university of mary washington ms4 general...

27
University of Mary Washington MS4 General Permit Annual Report for the period 01 July 2013 through 30 June 2014 Background Information The departments of Capital Outlay and Landscape and Grounds are responsible for implementation and maintenance of BMP's for the university. Roles and responsibilities of these departments in enacting compliance with the General Permit remain unchanged since those roles were defined. Beneath the umbrella of the Facilities Services Division, the Capital Outlay department remains tasked with identifying and implementing construction of management controls through its oversight capacity of capital projects with land disturbing components. Once completed, information pertaining to the operation and maintenance ofthe management devices is passed to the Landscaping and Grounds department. Landscaping and Grounds also continues contribution to, and monitoring of, community outreach programs. As in years past, new MS4 facilities have been added to the University. This change reflects new construction on the Fredericksburg campus. UMW campuses in Stafford County and King George County, Virginia are included in this annual report, although no land disturbing construction activities were conducted on either of those campuses during this reporting period. Certification: "I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations." ~~'----L Date VAR040094 University of Mary Washington Permit Number MS4 Name Status of permit compliance, including BMP effectiveness analysis The University of Mary Washington strives for permit compliance through application of its Stormwater Master Plan (approved April 2009). Calculations done as a part of the Master Plan study indicate the University is required to remove 19 Ibs of phosphorus annually. There are 1

Upload: others

Post on 02-Sep-2019

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University of Mary WashingtonMS4 General Permit

Annual Report for the period01 July 2013 through 30 June 2014

Background Information

The departments of Capital Outlay and Landscape and Grounds are responsible forimplementation and maintenance of BMP's for the university. Roles and responsibilities of thesedepartments in enacting compliance with the General Permit remain unchanged since thoseroles were defined. Beneath the umbrella of the Facilities Services Division, the Capital Outlaydepartment remains tasked with identifying and implementing construction of managementcontrols through its oversight capacity of capital projects with land disturbing components.Once completed, information pertaining to the operation and maintenance ofthe managementdevices is passed to the Landscaping and Grounds department. Landscaping and Grounds alsocontinues contribution to, and monitoring of, community outreach programs.

As in years past, new MS4 facilities have been added to the University. This change reflects newconstruction on the Fredericksburg campus. UMW campuses in Stafford County and KingGeorge County, Virginia are included in this annual report, although no land disturbingconstruction activities were conducted on either of those campuses during this reporting period.

Certification: "I certify under penalty of law that this document and all attachments wereprepared under my direction or supervision in accordance with a system designed to assure thatqualified personnel properly gather and evaluate the information submitted. Based on myinquiry of the person or persons who manage the system, or those persons directly responsiblefor gathering the information, the information submitted is, to the best of my knowledge andbelief, true, accurate, and complete. I am aware that there are significant penalties forsubmitting false information, including the possibility of fine and imprisonment for knowingviolations."

~~'----LDate

VAR040094 University of Mary WashingtonPermit Number MS4 Name

Status of permit compliance, including BMPeffectiveness analysis

The University of Mary Washington strives for permit compliance through application of itsStormwater Master Plan (approved April 2009). Calculations done as a part of the Master Planstudy indicate the University is required to remove 19 Ibs of phosphorus annually. There are

1

Page 2: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  2  

the  required  phosphorus  removal.    Additionally,  one  of  the  facilities  is  being  renovated  as  part  of  a  new  construction  project.  Currently  the  Fredericksburg  campus  exceeds  the  removal  requirements  by  3.3  lb  annually.  

Results  of  monitoring  data,  if  any,  collected  and  analyzed    2014    UMW  Fredericksburg  campus  has  developed,  and  is  implementing,  improvements  to  existing  stormwater  management  practices.  These  improvements  are  both  civil  improvements  to  conveyances  to  improved  or  new  recognized  BMP  devices,  and  through  elimination  of  channel  erosions  occurring  in  five  intermittent  and  /  or  permanent  stream  beds.  Monitoring  stations  on  the  channel  improvements  will  be  installed  at  the  completion  of  the  project  (estimated  to  be  October  2014).  It  is  expected  that  an  additional  Appendix  will  be  added  to  the  2015  report.  This  appendix  will  provide  inaugural  data  points  for  stream  monitoring.    2013  The  campus  characterizations  expressed  in  the  2012  report  have  improved  somewhat.  Through  Commonwealth  Pool-­‐funded  resources  UMW  Fredericksburg  is  developing  plans  to  improve  existing  stormwater  conveyances  by  means  of  two  distinctly  different  methods.  Some  area  with  existing  civil  site  installations  are  being  improved  to  better  convey  stormwater  while  reducing  time  of  concentration.  Other  improvements  are  classified  as  environmental  improvements,  incorporating  stream  channel  features  to  decrease  velocity  while  increasing  absorptive  characteristics  of  soils  and  vegetation.    2012  and  2011  No  permanent  monitoring  stations  have  been  established  on  any  UMW  campus.  The  Fredericksburg  campus  contains  one  stream  identified  as  capable  of  developing  erosive  velocities  during  both  2-­‐year  and  10-­‐year  storm  events.  This  stream  has  been  determined  to  be  within  Corp  of  Engineers  jurisdiction,  and  also  determined  to  be  eligible  for  a  stormwater  management  facility  within  a  Resource  Protection  Area.  This  is  the  principal  area  identified  for  the  regional  approach  to  UMW’s  future  stormwater  management  facilities.  

On  the  Battleground  Athletic  Complex  of  the  Fredericksburg  campus,  several  drainage  channels  exist  which  are  also  eligible  for  channel  improvements  and  detention  /  infiltration  facilities.  These  channels  demonstrate  little  likelihood  of  flooding,  but  do  develop  erosive  velocity  and  were  deemed  inadequate.  

In  Stafford  County,  UMW  has  a  48  acre  (+/-­‐)  campus,  of  which  approximately  38  acres  are  considered  developed.  The  campus  includes  a  presumed  perennial  spring  feeding  into  a  retention  pond  with  forebay.  The  combined  capacity  of  this  pond  is  about  70,000  cubic  feet  capacity.  There  is  also  a  bioretention  BMP  treating  about  3  acres  before  entering  the  county  stormwater  system.  

The  UMW  Dahlgren  property  in  King  George  County  is  28  acres  (+/-­‐),  with  approximately  20  acres  developed.  At  the  Dahlgren  campus  some  of  the  significant  features  are  a  stormwater  pond  and  five  bioretention  BMPs.  These  devices  treat  run-­‐off  from  the  parking  areas  and  the  first  building  on  campus.    

Activities  anticipated  for  the  next  reporting  cycle          

Page 3: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  3  

 2014    As  noted  in  the  2011  and  2012  reports,  the  Information  Technologies  Convergence  Center  (ITCC)  has  been  added  to  the  BMP  inventory  for  the  Fredericksburg  campus.  That  system  has  come  on-­‐line  and  is  listed  in  Appendix  A.     Also  noted  in  the  2012  report,  the  University  Center  is  now  under  construction  on  the  Fredericksburg  campus.  This  structure  replaces  the  (now  demolished)  Chandler  Hall.  Stormwater  management  for  the  University  Center  includes  conveyance  improvements  to  inadequately  sized  concrete  pipe  received  from  the  City  of  Fredericksburg.  Due  to  the  increase  in  impervious  area  from  both  the  building  size  and  from  parking  /  delivery  areas,  a  concrete  retention  vault  is  included  to  increase  the  release  time  while  decreasing  the  peak  flow.  

 2013  Construction  of  environmental  improvements  to  stream  channels  and  civil  improvements  to  existing  failing  conveyances  on  the  Fredericksburg  campus  are  expected  to  commence  in  the  next  reporting  cycle.  

 2012  On  the  Fredericksburg  campus,  work  has  begun  on  the  Convergence  Center,  one  of  two  projects  noted  as  anticipated  for  this  reporting  cycle.  New  stormwater  BMP’s  for  this  project  are  1)  a  9600  CF  (gross)  stormwater  detention  system  and,  2)  a  35  cartridge  CONTECH  filtration  system    with  a  water  quality  flow  rate  of  1.75  gps.  

Stormwater  plans  for  the  Student  Center  (replacing  Chandler  Hall)  are  still  in  development.    

2011  The  activity  reported  on  the  last  cycle  has  been  moved  to  #3  in  the  next  section.    Two  projects  are  upcoming.  One  is  the  Convergence  Center,  a  new  building  on  the  

Fredericksburg  campus  north  end  between  Arrington  Hall  and  Simpson  Library,  connecting  to  the  latter.  The  other  project  is  the  demolition  of  an  existing  building,  Chandler  Hall,  to  be  replaced  by  a  larger  building  housing  a  student  center  and  dining  facility.  Neither  project  development  is  advanced  to  the  point  of  understanding  stormwater  requirements  and  impacts.    

