
the transparency of the GHG emission reduction assertion.
3.6 Conservativeness
The calculations are considered conservative as the calibration factor adjustment is the median
between the calibration adjustments implied by the data logging measurements.
4 Project Scope
4.1 Assertion of GHG Emission Reductions
The total GHG emission reductions attributable to the Project for the period January 1, 2017 –
December 31, 2017 are:
11,686 metric tonnes of CO2 equivalent
While previous quantification periods included outside funding sources, there were no retrofits
completed during the current reporting period that utilized funding from ECO Canada or any other
outside source (for more information on the ECO Canada Adjustment, please see Section 7.4).
4.2 Roles and Responsibilities
Project
Proponent
Contact
Information
University of Alberta
Michael Versteege
Manager
Energy Management & Sustainable Operations
Phone: (780) 492-4024
Email: [email protected]
Room 110
Heating Plant
University of Alberta
Edmonton, AB
T6G-2N7
Canada
Web: www.ualberta.ca
3 Efficiency Valuation Organization (2010) International Performance Measurement and Verification Protocol. Concepts and Options of Determining Energy and Water Savings. Volume 1.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 11
Authorized Project Contact
Blue Source Canada ULC Kelsey Locke, AIT Carbon Solutions Analyst Phone: 403-262-3026 x 228 Fax: 403-269-3024 Email: [email protected]
Suite 1605 840 - 7th Avenue SW Calgary, AB T2P 3G2 Canada Web: www.bluesource.com
Verifier
GHD Jennifer Packer, P.Eng Lead Verifier Phone: 1-519-340-4288 Email: [email protected]
455 Phillip St Waterloo, ON N2L 3X2 Canada Web: www.ghd.com
4.3 Project Eligibility
As a measure to mitigate GHG emissions, the Proponent has undertaken a voluntary energy
efficiency retrofit program. This Project represents the aggregation of individual lighting retrofits
implemented across campus. Energy Efficiency is a valid category under the Canadian Standards
Association (CSA) GHG CleanProjectsTM Registry.
The Proponent's energy efficiency measures for GHG emission reductions are quantified in
according to the Alberta Quantification Protocol for Energy Efficiency in Commercial and
Institutional Buildings (Version 1.0, October 2010) in this GHG Report. This government approved
protocol is intended to generate carbon offsets from the direct and indirect reduction of GHG
emissions resulting from the implementation of facility retrofits that result in overall energy
efficiencies. While the Protocol is currently being reviewed by the Alberta Climate Change Office
(ACCO) as part of the Carbon Levy Alignment process with the Alberta offset system, this is a
voluntary ongoing project under the Protocol and will be adjusted for future deliveries as
required.
The following characteristics of the project ensure it meets the required eligibility criteria of the
CleanProjectsTM Registry:
• The quantification protocol referenced was developed in accordance with ISO 14064-2,
and quantification procedures follow this standard;
• The protocol is being used in conjunction with the International Performance
Measurement and Verification Protocol (IPMVP)4. This guidance document represents
the industry standard for good practice guidance when determining energy savings.
• The GHG assertion will be verified by an independent third-party – GHD – prior to project
registration;
4 Efficiency Valuation Organization (2009), International Performance measurement and Verification Protocol: Concepts and Options for Determining Energy and Water Savings, Volume 1.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 12
• The facility operations are not subject to any regulations requiring the lighting efficiency
upgrades in Alberta. The project is not subject to any climate change or emissions
management legislation in the province of Alberta or federally in Canada;
• Potential GHG emission reductions generated by this project are not listed on any other
GHG reduction registry in Canada or internationally and this project has not participated
under any other climate change incentive programs and has not received any public funds
related to such initiatives.
Note that not all project eligibility criteria in the Alberta Offset System’s Quantification Protocol
for Energy Efficiency Projects are applicable to this project since these offsets are not being
created for compliance use in Alberta. Specifically, the requirement of having a Certified
Measurement and Verification Professional or a Certified Energy Manager with at least three
years of experience in implementing and quantifying energy efficiency projection sign off on the
offset project plan and project report are not applicable since these offsets are being created for
voluntary purposes. As such, the Alberta Offset System protocol is used as a source of best
practice guidance for quantifying GHG emission reductions, but the overarching project eligibility
criteria are defined by the registry on which the offsets are to be listed or otherwise defined by
the ISO 14064 standards.
4.4 Additionality
Assessing project additionality is a necessary criterion in the Alberta offset system to determine
whether a project is still eligible and that the project activity is not considered ‘business-as-usual’
in the sector or industry. Even though this is a voluntary project, a review of additionality
regarding lighting technology is presented below.
In conjunction with lighting space re-design and the installation of occupancy/motion sensors,
lighting systems were retrofit from compact fluorescent or linear fluorescent T12 bulbs to more
efficient linear fluorescents (such as T5 or T8), high pressure sodium (HPS) bulbs, or light emitting
diode (LED) bulbs.
Bluesource recognizes that T8 technology has become more common since this project
commenced, and this resulted in a change to the project methodology during the 2015 delivery,
which places a 10 year ‘time limit’ on the T12 baseline for each building. This reflects the lifetime
of the fixture, after which time they would need to be replaced and would then move to a T8
baseline (see also Section 1.1 on Project Variances). Moreover, the U of A retrofits not only
changed the bulb types, rather they re-engineered the lighting space for optimal coverage and
duration. Therefore, this additional design allows for greater energy savings compared to the
original T12 configuration, or T8 lighting alone.
Bluesource is aware that this baseline may need to be adjusted for any new lighting retrofits
completed in future years. Any such changes will be noted in future reports.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 13
4.5 Environmental Impact Assessments and Stakeholder Consultations
Neither an environmental impact assessment nor stakeholder consultations were required for
this project.
4.6 Project History
The U of A lighting efficiency retrofits began May 15, 2004 and are ongoing. There were 41
buildings included in the quantification of offset credits for this reporting period, as no additional
projects were added since the last quantification. Appendix A provides details of all the retrofits
that occurred at the various sites across the U of A beginning in 2004.
5 Selection and Justification of the Baseline Scenario Three possible baselines were identified in the development of this GHG offset project. These
include:
• Status quo (i.e. keep the original lighting systems in place with gradual replacement as
required);
• Redesign and retrofit only some of the buildings;
• The project scenario (i.e. complete redesign of building lighting systems to maximize
energy savings, lighting quality, and occupancy comfort).
Since the inception of the lighting efficiency program in 2004, over 85% of large campus buildings
have been retrofitted under its direction. In fact, the program has been so successful, that the
percentage of T12s the University must order has dropped significantly. This has only been made
possible due to the high percentage of university buildings in the energy efficiency program. In
absence of the program, maintenance would consist of simply replacing existing lighting with T12s
until forced to change to T8s due to the recent phase out of T12s. Due to University budget
constraints, lighting retrofits are considered a low priority and must compete with other needs
that are considered to be more pressing such as safety and advancing student amenities.
Therefore, if it were not for the lighting efficiency program none of the completed retrofits would
have taken place. As mentioned in Section 1.1, buildings with retrofits that are over ten years in
age relative to the current quantification period, shall have a new T8 baseline remodeled. In doing
so, energy output at each building location is modeled downward to reflect the industry phase
out of T12s.
The approach used to select and justify the relevant baseline scenario for this offset project
consisted of two components: identification of barriers facing each alternative and an assessment
of the expected costs to implement and operate each alternative.
The three options listed above were evaluated to assess the likelihood that each could represent
the baseline scenario. A barriers test is a common technique used to help justify the most realistic
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 14
baseline scenario, where the most likely scenario is the option that does not have any significant
barriers to implementation. The relevant barriers affecting each of these scenarios are
summarized in Table 2 below.
