Page 1: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Risk Management

©USC-CSSE 1

Page 2: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

©USC-CSSE 2

Page 3: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Risk vs Issue

• A Risk is an uncertain event that could impact your chosen path should it be realised.

• Risks are events that are not currently affecting you – they haven’t happened yet. 

• Once a risk is realised, it has the potential to become an Issue

©USC-CSSE 3

Source: http://agile101.net/2009/07/26/agile-risk-management-the-difference-between-risks-and-issues/

Page 4: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Risk Management

• What is risk? • What about problem, concern, issue?

©USC-CSSE 4

Page 5: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Reactively Managing a Software Development Problem

System Integration Time:• We just started integrating the various software components to be used in

our project and we found out that COTS* products A and B can’t talk to one another

• This is a problem, caused by a previously unrecognized risk, that materialized: The risk that two COTS products might not be able to talk to one another; specifically that A and B might not be able to talk to one another)

• We’ve got too much tied up in A and B to change• Our best solution is to build wrappers around A and B to get them to talk via

CORBA**• This will result in:

– a 3 month schedule overrun = $100K contract penalty– a $300K cost overrun

*COTS: Commercial off-the-shelf**CORBA: Common Object Request Broker Architecture

©USC-CSSE 5

Page 6: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Proactively Managing a Risk (assessment)

System Design Time:– A and B are our strongest COTS choices

– But there is some chance that they can’t talk to one another • Probability that A and B can’t talk to one another

= probability of loss: P(L)

• From previous experience, with COTS like A and B, we assess P(L) at 50%

– If we commit to using A and B, and we find out at integration time that they can’t talk to one another

• Size of loss S(L) = $300K + $100K = $400K

• We have a risk exposure of RE = P(L) * S(L) = (.5) * ($400K) = $200K

©USC-CSSE 6

Page 7: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Risk Management Strategy 1:Buying Information

System Design Time:– Let’s spend $30K and 2 weeks prototyping the

integration of A and B– This will buy information on the magnitudes of

P(L) and S(L)– If RE = P(L) * S(L) is small, we’ll accept and

monitor the risk– If RE is large, we’ll use one/some of the other

strategies

©USC-CSSE 7

Page 8: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Other Risk Management Strategies• Risk Avoidance

– COTS product C is almost as good as B, and we know, from having used A and C, that C can talk to A

– Delivering on time is worth more to the customer than the small performance loss

• Risk Transfer– If the customer insists on using A and B, have them establish

a risk reserve, to be used in case A and B can’t talk to each other

• Risk Reduction– If we build the wrappers and the CORBA connections right

now, we add cost but minimize the schedule delay• Risk Acceptance

– If we can solve the A and B interoperability problem, we’ll have a big competitive edge on future procurements

– Let’s do this on our own money, and patent the solution©USC-CSSE 8

Page 9: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Software Risk Management

©USC-CSSE 9

ChecklistsDecision driver analysisAssumption analysisDecomposition

Performance modelsCost modelsNetwork analysisDecision analysisQuality factor analysis

Risk exposureRisk leverageCompound risk reduction

Buying informationRisk avoidanceRisk transferRisk reductionRisk element planningRisk plan integration

PrototypesSimulationsBenchmarksAnalysesStaffingMilestone trackingTop-10 trackingRisk reassessmentCorrective action

Risk Resolution

Risk Assessment

Risk Control

Risk Identification

Risk Analysis

Risk Prioritization

Risk mgmtPlanning

Risk Management

Risk Monitoring

Page 10: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Top 10 Risk Categories: 1989 and 1995

©USC-CSSE 10

1989

1. Personnel shortfalls

2. Schedules and budgets

3. Wrong software functions

4. Wrong user interface

5. Gold plating

6. Requirements changes

7. Externally-furnished components

8. Externally-performed tasks

9. Real-time performance

10. Straining computer science

1995

1. Personnel shortfalls

2. Schedules, budgets, process

3. COTS, external components

4. Requirements mismatch

5. User interface mismatch

6. Architecture, performance, quality

7. Requirements changes

8. Legacy software

9. Externally-performed tasks

10. Straining computer science

Page 11: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Primary CS577 Risk Categories (all on 1995 list) and Examples

