University of Virginia Tunnel C Structural Rehabilitation Permit Set February 3, 2017 Site Work On-Demand Construction WO: 2555325 / PIMS: P04479 SUBMITTED BY: Dewberry 4805 Lake Brook Drive Suite 200 Glen Allen, Virginia 23060 804.290.7957 SUBMITTED TO: University of Virginia 575 Alderman Road Charlottesville, Virginia 22903

Upload: vothien

Post on 15-Apr-2018

227 views

Category:

Documents


4 download

TRANSCRIPT

This text WILL NOT PRINTSize: 11"h x 8.5"wRevised 9.20.12

University of VirginiaTunnel C Structural Rehabilitation

Permit Set

February 3, 2017

Site Work On-Demand Construction

WO: 2555325 / PIMS: P04479

SUBMITTED BY:

Dewberry 4805 Lake Brook Drive Suite 200 Glen Allen, Virginia 23060804.290.7957

SUBMITTED TO:

University of Virginia575 Alderman RoadCharlottesville, Virginia 22903

This page intentionally left blank

Dewberry Engineers Inc. Table of Contents DEI# 50076991 00 01 02 - 1

UNIVERSITY OF VIRGINIA Tunnel C Structural Rehabilitation February 3, 2017 Permit Set Site Work On-Demand Construction Division 00 – Procurement and Contracting Requirements

00 01 02 Table of Contents 02/03/2017 00 01 07 Seals Page 02/03/2017 00 01 15 List of Drawing Sheets 02/03/2017

Prebid/Preproposal Question Form On-Demand Bid Form

HECO-6a&b 2012 Vusbc Statement of Structural & Special Inspections Form & Inspection Checklist

HECO-7 General Conditions of the Construction Contract for Capital Outlay Projects CO-7 Commonwealth Of Virginia General Conditions of the Construction

Contract CO-10.2 Commonwealth Of Virginia Standard Bid Bond

Forms Included by Reference

HECO-7a Instructions to Bidders HECO-9 Contract between University and Contractor HECO-10 Standard Performance Bond HECO-10.1 Standard Labor and Material Payment Bond HECO-11 Contract Change Order HECO-GC-1 Change Order Estimate (General Contractors) HECO-SC-1 Change Order Estimate (Subcontractors) HECO-SS-1 Change Order Estimate (Sub-Subcontractors) HECO-12 Schedule of Values and Certificate for Payment CO-13 Affidavit of Payment of Claims HECO-13.1b 2012 Final Report of Structural and Special Inspections HECO-13.2 Certificate of Completion by Contractor HECO-13.2a Certificate of Partial or Substantial Completion by Contractor

Division 01 – General Requirements

01 00 00 General Requirements 02/03/2017 01 11 00 Summary of Work 02/03/2017 01 14 00 Work Restrictions 02/03/2017 01 18 00 Project Utility Sources 02/03/2017 01 29 00 Payment Procedures 02/03/2017 01 31 00 Project Management and Coordination 02/03/2017 01 33 00 Submittal Procedures 02/03/2017 01 41 00 Regulatory Requirements 02/03/2017 01 43 00 Quality Assurance and Control 02/03/2017

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Table of Contents DEI# 50076991 00 01 02 - 2

01 50 00 Temporary Facilities and Controls 02/03/2017 01 51 00 Temporary Utilities 02/03/2017 01 52 00 Construction Facilities 02/03/2017 01 55 00 Vehicular Access and Parking 02/03/2017 01 56 00 Temporary Barriers and Enclosures 02/03/2017 01 70 00 Execution and Closeout Requirements 02/03/2017 01 78 00 Closeout Submittals 02/03/2017 Division 02 – Existing Conditions

02 41 19 Site Demolition 02/03/2017

Division 03 – Concrete

03 30 00 Cast-In-Place Concrete 02/03/2017

Division 05 – Metals

05 12 00 Structural Steel Framing 02/03/2017 Division 31 – Earthwork

31 10 00 Site Preparation: Clearing and Grubbing 02/03/2017 31 20 00 Earth Moving 02/03/2017 31 23 19 Dewatering 02/03/2017 31 25 00 Erosion and Sediment Control 02/03/2017

Division 32 – Exterior Improvements

32 12 16 Asphalt Paving 02/03/2017

Division 33 – Utilities

33 05 00 Earthwork: Utilities 02/03/2017 Appendix A – Utility Test Hole Reports

END OF SECTION 00 01 02

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. List of Drawing Sheets DEI# 50076991 00 01 15 - 1

SECTION 00 01 15 LIST OF DRAWING SHEETS

GENERAL

T1.01 Cover Sheet 02/03/2017 CIVIL

C0.01 General Notes 02/03/2017 C0.02 Erosion and Sediment Control Notes 02/03/2017 C0.03 Project Impact Coordination Plan 02/03/2017 C0.04 Pedestrian Wayfinding Signage Plan 02/03/2017 C1.01 Existing Site Conditions 02/03/2017

C2.01 Site Demolition and Erosion and Sediment Control Plan – Phase I 02/03/2017 C3.01 Site and Erosion and Sediment Control Plan – Phase II 02/03/2017 C5.01 Erosion and Sediment Control and Construction Details 02/03/2017

STRUCTURAL

S0.01 Structural General Notes, Details, and Schedules 02/03/2017 S3.01 Structural Tunnel Strengthening Plan 02/03/2017 S5.01 Structural Details 02/03/2017 S5.02 Tunnel Strengthening Structural Details 02/03/2017 S5.03 Floor Strengthening Structural Details 02/03/2017

END OF SECTION 00 01 15

This page intentionally left blank

Division 0: Procurement and Contract Documents

www.dewberry.com

PRE-PROPOSAL / PRE-BID QUESTION FORM Use separate form for each question submitted

Date: __________________________

Project: _Tunnel C Structural Rehabilitation_______ PIMS # _P04479 ________________

Project Code: _n/a__________________________________ WO #_2555325_________________

Question concerning Drawing Sheet # ____________:

____________________________________________ _____________________

____________________________________________ _________________________

_____________________________________________________________________

_____________________________________________________________________

_____________________________________________________________________

_____________________________________________________________________

Question concerning Specification Section # ____________, page _________, paragraph _________:

_____________________________________________________________________

_____________________________________________________________________

_____________________________________________________________________

_____________________________________________________________________

_____________________________________________________________________

_____________________________________________________________________

All responses to questions will be made by Amendment / Addendum

Submitted by: (Print) ____________________________ ______ (Sign) ________________ ______

Organization_ _______ Phone #

A/E Firm: _Dewberry Engineers Inc. ______ ATTN: Devin Keeler __ UVA PM: Caitlin Murtaugh ___ Email to: [email protected] and [email protected] A/E (email) UVA Project Manager (email)

This page intentionally left blank

SITE WORK “ON-DEMAND” CONSTRUCTION

BID FORM

Date:

Bidder: University of Virginia, Office of Contract Administration 1000 Ednam Center, Suite 100 Charlottesville, Virginia 22903 (Overnight Delivery) P.O. Box 400892, Charlottesville, VA 22904-4892 (U.S. Mail) ATTN: George Cullen Contract Administrator for Construction

Project Title: Tunnel C Structural Rehabilitation University of Virginia Charlottesville, Virginia UVA Work Order # 2555325 PIMS # P04479 In accordance with the “On-Demand” Construction Request for Proposal, the resulting contract, and the bid documents for the above-referenced project, the undersigned bidder proposes to furnish all supervision, labor, equipment, and materials and to perform all work necessary for construction of the project, in accordance with Plans and Specifications dated 02/03/17, and the Addenda noted below, as prepared by Dewberry Engineers Inc. for the consideration of the following amounts: BASE BID (INCLUDING THE FOLLOWING PARTS): Part A: Lump sum price for all work to rehabilitate approximately 60-LF of 6’x7’ walk-through tunnel and associated appurtenances, complete, and in accordance with the Plans and Specifications: PART A: BASE BID AMOUNT:

Dollars ($ ). (Amount shall be shown in both words and figures. In case of discrepancy, the amount shown in words shall govern.) PART B: EXCAVATION OF ROCK MATERIAL (ESTIMATED QUANTITY OF 200-CY) @ $ per CY =

Dollars ($ ). (Amount shall be shown in both words and figures. In case of discrepancy, the amount shown in words shall govern.) TOTAL BASE BID AMOUNT (FOR PARTS A AND B): Dollars ($ ). (Amount shall be shown in both words and figures. In case of discrepancy, the amount shown in words shall govern.) Bid Guarantee: Attached here is a bid guarantee in the form of a ________________ in the amount of 5%

(five percent) of the total Base Bid Amount (Only required for Base Bid Amount of $1,000,000 or more). Contract award will be based on the TOTAL BASE BID AMOUNT shown above (including any properly submitted bid modifications) plus as many Additive Bid Items as the Owner in its discretion decides to award. Time for Completion: The undersigned understands that time is of the essence and agrees that the date for Substantial Completion of the entire project shall be on or before August 11, 2017, and Final Completion shall be achieved within 30 consecutive calendar days after the date of Substantial Completion as determined by the A/E. The bidder has relied upon the following public historical climatological records: The Virginia State Climatology Office for Charlottesville, Virginia.

Acknowledgment is made of receipt of the following Addenda: If notice of acceptance of this bid is given to the undersigned within 30 days after the opening of bids, or any time thereafter before this bid is withdrawn, the undersigned will execute and deliver a contract in the prescribed form (Contract Between University and Contractor, HECO-9) within 10 days after the contract has been presented to him for signature. The required payment and performance bonds, on the forms prescribed, shall be delivered to the Owner along with the signed contract. Immigration Reform and Control Act of 1986: The undersigned certifies that it does not and will not during the performance of the Contract for this project violate the provisions of the Federal Immigration Reform and Control Act of 1986, which prohibits employment of illegal aliens. Either the undersigned or one of the following individuals, if any, is authorized to modify this bid prior to the deadline for receipt of bids by writing the modification and signing his name on the face of the bid, on the envelope in which it is enclosed, on a separate document, or on a document which is faxed to the University: I certify that the firm name given below is the true and complete name of the bidder and that the bidder is legally qualified and licensed by the Commonwealth of Virginia, Department of Professional and Occupational Regulation, to perform all Work included in the scope of the Contract. (The Bid Form must be signed by a Corporate Officer or a person who has written delegated authority to commit this firm for the purposes described herein by the Owner or Corporate Officer of this firm.) Firm Affix Seal of Incorporation: Authorized Signature Print Name Title: Telephone: Fax: E-mail address: Contractor # FEIN

HECO-6b

2012 Code Version Project Title: Tunnel C Structural Rehabilitation(Revised 12/14)

REQ'D

MATERIAL/ TYPE OF INSPECTION THIS

ACTIVITY (A/E add lines as needed to identify other required items) PROJ ? REFERENCE

Soil Classify & Test Existing Soils & Fill Materials X Specs, 1705.6 X (Spot)

Soil Compaction Of Fill Materials X Specs, 1705.6 X

Soil Bearing At Bottom Of Footing Excavations X Specs, 1705.6 X (Spot)

Piles Driving Records, Tip & Cutoff Elevations 1705.7, 1705.9 X 4

Piles Load Test 1705.7 X 4

Caissons Drilling, Size, Bearing Conditions, Materials 1705.8, 1705.3 X

Concrete Ready-Mix Plant Quality Control X Specs, 1704.2.5 2 X, 1

Concrete Mix Design Tests And Certificates X Specs, 1705.3 X X, 1

Reinf. Steel Shop Drawings Of Reinforcing Steel X Specs X

Reinf. Steel Placement Of Reinforcing Steel X 1705.3 X (Spot) X (Spot) X

Reinf. Steel Welding 1705.2.2 X (Spot) 2 X,1

Formwork Shape, Location, Dimensions X 1705.3 X (Spot) X X

Formwork Removal and Reshoring X 1705.3 X (Spot)

Concrete Test Cylinders & Strength Test X 1705.3, 1910.10 X 4

Concrete Mix Proportions & Mix On Delivery Tickets X 1705.3 X (Spot)

Concrete Slump Test X 1705.3 X 4 X

Concrete Placement Procedures X 1705.3 X X (Spot) X (Spot)

Concrete Curing Temperatures & Techniques X 1705.3 X X

Prestressed Prestressing Procedures & Forces 1705.3 X 2 X,1

Prestressed Shop Drawings Of Prestressed Units Specs X

Precast Quality Control Of Manufacturer 1704.2.5 2 X, 1

Precast Shop Drawings Of Precast Specs X

Precast Erection Of Precast 1705.3 X (Spot) X (Spot) X X

Precast Inspection Of Connections 1705.3 X (Spot)

Anchors Anchors Cast In Concrete X Specs, 1705.2.1, 1909 X (Spot)

Anchors Post Installed (Mechanical & Adhesive) X 033000 Spec X (Spot)

INSPECTION / TEST BY *

2012 VUSBC SPECIAL INSPECTIONS

PROJECT

INSPECTOR

CONTRACTOR /

SUPPLIER

FOUNDATIONS

CONCRETE CONSTRUCTION

WO: 2555325; PIMS: P04479

OWNER'S

TEST LAB

A/E OF

RECORD

SMOKE

CONTROL

HECO-6b

2012 Code Version Project Title: Tunnel C Structural Rehabilitation(Revised 12/14)

REQ'D

MATERIAL/ TYPE OF INSPECTION THIS

ACTIVITY (A/E add lines as needed to identify other required items) PROJ ? REFERENCE

INSPECTION / TEST BY *

2012 VUSBC SPECIAL INSPECTIONS

PROJECT

INSPECTOR

CONTRACTOR /

SUPPLIER

WO: 2555325; PIMS: P04479

OWNER'S

TEST LAB

A/E OF

RECORD

SMOKE

CONTROL

Quality Assurance Indicate Quality Assurance Level (A, B or C) ACI 530, 1.19.1, 2, 3 X

Clay Masonry Certificates, Tests & Technical Data ACI 530, Table 1.19.1 X (Spot) X 3

Concrete Masonry Certificates, Tests & Technical Data ACI 530, Table 1.19.1 X (Spot) X 3

Reinf. Steel Shop Drawings Specs X

Reinf. Steel Size, Grade, Type, Location, Spacing Of Reinf Steel ACI 530, Table 1.19.1 X (Spot)

Anchors Manufacturer's Data ACI 530, Table 1.19.1 X (Spot) X 3

Accessories Manufacturer's Data Specs X 3

Mortar & Grout Mix Design And Data Specs X 3

Mortar & Grout Field Samples ACI 530, Table 1.19.1 X (Spot) 4

Risk Cat. IV A/E Shall edit list as required by ACI 530 Tables 1.19.2, 1.19.3 X

Fabricator Quality Control Inspection Of Shop X 1704.2.5 2 X, 1

Fasteners Mfr's Certificate Of Compliance X AISC 360-10 2 3

Struct. Steel Mfr's Certificate Of Compliance X AISC 360-10 2 3

Weld Matl's Manufacturer's Certificate Of Compliance X AISC 360-10 2 3

Metal Decking Welding to Supports 1705.2.2 X (Spot)

Metal Decking Manufacturer's Certificate Of Compliance 1705.2.2 2 3

Details Shop Drawings Review X Specs X

Erection Installation Of High-Strength Bolts X AISC 360-10 X (Spot)

Erection Welding X AISC 360-10 X (Spot)

Erection Steel Framing And Connections X AISC 360-10 X (Spot) X (Spot) X

Grout Installation of High-Strength Non-Shrink Grout X 1705.2 X (Spot)

STEEL CONSTRUCTION

MASONRY CONSTRUCTION

HECO-6b

2012 Code Version Project Title: Tunnel C Structural Rehabilitation(Revised 12/14)

REQ'D

MATERIAL/ TYPE OF INSPECTION THIS

ACTIVITY (A/E add lines as needed to identify other required items) PROJ ? REFERENCE

INSPECTION / TEST BY *

2012 VUSBC SPECIAL INSPECTIONS

PROJECT

INSPECTOR

CONTRACTOR /

SUPPLIER

WO: 2555325; PIMS: P04479

OWNER'S

TEST LAB

A/E OF

RECORD

SMOKE

CONTROL

( Note: SDC refers to Seismic Design Category. )

Structural Steel Welding and Bolting 1705.11.1 X (Spot)

Wood Field Glueing 1705.11.2 X

Wood Fastening Of Seismic Force Resistance System 1705.11.2 X (Spot) X

Light Gage Steel Fastening 1705.11.3 X (Spot) X

Components Mechanical & Electrical - Anchorage and Labeling (SDC = C) 1705.11.4, 1705.11.6 X (Spot)

Components Architectural - Cladding, Veneer, Non-Bearing Walls (SDC = D) 1705.11.5 X (Spot)

Components Access Floors (SDC = D) 1705.11.5.1 X (Spot)

Components Storage Racks (SDC = D) 1705.11.7 X (Spot)

Concrete Reinforcing Steel (SDC=B) 1705.12.1 2 3

Fabrication Quality Control Inspection Of Shop 1704.2.5 2 X, 1

Wood Grade Stamp Specs, 1703.5 X (Spot) X

Wood/Light Gage Fastening Per Code And Drawings 1705.2.2.1.1, 1705.5.1 X (Spot) X

Trusses Shop Drawings Specs X

Trusses Truss Placement, Bracing and Fastening & Anchorage Specs, 1705.5.2 X (Spot) X

Laminates Shop Drawings Specs X

Laminates Identification Per Shop Drawings Specs X (Spot) X

Sheathing Grade Stamp, Thickness & Fastening Specs, 1705.5.1 X X (Spot) X

WOOD & LIGHT GAGE STEEL CONSTRUCTION

SEISMIC FORCE RESISTANCE INSPECTIONS (as required by VUSBC 1705.11)

SEISMIC RESISTANCE TESTING (as required by VUSBC 1705.12)

HECO-6b

2012 Code Version Project Title: Tunnel C Structural Rehabilitation(Revised 12/14)

REQ'D

MATERIAL/ TYPE OF INSPECTION THIS

ACTIVITY (A/E add lines as needed to identify other required items) PROJ ? REFERENCE

INSPECTION / TEST BY *

2012 VUSBC SPECIAL INSPECTIONS

PROJECT

INSPECTOR

CONTRACTOR /

SUPPLIER

WO: 2555325; PIMS: P04479

OWNER'S

TEST LAB

A/E OF

RECORD

SMOKE

CONTROL

Spray-on Manufacturer's Data Specs X 3

Spray-on Surface Conditions 1705.13.2 X

Spray-on Application 1705.13.3 X 3

Spray-on Thickness 1705.13.4 X

Spray-on Density 1705.13.5 X

Spray-on Bond Strength 1705.13.6 X

Mastic/Intumescent Fire-Resistant Coatings - Materials, Application 1705.14 X X (Spot) X 3

GWB Fireproof Manufacturer's Data Specs X 3

GWB Fireproof Placement Of Materials Specs X (Spot) X

Fire Wall Assembly Manufacturer's Data Specs, 706.2 X 3

Fire Wall Assembly Placement Of Materials Specs, 706.2 X (Spot) X

Materials Manufacturer's Data Specs X 3

Preparation Condition Of Substrate Specs, 1705.15.1 X (Spot) X

Application Methods, Proportions & Thickness Of Installation Specs, 1705.15.1 X (Spot) X (Spot) X

Ducts Device Location And Air Duct Leakage 1705.17.1 X

System Pressure Difference, Flow Measurements & Detection Testing 1705.17.1 X

Controls Activation Sequence 1705.17.1 X

EXTERIOR INSULATION & FINISH SYSTEMS (EIFS)

SMOKE CONTROL (see note 5 )

FIREPROOFING

HECO-6b

2012 Code Version Project Title: Tunnel C Structural Rehabilitation(Revised 12/14)

REQ'D

MATERIAL/ TYPE OF INSPECTION THIS

ACTIVITY (A/E add lines as needed to identify other required items) PROJ ? REFERENCE

INSPECTION / TEST BY *

2012 VUSBC SPECIAL INSPECTIONS

PROJECT

INSPECTOR

CONTRACTOR /

SUPPLIER

WO: 2555325; PIMS: P04479

OWNER'S

TEST LAB

A/E OF

RECORD

SMOKE

CONTROL

NOTES:1.

2.

3.

4.

5.

6.

following criteria:

independent inspection, testing or quality assurance agency attesting that the plant meets at least one of the

materials/products.

c. The plant has an in-shop quality assurance inspection program by an independent testing

inspections shall not be less than one every six months.

agency to conduct periodic in-plant quality assurance inspections. The frequency of these

A/E shall review fabricator/supplier/producer certificates for conformance with appropriate

Fabricator, supplier, ready-mixed plant or other production plant shall provide certificates from an approved

or quality assurance agency for the work/product to be provided on this project.

standards of practice and quality assurance.

Contractor/supplier shall submit manufacturer's certificates of compliance for the

a. The plant is a certified production plant meeting the quality assurance standards of a

Unless noted otherwise, the reference numbers listed refer to the 2012 VUSBC.

Reviews records and test results for conformance with requirements.

Special Inspection firm shall have expertise in fire protection engineering, mechanical engineering, and

certification as an air balancer. The special inspector listed on the cover page and the Agency are

responsible for verifying that the inspector (s) for smoke control is qualified as required by VUSBC 1705.17.2.

b. The plant maintains an agreement with an independent inspection or quality assurance

recognized national standards organization for that product.

HECO-7 (7/14/15) Page 1 of 8

1

HECO-7

GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT FOR CAPITAL OUTLAY PROJECTS

1. This addendum, HECO-7, modifies the Commonwealth of Virginia’s General Conditions

of the Construction Contract DGS-30-054 Form CO-7 (04/15), (attached) for use on all Capital Outlay Projects.

