university of nairobi department of...
TRANSCRIPT
i
UNIVERSITY OF NAIROBI
DEPARTMENT OF MECHANICAL AND MANUFACTURING
ENGINEERING
PROJECT TITLE:
DESIGN OF THE PLUMBING SYSTEMS OF A
COMMERCIAL BUILDING USING COMPUTER AIDED
DESIGN SOFTWARE AND BUILDING INFORMATION
MODELING SOFTWARE
AUTHORS:
RAPHAEL MKIREMA F18/36570/2010
JOB OKETCH F18/35916/2010
MUINDI DOMINIC F18/35840/2010
PROJECT CODE: GON 02/2015.
PROJECT SUPERVISOR: ENG: G. O. NYANGASI
YEAR: 2014/2015
THIS PROJECT REPORT IS A PARTIAL FULFILMENT OF A
DEGREE COURSE INBACHELOR OF SCIENCE
(MECHANICAL AND MANUFACTURINGENGINEERING).
UNIVERSITY OF NAIROBI
ii
DECLARATION We declare to the best of our knowledge that this Final Year Project report to be submitted as
a partial fulfilment of the Bachelor of Science ( Mechanical and Manufacturing Engineering)
degree, to be our own original work and has not been presented in this or any other university
for examination, academic or any other purpose.
NAME: RAPHAEL MKIREMA
REG. NO.: F18/36570/2010.
SIGN: ……………………………….
DATE: ………………………………
NAME: JOB OKETCH
REG. NO: F18/35916/2010
SIGN: …………………………………
DATE: ……………………………….
NAME: MUINDI DOMINIC
REG: NO: F18/35840/2010
SIGN: ………………………………..
DATE: ………………………………..
SUPERVISOR:
This project has been submitted for examination with my approval as the university
supervisor.
ENG.G. O. NYANGASI
SIGN: …………………………………………
DATE: …………………………………………
iii
ACKNOWLEDGEMENT
Our sincere gratitude to those who helped us along the way in reaching our potential through
completion ofthis project.
We acknowledge ourindebtedness to our supervisor Eng. Nyangasi for his continued
assistance and encouragement in the exercise.
To our parents for the financial, moral and material support given to us; you are truly a
blessing. We also thank Godfrey Muhinda for the support he gave us during this time.
And to the general staff in the Mechanical and Manufacturing Engineering Department
University of Nairobi headed by Prof. J.M Ogola for the part they played.
To all these may the peace of God that surpasses beyond human understanding be with you
all.
iv
SUMMARY
The overall objective of this project is to design the plumbing systems of a commercial
building within the Central Business District with the use of Computer Aided Design (CAD)
software and Building Information Modelling software (BIM).
A complete detailed Architectural drawing was proposed by one of the student. The
plumbing codes which were used were in line with those used by the Ministry of public
works and Nairobi City Council. This was followed by selection of an appropriate water
distribution system. Indirect water distribution system was the best suited for our plumbing
system. Calculation of the Daily water demand was then done by determining the number of
people in the office building and multiplying the number, with the amount of water one
person uses per day. Pipe material selection was then done and Polypropylene Random
Copolymer. (PPR) was the best fit after comparing it to other pipe materials.
Pipe sizing was done using a simplified tabular procedure as described in BS6700 which is a
British Standard that specifies requirements for and gives recommendations on the design,
installation, alteration, testing and maintenance of services supplying water for domestic use
within buildings and their curtilages. It covers the system of pipes, fittings and connected
appliances installed to supply any building. The tabular method uses a worksheet which is
completed using a simple pipe sizing procedure.
The modern approach involves gathering all the details concerning the project These details
are in the form of the project name, the owner of the project, the owner‟s project number, the
project address, the project description and the areas to be modelled. Integrated Project
delivery method was then selected because it brings together expertise of different
department and enables them to work together towards a common goal.
The drawing plans were prepared and a 3D model of the Architectural plans was drawn.
The Water Distribution system used in BIM was borrowed from the Traditional Approach,
this was followed by insertion of appropriate fixture units, standard values for the fixture
variables in the model. Pipe sizing was then done using the software and a pressure loss
report generated.
The sanitary piping system, three discharge systems were put into consideration and these
were; combined system, separate system and partially separate system. Combined system
whichuses a single drain to convey foul water from sanitary appliances to a shared sewer. The
system was selected since it is economical to install. Sanitary fixtures were assigned for each
fixture with the help of Building Service handbook; WCs- (14), WHB- (3) and Urinals-(0.3).
Sizing of the pipes was done using the discharge unit method which involves calculation of
the peak flow rate using the discharge units and converting the discharge units to flow in
litres per second using charts of flow rate (l/s). The calculated value was then used to obtain
the pipe diameter. This process was done for both the two sides of the pipe sizing diagram
and the size of the discharge stack pipe was obtained as 100mm. In selecting the pipe
material, characteristics of various pipe materials were viewed and U-PVC was selected since
it met the design requirements and specifications.
v
Design of pumps involved selection of the type of pump system determined as open system,
selection of the type of pump to supply water from the underground tank to the reservoir tank
on the roof. This was followed by selection of the type of power supply for the pump
considering both electrical and diesel engine. The Sizing of the pump was done by
determining the total pressure head to be overcome by the pump, Net positive Suction Head
Available (NPSHA) and the discharge flow rate required. Correct pump installation involved
determining the power required to run the pump as well as the output that will be generated
by a given pump.
The above objectives were met in both the two approaches and we came up with the
following conclusion: After the completion of design using the two approaches, Building
information modelling was found to have the following benefits over AutoCAD: improved
efficiency, improved integration and coordination hence less problems on site, increased
understanding and predictability therefore offering greater certainty and reduced risk. Lastly
the model saves time and renders extra coordination thus the information generated from the
model leads to fewer errors that are caused by inaccurate and uncoordinated information.
These factors are well elaborated under discussion.
vi
LIST ABBREVIATION.
WC – Water closet.
WHB – Wash Hand Basin.
NPSA – Net Positive Suction Head Available.
NPSH – Net Positive Suction Head.
PPR - Polypropylene Random Copolymer
PVC – Polyvinyl Chloride.
DU – Discharge Unit.
vii
Table of Contents CHAPTER ONE - INTRODUCTION ...................................................................................................... 1
1.1 BACKGROUND OF THE PROJECT .................................................................................... 1
1.2 STATEMENT OF THE PROBLEM ...................................................................................... 2
1.3 OBJECTIVES OF THE PROPOSED PROJECT ................................................................... 2
1.3.1 Overall Objective ............................................................................................................ 2
1.3.2 Specific Objectives .......................................................................................................... 2
1.4 JUSTIFICATION OF THE PROJECT ................................................................................... 3
1.5 SCOPE OF THE PROJECT ................................................................................................... 3
1.6 LIMITATIONS OF THE PROJECT ...................................................................................... 3
1.7 ASSUMPTIONS ..................................................................................................................... 3
1.8 REQUIREMENTS FOR THE PROJECT .............................................................................. 3
CHAPTER TWO – LITERATURE REVIEW ........................................................................................... 5
2.1 The Traditional Approach. ...................................................................................................... 5
2.2 Design using Building Information Modelling. ...................................................................... 6
CHAPTER THREE – PLUMBING SYSTEM DESIGN USING TRADITIONAL APPROACH. .............. 7
3.1 Selection of a complete detailed Architectural drawing. .................................................... 7
3.2 Plumbing Engineering codes and standards of practice .................................................. 15
3.3 Cold water piping system design ...................................................................................... 15
3.4 Sanitary Piping System Design. ........................................................................................ 39
3.5 Pumps Design for the Plumbing System. .......................................................................... 46
3.6 Pump Installation. ............................................................................................................. 52
CHAPTER FOUR – PLUMBING SYSTEM DESIGN USING BUILDING INFORMATION
MODELLING. ....................................................................................................................................... 58
4.1 Design using Building Information Modelling (BIM). ...................................................... 58
4.2 Selection of a complete detailed Architectural drawing ................................................... 58
4.3 Plumbing Engineering codes and standards of practice .................................................. 58
4.4 Project initiation using Revit Software. ............................................................................ 58
4.5 Project delivery method selection. .................................................................................... 59
4.6 Preparation of the modelling plans................................................................................... 60
4.7 Design of the Cold water piping system. ........................................................................... 63
4.8 Design of the Sanitary piping systems .............................................................................. 72
viii
CHAPTER FIVE – FINAL LIST OF THE DESIGN SPECIFICATIONS. ............................................. 77
5.1 DRAWINGS ..................................................................................................................... 77
5.2 INSPECTION AND TESTING OF MATERIALS .......................................................... 77
5.3 METRIC CONVERSION ................................................................................................. 77
5.4 MATERIALS .................................................................................................................... 77
5.5 SECTION-1 ...................................................................................................................... 78
5.6 SECTION -2 ..................................................................................................................... 79
5.7 SECTION 3 ....................................................................................................................... 80
5.8 PUMPING SYSTEM SPECIFICATION. ........................................................................ 80
CHAPTER SIX – QUANTITY ESTIMATION OF THE DESIGN. ......................................................... 82
6.1 QUANTITY ESTIMATION USING TRADITIONAL APPROACH. ................................... 82
6.2 QUANTITY ESTIMATION USING BUILDING INFORMATION MODELLING (BIM)
APPROACH. ................................................................................................................................. 87
CHAPTER SEVEN – DISCUSSION. .................................................................................................... 92
7.1 EVALUATION AND COMPARISON ............................................................................ 92
CHAPTER EIGHT – CONCLUSION ................................................................................................... 97
APPENDIX A - MODDY CHART. ........................................................................................................ 98
APPENDIX B – QUANTITY SCHEDULES BUILDING INFORMATION MODELLING. .................. 99
APPENDIX C - AUTOCAD DRAWINGS WATER SUPPLY. ............................................................ 113
APPENDIX D - AUTOCAD DRAWINGS DRAINAGE. ..................................................................... 114
APPENDIX E - BIM DRAWINGS WATER SUPPLY AND DRAINAGE. ........................................... 115
RECOMMENDATIONS ...................................................................................................................... 116
REFFERENCE. ................................................................................................................................... 117
1
CHAPTER ONE - INTRODUCTION
1.1 BACKGROUND OF THE PROJECT
The building construction industry in Kenya is a relatively growing industry and is one of the
pillars to Kenya‟s vision 2030 realization of a 10% GDP growth. The industry is bound to
expand as Kenyans have seen the growing need to come up with buildings for various
purposes such as areas of residence, hotels, offices, recreational malls, hospitals, libraries
e.t.c. These needs are met by the professionals in the industry namely the architects,
engineers, contractors and sub-contractors.
The engineers play a big-role in the building life-cycle which involves planning, design,
construction, operation and maintenance of the building. The foundation of this cycle is seen
in the design stage. The design stage involves several manual calculations that are
centredaround codes and standards of practice. The end result of the design stage is design
specifications and their conversion into detailed drawings. Computer Aided Design software
in the form of AutoCAD, was invented in order to produce these detailed drawings. The use
of Computer Aided Design software has been in use for several years ever since its inception
in the 1980‟s. Nowadays, clients have become increasingly demanding and projects have thus
become more complex. Computer Aided Design software, which is mostly in 2D format, is
not enough to do this. New software in the form of Building Information Modelling has been
created to replace the CAD processes.
Building Information Modelling (BIM), is a revolutionary technology that offers a new way
to design, document and procure buildings. It involves the creation of 3D model-based
buildings. These models, initially designed by the architect, are used by the other major
disciplines such as the engineers, contractors and sub-contractors, to carry out their own
designs and virtual installations of elements in the building. In the design stage, engineers can
carry out analysis that provides them with the necessary information to guide them towards
making intelligent design decisions. Design specifications are generated and detailed
drawings produced. The scheduling and quantity take offs can then be done once the
drawings and specifications are produced. These models are not only used for design
purposes, but also for visualization, simulation and collaboration purposes. The models are
also relied upon as a source of project information on the physical aspects of the building.
BIM enhances the design process for a mechanical consulting engineer by giving him/her the
ability to carry out analysis and visualize designs in 3D. The elements for plumbing can be
designed, sized and visualized as they are installed in the building. It is possible to make
alterations digitally while working in close coordination with the mechanical sub-contractor.
This new approach to building construction has brought about increased co-ordination
between disciplines; early conflict detection and resolution; and an easier way to
communicate changes in building plans from one discipline to another and thus enable
changes on previously designed drawings to be made (change propagation). The 3C‟s, co-
ordination, conflict detection and change propagation makes BIM the software of choice as it
2
overcomes all the previous hurdles that Computer Aided Design software e.g. AutoCAD,
could not overcome.
The need for professional engineers to shift from the traditional Computer Aided Design
software to Building Information Modelling software is imperative to the growth of a
building construction industry aimed towards producing safe, sustainable, durable, time-
saving and economical designs for buildings.
1.2 STATEMENT OF THE PROBLEM
Design in the building construction industry is a stage that enables the complete realization of
any building. Engineers involved in design do their work with utmost care and thus produce
buildings that are long-lasting and safe. The advent of computer technology is assisting these
professionals in performing their duties and also given them the ability to design buildings
economically.
Computer Aided Design software has met the design needs of many in the building
construction engineering profession and has stood at the forefront in design. Software
technology, such as CAD, continues to move forward rapidly. This rapid forward movement
will inevitably give birth to new and improved methods to meet client needs such as Building
Information Modelling. As a result, CAD will be placed on the backseat as new approaches
to design are adopted. The continued use of CAD in the building construction industry will
soon be phased out. Those that will be stuck with the old ways of design may be rendered
jobless for their inability to adopt these new methods. The same individuals will also fail to
realize the benefits that the new methods will have.
1.3 OBJECTIVES OF THE PROPOSED PROJECT
1.3.1 Overall Objective
To design the plumbing systems of a commercial building within the Central Business
District with the use of Computer Aided Design software and Building Information Modeling
software.
1.3.2 Specific Objectives
1. To identify and select the architectural drawings to be used in the design.
2. To conduct an analysis for the Plumbing system.
3. To generate specifications of all the elements in the system.
4. To create detailed drawings describing all the elements and their locations in the
building.
5. To compare and contrast the use of CAD and BIM software approaches to design.
6. To illustrate the benefits of the Building Information Modeling process in
construction.
3
1.4 JUSTIFICATION OF THE PROJECT
The project will provide the student with knowledge on the building construction industry
and the role the mechanical engineer plays in his/her everyday professional job. The project
further exposes the students to the technological advancements in use in the industry such as
Building Information Modelling and its impact on the engineering planning and design
process.
This project will enable the students of Mechanical engineering to clearly demonstrate the
benefits that Building Information Modelling has over the traditional Computer Aided Design
approach. Some of the benefits that will be seen are:
1. Improved communication and collaboration among all project team members.
2. Fewer problems related to overruns in cost, schedule, and scope, or quality concerns.
3. The ability to reliably deliver projects faster, more economically, and with reduced
environmental impact.
1.5 SCOPE OF THE PROJECT
The main area of concern of the project is designing of the plumbing system of a commercial
building within the Central Business District using Computer Aided Design software and
Building Information Modelling software.
For the design process we required the following:-
a) 2D AutoCAD software.
b) 3D Building Information Modeling software ( Autodesk Revit ).
c) Detailed Architectural drawings.
1.6 LIMITATIONS OF THE PROJECT
The design stage for the project is limited to the knowledge gained by fellow students that
had the opportunity to go for attachment and secondary sources of information such as books
and websites on the internet.
1.7 ASSUMPTIONS
The use of Building Information Modelling software is yet to take full flight in the building
construction industry in Kenya. Those that have done so are yet to use the software to meet
their project needs and fully realize the benefits that it has.
1.8 REQUIREMENTS FOR THE PROJECT
The following requirements have been put in place for the successful completion of this
project:
1. A copy of a complete detailed architectural drawing for a commercial building. A carefully selected and complete architectural drawing is used for the design purposes
of the project. The drawing was proposed by one of the students and will be used for
design and detailing of the plumbing system.