Changes  in  BMP’s  or  goals  for  the  minimum  measures,  and  steps  to  address  deficiencies       2014    UMW  has  implemented  changes  identified  during  the    last  MS4  Program  Plan  review.  To  

that  extent  that  internal  education  was  deficient,  UMW  engaged  in  training  materials  loaned  from  the  City  of  Fredericksburg.  These  programs  aimed  at  identifying  and  eliminating  point-­‐source  pollution.  Internally,  UMW  Sustainability  program  participates  in  student-­‐organized  events  where  the  principles  of  illicit  discharge  identification  are  described  along  with  other  sustainable  practices.  Externally,  UMW  participated  in  a  Virginia  Sports  Turf  Managers  Association  presentation  of  turf  management,  irrigation,  and  fertilizer  reduction.  

    2013  UMW  has  reviewed  and  revised  the  University’s  MS4  Program  Plan  to  more  accurately  

depict  the  goals  set  forth  therein.  These  revisions  are  particularly  in  the  education  of  staff,  the  University  community,  and  the  wider  Fredericksburg  area  to  the  negative  impact  of  uncontrolled  stormwater  runoff.  Internally,  staff  has  been  trained  in  identifying  and  reporting  

Page 4: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  4  

illicit  discharges  to  appropriate  administrators  so  that  such  discharge  can  be  eliminated  from  the  stormwater  stream.    

 2012  Construction  related  to  the  Anderson  Center,  located  at  the  northern  end  of  the  Fredericksburg  campus,  completed  the  renovation  of  the  existing  bio-­‐retention  pond.  

A  civil  engineering  firm  is  reviewing  the  overall  phosphorus  reduction  goal  for  the  Fredericksburg  campus.  While  the  result  of  this  study  is  still  forthcoming,  it  is  expected  that  a  project  to  improve  BMP  performance  will  be  initiated  as  a  response  to  the  study.  

 2011  1.  In  conjunction  with  new  work  begun  in  July  2009,  the  mid-­‐1990’s  style  bio-­‐retention  pond  located  between  Goolrick  Hall  and  the  Jepson  Science  Center  was  revised  to  a  345  cf  bio-­‐retention  filter  including  underdrain  with  tree  and  shrub  plantings.  This  work  has  now  been  completed,  and  the  device  is  in  operation.    2.  Two  playing  fields  in  the  Battleground  Athletic  Complex  are  undergoing  renovation.  The  renovations  do  not  include  new  BMP  devices.  However,  these  fields  are  expected  to  reduce  the  velocity  and  improve  the  quality  of  stormwater  leaving  University  property.  These  improvements  are  achieved  by  infiltration  through  the  field  surfaces.  As  the  average  infiltration  rate  through  the  subsurface  soils  averages  7.5  inches  of  water  per  hour,  the  Department  of  Conservation  and  Recreation  approved  a  field  design  capable  infiltrating  5  inches  per  hour.  No  subsurface  piping  is  involved,  and  all  water  received  on  either  field  moves  through  the  subsurface  via  percolation.        3.  Mason  and  Randolph  Halls,  a  joined  dormitory  group,  are  being  fully  renovated.  The  BMP  design  for  this  project  incorporates  a  5200  cu  ft  temporary  storage  vault  feeding  a  9-­‐cartridge  BaySaver  filtration  system  with  50%  removal  efficiency.    

Reliance  on  other  governmental  agencies  for  compliance       2014    UMW  retains  the  cordial  relation  between  governing  agencies  in  the  City  of  

Fredericksburg,  and  the  counties  of  Stafford  and  King  George.  UMW  maintains  campuses  in  all  three  of  these  governmental  areas.  There  is  interdependency  between  the  stormwater  management  systems  in  the  city  of  Fredericksburg  and  Stafford  County,  while  the  Dahlgren  campus  in  King  George  County  remains  stand-­‐alone.  

    2013  There  remains  interdependency  between  systems  in  Fredericksburg  and  Stafford.  

However,  neither  the  University  nor  the  City  or  Fredericksburg  or  Stafford  County  is  mutually  dependent  on  each  other  for  program  compliance.  A  cordial  relation  is  maintained  with  both  governments.  At  the  Dahlgren  campus  the  stormwater  system  remains  stand  alone.  

 2012  The  reliance  and  interdependence  between  the  University  of  Mary  Washington  and  the  city  of  Fredericksburg  remains.  Status  of  the  UMW  Stafford  and  UMW  Dahlgren  campuses  also  remain  as  described  in  2011.  

 

Page 5: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  5  

2011  The  University  of  Mary  Washington  both  receives  stormwater  from,  and  discharges  stormwater  to,  portions  of  the  city  of  Fredericksburg  stormwater  system.    The  two  systems  are  physically  interconnected.  Under  the  current  circumstances,  only  some  of  the  water  received  has  the  opportunity  for  settlement  or  filtration  before  passing  out  to  the  Fredericksburg  system  once  again.    

System  conveyance  evaluation  indicates  that  the  storm  sewer  system  is  generally  adequate  for  both  the  2-­‐year  and  10-­‐year  storm  cycles.  

Neither  the  Stafford  Campus  nor  the  Dahlgren  campus  is  currently  reliant  on  any  other  governmental  agency.  However,  approximately  6  acres  of  the  Stafford  campus  collect  stormwater  which  is  discharged  into  the  Stafford  County  storm  sewer  system.  Approximately  one-­‐third  of  that  area  is  filtered  through  a  bio-­‐retention  BMP,  while  the  remaining  area  is  filtered  through  the  grassy  lawns.    

Status  of  Section  IIC  programs  Implementation  of  Section  II  B  minimum  control  measures  1. Public  education  and  outreach  on  stormwater  impacts.    BMP  1.1  –  Education  As  a  state  supported  institution  of  higher  education,  UMW  recognizes  the  value  of  both  formal  as  well  as  informal  education  and  supports  life-­‐long  learning  opportunities  for  the  citizens  of  the  Commonwealth  of  Virginia.  As  a  practical  effort  in  student  learning  and  community  education  the  University  will  annually  support  the  employment  of  a  student  position  to  work  approximately  150  hours  per  year  with  Facilities  Services  staff  in  support  of  education  and  outreach  regarding  the  University’s  sustainability  programs,  including  storm  water.  Measurable  Goals:  UMW  will  promote  stormwater  awareness  through  the  UMW  website.  This  will  include  a  summary  statement  of  the  annual  evaluation  report.    2014  result:  On  Saturday,  Sept  28,  UMW  hosted  Sustainability  Day  at  Hurkamp  Park  (Farmer’s  Market).    Joining  UMW  were  the  Rappahannock  Chapter  of  the  Sierra  Club,  Tree  Fredericksburg  and  Downtown  Greens.  We  hosted  about  30  visitors  at  the  tables,  but  had  additional  foot  traffic  from  the  Farmer’s  Market.    Besides  the  information  provided  by  the  other  organizations  UMW  raised  awareness  about  the  issue  of  stormwater.  Information  included  what  stormwater  is,  why  there  is  a  problem  and  how  the  urban  dweller  is  a  part  of  the  solution.  Solutions  included  rain  barrels,  rain  gardens,  native  plants,  picking  up  pet  waste,  proper  fertilization  and  the  use  of  permeable  pavement.    Information  was  also  provided  on  our  watershed  address  and  how  to  report  illicit  discharge  in  Fredericksburg,  Stafford,  Spotsylvania  and  UMW.      In  addition  to  the  Stormwater  program,    UMW  provided  information  on  our  new  Food  Waste  Campaign  –  Think.  Change.  Eat.  –  informing  attendees  of  the  impact  food  waste  has  environmentally,  socially  and  economically.      There  were  interactive  games  that  brought  awareness  to  sustainable  choices  for  youth.  And  Bella  Acapella  performed  for  attendees  of  the  event  and  the  Farmer’s  Market.    

Page 6: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  6  

2013  result:  Goal  met.  UMW  continues  to  maintain  and  update  the  website  http://adminfinance.umw.edu/facilities/about-­‐facilities-­‐services/department-­‐policies-­‐programs/storm-­‐water-­‐systems/  May  21,  2013,  Joni  Wilson  hosted  the  UMW  Elder  Study  group  and  did  a  brief  talk  on  stormwater  as  a  part  of  the  Native  Plant/Sustainable  Landscape  Walk.  The  information  provided  in  the  talk  included:  watershed  address,  what  the  watershed  is,  the  impact  of  pollution,  what  the  homeowner  can  do,  illicit  discharge  and  how  to  report  it,  UMW’s  stormwater  master  plan,  UMW  and  state  oversight  of  soil  and  erosion  during  construction  and  stormwater  BMPs.  In  addition  as  we  walked  the  campus  we  saw  and  discussed  several  BMPs.  There  were  an  estimated  20  adults  in  attendance.    2012  result:  Goal  met.  UMW  again  employed  two  students  for  the  promotion  of  the  sustainability  program  and  maintenance  of  the  website  http//:www.umw.edu  click  the  Sustainability  tab  for  links  to  sustainability  at  UMW.    2011  result:  Goal  met.  UMW  employed  two  students  in  pursuit  of  sustainability  programs.  Stormwater  BMPs  are  posted  on  the  University’s  Sustainability  web  site  http://www.umw.edu/sustainability/initiatives/water/stormwater_best_practices1.php    

UMW  Sustainability  web  site  contains  information  on:  Sustainability  Day  2010,  Tri-­‐County/City  Conservation  District  Annual  Plant  Sale  and  Garden  Tour,  University  of  Mary  Washington  Sustainability  Policies  and  Practices,  UMW  Recycling  Program,  and  University  sustainability  initiatives:    

Water  -­‐Mary  Washington's  unique  position  in  the  Chesapeake  Bay  watershed  presents  us  with  great  responsibilities  for  conservation,  and  great  opportunities  to  preserve  this  unique  estuary.  We  strive  to  do  this  through  water-­‐saving  retrofits,  storm  water  management  outreach,  and  riparian  buffer  restoration.    