2. For all forms referenced in the attachment by ‘‘CO-”, replace ‘‘CO-” with ‘‘HECO-,’’ except the CO-9a and CO-13.

3. In §1, add definition for the term “Rules,” as follows:

Rules: The Rules Governing Procurement of Goods, Services, Insurance, and Construction, attached as Attachment 1 to that certain Policy Governing the Procurement of Goods, Services, Insurance, and Construction, and the Disposition of Surplus Materials adopted by the Board of Visitors of the University of Virginia, attached as Exhibit P to that certain Management Agreement dated November 15, 2005, by and between the Commonwealth of Virginia and The Rector and Visitors of the University of Virginia, as amended (Chapters 933 and 943 of the 2006 Acts of Assembly, as amended by Chapters 675 and 685 of the 2009 Acts of Assembly and Chapters 116 and 161 of the 2011 Acts of Assembly).

4. In §2(a), delete the words “Commonwealth of Virginia in its Construction and

Professional Services Manual” and insert in their place the words “University of Virginia in its Higher Education Capital Outlay Manual.”

5. In §3(e), delete the words “Building Official for State-owned Buildings” and insert in their place the words “Building Official for the University.”

6. Delete §4(a) and insert the following in its place:

(a) §10 of the Rules shall be applicable. It provides as follows:

HECO-7 (7/14/15) Page 2 of 8

2

1. During the performance of this contract, the contractor agrees as follows:

a. The contractor will not discriminate against any employee or applicant for employment because of race, religion, color, sex, national origin, age, disability, or other basis prohibited by state law relating to discrimination in employment, except where there is a bona fide occupational qualification reasonably necessary to the normal operation of the contractor. The contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this nondiscrimination clause.

b. The contractor, in all solicitations or advertisements for employees placed by or on behalf of the contractor, will state that such contractor is an equal opportunity employer.

c. Notices, advertisements and solicitations placed in accordance with federal law, rule or regulation shall be deemed sufficient for the purpose of meeting the requirements of this section.

2. The contractor will include the provisions of the foregoing paragraphs a, b and c in every subcontract or purchase order of over $10,000, so that the provisions will be binding upon each subcontractor or vendor.

7. Delete §5(a) and insert the following in its place:

(a) §11 of the Rules shall be applicable. It provides as follows:

“During the performance of this contract, the contractor agrees to (i) provide a drug-free workplace for the contractor’s employees; (ii) post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the contractor's workplace and specifying the actions that will be taken against employees for violations of such prohibition; (iii) state in all solicitations or advertisements for employees placed by or on behalf of the contractor that the contractor maintains a drug-free workplace; and (iv) include the provisions of the foregoing clauses in every subcontract or purchase order of over $10,000, so that the provisions will be binding upon each subcontractor or vendor.

HECO-7 (7/14/15) Page 3 of 8

3

For the purposes of this section, ‘drug-free workplace’ means a site for the performance of work done in connection with a specific contract awarded to a contractor in accordance with these Rules, the employees of whom are prohibited from engaging in the unlawful manufacture, sale, distribution, dispensation, possession or use of any controlled substance or marijuana during the performance of the contract.”

8. Delete §8(a) and insert the following in its place:

For contracts with a value exceeding one million dollars ($1,000,000), the Contractor shall deliver to the Owner or its designated representative, a University of Virginia Standard Performance Bond (HECO-10) and Standard Labor and Material Payment Bond (Form HECO-10.1), each fully executed by the Contractor and one or more surety companies legally licensed to do business in Virginia and each in an amount equal to one hundred percent (100%) of the accepted bid. If more than one Surety executes a bond, each shall be jointly and severally liable to the Owner for the entire amount of the bond. Sureties shall be selected by the Contractor, subject to approval by the Owner. No payment on the Contract shall be due and payable to the Contractor until the bonds have been approved by the Owner and the Office of the Attorney General of Virginia. In order to facilitate review of the bonds by the Office of the Attorney General, the power of attorney from the surety company to its agent who executes the bond shall be attached to the bond.

9. In §8(b), delete the references to “§2.2-4337.A.2 of the Code of Virginia” and insert in

their place references to “§29(A)(2) of the Rules.”

10. In §8(c), delete the reference to “§2.2-4338 of the Code of Virginia” and insert in its place a reference to “§30 of the Rules.”

11. In §8(d), delete the reference to “five hundred thousand dollars ($500,000)” and insert in its place a reference to “one million dollars ($1,000,000).

12. In §11(b), delete the reference to “§2.2-4332 of the Code of Virginia” and insert in its place a reference to “§25 of the Rules.”

13. Delete §11(c) and insert the following in its place:

(c) During the performance of the Work under this Contract, the Contractor shall maintain Commercial General Liability insurance to include Premises / Operations Liability,

HECO-7 (7/14/15) Page 4 of 8

4

Products and Completed Operations Coverage, Independent Contractor's Liability, Owner's and Contractor's Protective Liability, Contractual, and Personal Injury Liability, which shall insure him against claims of personal injury, including death, as well as against claims for property damage, which may arise from operations under this Contract, whether such operations be by himself or by any Subcontractor, or by anyone directly or indirectly employed by either of them. The amounts of general liability insurance shall be not less than $1,000,000 per occurrence and $2,000,000 aggregate combined limit. The Commonwealth of Virginia, The Rector and Visitors of the University of Virginia, and their respective officers, employees and agents, shall be named as additional insureds with respect to the Work being procured. The Supplemental General Conditions may require the Contractor to provide an Umbrella insurance policy in a specified amount for the Project.

14. Delete §11(e) and insert the following in its place:

(e) The Asbestos Contractor or Subcontractor, as the case may

be, shall provide occurrence-based liability insurance with asbestos coverages in an amount not less than $1,000,000 and shall name the following as additional insureds: The Commonwealth of Virginia, The Rector and Visitors of the University of Virginia, their respective officers, employees and agents; the Architect/Engineer (if not the Asbestos Project Designer); and the Contractor (where the asbestos work is being performed by the Asbestos Subcontractor). In those cases where only claims-made liability insurance is available, the policy will remain in force throughout the time of the asbestos work and for a minimum of two years beyond the completion of the work without coverage interruption, and if coverage is discontinued within that two year period, the extended reporting period endorsement must be added to the policy to cover the two year requirement beyond work completion.

15. In §12 delete the entire existing section and section title and insert the following in its

place:

“12. INSURANCE FOR OWNER, UNIVERSITY, AND CM/GC

HECO-7 (7/14/15) Page 5 of 8

5

(a) The University maintains property insurance on existing buildings (including fire, vandalism, and extended coverage).

(b) For all projects the CM/GC, at its cost, shall obtain and maintain in the names of the Owner, University, and CM/GC, Builders’ Risk Insurance for the total Project in an amount equal to one hundred percent (100%) of the construction Contract Price.

(c) Builders’ Risk Insurance shall be adjusted as required if the Contract Price changes.

(d) Insurance agreements shall include a provision that the

University may take occupancy of portions of the Work as it is completed, and prior to Substantial Completion of the Work, and that the Builders’ Risk Insurance provided by the CM/GC shall continue until the University accepts the entire, completed Work, unless alternative insurance coverage has been approved by the University’s Office of Risk Management (i.e. University property coverage of completed and occupied areas).

(e) The amount of any deductible must be acceptable to the

University. The CM/GC will be liable for any deductible whenever a claim arises.

(f) The loss, if any, is to be made adjustable with and payable

to the Owner and University, in accordance with its interests, as they may appear.

(g) The Owner and University and their officers, employees,

and its agents, shall be named as additional insured in any liability policy of insurance issued.

(h) Written evidence of the insurance shall be filed with the

University no later than thirty (30) days following the award of the construction phase Contract. In the event of cancellation of this insurance, not less than thirty (30) days prior written notice must be sent to the University. A copy of the policy or certificate of insurance shall be given to the University upon demand.

HECO-7 (7/14/15) Page 6 of 8

6

(i) The value of the Builders’ Risk Insurance shall include the costs of excavations, backfills, foundations, underground utilities, and site work.

(j) The CM/GC and the individual Subcontractors and CM

Agency Trade Contractors are responsible for providing any desired coverage for their buildings, equipment, materials, tools, or supplies that are on-site.

(k) Any insurance provided through the University on

buildings, construction, additions, or renovations will not extend to the CM/GC nor the individual Subcontractors and CM Agency Trade Contractors buildings, equipment, materials, tools, or supplies unless these items are to become property of the Owner upon completion of the Project and the Owner has assumed responsibility for such items at the time of the loss.

(l) Subcontractors and CM Agency Trade Contractors are covered under the CM/GC’s Builders’ Risk Insurance policy and need not provide Builders’ Risk Insurance.

16. In §13, delete the last sentence.

17. In §36(d), delete the reference to “§2.2-4333 of the Code of Virginia” and insert in its

place a reference to “§26 of the Rules.”

18. Delete §36(i) and insert the following in its place:

(i) Interest. (1) Interest shall accrue, at the rate determined pursuant to

subsection 2, on all amounts owed by the Owner to the Contractor that remain unpaid after seven (7) days following the payment date.

(2) The rate of interest charged the Owner pursuant to

subsection 1 shall be the base rate on corporate loans (prime rate) at large United States money center commercial banks as reported daily in the publication entitled The Wall Street Journal. Whenever a split prime rate is published, the lower of the two rates shall be used. However, in no event shall the rate of interest charged exceed the rate of interest established pursuant to §58.1-1812 of the Code of Virginia.

HECO-7 (7/14/15) Page 7 of 8

7

(3) Notwithstanding subsection 1, no interest penalty shall be charged when payment is delayed because of disagreement between the Owner and the Contractor regarding the quantity, quality or time of delivery of goods or services or the accuracy of any invoice received for the goods or services. The exception from the interest penalty provided by this subsection shall apply only to that portion of a delayed payment that is actually the subject of the disagreement and shall apply only for the duration of the disagreement.

(4) This section shall not apply to retainage during the period

of time prior to the date the final payment is due. (5) Notwithstanding subsection 1, no interest penalty shall be

paid to any debtor on any payment, or portion thereof, withheld pursuant to the Comptroller’s Debt Setoff Program, as authorized by the Virginia Debt Collection Act (§2.2-4800 et seq. of the Code of Virginia), commencing with the date the payment is withheld. If, as a result of an error, a payment or portion thereof is withheld, and it is determined that at the time of setoff no debt was owed to the Commonwealth of Virginia, then interest shall accrue at the rate determined pursuant to subsection 2 on amounts withheld that remain unpaid after seven days following the payment date.

(6) These same provisions relating to payment of interest to the

Contractor shall apply also to the computation and accrual of interest on any amounts due from the Contractor to the Owner for deductive change orders and to amounts due on any claims by the Owner.

(7) The date of mailing of any payment by the U.S. Mail is

deemed to be the date of payment to the addressee. 19. In §37, delete the references to §2.2-4354, Code of Virginia” and insert in their place

references to “§45 of the Rules.”

20. In §38(a), delete the last sentence in the first paragraph and insert the following in its place:

The Contractor agrees and understands that the authority of the Owner’s designee is limited by §8 of the Rules and any applicable statute.

HECO-7 (7/14/15) Page 8 of 8

8

21. In §38(b), delete the last sentence in the second paragraph and insert the following in its place:

Changes to the Contract time and/or Price shall be effective when signed by both parties.

22. In §43(f), delete the reference to “§2.2-4335 of the Code of Virginia” and insert in its place a reference to “§27 of the Rules.”

23. In §47, delete the respective references to §§2.2-4363, 2.2-4364, 2.2-4365 and 2.2-4366 of the Code of Virginia and insert in their place references to §§53, 54, 55 and 56 of the Rules, respectively.

DGS-30-054 CO-7 (04/15)

1

COMMONWEALTH OF VIRGINIA

GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT

TABLE OF CONTENTS SECTION TITLE PAGE

1. DEFINITIONS 3

2. CONTRACT DOCUMENTS 7

3. LAWS AND REGULATIONS 7

4. NONDISCRIMINATION 9

5. PROHIBITION OF ALCOHOL AND OTHER DRUGS 10

6. TIME FOR COMPLETION 10

7. CONDITIONS AT SITE 11

8. CONTRACT SECURITY 12

9. SUBCONTRACTS 13

10. SEPARATE CONTRACTS 13

11. CONTRACTOR'S AND SUBCONTRACTOR'S INSURANCE 14

12. "ALL-RISK" BUILDER'S RISK INSURANCE 15

13. TAXES, FEES AND ASSESSMENTS 15

14. PATENTS 15

15. ARCHITECT/ENGINEER'S STATUS 16

16. INSPECTION 17

17. SUPERINTENDENCE BY CONTRACTOR 19

18. CONSTRUCTION SUPERVISION, METHODS AND PROCEDURES 19

19. SCHEDULE OF THE WORK 20

20. SCHEDULE OF VALUES AND CERTIFICATE FOR PAYMENT 23

21. ACCESS TO WORK 24

22. SURVEYS AND LAYOUT 24

23. PLANS AND SPECIFICATIONS 25

24. SUBMITTALS 26

25. FEES, SERVICES AND FACILITIES 28

DGS-30-054 CO-7 (04/15)

2

26. EQUALS 29

27. AVAILABILITY OF MATERIALS 29

28. CONTRACTOR'S TITLE TO MATERIALS 29

29. STANDARDS FOR MATERIALS INSTALLATION & WORKMANSHIP 29

30. WARRANTY OF MATERIALS AND WORKMANSHIP 30

31. USE OF SITE AND REMOVAL OF DEBRIS 31

32. TEMPORARY ROADS 32

33. SIGNS 32

34. PROTECTION OF PERSONS AND PROPERTY 32

35. CLIMATIC CONDITIONS 32

36. PAYMENTS TO CONTRACTOR 33

37. PAYMENTS BY CONTRACTOR 37

38. CHANGES IN THE WORK 37

39. EXTRAS 43

40. CONTRACTOR'S RIGHT TO STOP WORK OR TERMINATE THE CONTRACT 43

41. OWNER'S RIGHT TO TERMINATE THE CONTRACT FOR CAUSE 44

42. TERMINATION BY OWNER FOR CONVENIENCE 45

43. DAMAGES FOR DELAYS; EXTENSION OF TIME 45

44. INSPECTION FOR SUBSTANTIAL COMPLETION & FINAL INSPECTION 48

45. GUARANTEE OF WORK 49

46. ASSIGNMENTS 50

47. CONTRACTUAL DISPUTES 51

48. ASBESTOS 52

49. TRAINING, OPERATION AND MAINTENANCE OF EQUIPMENT 52

50. PROJECT MEETINGS 53 51. SMALL BUSINESSES AND WOMEN-OWNED AND MINORITY-OWNED (SWAM) 54

BUSINESS PROCUREMENT PLAN

PLEASE NOTE: The CO-7, General Conditions of the Construction Contract, has been created specifically for the use of agencies of the Commonwealth of Virginia, which may not alter any provisions without the express written approval of the Virginia Department of General Services, Division of Engineering and Buildings. The General Conditions have significant legal implications and shall not be altered or modified. Nothing in the CO-7, General Conditions of the Construction Contract, shall be amended or deleted or its intent changed, except by an approved and properly issued Supplemental General Condition. The Commonwealth makes no representation as to their suitability for any other purpose. (Note: Political subdivisions intending to modify the General Conditions for their use should consult with their legal counsel.)

DGS-30-054 CO-7 (04/15)

3

1. DEFINITIONS Whenever used in these General Conditions of the Construction Contract ("General Conditions") or in the Contract Documents, the following terms have the meanings indicated, which are applicable to both the singular and plural and the male and female gender thereof: Agency: The Agency, institution or department which is a party to the Contract. For purposes of the Contract, the term Owner shall include such Agency, whether or not the Agency owns the site or the building. Architect, Engineer, Architect/Engineer or A/E: The term used to designate the Architect and/or the Engineer that contracts with the Owner to provide the Architectural and Engineering services for the Project. The A/E is a separate contractor and not an agent of the Owner. The term includes any associates or consultants employed by the A/E to assist in providing the A/E services. Beneficial Occupancy: The condition after Substantial Completion but prior to Final Completion of the Project at which time the Project, or portion thereof, is sufficiently complete and systems operational such that the Owner could, after obtaining necessary approvals and certificates, occupy and utilize the space for its intended use. Guarantees and warranties applicable to that portion of the Work begin on the date the Owner accepts the Project, or a portion thereof, for such Beneficial Occupancy, unless otherwise specified in the Supplemental General Conditions or by separate agreement. Change Order: A document (Form CO-11) issued on or after the effective date of the Contract Between Owner and Contractor (Form CO-9) which is agreed to by the Contractor and approved by the Owner, and which authorizes an addition, deletion or revision in the Work, including any adjustment in the Contract Price and/or the Contract Completion Date. The term Change Order shall also include written orders to proceed issued pursuant to Section 38 (a) (3). A Change Order, once signed by all parties, is incorporated into and becomes a part of the Contract. Code of Virginia: 1950 Code of Virginia as amended. Sections of the Code referred to herein are noted by § xx-xx. Construction: The term used to include new construction, reconstruction, renovation, restoration, major repair, demolition and all similar work upon buildings and ancillary facilities, including any draining, dredging, excavation, grading or similar work upon real property. Contract: The Contract Between Owner and Contractor, Form CO-9, hereinafter referred to as the Contract. Contract Completion Date: The date by which the Work must be substantially complete. The Contract Completion Date is customarily established in the Notice to Proceed, based on the Time for Completion. In some instances, however, the Contract contains a mandatory Contract Completion Date, which shall be stated in the Invitation for Bid or Request for Proposal, as applicable. Contract Documents: The Contract between Owner and Contractor (Form CO-9) signed by the Owner and the Contractor and any documents expressly incorporated therein. Such incorporated documents customarily include the bid submitted by the Contractor, these General Conditions, any Supplemental General Conditions, any Special Conditions, the plans and the specifications, and all modifications, including addenda and subsequent Change Orders. Contract Price: The total compensation payable to the Contractor for performing the Work, subject to modification by Change Order. Contractor: The person with whom the Owner has entered into a contractual agreement to do the Work on this project.

DGS-30-054 CO-7 (04/15)

4

Date of Commencement: the date as indicated in the written Notice to Proceed, the receipt of the earliest Building Permit, or a date mutually agreed to between the Owner and Contractor in writing, whichever is the latest. Day(s): Calendar day(s) unless otherwise noted. Defective: An adjective which, when modifying the word Work, refers to Work that is unsatisfactory, faulty, deficient, does not conform to the Contract Documents or does not meet the requirements of inspections, standards, tests or approvals required by the Contract Documents, or Work that has been damaged prior to the A/E's recommendation of Final Payment (unless responsibility for the protection thereof has been assumed by Owner at Substantial Completion or Beneficial Occupancy). Drawing: A page or sheet of the Plans which presents a graphic representation, usually drawn to scale, showing the technical information, design, location, and dimensions of various elements of the Work. The graphic representations include, but are not limited to, plan views, elevations, transverse and longitudinal sections, large and small scale sections and details, isometrics, diagrams, schedules, tables and/or pictures. DSBSD: Virginia Department of Small Business and Supplier Diversity Emergency: Any unforeseen situation, combination of circumstances, or a resulting state that poses imminent danger to health, life or property. Final Completion Date: The date of the Owner's acceptance of the Work from the Contractor upon confirmation from the Architect/Engineer and the Contractor that the Work is totally complete in accordance with Section 44(b). Field Order: A written order issued by the A/E which clarifies or explains the plans or specifications, or any portion or detail thereof, without changing the design, the Contract Price, the Time for Completion or the Contract Completion Date. Final Payment: The final payment that the Contractor receives pursuant to the applicable provisions of Section 36, except in the event no final payment is made due to termination of the Contract under either Sections 41 or 42. In the event of a termination for cause under Section 41, the Final Payment shall be when the termination became effective. In the event of a termination for convenience under Section 42, the Final Payment shall be either the payment of compensation for termination that the Contractor receives according to the provisions of Subsection 42, or the Owner’s determination that no compensation for termination is due the Contractor under Subsection 42, as the case may be. Float: The excess time included in a construction schedule to accommodate such items as inclement weather and associated delays, equipment failures, and other such unscheduled events. It is the contingency time associated with a path or chain of activities and represents the amount of time by which the early finish date of an activity may be delayed without impacting the critical path and delaying the overall completion of the Project. Any difference in time between the Contractor's approved early completion date and the Contract Completion Date shall be considered a part of the Project float. Float, Free: The time (in days) by which an activity may be delayed or lengthened without impacting upon the start day of any activity following in the chain. Float, Total: The difference (in days) between the maximum time available within which to perform an activity and the duration of an activity. It represents the time by which an activity may be delayed or lengthened without impacting the Time for Completion or the Contract Completion Date. Notice: All written notices, including demands, instructions, claims, approvals and disapprovals, required or authorized under the Contract Documents. Any written notice by either party to the Contract shall be

DGS-30-054 CO-7 (04/15)

5

sufficiently given by any one or combination of the following, whichever shall first occur: (1) delivered by hand to the last known business address of the person to whom the notice is due; (2) delivered by hand to the person's authorized agent, representative or officer wherever they may be found; or (3) enclosed in a postage prepaid envelope addressed to such last known business address and delivered to a United States Postal Service official or mailbox. Notice is effective upon such delivery. All notices to the Owner should be directed to the Project Manager. If the Owner and the Contractor agree in writing that Notices transmitted by Facsimile (Fax) or e-mail are acceptable for the Project, such Notice shall be transmitted to the Fax number or e-mail address listed in the agreement and shall have a designated space for the Fax or e-mail Notice recipient to acknowledge his receipt by authorized signature and date. The Fax or e-mail Notice with authorized signature acknowledging receipt shall be Faxed or e-mailed back to the sender. The Faxed or e-mailed Notice shall be effective on the date it is acknowledged by authorized signature. All Faxed or e-mailed Notices shall also be sent by hard copy, which shall be effective upon delivery, as provided herein. Notice shall be effective upon the date of acknowledgment of the Faxed or e-mailed Notice or the date of delivery, whichever occurs first.