4
2. Plumbing engineering codes and standards of practice.
Documents on the codes and standards of practice were carefully researched on,
retrieved and stored. Design of the system is in accordance to these standards.
3. Design software
The two design software that will be used are:
a. Autodesk AutoCAD 2014/2015 – Students version
Primary purpose of the software is to meet the detailed drawing requirements of the
project.
b. Autodesk Revit 2014 – Students version
It will be used on a broader spectrum that will involve project planning, modelling,
design, analysis, scheduling, cost estimation and optimization.
The above software serves as tools of communication. They are only present to meet the
project goals and objectives and are not meant to overtake the main design intent of the
project.
5
CHAPTER TWO – LITERATURE REVIEW
A plumbing system is a long-term investment, and should be so designed that it does
not become outdated and need replacement while its major parts are still serviceable. This
requires careful estimation of current and future demand so that the correct capacity can be
specified.
The capacity and dimensions of component parts in a plumbing installation should be
adequate to meet both immediate needs and anticipated future use. Due to this reason there‟s
a dire need to comeup with the best Design approach for a plumbing system in order to
establish efficient, safe and affordable installation.
The Project aims to help decide on the best design approach so as to achieve a good
plumbing design system.
The plumbing design process was tackled from two directions. These are namely:
The Traditional approach whereby design, analysis, scheduling and quantity
estimation is done manually and the final detailed drawings to communicate the
design are done with Autodesk AutoCAD.
The Building Information Modeling approach in which a 3D virtual architectural
model is created and from which design, analysis, scheduling and quantity estimation
is done. The final detailed design is communicated via this model which relays this
information through 3D virtual installation of the ventilation system design. Detailed
2D drawings are also created for proper documentation of the design.
Upon completion of these two stages, two final lists of the design specifications will be
presented which correspond to the two stages of the design process. These lists will be used
in the evaluation and comparison of the two processes.
2.1 The Traditional Approach.
The plumbing system design that is carried out in industry mainly constitutes of a number of
commonly used steps that were adopted in this project in order to fulfill the process. For this
stage, the steps listed were as follows:
Selection of a complete detailed architectural drawing.
Acquisition of the Plumbing Engineering codes and standards of practice.
Design of cold water piping system
Design of sanitary piping system
Design of pumps for the plumbing system
Final detailed drawing of the plumbing system Layout.
List of design specifications.
6
2.2 Designusing Building Information Modelling.
On completing the Traditional approach we went to the next phase, that is the design of the
plumbing system using building information modelling software. In this stage of the design,
various methods that were used earlier in the traditional approach were borrowed as they
proved useful in enhancing the BIM process. Building information modelling software was
revealed as a semi – automated software that brings together both the human mind and the
computer software to achieve the design goals. The following is a detailed methodology that
was followed in this new design process:
Selection of a complete detailed Architectural drawing
Acquisition of Engineering codes and standards of practice
Initiation of project using Autodesk Revit Software
Selection of an appropriate project delivery method
Preparation of the modeling plans
Design of the cold water piping system
Detailed design drawing of the plumbing system
Scheduling and quantity take offs of the system
List of the design specifications
7
CHAPTER THREE – PLUMBING SYSTEM DESIGN USING
TRADITIONAL APPROACH. This design approach mainly entails manual computations and was done in as per the
following listed procedure:-
3.1 Selection of a complete detailed Architectural drawing.
An architectural drawing of a commercial building was proposed by one of the
students. The drawing chosen, was fairly simple enough as to design an appropriate plumbing
system that can meet the requirements of the building.For this project, the type of commercial
building was an office building located within the Central Business District. It was assumed
that the client was the University of Nairobi and that the building was within the university
premises. The architectural drawings chosen lacked information on the construction materials
used and specifications, and the structural details. Due to this lack of information it was
mandatory for us, the students, to come up with this information based on common practices
in building construction industry. As a result, several assumptions on the construction
material, electrical specifications and structural information were made. The Architectural
drawings were in softcopy CAD format.
15
3.2 Plumbing Engineering codes and standards of practice
This involved gathering of all the information concerning the codes and standards of
practice in use. These codes chosen were in line with those used by the Ministry of
public works and Nairobi City Council.
3.3 Cold water piping system design
3.3.1 Selection of the appropriate water distribution system
In the design of this piping system, we first selected the appropriate water distribution
system. There two distinct Water Distribution systems for cold water supply.
a) Direct Water Distribution System.
b) Indirect Water Distribution System.
Direct Water Distribution System.
In this system, all the cold water in a building is fed „directly‟ from the supply main. The
water pressure is usually high at all outlets, so this system can have the disadvantage of being
more prone to water hammer.
Advantages of Direct System.
The cold water cistern is required solely to feed the hot water cylinder, and for
this reason need only have the same capacity.
Drinking water may be obtained at the wash hand basin taps which in hotels is
an advantage.
There is a suitable saving in pipework especially in multi-storey buildings.
This is due to the rising main supplying all the fittings, and a cold water
distribution pipe from the cistern being omitted.
Disadvantages of Direct System.
There is a danger of foul water from the sanitary fittings being siphoned back
into the main water.
There is a tendency to have more trouble with water hammer due to points
being connected directly to the main.
During peak periods there is a tendency for the lowering of pressure and with
buildings on higher ground a possible temporary loss of supply. If there is a
mains burst there is no store of water.
16
Indirect Water Distribution System.
In this system, only one draw-off point (i.e the kitchen sink) is fed from the mains supply
pipe. All other outlets are supplied via a cold storage cistern, usually located in the roof
space. Water pressure is usually much lower than with the direct system.
Advantages of an Indirect System.
There is no risk of back siphonage with this system.
There is no tendency of water hammer due to the low pressure in the pipe
work.
Should there be an interruption in the main supply there is an adequate store of
cold water.
Disadvantages of an Indirect System.
Longer pipe runs are required.
A larger storage cistern is necessary.
Drinking water is only available at the kitchen sink.
3.3.2 Design of the water distribution system.
Fig 3.2Indirect and Direct water distribution systems.( Reference : 9)
17
From the comparison between the two types of distribution system, Indirect Water supply
system was the system we found fit and economical for our commercial building.
The suitable design for our building‟s Indirect supply system is :-
Fig 3.3 A diagram showing the suitable Indirect supply system.(Reference : 9)
3.3.3 Calculation for the Daily Water Requirement for the Building.
Daily water requirement for the building depends on several factors :-
Type of Building and its function.
Number of occupants, permanent or transitional.
Typical appliances using the cold water (i.e Water closet cistern, wash basin,
bath, shower, sink, washing machine, dishwasher, Urinal flushing cistern.)
This building being a commercial building (Office Building) , there are several assumptions
we made towards its daily operation.
i. The building will operate for 10 Working hours (8:00am – 6:00pm)
ii. From the Architectural Drawing the building had no kitchen.
iii. The building has no canteen.
Determination of number of Occupants in the building.
Determining the number of people expected to use a facility at a single point in time involves
estimating not just employees, but customers and visitors as well. In ideal situations, the
actual or intended number of people for which a facility is designed would be known.
However, many buildings are constructed without specific number of occupants in mind, and
the use of the site remains unknown until a tenant is found.
18
Given the lack of measurable occupancy numbers, we found two ways that can be used to
determine the number of people in a proposed development as explained from (HWD
Appendix D Methods for Determining Concentration of People).
Parking Ordinance: The number of people present in a given area can be
calculated based upon the number of parking spaces provided. Some assumption
regarding the number of people per vehicle needs to be developed to determine
the numberof people on –site.
Maximum Occupancy:In this criteriona chart is provided indicating the required
number of square feet per occupant. The number of people on site can be
calculated by dividing the total floor area of a proposed use by the minimum
square feet per occupant requirements listed in the chart.
From our Architectural Plans and having measured the floor areas, Maximum Occupancy
was the best criterion to determine the occupancy of the building.
The measured Total Office Area in the Whole Building = 1446.735m2
According to Building Services Handbook by Fred Hall & Roger Greeno (page 59, Fig C
below)
For an office:- 1 person occupies 10m2 net Floor Area.
19
Fig 3.4: Cold water storage data.( Reference : 8)
Number of all occupants in the building =Total Floor Area.
(Effective Population) Net floor Area per person.
=2
2
10
735.1446
m
m= 144.67 145 people.
The Effective Population = 145 people.
Design Population:- The population figure is obtained by multiplying the effective-
population figure by the appropriate capacity factor.
Capacity Factor:- This is the multiplier which is applied to the effective population figure to
provide an allowance for reasonable population increase, variations in water demand,
uncertainties as to actual water requirements, and for unusual peak demands whose
magnitude cannot be accurately estimated in advance.
20
Design Population = Effective Population x Capacity factor.
= 145 x 1.5
= 217.5
The next step was to obtain amount of water one person uses per day.
On the same book (Building Services Handbook) and page (i.e. pg 59) highlighted above, it
clearly states that, an office with no canteen, a person uses 40litres of Water in 24hours.
Our commercial building operates for 10 hours as stated in the assumptions made. Therefore
the number of litres a person uses for 10 hours is:-
40litres = 24hours
?? = 10hours
litres67.1624
1040
17 litres/person/day.
The Daily Water Requirement is:-
217.5 x 17= 3697.5litres
The Daily Water requirement for the building is 3697.5litres.
Volume Analysis of the Tanks.
From the daily water demand, we calculated the volume of the roof tank and the underground
tank as follows:
Our roof tank was to have the capacity to supply the building for three days without a refill.
This is a common standard measure used. Therefore:-
Volume of Roof Tank = Daily water demand × No. of Days.
= 3697.5 × 3
=11092.5 litres. ≈ 12000 litres
From our building structure having a 12000 litre tank point load at the roof couldn‟t be safe
we decided to distribute the load to two tank of 6000 litre capacity.
A 6000 litre capacity tank was available from “ROTO TANKS” company as seen from their
tanks catalogue thereby supporting our choice.
For Our Underground tank we also made a commonly used assumption that the volume of the
this tank should be three times the volume of the roof tank, therefore;
Volume of the Underground Tank = 3 × Vol. Of Roof Tank.
= 3 × 12000
= 36000 litres.
Both tanks were drawn using Autodesk Inventor software and exported to Revit software
where they were positioned at their specified location as per the architectural drawings.
3.3.4 Products and materials used in Plumbing.
The durability of a plumbing system is dependent on the quality of its component parts
and the assembly skills of those who install it. No plumbing system, however well designed,
21
can be expected to operate safely or hygienically if the products or materials used are
unsatisfactory.
All pipes, valves, taps and other fittings used for the supply of drinking-water or the
removal of wastewater, must not contain harmful substances above the specified amount that
could leach into the water. Lead, cadmium and arsenic are examples of many possible
contaminants that could be present.
Due to this, pipe material selection is very important.
Pipe material selection.
There several factors to be considered in the selection of pipe material, this includes:-
1. Effect on water quality.
2. Cost, service life and maintenance needs.
3. For metallic pipes, internal and external corrosion.
4. Compatibility of materials.
5. Ageing, fatigue and temperature effects, especially in plastics.
6. Mechanical properties and durability.
7. Vibration, stress or settlement.
8. Internal water pressure.
The commonly used pipe materials are :-
Copper (BS EN 1057)
Galvanised iron (GI) with PVC-C lining (BS 1387)
Stainless steel (BS 4127)
PVC, unplasticized PVC, PB, PE ,PE-X
Polypropylene Random Copolymer. (PPR)
Classification of pipe materials.
Metallic:- 1. Copper
2. Stainless steel.
Thermoplastics:-1. Polyethylene (PE)
2. Medium Density Polyethylene (MDPE)
3. High Density Polyethylene (HDPE)
4. Cross linked Polyethylene. (PEX)
5. Polypropylene Random Copolymer. (PPR)
Composite: -1. Lined Galvanised Steel.
2. High Density Polyethylene (HDPE)
Polypropylene Random Copolymer. (PPR) is the pipe material we decided to use for
our project, we arrived at this choice of material after comparing it to the other pipe
22
materials and found PPR as fit and best for our cold water supply as explained and shown
on the table below:-
Presently PP-R pipes and fittings are most reliable in plumbing and water supply plants,
due to their chemical features and fusion welding, which ensures the plumbing to have a
perfect seal tight system.
Approved by the health Organisation, Eco-friendly Quality, Temperature Resistance
Quality etc, puts PP-R pipes and fittings as the best selection.
The Salient Features for PP-R:
Extremely long life, 50yr, service life.
Convenient and reliable installation.
Good chemical resistance.
No calcification.
Unique and un-rivaled jointing technique with lifetime security.
Leak proof and Frost proof.
Non-delayed and non-deforming.
Eco-friendly-recyclable.
23
Comparison of various piping material with PPR pipes.
CRITERIA GI PIPE COPPER
PIPE
HDPE
PIPE
PVC PIPE PP-R PIPE
EFFECT OF HARD
WATER
High scale
formation
Scale
formation is
prohibited
due to
smooth bore.
Scale
formation is
prohibited
due to
smooth
bore.
Scale
formation is
prohibited due
to smooth
bore.
Scale
formation is
prohibited due
to smooth
bore.
EFFECT OF SOFT
WATER
Gets
corroded
Gets
corroded due
to acidic
nature of
water.
No Effect No Effect No Effect
HEALTH CRITERION Low due to
lead
content and
corrosion.
Good with
ferrule but
lead content
in solder is
bad for
health.
Very good Very good Very good
JOINTING
TECHNIQUES
Threaded Soldered/
Ferrule
Fusion
Weld
Solvent
cement
Fusion Weld
CORROSION
RESISTANCE
Very Low Low No Effect No Effect No Effect
THERMAL
STRENGTH
PROPERTY AT 600C
TEMP.
Very good Very good Limited Not
Recommended
Very good
AVAILABILITY OF
FITTINGS
Very good Average Low Good Very good
THERMAL
EXPANSION
Low, good
for
concealed
piping
Low, good
for concealed
piping.
Very High,
not to be
used for
concealed
piping.
Very special
care is
required for
concealed
piping
Low, good for
concealed
piping.
EFFECT OF SUB-
ZERO TEMP.
Upto 0 C Upto 0 C Upto -40 C Upto 0 C Upto -40 C
UV RESISTANCE Very good Very good Very good Low Very good
EASE IN
INSTALLATION
Low Average Low Good Very good
FLOW PROPERTIES
FOR FRICTION.
Low Very good Very good Very good Very good
Table 3.1 Comparison of various Pipe materials.(Reference : 5)
24
3.3.5 Determination of loading unit.
In most buildings all appliances are seldom in simultaneous use. Forreasons of economy a
simultaneous demand which is less than the maximum demand from all appliances should be
provided for. This simultaneous demand can be estimated either from data derived by
observation and experience of similar installations, or by application of probability theory
using loading units.
Loading unit is a factor or number given to an appliance which relates the flow rate at its
terminal fitting to the length of time in use and the frequency of use for a particular type and
use of building. A loading unit has no precise value in terms of litres per second. The table
below sets out the „loading unit‟ rating for various appliances. Thus by multiplying the
number of each type of appliance by its loading unit/value and adding the results a figure for
the total loading units is obtained. This figure is converted to flow rate using conversion
charts – loading units to flow rate
APPLIANCE LOADING UNITS (LU)
WC flushing cistern 2
Wash basin domestic use 1.5
Wash basin public use 2
Wash basin concentrated use 3
Bath tap nominal size 3/4in 10
Bath tap nominal size 1in 22
Shower 3
Sink tap nominal size 1/2in 3
Sink tap nominal size 3/4in 10
Table 3.2 Appliances Loading Unit.(Reference : 17)
Analysis of the building shows that there are thirteen (13) Water closets and sixteen (16)
Wash hand basins.
Therefore Total number of loading units = (13×2) + (16×2)
= 58 LUs
25
3.3.6 Generation of an appropriate piping layout.
Fig 3.5 Pipe layout of the First Floor Plan.