Table 2. Barriers Assessment of Baseline Alternative Scenarios
Relevant Barriers Alternative 1:
Keep existing lighting in place with gradual
replacement as required
Alternative 2:
Lighting redesign and retrofits of only a few
buildings
Alternative 3:
The project scenario
Financial/Economic Barriers
None. There are no significant additional upfront capital costs.
Electrical utility costs are unchanged from previous years’
operating budgets.
Partial. Upfront capital costs associated with
retrofits. Additional costs to hire third party energy
efficiency experts to evaluate energy
efficiency opportunities and to complete
retrofits. Costs for new fixtures and control
systems are also additional to simple bulb
for bulb replacement.
Yes. Significant upfront capital costs associated
with retrofits. Additional costs to hire third party
energy efficiency experts to evaluate energy
efficiency opportunities and to complete
retrofits. Costs for new fixtures and control
systems are also additional to simple bulb
for bulb replacement.
Technology Implementation,
Operation, maintenance and Disposal Barriers
None. Locally available fuels, materials, know-how, technology, and
other resources are not limited.
Yes. There are some barriers to implementing
the project scenario including increased use of university time and resources, hiring an energy expert and engineering firm to
assess and design each building.
Yes. There are
significant barriers to
implementing the
project scenario
including greatly
increased use of
university time and
resources, hiring an
energy expert and
engineering firm to
assess and design each
building individually.
Barriers due to prevailing practice
None. None. None. The retrofits are not the first of their kind.
Skills and Training Barriers
None. Existing personnel possess skills and
training required for operation, maintenance,
and monitoring.
None. Existing personnel possess skills and
training required for operation, maintenance,
and monitoring.
None. Existing personnel possess skills and
training required for operation, maintenance,
and monitoring.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 15
Using the Barriers Assessment, the most likely baseline scenario would be the continued use of
the existing lighting systems with gradual replacement as required, as this scenario has the fewest
barriers to implementation. The project condition (i.e. where lighting systems are retrofit and
redesigned) has the most significant barriers of financial/ economic expenditures as well as
technology implementations barriers. Therefore, the comprehensive nature of the Project
exceeds a business-as-usual (BAU) scenario.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 16
6 Inventory of Sources, Sinks and Reservoirs
6.1 Project Condition
SSRs were identified for the project by reviewing the relevant process flow diagrams, consulting with relevant industry stakeholders (through the
Alberta Offset System Quantification Protocol Development Process) and reviewing available good practice guidance. This iterative process
confirmed that the SSRs in the process flow diagrams included below cover the full scope of eligible project activities under the protocol.
The project condition is defined including the relevant SSRs and processes as shown in Table3 and Figure 1 and Figure 2 below.
Table 3. Project Condition Sources, Sinks, and Reservoirs
1. SSR 2. Description 3. Controlled,
Related or Affected
Upstream SS’s before Project Operation
P3 Raw Material Production and
Transportation
Raw materials, used in the manufacture of equipment for in the implementation of Energy
Conservation Measure and conventional building operation. Usually produced offsite and
transported to the manufacturing facility. Emissions will arise from the use of fossil fuels
and electricity during these processes. These raw materials may include but are not limited
to cement, plastic, aluminum, steel and rubber.
Related
P4 Manufacture of Equipment
Greenhouse gas emissions will arise from the manufacturing process of the equipment to
implement the Energy Conservation Measures and conventional building operation in the
project. Such emissions will likely be associated with the fossil fuels and electricity
consumed during the manufacturing process.
Related
P5 Transportation of Equipment
Equipment used in the implementation of the Energy Conservation Measures and
conventional building operation must be transported to the project site. Greenhouse gas
emissions will primarily be attributed to the combustion of fossil fuels during the
Related
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 17
transportation process.
P6 Commissioning of Site
The development of the site (technically on-site before project) and installation of
equipment will result in greenhouse gas emissions, primarily from the use of fossil fuels and
electricity during this process. Related
Upstream SS’s During Project Operation
P1 Fuel Extraction and Processing
Each of the fuels used throughout the on-site component of the project will need to sourced
and processed. This will allow for the calculation of the greenhouse gas emissions from the
various processes involved in the production, refinement and storage of the fuels. The total
volumes of fuel for each of the on-site SS’s are considered under this SS. Volumes and types
of fuels are the important characteristics to be tracked.
Related
P2 Electricity Usage
Electricity will be used in the project condition. This power may be sourced either from
internal generation, connected facilities or the local electricity grid. Metering of electricity
may be netted in terms of the power going to and from the grid. Quantity and source of
power are the important characteristics to be tracked as they directly relate to the quantity
of greenhouse gas emissions.
Related
Onsite SS’s during Project Operation
P8 Building Energy Consumption
(with energy conservation measures)
Energy (including fossil fuel and electricity) is required on-site to operate the building.
Equipment utilizing this energy includes but is not limited to boilers, lighting systems, HVAC
Systems and ventilation systems. Controlled
P9 Maintenance/Operation
The facility and systems within the facility will require maintenance (both routine and non-
routine). Greenhouse gas emissions will arise from the use of fuels and electricity in
maintenance and/or operational procedures. Controlled
Downstream SS’s During Project Operation
P10 Disposal of Energy Conservation The disposal of some materials/equipment which compose all or a component of the Related
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 18
Measure Equipment Energy Conservation Measures may result in greenhouse gas emissions. E.g. the disposal of
Compact Fluorescent Light (CFL) bulbs to appropriately remove mercury, disposal of
transformer containing SF6
Downstream SS’s After Project Operation
P7 Decommissioning of Energy
Conservation Measure Equipment
Once the Energy Conservation Measure equipment comes to the end of its life Greenhouse
gas emissions may arise from the incremental use of fossil fuels and electricity during
equipment disassembly, disposal, and other required activities during the process,
compared to the baseline.
Related
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 19
Figure 1: Project Element Lift Cycle Chart
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 20
Figure 2: Process Flow Diagram for Project Condition
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 21
6.2 Baseline Condition
The baseline condition selected and justified in Section 3, includes building energy consumption. The baseline condition is defined including the
relevant SSRs and processes as shown in Table 4 and Figure 3 and Figure 4, below.
Table 4. Baseline Condition Sources, Sinks, and Reservoirs
1. SSR 2. Description 3. Controlled,
Related or Affected
Upstream SS’s before Project Operation
B3 Raw Material Production
and Transportation
Raw materials, used in the manufacture of equipment for in the implementation of Energy
Conservation Measure and conventional building operation. Usually produced offsite and transported
to the manufacturing facility. Emissions will arise from the use of fossil fuels and electricity during these
processes. These raw materials may include but are not limited to cement, plastic, aluminum, steel
and/or rubber.
Related
B4 Manufacture of
Equipment
Greenhouse gas emissions will arise from the manufacturing process of the equipment to implement
the Energy Conservation Measures and conventional building operation in the project. Such emissions
will likely be associated with the fossil fuels and electricity consumed during the manufacturing process.
Related
B5 Transportation of
Equipment
Equipment used in the implementation of the Energy Conservation Measures and conventional
building operation must be transported to the project site. Greenhouse gas emissions will primarily be
attributed to the combustion of fossil fuels during the transportation process
Related
B6 Commissioning of Site The development of the site (technically on-site before project) and installation of equipment will result
in greenhouse gas emissions, primarily from the use of fossil fuels and electricity during this process. Related
Upstream SS’s During Project Operation
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 22
B1 Fuel Extraction and
Processing
Each of the fuels used throughout the on-site component of the project will need to sourced and
processed. This will allow for the calculation of the greenhouse gas emissions from the various
processes involved in the production, refinement and storage of the fuels. The total volumes of fuel for
each of the on-site SS’s are considered under this SS. Volumes and types of fuels are the important
characteristics to be tracked.