Notice to Proceed: A written notice given by the Owner to the Contractor (with a copy to A/E) fixing the date on which the Contract time will commence for the Contractor to begin the prosecution of the Work in accordance with the requirements of the Contract Documents. The Notice to Proceed will customarily identify a Contract Completion Date. Owner: The public body with whom the Contractor has entered into a contractual agreement and for whom the Work or services is to be provided. The term "Owner", as used herein, shall also mean the Agency. Person: This term includes any individual, corporation, partnership, association, company, business, trust, joint venture, or other legal entity. Plans: The term used to describe the group or set of project-specific drawings which are included in the Contract Documents. Project: The term used instead of the specific or proper assigned title of the entire undertaking which includes, but is not limited to, the "Work" described by the Contract Documents. Project Inspector: One or more persons employed by the Owner to inspect the Work for the Owner and/or to document and maintain records of activities at the Site to the extent required by the Owner. The Owner shall notify the Contractor in writing of the appointment of such Project Inspector(s). The scope of the Project Inspector's authority with respect to the Contractor is limited to that indicated in Section 16 (e) and (f) and as supplemented by the Owner in writing to the Project Inspector and to the Contractor. Project Manager: The Project Manager as used herein shall be the Owner's designated representative on the Project. The Project Manager shall be the person through whom the Owner generally conveys written decisions and notices. All notices due the Owner and all information required to be conveyed to the Owner shall be conveyed to the Project Manager. The scope of the Project Manager's authority is limited to that authorized by the Owner, who shall provide written information to the Contractor at the Preconstruction meeting defining those limits. Upon receipt of such information, the Contractor shall be on notice that it cannot rely on any decisions of the Project Manager outside the scope of his authority. Nothing herein shall be construed to prevent the Owner from issuing any notice directly to the Contractor. The Owner may change the Project Manager from time to time and may, in the event that the Project Manager is absent, disabled or otherwise temporarily unable to fulfill his duties, appoint an interim Project Manager. Provide: Shall mean furnish and install ready for its intended use.

DGS-30-054 CO-7 (04/15)

6

Schedule of Values: The schedule prepared by the Contractor and acceptable to the Owner which indicates the value of that portion of the Contract Price to be paid for each trade or major component of the Work. Site: Shall mean the location at which the Work is performed or is to be performed. Specifications: That part of the Contract Documents containing the written administrative requirements and the technical descriptions of materials, equipment, construction systems, standards, and workmanship which describe the proposed Work in sufficient detail and provide sufficient information for the Building Official to determine code compliance and for the Contractor to perform the Work. (The General Conditions, any Supplemental General Conditions, various bidding information and instructions, and blank copies of various forms to be used during the execution of the Work are usually bound with the Specifications.) Subcontractor: A person having a direct contract with Contractor or with any other Subcontractor for the performance of the Work. Subcontractor includes any person who provides on-site labor but does not include any person who only furnishes or supplies materials for the Project. Submittals: All shop, fabrication, setting and installation drawings, diagrams, illustrations, schedules, samples, and other data required by the Contract Documents which are specifically prepared by or for the Contractor to illustrate some portion of the Work and all illustrations, brochures, standard schedules, performance charts, instructions, diagrams and other information prepared by a Supplier and submitted by the Contractor to illustrate material or equipment conformance of some portion of the Work with the requirements of the Contract Documents. Substantial Completion: The condition when the Owner agrees that the Work, or a specific portion thereof, is sufficiently complete, in accordance with the Contract Documents, so that it can be utilized by the Owner for the purposes for which it was intended. The Owner at its sole discretion may, after obtaining the necessary approvals and certificates, take Beneficial Occupancy at this time or choose to wait to occupy until after Final Completion is achieved. Supplemental General Conditions: That part of the Contract Documents which amends or supplements the General Conditions. Supplier: A manufacturer, fabricator, distributor, material-man or vendor who provides material for the Project but does not provide on-site labor. Small Business Procurement Plan: The proposed percentage of small business participation in the Total Base Bid Amount submitted by the Contractor as part of its Bid. Time for Completion: The number of consecutive calendar days following the Date of Commencement which the Contractor has to substantially complete all Work required by the Contract. Underground Facilities: All pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels or other such facilities or attachments, and any encasements containing such facilities which are or have been installed underground to furnish any of the following services or materials: electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, sewage and drainage removal, traffic or other control systems or water. Work: The services performed under this Contract including, but not limited to, furnishing labor, and furnishing and incorporating materials and equipment into the construction. The Work also includes the entire completed construction, or the various separately identifiable parts thereof, required to be provided under the Contract Documents or which may reasonably be expected to be provided as part of a complete, code compliant and functioning system for those systems depicted in the plans and specifications.

DGS-30-054 CO-7 (04/15)

7

2. CONTRACT DOCUMENTS

(a) The Contract Between Owner and Contractor (CO-9), the Workers' Compensation Certificate of Coverage (CO-9a), the Standard Performance Bond (CO-10), the Standard Labor and Material Payment Bond (CO-10.1), the Schedule of Values and Certificate for Payment (CO-12), the Affidavit of Payments of Claims (CO-13), the Contractor's Certificate of Substantial Completion (CO-13.2a), and the Contractor's Certificate of Completion (CO-13.2) issued by the Commonwealth of Virginia are forms incorporated in these General Conditions by reference and are made a part hereof to the same extent as though fully set forth herein. They must be used by the Contractor for their respective purposes.

(b) All time limits stated in the Contract Documents, including but not limited to the Time for

Completion of the Work, are of the essence of the Contract. (c) The Contract Between Owner and Contractor shall be signed by the Owner and the Contractor in

as many original counterparts as may be mutually agreed upon, each of which shall be considered an original.

(d) Anything called for by one of the Contract Documents and not called for by the others shall be of

like effect as if required or called for by all, except that a provision clearly designed to negate or alter a provision contained in one or more of the other Contract Documents shall have the intended effect. In the event of conflicts among the Contract Documents, the Contract Documents shall take precedence in the following order: the Contract between Owner and Contractor; the Supplemental General Conditions; the General Conditions; the Special Conditions; the specifications with attachments; and the plans.

(e) If any provision of this Contract shall be held invalid by any court of competent jurisdiction, such

holding shall not invalidate any other provision. (f) All correspondence, invoices, memoranda, submittals and other documents related to this Project

whether generated by the Owner, the A/E, the Contractor or others should be identified at the beginning of the document with the eleven digit (XXX-XXXXX-XXX) Project Code Number. Additional identification such as a job number, purchase order number or such may also be shown at the generator's option.

3. LAWS AND REGULATIONS

(a) The Contractor shall comply with all laws, ordinances, rules, regulations and lawful orders of any public authority bearing on the performance of the Work and shall give all notices required thereby. The Contractor shall assure that all Subcontractors and tradesmen who perform Work on the project are properly licensed by the Department of Professional and Occupational Regulation as required by Title 54.1, Chapter 11, Articles 1 and 3 and by applicable regulations.

(b) This Contract and all other contracts and subcontracts are subject to the provisions of Articles 3

and 5, Chapter 4, Title 40.1, Code of Virginia, relating to labor unions and the "right to work." The Contractor and its Subcontractors, whether residents or nonresidents of the Commonwealth, who perform any Work related to the Project shall comply with all of the said provisions.

(c) IMMIGRATION REFORM AND CONTROL ACT OF 1986: By signing this Contract, the

Contractor certifies that it does not and will not during the performance of this Contract violate the provisions of the Federal Immigration Reform and Control Act of 1986, which prohibits employment of illegal aliens.

(d) E-VERIFY PROGRAM: Pursuant to Code of Virginia, § 2.2-4308.2, any employer with more

than an average of 50 employees for the previous 12 months entering into a contract in excess of

DGS-30-054 CO-7 (04/15)

8

$50,000 with any agency of the Commonwealth to perform work or provide services pursuant to such contract shall register and participate in the E-Verify program to verify information and work authorization of its newly hired employees performing work pursuant to such public contract. Any such employer who fails to comply with these provisions may be debarred from contracting with any agency of the Commonwealth for a period up to one year. Such debarment may cease upon the employer’s registration and participation in the E-Verify program. If requested, the employer shall present a copy of their Maintain Company page from E-Verify to prove that they are enrolled in E-Verify.

(e) The provisions of all rules and regulations governing safety as adopted by the Safety Codes

Commission of the Commonwealth of Virginia and as issued by the Department of Labor and Industry under Title 40.1 of the Code of Virginia shall apply to all Work under this Contract. Inspectors from the Department of Labor and Industry shall be granted access to the Work for inspection without first obtaining a search or administrative warrant.

(f) Building Permit: Because this Project is on Commonwealth of Virginia property, codes or zoning

ordinances of local political subdivisions do not apply to Work on the property. The Virginia Uniform Statewide Building Code applies to the Work and is administered by the Building Official for State-owned Buildings. The Building Permit will be obtained and paid for by the Owner. All other permits, local license fees, business fees, taxes, or similar assessments imposed by the appropriate political subdivision and the Department of Environmental Quality shall be obtained and paid for by the Contractor. See Section 25 for utility connection fees and services.

(g) The Contractor shall include in each of its subcontracts a provision requiring each Subcontractor

to include or otherwise be subject to the same payment and interest requirements in Subsections (a), (b), and (c) of Section 37 of these General Conditions with respect to each lower-tier Subcontractor and Supplier.

(h) The Contractor, if not licensed as an asbestos abatement contractor in accordance with § 54.1-514,

Code of Virginia, shall have all asbestos-related Work performed by subcontractors who are duly licensed as asbestos contractors for the Work required.

(i) Lead Based Paint Activities: If the Contract Documents indicate that lead based paint is present on

existing materials, components, or surfaces, the Contractor shall conform to the following:

(1) The requirements set forth in 59 Federal Register 45,872 (September 2, 1994) Proposed Rule) - Lead; Requirements for Lead based Paint Activities (Proposed Rules) in selecting and performing the means, methods and procedures for performing the Work. This includes, but is not limited to, training of personnel, lead abatement, encapsulation of lead containing materials, removal and handling of lead containing materials, and methods of disposal. When the Final Rule, to be codified at 40 CFR 745, supersedes the Proposed Rule, the Contractor shall be responsible for conforming to the Final Rule, as of the effective date set forth therein.

(2) The requirements for employee protection contained in 29 CFR Part 1926, Subpart D,

and the requirements for record-keeping contained 29 CFR Part 1910. (3) The Virginia Department of Labor and Industry's (DLI) Emergency Regulation published

in the May 27, 1996 Virginia Register, requiring, among other things, that a permit be issued to the lead abatement contractor, or any subsequent regulation issued by DLI.

(j) If the Contractor violates laws or regulations that govern the Project, the Contractor shall take

prompt action to correct or abate such violation and shall indemnify and hold the Owner harmless against any fines, and/or penalties that result from such violation. To the extent that such violation is the result of negligence or other actionable conduct of the Contractor, the Contractor shall

DGS-30-054 CO-7 (04/15)

9

indemnify and hold the Owner harmless against any third party claims, suits, awards, actions, causes of action or judgments, including but not limited to attorney's fees and costs incurred thereunder, that arise or result from such violation.

(k) If the Work includes any land disturbing activities, the Contractor shall have on-site an individual

certified by the Department of Environmental Quality as a Responsible Land Disturber in accordance with § 10.1-563, Code of Virginia.

(l) The Contractor is neither required nor prohibited from entering into or adhering to agreements

with one or more labor organizations, or otherwise discriminating against subcontractors for becoming or refusing to become, or remaining signatories to or otherwise adhering to, agreements with one or more labor organizations. This section does not prohibit contractors or subcontractors from voluntarily entering into agreements with one or more labor organizations. Both the agency and contractor are entitled to injunctive relief to prevent any violation of this section.

This section does not apply to any public-private agreement for any construction in which the

private body, as a condition of its investment or partnership with the state agency, requires that the private body have the right to control its labor relations policy and perform all work associated with such investment or partnership in compliance with all collective bargaining agreements to which the private party is a signatory and is thus legally bound with its own employees and the employees of its contractors and subcontractors in any manner permitted by the National Labor Relations Act, 29 U.S.C. § 151 et seq., or the Railway Labor Act, 45 U.S.C. § 151 et seq.

This section does not prohibit an employer or any other person covered by the National Labor

Relations Act or the Railway Labor Act from entering into agreements or engaging in any other activity protected by law.

This section shall not be interpreted to interfere with the labor relations of persons covered by the

National Labor Relations Act or the Railway Labor Act.

4. NONDISCRIMINATION (a) § 2.2-4311 of the Code of Virginia shall be applicable. It provides as follows:

1. During the performance of this Contract, the Contractor agrees as follows:

a. The Contractor will not discriminate against any employee or applicant for employment because of race, religion, color, sex, national origin, age, disability, or other basis prohibited by state law relating to discrimination in employment, except where there is a bona fide occupational qualification reasonably necessary to the normal operation of the contractor. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this nondiscrimination clause.

b. The Contractor, in all solicitations or advertisements for employees placed by or on behalf of the contractor, will state that such Contractor is an equal opportunity employer.

c. Notices, advertisements and solicitations placed in accordance with federal law, rule or regulation shall be deemed sufficient for the purpose of meeting the requirements of this section.

2. The Contractor will include the provisions of the foregoing paragraphs a, b and c in every subcontract or purchase order of over $10,000, so that the provisions will be binding upon each subcontractor or vendor.”

DGS-30-054 CO-7 (04/15)

10

(b) Where applicable, the Virginians with Disabilities Act and the federal Americans with Disabilities Act shall apply to the Contractor and all Subcontractors.

5. PROHIBITION OF ALCOHOL AND OTHER DRUGS

(a) § 2.2-4312 of the Code of Virginia shall be applicable. It provides as follows:

“During the performance of this contract, the contractor agrees to (i) provide a drug-free workplace for the contractor's employees; (ii) post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the contractor's workplace and specifying the actions that will be taken against employees for violations of such prohibition; (iii) state in all solicitations or advertisements for employees placed by or on behalf of the contractor that the contractor maintains a drug-free workplace; and (iv) include the provisions of the foregoing clauses in every subcontract or purchase order of over $10,000, so that the provisions will be binding upon each subcontractor or vendor. For the purposes of this section, "drug-free workplace" means a site for the performance of work done in connection with a specific contract awarded to a contractor in accordance with this chapter, the employees of whom are prohibited from engaging in the unlawful manufacture, sale, distribution, dispensation, possession or use of any controlled substance or marijuana during the performance of the contract.”

(b) The Contractor shall also establish, maintain and enforce policies which prohibit the following acts by all Contractor, Subcontractor and Supplier personnel at the Site: (1) The manufacture, distribution, dispensation, possession, or use of alcohol, marijuana or

other drugs, except possession and medically prescribed use of prescription drugs; and (2) The impairment of judgment or physical abilities due to the use of alcohol, marijuana or

other drugs, including impairment from prescription drugs. 6. TIME FOR COMPLETION

(a) The Time for Completion shall be designated by the Owner on the Invitation for Bids, Request for

Proposals, or other prebid/proposal documents. In some instances, the Time for Completion may be stated on the Invitation for Bids, Request for Proposals, or other prebid/pre-proposal document in the form of a Contract Completion Date. The Work must be substantially completed by the Time for Completion or the Contract Completion Date. Unless otherwise specified, the Contractor shall achieve Final Completion within thirty (30) days after the date of Substantial Completion.

(b) The Time for Completion shall be stated in the Contract between Owner and Contractor and shall

become a binding part of the Contract upon which the Owner may rely in planning the use of the facilities to be constructed and for all other purposes. If the Contractor fails to substantially complete the Work within the Time for Completion or Contract Completion Date, as set forth in the Contract, he shall be subject to payment of actual damages incurred by the Owner or liquidated damages, if provided for in the Contract.

(c) The Contractor, in submitting his bid or proposal, acknowledges that he has taken into

consideration normal weather conditions. Normal weather does not mean statistically average weather, but rather means a range of weather patterns which might be anticipated based on weather data for the past ten (10) years, (i.e., conditions which are not extremely unusual). Normal weather conditions shall be determined from the public historical records available, including the U.S. Department of Commerce, Local Climatological Data Sheets, National Oceanic and Atmospheric Administration / Environmental Data and Information Service, National Climatic Center and National Weather Service. The data sheets to be used shall be those for the locality or localities closest to the site of the work. No additional compensation will be paid to the Contractor because of adverse weather conditions; however, an extension of time for abnormal weather will

DGS-30-054 CO-7 (04/15)

11

be considered by the Owner under the following conditions, all of which must be strictly complied with by the contractor:

(1) The request for additional time shall be further substantiated by weather data collected

during the period of delay at the Site. Said data must demonstrate that an actual departure from normal weather occurred at the Site during the dates in question.

(2) The extension requested must be supported by a delay in completion of the entire Project

shown on the critical path of the accepted CPM Schedule or the approved bar graph schedule required for the Project. Extensions will be granted only for delays in completion of the Project, not for that portion of any delay which consumes only "float" time.

(3) A request for extension of time based on abnormal weather must be made in writing

within fourteen (14) calendar days of the completion of the calendar month during which abnormal weather is claimed at the Site.

(4) All of the evidence and data supporting the request (including both historical data and the

recordings at the Site during the time of delay) must be furnished to the Owner before any consideration will be given to the request. That supporting data shall be submitted by the end of the calendar month following the month for which the request is made.

(d) The failure by the Contractor to comply with any and all of the conditions in (c) above shall

constitute a waiver of claims for the extension of time for abnormal weather. (e) The Contractor represents and agrees that he has taken into account in his bid the requirements of

the bid documents, the Contract Documents, local conditions, availability of materials, equipment, and labor, and any other factors which may affect the performance of the Work. The Contractor agrees and warrants that he will achieve Substantial Completion of the Work to allow the Owner to have Beneficial Occupancy not later than the Time for Completion or Contract Completion Date. The Contractor agrees and warrants that he will achieve Final Completion of the Work (the entire completion of all Work, including "punch list" items), not later than thirty (30) days after achieving Substantial Completion.

7. CONDITIONS AT SITE

(a) The Contractor shall have visited the Site prior to bidding or submitting its proposal and is totally responsible for having ascertained pertinent local conditions such as location, accessibility and general character of the Site, and the character and extent of existing conditions, improvements and work within or adjacent to the Site. Claims, which result from the Contractor's failure to do so, will be deemed waived.

(b) If, in the performance of the Contract, hidden physical conditions of a building being modified are

exposed revealing unusual or materially different conditions from those ordinarily encountered or inherent in work of this nature, or if subsurface or latent conditions at the Site are found which are materially different from those frequently present in the locality or from those indicated in the Contract Documents, the Contractor must report such conditions to the Owner and to the Architect/Engineer before the conditions are disturbed. Upon such notice, or upon his own observation of such conditions, the Architect/Engineer shall promptly propose such changes in the Contract Documents as he finds necessary to conform to the different conditions. Any change in the cost of the Work or additional time needed for completion must be requested pursuant to Sections 38, 39 and/or 43 of these General Conditions.

(c) If the Contractor, during the course of the Work, observes the existence of any material which he

knows, should know, or has reason to believe is hazardous to human health, the Contractor shall

DGS-30-054 CO-7 (04/15)

12

promptly notify the Owner. The Owner will provide the Contractor with instructions regarding the disposition of the material. The Contractor shall not perform any Work involving the material or any Work causing the material to be less accessible prior to receipt of special instructions from the Owner.

8. CONTRACT SECURITY

(a) For contracts with a value exceeding five hundred thousand dollars ($500,000), the Contractor

shall deliver to the Owner or its designated representative, a Commonwealth of Virginia Standard Performance Bond, DGS-30-084 (Form CO-10) and a Commonwealth of Virginia Standard Labor and Material Payment Bond, DGS-30-088 (Form CO-10.1) each fully executed by the Contractor and one or more surety companies legally licensed to do business in Virginia and each in an amount equal to one hundred percent (100%) of the accepted bid or proposal. If more than one Surety executes a bond, each shall be jointly and severally liable to the Owner for the entire amount of the bond. Sureties shall be selected by the Contractor, subject to approval by the Owner. No payment on the Contract shall be due and payable to the Contractor until the bonds have been approved by the Owner and the Office of the Attorney General of Virginia. In order to facilitate review of the bonds by the Office of the Attorney General, the power of attorney from the surety company to its agent who executes the bond shall be attached to the bond, or, if not so attached, prior to the execution of the bonds by the surety, recorded in the Office of the Clerk of Court for the City of Richmond, Virginia, at the John Marshall Court Building, 400 North Ninth Street, except when the Owner is one of the following, in which case the power of attorney must be recorded with the Clerk of Court in the place shown:

OWNER PLACE OF RECORDATION University of Virginia City of Charlottesville Old Dominion University City of Norfolk Norfolk State University City of Norfolk Christopher Newport University City of Newport News Virginia Polytechnic Institute County of Montgomery and State University

(b) For the purposes of all Standard Labor and Material Payment Bonds entered into, the term

"subcontractors" as used in § 2.2-4337(A)(2) of the Code of Virginia is interpreted to mean any contractors who participated in the prosecution of the Work undertaken by the Contractor (referred to in § 2.2-4337(A)(2) of the Code of Virginia as the "prime contractor"), whether such contractor had a direct contract with the Contractor (prime contractor) or whether there were one or more other intervening Subcontractors contractually positioned between it and the Contractor (prime contractor).