Fig 3.6 A clear section of the first floor pipe layout.
This generation of the pipe layout was done for all the floors on our commercial building.
26
3.3.7 Pipe Sizing.
The diameter of pipe necessary to give a required flow rate will depend upon the head
available, the smoothness of the pipe used (i.e. type of material) and the effective length of
pipe run.
In smaller, straightforward installations such as single dwellings, pipes are often sized onthe
basis of experience and convention. In larger and more complex buildings, or with supply
pipes that are very long, it is necessary to use a recognized method of calculation
Correct pipe sizes will ensure adequate flow rates at appliances and avoid problems caused
by oversizing and under sizing.
Oversizing will mean:
Additional and unnecessary installation costs
Delays in obtaining hot water at outlets
Increased heat losses from hot water distributing pipes
Under sizing may lead to:
Inadequate delivery from outlets and possibly no delivery at some outlets during
simultaneous use
Some variation in temperature and pressure at outlets, especially showers and other
mixers
Some increase in noise levels
The pipe sizing procedure involves:
1. Assumption of pipe diameter
In pipe sizing it is usual to make an assumption of the expected pipe size and then
prove whether or not the assumed size will carry the required flow.
2. Determination of the flow rate
In most buildings it is unlikely that all the appliances installed will be used
simultaneously. As the number of outlets increases the likelihood of them all being
used at the at the same time decreases. Therefore it is economic sense to design the
system for likely peak flows based on probability theory using loading units, rather
than using the possible maximum flow rate
The flow rate is determined by using
a) Loading units – By multiplying the total number of each type of appliance by
the appropriate loading unit number and adding the resultant totals together,
the recommended flow rate can be read from a nomogram depicting the
conversion of loading units to flow rate in litres per second
Total loading units = 58LU and from conversion chart
Flow rate = 0.85 l/s
27
Fig 3.6 Nomogram of Loading Unit and design Flow rate.(Reference : 17)
b) Continuous flow demand – the urinals are only considered hence
6 urinals × 0.004= 0.024l/s
28
NOTE: For some appliances such as automatic flushing cisterns, the flow rate
must be considered as continuous flow instead of applying probability theory
and using loading units. For our case this will be applied on the urinals
c) Design flow rate: this is the sum of the flow rate determined from loading
units(a) and continuous flow(b)
Thus design flow rate = 0.85 + 0.024
= 0.874l/s
NOTE: The continuous flow rate for the urinal is negligible and can be
ignored for design purposes. Hence design flow rate can be used as 0.85l/s
3. Determination of the effective pipe length
a) Calculation of the measured pipe length involves measuring the path through
which the pipe follows through to the last draw off point in a given section
b) Calculation of the equivalent pipe length for fittings – for convenience the
frictional resistances to flow through fittings are expressed in terms of pipe
lengths having the same resistance to flow as the fitting hence the term
equivalent „equivalent pipe length‟
The table below shows the equivalent pipe length for the fittings
Bore of pipe
(mm)
Equivalent pipe length
Elbow (m) Tee Stop valve(m) Check valve(m)
12 0.5 0.6 4.0 2.5
20 0.8 1.0 7.0 4.3
25 1.0 1.5 10.0 5.6
32 1.4 2.0 13.0 6.0
40 1.7 2.5 16.0 7.9
50 2.3 3.5 22.0 11.5
65 3.0 4.5 ------ -----
73 3.4 5.8 34.0 -----
Table 3.3 Equivalent pipe length of fittings.(Reference 17)
29
c) Calculation for the equivalent pipe length for draw – offs – The residual head
available at each tap or outlet fitting should be at least equal to the loss of head
through the tap at the design flow rate. Alternatively, the loss of head may be
expressed as an equivalent length of pipe. Some typical losses for low pressure
taps
d) Effective pipe length is the sum of the measured pipe length and the
equivalent pipe length for fitting s and draw offs
4. Permissible loss of head
Pressure can be expressed in the following ways;
In Pascals, the Pascal(Pa) being the SI unit for pressure
As force per unit area, N/m2
As a multiple of atmospheric pressure (bar).
Atmospheric pressure = 100KN/m2 = 100 kpa = 1bar
As metres head, that is, the height of the water column from the water level to
the draw – off point
1 m head = 9.81 kpa = 98.1mb
In the sizing of pipes, any of these units can be used. BS 6700 favours the Pascal
however the use of metres head is retained here giving a more visual indication of
pressure that compare readily to the height and position of fittings and storage vessels
in the building. Therefore the loss of head is determined from the following
a) Available head – this is the static head or pressure at the pipe or fitting under
consideration, measured into metres head
b) Head loss through pipes – the loss of head (pressure) through pipes due to
frictional resistance to water flow is directly related to the length of the pipe
run and the diameter of the pipe. Pipes of different materials will have
different head losses, depending on the roughness of the bore of the pipe and
on the water temperature. Plastic pipes have smooth bores and it is the only
material considered in this design
c) Head loss through fitting – in some cases it is preferable to subtract the likely
resistances in fittings (particularly draw – offs) from the available head, rather
than using equivalent pipe lengths.
Where meters are installed in a pipeline the loss of head through the meter
should be deducted from the available head
Gate valve offer little or no resistance to flow provided they are fully open
d) Permissible head loss – this relates the available head to the frictional
resistances in the pipeline. The relationship is given by the formula
30
𝑃𝑒𝑟𝑚𝑖𝑠𝑠𝑖𝑏𝑙𝑒 𝑒𝑎𝑑 𝑙𝑜𝑠𝑠 𝑚/𝑚 𝑟𝑢𝑛 =𝐴𝑣𝑎𝑖𝑙𝑎𝑙𝑒 𝑒𝑎𝑑 (𝑚)
𝐸𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒 𝑝𝑖𝑝𝑒 𝑙𝑒𝑛𝑔𝑡 (𝑚)
This formula is used to determine whether the frictional resistance in a pipe
will permit the required flow rate without too much loss of head or pressure.
5. Determine the pipe diameter
The pipe size for a certain pipe reference is first assumed. This pipe size must give the
design flow rate without the permissible head loss being exceeded. If it does not, a
fresh pipe size must be assumed and the procedure worked through again.
The figure below relates pipe size to flow rate, flow velocity and head loss. Knowing
the assumed pipe size and the calculated design flow rate, the flow velocity and the
head loss can be found from the figure as follows;
a) Draw a line joining the assumed pipe size and the design flow rate
b) Continue this line across the velocity and head loss scales
c) Check that the loss of head does not exceed the calculated permissible head
loss
d) Check that the flow velocity is not too high by referring to table x
Table 3.4 Maximum recommended flow velocities (Reference : 14)
Water temperature
°C
Flow velocity
Pipes readily accessible
m/s
Pipes not readily accessible
m/s
10 3.0 2.0
50 3.0 1.5
0 2.5 1.3
90 2.0 1.0
33
NOTE: If for any pipe or series of pipes, it is found that the assumed pipe size gives a
progressive head that is in excess of the available head, or is noticeably low, it will be
necessary to repeat the sizing operation using a revised assumed pipe diameter
Table 3.6 Pipe Sizes.
34
MEZZANINE
PIPE REFERENCE: 15
LOADING UNITS 4
FLOW RATE (L/S) 0.3
PIPE SIZE(mm Diameter) 20
LOSS OF HEAD(m) 0.06
FLOW VELOCITY(m/s) 0.93
MEASURED PIPE LENGTH(m) 1.28
EQUIVALENT PIPE LENGTH(m) 8.8
EFFECTIVE PIPE LENGTH(m) 10.08
HEAD CONSUMED(m) 0.6048
PROGRESSIVE HEAD(m) 13.003
AVAILABLE HEAD(m) 15.28
FINAL pipe size(mm) 20
PIPE REFERENCE: 14
LOADING UNITS 4
FLOW RATE (L/S) 0.3
PIPE SIZE(mm Diameter) 20
LOSS OF HEAD(m) 0.06
FLOW VELOCITY(m/s) 0.93
MEASURED PIPE LENGTH(m) 2.83
EQUIVALENT PIPE LENGTH(m) 15.4
EFFECTIVE PIPE LENGTH(m) 18.23
HEAD CONSUMED(m) 1.0938
PROGRESSIVE HEAD(m) 12.3982
AVAILABLE HEAD(m) 15.28
FINAL pipe size(mm) 20
PIPE REFERENCE: 5
LOADING UNITS 8
FLOW RATE (L/S) 0.3
PIPE SIZE(mm Diameter) 20
LOSS OF HEAD(m) 0.06
FLOW VELOCITY(m/s) 0.93
MEASURED PIPE LENGTH(m) 2.5
EQUIVALENT PIPE LENGTH(m)
EFFECTIVE PIPE LENGTH(m) 2.5
HEAD CONSUMED(m) 0.15
PROGRESSIVE HEAD(m) 11.304
AVAILABLE HEAD(m) 13.28
FINAL pipe size(mm) 20
35
FIRST FLOOR
PIPE REFERENCE: 13
LOADING UNITS 4
FLOW RATE (L/S) 0.3
PIPE SIZE(mm Diameter) 20
LOSS OF HEAD(m) 0.06
FLOW VELOCITY(m/s) 0.93
MEASURED PIPE LENGTH(m) 1.25
EQUIVALENT PIPE LENGTH(m) 8.8
EFFECTIVE PIPE LENGTH(m) 10.05
HEAD CONSUMED(m) 0.603
PROGRESSIVE HEAD(m) 11.154
AVAILABLE HEAD(m) 12.78
FINAL pipe size(mm) 20
PIPE REFERENCE:12
LOADING UNITS 10
FLOW RATE (L/S) 0.3
PIPE SIZE(mm Diameter) 20
LOSS OF HEAD(m) 0.06
FLOW VELOCITY(m/s) 0.93
MEASURED PIPE LENGTH(m) 7.63
EQUIVALENT PIPE LENGTH(m) 30.2
EFFECTIVE PIPE LENGTH(m) 37.83
HEAD CONSUMED(m) 2.2698
PROGRESSIVE HEAD(m) 10.551
AVAILABLE HEAD(m) 12.78
FINAL pipe size(mm) 20
PIPE REFERENCE: 4
LOADING UNITS 2
FLOW RATE (L/S) 0.46
PIPE SIZE(mm Diameter) 25
LOSS OF HEAD(m) 0.047
FLOW VELOCITY(m/s) 0.93
MEASURED PIPE LENGTH(m) 3
EQUIVALENT PIPE LENGTH(m)
EFFECTIVE PIPE LENGTH(m) 3
HEAD CONSUMED(m) 0.141
PROGRESSIVE HEAD(m) 8.216
AVAILABLE HEAD(m) 10.28
FINAL pipe size(mm) 25
36
SECOND FLOOR
PIPE REFERENCE: 11
LOADING UNITS 4
FLOW RATE (L/S) 0.3
PIPE SIZE(mm Diameter) 20
LOSS OF HEAD(m) 0.06
FLOW VELOCITY(m/s) 0.93
MEASURED PIPE LENGTH(m) 1.25
EQUIVALENT PIPE LENGTH(m) 8.8
EFFECTIVE PIPE LENGTH(m) 10.05
HEAD CONSUMED(m) 0.603
PROGRESSIVE HEAD(m) 8.1406
AVAILABLE HEAD(m) 9.78
FINAL pipe size(mm) 20
PIPE REFERNCE: 10
LOADING UNITS 10
FLOW RATE (L/S) 0.3
PIPE SIZE(mm Diameter) 20
LOSS OF HEAD(m) 0.06
FLOW VELOCITY(m/s) 0.93
MEASURED PIPE LENGTH(m) 7.63
EQUIVALENT PIPE LENGTH(m) 30.2
EFFECTIVE PIPE LENGTH(m) 37.83
HEAD CONSUMED(m) 2.2698
PROGRESSIVE HEAD(m) 7.5376
AVAILABLE HEAD(m) 9.78
FINAL pipe size(mm) 20
PIPE REFERENCE: 3
LOADING UNITS 36
FLOW RATE (L/S) 0.6
PIPE SIZE(mm Diameter) 25
LOSS OF HEAD(m) 0.76
FLOW VELOCITY(m/s) 1.25
MEASURED PIPE LENGTH(m) 3
EQUIVALENT PIPE LENGTH(m)
EFFECTIVE PIPE LENGTH(m) 3
HEAD CONSUMED(m) 0.228
PROGRESSIVE HEAD(m) 5.2678
AVAILABLE HEAD(m) 7.38
FINAL pipe size(mm) 25
37
THIRD FLOOR
PIPE REFERENCE: 9
LOADING UNITS 4
FLOW RATE (L/S) 0.3
PIPE SIZE(mm Diameter) 20
LOSS OF HEAD(m) 0.06
FLOW VELOCITY(m/s) 0.93
MEASURED PIPE LENGTH(m) 1.25
EQUIVALENT PIPE LENGTH(m) 8.8
EFFECTIVE PIPE LENGTH(m) 10.05
HEAD CONSUMED(m) 0.603
PROGRESSIVE HEAD(m) 5.0398
AVAILABLE HEAD(m) 6.78
FINAL pipe size(mm) 20
PIPE REFERENCE: 8
LOADING UNITS 10
FLOW RATE (L/S) 0.3
PIPE SIZE(mm Diameter) 20
LOSS OF HEAD(m) 0.06
FLOW VELOCITY(m/s) 0.93
MEASURED PIPE LENGTH(m) 7.63
EQUIVALENT PIPE LENGTH(m) 30.2
EFFECTIVE PIPE LENGTH(m) 37.83
HEAD CONSUMED(m) 2.2698
PROGRESSIVE HEAD(m) 4.431
AVAILABLE HEAD(m) 6.78
FINAL pipe size(mm) 20
PIPE REFERENCE: 2
LOADING UNITS 50
FLOW RATE (L/S) 0.78
PIPE SIZE(mm Diameter) 25
LOSS OF HEAD(m) 0.1154
FLOW VELOCITY(m/s) 1.5
MEASURED PIPE LENGTH(m) 3
EQUIVALENT PIPE LENGTH(m)
EFFECTIVE PIPE LENGTH(m) 3
HEAD CONSUMED(m) 0.3462
PROGRESSIVE HEAD(m) 2.16702
AVAILABLE HEAD(m) 4.28
FINAL pipe size(mm) 25
38
TERRACE
PIPE REFENCE: 7
LOADING UNITS 4
FLOW RATE (L/S) 0.3
PIPE SIZE(mm Diameter) 25
LOSS OF HEAD(m) 0.023
FLOW VELOCITY(m/s) 0.625
MEASURED PIPE LENGTH(m) 1.34
EQUIVALENT PIPE LENGTH(m) 12.5
EFFECTIVE PIPE LENGTH(m) 13.84
HEAD CONSUMED(m) 0.31832
PROGRESSIVE HEAD(m) 1.8208
AVAILABLE HEAD(m) 3.78
FINAL pipe size(mm) 25
PIPE REFERENCE: 6
LOADING UNITS 4
FLOW RATE (L/S) 0.3
PIPE SIZE(mm Diameter) 25
LOSS OF HEAD(m) 0.023
FLOW VELOCITY(m/s) 0.625
MEASURED PIPE LENGTH(m) 2.4
EQUIVALENT PIPE LENGTH(m) 35.1
EFFECTIVE PIPE LENGTH(m) 37.5
HEAD CONSUMED(m) 0.8625
PROGRESSIVE HEAD(m) 1.5025
AVAILABLE HEAD(m) 3.78
FINAL pipe size(mm) 25
PIPE REFERENCE: 1
LOADING UNITS 58
FLOW RATE (L/S) 0.85
PIPE SIZE(mm Diameter) 40
LOSS OF HEAD(m) 0.02
FLOW VELOCITY(m/s) 0.75
MEASURED PIPE LENGTH(m) 16.57
EQUIVALENT PIPE LENGTH(m) 15.5
EFFECTIVE PIPE LENGTH(m) 32.07
HEAD CONSUMED(m) 0.64
PROGRESSIVE HEAD(m) 0.64
AVAILABLE HEAD(m) 1.28
FINAL pipe size(mm) 40
39
3.4 Sanitary Piping System Design.
3.4.1 Selection of an appropriate discharge system:
The type of drainage system selected for a building is determined by the local water
authority‟s established sewer arrangements.These will be installed with regard to foul water
processing and the possibility of disposing surface water via a sewer into a local water course
or directly into a soakway.