Sustainable  Design  -­‐While  UMW  expands  at  an  unprecedented  rate,  our  commitment  to  environmentally  conscience  development  remains  strong.  This  is  manifested  through  our  goal  to  achieve  LEED  certification  on  all  new  construction  projects,  beginning  with  our  soon-­‐to-­‐be-­‐built  campus  in  Dahlgren,  Virginia.    

Transportation  -­‐UMW  promotes  and  encourages  alternative  modes  of  transportation  (bicycling,  walking,  vanpooling,  carpooling,  riding  transit,  etc.)  to  get  to,  from,  and  around  campus  instead  of  a  single  occupancy  vehicle  (SOV).  This  will  result  in  fewer  cars  on  campus  and  on  the  roads,  reduced  demand  for  parking  spaces,  less  traffic  congestion,  fewer  vehicle/pedestrian  conflicts,  and  less  air  pollution.  

Climate  Change  -­‐  The  University  of  Mary  Washington  is  taking  responsibility  and  leadership  for  reduction  of  its  warming  gases  such  as  carbon  dioxide.    

 Energy  -­‐  Mary  Washington  is  committed  to  reducing  its  carbon  footprint  and  operating  costs  by  both  decreasing  its  energy  consumption  and  investing  in  clean,  renewable  energy  sources.  Energy-­‐related  initiatives  include  energy  auditing,  retrofitting  all  campus  light  bulbs,  and  installation  of  energy  management  systems.    

 Food  -­‐  Food  is  an  essential  human  need,  and  one  of  our  closest  connections  to  the  natural  world  around  us.  UMW  supports  the  sustainable  use  of  this  resource  by  purchasing  locally,  and,  in  the  future,  beginning  a  campus  food  composting  process.    

Page 7: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  7  

 BMP  1.2  –  Outreach  For  several  years  the  University  has  worked  jointly  with  local  organizations  including:    the  George  Washington  Regional  Green  Commission,  Fredericksburg  Clean  and  Green  Commission,  Friends  of  the  Rappahannock,  the  Rappahannock  Group  Sierra  Club,  Tri-­‐County/City  Soil  and  Water  Conservation  District,  Rappahannock  Regional  R-­‐Board,  and  Stafford  County.  Meetings  of  these  groups  cover  a  range  of  horticultural,  conservation,  and  environmental  topics,  provide  educational  and  outreach  opportunities  allowing  for  the  dissemination  of  informational  brochures.  UMW  shall,  at  least  once  annually,  provide  informational  brochures  concerning  stormwater,  the  University’s  MS4  Program  or  other  sustainability  related  topics  at  a  public  event.  Measurable  Goal:  Provision  of  brochures  at  designated  event.    2014  result:  During  October,  Joni  Wilson  lead  the  Chancellor  Garden  Club  on  a  campus  tour  of  native  trees  and  sustainable  landscaping.  As  part  of  the  tour  I  explained  the  University’s  and  homeowner’s  responsibilities  in  maintain  a  healthy  watershed.  We  discussed  common  pollutants,  good  practices  for  keeping  stormwater  clean,  our  watershed  address  and  reporting  illicit  discharge.  We  looked  at  and  discussed  a  bio-­‐retention  BMP  and  the  University’s  Stormwater  master  plan.  The  group  was  approximately  20.  The  full  tour  took  more  than  2  hours.    2013  result:  Sustainability  Day  2012  is  a  student-­‐centered  event  promoted  sustainability,  including  information  on  the  UMW  D.O.T.  program,  recycling  relays,  and  clothing  swap,  stormwater  brochures  produced  by  UMW  students,  the  City  of  Fredericksburg,  and  the  surrounding  counties  were  provided.  Table  and  booth  displays  by  UMW  Ecology  Club,  Friends  of  the  Rappahannock,  the  Rappahannock  Group  Sierra  Club,  Fredericksburg  Clean  and  Green  Commission,  and  Tri-­‐County/City  Soil  and  Water  Conservation  District  provided  stormwater  and  sustainability  information.    2012  result:  Goal  met.  Sustainable  Landscape  and  Environmental  Fair  a  community  event  was  held  in  June  ‘11.  Outreach  was  provided  UMW  staff,  local  CSA,  Rappahannock  Regional  R-­‐Board,  Roxbury  Mills,  4-­‐Season  Recycling,  Friends  of  the  Rappahannock,  Allied  Waste,  Master  Gardeners,  UMW  Ecology  Club  and  a  host  of  volunteers.  Educational  opportunities  included:  a  broad  spectrum  of  stormwater  brochures  (local  and  the  surrounding  counties),  native  plants  in  the  landscape,  establishing  native  grass  meadows,  worm  bin  composting,  interactive  model  watershed,  CSA  opportunities,  organic  herbicide  display,  interactive  erosion  demonstration,  rain  barrels  and  composters,  learn  to  make  jewelry  from  recycled  products  and  games  that  teach  sustainability  to  the  young  visitor.  Into  the  Streets,  held  in  September,  is  a  service  day  for  UMW  students,  who  participated  in  tree  planting  on  campus  in  cooperation  with  Tree  Fredericksburg.  Sustainability  Day  2011  was  held  in  October  this  student  centered  event  promoted  sustainability,  including  information  on  the  UMW  D.O.T.  program,  recycling  relays,  and  clothing  swap,  a  broad  spectrum  of  stormwater  brochures  (local  and  the  surrounding  counties)were  provided,  UMW  Ecology  Club,  Fredericksburg  Clean  and  Green  Commission,  Friends  of  the  Rappahannock,  the  Rappahannock  Group  Sierra  Club,  and  Tri-­‐County/City  Soil  and  Water  Conservation  District  provided  stormwater  and  sustainability  information.      

Page 8: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  8  

2. Public  involvement  /  participation.  BMP  2.1  –  Public  Involvement  (Local  Jurisdictions)  The  University  has  endeavored  to  maintain  effective  communication  and  coordination  with  officials  both  in  the  City  of  Fredericksburg  and  in  Stafford  County.  Numerous  formal  and  informal  meetings  and  communications  are  exchanged  on  a  variety  of  topics  throughout  any  year.  The  University  will  specifically  include  storm  water  as  an  agenda  topic  at  least  once  annually  in  meeting  with  the  appropriate  administrative  staff  personnel  in  the  two  local  jurisdictions.  Measurable  Goal:  Record  of  each  meeting  in  which  storm  water  topics  are  discussed.    2014  result:  UMW  continues  to  meet  and  interact  with  the  city  of  Fredericksburg  staff  concerning  stormwater-­‐related  matters.  Informal  contacts  include  mutual  reporting  and  correction  of  detected  illicit  discharges,  coordination  of  training  activities  and  materials,  and  discussion  of  the  effects  of  changes  in  discharge  patterns  between  the  city  system  which  surrounds  UMW,  and  UMW’s  stormwater  system.    2013  result:  Goal  met.  UMW  personnel  attended  the  basic  Stormwater  Management  course  provided  by  DEQ.  The  local  two-­‐day  presentation  was  held  at  the  Spotsylvania  County  Schools  building  in  June  2013,  and  was  attended  by  three  UMW  employees.    2012  result:  Goal  met.  UMW  personnel  attended  three  George  Washington  Regional  Commission  (GWRC)  meetings  concerning  implementation  of  WIP-­‐2.    2011  result:  Goal  not  met.  While  attendance  at  one  meeting  is  known,  no  minutes  of  the  meeting  were  collected.  Since  then  lines  of  communication  have  improved  so  that  attending  members  receive  meeting  minutes.    BMP  2.2  –  Public  Involvement  (University  Neighbors)  UMW  is  in  regular  communication  with  local  neighborhood  associations  in  an  effort  to  keep  community  members  informed  of  campus  activities  such  as  construction  and  special  events.  University  officials  mail  newsletters  to  local  homeowners  and  are  in  turn  invited  to  attend  periodic  neighborhood  association  meetings.  UMW  will  provide  the  storm  water  brochure  (discussed  in  BMP  1.2)  in  at  least  one  newsletter  per  year.  UMW  administrators  will  solicit  comment  and  questions  concerning  storm  water  from  the  neighborhood  associations  at  least  one  annual  meeting  to  which  they  are  invited.  Measurable  Goal:  Record  of  annual  mailing  of  storm  water  brochure  and  each  meeting  in  which  storm  water  topics  are  discussed  with  neighborhood  associations.    2014  result:    Goal  met.  UMW  continues  to  provide  information  through  the  Sustainability  page  on  our  website,  and  the  Capital  Outlay  department  interacts  with  the  neighborhood  to  provide  updated  information  concerning  earth  disturbing  projects.    2013  result:  Goal  met.  UMW  has  provided  information  to  the  neighborhood  association  through  access  to  the  Sustainability  page  on  the  UMW  website  and  through  the  Town  &  Gown  meetings  held  on  campus  and  organized  through  the  UMW  President’s  office.  