(c) See § 2.2-4338 of the Code of Virginia, for alternative forms of security for payment and/or

performance bonds. (d) For contracts with a value of less than five hundred thousand dollars ($500,000), the Contractor

will not be required to provide a Standard Performance Bond and a Standard Labor and Material Payment Bond as described above unless the Invitation for Bid or Request for Proposal states that such bonds will be required.

DGS-30-054 CO-7 (04/15)

13

9. SUBCONTRACTS

(a) The Contractor shall, as soon as practicable after the signing of the Contract, notify the Owner and Architect/Engineer in writing of the names of all Subcontractors proposed for the principal parts of the Work and of such others as the Architect/Engineer may direct. Where the specifications establish qualifications or criteria for Subcontractors, manufacturers, or individuals performing Work on the Project, the Contractor shall be responsible for ascertaining that those proposed meet the criteria or qualifications. The Contractor shall not employ any Subcontractor that the Owner may, within a reasonable time, object to as unsuitable. Neither the Owner nor the Architect/Engineer shall direct the Contractor to contract with any particular Subcontractor unless provided in the specifications or Invitation for Bids or Request for Proposal.

(b) The Owner may select a particular Subcontractor for a certain part of the Work and designate on

the Invitation for Bids or Request for Proposal that the Subcontractor shall be used for the part of the Work indicated and that the Subcontractor has agreed to perform the Work for the subcontract amount stipulated on the bid or Proposal form. The Contractor shall include the stipulated amount plus his Contractor markups in the bid or Proposal. In such case, the Contractor shall be responsible for that Subcontractor and its work and the Subcontractor shall be responsible to the Contractor for its work just as if the Contractor had selected the Subcontractor. If the Contractor has a reasonable objection to the Subcontractor being assigned, then the Contractor shall note the exception in his bid or proposal and the reason for the exception and maintain appropriate provisions for coordinating the work of the Subcontractor. The Owner, at its sole discretion, may accept the Contractor’s bid or proposal with the exception noted and contract separately with the Subcontractor under the provisions Section 10 of the contract or assign a different Subcontractor.

(c) The Owner shall, on request, furnish to any Subcontractor, if practicable, the amounts of payments

made to the Contractor, the Schedule of Values and Requests for Payment submitted by the Contractor and any other documentation submitted by the Contractor which would tend to show what amounts are due and payable by the Contractor to the Subcontractor.

(d) The Contractor shall be fully responsible to the Owner for all acts and omissions of his agents and

employees and all succeeding tiers of Subcontractors and Suppliers performing or furnishing any of the Work. Nothing in the Contract Documents shall create any contractual relationship between Owner or Architect/Engineer and any such Subcontractor, Supplier or other person or organization, nor shall it create any obligation on the part of Owner or Architect/Engineer to pay for or to see to the payment of any moneys due any such Subcontractor, Supplier or other person or organization, except as may otherwise be required by law.

(e) The Contractor shall be fully responsible for his invitees at the Site and for those of his

Subcontractors, Suppliers, and their employees, including any acts or omissions of such invitees. (f) The Contractor agrees that he alone is responsible for all dealings with his Subcontractors and

Suppliers, and their subcontractors, employees and invitees, including, but not limited to, the Subcontractors' or Suppliers' claims, demands, actions, disputes and similar matters unless specifically provided otherwise by the Contract or by statute.

10. SEPARATE CONTRACTS

(a) The Owner reserves the right to let other contracts in connection with the Project, the Work under which may proceed simultaneously with the execution of this Contract. The Contractor shall afford other separate contractors reasonable opportunity for the introduction and storage of their materials and the execution of their work. The Contractor shall cooperate with them and shall take all reasonable action to coordinate his Work with theirs. If the Owner has listed other separate contracts in the Invitation for Bids or Requests for Proposal which it expects to proceed simultaneously with the Work of the Contractor, and has included the estimated timing of such

DGS-30-054 CO-7 (04/15)

14

other Contracts in the Invitation for Bids or Requests for Proposal, the Contractor shall integrate the schedule of those separate contracts into his scheduling. The Contractor shall make every reasonable effort to assist the Owner in maintaining the schedule for all separate contracts. If the work performed by the separate contractor is defective or performed so as to prevent or threaten to prevent the Contractor from carrying out his Work according to the Contract, the Contractor shall immediately notify the Owner and the Architect/Engineer upon discovering such conditions.

(b) If a dispute arises between the Contractor and any separate contractor(s) as to their responsibility

for cleaning up as required by Sections 31 (c) and 31 (d) of these General Conditions, the Owner may clean up and charge the cost thereof to the respective contractors in proportion to their responsibility. If a Contractor disputes the Owner's apportionment of clean-up costs, it shall be that contractor's burden to demonstrate and prove the correct apportionment.

11. CONTRACTOR'S AND SUBCONTRACTOR'S INSURANCE

(a) The Contractor shall not commence Work under this Contract until he has obtained all the insurance required hereunder from an insurer authorized to do business in Virginia and such insurance has been approved by the Owner; nor shall the Contractor allow any Subcontractor to commence Work on his subcontract until the same types of insurance in an appropriate amount have been obtained by the Subcontractor and approved by the Contractor. Approval of insurance by the Owner shall not relieve or decrease the liability of the Contractor hereunder.

(b) The Contractor shall take out, and shall maintain in force at all times during the performance of

the Work, Workers' Compensation and Employers' Liability Insurance for all of his employees engaged in the Work in an amount not less than the minimum required by § 2.2-4332 and § 65.2-100 et seq. of the Code of Virginia. In case any of the Work is sublet, the Contractor shall require each Subcontractor similarly to provide Workers' Compensation and Employers' Liability Insurance for all of the latter's employees to be engaged in the Work. Prior to award of the Contract, the Contractor shall submit, on the form provided by the Owner, a Certificate of Coverage verifying Workers' Compensation. The Contractor shall likewise obtain a Certificate of Coverage for Workers' Compensation coverage from each subcontractor prior to awarding the subcontract and shall provide a copy to the Owner.

(c) During the performance of the Work under this Contract, the Contractor shall maintain

commercial general liability insurance to include Premises / Operations Liability, Products and Completed Operations Coverage, Independent Contractor's Liability, Owner's and Contractor's Protective Liability, and Personal Injury Liability, which shall insure him against claims of personal injury, including death, as well as against claims for property damage, which may arise from operations under this Contract, whether such operations be by himself or by any Subcontractor, or by anyone directly or indirectly employed by either of them. The amounts of general liability insurance shall be not less than $1,000,000 per occurrence and $2,000,000 aggregate combined limit. The Commonwealth of Virginia, its officers, employees and agents, shall be named as an additional insured with respect to the Work being procured. The Supplemental General Conditions may require the Contractor to provide an Umbrella insurance policy in a specified amount for the Project.

(d) During the performance of the Work under this Contract, the Contractor shall maintain automobile

liability insurance which shall insure him against claims of personal injury, including death, as well as against claims for property damage, which may arise from operations under this Contract, whether such operations be by himself or by any Subcontractor, or by anyone directly or indirectly employed by either of them. The amounts of automobile insurance shall be not less than $1,000,000 combined limit for bodily injury and property damage per occurrence.

(e) The Asbestos Contractor or Subcontractor, as the case may be, shall provide occurrence-based

liability insurance with asbestos coverages in an amount not less than $1,000,000 and shall name

DGS-30-054 CO-7 (04/15)

15

the following as additional insureds: The Commonwealth of Virginia, its officers, its employees and its agents; the Architect/Engineer (if not the Asbestos Project Designer); and the Contractor (where the asbestos work is being performed by the Asbestos Subcontractor).

12. "ALL RISK" BUILDER'S RISK INSURANCE

(a) Contractor Controlled During Construction: The Contractor, at his cost, shall obtain and maintain in the names of the Owner and the Contractor "all-risk" builder's risk insurance (or fire, extended coverage, vandalism and malicious mischief insurance, if approved by the Owner and the Director, Division of Engineering and Buildings) upon the entire structure or structures on which the Work of this Contract is to be done and upon all material in or adjacent thereto which is intended for use thereon, to one hundred percent (100%) of the insurable value thereof (i.e. construction costs, soft costs, FF&E, and the residual value of the existing structure to remain). Such insurance may include a deductible provision if the Owner so provides in the Supplemental General Conditions, in which case the Contractor will be liable for such deductions, whenever a claim arises. The loss, if any, is to be made adjustable with and payable to the Owner, in accordance with its interests, as they may appear. The Owner, its officers, employees and its agents, shall be named as an additional insured in any policy of insurance issued. Written evidence of the insurance shall be filed with the Owner no later than thirty (30) days following the award of the Contract. In the event of cancellation of this insurance, not less than thirty (30) days prior written notice must be sent to the Owner. A copy of the policy of insurance shall be given to the Owner upon demand.

(b) Owner Controlled During Construction: The Owner maintains insurance coverage on its

buildings. On re-roofing, renovation, and interior modifications of existing building projects where the Owner continues to occupy the building, or a portion thereof, while the Work is being performed, the Contractor shall provide “all risk” builders risk insurance, as described above, in an amount equal to one hundred percent (100%) of the cost of the Work (i.e. construction costs, soft costs, and FF&E costs). In those instances, the Contract between the Owner and Contractor for the project shall expressly exclude the project from the requirements of Subsection 12(a). The Contractor is responsible for providing any desired coverage for Contractor's or Subcontractors' buildings, equipment, materials, tools or supplies that are on-site.

(c) The value of the builder's risk insurance shall exclude the costs of excavations, backfills,

foundations, underground utilities and sitework. (d) Any insurance provided through the Department of Treasury, Division of Risk Management, on

buildings, construction, additions or renovations will not extend to Contractor's nor Subcontractors' buildings, equipment, materials, tools or supplies unless these items are to become property of the Owner upon completion of the Project and the Owner has assumed responsibility for such items at the time of the loss.

13. TAXES, FEES AND ASSESSMENTS

The Contractor shall, without additional expense to the Owner, pay all applicable federal, state, and local taxes, fees, and assessments except the taxes, fees and assessments on the real property comprising the Site of the project. If the State Building Official elects to have the local building official inspect the Work as provided by § 36-98.1 of the Code of Virginia, the Owner shall pay the resulting fees to the local building official.

14. PATENTS

The Contractor shall obtain all licenses necessary to use any invention, article, appliance, process or technique of whatever kind and shall pay all royalties and license fees. The Contractor shall hold the Owner, its officers, agents and employees, harmless against any loss or liability for or on account of the

DGS-30-054 CO-7 (04/15)

16

infringement of any patent rights in connection with any invention, process, technique, article or appliance manufactured or used in the performance of the Contract, including its use by the Owner, unless such invention, process, technique, article or appliance is specifically named in the specifications or plans as acceptable for use in carrying out the Work. If, before using any invention, process, technique, article or appliance specifically named in the specifications or plans as acceptable for use in carrying out the Work, the Contractor has or acquires information that the same is covered by letters of patent making it necessary to secure the permission of the patentee, or other, for the use of the same, he shall promptly advise the Owner and the Architect/Engineer. The Owner may direct that some other invention, process, technique, article or appliance be used. Should the Contractor have reason to believe that the invention, process, technique, article or appliance so specified is an infringement of a patent, and fail to inform the Owner and the Architect/Engineer, he shall be responsible for any loss or liability due to the infringement.

15. ARCHITECT/ENGINEER'S STATUS

(a) The Architect/Engineer shall have authority to endeavor to secure the faithful performance by Owner and Contractor of the Work under the Contract. He shall review the Contractor's Submittals for conformance to the requirements of the Contract Documents and return copies to the Contractor with appropriate notations. He shall interpret the requirements of the plans and specifications and issue Field Orders to the Contractor as may be required. He shall recommend to the Owner suspension of the Work (in whole or in part) whenever such suspension may be necessary to ensure the proper execution of the Contract. He shall have authority to reject, in writing, Work, including material, installation or workmanship, which does not conform to the requirements of the plans and specifications. He shall determine the progress and quality of the Work, subject to the right of the Owner to make an overriding decision to the contrary. Upon request by the Contractor, the Architect/Engineer shall confirm, in writing within fourteen (14) days, any oral order or determination made by him.

(b) The Architect/Engineer shall have no authority to approve or order changes in the Work which

alter the design concept or which call for an extension of time or a change in the Contract Price. (c) Although the Owner is bound by the terms of the Contract with the Contractor, including the plans

and specifications, the Owner shall have the right, but not the duty, to countermand any decision of the Architect/Engineer and to follow or reject the advice of the Architect/Engineer, including but not limited to acceptance of the Work, as it deems best. In those instances where the Architect/Engineer has been given authority to act, the Architect/Engineer shall promptly do so, but in the case of disagreement between the Architect/Engineer and the Owner, the decision of the Owner shall be final. The Contractor shall not be bound by any determination, interpretation or decision of the Architect/Engineer, if it is later determined that the same is not in accord with the Contract Documents. The party taking issue with the determination, interpretation or decision of the Architect/Engineer shall give the other party written notice of such fact within fourteen (14) days after the determination, interpretation or decision is communicated by the Architect/Engineer. In the actual performance of the Work, however, the Contractor shall, in the first instance, proceed in accordance with instructions given by the Architect/Engineer unless the Owner and the Contractor mutually agree that the Contractor shall proceed otherwise.

(d) All orders from the Owner to the Contractor shall either be transmitted through the

Architect/Engineer or communicated directly to the Contractor and the Architect/Engineer by the Owner.

(e) Should the Owner choose to employ another or different Architect/Engineer, the status of the

Architect/Engineer so employed shall be the same as that of the former Architect/Engineer. (f) The Architect/Engineer will provide to the Owner and the Contractor after each visit to the Site, a

written report indicating the date, time of day, weather conditions and the names of the persons representing the Architect/Engineer who participated in the visit. The report will advise the Owner

DGS-30-054 CO-7 (04/15)

17

of any problems that were noted and shall compare the Architect/Engineer's observations of the actual progress of the Work with that reported by the Contractor. On the basis of his on-Site observations as Architect/Engineer, he will make every reasonable effort to guard the Owner against defects and deficiencies in the Work of the Contractor. He shall have the authority to inspect the Work, to note and report Defective Work and deviations from the Contract Documents to the Owner, to reject same, and to recommend to the Owner the suspension of the Work when necessary to prevent Defective Work from proceeding or being covered.

(g) The Architect/Engineer shall not be responsible for construction means, methods, techniques,

sequences or procedures (other than those expressly specified in Contract Documents), or for safety precautions and programs in connection with the Work, and he shall not be responsible for the Contractor's failure to carry out the Contractor's own responsibilities.

(h) The Architect/Engineer generally conveys written decisions and notices to the Contractor through

the Project Manager and shall generally receive information and Notices from the Contractor through the Project Manager unless otherwise agreed. The Owner may delegate from the Architect/Engineer to the Project Manager certain inspection, verification, acceptance, rejection, and administrative duties and authority, but any such delegation shall be in writing and a copy thereof provided to the Contractor.

(i) The provisions of this section are included as information only to describe the relationship

between the Owner, A/E, and Contractor. No failure of the A/E to act in accordance with this section shall relieve the Contractor from his obligations under the Contract or create any rights in favor of the Contractor.

16. INSPECTION

(a) All material and workmanship shall be subject to inspection, examination and testing by the Owner, the Architect/Engineer, the Project Inspector, authorized inspectors and authorized independent testing entities at any and all times during manufacture and/or construction. The Architect/Engineer and the Owner shall have authority to reject defective material and workmanship and require its correction. Rejected workmanship shall be satisfactorily corrected and rejected material shall be satisfactorily replaced with proper material without charge therefor, and the Contractor shall promptly segregate and remove the rejected material from the Site. If the Contractor fails to proceed at once with replacement of rejected material and/or the correction of defective workmanship, the Owner may, by contract or otherwise, replace such material and/or correct such workmanship and charge the cost to the Contractor, or may terminate the right of the Contractor to proceed as provided in Section 41 of these General Conditions, the Contractor and surety being liable for any damage to the same extent as provided in Section 41 for termination thereunder.

(b) Site inspections, tests conducted on Site or tests of materials gathered on Site, which the Contract

requires to be performed by independent testing entities, shall be contracted and paid for by the Owner. Examples of such tests are the testing of cast-in-place concrete, foundation materials, soil compaction, pile installations, caisson bearings and steel framing connections. The Contractor shall promptly furnish, without additional charge, all reasonable facilities, labor and materials necessary and convenient for making such tests. Except as provided in (d) below, whenever such examination and testing finds defective materials, equipment or workmanship, the Contractor shall reimburse the Owner for the cost of reexamination and retesting. Although conducted by independent testing entities, the Owner will not contract and pay for tests or certifications of materials, manufactured products or assemblies which the Contract, codes, standards, etc., require to be tested and/or certified for compliance with industry standards such as Underwriters Laboratories, Factory Mutual or ASTM. If fees are charged for such tests and certifications, they shall be paid by the Contractor. The Contractor shall also pay for all inspections, tests, and certifications which the Contract specifically requires him to perform or to pay, together with any

DGS-30-054 CO-7 (04/15)

18

inspections and tests which he chooses to perform for his own purposes, but are not required by the Contract.

(c) Where Work is related to or dependent on the Defective Work, the Contractor shall stop such

related or dependent Work until the Defective Work or deficiency is corrected or an alternative solution is presented that is satisfactory to the Owner. Where Work is rejected because of defective material or workmanship, the Contractor shall stop like Work in other areas or locations on the Project until the matter is resolved and the Owner has approved corrective measures.

(d) Should it be considered necessary or advisable by Owner or the Architect/Engineer at any time

before final acceptance of the entire Work to make an examination of any part of the Work already completed, by removing or tearing out portions of the Work, the Contractor shall on request promptly furnish all necessary facilities, labor and material to expose the Work to be tested to the extent required. If such Work is found to be defective in any respect, due to the fault of the Contractor or his Subcontractors, the Contractor shall bear all the expenses of uncovering the Work, of examination and testing, and of satisfactory reconstruction. If, however, such Work is found to meet the requirements of the Contract, the actual cost of the Contractor's labor and material necessarily involved in uncovering the Work, the cost of examination and testing, and Contractor's cost of material and labor necessary for replacement including a markup of fifteen (15%) percent for overhead and profit shall be paid to the Contractor and he shall, in addition, if completion of the Work has been delayed thereby, be granted a suitable extension of time. Notwithstanding the foregoing, the Contractor shall be responsible for all costs and expenses in removing and replacing the Work if the Contractor had covered the Work prior to any inspection or test contrary to the instructions of the A/E, Owner or Project Inspector.

(e) The Project Inspector has the authority to recommend to the Architect/Engineer and the Owner

that the Work be suspended when in his judgment the Contract Documents are not being followed. Any such suspension shall be continued only until the matter in question is resolved to the satisfaction of the Owner. The cost of any such Work stoppage shall be borne by the Contractor unless it is later determined that no fault existed in the Contractor's Work.

(f) The Project Inspector has the right and the authority to:

(1) Inspect all construction materials, equipment, and supplies for quality and for compliance with the Contract Documents and/or approved shop drawings and Submittals.

(2) Inspect workmanship for compliance with the standards described in the Contract

Documents.

(3) Observe and report on all tests and inspections performed by the Contractor.

(4) Recommend rejection of Work which does not conform to requirements of the Contract Documents.

(5) Keep a record of construction activities, tests, inspections, and reports. (6) Attend all joint Site construction meetings and inspections held by the Owner and/or the

A/E with the Contractor. (7) Check materials and equipment, together with documentation related thereto, delivered

for conformance with approved Submittals and the Contract. (8) Check installations for proper workmanship and conformance with shop drawing and

installation instructions.

DGS-30-054 CO-7 (04/15)

19

(9) Assist in the review and verification of the CO-12, Schedule of Values & Certificate for Payment, submitted by the Contractor each month.

(10) Do all things for or on behalf of the Owner as the Owner may subsequently direct in

writing. (g) The Project Inspector has no authority to:

(1) Authorize deviations from the Contract Documents;

(2) Enter into the area of responsibility of the Contractor's superintendent;

(3) Issue directions relative to any aspect of construction means, methods, techniques, sequences or procedures, or in regard to safety precautions and programs in connection with the Work;

(4) Authorize or suggest that the Owner occupy the Project, in whole or in part; or (5) Issue a certificate for payment.

(h) The duties of the Project Inspector are for the benefit of the Owner only and not for the

Contractor. The Contractor may not rely upon any act, statement, or failure to act on the part of the Project Inspector, nor shall the failure of the Project Inspector to properly perform his duties in any way excuse Defective Work or otherwise improper performance of the Contract by the Contractor.

17. SUPERINTENDENCE BY CONTRACTOR

(a) The Contractor shall have a competent foreman or superintendent, satisfactory to the Architect/Engineer and the Owner, on the Site at all times during the progress of the Work. The superintendent or foreman shall be familiar with and be able to read and understand the plans and specifications, and be capable of communicating orally and in writing with the Owner's inspectors and the Contractor's workers. The Contractor shall be responsible for all construction means, methods, techniques, sequences and procedures, for coordinating all portions of the Work under the Contract except where otherwise specified in the Contract Documents, and for all safety and worker health programs and practices. The Contractor shall notify the Owner, in writing, of any proposed change in superintendent, including the reason therefor, prior to making such change.