Combined system-This uses a single drain to convey both foul water from sanitary
appliances and rainwater from roofs and other surfaces to a shared sewer. The system is
economical to install,but the processing costs at sewage treatment are high.
Separate system-This has foul water from the sanitary appliances conveyed in a foul water
sewer.The rainwater from roofs and other surfaces is conveyed in a surface water drain into a
surface water sewer or a soak away.This system is relatively expensive to install,particularly
if the ground has poor drainage qualities and soakaways cannot be used.However,the benefit
is reduced volume and treatment costs at the processing plant.
Partially separate system-Most of the rainwater is conveyed by the surface drain into the
surface water sewer.For convenience and to reduce site costs,the local water authority may
permit an isolated rainwater inlet to be connected to the foul water drain.
We opted to use combined system so as to make our design as economical as possible.
3.4.2 Assigning of each sanitary fixture with appropriate discharge units.
From Buildings Service handbook (page 311) we were able to assign each sanitary fixtures as
tabulated below.
Fig 3.9 Appliance Discharge Unit.(Reference :8)
40
Appliances Discharge units
Water closet 14
Urinals 0.3
Wash hand basin 3
Table 3.7 Discharge Units.(Reference :8)
3.4.3 Sizing of the pipes using the discharge unit method:
a) Calculation of the peak flow rate using the discharge units.
Simultaneous demand process- Considers the number of appliances likely to be used at any
one time,relative to the total number installed on a discharge stack.
Formula:
)1(28.1 nnM
Where:M=no. of appliances discharging simultaneously
n=no. of appliances installed on stack
=appliance discharge time (t)÷intervals between use (T)
Average time for an appliance to discharge=10 seconds(t)
Intervals between use(commercial premises)=600(T)
For commercial premises;
=10÷600=0.0167
41
Fig 3.10 Pipe sizing diagram.(Reference : 14)
RIGHT SIDE OF THE PIPE SIZING DIAGRAM:
N=10(water closets)
Thus;
M=10×0.0167+1.8 )0167.01(0167.02
M=1.2
Hence;
Simultaneous demand factor=M÷n
=1.2÷10=0.12 or 12%
TABLE OF FLOWRATES:
TABLE 1(pg369 of Building Services Hand Book by Fred Hall & Roger Greeno)
Table 3.8 Flowrates.(Reference : 8)
42
Total flow rates=10×2.3=23l/s
Allowing 12% simultaneos demand:
Hence peak flow rate=23×(12/100)=2.76l/s
LEFT SIDE OF THE PIPE SIZING DIAGRAM.
M=25×0.0167+1.8 )0167.01(0167.0252
M=2.04
Simultaneous demand factor=2.04÷25=0.0816
=8.16%
TOTAL FLOW RATE:
FITMENT DISCHARGE FLOW RATE(l/s)
Water closets 3×2.3=6.9
Urinals 6×0.15=0.9
Basins 16×0.6=9.6
Total 17.4
Table 3.9 Total Flow Rate.(Reference :8)
Thus:
Peak flow rate=17.4÷(8.16/100)=1.42l/s
b) Determination of the diameter of the discharge stack required.
Discharge units can be converted to flow in litres per second using charts of flow rate (l/s)
againist discharge units. (pg 375 of Building Services Hand Book by Fred Hall & Roger
Greeno).
43
Fig. 3.11 Graph of Flowrate against Discharge Unit.(Reference : 8)
RIGHT SIDE OF THE PIPE SIZING DIAGRAM:
WCs=10
Thus;
Total discharge units=14×10=140DUs
Hence from the chart,140DUs coincide with a flow rate of 1.7(l/s)
Formula:
q =k3 8d
q=discharge or flowrate in l/s
k=constant of 32×10-6
d=diameter of stack in mm
Transposing the formula to make d the subject:
d= 8 3)( kq
d=38 6 )10327.1(
d=59mm
44
LEFT SIDE OF THE PIPE SIZING DIAGRAM.
WCs=3
Basins=16
Urinals=6
Thus:
Total discharge units(DUs)=(3×14)+(16×3)+(6×0.3)=91.8
Hence from the chart above and for DUs of 91.8,the flow is 1.5l/s.
d=38 6 )10327.1(
d=56mm
Discharge units on stacks(pg.376 of Building Services Hand Book by Fred Hall & Roger
Greeno):
Table 3.10 Discharge Units for different Stack Sizes.(Reference : 8)
Thus for both discharge units;140DUs and 91.8DUs,they can be adequatly served by a 75mm
or a 100mm daimeter stack.
c) Determination of the size of the branch to stack connections
Requirements:
WCs
8maximum
100mm branch pipe
15m maximum length
Gradient between 9 and 90mm/m( =90 1/2-95)
Basins
4 maximum
50mm pipe
4m maximum length
Gradient between 18 and 45mm/m( 91-921/2)
Urinals(bowls)5 maximum
50mm pipe
Branch pipe as short as possible
Gradient between 18 and 90mm/m
45
3.4.4 Selection of pipe material.
Some of the pipes used in drainage include:
Cast iron,Galvanised steel and copper pipes
Pex pipe
ABS pipe
PVC pipe
Metallic pipes(cast iron, galvanised steel and copper pipes) have been used for a long time for
both water supply and waste water lines. Due to the high cost of the metallic, they have been
used primarily for supply lines and even that is less common today. Other factors that led to
this are: rust build up on the inside of the pipe causing leaks, rough surfaces thus clogging
more easily, the fact that metallic pipes require threading tools or purchase of pre-theaded
pipe and also jointing of matallic pipes is not as easy as compared to plastic pipes.
ABS(Acrylonitrite –Butadiene-Styrene) pipe is the standard for waste pipe in most
modern homes. It has been in use for 30+ years and with few exceptions, it has been a very
reliable.Along with PVC it is a waste pipe system that is quite easy to maintain or modify.
Polyvinylchloride(PVC) is a white pipe material made from the same material as
vinylwindows. It can be used for water supply lines, fittings, waste and drainage lines.We
opted to use U-PVC because of the following factors:
Good corrosion and chemical resistance
Light weight
Smooth surface(low resistence to water
flow)
Not a conductor of electricity(no
galvanic/oxidative corrosion).
Can be connected to other materials
easily
Inexpensive
Easy to work with
One of the key disadvantages of PVC are; degradation on prolonged exposure to ultraviolet
rays and higher noise levels as compared to metallic pipes. However this limitations can be
countered by using ultraviolet stabilizers and wrapping the pipes with insulation respectively.
Also where the PVC pipe extend above roofs, they can be painted in some jurisdictions, to
protect them from the UV rays.
46
3.5 Pumps Design for the Plumbing System.
3.5.1 Selection of the type of pump system.
There are two systems that are commonly in use:
a) Open system
b) Closed system
Closed system- in a closed system, at no point is the water being pumped exposed to the
atmosphere during the pumping process. It is mostly used with hot water supply systems.
Open system- in open system,water being pumped is exposed to the atmosphere. This system
is mostly used in cold water supply system.
Hence,our design being based on cold water supply system only, open system is best suited
for this project.
3.5.2 Selection of the types of pumps to be used.
There are two common types available:
a) Positive displacement pumps.
b) Rotor dynamic pumps.
- Positive Displacement use the principal fluid displacement by a mechanical device and
have the characteristic of when priming at a constant speed they pump fluid at a fixed flow
irrespective of system pressure. There are two main types, reciprocating and rotary, the
common being the rotary peripheral type as used for small domestic pumps, though they
come in many configurations.
- Rotor dynamic pumpsdepend upon the rotation of a rotor to provide the pumping force
and have the characteristics that at a given speed flow varies with pressure. They are further
classified according to the type of rotor into radial flow, mixed flow and axial flow types.In
radial flow pumps, fluid moves through the rotor(impeller) in a radial direction and pressure
is developed by centrifugal force.
In axial flow pumps, the fluid is pumped through the rotor in a direction axis to the motor
shaft and pressure is developed by the lifting action of the propeller. Mixed flow pumps have
impellers that are a mixture of both types.
Main characteristics of centrifugal and positive displacement
47
Centrifugal pumps Positive displacement pumps
Capacity varies with head Capacity substantially independent of head
Capacity proportional to pump speed Capacity proportional to speed
Non self–priming Self priming
Suitable for low – viscosity liquid Suitable for various liquids(reduced speeds
usually necessary for high Viscosity
Table 3.11 Difference between Centrifugal and Positive Displacement Pumps.(Reference :12)
The most common rotor dynamic pump is the centrifugal type,which are mechanically
simple, efficient and economical.It is due to these factors and the one listed above that made
us settle for the centrifugal pump type as well as the fact that the centrifugal pump met our
design specifications. Centrifugal pumps also have different types categorised by the impeller
design as follows:
Closed impeller
The impeller vanes are enclosed between two discs. This is the most efficient design though
is only suitable for clear water as the vanes tend to clog when pumping suspended solids.
Open impeller
The vanes are open on one side which improves silt handling capacity but reduces efficiency.
Vortex impeller
Pumps by creating a vortex in the pump chamber so providing a freer flow passage giving
improved silt and solid handling capacity.
Single and double channel impeller
Designed with large flow passages within the impeller for the pumping of fluids with large
size solid content.
Cutter and Grinder impellers
Specialised designs for macerating string materials and small solids before being passed as
sludge through the pumps.
Thus, when choosing a pump it is important to select the impeller type and impeller materials
to avoid operational problems. Generally if water is clean and thin with no suspended solids a
closed impeller or peripheral pump should be used while for polluted water an appropriate
impeller type should be selected. Thus a closed impeller would be appropriate for our design
since it involves water which is clean and with no suspended solids.
48
1)Selection of the type of power supply for the pumps.
Duplicate pumps are manually provided and these maybe controlled as follows:
Automatic „on‟ and manual „off‟ – the pump is started automatically by a pressure
switch and stopped manually by a „Stop/ Reset‟ push button on the starter. In addition,
an electric alarm bell is provided to register all the time the pump is running.
Automatic „on‟ and „off‟- The pumps are started by a pressure switch but a flow
switch is also provided in the pump delivery line to ensure that the pump continuously
runs all the time
Diesel pumps are only Auto „On‟ and Manual „Off‟.
For the Electric motor powered pump, we chose the Automatic „On and „Off‟ type of power
supply for the pumps due to its effectiveness in terms of ensuring no over flow of water and
also, it doesn‟t require the presence of a person to switch the pump of once the tank is full
hence its more effective and reliable as compared to its counterpart.
2)Sizing of the pump to be used using the following design variables:
a) Daily water requirement for the building
b) Capacity of the storage tank
c) Static delivery head and velocity head
d) Friction head in the pipe system
e) Static suction lift and static suction head
f) Total pump head
g) Total delivery head
h) Total head on the pump
i) Total suction head(Positive)
j) Vapor pressure
Solution:
a) Total static head
The total static head(hts) in the pumping system is the water level difference between the
suction and delivery reservoirs. For our case, the total static head is 20.483m
b) Total friction head
The friction head (hf) is the total pressure head lost due to fluid friction which occurs as fluid
flows through the pipeline. This friction head loss includes that in pipe-work and fittings
starting from the suction inlet fitting, through to the discharge pipe outlet. For a given
discharge flow rate, this friction depends on the pipe material, size, length, and the type and
number of fittings.
49
It can be computed once these pipeline specifications are determined.
Calculations for friction head in the pipe(hf):
Total length of the pipe = 38.642m
Velocity of water in the pipe = 2m/s
Pipe diameter = 40mm = 0.04m
Kinematic viscosity of water at (20ᵒ) = 1.004×10
-6
Reynolds number = Velocity × Diameter=2×0.004= 7.968×104
Kinematic viscosity 1.004×10-6
Relative roughness (r) = E/D (E in mm, D in mm)
Where:
E= effective roughness = 0.002mm
D= diameter of pipe = 40mm
Hence:
r= 0.002/40 = 5×10-5
From Moody diagram and with the above values of Reynolds number and Relative
roughness, we obtained friction factor (f) as 3.3×10-2
.
Thus:
hf = flv2/ 2gd
= 3.3×10-2
×38.642×22 = 6.499m
2×9.81×0.04
hf= 6.449m
c) Total pressure head on pump
The total pressure head to be overcome by pumping system is therefore given by the
expression:
H= hts + hf
Where,
H = Total pressure head to be overcome by pumping
hts= Total static head to be overcome by pumping
hf = Total head loss due to fluid friction in pipeline
Therefore,
H= 20.483+ 6.449 = 26.932m
Net Positive Suction Head(NPSH
Liquid is not sucked into the inlet of a pump.A positive pressure head must exist at inlet of a
pump to push liquid into the pump inlet.Net positive suction head is the measure of this
pressure head required at the inlet of the pump.
50
a) Net Positive Suction Head Required (NPSHR)
Net positive suction head required(NPSHR) is a characteristic of a pump. The net positive
suction head required by the pump is the minimum fluid pressure required at the inlet of the
pump to enable it to operate satisfactorily. This characteristic of the pump depends on the
pump‟s design, and is included in the manufacturer‟s performance specifications for each
pump.
b) Net Positive Suction Head Available (NPSHA)
Net positive suction head available (NPSHA) is the actual fluid pressure at the pump inlet,
arising from a given suction design, at a particular geographicallocation. The balance
between (NPSHA) and (NPSHR) is the variable factor that the designer seeks to control by
suction design.The object of designing suction arrangements is to ensure that NPSHAat the
pump inlet exceeds the NPSHR of the selected pump.
The (NPSHA) for a particular suction design is given by the expression:
NPSHA = ha + hs – hf ˗ hvp (for a design with positive suction head)
NPSHA=ha – hl ˗ hf ˗ hvp (for a design with negative static suction head)
Where,
ha= Atmospheric pressure operating at site in moW
hf = Friction head loss in suction pipework
hvp= Vapour pressure at site
Thus:
ha= 8 (MWH) in Nairobi which has an altitude of 2000m
hvp= 0.43(MWH) at an average temperature of 30ᵒc
Since our design has a negative static suction head,
NPSHA = ha – hl – hf - hvp
hf=3.3×10-2
×22×3.376 = 0.5678m
2×9.81×0.004
NPSHA=8 – 0.603 -0.5678 - 0.43 =6.4
Discharge flow rate required
Roof tank capacity =12000l =12m3
Specifications include:
51
1) The tank should be filled in two hours(7200 seconds )
2) The flow velocity in the pipeline is 2m/s
Thus,
Q =12m3/7200s =0.00167 m
3/s
But,
Q = A × v
Where,
A = Area
V = velocity
0.00167=(π ×d2
× 2)/4
d = 00106316.0 =0.033m
Therefore the diameter of the riser pipe is 40mm since it is the next standard pipe size after
32mm for PPR.
Thus
Daily water demand=3697.5l
Capacity of the storage tank=12000l=12m3
Static delivery head (hts)=20.483m
Friction head in the pipe system(hf) = 6.449mm
Total head on the pump = 26.932m
Total suction lift (Negative) = 6.4m
Vapor pressure = 0.43 MWH
52
Pump selection:
Finally, we selected the pump type and size required, by considering the above total head to
be overcome, in conjunction with the discharge flow rate required and thus using available
catalogues from Davies and Shirtliff, Horizontal Multistage CM-15 met the above
specifications hence our choice of pump.
3.6 Pump Installation.
The installation of the pump mainly refers to the detailed specifications outlining the power
required to run the pump as well as the power output that will be generated by a given pump.