Related
B2 Electricity Usage
Electricity will be used in the project condition. This power may be sourced either from internal
generation, connected facilities or the local electricity grid. Metering of electricity may be netted in
terms of the power going to and from the grid. Quantity and source of power are the important
characteristics to be tracked as they directly relate to the quantity of greenhouse gas emissions.
Related
Onsite SS’s during Project Operation
B8 Building Energy
Consumption (without
energy conservation
measures)
Energy (including fossil fuel and electricity) is required on-site to operate the building. Equipment
utilizing this energy includes boilers, lighting systems, HVAC Systems, ventilation systems, etc... Controlled
B9 Maintenance/Operation
The facility and systems within the facility will require will require maintenance (both routine and non-
routine). greenhouse gas emissions will arise from the use of fuels and electricity in maintenance
and/or operational procedures.
Controlled
Downstream SS’s during Project Operation
None
Downstream SS’s After Project Operation
B7 Decommissioning of Site
Once the site is no longer in operation, the site will most likely need to be decommissioned.
Greenhouse gas emissions will arise from the use of fossil fuels and electricity during equipment
disassembly, disposal, and other required activities during the process.
Related
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 23
Figure 3: Baseline Element Life Cycle Chart
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 24
Figure 4: Process Flow Diagram for Baseline Condition
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 25
6.3 Comparison of Project and Baseline SSRs
Table 5 provides the justification for excluding certain source/sinks included in the Protocol from the project.
Table 5. Project and Baseline SSRs and Justification for Exclusion of SSRs
1. Identified SS’s
2.
Baseline
(C, R, A)
2. Project
(C, R, A)
4. Include or
Exclude from
Quantification
5. Justification for Exclusion
Upstream SS’s
P1/B1 Fuel Extraction
and Processing Related Related Excluded
Excluded since emissions from fuel production/distribution are
expected to be greater under the baseline condition
P2/B2 Electricity Usage Related Related Excluded
Excluded since emissions from electricity generation/distribution are
greater under the baseline condition where more inefficient lighting
was used and hence required more electricity consumption to run.
P3/B3 Raw Material
Production and
Transportation
Related Related Excluded
Excluded as per good practice guidance from Environment Canada: these
greenhouse gas emissions are expected to be insignificant over the
course of the project.
P4/B4 Manufacture of
Equipment Related Related Excluded
Excluded as per good practice guidance from Environment Canada; These
greenhouse gas emissions are expected to be insignificant over the
course of the project.
P5/B5 Transportation
of Equipment Related Related Excluded
Emissions from transportation of equipment are not expected to be
material given the long project life and the minimal transportation of
equipment typically required.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 26
1. Identified SS’s
2.
Baseline
(C, R, A)
2. Project
(C, R, A)
4. Include or
Exclude from
Quantification
5. Justification for Exclusion
P6/B6 Commissioning
typically required for
Energy Conservation
Measure
implementation on site
Related Related Excluded
Emissions from the commissioning of the site are not material given the
long project life and minimal construction required for installing lighting.
Onsite SS’s
P8/B8 Building Energy
Consumption
(with/without energy
conservation measure)
Controlled Controlled Included
The difference in emissions from the baseline to the project period are
mainly due to implemented Energy Conservation Measures. However,
as this energy efficiency project involves replacing lighting only, only
electricity usage is considered rather than the whole energy use of the
building. Natural gas use is not affected by the change in lighting.
P9/B9 Maintenance
and Operations Controlled Controlled Excluded
Excluded on the basis that maintenance between the baseline and
project conditions will not change and thus can be excluded as they are
functionally equivalent.
Downstream SS’s
P7/B7
Decommissioning of
Site
Related Related Excluded
Excluded as per good practice guidance from Environment Canada; These
greenhouse gas emissions are expected to be insignificant over the
course of the project.
P10 Disposal of
Equipment for Energy
Conservation Measure
N/A Related Excluded Excluded as emissions from equipment disposal are expected to be
minimal.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 27
6.4 Quantification and Calculation of GHG Emissions and Reductions GHG emission reductions from this project are quantified with guidance from IPMVP’s Option D
– Calibrated Simulation. This quantification option is used for energy management programs in a
facility where no meter existed in the baseline period or when monitoring of energy savings
associated with individual energy savings measures are too costly or difficult to monitor directly.
The following three equations serve as the basis for the quantification of emission reductions:
Where the following SSRs have been quantified as applicable to the project:
EmissionsBaseline = sum of the emissions under the baseline condition
EmissionsEnergyUsage(withoutECMs) = emissions under SS B8 Building Energy Usage (without
energy conservation measures (ECM))
Calibration error = Calibration achieved by verifying that the simulation model
reasonable predicts the energy patterns of the facility by comparing model results to a
set of calibrations data.
EmissionsProject = sum of the emissions under the project condition
EmissionsEnergyUsage(withECMs) = emissions under SS P8 Building Energy Usage (with energy
conservation measures)
Calibration error = Calibration achieved by verifying that the simulation model
reasonable predicts the energy patterns of the facility by comparing model results to a
set of calibrations data.
The following SSRs were not applicable to this project and as such were not quantified:
Emissions Fuel Extraction / Processing = emissions under SS P1/B1 Fuel Extraction and Processing
EmissionsElectricityUsage = emissions under SS P2/B2 Electricity Usage (upstream)
EmissionsMaterialProduction= emissions under SS P3/B3 Raw Material Production and
Transportation
GHG Emission Reduction = Emissions Baseline – Emissions Project
Emissions Baseline = Emissions Electricity Usage(without ECMs) - Calibration error in
the corresponding calibration reading
Emissions Project = Emissions Electricity Usage (with ECMs) - Calibration error in the
corresponding calibration reading
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 28
EmissionsEquipment = emissions under SS P4/B4 Manufacture of Equipment
EmissionsTransportation = emissions under SS P5/B5 Transportation of Equipment
EmissionsCommissioning = emissions under SS P6/B6 Commissioning typically required for
Energy Conservation Measure implementation on site.
EmissionsMaintenance= emissions under SS P9/B9 Maintenance and Operations
EmissionsDecommissioning= emissions under SS P7/B7 Decommissioning of Site
EmissionsDisposal= emissions under SS P10 Disposal of Equipment for Energy Conservation
Measure
For justifications of exclusion from quantification see Table 5.
The annual CO2 reductions are determined by multiplying the difference between pre-project and
post-project annual energy consumption (kWh) and the electrical grid intensity factors for 2017.
7 Data Quantification and Adjustments
7.1 Calibration
Data logging activities were performed to provide measured support for the accuracy of the
Simulated Lighting Systems Model, in both 2010 and 2015. The measured data set illustrates
trends in peak load demand (kW) and consumption (kWh). In addition, data logging provides a
graphical representation of building occupancy patterns and provides validation for the operating
hours included in the simulated lighting model. The 1-week metering period captures building
occupancy patterns during a typical week during the University’s winter semester classes.
Data logging equipment used onsite included current transducers, voltage transducers,
SmartReader 3+ loggers and TrendReader Version TR2 2.31 software, all manufactured by ACR
Systems. Lighting throughout campus buildings is electrically fed by designated 347Vac lighting
panels. Lighting panels generally feed an entire floor or wing of a building. Data logging equipment
was connected to select 347Vac lighting panels to measure the total panel load (Phases A, B, & C
metered individually) as well as the building voltage over the course of a one-week period. Note
that for a sample case where multiple panels were metered simultaneously in the same building,
only voltage from one panel was metered and extrapolated to other panels during analysis.
Voltage drop is considered negligible.