(b) The Contractor shall, at all times, enforce strict discipline and good order among the workers on

the Project, and shall not employ on the Work, or contract with, any unfit person, anyone not skilled in the Work assigned to him, or anyone who will not work in harmony with those employed by the Contractor, the Subcontractors, the Owner or the Owner's separate contractors and their subcontractors.

(c) The Owner may, in writing, require the Contractor to remove from the Site any employee or

Subcontractor's employee the Owner deems to be incompetent, careless, not working in harmony with others on the Site, or otherwise objectionable, but the Owner shall have no obligation to do so.

18. CONSTRUCTION SUPERVISION, METHODS AND PROCEDURES

(a) The Contractor shall be solely responsible for supervising and directing the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract. The Contractor shall be solely responsible for the means, methods, techniques, sequences and procedures of construction and for coordinating all portions of the Work under the Contract, except where otherwise specified in the

DGS-30-054 CO-7 (04/15)

20

Contract Documents. However, the Contractor shall not be responsible for the negligence of others in the design or selection of a specific means, method, technique, sequence or procedure of construction which is indicated in and required by the Contract. The Contractor is solely responsible to the Owner that the finished Work complies with the Contract Documents.

The Contractor shall be solely responsible for health and safety precautions and programs for workers and others in connection with the Work. No inspection by, knowledge on the part of, or acquiescence by the Architect or Engineer, the Project Inspector, the Owner, the Owner's employees and agents, or any other entity whatever shall relieve the Contractor from its sole responsibility for compliance with the requirements of the Contract or its sole responsibility for health and safety programs and precautions.

(b) If a specific means, method, technique, sequence or procedure of construction is indicated in or

required by the Contract Documents, the Contractor may furnish or utilize a substitute means, method, sequence, technique or procedure of construction acceptable to Architect/Engineer, subject to the Owner's right to disapprove. The Contractor must submit its written request for the substitution to the Architect/Engineer with sufficient information to allow the Architect/Engineer to determine that the substitute proposed is equivalent to that indicated or required by the Contract.

(c) The divisions and sections of the Specifications and the identification of any drawings shall not

control the Contractor in dividing the Work among Subcontractors or Suppliers or delineating the Work to be performed by any specific trade.

19. SCHEDULE OF THE WORK

(a) General: The Contractor is responsible for the scheduling and sequencing of the Work, for coordinating the Work, for monitoring the progress of the Work, and for taking appropriate action to keep the Work on schedule. The Contractor may attempt to achieve Substantial Completion on or before the Time for Completion or the Contract Completion Date established by the Contract and receive payment in accordance with Section 36 for the Work completed each period. However, the date established by the Contract Documents as the deadline for achieving Substantial Completion must be used in all schedules as the date on which Substantial Completion will be achieved. The time (in days) between the Contractor's planned early completion and the contracted Time for Completion is part of the Project "Total Float" time and will be used as such. Extensions of time pursuant to Sections 38, 39, and 43, damages for delay, and all other matters between the Owner and the Contractor will be determined using the contractually required Substantial Completion date, not an early Substantial Completion date planned by the Contractor.

Within two (2) weeks after the Contractor signs the Contract Between Owner and Contractor, unless otherwise extended by the Owner at the time of the signing, the Contractor shall prepare and submit to the Owner, with a copy to the Architect/Engineer, a preliminary bar graph schedule for accomplishing the Work based upon the Time for Completion stated in the Contract. The preliminary schedule shall be in sufficient detail to show the sequencing of the various trades for each floor level, wing or work area. The Owner will notify the Contractor of its acceptance of or objections to the preliminary schedule within fifteen (15) days of receipt by the Owner. A fully complete Project schedule for accomplishing the Work must be submitted in like manner no later than sixty (60) days after the Contract is signed by the Owner.

The Owner's failure to reject or its acceptance of any schedule, graph, chart, recovery schedule, updated schedule, plan of action, etc. shall not constitute a representation or warranty by the Owner, including but not limited to a representation or warranty that the schedule is feasible or practical nor shall any such acceptance or failure to reject relieve the Contractor from sole responsibility for completing the Work within the time allowed.

DGS-30-054 CO-7 (04/15)

21

No progress payments will be payable to the Contractor until after it has submitted a preliminary schedule which is acceptable to the Owner. Neither the second progress payment nor any subsequent payment shall be payable to the Contractor until it has submitted a fully complete Project schedule accepted by the Owner. Nor shall subsequent progress payments be payable to the Contractor unless and until he submits the monthly bar graphs or status reports required by Section 19(d) herein or unless and until he provides any recovery schedule pursuant to Section 19(e) herein.

Failure to provide a satisfactory preliminary or fully complete Project schedule within the time limits stated above shall be a breach of contract for which the Owner may terminate the Contract in the manner provided in Section 41 of these General Conditions.

The fully complete Project schedule for accomplishing the Work shall be of the type set forth in subparagraph (1) or (2) below, as appropriate:

(1) For Contracts with a price of $1,500,000 or less, a bar graph schedule will satisfy the

above requirement. The schedule shall indicate the estimated starting and completion dates for each major element of the work. See (b) below.

(2) For Contracts with a price over $1,500,000, a Critical Path Method (CPM) schedule shall

be utilized to control the planning and scheduling of the Work. The CPM schedule shall be the responsibility of the Contractor and shall be paid for by the Contractor. See (c) below.

(b) Bar Graph Schedule: Where a bar graph schedule is required, it shall be time-scaled in weekly

increments, shall indicate the estimated starting and completion dates for each major element of the Work by trade and by area, level, or zone, and shall schedule dates for all salient features, including but not limited to the placing of orders for materials, submission of shop drawings and other Submittals for approval, approval of shop drawings by Architect/Engineer, the manufacture and delivery of material, the testing and the installation of materials, supplies and equipment, and all Work activities to be performed by the Contractor.

The Contractor shall allow sufficient time in his schedule for the A/E to conduct whatever associated reviews or inspections as may be required under the A/E's contract with the Owner. If the A/E and the Contractor are unable to agree as to what constitutes sufficient time, the Owner shall determine the appropriate duration for such Architect/Engineer activities. Each Work activity will be assigned a time estimate by the Contractor. One day shall be the smallest time unit used.

It is the Contractor's responsibility to submit a schedule that shows Substantial Completion of the Work by the Contract Time for Completion or the Contract Completion Date and any interim deadlines established by the Contract.

(c) CPM Schedule: Where a CPM schedule is required, it shall be in the time-scaled precedence

format using the Contractor's logic and time estimates. The CPM schedule shall be drawn or plotted with activities grouped or zoned by Work area or subcontract as opposed to a random (or scattered) format.

The CPM schedule shall be time-scaled on a weekly basis and shall be drawn or plotted at a level of detail and logic which will schedule all salient features of the Work, including not only the actual construction Work for each trade, but also the submission of shop drawings and other Submittals for approval, approval of shop drawings by Architect/Engineer, placing of orders for materials, the manufacture and delivery of materials, the testing and installation of materials and equipment, and all Work activities to be performed by the Contractor. Failure to include any element of Work required for the performance of this Contract shall not excuse the Contractor

DGS-30-054 CO-7 (04/15)

22

from completing all Work required within the Time for Completion, Contract Completion Date and any interim deadlines established by the Contract.

The Contractor shall allow sufficient time in his schedule for the A/E to conduct whatever associated reviews or inspections as may be required under the A/E's contract with the Owner. If the A/E and the Contractor are unable to agree as to what constitutes sufficient time, the Owner shall determine the appropriate duration for such Architect/Engineer activities. Each Work activity will be assigned a time estimate by the Contractor. One day shall be the smallest time unit used.

It is the Contractor's responsibility to submit a schedule that shows Substantial Completion of the Work by the Contract Time for Completion or the Contract Completion Date and any interim deadlines established by the Contract.

When completed, the CPM schedule shall be submitted to the Architect/Engineer and the Owner for review. The CPM schedule will identify and describe each activity, state the duration of each activity, the calendar dates for the early and late start and the early and late finish of each activity, and clearly highlight all activities on the critical path. "Total float" and "free float" shall be indicated for all activities. Float time, whether "free float" or "total float" as defined in Section 1, shall not be considered for the exclusive use or benefit of either the Owner or the Contractor, but must be allocated in the best interest of completing the Work within the Time for Completion or the Contract Completion Date. Extensions to the Time for Completion or the Contract Completion Date, when granted by Change Order, will be granted only when equitable time adjustment exceeds the Total Float in the activity or path of activities affected by the change provided that the Owner has reasonably provided information necessary to allow for the orderly progression of the Work. On contracts with a price over $5,000,000, the CPM schedule shall also show what part of the Contract Price (expressed in U.S. dollars) is attributable to each activity on the schedule and shall be in agreement with the schedule of values, the sum of which for all activities shall equal the total Contract Price. The CPM schedule shall have no line-item activities longer than thirty (30) days in duration, and activities shall be included to provide sufficient detail for effectively managing the sequence of the Work. When acceptable to the Owner and Architect/Engineer as to compliance with the requirements of this Section, the schedule shall become the CPM schedule for the Project. Acceptance of the schedule by the Owner does not indicate agreement with, nor responsibility for the proposed or actual duration of any activity or logic shown on the accepted schedule.

(d) Monthly Project Reports: The Contractor shall review progress not less than each month, but as

often as necessary to properly manage the Project and stay on schedule. The Contractor shall collect and preserve information on Change Orders, including extensions of time. The Contractor shall evaluate this information and update the latest accepted schedule as often as necessary to finish within the Contract Time for Completion or before the Contract Completion Date. The Contractor shall submit to the A/E along with his monthly request for payment a copy of the bar graph schedule annotated to show the current progress. For projects requiring a CPM schedule, the Contractor shall submit a monthly report of the status of all activities. The bar graph schedule or monthly status report submitted with each periodic request for payment shall show the Work completed to date in comparison with the Work scheduled for completion, including but not limited to the dates for the beginning and completion of the placing of orders; the manufacture, testing and installation of materials, supplies and equipment. The form shall be approved by the A/E and the Owner; however, a bar graph or a CPM schedule marked, colored or annotated to reflect the above will usually satisfy this requirement. If any elements of the Work are behind schedule, regardless of whether they may prevent the Work from being completed on time, the Contractor must indicate in writing in the report what measures he is taking and plans to take to bring each such element back on schedule and to ensure that the Time for Completion or Contract Completion Date is not exceeded.

DGS-30-054 CO-7 (04/15)

23

(e) Progress Delay: Should any of the following conditions exist, the Owner may require the Contractor to prepare, at no extra cost to the Owner, a plan of action and a recovery schedule for completing the Work by the Contract Time for Completion or the Contract Completion Date:

(1) The Contractor's monthly project report indicates delays that are, in the opinion of the

A/E or the Owner, of sufficient magnitude that the Contractor's ability to complete the Work by the scheduled Time for Completion or the Contract Completion Date is brought into question;

(2) The CPM schedule sorted by early finish shows the Contractor to be thirty (30) or more

days behind the critical path schedule at any time during construction up to thirty (30) days prior to scheduled Substantial Completion date;

(3) The Contractor desires to make changes in the logic (sequencing of Work) or the planned

duration of future activities of the CPM schedule which, in the opinion of the Architect/Engineer or the Owner, are of a major nature.

The plan of action and recovery schedule, when required, shall explain and display how the Contractor intends to regain compliance with the current accepted, fully completed, Project CPM schedule, as updated by approved change orders.

The plan of action, when required, shall be submitted to the Owner for review within two (2) business days of the Contractor receiving the Owner's written demand. The recovery schedule, when required, shall be submitted to the Owner within five (5) calendar days of the Contractor's receiving the Owner's written demand.

(f) Early Completion of Project: The Contractor may attempt to achieve Substantial Completion on

or before the Time for Completion or the Contract Completion Date. However, such planned early completion shall be for the Contractor's convenience only and shall not create any additional rights of the Contractor or obligations of the Owner under this Contract, nor shall it change the Time for Completion or the Contract Completion Date. The Contractor shall not be required to pay damages to the Owner because of its failure to achieve Substantial Completion by its planned earlier date. Likewise, the Owner shall not pay the Contractor any additional compensation for achieving Substantial Completion early nor will the Owner owe the Contractor any compensation should the Owner, its officers, employees, or agents cause the Contractor not to achieve Substantial Completion earlier than the date required by the Contract Documents.

If the Contractor seeks to change the Time for Completion or the Contract Completion Date to reflect an earlier completion date, he may request or propose such a change. The Owner may, but is not required to, accept such proposal. However, a change in the Time for Completion or the Contract Completion Date shall be accomplished only by Change Order. If the Contractor's proposal to change the Time for Completion or the Contract Completion Date is accepted, a Change Order will be issued stating that all references in the Contract, including these General Conditions, to the Time for Completion or the Contract Completion Date shall thereafter refer to the date as modified, and all rights and obligations, including the Contractor's liability for actual damages, delay damages and/or liquidated damages, shall be determined in relation to the date, as modified.

20. SCHEDULE OF VALUES AND CERTIFICATE FOR PAYMENT

(a) Before submittal of the first partial payment request under the Contract, the Contractor shall prepare for review and approval of the Architect/Engineer and the Owner, a schedule of the estimated values listed by trades or by specification sections of the Work, totaling the Contract Price. Where the total project has multiple parts or phases, the Contractor shall prepare appropriate schedules of values to facilitate reviews and justifications for payments.

DGS-30-054 CO-7 (04/15)

24

All requests for payment shall be made in the ASTM Uniformat II structure on the Schedule of Values and Certificate for Payment (Form CO-12) pages 1 and 2. Succeeding pages may be on the Form CO-12 continuation sheets or a computerized spreadsheet which is in the same format and which contains the same information. Where a computerized spreadsheet is used, one copy of the entire Schedule of Values shall be provided to the Owner in an agreed electronic format (e.g. EXCEL) with the initial request for payment.

(b) If the Contractor requests, or intends to request, payment for materials stored in an approved and

secure manner, the Schedule of Values must indicate the amount for labor and the amount for materials, and in a supplement thereto must include an itemized list of materials for that trade or Work section. The material breakdown shall be in sufficient detail to allow verification of the quantities required for the Project, the quantities delivered, the Work completed, and the quantities stored on or off Site.

(c) The "Value of Work Completed" portion of the Form CO-12 shall be completed, the Contractor's

certification completed and signed, and the appropriate substantiating material attached to each Certificate for Payment (CO-12). Such substantiating material includes, but is not limited to, invoices for materials, delivery tickets, time sheets, payroll records, daily job logs/records, and similar materials which, in the opinion of the Owner and the A/E, are necessary or sufficient to justify payment of the amount requested.

(d) The labor progress for any task or activity shall be calculated based upon the percentage of Work

complete up to fifty percent (50%) of the completion of the task or activity. Thereafter, the evaluation of labor progress will be based upon the effort required to complete that task or activity. The material progress shall be calculated as the invoiced dollar cost of materials used in relationship to the amount estimated as necessary to complete a particular element of Work. When calculating material progress, credit shall be given for installed material as well as that stored on the Site and any material stored off Site which has been certified by the Architect/Engineer in accordance with Section 36 of these General Conditions.

(e) Should Work included in previous Form CO-12 submittals, and for which payment has been

made, subsequently be identified, by tests, inspection, or other means, as not acceptable or not conforming to Contract requirements, the "Value of Work Completed" portion of the first Form CO-12 submitted after such identification shall be modified to reduce the "completed" value of that Work by deleting the value of that which has been identified as not acceptable or nonconforming.

21. ACCESS TO WORK

The Architect/Engineer, the Owner, the Project Manager, the Owner's inspectors and other testing personnel, inspectors from the Department of Labor and Industry, and others authorized by the Owner, shall have access to the Work at all times. The Contractor shall provide proper facilities for access and inspection.

22. SURVEYS AND LAYOUT

(a) The Owner shall furnish the Contractor all necessary documents showing property lines and the location of existing buildings and improvements. The Contractor shall provide competent surveying and engineering services to execute the Work in accordance with the Contract and shall be responsible for the accuracy of these surveying and engineering services.

(b) The Owner shall provide such general reference points and benchmarks on the Site as will enable

the Contractor to proceed with the Work will be established in the plans and specifications. If the

DGS-30-054 CO-7 (04/15)

25

Contractor finds that any previously established reference points have been lost or destroyed, he shall promptly notify the Architect/Engineer.

(c) The Contractor shall protect and preserve the established benchmarks and monuments and shall

make no changes in locations without written notice to the Architect/Engineer and the written approval from the Owner. Any of these which may be lost or destroyed or which require shifting because of necessary changes in grades or locations shall, subject to prior written approval of the Owner, be replaced and accurately located by the Contractor.

23. PLANS AND SPECIFICATIONS

(a) The general character and scope of the Work are illustrated by the plans and the specifications. If the Contractor deems additional detail or information to be needed, he shall request the same in writing from the Architect/Engineer. His request shall precisely state the detail or information needed and shall explain why it is needed. The Contractor shall also indicate a date when the requested information is required. The Architect/Engineer shall provide by Field Order such further detail and information as is necessary by the date required so long as the date indicated is reasonable. Any additional drawings and instructions supplied to the Contractor shall be consistent with the Contract Documents, shall be true developments thereof, and shall be so prepared that they can be reasonably interpreted as a part thereof. The Contractor shall carry out the Work in accordance with the additional detail drawings and instructions at no additional cost or time to the Owner.

(b) If the Contractor finds a conflict, error, omission, or other discrepancy in the plans or

specifications, he shall notify the Architect/Engineer in writing as soon as possible, but before proceeding with the affected Work. The Architect/Engineer shall issue a clarification by Field Order to the Contractor stating the correct requirements. If the Contractor deems the Field Order requires additional Work, he shall notify the A/E of such prior to proceeding with that Work and he shall submit a request for Change Order along with a detailed substantiating cost proposal through the A/E to the Owner within fourteen (14) calendar days. If such conflict, error, omission or other discrepancy in plans or specifications was reasonably apparent or with reasonable diligence should have been apparent to the Contractor prior to submitting its bid or Proposal, and the Contractor failed to submit questions to the A/E in the time and manner required by the Instructions to Bidders or Request for Proposal, then any claims shall be deemed waived and the Contractor shall not be entitled to additional compensation or time, or entitled to sue the Owner based on such conflict, error, omission or other discrepancy. If the Contractor performs any Work, or is delayed in performing any Work, where such Work involves a conflict, error, omission, or other discrepancy in the plans and specifications that the Contractor knew about, or with reasonable diligence should have known about, and fails to notify the A/E and Owner as required, the Contractor shall assume full responsibility for such performance or delay and shall bear all costs attributable to correcting any Work requiring correction or to any delay, and such conflict, error, omission, or other discrepancy shall not be the basis for a claim, cause of action or right to sue the Owner.

(c) In case of differences between small and large scale drawings, the large scale drawings shall

govern. Where on any of the drawings a portion of the Work is drawn out and the remainder is indicated in outline, the parts drawn out shall apply also to all other like portions of the Work.

(d) Where the word "similar" appears on the drawings, it shall be interpreted in its general sense and

not as meaning identical, and all details shall be worked out in relation to their location and their connection with other parts of the Work.

(e) The specifications are divided into several parts, or sections, for convenience only, since the entire

specifications must be considered as a whole. The divisions of the specifications are not intended to control the Contractor in dividing the Work among Subcontractors or to limit the Work

DGS-30-054 CO-7 (04/15)

26

performed by any trade. The Contractor shall be solely responsible for the coordination of the trades, Subcontractors and vendors engaged in the Work and for the compensation of the trades, Subcontractors and vendors for the Work performed.

(f) Measurements or dimensions shown on the drawings for Site features, utilities and structures shall

be verified at the Site by the Contractor before commencing the Work. The Contractor shall not scale measurements or dimensions from the drawings. If there are discrepancies, the Architect/Engineer shall be consulted. If new Work is to connect to, match with or be provided in existing Work, the Contractor shall verify the actual existing conditions and necessary dimensions prior to ordering or fabrication.

(g) As-Built Drawings: The Contractor shall maintain at the Site for the Owner one copy of all

drawings, specifications, addenda, approved shop or setting drawings, Change Orders and other modifications (collectively referred to herein as "As-Built Drawings") in good order and marked to record all changes as they occur during construction. These shall be available to the Architect/Engineer, the Owner, the Project Inspector, the Owner's other inspectors and to the Owner's testing personnel. The drawings shall be neatly and clearly marked in color during construction to record all variations made during construction. The representation of such variations shall include such supplementary notes, symbols, legends, and details as may be necessary to clearly show the as-built construction.

(h) Record Drawings: Upon completion of the Work and prior to the final inspection, the Contractor

shall deliver to the Architect/Engineer, for preparation of the Record Drawings, one complete set of "As-Built Drawings" referred to in the preceding subsection.

24. SUBMITTALS

(a) The Contractor shall submit a listing of all Submittals required by the Architect/Engineer or which the Contractor identifies as necessary, fixing the dates for the submission of shop or setting drawings, samples and product data. The listing shall be in a format acceptable to the Architect/Engineer. The Contractor shall identify all Submittals with the Owner's Project Code Number as required by Section 2(f).

(b) Submittals shall be forwarded to the Architect/Engineer for approval if required by the

specifications or if requested by the Architect/Engineer or the Owner. No part of the Work dealt with by a Submittal shall be ordered, fabricated or installed by the Contractor, save at his own risk, until such approval has been given.

Working drawings, shop drawings and/or submittals for fire protection, fire alarm, fire detection and security systems shall be submitted to, and approved by, the Building Official prior to ordering, fabricating or installing such systems. The Contractor shall be solely responsible for obtaining such approval. No part of the Work involving such systems shall be ordered, fabricated or installed by the Contractor until such approval has been obtained.