These variables are of the utmost importance as they will determine whether the pump
selected can be able to handle the head and not be overworked or underworked. Pump
installation involves
1. Piping – Size and suction of delivery pipes should be calculated and not be smaller
than pump connectors. They should be accurately cut and fitted so that it can be
bolted up to the pump or pipe joints. Easy bends to be used and sharp elbows and tees
avoided
2. Suction strainer – total area of the holes in the strainer should never be less than
twice the cross sectional area of the suction pipe
3. Foot valve – desirable at the end of the suction pipe to keep the suction pipe full at all
times and eliminate the need for priming after a shut down
4. Discharge Non return valve – Should be fitted both to make it possible to open up
the pump without draining the pipe and to prevent the head of water from driving the
pump in reverse after stopping
5. Relief valve – Designed to give temporary protection against an abnormal condition
and should the valve fail, the cause should be ascertained and rectified
6. Electric motors – Squirrel – cage AC motors are the normal choice wherever
possible and can usually be started direct online
7. Switch gear - It is not possible to protect a motor adequately by means of fuses only
as a fuse that will carry the normal starting current is too heavy to give protection -
against ordinary overloads. Pumps should be controlled
The most important provisions relating to pumps are as follows;
1. An automatic pump supply consisting of two automatic pumps at least one must be
driven by a compression ignition engine with each pump capable of providing the
required pressure and flow independently. If there are three automatic pumps at least
two must be driven by CI
2. In the case of an electric motor driven pump it must be housed in a separate building
of non-combustible construction used for no purpose other than housing of fire
protection water supplies
3. Automatic priming equipment must be provided where necessary to ensure that the
pump will be fully primed with water at all times
4. Pumps must be capable of providing the rate of flow and pressure required at the
highest and most remote parts of the protected premises. The performance
53
characteristics of the pumps should be such that the pressure falls progressively with
the rate of demand
5. A pump may draw directly from a town main provided the latter is capable of
supplying water at all times at the max rated output of pump
6. In the case where an automatic pump forms the sole supply a fall in water pressure in
the sprinkler system which is intended to initiate the automatic starting of the pump,
shall at the same time provide a visual and audible alarm at some suitable location
3.6.1 Pumping Power
Water Horsepower
Power required to pump water is determined by the flow rate, and the total head generated as
shown below;
Water Horsepower PW = ρgQH
Where
ρ = Density of water in Kg/m3
g = Gravity constant m/s2
Q = Flow rate in m3/s
H = Total pumping head
Taking p = 1000 Kg/m3 and transforming into Kilowatts
𝑃𝑤 = 𝑔𝑄𝐻 KW
𝑃𝑤 = 9.81 ∗ 𝑄𝐻 𝐾𝑊
PW = 1000 × 9.81 × 1.67 × 10-3
× 27.98
PW = 0.4584 KW
The water horse – power that the pump must inject into the water is therefore fixed once the
design specifications of the pumping system are determined.
Pump shaft – power
The power that must be injected into the pump shaft by the prime – mover includes the water
horsepower as well as other losses, namely;
Hydraulic loses in the pump
Mechanical losses in the transmission shaft and the coupling between the pump and
the prim – mover
54
The input power required at the pump shaft is therefore given by;
𝑃𝑠 = 𝑃𝑤
𝜂𝑝 ∗ 𝜂𝑐
Where
𝜂𝑝 = Overall pump efficiency. Indicative value for horizontal centrifugal at 1450rpm
𝜂𝑝 = 0.55 for ratings up to 5 Kw
𝜂𝑝 = 0.65 for ratings of 5 – 10 Kw
𝜂𝑝 = 0.70 for ratings of 10 – 20 Kw
𝜂𝑝 = 0.75 for ratings of 20 – 30 Kw
𝜂𝑝 = 0.78 for ratings of 30 – 40 Kw
𝜂𝑝 = 0.82 for ratings above 40 Kw
𝜂𝑐 = Efficiency of transmission coupling. Indicative values are
𝜂𝑐 = 1.0 for direct coupling
𝜂𝑐 = 0.95 for V belt or gear coupling
𝜂𝑐 = 0.80 for flat belt drive
PS = 0.4584
0.5 ×1
PS = 0.8335 kW
3.6.2 Power Sources
The prime movers encountered in small – scale water pumping duties, in irrigation and water
supply projects are petrol engines, diesel engines and electric motors
1. Petrol engines
The availability of petrol driven stationary engines is limited to a maximum power
demand of approximately 7.5 Kilowatts. Petrol engines are less reliable than diesel
engines and tend to be built with shorter economic lives. To their advantage, their
initial costs are lower.
2. Diesel engines
They are available in a wide range of power capacities. Standard products of up to 25
Kilowatt capacity are available as stand-alone. Locally, large capacities are only
available already assembled in other products such as generating sets, agricultural
machines and earth moving equipment
55
3. Electric motors
Electric power is available from the national grid in those locations where the electric
power lines already reach
Electric Power
Electric power from the national grid is available in several parts of Kenya, and is being
extended constantly. When electric power is not available on site, then the cost of bringing it
to the site is part of the capital cost of the project. Consequently, when additional cost has to
be incurred to extend the power – line to the site, other alternatives such as the use of diesel
engine must be examined
Electric motors are available in sizes and speeds shown below:
1) Standard motor sizes (input brake hp)
½, 3/4, 1, 11/2, 2, 3, 5, 7 ½, 10, 15, 20, 25, 30, 40, 50, 60, 75, 100, 125, 150, 200, 250
2) Standard motor speeds (Full load, 50 cycles per second local power supply)
2900, 1450, 960, 720 rpm
Electric motor power requirements
Electric motor speeds can be chosen to make direct coupling to the pump shaft appropriate.
Assuming the transmission efficiency is 1, the power output required from the motor then
equals the power absorbed by the pump shaft.
The table shows typical variation of efficiency of electric motors with altitude, and ambient
temperature. The test results are obtained at an operating temperature of 40°, and an altitude
of 1000 metres. The temperature derating factor can therefore be ignored when the operating
environment is close to the 40°C. This is a common situation in a country such as Kenya.
ALT. IN
METRES
AMBIENT TEMPERATURE(DEGREES CENTRIGADE) AND %
MOTOR EFFICIENCY
30 35 40 45 50 55 60
1000 107 104 100 96 91 86 80
2000 101 98 94 90 85 81 75
3000 92 90 86 83 79 75 69
4000 82 80 77 74 70 66 61
Table 3.12 Ambient Temperature and Motor Efficiency.(Reference : Lecture notes)
56
From the variation of efficiency with altitude shown it can be concluded that a 1% reduction
in electric motor efficiency should be applied for every 100 metres above 1000 metre
elevation.
Considering the foregoing, the power input by the electric driving motor can be determined
from the input power required by pump shaft as follows
𝑃𝑚 = 𝑃𝑠 × 𝑆𝑓
𝜂𝑚 ∗ 𝐴𝑓
Where,
𝑃𝑚 = Power input required by motor
𝑃𝑠 = Power input required by pump shaft
𝐴𝑓 = Altitude derating factor
𝐴𝑓 = 1% reduction for every 100m above 1000m
𝑆𝑓 = Safety factor;
𝑆𝑓 = 1.50 for ratings up to 1.5 Kw
𝑆𝑓 = 1.30 for ratings of 1.5 – 4 Kw
𝑆𝑓 = 1.20 for ratings of 4 – 8 Kw
𝑆𝑓 = 1.15 for ratings of 8 – 15 Kw
𝑆𝑓 = 1.10 for ratings above 15 Kw
𝜂𝑚 = Efficiency of motor
𝜂𝑚 = 0.7 for ratings of 1 – 2 Kw
𝜂𝑚 = 0.8 for ratings of 2 – 10 Kw
𝜂𝑚 = 0.85 for ratings of 10 – 50 Kw
𝜂𝑚 = 0.9 for ratings above 50 Kw
𝑃𝑚 = 0.8335 × 1.5
0.7 × 0.9
= 1.779 Kw
57
Diesel and Petrol Engines
The actual power of the engine to be chosen is further adjusted by other factors as shown
below:
Engine power requirement 𝑃𝐸 = 𝑃𝑠∗𝑆𝑓
0.95∗𝐴𝑓∗𝑇𝑓
Where,
𝑃𝑆 = Pump shaft power requirement before adjusting for transmission losses
𝐴𝑓 = Altitude derating factor
𝐴𝑓 = 1% reduction for every 100 metres above sea level
𝑆𝑓 = Safety factor, taken as 1.2 for engines
𝑇𝑓 = Ambient temperature derating factor
𝑇𝑓 = 2% for every 5 degrees centigrade above 30 degrees
𝑃𝐸 =0.8335 × 1.2
0.95 × 0.8 × 1
= 1.3161 kW
The electric power computed above is the maximum power that the motor will require for
example during starting. It can be used to forecast the unit power consumption of the
pumping system as shown;
Electric power consumption of pump = 1.779Kw
Therefore power consumption of pump per hour = 3.5 Kwh
Power consumed per unit of water delivered is given by:
Unit power consumption = 1.779
6.012Kwh/m
3 = 0.296 Kwh/m
3
Detailed design drawing of the plumbing system layout.
The drawings for both cold water supply and the sanitary drainage system layout, entailing
their associated elements.The layouts are generated using Autodesk AutoCAD software as
shown on the Appendix.
58
CHAPTER FOUR – PLUMBING SYSTEM DESIGN USING
BUILDING INFORMATION MODELLING.
4.1 Design using Building Information Modelling (BIM).
The Building Information Model is primarily a three dimensional digital representation of a
building and its intrinsic characteristics. It is made of intelligent building components which
includes data attributes and parametric rules for each object.
BIM provides consistent and coordinated views and representations of the digital model
including reliable data for each view.
In this stage, Building Information Modelling software is now used to carry out the design
process.
The following is a detailed methodology that was followed in this new design process:
4.2 Selection of a complete detailed Architectural drawing
The architectural drawings used were the same as those used during the Traditional approach
in Fig A above.
4.3 Plumbing Engineering codes and standards of practice
This involved gathering of all the information concerning the codes and standards of practice
in use as done on the traditional method. These codes chosen were in line with those used by
the Ministry of public works and Nairobi City Council.
4.4 Project initiation using Revit Software.
The project started by gathering all the details concerning the project. These details are in the
form of the project name, the owner of the project, the owner‟s project number, the project
address, the project description and the areas to be modelled. It is also important to note that
definition of a core collaborative team, project objectives, project phases and overall
communication plan are part and parcel of the project initiation phase. Due to the simple
nature of the project, the need to define all the aforementioned key elements was of no use.
However, all details concerning the project were available and were listed below as:
1. Project name – Design of the Plumbing system.
2. Owner of the project – The University of Nairobi.
3. Owner‟s project number – GON/2015
4. Project address – University of Nairobi Premises off Harry Thuku Road
5. Project description –Plumbing design for a commercial building.
59
Revit Software offers a platform where this details are recorded for easy review when need
be.
This was done using the software as shown in the interface below:
Fig 4.1 Project Properties.
4.5 Project delivery method selection.
There 3 common project delivery methods used, they include:-
Design-Bid-Build Project delivery.
This is a project delivery method in which the agency or owner contracts with separate
entities for the design and construction of a project. This delivery has three phases:-
i. Design Phase – Engineer and Architect design and produce bid documents,
including construction drawings and technical specifications, on which various
contractors will in turn bid to construct the project.
ii. Bid Phase –Here contractors bid for the Job.
iii. Construction Phase – On this phase, after the Bid has been awarded
construction starts.
Design / Build delivery Approach.
This requires a single entity to take over the responsibilities of the designer and the
builder for the owner. Selection of this approach is usually based on a combination of cost
and qualification. Since the designer and the General contractor work together, quality
assurance is limited. (Cost becomes a priority over Quality).
60
Here BIM is used freely right from the start of the project. BIM has a strong and effective
process in this approach.
Integrated Project Delivery (IPD)
This approach requires designers, construction manager, sub-contractors and owners to
share the project risks. If the project stays within budget, then all the project participants
receive their share of profit, otherwise lose their fee.
Due to this incentive it promotes all participants to work together towards a common
goal. They share all the BIM, decision making and responsibility. IPD results in pure
collaboration and no litigation.
Overall BIM makes IPD achievable.
From the above explained Project delivery approaches, Integrated Project Delivery
method was the best for our project because of the fact that it brings together expertise of
different department and enables them to work together towards a common goal.
Decision making and responsibilities are shared across the expertise hence Quality
becomes a priority.
After selection of the project delivery method, preparation of the modelling plans
commenced.
4.6 Preparation of the modelling plans
4.6.1 Definition of the modelling components
On this stage, several setups were made before the design procedure commenced ie
File naming structure was first defined and was named and listed as indicated
{COMMERCIAL BUILDING PLUMBING DESIGN –GON 02/2015}This was
followed by.
Precision and dimensioning –here the models used were drawn and measured
using Metric Units hence could be used for design intent, analysis and
construction.
Modelling object properties – During the course of the project, the project
teamgenerated a Plumbing Model and an input Design Intent model provided.
61
The table below, outline the model we created in this project. Model name, Model content,
Project Phase and the Authoring Tool were listed as shown:-
Model Name Model Content Project Phase Authoring Tool
Architectural Model - - Autodesk Revit
Architecture software
Plumbing Model Contains pipes,
valves, tanks, water
closet, urinals and
sinks.
Design development
and Plumbing
documents.
Autodesk Revit
Architecture
software.
Mechanical Model - - Autodesk Revit
Architecture software
Structural Model - - Autodesk Revit
Architecture software
Table 4.1 Models (Reference : 4)
System of Measurement Convention – The standard unit of convection for our
Project is Metric
4.6.2 Drawing of the 3D model.
Below is a sample procedure of what was done in coming up with the complete 3D
model.
STEP 1: Linking of the CAD architectural plans to Autodesk Revit.
Here all the floor plans were saved independently corresponding with their respective
levels in the AutoCAD software. As shown below:-
Fig 4.2 Architectural plan in AutoCAD.
62
This was followed by linking the saved file above to Revit which is to say the
Architectural Plans were copied directly to the drawing platform as they appeared on the
AutoCAD software citing an illustration below.
Fig 4.3 Architectural plan in Revit Software.
Using Revit commands and features we were able to link all the Architectural drawings
and modelled over them producing a complete 3D model of the commercial building
below.
Fig 4.4 A complete 3D model of all the Architectural plans
63
4.7 Design of the Cold water piping system.
4.7.1 The water distribution system.
Its design and the calculated value for the daily water requirement are borrowed from the
earlier design process.
The Daily Water requirement for the building is 3697.5litres
4.7.2 Insertion of appropriate Fixtures in the Model.
The Architectural Plans had the stated fixtures with the required position of the fixtures
on the Plans, with this and having linked the floor plan to the Revit Software we could
easily trace the position of the fixtures.
Revit Software has a Library which contains all the construction features, appliances and
fixtures grouped in different Families. This enabled us to pick from a variety, the required
fixture stated by the engineer on the Plan for our Commercial Building. (ie Water Closet,
Wash hand Basin, Urinals etc)
The insertion of the wash hand basin into the model required creation of levels on each
floor.This levels were measured from the floors. The reason for this was to insert the
wash hand basins at the required standard level from the floor/ground.
Fig 4.5 A wash hand basin fixture level.
4.7.3 Insertion of Standard values for Fixture Variables.
Computing fixture units is a fundamental element of sizing piping systems for water
distribution and drainage. Values assigned to specific types of fixtures are crucial in
sizing of a plumbing systems.
Loading unit is a factor given to an appliance relating the flow rate at its terminal fitting
to length of time in use, frequency of use for a particular type, use of building.
Revit Software offers a dialogue box containing fields which were filled with the loading
units found during the Traditional approach. The platform is as shown below:
64
Fig 4.6 A dialogue box indicating loading unit for a water closet.
Flow pressure is a measure of force that gets water through mains and into the pipes. The
software displays the flow pressure value as soon as a fixture is chosen.