• Personnel shortfalls: commitment (This is team member’s last course; only needs C to graduate); compatibility; communication problems; skill deficiencies (management, Web design, Java, Perl, CGI, data compression, …)

• Schedule: project scope too large for 24 weeks; IOC content; critical-path items (COTS, platforms, reviews, …)

• COTS: see next slide re multi-COTS

• Rqts, UI: mismatch to user needs (recall overdue book notices)

• Performance: #bits; #bits/sec; overhead sources

• Externally-performed tasks: Client/Operator preparation; commitment for transition effort

©USC-CSSE 11

Page 12: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

COTS and External Component Risks

• COTS risks: immaturity; inexperience; COTS incompatibility with application, platform, other COTS; controllability

• Non-commercial off-the shelf components: reuse libraries, government, universities, etc.– Qualification testing; benchmarking;

inspections; reference checking; compatibility analysis

©USC-CSSE 12

Page 13: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Risk Exposure Factors(Satellite Experiment Software)

©USC-CSSE 13

Unsatisfactory Outcome (UO) Prob (UO) Loss (UO) Risk ExposureA. S/ W error kills experiment

B. S/ W error loses key data

C. Fault tolerance features cause unacceptable

performance

D. Monitoring software reports unsafe condition

as safe

E. Monitoring software reports safe condition

as unsafe

F. Hardware delay causes schedule overrun

G. Data reduction software errors cause extra

work

H. Poor user interface causes inefficient

operation

I. Processor memory insufficient

J. DBMS software loses derived data

3 - 5

3 - 5

4 - 8

5

5

6

8

6

1

2

10

8

7

9

3

4

1

5

7

2

30 - 50

24 - 40

28 - 56

45

15

24

8

30

7

4

Page 14: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Risk Reduction Leverage (RRL)Change in Risk Exposure / cost to implement avoidance method

©USC-CSSE 14

RRL - RE BEFORE - RE AFTER

RISK REDUCTION COST

· Spacecraft Example

LOSS (UO)PROB (UO)RE

BB

LONG DURATIONTEST

$20M0.2$4M

FAILURE MODETESTS

$20M0.2$4M

PROB (UO)RE A

A

0.05$1M

0.07$1.4M

COST $2M $0.26M

RRL4-12

= 1.54- 1.40.26

= 10

Page 15: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Risk Management Plans

©USC-CSSE 15

For Each Risk Item, Answer the Following Questions:1. Why?

Risk Item Importance, Relation to Project Objectives2. What, When?

Risk Resolution Deliverables, Milestones, Activity Nets3. Who, Where?

Responsibilities, Organization4. How?

Approach (Prototypes, Surveys, Models, …)5. How Much?

Resources (Budget, Schedule, Key Personnel)

Page 16: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Risk Management Plan: Fault Tolerance Prototyping

1. Objectives (The “Why”)– Determine, reduce level of risk of the software fault tolerance features

causing unacceptable performance– Create a description of and a development plan for a set of low-risk fault

tolerance features

2. Deliverables and Milestones (The “What” and “When”)– By week 3

1. Evaluation of fault tolerance option2. Assessment of reusable components3. Draft workload characterization4. Evaluation plan for prototype exercise5. Description of prototype

– By week 76. Operational prototype with key fault tolerance features7. Workload simulation8. Instrumentation and data reduction capabilities9. Draft Description, plan for fault tolerance features

– By week 1010. Evaluation and iteration of prototype11. Revised description, plan for fault tolerance features

©USC-CSSE 16

Page 17: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Risk Management Plan: Fault Tolerance Prototyping (concluded)