(c) The Contractor shall furnish to the Architect/Engineer for approval the name of the manufacturer,

the model number, and other identifying data and information respecting the performance, capacity, nature and rating of the machinery and mechanical and other equipment which the Contractor contemplates incorporating in the Work. When Submittals are required by this Contract for materials, the Contractor shall furnish full information concerning the material or articles which he contemplates incorporating in the Work. When required, samples shall be submitted for approval at the Contractor's expense, with all shipping charges prepaid. Machinery, equipment, material and articles installed or used without required approval shall be at the risk of subsequent rejection.

DGS-30-054 CO-7 (04/15)

27

(d) Unless otherwise indicated or required elsewhere in the specifications, shop drawings shall be submitted in the form of one reproducible tracing and three blue line or black line prints. Catalog cuts, product data and other non-reproducible literature, except certificates, shall be submitted in six (6) copies minimum, of which three (3) will be retained by the Architect/Engineer and the remainder will be returned to the Contractor. As is mutually agreeable to the Owner, Architect/Engineer, and Contractor, Submittals may be provided in electronic format in lieu of hardcopy format.

(e) Submittals shall be accompanied by a letter of transmittal which shall list the Project Code

Number, the Submittals included, the specification section number applicable to each, and the date shown on each Submittal. Submittals shall be complete in every respect and bound in sets. Each Submittal shall be clearly marked to show each item, component and/or optional feature proposed to be incorporated into the Project. Cross reference to the plans or specifications as needed to identify the use for which the item or component is intended.

(f) The Contractor shall check the Submittals for compliance with the requirements of the Contract

Documents. The Contractor shall clearly note in writing any and all items which deviate from the requirements of the Contract Documents. Reasons for deviation shall be included with the Submittal. The Contractor shall be solely responsible for checking all dimensions and coordinating all materials and trades to ensure that the components or products proposed, individually or in combination, will fit in the space available and that they will be compatible with other components or products provided.

(g) After checking each submittal, the Contractor shall stamp each sheet of the Submittal with the

Contractor's review stamp. Data submitted in a bound volume or on one sheet printed on two sides, may be stamped on the front of the first sheet only. The Contractor's review stamp shall be worded as follows:

The equipment and material shown and marked in this submittal is that proposed to be incorporated into this Project, is in compliance with the Contract drawings and specifications unless otherwise shown in bold face type or lettering and listed on a page or pages headed "DEPARTURES FROM DRAWINGS AND SPECIFICATIONS", and can be installed in the allocated spaces. Reviewed by _______________________________________ Date ____________________

The person signing the review stamp shall be the person designated in writing by the Contractor as having that authority. (A copy of such designation shall be forwarded to the A/E prior to or with the first Submittal.) The signature on the stamped review statement shall be handwritten in ink, or in the case of electronic submittals, electronically signed in accordance with § 59.1-479 et seq. of the Code of Virginia. Stamped signatures are not acceptable.

(h) The Contractor shall forward all Submittals sufficiently in advance of construction requirements to

allow reasonable time for checking, correcting, resubmitting and rechecking. (i) If a Submittal indicates a departure from the Contract requirements, the Architect/Engineer may

reject the Submittal or, if he deems it to have merit, may recommend it to the Owner, who shall approve or reject it as the Owner, in its sole discretion, sees fit. The departure from the Contract requirements shall be further authorized by a Change Order, if a reduction or increase in the Contract Price is appropriate.

(j) The Architect/Engineer is responsible to the Owner, but not to the Contractor, to verify that the

Submittals conform to the design concept and functional requirements of the plans and specifications, that the detailed design portrayed in shop drawings and proposed equipment and

DGS-30-054 CO-7 (04/15)

28

materials shown in Submittals are of the quality specified and will function properly, and that the Submittals comply with the Contract Documents.

(k) The Work shall be in accordance with approved Submittals. Approval of the Contractor's

Submittals by the A/E does not relieve the Contractor from responsibility of complying with the Contract and all drawings and specifications, except as changed by Change Order.

(l) The plans and/or specifications may indicate that the Architect/Engineer designed or detailed a

portion of the plans around a particular product (most commonly a piece of equipment). Should a different product be proposed by the Contractor and accepted, all modifications, rerouting, relocations and variations required for proper installation and coordination to comply with the design concept and requirements of the Contract Documents shall be the responsibility of the Contractor and shall be made at no extra cost to the Owner. If the plans were noted as designed or detailed around a particular product and/or if a product is named when a "brand name or equal" specification has been used, this is not intended to favor or preclude the use of other products pursuant to Section 26 of these General Conditions. Rather such design merely acknowledges the reality that in many instances the Architect/Engineer must have a basis to design and detail around for dimensions and characteristics of a product or system.

(m) Additional Submittal requirements are shown in the specifications.

25. FEES, SERVICES AND FACILITIES

(a) The Contractor shall obtain all permits, except the Building Permit, and pay for all fees and charges necessary for temporary access and public right-of-way blockage or use, for temporary connections to utilities and for the use of property (other than the Site) for storage of materials and other purposes unless otherwise specifically stated in the Contract Documents.

(b) Certain projects such as renovations and interior modifications of existing buildings will usually

have water and electric service to the building. In those instances, water and electric power, if required for the Work under the Contract, will be furnished by the Owner subject to reasonable use by the Contractor, only to the extent and capacity of present services. The Contractor shall be responsible for providing required connections, temporary wiring, piping, etc. to these services in a safe manner and in accordance with applicable codes. All temporary wire, pipe, etc. shall be removed before the Substantial Completion inspection. Acceptance by the Contractor of the use of Owner's water and electricity constitutes a release to the Owner of all claims and of all liability to the Contractor for whatever damages which may result from power and water outages or voltage variations.

(c) The Owner shall pay any connection charges for permanent utility connections directly to the

utility Supplier. The Contractor shall coordinate such connections with the utility Supplier. (d) It is understood that, except as otherwise specifically stated in the Contract Documents, the

Contractor, either directly or through his Subcontractors, shall provide and pay for all material, labor, tools, equipment, water, light, power, telephone and other services or facilities of every nature whatsoever necessary to execute completely and deliver the Work within the Contract Time for Completion or before the Contract Completion Date.

(e) The Contractor shall provide temporary facilities including Contractor’s office space, Owner’s

Project Inspector office space (if required by the specifications), toilet facilities, and storage space, as required for the operations and the protection of the material and work. Number, sizes and locations shall be subject to approval of the Owner. Sanitary facilities shall be plumbed into an approved waste treatment system or shall be an approved type of chemical toilet and shall be regularly serviced.

DGS-30-054 CO-7 (04/15)

29

26. EQUALS (a) Brand names: Unless otherwise stated in the specifications, the name of a certain brand, make or

manufacturer denotes the characteristics, quality, workmanship, economy of operation and suitability for the intended purpose of the article desired, but does not restrict the Contractor to the specific brand, make, or manufacturer; it is set forth to convey to the Contractor the general style, type, character and quality of the article specified.

(b) Equal materials, equipment or assemblies: Whenever in these Contract Documents, a particular

brand, make of material, device or equipment is shown or specified, such brand, make of material, device or equipment shall be regarded merely as a standard. Any other brand, make or manufacturer of a product, assembly or equipment which in the opinion of the Architect/Engineer is the equal of that specified, considering quality, capabilities, workmanship, configuration, economy of operation, useful life, compatibility with design of the Work, and suitability for the intended purpose, will be accepted unless rejected by the Owner as not being equal.

(c) Substitute materials, equipment or assemblies: The Contractor may propose to substitute a

material, product, equipment, or assembly which deviates from the requirements of the Contract Documents but which the Contractor deems will perform the same function and have equal capabilities, service life, economy of operations, and suitability for the intended purpose. The proposal must include any cost differentials proposed. The Owner will have the A/E provide an initial evaluation of such proposed substitutes and provide a recommendation on acceptability and indicate the A/E's redesign fee to incorporate the substitution in the design. If the proposed substitute is acceptable to the Owner, a Change Order will be proposed to the Contractor to accept the substitute and to deduct the cost of the A/E redesign fee and the proposed cost savings from the Contract Price. The Owner shall have the right to limit or reject substitutions at its sole discretion.

(d) The Contractor shall be responsible for making all changes in the Work necessary to adapt and

accommodate any equal or substitute product which it uses. The necessary changes shall be made at the Contractor's expense.

27. AVAILABILITY OF MATERIALS

If a brand name, product, or model number included in the Contract Documents is not available on the present market, alternate equal products or model numbers may be proposed by the Contractor through the Architect/Engineer for approval by the Owner.

28. CONTRACTOR'S TITLE TO MATERIALS

No materials or supplies for the Work shall be purchased by the Contractor, or by any Subcontractor or Supplier, subject to any security interest, installment or sales contract or any other agreement or lien by which an interest is retained by the seller or is given to a secured party. The Contractor warrants that he has clear and good title to all materials and supplies which he uses in the Work or for which he accepts payment in whole or in part.

29. STANDARDS FOR MATERIALS INSTALLATION & WORKMANSHIP

(a) Unless otherwise specifically provided in the Contract, all equipment, material, and accessories

incorporated in the Work are to be new and in first class condition. (b) Unless specifically approved by the Owner or required by the Contract, the Contractor shall not

incorporate into the Work any materials containing asbestos or any material known by the industry to be hazardous to the health of building construction workers, maintenance workers, or occupants. If the Contractor becomes aware that a material required by the Contract contains

DGS-30-054 CO-7 (04/15)

30

asbestos or other hazardous materials, he shall notify the Owner and the Architect/Engineer immediately and shall take no further steps to acquire or install any such material without first obtaining Owner approval.

(c) All workmanship shall be of the highest quality found in the building industry in every respect. All

items of Work shall be done by craftsmen or tradesmen skilled in the particular task or activity to which they are assigned. In the acceptance or rejection of Work, no allowance will be made for lack of skill on the part of workmen. Poor or inferior workmanship (as determined by the Architect/Engineer, the Owner or other inspecting authorities) shall be removed and replaced at Contractor's expense such that the Work conforms to the highest quality standards of the trades concerned, or otherwise corrected to the satisfaction of the Architect/Engineer, the Owner, or other inspecting authority, as applicable.

(d) Under the various sections of the plans or specifications, where specified items are supplied with

the manufacturer's printed instructions, recommendations, or directions for installation, or where such instructions, recommendations, or directions are available, installation of the specified items shall be in strict accordance with the manufacturer's printed instructions unless those instructions contradict the plans or specifications, in which case the Architect/Engineer will be notified for an interpretation and decision.

(e) Under the various sections of the plans or specifications, where reference is made to specific codes

or standards governing the installation of specified items, installation shall in all cases be in strict accordance with the referenced codes and standards. Where no reference is made to specific codes or standards, installation shall conform to the generally recognized applicable standards for first-class installation of the specific item to be installed. Contractors are expected to be proficient and skilled in their respective trades and knowledgeable of the Codes and Standards of the National Fire Protection Association (NFPA), National Electric Code (NEC), Occupational Safety and Health Act (OSHA) and other codes and standards applicable to installations and associated work by his trade.

(f) Where the manufacturer's printed instructions are not available for installation of specific items,

where specific codes or standards are not referenced to govern the installation or specific items, or where there is uncertainty on the part of the Contractor concerning the installation procedures to be followed or the quality of workmanship to be maintained in the installation of specific items, the Contractor shall consult the Architect/Engineer for approval of the installation procedures or the specific standards governing the quality of workmanship the Contractor proposes to follow or maintain during the installation of the items in question.

(g) During and/or at the completion of installation of any items, the tests designated in the plans or

specifications necessary to assure proper and satisfactory functioning for its intended purpose shall be performed by the Contractor or by its Subcontractor responsible for the completed installation. All costs for such testing are to be included in the Contract Price. If required by the Contract Documents, the Contractor shall furnish prior to final inspection the manufacturers' certificates evidencing that products meet or exceed applicable performance, warranty and other requirements, and certificates that products have been properly installed and tested.

30. WARRANTY OF MATERIALS AND WORKMANSHIP

(a) The Contractor warrants that, unless otherwise specified, all materials and equipment incorporated in the Work under the Contract shall be new, in first class condition, and in accordance with the Contract Documents. The Contractor further warrants that all workmanship shall be of the highest quality and in accordance with the Contract Documents and shall be performed by persons qualified at their respective trades.

(b) Work not conforming to these warranties shall be considered defective.

DGS-30-054 CO-7 (04/15)

31

(c) This warranty of materials and workmanship is separate and independent from and in addition to

any of the Contractor's other guarantees or obligations in the Contract or under Virginia law. 31. USE OF SITE AND REMOVAL OF DEBRIS

(a) The Contractor shall: (1) Perform the Work in such a manner as not to interrupt or interfere with the operation of

any existing activity on, or in proximity to, the Site or with the Work of any other separate contractor;

(2) Store his apparatus, materials, supplies and equipment in such orderly fashion at the Site

of the Work as will not unduly interfere with the progress of his Work or the work of any other separate contractor; and

(3) Place upon the Work or any part thereof only such loads as are consistent with the safety

of that portion of the Work. (b) The Contractor expressly undertakes, either directly or through his Subcontractor(s), to effect all

cutting, filling or patching of the Work required to make the same conform to the plans and specifications, and, except with the consent of the Architect/Engineer, not to cut or otherwise alter the Work of any other separate contractor. The Contractor shall not damage or endanger any portion of the Work or Site, including existing improvements, unless called for by the Contract.

(c) The Contractor expressly undertakes, either directly or through his Subcontractor(s), to clean up

frequently all refuse, rubbish, scrap materials and debris caused by his operations, to the end that at all times the Site shall present a neat, orderly and workmanlike appearance. No such refuse, rubbish, scrap material and debris shall be left within the completed Work nor buried on the building Site, but shall be removed from the Site and properly disposed of in a licensed landfill or otherwise as required by law.

(d) The Contractor expressly undertakes, either directly or through his Subcontractor(s), before Final

Payment or such prior time as the Owner may require, to remove all surplus material, false Work, temporary structures, including foundations thereof, plants of any description and debris of every nature resulting from his operations and to put the Site in a neat, orderly condition; to thoroughly clean and leave reasonably dust free all finished surfaces including all equipment, piping, etc., on the interior of all buildings included in the Contract; and to clean thoroughly all glass installed under the Contract, including the removal of all paint and mortar splatters and other defacements.

If the Contractor fails to clean up at the time required herein, the Owner may do so and charge the costs incurred thereby to the Contractor in accordance with Section 10 (b) of these General Conditions.

(e) The Contractor shall have, On-Site, an employee certified by the Department of Environmental

Quality as a Responsible Land Disturber who shall be responsible for the installation, inspection and maintenance of erosion control and stormwater management measures and devices. The Contractor shall prevent Site soil erosion, the runoff of silt and/or debris carrying water from the Site, and the blowing of debris off the Site in accordance with the applicable requirements and standards of the Contract and the Virginia Department of Environmental Quality’s Erosion and Sediment Control Regulations and the Virginia Stormwater Management Regulations.

DGS-30-054 CO-7 (04/15)

32

32. TEMPORARY ROADS

Temporary roads, if required, shall be established and maintained until permanent roads are accepted, then removed and the area restored to the conditions required by the Contract Documents. Crushed rock, paving and other road materials from temporary roads shall not be left on the Site unless permission is received from the Owner to bury the same at a location and depth approved by the Owner.

33. SIGNS

The Contractor may, at his option and without cost to the Owner, erect signs acceptable to the Owner on the Site for the purpose of identifying and giving directions to the job. No signs shall be erected without prior approval of the Owner as to design and location.

34. PROTECTION OF PERSONS AND PROPERTY

(a) The Contractor expressly undertakes, both directly and through his Subcontractors, to take every reasonable precaution at all times for the protection of all persons and property which may come on the Site or be affected by the Contractor's Work.

(b) The Contractor shall be solely responsible for initiating, maintaining and supervising all safety

precautions and programs in connection with the Work. Any violation of these requirements or duties or any potential safety hazard that is brought to the attention of the Contractor by the Architect/Engineer, the Owner, or any other persons shall be immediately abated.

(c) The provisions of all rules and regulations governing health and safety as adopted by the Safety

Codes Commission of the Commonwealth of Virginia, issued by the Department of Labor and Industry under Title 40.1 of the Code of Virginia, shall apply to all Work under this Contract.

(d) The Contractor shall continuously maintain adequate protection of all his Work from damage and

shall protect the Owner's property from injury or loss arising in connection with this Contract. He shall make good any such damage, injury or loss, except as may be directly and solely due to errors in the Contract Documents or caused by agents or employees of the Owner. The Contractor shall adequately protect adjacent property to prevent any damage to it or loss of use and enjoyment by its owners. The Contractor shall provide and maintain all passageways, guard fences, lights and other facilities for protection as required by public authority, local conditions, or the Contract.

(e) In an emergency affecting the health, safety or life of persons or of the Work, or of the adjoining

property, the Contractor, without special instruction or authorization from the Architect/Engineer or the Owner, shall act, at his discretion, to prevent such threatened loss or injury. Also, should he, to prevent threatened loss or injury, be instructed or authorized to act by the Architect/Engineer or the Owner, he shall so act immediately, without appeal. Any additional compensation or extension of time claimed by the Contractor on account of any emergency work shall be determined as provided by Section 38 of these General Conditions.

(f) When necessary for the proper protection of the Work, temporary heating of a type approved by

the Architect/Engineer must be provided by the Contractor, at the Contractor's expense, unless otherwise specified.

35. CLIMATIC CONDITIONS

The Contractor shall suspend activity on and protect any portion of the Work that may be subject to damage by climatic conditions.

DGS-30-054 CO-7 (04/15)

33

36. PAYMENTS TO CONTRACTOR (a) Unless otherwise provided in the Contract, the Owner will make partial payments to the

Contractor on the basis of a duly certified and approved Schedule of Values and Certificate for Payment, Form CO-12, showing the estimate of the Work performed during the preceding calendar month or work period, as recommended by the Architect/Engineer. When evaluating the Contractor's Form CO-12, the Architect/Engineer will consider the value of the Work in place, the value of approved and properly stored materials, the status of the Work on the critical path with regard to the Time for Completion, and the estimated value of the Work necessary to achieve Final Completion. The Architect/Engineer will schedule a monthly pay meeting to occur no earlier than the 25th day of the month represented by the payment request or not later than the 5th day of the following month. The Contractor shall submit his monthly estimate of Work completed on Form CO-12 in accordance with the Contract between the Owner and Contractor so that it is received by the Architect/Engineer and the Owner's Project Manager at least one work day prior to the date scheduled by the Architect/Engineer for the monthly pay meeting. The Owner will review the estimate with the Architect/Engineer and the Contractor at the monthly pay meeting, which shall be considered the receipt date, and may approve any or all of the estimate of Work for payment. In preparing estimates, the material delivered to the Site and preparatory Work done shall be taken into consideration, if properly documented as required by Section 20 of these General Conditions, or as may be required by the Architect/Engineer so that quantities may be verified. In addition to material delivered to the Site, material such as large pieces of equipment and items purchased specifically for the Project, but stored off the Site within the Commonwealth of Virginia, may be considered for payment, provided all of the following are accomplished prior to the submission of the monthly payment request in which payment for such materials is requested:

(1) The Contractor must notify the Owner in writing, at least ten (10) days prior to the

submission of the payment request, through the Architect/Engineer, that specific items will be stored off Site in a designated, secured place within the Commonwealth of Virginia. The Schedule of Values must be detailed to indicate separately both the value of the material and the labor/installation for trades requesting payment for stored materials. By giving such notification and by requesting payment for material stored off Site, the Contractor warrants that the storage location is safe and suitable for the type of material stored and that the materials are identified as being the property of the Contractor, and agrees that loss of materials stored off the Site shall not relieve the Contractor of the obligation to timely furnish these types and quantities of materials for the Project and meet the Time for Completion or Contract Completion Date, subject to Section 43 (b) of these General Conditions. If the storage location is more than 20 miles from the Site, the Contractor may be required to reimburse the Owner for the cost incurred for travel to the storage location to verify the Contractor's request for payment for materials stored off Site. A Supplementary Agreement shall be required for payment by the Owner to the Contractor for materials or equipment that is stored offsite at a location that is not within the Commonwealth of Virginia.

(2) Such notification, as well as the payment request, shall:

(a) Itemize the quantity of such materials and document with invoices showing the

cost of said materials; (b) Indicate the identification markings used on the materials, which shall clearly

reference the materials to the particular project; (c) Identify the specific location of the materials, which must be within reasonable

proximity to the Site and within the Commonwealth of Virginia;

DGS-30-054 CO-7 (04/15)

34

(d) Include a letter from the Contractor's Surety which confirms that the Surety on the Performance Bond and the Labor and Material Payment Bond has been notified of the request for payment of materials stored off the Site and agrees that the materials are covered by the bond; and

(e) Include a certificate of all-risk builder's risk insurance in an amount not less than

the fair market value of the materials, which shall name the Owner and the Contractor as co-insureds.

(3) The Architect/Engineer shall indicate, in writing, to the Owner that Submittals for such

materials have been reviewed and meet the requirements of the Contract Documents, that the stored materials meet the requirement of the plans and specifications, and that such materials conform to the approved Submittals. Should the A/E deem it necessary to visit the storage site to make such review, the Contractor shall bear the costs incurred therewith.

(4) The Owner, through the Architect/Engineer, shall notify the Contractor in writing of its

agreement to prepayment for such materials. (5) The Contractor shall notify the Owner in writing, through the Architect/Engineer, when

the materials are to be transferred to the Site and when the materials are received at the Site.