Fig 4.7 Properties of the water closet.
65
4.7.4 Pipe type creation and material selection
There several pipe types made of different material with the intent of serving different
functions. Cold water supply and sanitary drainage are the major services required in our
building. Due to the fact that the two fluids being supplied and drained have different
chemical properties, their need to create a pipe type suitable to meet those properties.
Revit software has a system family pipe types which allows one to choose from the
available pipe types provided or create a new pipe type and fill the provided fields with
the properties of the new pipe.
This is the followed up by Routing Preferences settings where all possible connectors are
loaded into the system for easy and fluent pipe connection. This is illustrated below:-
Fig 4.8 Routing Preferences.
After the creation of the pipe type, material selection and setting routing
preferences.Routing of the cold water pipes on the model commenced, this was done by
selecting the PPR-C pipe type and connecting it to inlets on all the available fixtures on
the model.As shown in a sample floor section below:
66
Fig 4.9 Cold water routing in the model.
4.7.5 Pipe Sizing of the system
There are 2 methods for pipe sizing in Revit Software:-
Velocity method.
Friction method.
Options in the Pipe Sizing dialog let you select either method by itself (select Only) or in
combination with the other (select And or Or).
Fig 4.10 Pipe sizing dialog box.
67
Considering our project we used velocity method approach to pipe size. As seen from the
above dialog box we imported the velocity values from the Traditional Approach and inserted
them on the field provided with reference to their branch levels as per the pipe sizing diagram
on page 25. (i.e For branch 6 – the velocity was 0.625m/s as shown the dialog box above.)
The software then automatically pipe sizes the pipe on the project.
However, we experienced an over sizing problem with the software. The values obtained
after pipe sizing were larger compared to the calculated values especially when sizing the
branch pipesThis a common problem with the Revit software because the theory of Fixture
Units when developed by Hunter were for complete large systems, hence the pipe sizing was
incorrect when branching off.
4.7.6 Generation of pressure Loss report.
After sizing of the pipes a pressure loss report was generated as follows: On the Revits‟
toolbar, select analyse then on the options that are laid out after this select reports and finally
select pipe pressure loss report. This procedure provides you with table of fields containing
elements that you want appearing on the pressure loss report.
Fig 4.11 Pipe Pressure Loss report Procedure.
68
4.7.7 Pump sizing.
a) Total pressure head on pump
The total pressure head to be overcome by pumping system is therefore given by the
expression:
H= hts + hf
Where,
H = Total pressure head to be overcome by pumping
hts= Total static head to be overcome by pumping
hf = Total head loss due to fluid friction in pipeline
The Total static headwas measured from the model building drawn on the Revit
software.
hts = 23.3m
The Friction factor and the discharge flow rate was the same as the one used during
earlier approach.
Therefore: - f = 3.3×10-2
Q =12m3/7200s =0.00167 m
3/s
hf = flv2/ 2gd
= 3.3×10-2
×37.4×22 =6.3 m
2×9.81×0.04
hf=6.3 m
Therefore,
H= 23.3 + 6.3 = 29.6m
a) Net Positive Suction Head Available (NPSHA)
NPSHA=ha – hl ˗ hf ˗ hvp (for a design with negative static suction head)
Where,
ha= Atmospheric pressure operating at site in moW
hvp= Vapour pressure at site
hf = Friction head loss in suction pipe work
ha= 8 (MWH) in Nairobi which has an altitude of 2000m
hvp= 0.43(MWH) at an average temperature of 30ᵒc
hf = flv2/ 2gd
= 3.3×10-2
×5.5×22 = 0.93m
2×9.81×0.04
69
hf= 0.93m
The static head from the underground tank to the pump was measured from the revit
model and was found as.
hts = 0.6m
NPSHA=ha – hl ˗ hf ˗ hvp
= 8 –0.6 - 0.93 - 0.43
= 6.04m
Using the above values of NPSHA, discharge flow rate and Static Headwe selected the pump
type and size required, by considering the above total head to be overcome, in conjunction
with the discharge flow rate required and thus using available catalogues from Davies and
Shirtliff, Horizontal Multistage CM-15 met the above specifications hence our choice of
pump
4.7.8 Detailed design drawing of the plumbing system.
The following daigrams shows the detailed pipes layout done by the Revit software for all the
respective floors.
Mezzanine Floor Pipe Detailed Layout.
71
Third Floor Pipe Layout.
Terrace Floor pipe layout.
LEGEND
1. Green pipe – This indicates the cold water supply pipes.
2. Orange pipe – This indicates the Sanitary drainage pipes.
72
Fig 4.12 Complete Model of Architectural Plans.
This was our final design drawing for the entire plumbing system, it entails both the
underground and the roof tank as well as the plumbing fixtures under the scope of our design
and the pipe layout for the entire system.
4.8 Design of the Sanitary piping systems
4.8.1 Selection of an appropriate discharge stack
The appropriate discharge stack system was borrowed from the traditional method hence
combined stack system which involves the usage of a single drain to convey both foul water
from sanitary appliances and rainwater from roofs and other surfaces to a shared sewer
making the system economical to install.
4.8.2 Insertion of the standard values of discharge units to each fixture
In plumbing, a fixture unit is equal to one cubic foot(7.48 gallons) of water drained in a pipe
over one minute,thus a fixture unit is not a flow rate unit but a design factor.A fixture unit is
73
used in plumbing design for both water supply and waste water (Discharge unit) thus as
mentioned earlier, computing fixture units is a fundamental element of sizing piping systems
for water distribution and drainage. Values assigned to specific types of fixtures are crucial in
sizing of a plumbing systems as different fixtures have different flow requirement, in order to
determine the required size of pipe, an arbitrary unit is used for pipe sizing which takes into
account the likelihood that all fixtures will not be used at the same time . There are situations
where a design provides for more FUs being discharged than supplied. This occurs in
situations where liquids like rain water may infiltrate or are added to a draining system. This
is reflected in our design where we are using a combined discharged system.
Revit Software offers a dialogue box containing fields which were filled with the discharge
units found during the Traditional approach. A sample of this is as shown below for WCs.
Fig 4.12 Type Properties.
4.8.3 Pipe type creation and material selection
As mentioned earlier, Revit software has a system family pipe types which allows one to
choose from the available pipe types provided or create a new pipe type and fill the provided
fields with the properties of the new pipe. This is due to the fact that, the waste water being
drained has different chemical properties hence the need to create a pipe type suitable for
certain fluid properties. For our drainage pipe material, we used U-PVC which is a commonly
used material currently for almost all discharge stacks. This was then followed by Routing
Preferences settings where all possible connectors were loaded into the system for easy and
fluent pipe connection. This is illustrated below:-
74
Fig 4.13 Routing Preferences.
4.8.4 Routing of the sanitary pipes
After the creation of the pipe type, material selection and setting routing preferences. Routing
of the cold water pipes on the model commenced, this was done by selecting the U-PVC pipe
type and connecting it to the outlets on all the available fixtures on the model. This is shown
in the sample floor section below:
Fig 4.14 Diagram showing sanitary routing of the pipes.
75
4.8.5 Scheduling and quantity take offs of the system
This is a feature of the Revit software that enables you to view different fields ( i.e system
classifications, diameter size,material, flow, length e.t.c). It also sums up the total for various
parameters like pipe length thus giving you accurate figures as per the design, this is one of
the main advantages of the software as it saves time and reduces the hectic process of
computing for each parameter in the design manually.
Step 1.
Step 2
77
CHAPTER FIVE – FINAL LIST OF THE DESIGN
SPECIFICATIONS.
5.1 DRAWINGS
Plumbing drawings are diagrammatic but shall be followed as closely as actual
construction permits. Any deviation made shall be in conformity with the
architectural and other services drawings.
Architectural drawings shall take precedence over plumbing or other services as to all
dimensions.
Any drawings issued by the Architects for the works are the property of the architects
and shall not be lent, reproduced or used on any other intended without the written
permission of the Architect.
5.2 INSPECTION AND TESTING OF MATERIALS
Contractor shall be required, to produce manufacturers test certificate for the particular batch
of materials supplied to him. The tests carried out shall be as per the relevant British
standards.
All materials and equipment found defective shall be replaced and whole work tested to meet
the requirement of the specifications.
5.3 METRIC CONVERSION
All dimensions and sizes of materials and equipment given are commercial metric sizes.
Any weights or sizes given having changed due to metric conversion, the nearest equivalent
sizes accepted by British standards shall be accepted.
5.4 MATERIALS
All the supply water supply pipes and the drainage pipes shall be PPR and U-PVC
respectively.
78
5.5 SECTION-1
WATER SUPPLY
1.0 SCOPE OF WORK
1.1 Work under this section consists of furnishing all labour, materials equipment and
appliances
necessary to completely install the water supply system as required by the architectural
drawings.
1.2 Without restricting to the generality of the foregoing, the water supply system shall
include
the following :-
All water lines to different parts of building and making connection from source etc.
Control valves and other appurtenances.
Connections to all plumbing fixtures, tanks and appliances.
Excavation and refilling of pipe trenches, wherever necessary
2.0 GENERAL REQUIREMENTS
2.1 All materials shall be new of the best quality conforming to specifications. All works
executed shall be to the satisfaction of the Architect.
2.2 Pipes and fittings shall be fixed truly vertical, horizontal or in slopes as required in a neat
workmanlike manner.
2.3 Short or long bends shall be used on all mainpipe lines as far as possible. Use of elbows
shall be restricted for short connections.
2.4 Pipes shall be fixed in a manner as to provide easy accessibility for repair and
maintenance
and shall not cause obstruction in shafts, passage etc.
2.5 Pipes shall be securely fixed to walls and ceilings by suitable clamps at intervals
specified.
2.6 Valves and other appurtenances shall be solocated as to provide easy accessibility for
operations, maintenance and repairs.
2.7 The plumbing shall have an underground tank from which water will pumped by the
pump to the roof tank. From the roof tank, water shall be supplied to the plumbing
fixtures/appliances.
3.0 PIPES, FITTING AND VALVES
3.1 All pipes inside the buildings and where specified, outside the building shall be made of
polypropylene random copolymer.
3.2 Fittings shall be malleable PPR fittings, of approved make. All fittings shall have
manufacturer's trade mark stamped on it. Fittings for PPR pipes shall include elbows,
bends , tees, reducers, unions, bushes.
79
5.6 SECTION -2
SANITARY FIXTURES
1.0 SCOPE OF WORK
1.1 Work under this section shall consist of furnishing all material and labour required to
completely install all sanitary fixtures and accessories as required by the architectural
drawings.
2.0 GENERAL REQUIREMENTS
2.1 All fixtures and fittings shall be provided with all such accessories as are required to
complete the item in working condition whether specifically mentioned or not in the
schedule of quantities, specifications, drawings or not.
2.2 All fixtures and accessories shall be fixed in accordance with a set pattern matching the
tiles or interior finish as per architectural/interior designers requirements. Wherever
necessary the fittings shall be centred to dimensions and pattern desired
2.3 All fittings and fixtures shall be fixed in a neat workmanlike manner true to levels and
heights as shown on the drawings and in accordance with the manufacturers‟
recommendations. Care shall be taken to fix all inlet and outlet pipes at correct positions.
2.4 The sanitary system shall contain the following plumbing appliances:
• Wash hand basins
• Water closets
• Urinals
• Pipes
80
5.7 SECTION 3
DRAINAGE SYSTEM
1.0 SCOPE OF WORK
1.1 Work under this section shall consist of furnishing all labour, materials,equipments and
appliances necessary and required to completely finish drainage system as required by the
architectural drawings.
1.2 Without restricting to the generality of the foregoing, the sewerage system shall include:
Internal/external sewer line.
Storm water drainage and disposal
Construction of collection chambers, manholes and drop connections.
2.0 GENERAL REQUIREMENTS.
2.1 All materials shall be new of the best quality conforming to specifications and subject to
the approval of the Architect.
2.2 Drainage lines shall be laid to the required gradients and profiles.
2.3 All drainage work shall be done in accordance with the local municipal by-laws.
2.4 Location of all manholes, catch basins etc., shall be got confirmed from the contractor
from the Architect before the actual execution of work at site.
2.5 All works shall be executedas directed by Architect.
2.6 All drainage pipes shall be U-PVC pipes.
3.0 ALIGNMENT AND GRADE
The sewer pipes shall be laid to alignment and gradient shall be permitted except by the
express direction in writing of the Architect
5.8 PUMPING SYSTEM SPECIFICATION.
The system consists of suction through the inlet pipe as water is drawn in from the source by
the suction created by the impeller in the pump. The water source consists of an underground
tank found beneath the building in that the suction pipe runs from the outlet of the tank to the
inlet of the specified pump where the water passes through a series of impellers that create a
pressure that pumps the water wither a higher velocity than inlet velocity.
The water runs up the riser main pipe with enough pressure to work against gravity without
much pressure drop to the overhead tanks found on the roof floor of the building. The
position of the overhead tanks are specified on the architectural drawings as shown in the
plan for the roof floor. The water flows into the tanks at a flow rate that will be determined.
After some time when the tanks become filled to the brim the float valve installed into the
tank stops the incoming flow by shutting off the pump.
81
The important components that make up the plumbing systems as specified include:
1. Pump
2. Underground tank
3. Overhead tank
4. Pipework consisting of the material Polypropylene Random Copolymer (PPR – C)
82
CHAPTER SIX – QUANTITY ESTIMATION OF THE DESIGN.
6.1 QUANTITY ESTIMATION USING TRADITIONAL APPROACH.
Incoming water pipework from Nairobi City Council (NCC) to underground and
roof tank
1. Incoming cold water pipework from NCC to underground tank
ITEM DESCRIPTION QUANTITY UNIT
1 Ø25 mm PPR – C tubing chased in wall 5 M
BENDS/ELBOWS
2 Ø25 mm bend 2 No.
VALVES
3 Ø25 mm gate valve 2 No.
4 Ø25 mm float valve 1 No.
2. Incoming Cold water pipework from pump to overhead tank and riser pipes
ITEM DESCRIPTION QUANTITY UNIT
1 Ø40 mm tubing 40 M
BENDS/ELBOWS
2 Ø40 mm bend 7 No.
VALVES
3 Ø40 mm non return valve 1 No.
4 Ø25 mm float valve 1 No.
5 Ø40mm gate valve 2 No.
83
A) COLD WATER PIPEWORK.
1. Roof floor
ITEM DESCRIPTION QUANTITY UNIT
1 Ø40 mm tubing 17 M
BENDS/ELBOWS
2 Ø40 mm bend 4 No.
VALVES
3 Ø40 mm gate valve 1 No.
4 Ø40 mm non return valve 1 No.
TEES
5 Ø40 mm tee 1 No.
2. Terrace
ITEM DESCRIPTION QUANTITY UNIT
1 Ø32 mm tubing 4 M
2 Ø25 mm tubing 4 M
BENDS/ELBOWS
3 Ø25 mm bend 4 No.
TEES
4 Ø32 mm tee 1 No.
5 Ø25 mm tee 2 No.
VALVES
6 Ø25 mm gate valve 2 No.
84
3. Typical floors (1st
2nd
3rd
floors)
ITEM DESCRIPTION QUANTITY UNIT
1 Ø25 mm tubing 4 M
2 Ø20 mm tubing 9 M
BENDS/ELBOWS
3 Ø25 mm bend 2 No.
TEES
4 Ø25 mm tee 1 No.
5 Ø20 mm tee 6 No.
VALVES
6 Ø20 mm gate valve 2 No.
4. Mezzanine floor
ITEM DESCRIPTION QUANTITY UNIT
1 Ø20 mm tubing 8 M
BENDS/ELBOWS
2 Ø20 mm bend 4 No.
TEES
3 Ø20mm tee 3 No.
VALVES
4 Ø20 mm gate valve 2 No.
85
B) DRAINAGE UPVC PIPE SYSTEM AS DESCRIBED AND SHOWN IN THE
DRAWINGS.