• Responsibilities (The “Who” and “Where”)– System Engineer: G. Smith

• Tasks 1, 3, 4, 9, 11, support of tasks 5, 10

– Lead Programmer: C. Lee• Tasks 5, 6, 7, 10 support of tasks 1, 3

– Programmer: J. Wilson• Tasks 2, 8, support of tasks 5, 6, 7, 10

• Approach (The “How”)– Design-to-Schedule prototyping effort– Driven by hypotheses about fault tolerance-performance effects– Use real-time OS, add prototype fault tolerance features– Evaluate performance with respect to representative workload– Refine Prototype based on results observed

• Resources (The “How Much”)$60K - Full-time system engineer, lead programmer, programmer (10

weeks)*(3 staff)*($2K/staff-week)$0K - 3 Dedicated workstations (from project pool)$0K - 2 Target processors (from project pool)$0K - 1 Test co-processor (from project pool)$10K - Contingencies$70K - Total ©USC-CSSE 17

Page 18: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Risk Monitoring

Milestone Tracking– Monitoring of risk Management Plan Milestones

Top-10 Risk Item Tracking– Identify Top-10 risk items– Highlight these in monthly project reviews– Focus on new entries, slow-progress items

Focus review on manger-priority items

Risk Reassessment

Corrective Action

©USC-CSSE 18

Page 19: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Project Top 10 Risk Item List: Satellite Experiment Software

©USC-CSSE 19

Risk Item Mo. RankingThis Last #Mo. Risk Resolution Progress

Replacing Sensor-Control Software 1 4 2 Top Replacement Candidate UnavailableDeveloper

Target Hardware Delivery Delays 2 5 2 Procurement Procedural Delays

Sensor Data Formats Undefined 3 3 3 Action Items to Software, Sensor Teams; Due Next Month

Staffing of Design V&V Team 4 2 3 Key Reviewers Committed; Need Fault- Tolerance Reviewer

Software Fault-Tolerance May 5 1 3 Fault Tolerance Prototype Successful Compromise Performance

Accommodate Changes in Data 6 - 1 Meeting Scheduled With Data Bus Bus Design Designers

Testbed Interface Definitions 7 8 3 Some Delays in Action Items; Review Meeting Scheduled

User Interface Uncertainties 8 6 3 User Interface Prototype Successful

TBDs In Experiment Operational - 7 3 TBDs Resolved Concept

Uncertainties In Reusable - 9 3 Required Design Changes Small, Monitoring Software Successfully Made

Page 20: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Early Risk Management in 577Project Tasks Risk Management Skills; Skill-building activities

Select projects; form teams Project risk identificationStaffing risk assessment and resolution- Readings, lectures, homework, case study, guidelines

Plan early phases Schedule/budget risk assessment, planningRisk–driven processes (ICSM)- Readings, lectures, homework, guidelines, planning and estimating tools

Formulate, validate concept of operation

Risk-driven level of detail- Readings, lecture, guidelines, project

Manage to plans Risk monitoring and control- Readings, lecture, guidelines, project

Develop, validate FC package Risk assessment and prioritization- Readings, lecture, guidelines, project

FC Architecture Review Risk-driven review process

Review of top-N project risks Readings, lecture, case studies, review

©USC-CSSE 20

Page 21: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Software Risk Management TechniquesSource of Risk Risk Management Techniques

1. Personnel shortfalls Staffing with top talent; key personnel agreements; team-building; training; tailoring process to skill mix; walkthroughs

2. Schedules, budgets,Process

Detailed, multi-source cost and schedule estimation; design to cost; incremental development; software reuse; requirements descoping; adding more budget and schedule; outside reviews

3. COTS, external components

Benchmarking; inspections; reference checking; compatibility prototyping and analysis

4. Requirements mismatch

Requirements scrubbing; prototyping; cost-benefit analysis; design to cost; user surveys

5. User interface mismatch

Prototyping; scenarios; user characterization (functionality; style, workload); identifying the real users