Page 9: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  9  

 2012  result:  Goal  not  met.    2011  result:  Goal  not  met  as  no  neighborhood  association  meetings  were  known.    3.  Illicit  discharge  detection  and  elimination.  BMP  3.1  –  Staff  Training  Historical  data  indicates  that  the  University’s  front  line  service  employees  are,  by  nature  of  their  duties,  collectively  more  likely  to  observe  and  report  unusual  or  aberrant  conditions  than  any  other  constituent  group  on  the  University  grounds.  Consequently  all  grounds  and  maintenance  services  staff  will  be  provided  annual  training  to  allow  them  to  detect  and  eliminate  illicit  discharges.  This  training  will  be  provided  based  on  available  EPA,  DCR  and  other  authoritative  resources.    Measurable  Goal:  Record  of  annual  training.      2014  result:  Goal  met.  UMW  revisited  the  training  films  shown  in  2013.  We  are  looking  for  other  such  training  materials.    2013  result:    Goal  met.  UMW  Grounds  and  Housekeeping  staff  viewed  presentations  of  “Storm  Watch”  and  “IDDE,  Illicit  Discharge  Detection  and  Elimination”  distributed  by  EXCAL  Visual.      2012  result:  Continued  training  is  available  through  the  UMW  domain  of  the  VA  Knowledge  Center.    2011  result:  Annual  training  /  review  occurs  through  the  Knowledge  Center  Training  which  complies  with  training  requirements  for  state  agencies.    BMP  3.2  –  Campus  Community  Reporting    While  Facilities  Services  staff  is  most  likely  to  detect  illicit  discharges,  it  is  still  important  to  provide  reporting  mechanisms  to  allow  students,  faculty,  other  staff,  and  visitors  to  detect  and  report  illicit  discharges  or  suspected  discharges.  UMW  will  provide  reporting  guidelines  on  the  University’s  MS4  (storm  water)  program  web  site  for  this  purpose.  The  MS4  Program  Plan  brochure  (see  BMP  1.2)  will  also  provide  reporting  information.  The  campus  community  is  informed  of  the  web  site  via  the  employee  electronic  information  newsletter  or  other  electronic  notification.  Measurable  Goal:  Twice  yearly  announcements  via  electronic  means  (web  page  or  email).    2014  result:  Goal  met.  UMW  Capital  Outlay  continues  to  update  the  UMW  community  about  project  activities  that  may  disrupt  the  flow  of  normal  business.  These  activities  usually  include  earth  disturbing  activities  and  UMW  pointedly  speaks  about  contacting  Capital  Outlay  personnel  with  questions  and  concerns.    2013  result:  Goal  met.  UMW  continues  to  employ  an  E&S  inspector  certified  in  the  Commonwealth  as  our  primary  defense  against  illicit  discharges,  and  the  Sustainability  page  on  the  UMW  website  offers  UMW  community  guidelines  on  detection  along  with  a  reporting  avenue.  

Page 10: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  10  

 2012  result:    Goal  partially  met.  As  noted  in  previous  reports,  the  Capital  Outlay  department  employs  a  certified  E&S  inspector.  The  weekly  inspection  reports  are  provided  to  the  Facilities  Services  Vice  President  at  least  bi-­‐monthly  through  meetings  which  involve  heads  of  all  departments  within  Facilities  Services.  The  departments  represented  include  Capital  Outlay,  Landscape  and  Grounds,  and  Maintenance  and  Skilled  Services.  Reporting  guidelines  along  with  the  annual  summary  are  provided  on  the  program  website.    2011  result:  Goal  was  not  met.     The  Capital  Outlay  department  of  the  university  has  a  certified  E&S  inspector  among  its  members.  This  inspector  monitors  all  UMW  construction  sites  requiring  E&S  controls,  notifying  the  RLD  of  violations  and  monitoring  corrections.  This  practice  is  standard  across  all  three  campuses.    4.  Construction  site  stormwater  runoff  control.  BMP  4.1  –  Erosion  and  Sediment  Control  Authority  As  a  state  agency,  UMW  is  required  to  comply  with  the  statutes  and  regulations  of  the  Commonwealth  of  Virginia,  including  construction  requirements  as  reflected  in  the  Code  of  Virginia  and  implementing  regulations.  Erosion  and  Sediment  Control  plans  are  prepared  by  the  University  and  submitted  to  DCR  for  review  and  approval.  As  the  University  performs  almost  all  construction  via  contracted  services,  UMW  incorporates  appropriate  contractual  requirements  by  which  contractors  are  required  to  meet  the  conditions  of  the  approved  Erosion  and  Control  plans.  Measurable  Goals:  All  appropriate  projects  will  have  approved  ESC  plans.    2014  result:  Goal  met.  UMW  has  three  active  construction  projects  on  the  Fredericksburg  campus,  one  with  several  discrete  sites.  All  these  projects  have  separate  E&S  programs,  and  two  have  recently  updated  their  SWPPPP  programs  to  meet  the  current  Virginia  regulations.    2013  result:    Goal  met.  There  are  two  construction  projects  currently  active  on  UMW  campuses,  both  of  them  are  located  on  the  Fredericksburg  campus.  Both  projects  have  separate  E&S  programs  employing  on-­‐going  inspections  by  both  the  UMW  E&S  inspector  and  the  DCR  regional  inspector.    2012  result:    One  construction  project  has  begun  during  this  reporting  period,  along  with  an  electrical  utility  effort  to  upgrade  the  underground  supply  conductors  and  surface  level  transformers  throughout  the  Fredericksburg  campus.  The  two  construction  projects  reported  in  last  year’s  report  have  been  successfully  closed.    

The  inaugural  construction  of  the  Dahlgren  campus  was  completed.  SWPPP  was  successfully  closed  and  the  E&S  controls  have  been  superseded  by  permanent  BMP’s.  

There  were  no  construction  projects  involving  the  Stafford  campus.    2011  result:  Two  projects  were  completed  where  SWPPP  and  E&S  controls  where  maintained  per  DCR.  There  are  two  on-­‐going  projects,  the  SWPPP  and  controls  are  being  maintained  and  inspected  per  DCR.    BMP  4.2  –  Construction  Site  Operator  Training  

Page 11: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  11  

The  University  requires  that  all  land  disturbing  projects  provide  the  name  and  telephone  number  of  the  DCR  certified  Responsible  Land  Developer  (RLD).  The  RLD  information  is  maintained  with  the  official  contract  files  for  each  respective  project  and  made  available  to  DCR  staff  as  may  be  requested.    A  copy  of  the  land  disturbance  permit  is  also  required.  Measurable  Goals:  All  appropriate  projects  will  have  a  RLD.    2014  result:  Goal  met.  All  projects  maintain  and  update  their  RDL  certifications  as  necessary.    2013  result:  Goal  met.  Both  current  projects  maintain  current  RLD  certificates  at  their  respective  jobsite  offices.    2012  result:    Goal  met.  UMW’s  E&S  inspector  confirms  the  currency  of  each  RLD  certification.  The  certification  serves  as  evidence  of  the  site  operator’s  ongoing  training.    2011  result:  Each  RLD  maintains  a  copy  of  Certificate,  and  maintain  SWPPP  and  E&S  controls  per  DCR.    BMP  4.3  –  Staff  Training  UMW  will  ensure  that  site  inspections  are  conducted  by  a  DCR  certified  inspector.  Copies  of  certifications  will  be  maintained  by  the  Director  of  Capital  Outlay  for  the  University.  Measurable  Goal:  All  appropriate  staff  will  be  certified  as  required  by  Virginia  ESCL.    2014  result:  Goal  met.  UMW’s  E&S  inspector  maintains  current  certification,  has  attended  continuing  education  training  sessions,  and  is  seeking  the  most  current  Virginia  inspector’s  certificate.    2013  result:  Goal  met.  UMW’s  E&S  inspector  maintains  current  certification.    2012  result:  Goal  met.  Existing  projects  noted  in  the  previous  report  have  been  successfully  completed.  The  new  projects  at  UMW  Fredericksburg  are  being  handled  by  the  certified  E&S  inspector  as  prescribed  by  DCR.    2011  result:  Projects  with  E&S  Plans  are  being  inspected  by  a  certified  E&S  inspector  employed  by  the  university,  and  a  DCR  state  inspector.     For  the  reporting  period,  four  UMW  Fredericksburg  construction  sites  had  site  disturbance,  and  one  construction  site  at  UMW  Dahlgren.  The  sites  have  approved  E&S  controls  installed,  which  are  being  maintained  during  construction.      5.  Post-­‐construction  stormwater  management  in  new  development  and  re-­‐development.  BMP  5.1  –  Site  Monitoring  The  University  will  conduct  both  routine  as  well  as  event  generated  inspection  of  storm  water  runoff  for  a  two  year  period  following  completion  of  construction  or  redevelopment  work.  Grounds  maintenance  staff  will  inspect  sites  at  least  once  monthly  as  well  as  both  during  and  subsequent  to  major  rain  fall  in  order  to  ensure  that  constructed  storm  water  management  devices  are  working  as  designed  and  intended.  