1. Mezzanine floor waste drainage
ITEM DESCRIPTION QUANTITY UNIT
1 Ø100 mm Brown UPVC pipe 2 M
2 Ø50 mm Brown UPVC pipe 1 M
BENDS/ELBOWS
3 Ø100 mm sweep 90° bend 1 No.
4 Ø50 mm sweep 90° bend 1 No.
WYE
5 Ø100 mm wye 1 No.
6 Ø50 mm wye 1 No.
STACK VENT PIPE
7 Ø100 mm Brown UPVC Pipe 8 M
2. 1ST
– 3TH
Floor Waste Drainage
ITEM DESCRIPTION QUANTITY UNIT
1 Ø100 mm Brown UPVC Pipe 3 M
2 Ø50 mm Brown UPVC Pipe 3 M
BENDS/ELBOWS
3 Ø100 mm sweep 90° bend 2 No.
4 Ø50 mm sweep 90° bend 2 No.
WYE
5 Ø100 mm wye 1 No.
6 Ø50 mm wye 4 No.
STACK VENT PIPE
7 Ø100 mm Brown UPVC Pipe 8 M
86
3. Terrace Floor Waste Drainage
ITEM DESCRIPTION QUANTITY UNIT
1 Ø100 mm Brown UPVC Pipe 2 M
2 Ø50 mm Brown UPVC Pipe 2 M
BENDS/ELBOWS
3 Ø100 mm sweep 90° bend 1 No.
4 Ø50 mm sweep 90° bend 1 No.
WYE
5 Ø100 mm wye 1 No.
6 Ø50 mm wye 1 No.
STACK VENT PIPE
7 Ø100 mm Brown UPVC Pipe 8 M
4. Roof Floor Waste Drainage
ITEM DESCRIPTION QUANTITY UNIT
STACK VENT PIPE
1 Ø100 mm Brown UPVC Pipe 8 M
2 Ø100 mm Vent Cowl 2 No.
87
6.2 QUANTITY ESTIMATION USING BUILDING INFORMATION
MODELLING (BIM) APPROACH.
Quantity estimation gives a description of the amount of items or elements in the various
systems on the building. This process of estimation is easier done on Revit software
becausethere‟s a list of fields provided which one can use to filter and get the desired
information he would want from the project. (ie Pipe material, size and length, fittings for
the pipe, System Classification etc). Below is a dialogue box that shows a list of available
fields used to filter information.
Fig 6.1 Schedule Properties.
The two systems involved in our building were quantified as follows:-
1. Cold water piping system.
a) Pipe material, size and length.
From the quantity schedule we were able to get the totals of the pipes length required in
our building, size of the pipe and also the material used was also highlighted as shown by
the sample diagram below:-
88
The total length for all the Domestic Cold water pipes in our project is 130.998m.
b) Fittings for the pipes.
From the Pipe Fitting schedule,the total counts for all the fittings on Domestic Cold
Water on the project were deduced, moreover the size and family and type were also
stated. This is indicated by the diagram below.
The total No. of fittings on our project for the Domestic cold water is 186.
89
c) Valves and Accessories
The Pipe Accessory schedules clearly pin pointed the number of valves on the building
and states its size. This is indicated below.
The schedule clearly states that their are 11 gate valves in our building.
2. Sanitary Piping System.
The process done to obtain the length and sizes on the cold water piping system, was also
done for sanitary system and the following was deduced.
a) Pipe material, size and length.
90
b) Fittings for the pipe.
This schedule showed the system classification, size and family and type for the
sanitary system classification. The grand total for all the fittings ( ie Bends, Tee,
Reducer )on the sanitary system has been indicated at the bottom of the table.
91
Location of the systems in the building plan.
Our plumbing systems are located at the centre of the diagram, as seen from the figure
below.
Fig 6.2 Location of the plumbing system.
92
CHAPTER SEVEN – DISCUSSION.
7.1 EVALUATION AND COMPARISON
7.1.1 Analysis of the two Approaches.
Similarities:
Both approaches shared the following basic standard information for the analysis of
the plumbing system:-
1. Selection of the appropriate water distribution system to be used.
2. Design of the water distribution system.
3. Calculation of the daily water requirement for the building.
4. Pipe material selection.
5. Determination of the loading values/loading units.
6. Generation of an appropriate piping layout.
Differences.
AutoCAD: - Pipe sizing analysis for this approach involved manual computations for
the flowrate, Effective Pipe Length (EPL), Permissible Head Loss (PHL) as shown in
the analysis of Cold water piping system.
BIM has inbuilt formulae that is uses to automatically generate value for the required
pipe length, diameter and pressure depending on the input data (ie Fixture units and
velocities borrowed from the traditional approach.)
7.1.2 Efficiency of the two approaches.
In AutoCAD approach, as much as the process was done by manual computations, the
efficiency of the process was only dependent on the assumptions made.( Example Pipe
diameter).
Building Information Modelling generates the pipe system as well as the pressure
report suitable for the plumbing system hence no need for manual calculations
involved with the generation of the above factors as seen in AutoCAD. Thus saving
time and also its more accurate.
7.1.3 Conflict, Interference and collision detection.
BIM models are created to scale, in 3D space. All major systems can be visually
checked for interference. This process can verify that piping does not intersect with
steel beams, ducts or walls as shown below:
93
Fig 7.1 Diagram showing pipe collision.
AutoCAD has 2D visuals hence cannot detect conflicts properly giving BIM an
advantage over it.
7.1.4 Differences in the Quantity take offs and scheduling methods.
Building Information Modelling (BIM) has good scheduling methods due to its
automation. The software has its own built-in quantity take offs procedure whereby it
computes all the required details from the constructed model on the software, hence
giving accurate values.
AutoCAD quantity take off and scheduling are done manually, this clearly makes this
approach prone to human errors.
7.1.5 Detailing of Final design in the two processes.
1. Setting Line Weights.
In AutoCAD, the ability to set multiple layers, and within each layer, adjust color, line
type, line weight, etc., provides a meticulous amount of control but can also be
overwhelming, depending on the complexity of your project.
Revit; however, offers a streamlined approach to setting line weights. You can adjust
the cut or projection line weights of any object via the Manage tab and Object Styles
dialog to set projection. For example, by selecting the pipes category, you can quickly
and easily adjust the line weight by changing the value in the drop-down next to the
category.
94
Fig 7.2 Object Styles.
2. Adding Structural Details.
When wanting to add structural details in AutoCAD, unless you have the time or a
team to focus on creating the detail elements, it can be very time consuming. This is so
because AutoCAD lacks inbuilt components for detail drawing hence requires drawing
and saving these elements manually.
Revit; however, comes with plenty of components for your detail drawings in a
“Detail” family folder available for view in 3D as well as a side view. There‟s no
need to spend anytime drawing and saving these elements manually.
7.1.6 Visualization of final designs in the two processes.
Revit enables the scheduler to view the entire construction site in nutshell. The
scheduler is able to move around, look outside, inside, under the building and verify
the progress of the project. It helps the scheduler to detect inconsistency and avoid
visual incongruities in the representation. Integrated with BIM modeling, 3D
scheduling helps the owner as well as the project team to visualize time constraints
and investment in the project.
95
Fig 7.3 Revit 3D visuals of the cold water pipe connection.
AutoCADoften relies on envisioning the building based on orthogonal drawings or a
small-scale physical model. Visualization such as these can be hampered by the
viewer‟s ability to mentally interpret 2D drawings,
Fig 7.4 AutoCAD 2D visuals of the cold water pipe connection.
7.1.7 Effectiveness of change propagation in the two processes.
Change propagation practices explore how changes made to one version of the
application are migrated to other living versions of the application.
Software maintenance and evolution are inevitable activities since almost all software
that is useful and successful stimulates user – generated requests for change and
improvements. One of the most critical problems is to maintain consistency between
software artefacts by propagating changes correctly. Each component is linked
through a high performance change propagation, allowing a single change in any
model view to be propagated throughout all view, both parametrically and bi –
directionally.
Revit is a change propagation engine that is any revision to the model will
immediately and automatically show in all views, sheets and schedules. All
relationships between components, views and annotations are captured by the model
so that a change to any element would automatically propagate to keep the model
consistent for example, moving a wall would update the neighbouring walls, floors,
96
and roofs, correct the placement and values of dimensions and notes, adjust the floor
areas reported in schedules, redraw section views, etc., so that the model would
remain connected and all documentation would be coordinated
AutoCAD does not possess change propagation capabilities in that changes made to a
model on a single element than has to be repeated manually to other elements in the
model as well. This is especially tiresome as all changes must be foreseen by the
draftsman and captured on the model otherwise there would not be cohesion between
the various elements
7.1.8 Advantages of Building Information Modelling.
BIM offers several key benefits:
a) Improved visualization.
b) Improved productivity due to easy retrieval of information.
c) Increased coordination of construction documents.
d) Increased speed of delivery.
e) Embedding and linking of vital information such as vendors for specific materials,
location of details and quantities required for estimation and tendering.
97
CHAPTER EIGHT – CONCLUSION
The project involves the design of the plumbing system of a commercial building using both
AutoCAD and REVIT Software. The project design of the plumbing system gives the step by
step procedure of the important elements to be applied when designing a plumbing system.
This involved defining the specifications for the water supply system, drainage system, and
the plumbing system. The water supply system involved the supply lines from the overhead
tanks to the corresponding fixtures on the corresponding floor where the water flows by
gravity. The drainage system involves the system put in place to dispose of the liquid waste
that emanates from the fixtures i.e. water closets, urinals and sinks. The drainage pipes run
vertically along the building and emptied at manholes in predetermined areas. The plumbing
system consists of pumping water from the underground tank to the overhead tanks to be
supplied to the building through gravity.
The three individual systems were chosen according to type but with respect to a
predetermined piping layout. According to the traditional approach the schematic was drawn
on AutoCAD, and rigorous manual calculations were dine in order to justify the design as
outlined in the report. Considering the BIM approach, the schematic was drawn to 3D to
outline outstanding features clearly shown. The calculations done with this approach were
relatively automatic using the tools that are in – built.
The two processes were then evaluated according to some specific characteristics with
respect to how the plumbing system was designed using both approaches with each
displaying various advantages and disadvantages.
99
APPENDIX B – QUANTITY SCHEDULES BUILDING
INFORMATION MODELLING.
Quantity Schedule System Classification Material Size Length
Domestic Cold Water PPR-C 20 mmø 0.081
Domestic Cold Water PPR-C 20 mmø 0.027
Domestic Cold Water PPR-C 20 mmø 0.063
Domestic Cold Water PPR-C 15 mmø 0.051
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.051
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 20 mmø 0.073
Domestic Cold Water PPR-C 20 mmø 0.073
Domestic Cold Water PPR-C 20 mmø 0.099
Domestic Cold Water PPR-C 20 mmø 0.073
Domestic Cold Water PPR-C 20 mmø 0.073
Domestic Cold Water PPR-C 20 mmø 0.028
Domestic Cold Water PPR-C 20 mmø 0.027
Domestic Cold Water PPR-C 20 mmø 0.048
Domestic Cold Water PPR-C 20 mmø 0.073
Domestic Cold Water PPR-C 20 mmø 0.073
Domestic Cold Water PPR-C 20 mmø 0.024
Domestic Cold Water PPR-C 20 mmø 0.024
Domestic Cold Water PPR-C 40 mmø 2.676
Domestic Cold Water PPR-C 40 mmø 2.179
Domestic Cold Water PPR-C 40 mmø 7.746
Domestic Cold Water PPR-C 40 mmø 3.606
Domestic Cold Water PPR-C 20 mmø 0.081
Domestic Cold Water PPR-C 15 mmø 0.199
Domestic Cold Water PPR-C 15 mmø 0.005
Domestic Cold Water PPR-C 15 mmø 0.191
Domestic Cold Water PPR-C 20 mmø 0.063
Domestic Cold Water PPR-C 20 mmø 10.879
Domestic Cold Water PPR-C 20 mmø 0.027
Domestic Cold Water PPR-C 20 mmø 0.533
Domestic Cold Water PPR-C 20 mmø 0.041
Domestic Cold Water PPR-C 20 mmø 0.164
100
Domestic Cold Water PPR-C 20 mmø 0.027
Domestic Cold Water PPR-C 20 mmø 3.452
Domestic Cold Water PPR-C 20 mmø 0.319
Domestic Cold Water PPR-C 20 mmø 0.019
Domestic Cold Water PPR-C 20 mmø 2.952
Domestic Cold Water PPR-C 20 mmø 0.102
Domestic Cold Water PPR-C 20 mmø 0.459
Domestic Cold Water PPR-C 20 mmø 0.621
Domestic Cold Water PPR-C 20 mmø 0.319
Domestic Cold Water PPR-C 20 mmø 1.684
Domestic Cold Water PPR-C 15 mmø 0.065
Domestic Cold Water PPR-C 15 mmø 0.065
Domestic Cold Water PPR-C 15 mmø 0.556
Domestic Cold Water PPR-C 20 mmø 1.669
Domestic Cold Water PPR-C 15 mmø 0.556
Domestic Cold Water PPR-C 20 mmø 0.412
Domestic Cold Water PPR-C 20 mmø 0.799
Domestic Cold Water PPR-C 20 mmø 0.525
Domestic Cold Water PPR-C 15 mmø 0.057
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.556
Domestic Cold Water PPR-C 20 mmø 0.211
Domestic Cold Water PPR-C 15 mmø 0.057
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.563
Domestic Cold Water PPR-C 20 mmø 0.419
Domestic Cold Water PPR-C 20 mmø 0.375
Domestic Cold Water PPR-C 20 mmø 0.027
Domestic Cold Water PPR-C 20 mmø 0.019
Domestic Cold Water PPR-C 20 mmø 2.952
Domestic Cold Water PPR-C 20 mmø 0.286
Domestic Cold Water PPR-C 20 mmø 1.538
Domestic Cold Water PPR-C 15 mmø 0.065
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.556
Domestic Cold Water PPR-C 20 mmø 1.756
Domestic Cold Water PPR-C 15 mmø 0.065
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.556
Domestic Cold Water PPR-C 20 mmø 0.432
Domestic Cold Water PPR-C 20 mmø 0.879
Domestic Cold Water PPR-C 20 mmø 0.525
Domestic Cold Water PPR-C 15 mmø 0.052
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.556
Domestic Cold Water PPR-C 20 mmø 0.312
101
Domestic Cold Water PPR-C 15 mmø 0.052
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.563
Domestic Cold Water PPR-C 20 mmø 0.419
Domestic Cold Water PPR-C 20 mmø 0.309
Domestic Cold Water PPR-C 20 mmø 0.027
Domestic Cold Water PPR-C 20 mmø 0.009
Domestic Cold Water PPR-C 20 mmø 1.558
Domestic Cold Water PPR-C 20 mmø 0.326
Domestic Cold Water PPR-C 15 mmø 0.055
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.556
Domestic Cold Water PPR-C 20 mmø 1.814
Domestic Cold Water PPR-C 15 mmø 0.055
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.556
Domestic Cold Water PPR-C 20 mmø 0.412
Domestic Cold Water PPR-C 20 mmø 0.899
Domestic Cold Water PPR-C 20 mmø 0.505
Domestic Cold Water PPR-C 15 mmø 0.079
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.556
Domestic Cold Water PPR-C 20 mmø 0.141
Domestic Cold Water PPR-C 15 mmø 0.079
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.571
Domestic Cold Water PPR-C 20 mmø 0.417
Domestic Cold Water PPR-C 20 mmø 2.952
Domestic Cold Water PPR-C 20 mmø 0.678
Domestic Cold Water PPR-C 20 mmø 0.009
Domestic Cold Water PPR-C 20 mmø 1.559
Domestic Cold Water PPR-C 15 mmø 0.055
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.556
Domestic Cold Water PPR-C 20 mmø 1.686
Domestic Cold Water PPR-C 15 mmø 0.055
Domestic Cold Water PPR-C 15 mmø 0.086
Domestic Cold Water PPR-C 15 mmø 0.563
Domestic Cold Water PPR-C 20 mmø 0.419
Domestic Cold Water PPR-C 40 mmø 1.252
Domestic Cold Water PPR-C 40 mmø 2.101
Domestic Cold Water PPR-C 20 mmø 2.918
Domestic Cold Water PPR-C 20 mmø 0.957
Domestic Cold Water PPR-C 20 mmø 0.437
Domestic Cold Water PPR-C 20 mmø 0.64
Domestic Cold Water PPR-C 20 mmø 0.095
102
Domestic Cold Water PPR-C 20 mmø 0.322
Domestic Cold Water PPR-C 20 mmø 0.082
Domestic Cold Water PPR-C 20 mmø 0.809
Domestic Cold Water PPR-C 20 mmø 0.082
Domestic Cold Water PPR-C 20 mmø 0.81
Domestic Cold Water PPR-C 20 mmø 0.072
Domestic Cold Water PPR-C 20 mmø 0.81
Domestic Cold Water PPR-C 20 mmø 0.112
Domestic Cold Water PPR-C 20 mmø 0.803
Domestic Cold Water PPR-C 20 mmø 0.579
Domestic Cold Water PPR-C 20 mmø 0.027
Domestic Cold Water PPR-C 20 mmø 0.803
Domestic Cold Water PPR-C 20 mmø 0.619
Domestic Cold Water PPR-C 20 mmø 0.097
Domestic Cold Water PPR-C 20 mmø 0.092
Domestic Cold Water PPR-C 20 mmø 0.459
Domestic Cold Water PPR-C 20 mmø 0.677
Domestic Cold Water PPR-C 20 mmø 0.371
Domestic Cold Water PPR-C 20 mmø 0.102
Domestic Cold Water PPR-C 20 mmø 0.459
Domestic Cold Water PPR-C 20 mmø 0.351
Domestic Cold Water PPR-C 20 mmø 0.803