Option D Calibrated Simulation Model requires the lighting system energy to be isolated from that
of the rest of the facility by appropriate meters. This was achieved through selecting designated
lighting panels serving each floor. There were many instances where lighting panels fed other
loads, such as transformers and subpanels. These cases were excluded from the sample
population selection. Data logging of a random sample of campus buildings (by floor) was
performed by ReLumen Engineering throughout the month of March 2010 as well as throughout
February 2015. Details regarding data logging, the sample population, and analysis for the
calibration adjustment calculations are attached in ReLumen Engineering’s CO2 Offset
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 29
Quantification Procedure Lighting Upgrade Projects 2004-2014: University of Alberta (March,
2015).
The evaluation of the calibration adjustment using a total sum of the data logging samples and
the total sum of extracted lighting model values (as described in the procedure above) show a
44% spread in adjustment i.e. 72% (-28%) and 116% (+16%) between the worst and best-case
scenarios. The mean calibration adjustment implied using the total sum of data samples is found
to be 94.3%. Note, when using two data points, the mean is equivalent to the median value.
The same procedure and analysis was used to compare calibration adjustments derived from each
individual data logging sample (i.e. per lighting panel) and the extracted values from their
respective lighting models. With the revised data logging sample population, the median of and
mean percent differences were found 97.5% and 95.2%, respectively, from the percent
differences (between best and worst-case scenarios) of the original CO2 claim.
Compared to prior quantifications, the mean calibration factor of 94.3% was calculated and has
been truncated to 94% to remain conservative in the overall approximation of energy savings
predicted by the model. This represents a calibration adjustment of -6% and compared to the
previous calibration of -5% in the 2015 reporting period, increases the conservativeness of the
project calculations. This calibration adjustment of -6% is applied to the kilowatt-hour energy
savings for each simulated project model.
7.2 Functional Equivalence
The baseline scenario and project deliver the same type and level of product or service (i.e. they
are functionally equivalent). In both the baseline and project scenarios, the Proponent’s internal
lighting guidelines were followed. In some cases, lower light levels were adjusted upwards to
reflect the design guidelines. These guidelines were established by an engineering firm that
specializes in lighting and electrical consulting services. The guidelines are based on published
standards by the Illuminating Engineering Society of North America (IESNA).
7.3 Interactive Effects
Energy flows affected by the energy efficiency retrofit must be taken into consideration. A lighting
load reduction can affect HVAC system use, but such effects are beyond the project measurement
boundary. The measurement boundary for this project encompasses just the electricity use of the
lighting and not their heating and cooling energy impacts.
To justify this exclusion, the interactive effect (i.e. the lighting retrofit’s effect on HVAC energy
requirements) must be assessed. In this case, heating and cooling demand (i.e. kilograms of steam
and cubic meters of chilled water) were plotted against heating and cooling degree data where
18 degrees Celsius is the base temperature. Heating and cooling data was chosen for several
buildings which had their own individual heating and cooling systems and where retrofits were
completed early in the project as to allow for data retrieval in a timely manner as a new platform
for data retrieval has been implemented.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 30
Only the plot of heating demand data versus temperature data showed a strong correlation. The
R-Squared value for heating degree days versus heating demand were 0.959 and 0.908 in the
project and baseline scenarios respectively. The R-Squared value for cooling degree days versus
cooling demand was only 0.444 and 0.649 in the project and baseline scenarios respectively and
were therefore not considered in the analysis.
The difference between the slope of the heating degree days versus heating demand in the
project and baseline condition varied from -30.58% to +6.81%. The average difference between
the heating degree days versus heating demand in the project and baseline condition was -4.92%.
This shows that there is no net increase in heating demand as a result of lighting retrofits. In fact,
the analysis shows an overall reduction of heating of -4.92%.
This analysis is consistent with engineering estimates conducted by an engineering consulting firm
that provided lighting and electrical consulting services for the project. That the lighting retrofits
have no effect on the building’s heating and cooling demands is consistent with lighting retrofits
that largely involve replacing T12 fluorescents with more efficient T5 and T8 fluorescents. It is
therefore safe to exclude interactive effects from the GHG emission reduction quantification.
7.4 Adjustment for ECO Canada Funding
The Proponent received a grant from ECO Canada to aid in funding the first lighting retrofits at
the University through their ecoENERGY Retrofit program. The funding amount was 2.5% of the
total cost to retrofit the buildings included in the first quantification. To be conservative, any
buildings with completion dates before July 1, 2011 have had a 2.5% discount applied to the
credits created. Any buildings with completion dates after this date have not had this discount
factor applied, as they were completed without funding from ECO Canada or from any other
outside organization. No additional funding from ECO Canada or an exterior source has been
received by the U of A after the initial funding amount.
7.5 Sample Calculations
Sample calculations are presented for the Agricultural Forestry building, as an adjusted T8
baseline was required for this quantification. Building energy consumption included in the
quantification is from electricity consumption only; therefore, annual energy use is represented
as kWh.
Example #1: Agricultural Forestry Building
The calculation of GHG emission reductions for the Agricultural Forestry building is as follows,
where the project completion date was January 15, 2007 and the combined T8/T12 baseline
methodology is required:
Emissions EnergyUsage = (T8 Annual energy savings * Grid intensity factor) * (Reporting end
date – T8 Start date)/365)
+ (T12 Annual energy savings * Grid intensity factor) * [(T12 end date – Reporting start
date)/365]
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 31
Where:
Annual energy savings = (Annual quantity of electricity consumed in the baseline scenario
(kWh) - Annual quantity of electricity consumed in the project
scenario (kWh)) * Calibration error
and
Grid intensity factor = 0.64 tonnes CO2e/kWh according to the Alberta Carbon Offset
Emissions Factor Handbook (2015).
Calibration error = 6%
Therefore:
Emissions EnergyUsage T8 = [((1,130,517 kWh – 470,443 kWh) * (1 -0.06)) * 0.00064] *
((December 31, 2017 – January 16, 2017)/365)
+
Emissions EnergyUsage T12 = [((1,510,549 kWh – 390,155 kWh) * (1-0.06)) * 0.00064] *
((January 15, 2017 – January 1, 2017)/365)
=25 t CO2e (T8 baseline) + 379 t CO2e (T12 baseline) Annual Emissions Reduction
= 405 t CO2e
Eco-Canada Discount
As the Agricultural Forestry building was retrofitted prior to July 1, 2011, it would have received
eco Canada funding in support of the retrofit. Therefore, emissions are discounted 2.5%, as
indicated below:
= 405 t CO2e * (1-0.025)
= 394 t CO2e offsets claimed
7.6 GHG Assertion Consistency
The following figure illustrates GHG emission reductions over the entire life of the project (from
January 1, 2004 to the current quantification year, 2017) as a function of the number of retrofits
completed. In general, the trend shows that emission reductions increase over time as the
number of retrofits increases. However, where the number of retrofits remain constant, the
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 32
reductions decrease as additional buildings are converted to the T8 baseline and a smaller
quantity of energy savings is realized.
Figure 5: GHG Reductions vs. Number of Retrofits
8 Data Management, Monitoring and Control
8.1 Quantification and Monitoring
Table 6, below, provides a summary for the data quality management procedures for the
Project.
0
5
10
15
20
25
30
35
40
45
0
2000
4000
6000
8000
10000
12000
14000
16000
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
# B
uild
ings
t C
O2e
GHG Reductions (t CO2e) Number of Retrofits
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 33
Table 6. Data Quality Management Procedures for the Project
SSR identifier
or name
Data
parameter
Estimation,
modeling,
measurement or
calculation
approaches
Data
Recording
(electronic
or paper)
Data
unit
Sources/
Origin
Monitoring
frequency
Description
and
justification
of monitoring
method
Uncertainty Other details
Baseline/Project
Electricity
Usage
KWh of
electricity
consumed
Modeled using
IPMVP Calibrated
Simulation –
Option D.
Calibration is
done using data
logging
equipment used
onsite included
SmartReader 3 5
loggers and
SmartReader 3+6
loggers.