Page 12: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  12  

Measurable  Goals:  All  designated  sites  will  be  inspected  monthly  for  the  first  two  years  following  completion  of  construction.    2014  result:  Goal  met.    The  Dahlgren  campus  has  now  exceeded  the  two-­‐year  monthly  inspection  period.  During  that  time  monthly  inspections  were  conducted  and  deficiency  reports  issued  as  necessary  to  correct  any  stormwater  issues  which  developed.    On  the  Fredericksburg  campus,  the  Battleground  Athletic  Complex  sports  turf  fields  moved  beyond  the  two-­‐year  monthly  inspection  period.    There  was  no  construction  activity  requiring  monitoring  at  the  Stafford  campus.     For  all  campuses,  BMP  devices  are  inspected  for  correct  function  within  48  hours  after  significant  weather  events.  BMP  devices  are  cleared  of  collected  debris.    2013  result:  Goal  met.  UMW’s  E&S  inspector,  and  separately  the  UMW  Grounds  Supervisor,  conduct  monthly  inspection  of  the  Dahlgren  campus  and  the  Fredericksburg  campus,  where  recent  projects  fall  within  the  BMP  parameter.  Additionally,  both  current  construction  and  general  campus  facilities  are  inspected  within  48  hours  of  major  storm  events.    2012  result:    Goal  met.  Both  the  UMW  E&S  inspector  and  the  Grounds  supervisors  conduct  reviews  of  stormwater  control  devices  within  48  hours  of  weather  events.    2011  result:  BMPS  were  monitored  as  required.  Re-­‐inspection  and  renewing  are  done  per  major  event  and  /  or  quarterly,  semiannual,  or  annually  as  required.    BMP  5.2  Records  Management  The  availability  of  accurate  utility  drawings  is  essential  for  staff  that  may  need  to  respond  to  illicit  discharges,  plan  for  new  facilities,  and  for  training  new  staff.  UMW  shall  maintain  accurate  and  detailed  drawings  of  all  storm  water  system  features.  Drawings  shall  be  updated  following  every  major  construction  project.  Measurable  Goals:  All  storm  water  system  components  shall  be  mapped  and  available  for  plan  review.    2014  result:  Goal  met.  The  policy  of  mapping  existing  utilities  and  stormwater  conveyances  through  construction  project  civil  work  continues  in  force.  System  changes  are  duly  recorded.    2013  result:  Goal  met.  Current  projects  are  required  to  map  existing  utilities  including  stormwater  conveyances,  and  record  any  changes  to  systems.    2012  result:  No  new  information  was  added  to  the  2011  result.    2011  result:  A  Geographic  Information  System  (GIS)  student-­‐intern  collected  information  including  location  and  pictures  of  stormwater  inlets  and  BMPs  on  the  Fredericksburg  Campus.     There  is  no  new  activity  to  report  during  this  cycle.    6.  Pollution  prevention  /  good  housekeeping  for  municipal  operations.    BMP  6.1-­‐  Nutrient  Management  Program  

Page 13: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  13  

In  accordance  with  DCR  requirements,  the  University  has  prepared  nutrient  management  plans  for  each  major  discrete  physical  area  owned  by  UMW.  The  university  is  committed  to  responsible  environmental  stewardship  and  will  maintain  turf  and  field  areas,  as  well  as  naturalized  areas  with  care  to  control  storm  water  runoff  of  chemical  and  biological  elements.  Measurable  Goals:  Campus  grounds  operations  shall  comply  with  approved  Nutrient  Management  Plans.    2014  result:  Goal  met.    The  University  continues  to  follow  the  prescribed  Nutrient  Management  plan.    2013  result:  Goal  met.  In  addition  to  review  of  and  compliance  with  the  Nutrient  Management  plan,  UMW  sponsored  Field  Days  for  the  Virginia  Sports  Turf  Managers  Association  in  June  2013.  The  two-­‐day  event  included  education  sessions,  one  of  which  was  specifically  focused  on  Nutrient  Management.    2012  result:  UMW’s  Division  of  Landscape  &  Grounds  limits  the  amounts  of  fertilizer  applied  to  its’  properties  and  utilizes  fertilizer  blends  with  no  Phosphorous,  meeting  and  or  exceeding  the  University’s  Nutrient  Management  Program.  All  fertilization  is  based  on  soil  tests.  UMW  received  certification  for  the  current  Nutrient  Management  Plan.    2011  result:  UMW’s  Division  of  Landscape  &  Grounds  limits  the  amounts  of  fertilizer  applied  to  its’  properties  and  utilizes  fertilizer  blends  with  no  Phosphorous,  meeting  and  or  exceeding  the  University’s  Nutrient  Management  Program.  

During  winter  weather  treatment,  no  snow  melting  chemicals  containing  urea  are  utilized.  Sand  alone  is  utilized  on  roadways  and  lots  (Fredericksburg  campus)  for  Snow  and  Ice  Management.    BMP  6.2  –  Recycling  Program  For  over  fifteen  years  the  university  has  operated  a  highly  effective  recycling  program  aimed  not  only  at  high  volume  materials  such  as  paper,  glass,  and  aluminum,  but  also  including  relative  low  volume,  but  equally  important  potential  pollutants  such  as  vehicle  batteries,  printer  cartridges,  and  fats/greases.  Measurable  Goals:  Maintain  or  improve  the  annual  amount  of  recycled  material.  Accurate  figures  are  not  available  on  monthly  or  annual  waste  amounts  so  accurate  comparisons  of  waste  to  recycling  are  not  possible.    2014  result:  Goal  met.  UMW  continues  to  dominate  Virginia  in  RecycleMania,  retaining  its’  #1  ranking.    Internationally,  UMW  is  now  ranked  #4.    2013  result:  Goal  met.  UMW  retained  its’  title  as  #1  in  Virginia,  and  climbed  to  12th  place  overall  in  the  RecycleMania  tournament.  Details  are  on  the  UMW  website,  Sustainability  page.    2012  result:  The  UMW  recycling  program  continues  to  be  comprehensive  in  its  collection  of  recyclables  and  encouragement  of  waste  reduction.  We  constantly  seek  new  avenues  for  communication  and  education.  The  recycling  program  has  expanded  with  the  addition  of  the  Anderson  Center,  opening  of  

Page 14: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  14  

newly  renovated  residence  halls,  and  a  new  satellite  campus  at  Dahlgren.  UMW  placed  18th  in  the  2012  Recyclemania  per  capita  contest  and  first    Virginia.      2011  result:  The  following  efforts  were  made  to  increase  effectiveness  of  the  recycling  program:    

• Office  Paper  and  Brown  Paper/Cardboard  is  source  separated,  marketing  of  Office  Paper  resulted  in  lower  costs  to  the  university  

• Reusable  mug  were  distributed  to  incoming  first  year  students    • New  graphic  signs  with  recycling  collection  information  were  designed  and  made  printable  from  

the  recycling  web  site  • Increased  communication  about  recycling  with  sustainability  coordinators  in  residence  hall  held  

monthly  meetings  • UMW  participated  in  RECYCLEMANIA  2010,  many  forms  of  media  were  used  for  publicity  

increasing  awareness  in  recycling  • Educational  sessions  were  held  with  Resident  Assistants,  Sustainability  Organizers,  Housekeeping  

Staff  • Outreach  session  on  recycling  and  Recyclemania  were  held  with  the  following  departments:    

Library,  Faculty  Senate,  Residence  Life,    Alumni  Executive  Center,  Admissions,  Academic  Services  ,  Banner  Users  Group,    Career  Services,  Foundation,  and  University    Advancement,  Registrar.  

