university of missouri - * up to 5 safety points will …faculty.missouri.edu/~schumacherl/grain bin...

19
Agricultural Mechanics CDE Team Activity Exercise - Grain Bin Read First Your team will be expected to complete a number of activities today. They include the following. 1. Calculate amount of concrete and rebar required for specific grain bin. 2. Select the correct motor to provide power for the grain auger 3. Figure Bill of Materials for concrete foundation for specific grain bin. You will have 40 minutes to complete the activity. You will be given verbal warnings 10 minutes and 5 minutes remaining. You will be expected to turn in the following for evaluation. 1. Completed concrete and rebar calculations. 2. Completed electrical motor selection 3. Completed Bill of Materials for concrete foundation . Review the Scoring Rubrics to determine how your activities will be evaluated. Follow all safety precautions (safety glasses), appropriate safe practices of handling tools. Scenario: A farmer is planning to install a grain bin for use in drying grain crops. The producer has decided he wants a 30’ diameter bin to meet his needs. His local farm supply store is a SUKUP grain bin dealer.

Upload: others

Post on 15-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise

Agricultural Mechanics CDE Team Activity Exercise- Grain Bin

Read FirstYour team will be expected to complete a number of activities today. They include the following.

1. Calculate amount of concrete and rebar required for specific grain bin.2. Select the correct motor to provide power for the grain auger3. Figure Bill of Materials for concrete foundation for specific grain bin.

You will have 40 minutes to complete the activity. You will be given verbal warnings 10 minutes and 5 minutes remaining. You will be expected to turn in the following for evaluation.

1. Completed concrete and rebar calculations.2. Completed electrical motor selection3. Completed Bill of Materials for concrete foundation .

Review the Scoring Rubrics to determine how your activities will be evaluated. Follow all safety precautions (safety glasses), appropriate safe practices of handling tools.

Scenario: A farmer is planning to install a grain bin for use in drying grain crops. The producer has decided he wants a 30’ diameter bin to meet his needs. His local farm supply store is a SUKUP grain bin dealer.

Using this information and the charts below, complete the following tasks:1. Calculate amount of concrete required for foundation for specific

grain bin.2. Select the correct motor to provide power for the grain auger.3. Figure Bill of Materials for concrete foundation for specific grain bin.

Page 2: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise

ConcreteDirections: Please circle the appropriate answer or fill in the blank for each question. When you are finished please turn your sheet into one of the event officials. Remember to put your name, contestant number and chapter name at the top of this sheet. Not doing so will result in a zero for this section. If you have questions please feel free to ask.

* Up to 5 safety points will be deducted from your final score if necessary. Please wear your safety glasses and practice safe methods while competing in this activity.

Concrete ProblemsShow work for full credit, partial credit will be given for work shown. See the following page for illustrations for the following problems.

1. You are adding on to your grain storage facility. You are putting up a new grain bin and pouring the concrete yourself. See the back page for the dimensions and thickness for grain bin pad. You will be using a 6 sack mix. (Assume 10% waste factor)

(Concrete cost $105.00 yd3. delivered)

a. How many linear feet of rebar do you need to put in footing? (3 Pts)

b. How many square feet of wire mesh is need for the floor? (3pts)

c. How many cubic yards of sand are needed for a grain bin 6” above grade?(3pts)

d. How many cubic yards should you order to pour the grain bin pad? (3pts)

e. What is the total concrete cost for the grain bin? (3pts)

Page 3: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise

Foundation Preparation Recommendations

DISCLAIMER: Sukup Manufacturing Co. assumes no responsibility regarding the foundation specifications. This is not an engineered foundation and shall not be constructed as such. The specifications given are intended for quoting and estimating purposes only. It shall be the sole responsibility of the customer to obtain actual foundation drawings designed by and constructed to the specifications of a licensed professional structural engineer with knowledge of the actual soil and load specific to the project and location. Consideration should also include, but not be limited to, live loads, dead loads, wind loads, soil bearing loads, seismic zone, proper moisture run-off on top of base, and types of aeration applied for the project.

Sukup Manufacturing Co. will not be responsible for any damage to a product, including, but not limited to, any damage that results from poor soil conditions or inadequate concrete type, grade, bearing strength, and construction method. Soil bearing tests must be performed by a competent, independent, engineering firm. Concrete foundation construction must be done by a competent, concrete contractor.

Check local and/or regional building codes and regulations to ensure compliance.

Sukup Manufacturing Co. provides foundation data based on 3,000 psf bearing capacity.

All backfill material used in foundation preparations should be clean, crushed stone or sand/gravel mixture of a highly compactable material. Backfill should be layered up in 6” lifts and well compacted.

Concrete Specifications

Cement is to be Type 1 Portland Cement that conforms to ASTM C150.

Maximum aggregate size is to be 3/4 of minimum clear spacing between reinforcing bars and/or

wire mesh. Concrete must be 3,000 psi compressive strength at 28 days cured minimum.

Concrete is to be cured at 50°F and kept moist for a minimum of seven (7) days.

Foundation surface should not vary from level by more than 1/4” in 10 feet or more than 1/4” from specified elevation. Uneven surface may cause bin failure.

Elevation of surface above grade should not exceed 6”.

A beveled edge around foundation allows water to run off of surface.

Reinforcing Steel

Steel reinforcing bar (rebar) should conform to ASTM A615 or ASTM A617 and be Grade

60 or better. To properly size diameter of rebar for specific bin size, consult bin

specifications chart.

All circumferential bar laps should be 35 bar diameters and staggered by 3’ minimum.