Electronic
and hard
copy
kWh
Calibrated
Simulations
conducted
by lighting
and
electrical
engineering
consulting
firm.
Monitoring
done for one
week to
capture
building
occupancy
patterns during
typical facility
operations.
This is the
most accurate
method given
the lack of
monitored
data in the
baseline and
the costs
associated
monitoring.
Uncertainty is low as
calibration is applied
to both baseline and
project conditions.
The accuracy of the
SmartReader3 logger
current transducer is
+/- 4% FS (Full Scale)
(above 10% of range)
The SmartReader 3+
logger current
transducer has an
accuracy of +/-
3.5% FS (above 10%
of range). Voltage
channels have an
accuracy of +/-
0.5% FS (5 VDC).
Operating hours of each
fixture per room is
approximated for the
baseline conditions and
entered into the
simulated lighting
model. The
approximated
operating hours are
derived from posted
campus building hours,
a survey of observed
occupancy patterns and
previous project
experience. Operating
hours in the baseline
and project condition
are assumed to be
identical.
5 Arc Systems, http://www.acrsystems.com/products/smartreader3/
6 Arc Systems, http://www.acrsystems.com/products/smartreaderplus3/
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 34
8.2 Data Management and QA/QC at Blue Source
7.2.1 Blue Source Standards
Blue Source Canada holds itself to the highest professional and ethical standards. Staff all have
experience in working on GHG projects and/or training in the use of ISO14064-2. Junior staff
members are mentored closely until their level of competence is deemed sufficient for them to
work more independently. This experience and training helps to ensure that errors and omissions
are minimized, and that project documentation is compiled in accordance with the principles of
relevance, completeness, consistency, accuracy, transparency and conservativeness.
Blue Source Canada operates a rigorous internal QA/QC process that is built around the principle
of senior review (i.e. calculations and reports are checked by experienced staff members prior to
being released). The quantification calculator, for example, will be checked for:
• Transcription errors/omissions
• Correctly functioning links/formulas in spreadsheets
• Correct and transparent referencing of data sources
• Justification of assumptions
• Use of, and compliance with, most up-to-date versions of protocols, technical guidance,
etc.
In addition, the Project Report is also senior-reviewed for errors, omissions, clarity, etc.
Any issues with any of the project documentation – including the calculator – are recorded using
Blue Source’s in-house QA/QC tracking sheet and, as necessary, comments are embedded into
the reviewed version of the documents and/or calculator. These must then be corrected before
any documents are sent to the third-party verifier.
Staff sign an “Attestation of Quality Assurance and Quality Control” to document that the QA/QC
process was followed.
7.2.2 Back-up Procedures at Blue Source
Electronic data is backed up by Blue Source’s IT service provider, Calitso. A recent copy of this
back-up procedure is provided in Appendix B.
7.2.3 Document Retention Policy at Blue Source
Blue Source operates a documentation retention policy, which all staff must abide by as a
condition of their employment. A copy of this document retention policy is provided as
Appendix C.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 35
9 Statement of Senior Review This offset project report was prepared by Kelsey Locke, Carbon Solutions Analyst, Blue Source
Canada and senior reviewed by Graham Harris, Principal Consultant, Firefly GHG. Although care
has been taken in preparing this document, it cannot be guaranteed to be free of errors or
omissions.
Prepared by: Senior reviewed by:
Kelsey Locke
04/12/2018
Graham Harris, Firefly GHG
04/17/2018
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 36
10 References
Efficiency Valuation Organization. (2009). International Performance Measurement &
Verification Protocol: Concepts and Options for Determining Energy and Water
Savings, volume 1.
Government of Alberta. Alberta Quantification Protocol for Energy Efficiency in
Commercial and Institutional Buildings, Version 1.0, October 2010.
ReLumen Engineering (2015). CO2 Offset Quantification Procedure Lighting Upgrade
Projects 2004-2014: University of Alberta.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 37
Appendix A: List of University of Alberta Facilities that Underwent
Energy Efficiency Retrofits
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 38
Table 9 – List of U of A Facilities that Underwent Lighting Retrofits
BUILDING CODE COMPLETION DATE BASELINE
Biological Sciences Building 51550
Genetics Wing
May 15, 2004 T8
Psychology Wing
August 15, 2004 T8
Centre Wing
October 15, 2004 T8
Zoology Wing
January 14, 2005 T8
Microbiology Wing
April 13, 2005 T8
Botany Wing
June 24, 2005 T8
Agricultural Growth Chambers
December 10, 2005 T12
Law Centre 52950 June 12, 2006 T8
Earth Sciences Building 51050 October 8, 2006 T8
Agricultural Greenhouse 52650 November 10, 2006 T12
Rutherford Libraries (North / South) 53200/53850 November 10, 2006 T8
Agricultural Forestry Bldg* 51060 January 15, 2007 T12 until 2017-1-15
T8 starting 2017-1-16
Medical Sciences* 51500 April 4, 2007 T12 until 2017-4-4
T8 starting 2017-4-5
Arts Building and Convocation Hall* 51250 May 15, 2007 T12 until 2017-5-15
T8 starting 2017-5-16
Tory* 54550 June 28, 2007 T12 until 2017-6-28
T8 starting 2017-6-29
Physical Education East / West (Van Vliet)* 53410 / 53400 August 23, 2007 T12 until 2017-8-23
T8 starting 2017-8-24
Humanities 51260 February 8, 2008 T12
Universiade Pavilion (Butterdome) 54320 January 15, 2008 T12
Corbett 52100 April 17, 2008 T12
Chemistry Building, East 52000 June 30, 2008 T12
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 39
Extension centre/Terrace 52200 April 21, 2009 T12
OSBM
July 15, 2009 T12
Morrison Structural Lab
October 22, 2009 T12
RCMS 53550 January 18, 2010 T12
Industrial Design
March 26, 2010 T12
Fine Arts
April 14, 2010 T12
Administration Building
May 31, 2010 T12
Students Union Building
December 15, 2009 T12
Hatchery
October 12, 2010 T12
Augustana Campus
November 8, 2010 T12
Mechanical Engineering
November 6, 2010 T12
Education North
March 21, 2011 T12
HUB Main Floor
May 30, 2011 T12
Environmental Engineering
August 9, 2011 T12
Education South
September 14, 2011 T12
Timms
April 11, 2012 T12
Campus St. Jean
June 21, 2012 T12
Heritage Medical Research Centre
September 27, 2013 T12
Augustana Residences
November 8, 2010 T12
Clinical Sciences 2, 3, 5, 6 Floor Corridors
September 30, 2014 T12
* Buildings that have been remodeled, providing a T8 baseline that has been used in
conjunction with a T12 baseline for this quantification period, for building retrofits completed
ten years ago.
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 40
Appendix B: Back-up Procedures at Blue Source
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 41
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 42
Appendix C: Data Retention Policy at Blue Source
Last Revision: August 2, 2017
Document Retention Policy, version 1.4.
1. All documents relevant to Offset Projects will be kept, in at least
electronic format, and where possible, in hardcopy format, for
a. At least 10 years beyond the last year in which credits are created
(e.g. a project that creates credits between 2010-2018 will have
all records kept until at least 2028), or
b. As required by the Offset Project Program
whichever period is longer.
2. Hard copy documents will be kept in project folders in our Blue Source
Canada head office location, which is currently Suite 1605, 840 – 7th Av
SW, Calgary, AB, T2P 3G2. All electronic documents will be saved to the
appropriate project folder on the Calgary Server (“S:\ drive”).
3. The S:\ drive will be backed up in accordance with Blue Source’s IT
Backup Procedure, which may change from time to time.
4. Blue Source’s preference is to keep all documents in electronic form,
wherever possible.
5. All employees will comply with this policy as a condition of their
employment.