 BMP  6.3  –  Waste  Management  Program  Along  with  the  recycling  efforts  of  the  University,  the  Facilities  Services  department  has  also  led  numerous  initiatives  to  minimize  waste  stream  of  hazardous  as  well  as  non-­‐hazardous  materials.  Wastes  are  segregated  and  handled  to  reduce  weight  (e.g.  allowing  waste  latex  paints  to  evaporate  water  vapor  prior  to  disposal  of  remaining  paint  solids)  as  well  as  for  reducing  waste  management  costs.  Measurable  Goals:  See  BMP  6.2    2013  result:  This  item  incorporates  information  found  in  BMP  6.2,  and  has  been  dropped  from  the  revised  MS4  Program  plan.    2012  result:    All  yard  waste  is  composted  and  used  on  site,  commercial  tree  companies  dump  chips  which  are  used  as  mulch  on  the  main  campus.  Education  of  res  life  staff,  first  year  students  and  ongoing  programming  with  students  has  waste  reduction  and  energy  conservation  component.  CFL  exchange  program  has  waste  reduction  component  due  to  long  life.    Hydration  stations  are  used  at  Move-­‐in  to  encourage  use  of  reusable  water  bottles  and  set  culture  of  reuse  on  campus.  2011-­‐12  Do  One  Thing  campaign  promoted  waste  reduction  through  individual  responsibility.      2011  result:    Approximately  400  yards  of  wood  chips  have  been  recycled  as  mulch.  Approximately  100  yards  of  leaves  and  yard  waste  have  been  composted  and  being  utilized  throughout  campus.  All  other  leaves  are  shredded  on  site  and  returned  to  the  soil  for  decomposition.  Logs  from  tree  operations  are  either  chipped  up  for  mulch  or  utilized  for  fire  wood  by  local  citizens.  Wood  products  in  natural  state  are  not  relegated  to  any  land  fill.  

Page 15: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  15  

 

Required  Section  IB9  information  1.  Copy  of  updated  MS4  Program  Plan  along  with  any  new  information  regarding  TMDL.     UMW’s  revised  (June  2013)  MS4  Program  Plan  is  found  in  this  document,  beginning  on  page  17.      2.  Estimate  of  the  cubic  foot  volume  of  stormwater  discharged,  and  the  quantity  of  pollutant  identified  in  the  WLA.    2014  Estimated  stormwater  totals,  utilizing  precipitation  observations  from  the  National  Weather  Service  at  Dulles  International  Airport,  totaling  42.20”.  Precipitation  distributions  across  the  three  university  campuses  are:     UMW  Fredericksburg  (170  acres):   194,802,796  gallons  /    26,041,346  cu  ft     UMW  Stafford  (48  acres):     055,003,142.4  gallons  /    7,352,851  cu  ft     UMW  Dahlgren  (28  acres):     032,085,166.4  gallons  /    4,289,163  cu  ft    2013  Estimated  stormwater  totals,  utilizing  precipitation  observations  from  the  National  Weather  Service  at  Dulles  International  Airport,  totaled  39.65  inches.    Precipitation  distribution  across  the  three  university  campuses  are:     UMW  Fredericksburg  (170  acres):   183,033,492  gallons  /  24,468,019  cu  ft       UMW  Stafford  (48  acres):     051,680,045  gallons  /  06,908,617  cu  ft       UMW  Dahlgren  (28  acres):     030,146,682  gallons  /  04,030,025  cu  ft      2012  Estimated  stormwater  totals,  utilizing  precipitation  observations  from  the  National  Weather  Service  at  Dulles  International  Airport,  totaled  41.76  inches.    Precipitation  distribution  across  the  three  university  campuses  are:     UMW  Fredericksburg  (170  acres):   192,773,700  gallons  /  25,773,844  cu  ft       UMW  Stafford  (48  acres):     054,430,221  gallons  /  07,277,321  cu  ft       UMW  Dahlgren  (28  acres):     031,752,132  gallons  /  04,245,260  cu  ft    2011  The  estimated  stormwater  for  the  period  was  28  million  cubic  feet,  most  of  which  was  discharged  from  the  site  through  the  established  stormwater  conveyance  systems.  Concerning  Waste  Load  Allocation,  UMW’s  permit  does  not  establish  an  individual  allocation.  

Illicit  Discharge  information    

2014:  The  Fredericksburg  campus  has  all  the  active  construction  sites.  Two  are  single-­‐site  projects  while  the  third  is  composed  of  seven  small  projects.  Three  permits  cover  all  the  projects,  and  E&S  measures  are  in  place  at  every  active  site.      

Page 16: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  16  

2013:  Only  two  projects  are  currently  active  across  all  three  UMW  campuses.  All  illicit  discharges  resulted  from  failures  in  E&S  controls.  All  discharges  were  documented  and  reported  by  the  E&S  inspector  to  the  appropriate  RLD,  and  corrections  were  made  within  the  allotted  correction  period.  

    2012  Four  of  UMW  Fredericksburg’s  five  projects  closed  during  the  reporting  period.  Of  those  projects,  

two  continue  to  deal  with  permanent  establishment  of  native  grasses  is  small  areas.  No  illicit  discharges  were  noted  after  removal  of  E&S  controls.    

    One  new  project  was  begun  on  the  UMW  Fredericksburg  campus.  E&S  controls  have  been  successfully  established,  and  no  illicit  discharges  have  been  observed.  

UMW  Dahlgren  project  completed,  with  all  illicit  discharge  issues  satisfactorily  resolved.       UMW  Stafford  had  no  projects.    

2011  Five  projects  were  active  on  the  Fredericksburg  campus  while  one  project  was  active  at  the  Dahlgren  campus.  Four  of  the  Fredericksburg  sites  suffered  occasional  E&S  failures.  These  failures  were  identified  within  the  prescribed  48-­‐hr  inspection  period  following  all  falling  weather  events.  The  Dahlgren  site  also  suffered  occasional  failures.  As  noted  at  the  Fredericksburg  campus,  these  failures  were  identified  within  the  prescribed  48-­‐hr  period,  reports  written  and  corrective  action  taken.  All  failures  were  corrected  by  the  RLD  within  the  prescribed  correction  period.  

 

Regulated  Land  Disturbance  Activities    

2014:  UMW’s  E&S  inspector  monitors  the  land  disturbance-­‐related  activities  for  the  active  construction  sites.  This  year  those  activities  were  confined  to  the  Fredericksburg  campus,  but  included  the  monitoring  of  short-­‐term  stockpiled  materials,  the  movement  of  soils  to  and  from  the  campus  through  truck  ticket  information,  and  the  inspection  of  E&S  controls  every  two  weeks.  Monitoring  and  reporting  includes  site  inspections  within  48-­‐hours  of  storm  events.  

 2013:  UMW  Fredericksburg  continually  monitors  the  activities  of  the  two  on-­‐going  construction  projects,  and  conducts  regular  inspections  at  two  week  intervals  of  these  projects  for  maintenance  of  E&S  controls.  Reports  are  issued  to  the  project  RLD’s  the  day  following  each  inspection.  

 2012  UMW  Fredericksburg  continues  to  monitor  permanent  grass  establishment  on  two  of  the  otherwise  completed  projects,  as  noted  in  the  previous  item,  Illicit  Discharge  Information.  Also  of  note  is  the  joint  effort  between  the  university  and  the  neighboring  National  Park  Service  along  their  joint  boundary.  The  work  includes  removal  of  an  established  bamboo  area  which  is  to  be  replaced  with  native  plantings.  This  work  is  expected  to  continue  through  the  fall  of  2012.  Finally,  work  has  begun  on  the  IT  Convergence  Center.  All  identified  and  necessary  E&S  controls  are  in-­‐place  and  being  properly  maintained.  

UMW  Dahlgren  continues  to  deal  with  small  areas  of  native  grass  establishment.  UMW  Stafford  had  no  land  disturbance  projects  during  this  period.  

   

Page 17: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  17  

2011  During  the  reporting  period,  UMW  Fredericksburg  had  four  regulated  land  disturbance  activities.  Appropriate  E&S  controls  for  surface  runoff  and  inlet  protection  were  placed  in  service  and  are  being  maintained  throughout  the  construction  period  at  all  sites.    The  active  sites  are  characterized  as:  1) New  building  construction  abutting  two  existing  structures.  Permanent  stormwater  management  

devices  are  being  retro-­‐fitted  to  accommodate  the  increased  impervious  area  of  the  project.    2) Roadway  re-­‐construction  without  previous  adequate  stormwater  management.  New  stormwater  

management  installations  control  the  discharge  from  the  re-­‐constructed  area  down  a  steep  slope  to  an  adapted  rip-­‐rap  plunge  pool    /    level  spreader.  

3) Dormitory  renovation  which  includes  stormwater  facilities  for  most  of  the  affected  site,  where  no  controls  or  filtration  previously  existed.  

4) Artificial  turf  renovations  of  two  natural  turf  fields.  These  fields  incorporate  the  very  good  drainage  characteristics  of  the  subsoil  to  advantage  by  eliminating  the  need  for  stormwater  drainage  devices  on  the  fields.  The  artificial  surface  allows  continuous  drainage  through  the  fabric  to  the  subsoil  where  the  water  percolates  away.  Fertilizers  are  no  longer  necessary.  

 UMW  Stafford  had  no  land  disturbance  activities  during  this  period.  UMW  Dahlgren  has  only  one  regulated  land  disturbance  associated  with  the  development  of  this  

campus  in  an  otherwise  undeveloped  area.  