All laps of circumferential bar (rebar) should be bound by either wire tie or welded. Number 6 (6” x 6”) wire mesh may be used. Overlap of wire mesh should be 6 inches minimum.

Page 4: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise

Anchor Bolts

Follow specifications on subsequent pages for appropriate size foundation and anchor bolts.

Foundation Construction Procedure

(Monolithic Type)

1. Determine center of foundation. Set a center stake. It can be anything from a simple 2” x 4” to a solid steel stake. In any case, a pivot point must be established from which outside radius can be marked.

2. Attach a straight 2” x 4” board or steel tube to center stake. Attachment must be two feet

longer than radius of bin. Adjust so bottom of board is same as desired height of floor surface. Attach so device can swivel 360 degrees unobstructed and remain at desired height. TIP: Use a stout enough device that can be used as a concrete leveler later when concrete is poured. See Fig. 4.

3. Determine radius of bin from center stake and mark on board or steel tube. Attach a second pointed stake to board so it can be used to scribe radius of bin foundation. See Fig. 5.

Page 5: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise

4. Dig footings for foundation per specifications given in foundation chart.

5. Place backfill using 6” lifts. Compact well. Board can be used to level backfill. Measure from bottom of board to determine proper thickness of floor, as specified.

6. Set forms, ensuring they are level and sturdy.

7. Lay steel rebar laterally into footings as specified. Follow overlap procedures outlined in Reinforcing Steelguidelines.

8. Lay steel wire mesh in floor area if specified.

9. Lay steel rebar radially in floor area if specified.

10. Wet sand/gravel and pour concrete.

11. Anchor bolts can be placed into concrete when concrete is wet or after concrete has cured. For wet concrete installation, follow instructions 12 through 14. Otherwise skip to 15.

12. Consult foundation specifications table for anchor bolt placement and chord dimensions.

13. Using center stake and scribe board, scribe anchor bolt radius into wet concrete. See Fig. 6.

14. Place foundation anchor bolts into concrete while concrete is workable.

15. Anchor bolts may be placed after concrete has cured by drilling holes on concrete and placing bolts with an anchoring adhesive material such as epoxy. Epoxy adhesive should comply with ASTM C881, two- component material suitable for use on dry and damp surfaces. All surfaces must be clean, dry and free of all dust and debris. Clearly mark all areas to be anchored.

Page 6: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise

Drill holes in concrete and inject epoxy adhesive according to manufacturer’s specifications. Insert anchor bolt fully into hole and remove excess adhesive. Rebar or plate cutters may be used accordingly when rebar is in the way. Inspect all anchor locations after adhesive has cured.

Page 7: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise
Page 8: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise
Page 9: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise
Page 10: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise
Page 11: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise
Page 12: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise
Page 13: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise

Electrical

In this section you will determine what type

Based off the chart below what size horsepower motor would required to achieve 2 cfm in 16 ft of graina. 10b. 20c. 30d. 40

Table 1 Air Flow Rates for Various Depths in a 30-Foot Diameter BinPower needed to deliver air flow thru grain depth of--

Air flow ------------------------------------------------------------- rate 10 feet 12 feet 16 feet 20 feet --------------------------------------------------------------------------cfm/bu

1.0 --- 2.5 hp 6.7 hp 14.2 hp2.0 7.1 hp 13.2 hp 36.2 hp 80.6 hp (16.0 cfm.sq ft) (19.2 cfm/sq ft) (25.6 cfm/sq ft) (32.0 cfm/sq ft)

3.0 --- 36.8 hp 103.5 hp ---------------------------------------------------------------------------------

According to the chart below what is the static pressure for the same grain scenario from previous questiona. 2.4b. 4.0c. 6.4d. 4.6

Page 14: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise

Figure 3. Grain depth vs. static pressure at selected air flow rates for bin drying shelled corn and soybeans

Using the previous static pressure measurement what style of fan would be recommended

Figure 4. Basic fan types for bin drying/cooling. (a) The vane-axial type has a propeller and vanes, and is best for static pressures under 4.0-4.5 inches of water. (b) The centrifugal type generally supplies more cfm per horsepower at static pressures over 4.0-4.5 inches of water and is often used where low noise level is desired

Practicum: Since the blower requires such high amperage you will need to wire in a magnetic switch (solenoid). The wires coming from the service entrance panel are labeled and the wires running to the dryer are labeled. Correctly connect the wires to the appropriate terminals.

Page 15: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise

Team Activity Scoring Guide

Points Possible

Points Awarded

I. Concrete and rebar

a. Rebar for footing 3

b. Wire Mesh for flooring 3

c. Cubic Yards of Sand 3

d. Cubic Yards of Concrete 3

3. Total Concrete cost 3

Sub-total 15

II. Concrete base

a. Correct outside base dimensions identified 5

b. Recommended mounting pad extension 5

c. Recommended riser tile size identified 5

d. Cubic feet of concrete calculated (+10%) 5

Sub-Total 20

III. Electrical and Solenoid wiring

a. Correct wires hooked to input side 6

b. Correct wires hooked to output side 6

c. Correct wrapping of wires on the terminals 6

d. Answers to electrical questions 6

e. Correct wires hooked to activation terminals 6

Sub-Total 30

IV. Work Habits, Safety, etc.

a. PPEs 5

b. Use of Tools 5

c.Teamwork 5

Sub-total 15

TOTAL 120

Page 16: University of Missouri - * Up to 5 safety points will …faculty.missouri.edu/~schumacherl/Grain Bin Team Activity... · Web viewAgricultural Mechanics CDE Team Activity Exercise