Yvan Champagne
President, Blue Source Canada ULC
University of Alberta Energy Efficient Lighting Project
April 2018
Page | 44
Appendix D: Relumen Quantification Procedure
CO2 OFFSET QUANTIFICATION PROCEDURE
LIGHTING UPGRADE PROJECTS 2004-2014 University of Alberta
Prepared By: Eric Budd, P.Eng.
ReLumen Engineering Inc. Edmonton, AB
March 13, 2015
REVISION 5
(REI Ref No. B252-R07)
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 1 of 13
EXECUTIVE SUMMARY
The University of Alberta completed several lighting upgrade projects throughout campus buildings.
Projects summarized in this quantification report were completed between the years of 2009 and 2014.
This report outlines the methodology used to provide a conservative approximation of the total CO2
offset Tonnes attributed to the University of Alberta’s lighting upgrade projects. The methodology
follows the guideline requirements of Option D – Calibrated Simulation Model as per EVO 10000-1.2010
International Performance Measurement and Verification Protocol.
A simulated lighting model is created for each lighting upgrade project to approximate the total lighting
energy used in baseline and post-project conditions. The model is developed from a data set of building
conditions, industry standards for lamp wattages, fixture/lamp quantities, and approximate operating
hours. This simulated model outputs a Summary of Measures sheet for each project which effectively
shows the energy savings attributed to lighting.
Lighting upgrade projects completed more than 10 years ago have been re-modelled using revised
baselines.
Operating hours input into the simulated lighting model assume peak load conditions. Data logging was
performed in March 2010 and February 2015 on a sample population of building lighting panels. This
was done to capture data to show actual building occupancy patterns and validate the peak load,
operating hours and total consumption used in the simulated model. The results of the data logging
analysis show that in all cases the measured values are less than the model values with respect to panel
peak load (kW), consumption (kWh), and operating hours (weighted average). The energy savings
derived from the simulated model can then be considered as a conservative approximation in
comparison to the measured data.
Data logging activities and available project documentation was collected and reviewed to substantiate
the results of the simulated lighting model. The results of comparing measured data sets to the
simulated model provided a means to effectively calibrate the model while maintaining a conservative
value of total lighting energy savings. A revised calibration adjustment of -6% has been applied to the
results of the simulated model.
All required project documentation not previously issued is available in the Appendix of this report. This
includes Lien Holdback Release Certificates and Summary of Measures – Electrical Savings sheets for
each project added to the quantification portfolio in addition to Lamp Type Input Wattage Data Sheets
and data logging results.
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 2 of 13
TABLE OF CONTENTS
Executive Summary ...................................................................................................... 1
Table of Contents .......................................................................................................... 2
Introduction ................................................................................................................... 3
Project Background ................................................................................................................ 3 Quantification Team ................................................................................................................ 3
Summary of Methodology ............................................................................................ 5
Calibrated Simulation (Option D) ............................................................................................ 5 Simulated Lighting Systems Model ......................................................................................... 5 Model Calibration .................................................................................................................... 8
Summary of CO2 Offset Quantification ..................................................................... 13
Conclusion ................................................................................................................... 14
Appendix ...................................................................................................................... 15
U of A Summary of CO2 Reduction 2004-2014, Rev 5 ...........................................................16 U of A Summary of CO2 Reduction 2015, Rev 5 ....................................................................17 Lien Holdback Release Certificates .......................................................................................18 Project Summary of Measures ...............................................................................................19 List of Assumptions and Explanation of Columns ...................................................................20 Default Operating Hours ........................................................................................................21 BC Hydro – Lamp Type Input Wattage Data Sheets ..............................................................22 Data Logging – Sample Population, Graphs & Analysis .........................................................23
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 3 of 13
INTRODUCTION
Project Background
Energy savings throughout the University of Alberta campus were achieved through building
lighting upgrade projects.
The University of Alberta identified a need for lighting upgrade projects based upon existing
building conditions and existing lighting systems within the building. Existing lighting was either
replaced or retrofitted with modern lighting system technologies. There were also instances on
many projects where lighting requirements were reviewed by the lighting engineering consultant
and modified to reflect changes in building use and occupancy requirements. As a side effect,
the lighting upgrade projects also promoted building occupancy awareness and campus wide
energy conservation which improved energy savings further.
The University of Alberta completed several lighting upgrade projects throughout campus
buildings. This report captures CO2 offset quantification of projects completed between the
years 2009 and 2014. Previously issued report Rev 2A summarized projects completed
between 2004-2010, Rev 3A between 2010 and 2013. The project and quantification
methodology was successfully verified in 2011 and again in 2013.
Quantification Team
ReLumen Engineering Inc. is an Edmonton based engineering firm that provides lighting and
electrical consulting services. ReLumen is a team of professional electrical and mechanical
engineers, energy managers, lighting specialists, power quality experts and project managers.
In addition to industrial and commercial project experience, ReLumen has performed lighting
and electrical audits and retrofits on over 500 schools, university buildings and health care
facilities. ReLumen has been involved in CO2 quantification projects for various clients over the
past 4 years.
ReLumen is also a consultant member of the BC Hydro PowerSmart Industrial Alliance program
and holds a direct service contract with BC Hydro as a lighting engineering specialist.
ReLumen’s simulated lighting systems model is recognized and approved by BC Hydro.
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 4 of 13
Blue Source Canada is North America’s premier greenhouse gas emissions related marketing
and technical services firm, with extensive experience in quantifying, documenting, and trading
greenhouse gas offsets and renewable energy certificates in Canada and the United States.
Blue Source holds the leading climate change offset portfolio in North America with more
publicly registered third-party verified GHG offsets, more historical GHG offset sales and more
GHG offset types by location, vintage and source than any other company in North America.
Blue Source is a leader in the development and application of GHG emission reduction
quantification standards. Blue Source has worked alongside industry stakeholders in quantifying
potential project-based emission reductions, and guiding proponents through the data collection
and verification process for the California Action Reserve, Voluntary Carbon Standard, Alberta
Offset System, American Carbon Registry and other emerging systems.
Blue Source is the largest contributor to the ISO 14064-2-based, Alberta Offset System
producing various system guidance documents and over 25 of the approved and pending
protocols with another set at various stages in the approval process.
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 5 of 13
SUMMARY OF METHODOLOGY
Calibrated Simulation (Option D)
The International Performance Measurement and Verification Protocol (IPMVP) is a guidance
document describing the common practice in measuring, computing, and reporting energy
savings.
As outlined in the EVO 10000-1.2010 Protocol, Option D was selected to as the approach for
measurement and quantification of the University of Alberta’s energy savings attributed to
lighting system upgrades.
Lighting energy savings derived from the simulated model is calculated using the following
equation:
Energy Savings =
(Pre-Project Energy Use) – (Post-Project Energy Use) ± Calibration Adjustment
The calibration adjustment value is determined from analysis of data logging activities
performed on a sample population. The simulated model is then calibrated so that it predicts
energy patterns that approximately match actual metered data trends.
Simulated Lighting Systems Model
A simulated model of building lighting systems was created by ReLumen Engineering to provide
a realistic approximation of the expected energy savings attributed to upgraded lighting
technologies. This lighting model has been adopted by the University of Alberta and is used by
all consultants (ReLumen Engineering and others) for all lighting upgrade projects on campus.
The simulated model for each project is captured using MS Excel software. The MS Excel
workbook template is fairly elaborate, using a collection of large two dimensional data sets and
lookup tables. Several matrices within the spreadsheet workbook are used to summarize the
baseline and post-project conditions of the simulated model and approximate the energy
savings.
The initial step of a lighting upgrade project is to establish baseline conditions for the building.
Architectural drawings and an official list of building rooms complete with room number, square
footage and description of use, are provided by the U of A to the lighting consultant. This list is
imported into the simulated lighting model template.