Page 18: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  18  

Appendix  A  

Stormwater  Management  Facility  data  

Contech(StormFilter((Fredericksburg,(ITCC) 8.02((offsite)Concrete(Vault(Detention((Fredericksburg,(ITCC) 0.8

Bioretention(#3C((Dahlgren) 0.92Bioretention(#3D((Dahlgren) 1.01Bioretention(#3E((Dahlgren) 0.68

Bioretention(Pond(A((Dahlgren) 2.87Bioretention(#1G((Dahlgren) 0.42Bioretention(#1H((Dahlgren) 0.68

1.460.0452.149.723.07

Roof(Downspout(Infiltration((Woodard(Campus(Center)Detention(and(Filtration(system((MasonVRandolph)

Bioretention(Pond((Stafford(Campus)Bioretention(Area((Stafford(Campus)

Sand(Filter((Artificial(Turf(Field)Water(Quality(vault((Lee(Hall)

1.8512.210.841.65

3.47

0.721.260.681

5.39

2.74

Bioretention((Indoor(Tennis(Facility)Bioretention(Green(Alley((Indoor(Tennis(Fac)Infiltration(/(Poly(Chamber((Indoor(Tennis(Fac)Infiltration(Trench((Alumni(Executive(Center)

Underground(System((Sunken(Road(Parking)

Bioretention((Jepson(Science(Center)Retention((Jepson(Science(Center)

Bioretention((Sunken(Road)Water(Quality(vault((Parking(Garage)Extended(Detention((Arrington(Hall)

University*of*Mary*WashingtonPermit'Number: !VAR040094

Permit!Year!1!HUC:(RA46((((((((((((((((((((IMPAIRED'WATER:(Rappahannock(River

BMP*Type NO.*OF*ACRES*TREATED

             

Page 19: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  19  

           

Appendix  B      University  of  Mary  Washington    Facilities  Services  Policy  Directive  005  Policy  Name:  Storm  Water  Management    Date:   February  1,  2007,  rev.  June  2013        

I. PURPOSE    To  assure  that  University  operations  comply  with  best  practices  for  the  protection  of  storm  water  and  comply  with  the  MS4  Permit  VA040094.    

II. BACKGROUND    The  Virginia  Department  of  Conservation  and  Recreation  (DCR)  is  tasked  with  regulation  of  discharges  of  contaminates  from  businesses  and  industry  to  surface  water.  The  majority  of  pollution  to  surface  water  now  comes  from  non-­‐specific  sources  such  as  pesticide  over-­‐applications,  motor  oil  from  poorly  maintained  vehicles,  and  run  off  carrying  animal  waste,  construction  sediment,  etc.  In  an  effort  to  address  this  type  of  pollution,  DCR's  storm  water  management  requirements  were  established  to  guide  municipalities  to  reduce  contamination  of  this  nature  and  to  educate  the  public  concerning  best  practices  to  protect  surface  water.  Procedures  to  identify  and  remediate  illicit  discharges  to  storm  water  systems  are  also  part  of  storm  water  protection  programs.    

III. POLICY    Under  this  policy  it  is  not  permitted  for  any  University  employee,  student  or  contractor  to  place  any  chemical  or  chemical  containing  solution  into  a  drain  that  leads  to  the  storm  water  system  without  prior  approval  from  Facilities  Services.    The  University  in  partnership  with  the  City  of  Fredericksburg  and  Stafford  County  is  committed  to  implementing  a  storm  water  management  program  that  addresses  the  four  areas  of  public  education  and  outreach,  public  involvement  and  participation,  illicit  discharge  and  removal,  and  construction  site  runoff  control.  

Page 20: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  20  

 The  University  will  complete  the  requirements  set  forth  in  the  permit  obtained  through  DCR  and  will  report  activities  as  required.    For  more  information  regarding  storm  water  management  or  to  view  permit  requirements  please  contact  Facilities  Services  at  654-­‐1047.    

Page 21: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  21  

MS4  Program  Plan  PUBLIC  EDUCATION  AND  OUTREACH  ON  STORM  WATER    BMP  1.1  –  EDUCATION    As  a  state  supported  institution  of  higher  education,  UMW  recognizes  the  value  of  both  formal  as  well  as  informal  education  and  supports  life-­‐long  learning  opportunities  for  the  citizens  of  the  Commonwealth  of  Virginia.  As  a  practical  effort  I  student  learning  and  community  education  the  University  will  annually  support  the  employment  of  a  student  position  to  work  approximately  150  hours  per  year  with  Facilities  Services  staff  in  support  of  education  and  outreach  regarding  the  university’s  environmental  stewardship  programs  including,  but  not  exclusively,  stormwater.  The  University  expects  to  hire  new  individuals  into  the  position  on  an  annual  basis.  Consequently  the  staff  in  Facilities  Services  will  endeavor  to  establish  discrete,  varying  annual  objectives  for  the  student  hired  into  the  position.  Sample  objectives:  update  and  revise  websites;  coordinate  with  student  clubs  such  as  the  Ecology  Club  in  project  development;  develop  materials  for  Residence  Life  staff  programs;  and  develop  project  that  may  be  integrated  with  local  jurisdictions  or  organizations  such  as  the  Friends  of  the  Rappahannock.    Policy:  The  Facilities  Services  department  will  endeavor  to  complete  the  annual  hiring  of  the  student  by  September  of  each  year.  As  a  part  of  the  hiring  process,  student  interest  and  ability  to  support  environmental  stewardship  programs  will  be  considered.  A  set  of  specific  objectives  will  be  defined  by  the  end  of  each  October.  During  the  following  April  the  student’s  efforts  will  be  evaluated  by  both  the  student  and  members  of  the  Facilities  Services  staff.  A  summary  report  shall  be  provided  to  the  AVP  for  Facilities  Services.    Responsible  Parties:  AVP  for  Facilities  Services  and  subordinate  staff  as  tasked.    Necessary  Documents:  Approved  budget  for  student  position.  Definition  of  annual  objectives.  Annual  evaluation  report.    Measurable  Goals:  UMW  will  promote  stormwater  awareness  through  the  UMW  website.  This  will  include  a  summary  statement  of  the  annual  evaluation  report.        BMP  1.2  –  Outreach      For  several  years  the  University  has  worked  jointly  with  local  organizations  including:  the  George  Washington  Regional  Green  Commission,  Fredericksburg  Clean  and  Green  Commission,  Friends  of  the  Rappahannock,  the  Rappahannock  Group  Sierra  Club,  Tri-­‐County  /  City  Soil  and  Water  Conservation  District,  Rappahannock  Regional  R-­‐Board,  and  Stafford  County.  Meetings  of  these  groups  cover  a  range  of  horticultural,  conservation,  and  environmental  topics,  provide  educational  and  outreach  opportunities  allowing  for  the  dissemination  of  informational  brochures.  UMW  shall,  at  least  once  annually,  provide  informational  brochures  concerning  stormwater,  the  University’s  MS4  Program  or  other  sustainability  related  topics  at  a  public  event.  

Page 22: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  22  

 Policy:  The  Facilities  Services  department  will  annually  prepare  a  brochure  for  distribution  at  events.    Responsible  Parties:  AVP  for  Facilities  Services  and  subordinate  staff  as  tasked.    Necessary  Documents:  MS4  Program  Plan  brochure.    Measurable  Goal:  Provision  of  brochures  at  designated  event.        PUBLIC  INVOLVEMENT  AND  PARTICIPATION    BMP  2.1  –  Public  Involvement  (Local  Jurisdictions)    The  University  has  endeavored  to  maintain  effective  communication  and  coordination  with  officials  both  in  the  City  of  Fredericksburg  and  in  Stafford  County.  Numerous  formal  and  informal  meetings  and  communications  are  exchanged  on  a  variety  of  topics  throughout  any  year.  The  University  will  specifically  include  storm  water  as  an  agenda  topic  at  least  once  annually  in  meeting  with  the  appropriate  administrative  staff  personnel  in  the  two  local  jurisdictions.    Policy:  UMW  will  comply  with  state  and  local  public  notice  requirements  for  stormwater  management  programs.    Responsible  Party:  AVP  for  Facilities  Services,  and  AVP  for  Enrollment  and  Communications.    Necessary  Documents:  MS4  Program  Plans  for  UMW,  the  City  of  Fredericksburg,  and  Stafford  County.    Measurable  Goal:  Record  of  each  meeting  in  which  storm  water  topics  are  discussed.      BMP  2.2  –  Public  Involvement  (University  Neighbors)  UMW  is  in  regular  communication  with  local  neighborhood  associations  in  an  effort  to  keep  community  members  informed  of  campus  activities  such  as  construction  and  special  events.  University  officials  mail  newsletters  to  local  homeowners  and  are  in  turn  invited  to  attend  periodic  neighborhood  association  meetings.  UMW  will  provide  the  storm  water  brochure  (discussed  in  BMP  1.2)  in  at  least  one  newsletter  per  year.  UMW  administrators  will  solicit  comment  and  questions  concerning  storm  water  from  the  neighborhood  associations  at  least  one  annual  meeting  to  which  they  are  invited.    Policy:  The  Facilities  Services  department  will  provide  copies  of  the  stormwater  brochure  to  the  President’s  Office  for  inclusion  in  the  newsletter  once  per  year.  The  department  will  also  provide  the  President’s  Office  with  a  form  for  recording  attendance  and  any  comments  or  questions  arising  from  the  neighborhood  meetings.  Department  staff  will  be  available  to  accompany  UMW  administrators  to  the  neighborhood  meetings  if  requested.  