Domestic Cold Water PPR-C 20 mmø 0.279
Domestic Cold Water PPR-C 20 mmø 0.123
Domestic Cold Water PPR-C 20 mmø 0.316
Domestic Cold Water PPR-C 20 mmø 0.803
Domestic Cold Water PPR-C 20 mmø 0.724
Domestic Cold Water PPR-C 20 mmø 0.115
Domestic Cold Water PPR-C 20 mmø 0.303
Domestic Cold Water PPR-C 20 mmø 0.305
Domestic Cold Water PPR-C 20 mmø 0.108
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.08
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.184
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.08
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.082
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.121
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.082
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.077
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.196
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.072
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.072
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.171
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.18
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.687
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.029
Sanitary Polyvinyl Chloride - Rigid 100 mmø 2.738
103
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.018
Sanitary Polyvinyl Chloride - Rigid 100 mmø 5.861
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.498
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.496
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.202
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.147
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.118
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.457
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.241
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.222
Sanitary Polyvinyl Chloride - Rigid 100 mmø 2.197
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.074
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.457
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.352
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.117
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.499
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.343
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.074
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.499
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.352
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.118
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.45
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.181
Sanitary Polyvinyl Chloride - Rigid 100 mmø 2.754
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.074
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.45
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.352
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.031
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.463
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.098
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.225
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.469
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.031
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.336
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.109
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.039
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.495
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.078
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.25
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.502
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.039
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.375
Sanitary Polyvinyl Chloride - Rigid 100 mmø 2.126
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.227
Sanitary Polyvinyl Chloride - Rigid 100 mmø 2.222
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.067
104
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.079
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.444
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.097
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.428
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.064
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.365
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.036
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.444
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.336
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.198
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.457
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.352
Sanitary Polyvinyl Chloride - Rigid 100 mmø 5.248
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.154
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.457
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.205
Domestic Cold Water PPR-C 20 mmø 0.094
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.322
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.104
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.135
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.647
Sanitary Polyvinyl Chloride - Rigid 50 mmø 0.031
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.018
Sanitary Polyvinyl Chloride - Rigid 50 mmø 0.116
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.147
Sanitary Polyvinyl Chloride - Rigid 50 mmø 0.023
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.018
Sanitary Polyvinyl Chloride - Rigid 50 mmø 0.116
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.528
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.329
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.104
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.19
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.667
Sanitary Polyvinyl Chloride - Rigid 50 mmø 0.079
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.018
Sanitary Polyvinyl Chloride - Rigid 50 mmø 0.116
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.468
Sanitary Polyvinyl Chloride - Rigid 50 mmø 0.058
Sanitary Polyvinyl Chloride - Rigid 50 mmø 0.046
Sanitary Polyvinyl Chloride - Rigid 50 mmø 0.116
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.187
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.322
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.747
Sanitary Polyvinyl Chloride - Rigid 50 mmø 0.038
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.018
Sanitary Polyvinyl Chloride - Rigid 50 mmø 0.116
105
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.187
Sanitary Polyvinyl Chloride - Rigid 50 mmø 0.03
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.018
Sanitary Polyvinyl Chloride - Rigid 50 mmø 0.116
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.468
Domestic Cold Water PPR-C 20 mmø 0.056
Domestic Cold Water PPR-C 20 mmø 0.05
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.436
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.401
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.435
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.265
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.202
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.336
Domestic Cold Water PPR-C 20 mmø 0.145
Domestic Cold Water PPR-C 20 mmø 0.1
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.231
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.067
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.242
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.13
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.067
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.834
Domestic Cold Water PPR-C 20 mmø 0.125
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.145
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.104
Domestic Cold Water PPR-C 20 mmø 0.024
Domestic Cold Water PPR-C 20 mmø 0.155
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.185
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.074
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.797
Domestic Cold Water PPR-C 20 mmø 0.013
Domestic Cold Water PPR-C 40 mmø 0.025
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.435
Sanitary Polyvinyl Chloride - Rigid 40 mmø 0.41
Sanitary Polyvinyl Chloride - Rigid 100 mmø 2.7
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.721
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.193
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.094
Sanitary Polyvinyl Chloride - Rigid 100 mmø 2.687
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.828
Sanitary Polyvinyl Chloride - Rigid 100 mmø 2.811
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.132
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.088
Domestic Cold Water PPR-C 20 mmø 0.125
Domestic Cold Water PPR-C 20 mmø 0.151
Domestic Cold Water PPR-C 20 mmø 0.082
Domestic Cold Water PPR-C 20 mmø 0.148
106
Domestic Cold Water PPR-C 20 mmø 0.125
Domestic Cold Water PPR-C 20 mmø 0.059
Domestic Cold Water PPR-C 20 mmø 0.073
Domestic Cold Water PPR-C 20 mmø 0.025
Domestic Cold Water PPR-C 20 mmø 0.177
Domestic Cold Water PPR-C 20 mmø 0.054
Domestic Cold Water PPR-C 20 mmø 0.063
Domestic Cold Water PPR-C 20 mmø 0.025
Domestic Cold Water PPR-C 20 mmø 0.111
Domestic Cold Water PPR-C 20 mmø 0.45
Domestic Cold Water PPR-C 20 mmø 0.058
Domestic Cold Water PPR-C 20 mmø 0.506
Domestic Cold Water PPR-C 20 mmø 0.096
Domestic Cold Water PPR-C 20 mmø 0.345
Domestic Cold Water PPR-C 20 mmø 0.203
Domestic Cold Water PPR-C 20 mmø 0.489
Domestic Cold Water PPR-C 20 mmø 1.948
Domestic Cold Water PPR-C 20 mmø 0.497
Domestic Cold Water PPR-C 40 mmø 3.373
Domestic Cold Water PPR-C 40 mmø 1.504
Domestic Cold Water PPR-C 40 mmø 0.498
Domestic Cold Water PPR-C 32 mmø 0.167
Domestic Cold Water PPR-C 32 mmø 0.259
Domestic Cold Water PPR-C 32 mmø 0.067
Domestic Cold Water PPR-C 40 mmø 17.256
Sanitary Polyvinyl Chloride - Rigid 100 mmø 3.415
Sanitary Polyvinyl Chloride - Rigid 100 mmø 2.701
Sanitary Polyvinyl Chloride - Rigid 100 mmø 1.77
Sanitary Polyvinyl Chloride - Rigid 100 mmø 2.765
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.554
Sanitary Polyvinyl Chloride - Rigid 100 mmø 0.577
Sanitary Polyvinyl Chloride - Rigid 100 mmø 1.716
Domestic Cold Water PPR-C 20 mmø 0.659
Domestic Cold Water PPR-C 20 mmø 0.045
Domestic Cold Water PPR-C 20 mmø 0.179
Domestic Cold Water PPR-C 20 mmø 0.045
347
204.294
107
Pipe Fitting Schedule. System Classification Size Family and Type
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 40 mmø-40 mmø M_Elbow - Generic: Standard
Domestic Cold Water 40 mmø-40 mmø M_Elbow - Generic: Standard
Domestic Cold Water 40 mmø-40 mmø M_Elbow - Generic: Standard
Domestic Cold Water 40 mmø-40 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø-15 mmø M_Tee - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
108
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
109
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 15 mmø-15 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 40 mmø-40 mmø M_Elbow - Generic: Standard
Domestic Cold Water 40 mmø-40 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø-20 mmø M_Cross - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø-20 mmø M_Cross - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø-20 mmø M_Cross - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø-20 mmø M_Cross - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
110
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 40 mmø-40 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 20 mmø-15 mmø M_Transition - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
111
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 50 mmø-20 mmø M_Transition - Generic: Standard
Domestic Cold Water 40 mmø-40 mmø M_Elbow - Generic: Standard
Domestic Cold Water 32 mmø-30 mmø M_Transition - Generic: Standard
Domestic Cold Water 32 mmø-32 mmø M_Elbow - Generic: Standard
Domestic Cold Water 32 mmø-32 mmø M_Elbow - Generic: Standard
Domestic Cold Water 32 mmø-32 mmø M_Elbow - Generic: Standard
Domestic Cold Water 40 mmø-32 mmø M_Transition - Generic: Standard
Domestic Cold Water 40 mmø-40 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø-20 mmø M_Tee - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Domestic Cold Water 20 mmø-20 mmø M_Elbow - Generic: Standard
Grand total: 191
112
Pipe Accessory Schedule
System Classification Overall Size Size Count
Domestic Cold Water 50 mmø-50 mmø 50 mmø-50 mmø 1
Domestic Cold Water 50 mmø-50 mmø 50 mmø-50 mmø 1
Domestic Cold Water 50 mmø-50 mmø 50 mmø-50 mmø 1
Domestic Cold Water 50 mmø-50 mmø 50 mmø-50 mmø 1
Domestic Cold Water 50 mmø-50 mmø 50 mmø-50 mmø 1
Domestic Cold Water 50 mmø-50 mmø 50 mmø-50 mmø 1
Domestic Cold Water 50 mmø-50 mmø 50 mmø-50 mmø 1
Domestic Cold Water 50 mmø-50 mmø 50 mmø-50 mmø 1
Domestic Cold Water 50 mmø-50 mmø 50 mmø-50 mmø 1
Domestic Cold Water 50 mmø-50 mmø 50 mmø-50 mmø 1
Domestic Cold Water 50 mmø-50 mmø 50 mmø-50 mmø 1
116
RECOMMENDATIONS In order for one to carry out an elaborate study of the plumbing system the following areas
which were outside the scope of this project should be considered.
Pump manufactures should be consulted to provide effective pump type and sizes based on
the available ranges and their specifications in terms of efficiencies. This should be done on
the basis of the data provided which is in line with this project.
This design should be used hand in hand with the design manual for water supply in Kenya in
case of a water supply system to enable the designer or engineer to come up with all the
aspects involved in a water supply system.
A catalogue for PPR pipe should be made available to help come up with the design factors
and properties related to the pipe thus making the design process easy and more effective.
Lastly; Revit software being a new product in the field of design, it is highly effective in the
ways discussed above in the project, thus recommended for use in any design project .
117
REFFERENCE.
1. Anonymous. (2010). Introduction to water Pipe Sizing. Retrieved August 2014, from
OBOA: http://www.oboa.on.ca/events/2010/sessions/files/410.pdf
2. Anonymous. (2012). International Plumbing Code 2012. Retrieved August 2014, from
Law Resource: https://law.resource.org/pub/us/code/ibr/icc.ipc.2012.pdf
3. Australian Copper Tube Industry. (2013). The Plumbers Handbook. Retrieved August
2014, from KEMBLA: http://www.kembla.com/assets/Uploads/general-PDFs/The-
Plumbers-Handbook.pdf
4. Autodesk. (2014). BIM Deployment Plan. Retrieved July 30, 2014, from Akcb:
http://www.akcb.com/attachments/bim_deployment_plan_final.pdf
5. Baheti Group. (2010, 6 15). PPR. Retrieved from PPR Pipes: www.pprpipes.com/PPR-
Pipes.htm
6. Bhatia, A. (2012). A Guide to Heating and Cooling load Estimation. Retrieved July 30,
2014, from PDH Online: http://www.pdhonline.org/courses/m196/m196content.pdf
7. Graphisoft. (2014). About BIM. Retrieved September 2014, from Graphisoft:
http://www.graphisoft.com/archicad/open_bim/about_bim/
8. Hall, F., & Greeno, R. (2011). Building Services Handbook. Oxford: Elsevier Limited.
9. Hammoud, D. (2005, 01 28). Pump Fundamentals. Retrieved from Lecture Notes -
Pumps:
www.google.com/url?q=http://www.pumpfundamentals.com/yahoo/lecture_notes.pdf
10. Han Yan, P. D. (2013). Benefits and Barriers of BIM. Retrieved 2014, from homepages:
http://homepages.lboro.ac.uk/~cvpd2/PDFs/294_Benefits%20and%20Barriers%20of%20
Building%20Information%20Modelling.pdf
11. Hergunsel, M. (2013). Thesis on the Benefits of Building Information Modelling.
Retrieved August 2014, from Scribd: http://www.scribd.com/doc/83205152/MHergunsel-
Thesis-BIM
12. Ho, D. B. (2013). Design of cold and hot water systems. Retrieved August 2014, from
Mech. Hong Kong University:
http://www.mech.hku.hk/bse/MEBS6000/mebs6000_1011_03_cold_and_hot_water_desi
gn.pdf
13. Hui, S. C. (2010, 9 2010). MEBS6000. Retrieved 2014, from Design of Cold and Hot
Water Systems - Department of Mechanical Engineering:
www.mech.hku.hk/bse/MEBS6000/mebs6000_0809_03_cold_and_hot_water_design.pdf
118
14. Jin, L. Z. (2008, 24 7). HAC_C05.qxd. Retrieved from Pipe sizing - BSI Shop:
www.yumpu.com/en/document/view/4610711/pipe-sizing-bsi-shop/13
15. Kenya Vision 2030. (2013). Kenya Vision 2030. Retrieved August 2014, from CBC
Global:
http://www.cbcglobal.org/images/uploads/library/KIS2012_Vision_2030_Minister_of_St
ate_Planning,_National_Development_and_Vision_2030.pdf
16. McDonald, M. (2014). Building Information Modeling. Retrieved August 17, 2014, from
Mott McDonald: https://www.mottmac.com/article/2385/building-information-modelling-
bim
17. Moulton, M. (2013). BS6700:2006. Retrieved August 2014, from Moodle Moulton:
http://moodle.moulton.ac.uk/pluginfile.php/155748/mod_resource/content/3/BS6700%20
Domestic%20Water%20Systems%202006.pdf
18. Project and construction services. (2014). Building Information Modeling. Retrieved
september 2014, from PCSCMservices: http://www.pcscmservices.com/serBIM.asp
19. Simon, W., Bokmiller, D., & Hristov, P. (2013). Mastering Autodesk Revit. In D.
Bokmiller, S. Whitbread, & P. Hristov, Mastering Autodesk Revit (pp. 237-343). John
Wiley and Sons Inc.