Project models have been completed using a T12 baseline to reflect actual pre-project site
conditions. Retrofit projects replaced T12 with T8 lighting technology to achieve energy savings.
However, lighting upgrade projects completed more than 10 years ago and previously quantified
(and verified) using the actual pre-project T12 baseline condition have been re-modelled using a
T8 baseline to reflect modern lighting standards for this 2015 quantification.
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 6 of 13
A physical inspection of site conditions is performed by the lighting consultant. An audit tally of
existing fixture quantities, types, and number of lamps per fixture is completed on a room-by-
room basis of the building. In addition, lamp burnouts and de-lamping observed onsite are
noted to account for lighting energy removed from the Baseline. This collected information is
entered into the simulated lighting model to provide a baseline data set.
Operating hours for each fixture (per room) is approximated for the baseline conditions and
entered into the simulated lighting model. The U of A Lighting - Default Operating Hours table
lists the default operating hours assigned to the variety of rooms and typical spaces found at the
University of Alberta. Refer to the Appendix. These default operating hours are used as a
starting point; while conducting the lighting audit at the outset of the lighting upgrade project,
default operating hour values are modified to match lighting useage in the building as observed
onsite, posted campus building hours, a survey of occupancy patterns and previous project
experience. When the lighting project is complete, the model results will be back checked
against actual utility bills to determine the percentage of lighting energy useage in the building.
The operating hours are then slightly adjusted from the default values if the modeled lighting
energy usage amounts seem unreasonable
Once baseline conditions have been established in the simulated lighting model, existing utility
bills are reviewed by the lighting consultant to validate the entered data is correct and the
approximated operating hours are reasonable. Consideration is given to the fact that the utility
bills reflect total building load demand and consumption.
The lighting consultant provides recommendations for different retrofit measures for the lighting
upgrade project. This includes replacement fixture types and new lighting technologies which
will recognize energy savings. The U of A then provides approval of the recommended design
concepts outlined in this preliminary engineering phase and the consultant proceeds. A detailed
lighting upgrade detailed design refines the retrofit measures and the project is then issued for
tender. A contractor is awarded the tender and proceeds with construction.
Following completion of construction, the lighting consultant completes a post-project review of
the actual installation. Contractor as built mark-ups are reviewed and the completed installation
is confirmed onsite. A follow-up audit tally of all new fixture quantities, replacement types,
number of lamps per fixture and lighting energy added or removed is completed on a room-by-
room basis of the building and entered into the simulated lighting model to provide a post-
project data set. Operating hours under post-project conditions are assumed identical to the
operating hour approximations made under the baseline conditions.
The amount of lighting energy used is applied to baseline and post project conditions. These
values represent industry standards and manufacturer’s data for average energy use given
lamp types, lamp quantities per fixture, and ballast configurations (i.e. slaving). Available in the
Appendix are the BC Hydro Power Smart Input Wattage Data sheets for different lamp types
and conditions which reflect values input in the simulated lighting model.
A Summary of Measures – Electrical Savings sheet is produced as an output from the simulated
lighting model and provided for each project (building). Refer to the Appendix. These
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 7 of 13
summaries indicate baseline consumption (Previous Annual kWh Usage) and the approximated
savings (Annual Energy Savings) derived from the lighting model. A List of Assumptions and
Explanation of Columns sheet which describes the Summary of Measures is also available in
the Appendix.
As built drawings were reviewed and site inspections were performed by ReLumen Engineering
as part of the quantification process. This was done to confirm that the input values used in the
simulated lighting model (and as a result the derived savings) accurately reflect present site
conditions (i.e. no lighting fixtures were added or removed between the time the lighting
upgrade was complete and the present).
This Simulated Lighting Systems Model developed by ReLumen Engineering is recognized and
approved by BC Hydro. BC Hydro is a leading public works utility company in the areas of
energy conservation. BC Hydro standards historically have become accepted nationwide as
standard practice.
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 8 of 13
Model Calibration
Data Logging & Analysis
Data logging activities were performed as part of the initial CO2 offset quantification for the U of
A’s lighting systems. This was done to provide measured support for the accuracy of the
Simulated Model described previously. The measured data set would illustrate trends in peak
load demand (kW) and consumption (kWh).
In addition, data logging would provide a graphical representation of building occupancy
patterns and provide validation to the operating hours included in the simulated lighting model.
The 1 week metering period would ideally capture building occupancy patterns during the
University’s winter semester.
Additional data logging was performed as part of the 2015 year quantification to increase the
sample population to meet the growing total CO2 offset portfolio for the U of A.
Data logging equipment used onsite included current transducers, voltage transducers,
SmartReader 3+ loggers and TrendReader Version TR2 2.31 software, all manufactured by
ACR Systems.
Lighting throughout campus buildings is electrically fed by designated 347Vac lighting panels.
Lighting panels generally feed an entire floor or wing of a building. Data logging equipment was
connected to select 347Vac lighting panels to measure the total panel load (Phases A, B, & C
metered individually) as well as the building voltage over the course of a one week period.
Please note that for a sample case where multiple panels were metered simultaneously in the
same building, only voltage from one panel was metered and extrapolated to other panels
during analysis. Voltage drop is considered negligible.
Option D Calibrated Simulation Model (EVO 10000-1.2010) requires the lighting system energy
to be isolated from that of the rest of the facility by appropriate meters. This was achieved
through selecting designated lighting panels serving each floor. There were many instances
where lighting panels fed other loads, such as transformers and subpanels. These cases were
simply excluded from the sample population selection.
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 9 of 13
Data logging of a random sample of campus buildings (by floor) was performed by ReLumen Engineering throughout the month of March 2010 as well as February 2015. A list of samples collected with metering start and finish dates is as follows:
BUILDING FLOOR PANEL DESCRIPTION START FINISH
Chemistry East
1st Floor Panel H1A Lecture theatres, labs 4-Mar-2010 11-Mar-2010
Chemistry East
4th Floor Panel H4A Labs, Offices 4-Mar-2010 11-Mar-2010
Chemistry East
5th Floor Panel H5A Labs, Offices 4-Mar-2010 11-Mar-2010
Rutherford North
Main Floor Panel EE Library stacks, offices, common 11-Mar-2010 18-Mar-2010
Rutherford North
3rd Floor Panel CC Library stacks, offices, common 11-Mar-2010 18-Mar-2010
Bio Sci Centre Wing
1st Floor Panel C1L1 Labs, classrooms, offices 16-Mar-2010 23-Mar-2010
Bio Sci Centre Wing
2nd Floor Panel C2L1 Labs, classrooms, offices 16-Mar-2010 23-Mar-2010
Universiade Pavilion Catwalk Panel 6B Track, Infield, Bleachers etc 18-Mar-2010 25-Mar-2010
Clinical Sciences 3rd
Floor Panel 3A Labs, classrooms, offices 5-Feb-2015 11-Feb-2015
Fine Arts 3rd
Floor Panel H3B Labs, classrooms, offices 5-Feb-2015 11-Feb-2015
General Services 2nd
Floor Panel H3 Offices, common 28-Jan-2015 4-Feb-2015
Refer to the Appendix for data logging graph results. Graphs were created directly from logger
output (.dlf file) and printed via TrendReader software platform.
Data logger outputs were converted to comma separated values (.csv file) and then dumped
into MS Excel for analysis. Real power (VA) from all phases is summed together for each
record interval (1 sample per minute). A 0.9 power factor is approximated and used to convert
to kilowatts (kW). MS Excel was then used to used to analyze the data logging results
graphically and mathematically.
In order to accurately compare of data sets (i.e. model & logged data), post-project model data
was extracted to match quantities of fixtures connected to the logged lighting panel. This was
achieved through assessing as built drawings, panel schedules, and accessing the post-project
model data set. This allowed for a direct comparison between the logged lighting panel and a
subset of the post-project model. Please note post-project kilowatt-hours were adjusted to
reflect weekly consumption.