Page 23: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  23  

 Responsible  Parties:  UMW  President’s  Office,  Vice  President  for  Administration  and  Finance,  AVP  for  Facilities  Services  and  subordinate  staff  as  tasked.    Necessary  Documents:  MS4  Program  Plan  brochure.    Measurable  Goal:  Record  of  annual  mailing  of  storm  water  brochure  and  each  meeting  in  which  storm  water  topics  are  discussed  with  neighborhood  associations.    

Page 24: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  24  

ILLICIT  DISCHARGE  DETECTION  AND  ELIMINATION    BMP  3.1  –  Staff  Training  Historical  data  indicates  that  the  University’s  front  line  service  employees  are,  by  nature  of  their  duties,  collectively  more  likely  to  observe  and  report  unusual  or  aberrant  conditions  than  any  other  constituent  group  on  the  University  grounds.  Consequently  all  grounds  and  maintenance  services  staff  will  be  provided  annual  training  to  allow  them  to  detect  and  eliminate  illicit  discharges.  This  training  will  be  provided  based  on  available  EPA,  DCR  and  other  authoritative  resources.    Policy:  UMW  will  provide  training  sessions  throughout  the  year  to  all  departments  within  Facilities  Services  to  reinforce  identification  and  reporting  procedures  for  illicit  discharge  elimination.  An  annual  summary  report  will  be  furnished  to  the  AVP  for  Facilities  Services.    Responsible  Party:  AVP  for  Facilities  Services,  and  department  heads  as  assigned.    Measurable  Goals:  Record  of  annual  training.      BMP  3.2  -­‐  Campus  Community  Reporting  While  Facilities  Services  staff  is  most  likely  to  detect  illicit  discharges,  it  is  still  important  to  provide  reporting  mechanisms  to  allow  students,  faculty,  other  staff,  and  visitors  to  detect  and  report  suspected  illicit  discharges.  Currently  the  campus  can  report  illicit  discharges  through  the  Work  Order  management  feature  of  the  Facilities  Services  website.    Policy:  UMW  is  committed  to  active  community  participation  in  identifying  and  remediating  illicit  discharge  to  the  stormwater  system.    Responsible  Party:  AVP  for  Facilities  Services  through  the  Landscape  and  Grounds  department.    Measurable  Goals:  Twice  yearly  announcements  via  electronic  means  (web  page  or  email).    

Page 25: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  25  

 CONSTRUCTION  SITE  STORMWATER  RUNOFF  CONTROL    BMP  4.1  –  Erosion  and  Sediment  Control  Authority  As  a  state  agency,  UMW  is  required  to  comply  with  the  statutes  and  regulations  of  the  Commonwealth  of  Virginia,  including  construction  requirements  as  reflected  in  the  Code  of  Virginia  and  implementing  regulations.  Erosion  and  Sediment  Control  plans  are  prepared  by  the  University  and  submitted  to  DCR  for  review  and  approval.  As  the  University  performs  almost  all  construction  via  contracted  services,  UMW  incorporates  appropriate  contractual  requirements  by  which  contractors  are  required  to  meet  the  conditions  of  the  approved  Erosion  and  Control  plans.    Policy:  UMW  will  regulate  and  monitor  construction-­‐related    land  disturbance  activities  through  its  Capital  Planning  and  Development  projects.    Responsible  Party:  AVP  for  Facilities  Services  through  the  Capital  Planning  and  Development  department.    Measurable  Goals:  All  appropriate  projects  will  have  approved  ESC  plans.    BMP  4.2  –  Construction  Site  Operator  Training  The  University  requires  that  all  land  disturbing  projects  provide  the  name  and  telephone  number  of  the  DCR  certified  Responsible  Land  Developer  (RLD).  The  RLD  information  is  maintained  with  the  official  contract  files  for  each  respective  project  and  made  available  to  DCR  staff  as  may  be  requested.    A  copy  of  the  land  disturbance  permit  is  also  required.    Policy:  UMW  requires  land  disturbing  contractors  be  certified  Responsible  Land  Developers  through  OCR.    Responsible  Party:  Director  of  Purchasing  and  Director  of  Capital  Planning  and  Development.    Measurable  Goals:  All  appropriate  projects  will  have  a  RLD.    BMP  4.3  –  Staff  Training  UMW  will  ensure  that  site  inspections  are  conducted  by  a  DCR  certified  inspector.  Copies  of  certifications  will  be  maintained  by  the  Director  of  Capital  Outlay  for  the  University.    Policy:  UMW  requires  that  E&S  inspectors  be  certified  through  the  Department  of  Soil  and  Water  Conservation.    Responsible  Party:  Capital  Planning  and  Development  department.    Measurable  Goal:  All  appropriate  staff  will  be  certified  as  required  by  the  Commonwealth  of  Virginia  ESCL.    

Page 26: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  26  

 POST  CONSTRUCTION  STORMWATER  MANAGEMENT    BMP  5.1  -­‐  Site  Monitoring  The  University  will  conduct  both  routine  as  well  as  event  generated  inspection  of  storm  water  runoff  for  a  two  year  period  following  completion  of  construction  or  redevelopment  work.  Grounds  maintenance  staff  will  inspect  sites  at  least  once  monthly  as  well  as  both  during  and  subsequent  to  major  rain  fall  in  order  to  ensure  that  constructed  storm  water  management  devices  are  working  as  designed  and  intended.    Policy:  UMW  will  require  revision  of  the  approved  Stormwater  Master  Plan  to  include  provisions  for  new  stormwater  management  features.    Responsible  Party:  Jointly  by  Capital  Planning  and  Development  department  through  the  project  warranty  period  followed  by  landscape  and  Grounds  department.    Measurable  Goals:  All  designated  sites  will  be  inspected  monthly  for  the  first  two  years  following  completion  of  construction.      BMP  5.2  -­‐  Records  Management    The  availability  of  accurate  utility  drawings  is  essential  for  staff  that  may  need  to  respond  to  illicit  discharges,  plan  for  new  facilities,  and  for  training  new  staff.  UMW  shall  maintain  accurate  and  detailed  drawings  of  all  storm  water  system  features.  Drawings  shall  be  updated  following  every  major  construction  project.    Policy:  UMW  shall  maintain  accurate,  detailed  drawings  of  all  stormwater  system  features.    Responsible  Party:  AVP  for  Facilities  Services,  and  department  heads  as  assigned.      Measurable  Goals:  All  storm  water  system  components  shall  be  mapped  and  available  for  plan  review.    

Page 27: University of Mary Washington MS4 General Permitadminfinance.umw.edu/facilities/files/2015/03/UMW_MS4-General-Permit... · University of Mary Washington MS4 General Permit Annual

University  of  Mary  Washington                        MS4  General  Permit  

 

  27  

 POLLUTION  PREVENTION  /    GOOD  HOUSEKEEPING  FOR  UMW  OPERATIONS    BMP  6.1  -­‐  Nutrient  Management  Program  In  accordance  with  DCR  requirements,  the  University  has  prepared  nutrient  management  plans  for  each  major  discrete  physical  area  owned  by  UMW.  The  university  is  committed  to  responsible  environmental  stewardship  and  will  maintain  turf  and  field  areas,  as  well  as  naturalized  areas  with  care  to  control  storm  water  runoff  of  chemical  and  biological  elements.    Policy:  UMW  will  maintain  nutrient  management  plans  for  each  major  discrete  physical  area  owned  by  UMW.    Responsible  Party:  Director  of  Landscape  and  Grounds.    Measurable  Goals:  Campus  grounds  operations  shall  comply  with  approved  Nutrient  Management  Plans.      BMP  6.2  -­‐  Recycling  Program  For  over  fifteen  years  the  university  has  operated  a  highly  effective  recycling  program  aimed  not  only  at  high  volume  materials  such  as  paper,  glass,  and  aluminum,  but  also  including  relative  low  volume,  but  important  potential  pollutants  such  as  vehicle  batteries,  printer  cartridges,  and  fats/greases.    Policy:  UMW  will  continue  the  current  recycling  program  and  add  new  components  based  on  need.    Responsible  Party:  Director  of  Landscape  and  Grounds    Measurable  Goals:  Maintain  or  improve  the  annual  amount  of  recycled  material.  Accurate  figures  are  not  available  on  monthly  or  annual  waste  amounts  so  accurate  comparisons  of  waste  to  recycling  are  not  possible.