©USC-CSSE 21

Page 22: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Software Risk Management TechniquesSource of Risk Risk Management Techniques

6. Architecture, performance, quality

Simulation; benchmarking; modeling; prototyping;instrumentation; tuning

7. Requirements changes High change threshold: information hiding; incrementaldevelopment (defer changes to later increments)

8. Legacy software Reengineering; code analysis; interviewing; wrappers; incremental deconstruction

9. COTS, Externally-performed tasks

Pre-award audits, award-fee contracts, competitive design or Prototyping

10. Straining computerscience

Technical analysis; cost-benefit analysis; prototyping; reference checking

©USC-CSSE 22

Page 23: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Validation Results on Process Adoption

• Incidents of Process Selection and Direction Changes

23

#of teams Results on Project Process Selection

8/14 Selected the right process pattern from the beginning

3/14 Unclear project scope ; re-select right at the end of the Exploration phase

1/14 Minor changes on project scope ; right at the end of the Valuation phase

1/14 Major change in Foundations phase

1/14 Infeasible project scope

©USC-CSSE

Page 24: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Top 10 Risk Categories: 1995 and 2010

1995 2010

1. Personnel shortfalls 1. Customer-developer-user team cohesion

2. Schedules, budgets, process 2. Personnel shortfalls

3. COTS, external components 3. Architecture complexity; quality tradeoffs

4. Requirements mismatch 4. Budget and schedule constraints

5. User interface mismatch 5. COTS and other independently evolving systems

6. Architecture, performance, quality 6. Lack of domain knowledge

7. Requirements changes 7. Process Quality Assurance

8. Legacy software 8. Requirements volatility; rapid change

9. Externally-performed tasks 9. User interface mismatch

10. Straining computer science 10. Requirements mismatch

©USC-CSSE 24

Page 25: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Primary CS577 Risk Categories (all on 1995 list) and Examples

• Personnel shortfalls: commitment (This is team member’s last course; only needs C to graduate); compatibility; communication problems; skill deficiencies (management, Web design, Java, Perl, CGI, data compression, …)

• Schedule: project scope too large for 24 weeks; IOC content; critical-path items (COTS, platforms, reviews, …)

• COTS: see next slide re multi-COTS

• Rqts, UI: mismatch to user needs (recall overdue book notices)

• Performance: #bits; #bits/sec; overhead sources

• Externally-performed tasks: Client/Operator preparation; commitment for transition effort

©USC-CSSE 25

Page 26: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Top 11 - Risk distribution in CSCI577

©USC-CSSE 26

Page 27: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Comparing between risks in Fall and Spring

©USC-CSSE 27

Page 28: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Conclusions• Risk management starts on Day One

– Delay and denial are serious career risks– Data provided to support early investment

• Win Win spiral model provides process framework for early risk resolution– Stakeholder identification and win condition

reconciliation– Anchor point milestones

• Risk analysis helps determine “how much is enough”– Testing, planning, specifying, prototyping,…– Buying information to reduce risk

©USC-CSSE 28

Page 29: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Quality Management

©USC-CSSE 29

Page 30: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Outline

• Quality Management – In CMMI 1.3– In ISO 15288– In CSCI577ab

(c) USC-CSSE 30

Page 31: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Objectives of QM

• To ensure the high quality process • in order to deliver high quality products

(c) USC-CSSE 31

Page 32: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Quality Management in CMMI 1.3

(c) USC-CSSE 32

Process Areas

Configuration Management (CM) Product Integration (PI)

Causal Analysis and Resolution (CAR) Project Monitoring and Control (PMC)

Decision Analysis and Resolution (DAR) Project Planning (PP)

Integrated Project Management (IPM) Quantitative Project Management (QPM)

Measurement and Analysis (MA) Requirements Development (RD)

Organizational Performance Management (OPM)

Requirements Management (REQM)

Organizational Process Definition (OPD) Risk Management (RSKM)