As stated in the description of the simulated lighting model, the model assumes peak load
demand (kW). As expected the peak load demand (kW) was shown to be greater in the post-
project model when compared to the data logging sample.
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 10 of 13
Using the trapezoidal rule the energy used between each sampling was calculated and then
summed together. This integration of the data set approximates the area underneath the
logged kW vs time operating curve. This gives the total energy use (kWh) during the week-long
data logging period. This calculation is recognized using the following formula:
xii
iitot
tPtPttE
1
11
2
)()()(
Etot = Total energy used over entire data logging period ti = Time at reading i ti+1 = Time at subsequent reading P(ti) = Power at time i P(ti) = Power at time of subsequent reading X = Total number of readings
The results show that the post-project model (subset) showed greater energy consumption
(kWh) than the data logged samples.
By dividing energy consumption (kWh) by peak load demand (kW), a weighted average or
equivalent weekly operating hours is calculated for both the post-project model and the data
logging results. In all cases from the 2010 data logging sample, the operating hours derived
from post-project model data subset and the data logging samples were within 10%. For the
additional data logging performed in 2015, data logging sample showed a wider variance. This
can be attributed to changes in load diversity (i.e. changing hours) and deleted load demand
(i.e. some breakers were observed to be turned off).
Refer to the Data Logging Comparison sheet located in the Appendix. Also available in the
Appendix are graphs produced for each logged lighting panel showing a comparison of pre-
project model, post-project model, and data logged kilowatt hours.
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 11 of 13
The data logging analysis graph set shows three curves per logged lighting panel: Pre-Project
Model kWh, Post-Project Model kWh and Post-Project Data Logged kWh. The proceeding
calculations represent the cases of differences between the areas under the three curves shown
on the data analysis graph sets.
All values for pre-project model, post-project model, and data logging from the data sample
population i.e. logged lighting panels are summed. These summed values are used in the
calculations in the following steps to evaluate the model calibration adjustment.
1. The following difference represents 100% energy savings approximated by the model.
This represents the basis of the CO2 offset tonnes claimed through the use of the
simulated lighting systems model.
(S Pre-Model kWh) - (S Post-Model kWh)
i.e. blue curve – pink curve
2. The following difference represents 116% energy savings approximated by the model.
(S Pre-Model kWh) - (S Post-Data Logged kWh)
i.e. blue curve – green curve 3. Pre-Project Model kWh are calibrated using the ratio of post-project data logged and
model kWh values:
(S Calibrated Pre-Model kWh) = (S Pre-Model kWh) x (S Post-Data Logged kWh) / (S Post-Model
kWh)
The post-project data logged kWh are subtracted from the calibrated pre-project kWh:
(S Calibrated Pre-Model kWh) - (S Post-Data Logged kWh)
i.e. calibrated blue curve – green curve
This illustrates the worst case scenario for calibrating the model using the data logging results, representing roughly 72% of the energy savings approximated by the model. This calculation suggests that since the post-project model kWh are greater than the data logged kWh, than the same must be true of the pre-project model kWh.
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 12 of 13
Calibration Adjustment
The evaluation of the calibration adjustment is derived from a comparison of data logging samples to the lighting models. Please refer to the analysis sheet located in the Appendix.
The evaluation of the calibration adjustment using a total sum of the data logging samples and the total sum of extracted lighting model values (as described in the procedure above) show a 44% spread in adjustment i.e. 72% (-28%) and 116% (+16%) between the best and worst case scenarios. The mean calibration adjustment implied using the total sum of the data samples is found to by 94.3%. Note, when using two data points the mean is equivalent to the median value.
The same procedure and analysis was used to compare calibration adjustments derived from each individual data logging sample (i.e. per lighting panel) and the extracted values from their respective lighting models. With the revised data logging sample population, the median of and mean percent differences were found 97.5% and 95.2%, respectively, from the percent differences (between best and worst case scenarios) of the original CO2 claim.
A median value is used when there are a few extreme data points that could impact the calculated average and misrepresent the data sample. In the case of the derived calibration adjustments using individual data logging samples (i.e. per lighting panel), similar results were found between the best and worst case scenarios. Therefore the mean is a more appropriate calculation.
Because a data logging sample population was used to determine the calibration adjustment factor to apply across the entire collection of CO2 savings, using the total sum of the data samples was a more suitable analysis method. Furthermore, the calibration adjustment is nearly identical using either of the calculation methods described above (total sum vs individual data logging sets).
The mean calibration factor of 94.3% has been truncated to 94% to remain conservative in the overall approximation of energy savings predicted by the model. A calibration adjustment of -6% is applied to the kilowatt-hour energy savings for each simulated project model.
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 13 of 13
SUMMARY OF CO2 OFFSET QUANTIFICATION
Annual energy savings (kWh) is calculated as follows:
Annual Energy Savings kWh = Post kWh - Baseline kWh +/- Calibration Adjustment
The revised Calibration Adjustment used for the 2015 quantification is -6% as determined by the
results and analysis of the data logging sample population.
Alberta Environment’s protocol for quantification of greenhouse gas emissions uses the
following equation to convert kilowatt-hours to tonnes of CO2:
1 Tonne of CO2 = 0.00065 x kWh
This emission factor is increased by 12% to reflect reduction targets that electrical generators
are subject to under the Specified Gas Emitters Regulation. The following equation is used for
the purpose of the quantification of CO2 reduction for the University of Alberta’s lighting upgrade
projects:
1 Tonne of CO2 = 0.00073 x kWh
Using the above factor of 0.00073, annual energy savings (kWh) is converted to annual CO2
reduction (Tonnes).
Lien Holdback Release Certificates and in select cases equivalent documents such as
Certificates of Substantial Performance or correspondence which indicate project completion
are available for each building lighting project. This documentation indicates the project
installation was completed by the contractor and all deficiencies were resolved. The date of lien
holdback release (or appropriate dates indicated on equivalent documentation where
applicable) is used to signify project completion.
Annual CO2 Reduction (Tonnes) is summarized from project completion dates to April 30, 2015
(identified as the target date of sale) to calculate the Total CO2 Reduction (Tonnes) the
University is eligible to claim forward.
The total CO2 Reduction (Tonnes) as result of additional Lighting Upgrade Projects at the
University of Alberta not previously quantified, as well as previously included projects that have
had model baselines revised, referenced by this revision (Rev 5) of the quantification report is
2,665 Tonnes.
Please see attached U of A Summary of CO2 Reduction For 2015, Rev 5 located in the
Appendix.
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 14 of 13
CONCLUSION
This methodology for the quantification of Tonnes of CO2 offsets provides a conservative
approximation of energy savings attributed to Lighting Upgrade projects throughout the University of Alberta campus buildings This approach to quantification meets criteria and requirements outlined in the EVO International Performance Measurement and Verification Protocol in addition to guidelines included in Alberta Environment’s protocol for the quantification of greenhouse gas emissions.
x:\b252 blue source\b252-r07 uofa co2 quantification lighting retrofit projects 2014\02 quantification\uofa lighting co2 offsets quantification procedure rev 5 20150313.docPage 15 of 13
APPENDIX
Appendix
U of A Summary of CO2 Reduction 2004-2014, Rev 5
Appendix
U of A Summary of CO2 Reduction 2015, Rev 5
Appendix
Lien Holdback Release Certificates
Appendix
Project Summary of Measures
Appendix
List of Assumptions and Explanation of Columns
(re: Summary of Measures)
Appendix
Default Operating Hours
Appendix
BC Hydro – Lamp Type Input Wattage Data Sheets
Appendix
Data Logging – Sample Population, Graphs & Analysis