(b) Payment will not be made for materials or equipment stored on or off the Site which are not

scheduled for incorporation into the Work within the six months next following submission of the request for payment, unless the Contractor has the prior consent of the Owner, which consent may be granted or withheld by the Owner in its discretion if, in the opinion of the Owner, it is not necessary to procure the materials more than six months in advance of use to assure their availability when needed.

(c) No payment shall be made to the Contractor until:

(1) The Contractor furnishes to the Owner its Social Security Number (SSN) if an individual, or its Federal Employer Identification Number (FEIN) if a proprietorship, partnership, corporation or other legal entity.

(2) Certificates of Insurance or other satisfactory evidence of compliance by the Contractor

with all the requirements of Section 11 (and Section 12 if applicable) of these General Conditions have been delivered to the Owner.

(3) Copies of any certificates of insurance required of a Subcontractor under Section 11 have

been delivered to the Owner for payments based on Work performed by a Subcontractor. (4) The Contractor has (i) submitted a preliminary schedule which is acceptable to the Owner

in accordance with Section 19(a), (ii) submitted a fully complete Project schedule accepted by the Owner in accordance with Section 19(a), (iii) maintained the monthly bar graphs or status reports required by Section 19(d), or (iv) provided a recovery schedule pursuant to Section 19(e), as each of them may be required.

(d) In making such partial payments, five percent (5%) of each payment to the Contractor shall be

retained until Final Completion and acceptance of all Work covered by the Contract, unless otherwise provided by any law, regulation or program of the federal government. Such retainage shall be held to assure faithful performance of the Contract and may also be used as a fund to deduct amounts due to or claimed by the Owner, including, but not limited to, payment to the Owner of all moneys due for deductive change orders, credits, uncorrected Defective Work,

DGS-30-054 CO-7 (04/15)

35

interest, damages, and the like. (§ 2.2-4333 of the Code of Virginia) The Owner may, at its sole discretion, agree on an item by item basis to release the retainage on items which are fully 100% complete and which have accepted by the Owner as being tested and complete and on which no further action or work will be required. Retainage which is released by the Owner shall be distributed by the Contractor in conformance with Section 37 of these General Conditions.

(e) All material and Work for which partial payments are made shall thereupon become the sole

property of the Owner, but this provision shall not relieve the Contractor from the sole responsibility for all materials and Work, including those for which payment has been made, or for the restoration of any damaged materials or Work. Nor shall this provision serve as a waiver of the right of the Owner to require the fulfillment of all of the terms and conditions of the Contract.

(f) The Final Payment, which shall include the retainage, less any amounts due to or claimed by the

Owner, shall not become due until the Architect/Engineer and the Owner agree that Final Completion has been achieved and until the Contractor shall deliver to the Owner through the Architect/Engineer a Certificate of Completion by the Contractor (Form CO-13.2) and an Affidavit of Payment of Claims (Form CO-13), stating that all Subcontractors and Suppliers of either labor or materials have been paid all sums claimed by them for Work performed or materials furnished in connection with this Project less retainage. Amounts due the Owner which may be withheld from the Final Payment may include, but are not limited to, amounts due pursuant to Section 3(i), Section 16(a)-(d), Section 31(d), costs incurred to repair or replace Defective Work, costs incurred as a result of the Contractor's negligent acts or omissions or omissions of those for whom the Contractor is responsible, delay damages under Section 43(h), and any liquidated or actual damages. If all Subcontractors and Suppliers of labor and materials have not been paid the full amount claimed by them, the Contractor shall list each to which an agreed amount of money is due or which has a claim in dispute. With respect to all such Subcontractors and Suppliers, the Contractor shall provide to the Owner, along with the Affidavit of Payment of Claims (Form CO-13), an affidavit from each such Subcontractor and Supplier stating the amount of their subcontract or supply contract, the percentage of completion, the amounts paid to them by the Contractor and the dates of payment, the amount of money still due if any, any interest due the Subcontractor or Supplier pursuant to Section 37(b) below, and whether satisfactory arrangements have been made for the payment of said amounts. If no agreement can be reached between the Contractor and one or more Subcontractors or Suppliers as to the amounts owed to the Subcontractors or Suppliers, the Owner may, in its discretion, pay such portion of the moneys due to the Contractor which is claimed by the Subcontractor or Supplier into a Virginia Court or Federal Court sitting in Virginia, in the manner provided by law. Said payment into court shall be deemed a payment to the Contractor. Nothing in this Section shall be construed as creating any obligation or contractual relationship between the Owner and any Subcontractor or Supplier, and the Owner shall not be liable to any Subcontractor or Supplier on account of any failure or delay of the Owner in complying with the terms hereof.

Before Final Payment is made, the Owner shall confirm that the Contractor has certified compliance with the contract’s small business procurement plan by providing a report in accordance with DSBSD’s requirements. If there are variances between the Contractor’s required small business procurement plan and the actual participation, the Contractor shall provide a written explanation which shall be kept with the contract file and made available upon request. The Owner, in its sole discretion, may withhold the Final Payment until the Contractor is in compliance with its small business procurement plan.

(g) Upon successful completion of the final inspection and all Work required by the Contract,

including but not limited to the delivery of As-Built drawings, equipment manuals, written warranties, acceptance of the Work by the Owner and the delivery of the affidavits required in Section 36(f) of these General Conditions, the Architect/Engineer shall deliver the written Certificate of Completion by the Architect/Engineer (Form CO-13.1) to the Owner, with a copy to the Contractor, stating the entire amount of Work performed and compensation earned by the

DGS-30-054 CO-7 (04/15)

36

Contractor, including extra work and compensation therefor. The Owner may accept the Work for occupancy or use while asserting claims against the Contractor; disputing the amount of compensation due to the Contractor; disputing the quality of the Work, its completion, or its compliance with the Contract Documents; or any other reason.

(h) Unless there is a dispute about the compensation due to the Contractor, Defective Work, quality of

the Work, compliance with the Contract Documents, completion itself, claims by the Owner, other matters in contention between the parties, or unless monies are withheld pursuant to the Comptroller's Debt Setoff Program, within thirty (30) days after receipt and acceptance of the Schedule of Values and Certificate for Payment (Form CO-12) in proper form by the Architect/Engineer at the monthly pay meeting, which shall be considered the receipt date, the Owner shall pay to the Contractor the amount approved by the Architect/Engineer, less all prior payments and advances whatsoever to or for the account of the Contractor. In the case of Final Payment, the completed Affidavit of Payment of Claims (Form CO-13), the Certificate of Completion by the Contractor (Form CO-13.2) and the Certificate of Completion by the Architect/Engineer (Form CO-13.1) shall accompany the final Schedule of Values and Certificate for Payment (Form CO-12) which is forwarded to the Owner for payment. The date on which payment is due shall be referred to as the Payment Date. In the event of disputes, payment shall be mailed on or before the Payment Date for amounts and Work not in dispute, subject to any set offs claimed by the Owner; provided, however in instances where further appropriations are required by the General Assembly or where the issuance of further bonds is required, in which case, payment shall be made within thirty (30) days after the effective date of such appropriation or within thirty (30) days after the receipt of bond proceeds by the Owner. All prior estimates and payments including those relating to extra Work may be corrected and adjusted in any payment and shall be corrected and adjusted in the Final Payment. In the event that any request for payment (CO-12) by the Contractor contains a defect or impropriety, the Owner shall notify the Contractor of any defect or impropriety which would prevent payment by the Payment Date, within five (5) days after receipt of the Schedule of Values and Certificate for Payment (Form CO-12) by the Owner from the Architect/Engineer.

(i) Interest shall accrue on all amounts owed by the Owner to the Contractor which remain unpaid

seven (7) days following the Payment Date. Said interest shall accrue at the discounted ninety-day U.S. Treasury bill rate as established by the Weekly Auction and as reported in the publication entitled The Wall Street Journal on the weekday following each such Weekly Auction. During the period of time when the amounts due to the Contractor remain unpaid following the seventh (7) day after the Payment Date, the interest accruing shall fluctuate on a weekly basis and shall be that established by the immediately prior Weekly Auction. It shall be the responsibility of the Contractor to gather and substantiate the applicable weekly interest rates to the satisfaction of the Owner and to calculate to the satisfaction of the Owner the interest due. In no event shall the rate of interest charge exceed the rate of interest charged pursuant to § 58.1-1812 of the Code of Virginia. No interest shall accrue on retainage or when payment is delayed because of disagreement between the Owner and the Contractor regarding the quantity, quality or timeliness of the Work, including, but not limited to, compliance with Contract Documents or the accuracy of any Request for Payment received. This exception to the accrual of interest stated in the preceding sentence shall apply only to that portion of a delayed payment which is actually the subject of such a disagreement and shall apply only for the duration of such disagreement. Nothing contained herein shall be interpreted, however, to prevent the withholding of retainage to assure faithful performance of the Contract. These same provisions relating to payment of interest to the Contractor shall apply also to the computation and accrual of interest on any amounts due from the Contractor to the Owner for deductive change orders and to amounts due on any claims by the Owner. The date of mailing of any payment by the U.S. Mail is deemed to be the date of payment to the addressee.

(j) The acceptance by the Contractor of the Final Payment shall be and operate as a release to the

Owner of all claims by the Contractor, its Subcontractors and Suppliers, and of all liability to the

DGS-30-054 CO-7 (04/15)

37

Contractor whatever, including liability for all things done or furnished in connection with this Work, except for things done or furnished which are the subject of unresolved claims for which the Contractor has filed a timely written notice of intent, provided a claim is submitted no later than sixty (60) days after Final Payment. Acceptance of any interest payment by the Contractor shall be a release of the Owner from claims by the Contractor for late payment.

(k) No certificate for payment issued by the Architect/Engineer, and no payment, final or otherwise,

no certificate of completion, nor partial or entire use or occupancy of the Work by the Owner, shall be an acceptance of any Work or materials not in accordance with the Contract, nor shall the same relieve the Contractor of responsibility for faulty materials or Defective Work or operate to release the Contractor or his Surety from any obligation under the Contract, the Standard Performance Bond and the Standard Labor and Material Payment Bond.

37. PAYMENTS BY CONTRACTOR (§ 2.2-4354, Code of Virginia)

Under § 2.2-4354, Code of Virginia, the Contractor is obligated to: (a) Within seven (7) days after receipt of amounts paid to the Contractor by the Owner for Work

performed by the Subcontractor or Supplier under this Contract,

(1) Pay the Subcontractor or Supplier for the proportionate share of the total payment received from the Owner attributable to the Work performed by the Subcontractor or the materials furnished by the Supplier under this Contract; or

(2) Notify the Subcontractor or Supplier, in writing, of his intention to withhold all or a part

of the Subcontractor or Supplier's payment with the reason for nonpayment; (b) Pay interest to the Subcontractor or Supplier on all amounts owed by the Contractor that remain

unpaid after seven (7) days following receipt by the Contractor of payment from the Owner for Work performed by the Subcontractor or materials furnished by the Supplier under this contract, except for amounts withheld as allowed under subsection (a) (2) of this Section.

(c) Include in each of his subcontracts a provision requiring each Subcontractor to include in each of

its subcontracts a provision requiring each subcontractor to include or otherwise be subject to the same payment and interest requirements with respect to each lower tier subcontractor. Each Subcontractor shall include with its invoice to, or request for payment from, the Contractor, a certification that that Subcontractor has paid each of its suppliers and lower tier subcontractors their proportionate share of previous payments received from the Contractor attributable to the Work performed or the materials furnished by it under this Contract.

The Contractor's obligation to pay interest to the Subcontractor or Supplier pursuant to subsection (b) of this Section is not an obligation of the Owner. A modification to this Contract shall not be made for the purpose of providing reimbursement for such interest charge. A Contractor's cost reimbursement claim shall not include any amount for reimbursement of such interest charge.

38. CHANGES IN THE WORK

(a) The Owner may at any time, by written order utilizing the Commonwealth of Virginia Change Order Form CO-11 and without notice to the sureties, make changes in the Work which are within the general scope of the Contract, except that no change will be made which will increase the total Contract Price to an amount more than twenty percent (20%) in excess of the original Contract Price without notice to sureties. At the time of the Preconstruction Meeting described in Section 50(b), the Contractor and the Owner shall advise each other in writing of their designees authorized to accept and/or approve changes to the Contract Price and of any limits to each designee's authority. Should any designee or limits of authority change during the time this

DGS-30-054 CO-7 (04/15)

38

Contract is in effect, the Contractor or Owner with such a change shall give written notice to the other within seven (7) calendar days, utilizing the procedures set forth in these General Conditions. The Contractor agrees and understands that the authority of the Owner's designee is limited by Virginia Code §2.2-4309 and any other applicable statute.

In making any change, the charge or credit for the change shall be determined by one of the following methods as selected by the Owner:

(1) Fixed Price: By a mutually agreed fixed amount change to the Contract Price and/or

time allowed for completion of the Work. The Change Order shall be substantiated by documentation itemizing the estimated quantities and costs of all labor, materials, and equipment required as well as any mark-up used. The price change shall include the Contractor's reasonable overhead and profit, including overhead for any unreasonable delay arising from or related to the Change Order and/or the change in the Work. See Subsections (d), (e) and (f), below.

(2) Unit Price: By using unit prices and calculating the number of net units of Work in each

part of the Work which is changed, either as the Work progresses or before Work on the change commences, and by then multiplying the calculated number of units by the applicable unit price set forth in the Contract or multiplying by a mutually agreed unit price if none was provided in the Contract. No additional percentage markup for overhead or profit shall be added to the unit prices.

(3) Cost Reimbursement: By ordering the Contractor to perform the changed Work on a

cost reimbursement basis by issuing two Change Orders citing this Subsection, an initiating Change Order, authorizing the changed Work, and a confirming Change Order approving the additional cost and time for the changed Work. The initiating Change Order shall: (i) Describe the scope or parameters of the change in the Work;

(ii) Describe the cost items to be itemized and verified for payment and the method

of measuring the quantity of work performed; (iii) Address the impact on the schedule for Substantial Completion; (iv) Order the Contractor to proceed with the change to the Work; (v) Order the Contractor to keep in a form acceptable to the Owner, an accurate,

itemized account of the actual cost of the change in the Work, including, but not limited to, the actual costs of labor, materials, equipment, and supplies;

(vi) Order the Contractor to annotate a copy of the Project schedule to accurately

show the status of the Work at the time this first Change Order is issued, to show the start and finish dates of the changed Work, and the status of the Work when the changed Work is completed; and

(vii) State that a confirming Change Order will be issued to incorporate the cost of

the ordered changed in the Work into the Contract Price and any change in the Contract Time for Completion or Contract Completion Date.

The Contractor shall sign the initiating Change Order acknowledging he has been ordered to proceed with the change in the Work. The Contractor's signature on each initiating Change Order citing this Subsection 38(a)(3) as the method for determining the cost of

DGS-30-054 CO-7 (04/15)

39

the Work shall not constitute the Contractor's agreement on the cost or time impact of the ordered Work.

Except as otherwise may be agreed to in writing by the Owner, such costs shall not exceed those prevailing for the trades or crafts (based upon rates established by the US Department of Labor, Bureau of Labor Statistics, or other generally recognized cost data publication), materials, and equipment in the locality of the Project, may include only those items listed as allowable in Subsection 38(e), and shall not include any of the costs listed as not allowable in Subsection 38(f). The Owner shall be permitted, on a daily basis, to verify such records and may require such additional records as are necessary to determine the cost of the change to the Work.

Within fourteen (14) days after the conclusion of such ordered Work, the Contractor and the Owner shall reach agreement on (i) a cost for the ordered Work, based on the records kept and the Contractor's allowance for overhead and profit determined in accordance with the provisions set forth in Subsections 38(d), (e), and (f) below; and (ii) the change in the Contract Time for Completion or Contract Completion Date, if necessary, as a result of the ordered Work. Such costs and time shall be incorporated into a confirming Change Order which references the initiating Change Order. If agreement on the cost and time of the changed Work cannot be reached within the fourteen (14) days allotted, the Contractor may submit a claim for the disputed cost or time as provided for in Section 47.

(4) By issuing a unilateral change order in the amount deemed appropriate by the Owner for the Work. If the Contractor objects to the amount or scope of the change order then the Contractor may within the 14 days of the date of the change order file a claim for the disputed amount as provided for in section 47.

(b) The Contractor shall review any Owner requested or directed change and shall respond in writing

within fourteen (14) calendar days after receipt of the proposed change (or such other reasonable time as the Owner may direct), stating the effect of the proposed change upon his Work, including any increase or decrease in the Contract time and price. The Contractor shall furnish to the Owner an itemized breakdown of the quantities and prices used in computing the proposed change in Contract Price.

The Owner shall review the Contractor's proposal and respond to the Contractor within thirty (30) days of receipt. If a change to the Contract Price and Time for Completion or Contract Completion Date are agreed upon, both parties shall sign the Change Order. If the Contract Price and Time for Completion or Contract Completion Date are not agreed upon, the Owner may direct the Contractor to proceed under Subsection 38(a)(3), above. Change Orders shall be effective when signed by both parties, unless approval by the Governor or his designee is required, in which event the Change Order shall be effective when signed by the Governor or his designee.

(c) In figuring changes, any instructions for measurement of quantities set forth in the Contract shall

be followed.

(d) Overhead and profit for both additive and deductive changes in the Work (other than changes covered by unit prices) shall be paid by applying the specified percentage markups only on the net cost of the changed Work (i.e. difference in cost between original and changed Work excluding overhead and profit). Said percentages for overhead and profit shall reasonably approximate the Contractor’s overhead and profit, but shall not exceed the percentages for each category listed below:

(1) If a Subcontractor does all or part of the changed Work, the Subcontractor's mark-up for

overhead and profit on the Work it performs shall be a maximum of fifteen percent

DGS-30-054 CO-7 (04/15)

40

(15%). The Contractor's mark-up for overhead and profit on the Subcontractor's price shall be a maximum of ten percent (10%).

(2) If the Contractor does all or part of the changed Work, its markup for overhead and profit

on the changed Work it performs shall be a maximum of fifteen percent (15%). (3) If a Sub-subcontractor at any tier does all or part of the changed Work, the Sub-

subcontractor's markup on that Work shall be a maximum of fifteen percent (15%). The markup for overhead and profit on a sub-subcontractor's Work by the Contractor and all intervening tiers of Subcontractors shall not exceed a total of ten percent (10%).

(4) Where Work is deleted from the Contract prior to commencement of that Work without

substitution of other similar Work, one hundred percent (100%) of the Contract Price attributable to that Work shall be deducted from the Contract Price. However, in the event that material Submittals have been approved and orders placed for said materials, a lesser amount, but in no case less than eighty percent (80%) of the Contract Price attributable to that Work, shall be deducted from the Contract Price. The credit to the Owner for reduced premiums on labor and material bonds and performance bonds shall in all cases be one hundred percent (100%).

(e) Allowable costs for changes in the Work may include but are not limited to the following:

(1) Labor costs for employees directly employed in the change in the Work, including

salaries and wages plus the cost of payroll charges and fringe benefits and overtime premiums, if such premiums are explicitly authorized by the Owner.

(2) Materials incorporated into the change to the Work, including costs of transportation and

storage, if applicable. If applicable, all cash discounts shall accrue to the Contractor, unless the Owner deposits funds with the Contractor to make such payments, and all trade discounts, rebates, refunds, and returns from the sale of surplus materials shall accrue to the Owner.

(3) Equipment incorporated in the changed Work or equipment used directly in

accomplishing the Work. If rented expressly for accomplishing the change in the Work, the cost shall be the rental rate according to the terms of the rental agreement, which the Owner shall have the right to approve. If owned by the Contractor, the costs shall be a reasonable price based upon the life expectancy of the equipment and the purchase price of the equipment. If applicable, transportation costs may be included.

(4) Costs of increases in premiums for the Standard Labor and Material Payment Bond and

the Standard Performance Bond, provided coverage for the cost of the change in the Work results in such increased costs. At the Owner's request, the Contractor shall provide proof of his notification to the Surety of the change in the Work and of the Surety's agreement to include such change in its coverage. The cost of the increase in premium shall be an allowable cost but shall not be marked up.

(5) Contractor and Subcontractor overhead costs as set forth in Subsection (d) markups above. (6) Agreed Compensation for Overhead for Changes to Time for Completion or

Contract Completion Date for Changes to the Work: If the change in the Work also changes the Time for Completion or the Contract Completion Date by adding days to complete the Work, an itemized accounting of the following direct Site overhead and home office overhead and other indirect overhead expenses set forth in subparagraphs (i) and (ii) below may be considered as allowable costs for compensation in addition to those shown above:

DGS-30-054 CO-7 (04/15)

41

(i) Direct Site Overhead Expenses:

The Contractor’s per diem expenses, as shown by the itemized accounting, for the following allowable direct Site overhead expenses: The Site superintendent's pro-rata salary, temporary Site office trailer, and temporary Site utilities including basic telephone service, electricity, heat, water, and sanitary / toilet facilities for each day added. All other direct expenses are covered by and included in the Subsection 38(d) markups above.

(ii) Home Office and Other Indirect Overhead Expenses:

A five percent (5%) markup on the above direct Site overhead expenses will be allowed as compensation for the Contractor’s home office overhead and all other direct or indirect overhead expenses for days added to the Time for Completion or the Contract Completion Date for a change in the Work. All other overhead and other direct or indirect overhead expenses are covered by and included in this markup and the Subsection (d) markups above.