Organizational Process Focus (OPF) Supplier Agreement Management (SAM)

Organizational Process Performance (OPP)

Technical Solution (TS)

Organizational Training (OT) Validation (VAL)

Process and Product Quality Assurance (PPQA)

Verification (VER)

Page 33: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

PPQA - Product and Process Quality Assurance

(c) USC-CSSE 33

Page 34: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

PPQA - Product and Process Quality Assurance

(c) USC-CSSE 34

Page 35: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

PPQA for Agile development

(c) USC-CSSE 35

Page 36: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

CM – Configuration Management

(c) USC-CSSE 36

Page 37: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

CM – Configuration Management

(c) USC-CSSE 37

Page 38: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

CM – Configuration Management

(c) USC-CSSE 38

Page 39: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

MA – Measurement and Analysis

(c) USC-CSSE 39

Page 40: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

VER - Verification

(c) USC-CSSE 40

Page 41: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

VER - Verification

(c) USC-CSSE 41

Page 42: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

VAL - Validation

(c) USC-CSSE 42

Page 43: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

VAL - Validation

(c) USC-CSSE 43

Page 44: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Quality Management in ISO 15288Activitiesa) Plan quality management.

1. Establish quality management policies

2. Establish organization quality management objectives

3. Define responsibilities and authority for implementation of quality management.

b) Assess quality management. 1. Assess customer satisfaction and report.

2. Conduct periodic reviews of project quality plans.

3. The status of quality improvements on products and services is monitored.

c) Perform quality management corrective action. 1. Plan corrective actions when quality management goals are

not achieved.

2. Implement corrective actions and communicate results through the organization.

(c) USC-CSSE 44

Page 45: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Configuration Management in ISO 15288Activities

a)Plan configuration management. 1) Define a configuration management strategy

2) Identify items that are subject to configuration control.

b)Perform configuration managementa) Maintain information on configurations with an

appropriate level of integrity and security

b) Ensure that changes to configuration baselines are properly identified, recorded, evaluated, approved, incorporated, and verified.

(c) USC-CSSE 45

Page 46: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Quality Management in 577ab

• IIV&V• Configuration Management• Defect Reporting and Tracking• Testing• Buddy Review• Architecture Review Board• Core Capability Drive through• Design Code Review• Document template• Sample artifacts

(c) USC-CSSE 46

Page 47: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Quality Guidelines

• Design Guidelines– Describe design guidelines on how to improve

or maintain modularity, reuse and maintenance– How the design will map to the implementation

• Coding Guidelines– Describe how to document the code in such as

way that it could easily be communicated to others

(c) USC-CSSE 47

Page 48: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Coding Guidelines

• C: http://www.gnu.org/prep/standards/standards.html• C++ : http://geosoft.no/development/cppstyle.html• Java: http://geosoft.no/development/javastyle.html• Visual Basic:

http://msdn.microsoft.com/en-us/library/h63fsef3.aspx

(c) USC-CSSE 48

Page 49: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Quality Guidelines

• Version Control and History– Chronological log of the changes introduced to

this unit

• Implementation Considerations– Detailed design and implementation for as-built

considerations

• Unit Verification– Unit / integration test– Code walkthrough / review / inspection

(c) USC-CSSE 49

Page 50: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Quality Assessment Methods

• Methods, tools, techniques, processes that can identify the problems– Detect and report the problem– Measure the quality of the software system

• Three methods of early defect identification– peer review, IIV&V, Automated Analysis

(c) USC-CSSE 50

Page 51: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering

Peer Review

• Reviews performed by peers in the development team– Can be from Fagan’s inspections to simple

buddy checks– Peer Review Items– Participants / Roles– Schedule

(c) USC-CSSE 51

Page 52: University of Southern California Center for Systems and Software Engineering Risk Management ©USC-CSSE1

University of Southern California

Center for Systems and Software Engineering Defect Removal Profiles

(c) USC-CSSE 52