(7) Any other costs directly attributable to the change in the Work with the exception of

those set forth in Subsection 38(f) below. (f) Allowable costs for changes in the Work shall not include the following:

(1) Costs due to the negligence of the Contractor, any Subcontractor, Supplier, their

employees, or other persons for whom the Contractor is responsible, including, but not limited to, costs for the correction of Defective Work, for improper disposal of material, for equipment wrongly supplied, for delay in performing the Work, or for delay in obtaining materials or equipment.

(2) Home office expenses including payroll costs for the Contractor's officers, executives,

administrators, accountants, counsel, timekeepers, clerks, and other similar administrative personnel employed by the Contractor, whether at the Site or in the Contractor's principal or branch office for general administration of the Work. These costs are deemed overhead included in the percentage markups allowable in Subsections 38(d) above.

(3) Home and field office expenses not itemized in Subsection 38(e)(6) above. Such items

include, but are not limited to, expenses of Contractor's home and branch offices, Contractor's capital expenses, interest on Contractor's capital used for the Work, charges for delinquent payments, small tools, incidental job costs, rent, utilities, telephone and office equipment, and other general overhead expenses.

(4) Other items reasonably determined by the Owner to not be allowed.

(g) All Change Orders, except the "initial" Change Orders authorizing work citing Subsection 38(a)(3) procedures, must state that the Contract Time for Completion or Contract Completion Date is not changed or is either increased or decreased by a specific number of days. The old Time for Completion and, if changed, the new Time for Completion must be stated.

If the Contractor requests an extension to the Time for Completion or a later Contract Completion Date, he must provide written justification for the extension to the Architect/Engineer and to the Owner. The written justification must demonstrate an anticipated actual increase in the time required to complete the Work beyond that allowed by the Contract as adjusted by prior change orders or amendments to the Contract, not just an increase or decrease in the time needed to complete some portion of the total Work. When a CPM schedule is required by the Contract, no

DGS-30-054 CO-7 (04/15)

42

extension to the Time for Completion or Contract Completion Date shall be allowed unless, and then only to the extent that, the additional or changed Work increases the length of the critical path beyond the Time for Completion or Contract Completion Date. If approved, the increase in time required to complete the Work shall be added to the Time for Completion or Contract Completion Date. The Owner may decrease, by Change Order, the Time for Completion or Contract Completion Date when an Owner-requested deletion from the Work results in a decrease in the actual time required to complete the Work as demonstrable on the Bar Graph Schedule or on the CPM Schedule, whichever is appropriate. The Contractor may submit a request to decrease, by Change Order, the Time for Completion or Contract Completion Date under the procedures and subject to the considerations set forth in Section 19(f). No request for such decrease shall be considered for approval unless the proposed shorter schedule is otherwise acceptable under Sections 19(b) or (c), whichever is applicable. The Change Order decreasing the Time for Completion or changing the Contract Completion Date must be signed by both the Owner and the Contractor.

With the exception of Change Orders under Subsection 38(a)(3), which shall arrive at a change to the Contract Price and any change to time using the procedures set forth therein, each Change Order shall include all time and monetary impacts of the change, whether the Change Order is considered alone or with all other changes during the course of the Project. Failure to include a change to time and changes in the Contract Price attributable to the change in time under Subsections 38(a)(1) or (2) shall waive any change to the time and Contract Price unless the parties mutually agree in writing to postpone a determination of the time related impacts of the change. Such a determination may be postponed not more than forty-five (45) days to give the Contractor an opportunity to demonstrate a change in the time and price needed to complete the Work. During any such postponement, the Work shall proceed, unless the Owner agrees otherwise.

If at any time there is a delay in the critical path of the Work due to postponement, due to the Contractor's efforts to justify an extension of the time or an increase in the Contract Price, or due to the Contractor's refusal to proceed with any of the Work, pending agreement on a change in time or price, such delay and any Contractor costs resulting from it shall not serve as the basis for the extension of the Time for Completion or Contract Completion Date or for an increase in the Contract Price.

(h) The acceptance by the Contractor of any payment made by the Owner under a Change Order shall

be and operate as a release to the Owner of all claims by the Contractor and of all liability owing to the Contractor for all things done or furnished in connection with the Work described in the Change Order. The execution of any Change Order by the Owner shall not be an acceptance of any Work or materials not in accordance with the Contract Documents, nor shall it relieve the Contractor of responsibility for faulty materials or workmanship or operate to release the Contractor or his surety from any obligation arising under the Contract, the Standard Performance Bond, or the Standard Labor and Material Payment Bond.

(i) Payments will not be made for any Work, labor, or materials performed on a unit price or a

Subsection 38(a)(3) basis until the Contractor has furnished the Owner documents, certified as true and correct by an authorized officer or agent of the Contractor, evidencing the cost of such Work, labor, and materials. The Owner may require any or all of the following documentation to be provided by the Contractor.

For Work performed on a Unit Price basis: (1) Certified measurements of authorized and approved excavations, over-excavations, fills

and/or backfills, and similar work; and/or

DGS-30-054 CO-7 (04/15)

43

(2) Certified measurements of piling installed, caissons installed, and similar work; and/or (3) Daily records of waste materials removed from the Site and/or fill materials imported to

the Site. For Work performed on a Subsection 38(a)(3) basis: (1) Certified payroll records showing the name, classification, date, daily hours, total hours,

rate, and extension for each laborer, foreman, supervisor, or other worker; and/or (2) Equipment type & model, dates, daily hours, total hours, rental rate, or other specified

rate, and extension for each unit of equipment; (3) Invoices for materials showing quantities, prices, and extensions; (4) Daily records of waste materials removed from the Site and/or fill materials imported to

the Site; (5) Certified measurements of over-excavations, piling installed and similar work; and/or (6) Transportation records for materials, including prices, loads, and extensions. Requests for payment shall be accompanied and supported by invoices for all l materials used and for all transportation charges claimed. If materials come from the Contractor's own stock, then an affidavit may be furnished, in lieu of invoices, certifying quantities, prices, etc. to support the actual cost.

39. EXTRAS

If the Contractor claims that any instructions given to him by the Architect/Engineer or by the Owner, by drawings or otherwise, involve extra Work which increases the scope of the Contract, then, except in emergencies endangering life or property, he shall give the Architect/Engineer and the Owner written notice thereof before proceeding to execute the Work. Said notice shall be given promptly enough to avoid delaying the Work and in no instance later than fourteen (14) days after the receipt of such instructions. Should it not be immediately clear to the Contractor that the change involves extra Work outside the scope of the Contract, written notice shall be sufficient if given as soon as possible after such realization, but in no event later than fourteen (14) days after the start of such Work. If the Owner agrees, a Change Order shall be issued as provided in Section 38 of these General Conditions, and any additional compensation shall be determined by one of the three (3) methods provided in Subsection 38(a), as selected by the Owner. If the Owner does not agree, then any claims for compensation for the extra Work shall be filed in accordance with Section 47.

40. CONTRACTOR'S RIGHT TO STOP WORK OR TERMINATE THE CONTRACT

If the Work should be stopped under an order of any court or other public authority for a period of ninety (90) days through no fault of the Contractor or anyone employed by him, or if the Owner should fail to pay to the Contractor within thirty (30) days any sum certified by the Architect/Engineer when no dispute exists as to the sum due or any provision of the Contract, then the Contractor may, upon ten (10) calendar days written notice to the Owner and the Architect/Engineer, stop Work or terminate the Contract and recover from the Owner payment for the cost of the Work actually performed, together with overhead and profit thereon, but profit on the Work performed shall be recovered only to the extent that the Contractor can demonstrate that he would have had profit on the entire Contract if he had completed the Work. The Contractor may not receive profit or any other type of compensation for parts of the Work not performed. The Contractor may recover the reasonable cost of physically closing down the Site, but no other costs of termination. The Owner may offset any claims it may have against the Contractor against the amounts due

DGS-30-054 CO-7 (04/15)

44

to the Contractor. In no event shall termination of the Contract by the Contractor terminate the obligations of the Contractor's surety on its payment and performance bonds.

41. OWNER'S RIGHT TO TERMINATE THE CONTRACT FOR CAUSE

(a) If the Contractor should be adjudged as bankrupt, or if he should make a general assignment for

the benefit of his creditors, or if a receiver should be appointed on account of his insolvency, the Owner may terminate the Contract. If the Contractor should refuse or should repeatedly fail, except in cases for which extension of time is provided, to supply enough properly skilled workmen or proper materials and equipment, or if he should fail to perform the Work in a diligent, efficient, workmanlike, skillful, and careful manner, or if he should fail or refuse to perform the Work in accordance with the Contract Documents, or if he should fail to make prompt payment to Subcontractors or Suppliers of material or labor, or if he should disregard laws, ordinances or the written instructions of the Architect/Engineer or the Owner, or otherwise be in substantial violation of any provision of the Contract, then the Owner may terminate the Contract.

(b) Prior to termination of the Contract, the Owner shall give the Contractor and his surety ten (10)

days written notice of such termination in the manner provided in Section 1 (definition of "Notice") of these General Conditions and allow ten (10) days during which the Contractor and/or his surety may rectify the basis for the notice. If rectified to the satisfaction of the Owner within said ten (10) days, the Owner may rescind its notice of termination. If not, the termination for cause shall become effective at the end of the ten (10) day notice period without further notice to the Contractor. In the alternative, the Owner may, in writing, postpone the effective date of the termination for cause, at its sole discretion, if it should receive reassurances from the Contractor and/or its surety that the basis for the termination will be remedied in a time and manner which the Owner finds acceptable. If at any time after such postponement, the Owner determines that Contractor and/or its surety has not or is not likely to rectify the causes of termination in an acceptable manner or within the time allowed, then the Owner may immediately terminate the Contract for cause, without the necessity of further ten (10) day notice, by notifying the Contractor and his surety in writing of the termination. In no event shall termination for cause terminate the obligations of the Contractor's surety on its payment and performance bonds.

(c) Upon termination of the Contract becoming effective, the Owner shall take possession of the Site

and of all materials, tools and equipment thereon and shall proceed as follows:

(1) No Security Provided: If no security has been provided pursuant to Section 8 herein, the Owner shall finish the Work by whatever method he may deem expedient. If the expense of finishing the Work, including compensation for additional managerial and administrative services, shall exceed the unpaid balance of the Contract Price, the Contractor shall pay the difference to the Owner, together with any other expenses of terminating the Contract and having it completed by others.

(2) Security Provided: If security has been provided pursuant to Section 8 herein, the

Owner shall provide Notice to the Surety that termination of the Contract became effective and proceed as set forth in the Standard Performance Bond, CO-10, Form DGS-30-084, and the Terms and Conditions therein. If the expense of finishing the Work, including compensation for additional managerial and administrative services, shall exceed the unpaid balance of the Contract Price and the penal amount of the Standard Performance Bond, the Contractor shall pay the difference to the Owner, together with any other expenses of terminating the Contract and having it completed by others.

(d) If it should be judicially determined that the Owner improperly terminated this Contract for cause,

then the termination shall be deemed to be a termination for the convenience of the Owner and the Contractor’s rights and remedies shall be solely limited to those provided by Section 42 of these General Conditions.

DGS-30-054 CO-7 (04/15)

45

(e) Termination of the Contract under this Section is in addition to and without prejudice to any other

right or remedy of the Owner. Any actions by the Owner permitted herein shall not be deemed a waiver of any other right or remedy of the Owner under the Contract or under the law. The Owner may offset any claims it may have against the Contractor against the amounts due to the Contractor. The provisions of this Section shall survive termination of the Contract.

42. TERMINATION BY OWNER FOR CONVENIENCE

(a) The Owner may terminate this Contract, in whole or in part, at any time without cause upon giving the Contractor written notice of such termination in the manner provided in Section 1 (definition of "Notice") of these General Conditions. Upon such termination, the Contractor shall immediately cease Work and remove from the Site all of its labor forces, equipment and such of its materials as Owner elects not to purchase or to assume in the manner hereinafter provided. Upon such termination, the Contractor shall take such steps as Owner may require to assign to the Owner the Contractor's interest in all Subcontracts and purchase orders designated by Owner. After all such steps have been taken to Owner's satisfaction, the Contractor shall receive as full compensation for termination and assignment the following:

(1) Amounts due for Work performed in accordance with the Contract subsequent to the

latest approved Schedule of Values and Certificate for Payment (Form CO-12) through the date of termination; and

(2) All amounts then otherwise due under the terms of this Contract associated with the

Work performed prior to the date of termination; and (3) Reasonable compensation for the actual cost of demobilization incurred by the Contractor

as a direct result of such termination. The Contractor shall not be entitled to any compensation or damages for lost profits or for any other type of contractual compensation or damages other than those provided in Subsection 42(a). The Owner may offset any claims it may have against the Contractor against the amounts due to the Contractor. Upon payment of the foregoing, Owner shall have no further obligations to Contractor of any nature. The Contractor agrees to waive all claims against the Owner for any consequential damages that may arise from or relate to the Owner’s termination of the Contract including, but not limited to, damages for loss of revenue, income, profit, business, reputation, or bonding capacity.

(b) In no event shall termination for the convenience of the Owner terminate the obligations of the Contractor's surety on its payment and performance bonds.

(c) Any actions by the Owner permitted herein shall not be deemed a waiver of any other right or

remedy of the Owner under the Contract or under the law. The provisions of this Section shall survive termination of the Contract.

43. DAMAGES FOR DELAYS; EXTENSION OF TIME

(a) Excusable Non-Compensable Delays: If and to the extent that the Contractor is delayed at any time in the progress of the Work by strikes, fires, unusual delays in transportation or unavoidable casualties, or other causes outside the control of the Owner or the Contractor, with the exception of delays caused by weather provided for in Section 6, for which the Contractor intends to request an extension of either the Time for Completion or the Contract Completion Date, as the case may be, then the Contractor shall give the Owner and Architect/Engineer written notice of the delay within fourteen (14) days of the inception of the delay. The Contractor shall also give written notice to the Owner and Architect/Engineer of the termination of the delay not more than fourteen

DGS-30-054 CO-7 (04/15)

46

(14) days after such termination. If the Owner agrees with the existence and the impact of the delay, the Owner shall extend the Time for Completion, the Contract Completion Date or Final Completion Date, as the case may be, for the length of time that the date for Substantial Completion or Final Completion was actually delayed thereby, and the Contractor shall not be charged with liquidated or actual damages for delay during the period of such extension nor shall the Contractor be due compensation or damages of any kind, under any theory of law, as a result of such delay, the impact of such delay, or acceleration of Work as a result of such delay. In the event a CPM schedule is required by the Contract, no extension of the Time for Completion or Contract Completion Date shall be granted unless the Contractor demonstrates a delay in the critical path of the approved CPM schedule or approved bar graph schedule.

(b) Excusable Compensable Delays: If and to the extent that the Contractor is unreasonably delayed

at any time in the progress of the Work by any acts or omissions of the Owner, its agents, or employees due to causes within the Owner's control, and the Contractor intends to request an extension of either the Time for Completion or the Contract Completion Date, as the case may be, and/or additional compensation for damages, if any, caused by the delay, then the Contractor shall notify the Owner and the Architect/Engineer immediately at the time of the occurrence giving rise to the delay by the fastest means available and shall give written notice no later than two (2) working days after inception of the delay. The Contractor's written notice shall specify the nature of the delay claimed by the Contractor, the cause of the delay, and the impact of the delay on the Contractor's Work schedule. The Owner shall then have three (3) working days to respond to the Contractor's notice with a resolution, remedy, direction to alleviate the delay, or rejection of the Contractor’s notice of delay. The Owner’s failure to respond within the time required shall be deemed to be a rejection of the Contractor’s notice. The Contractor shall also give written notice to the Owner and Architect/Engineer of the termination of the delay not more than fourteen (14) days after such termination. If and to the extent that a delay is caused by or due to the Owner or A/E taking any actions permitted or required by the Contract, the Contractor shall be entitled to an extension of time or additional compensation only for the portion of the delay that is unreasonable, if any.

(c) Non-Excusable Non-Compensable Delays: The Contractor shall not be entitled to an extension

of the Time for Completion or Contract Completion Date or to any additional compensation for delays if and to the extent they are (1) caused by acts, omissions, fault, or negligence of the Contractor or his Subcontractors, agents or employees or due to foreseeable causes within their control, including, but not limited to, delays resulting from Defective Work including workmanship and/or materials, from rejected work which must be corrected before dependent work can proceed, from Defective Work or rejected work for which corrective action must be determined before like work can proceed, from incomplete, incorrect, or unacceptable Submittals or samples, or from the failure to furnish enough properly skilled workers, proper materials or necessary equipment to diligently perform the work in a timely manner in accordance with the Project schedule; or (2) due to causes that would entitle the Owner to recover delay costs or damages.

(d) No extension of time or additional compensation, if applicable, will be granted for any delay

unless the claimed delay directly affects the critical path of the approved CPM schedule or the schedule shown on the approved bar graph schedule, whichever is applicable, and any float has been consumed. No extension of time or additional compensation shall be given for a delay if the Contractor failed to give notice in the manner and within the time prescribed in Subsections 43(a) or (b) above, whichever applies. Furthermore, no extension of time or additional compensation shall be given for any delay unless a written request therefor is made in writing to the Owner, with a copy to the Architect/Engineer, within twenty (20) days of the end of the delay. The request shall state the cause of the delay, the number of days of extension requested, and any additional compensation requested by the Contractor. Failure to give written notice of either the inception or the termination of the cause of delay or failure to present a claim for extension of time and/or

DGS-30-054 CO-7 (04/15)

47

monetary compensation within the times prescribed shall constitute a waiver of any claim for extension or additional compensation based upon that cause.

(e) Requests for extensions of time and/or compensation for delays pursuant to Subsection 43(b)

above must be substantiated by itemized data and records clearly showing that the Work delayed was on the critical path of the approved CPM schedule or on the sequence of Work on the approved bar graph schedule, as modified, whichever applies, and that the additional time and/or costs incurred by the Contractor are directly attributable to the delay in the Work claimed. Furthermore, compensation for delay shall be calculated from the contractual Time for Completion or Contract Completion Date, as adjusted by Change Order, and shall not be calculated based on any early completion planned or scheduled by the Contractor, unless a Change Order has been executed pursuant to Section 19(f) changing the Time for Completion or the Contract Completion Date to reflect such early completion. See Section 19 for procedures for the Contractor to follow if he plans early completion of the Work and wishes to request a Change Order reflecting the early completion date.

Agreed Compensation/Liquidated Damages for Owner Delay:

If and to the extent that the Contractor is entitled to an extension in the Time for Completion or the Contract Completion Date and additional compensation purely as a result of delay under Subsection 43(b) and not as a result of a change in the Work under Section 38, the agreed compensation and liquidated damages due the Contractor for days added to the Time for Completion or the Contract Completion Date for each day of such delay shall be the per diem expenses as determined from an itemized accounting of the direct Site overhead expenses and home office and other indirect overhead expenses only as specified in Subsections 38(e)(6)(i) and (ii). These expenses shall exclude any and all expenses specified in Subsection 38(f).

(f) If the Contractor submits a claim for delay damages pursuant to Subsection 43(b) above, the

Contractor shall be liable to the Owner for a percentage of all costs incurred by the Owner in investigating, analyzing, negotiating, and litigating or arbitrating the claim, which percentage shall be equal to the percentage of the Contractor's total delay claim which is determined through litigation or arbitration to be false or to have no basis in law or in fact. (§ 2.2-4335, Code of Virginia)

(g) Any change in the Contract Time for Completion or Contract Completion Date shall be

accomplished only by issuance of a Change Order. (h) Agreed Compensation/Liquidated Damages for Contractor Delay: If the Contractor fails to

complete the Work within the Time for Completion or the Contract Completion Date, the Contractor shall be liable to the Owner in the amounts set forth in the Supplemental General Conditions, if any, not as a penalty, but as fixed, agreed, and liquidated damages for delay until the Work is substantially or finally completed as the case may be. If liquidated damages are not so fixed in the Supplemental General Conditions, the Contractor shall be liable for any and all actual damages sustained as a result of delay. In addition to damages for delay, whether liquidated or actual, the Contractor shall also be liable for any and all actual damages sustained by the Owner as a result of any other breach of the Contract, including, but not limited to, Defective Work and abandonment of the Contract.

(i) If liquidated damages are provided by the Supplemental General Conditions, the following

provisions apply:

(1) If the Work is not substantially complete by the Time for Completion or Contract Completion Date, the Contractor shall owe to the Owner, not as a penalty but as Step One liquidated damages, the sum stated in the Supplemental General Conditions for Step One

DGS-30-054 CO-7 (04/15)

48

liquidated damages for each and every partial or total calendar day of delay in Substantial Completion.

(2) Once the Work is substantially complete, the accrual of Step One liquidated damages

shall cease and the Contractor shall have thirty (30) calendar days in which to achieve Final Completion of the Work.

(3) If Final Completion of the Work is not achieved on or before the thirtieth (30th) calendar

day after Substantial Completion, and if the Owner has not granted any extension of time, the Contractor shall owe to the Owner, not as a penalty but as Step Two liquidated damages, the sum stated in the Supplemental General Conditions as Step Two liquidated damages for each and every partial or total calendar day of delay in Final Completion.

(j) The Contractor waives any and all defenses as to the validity of any liquidated damage provisions

in the General Conditions or other Contract Documents, or of any liquidated damages assessed against the Contractor, on the grounds that such damages are void as penalties or are not reasonably related to actual damages.

44. INSPECTION FOR SUBSTANTIAL COMPLETION & FINAL COMPLETION

(a) The Contractor shall notify the Owner, in writing on the Certificate of Partial or Substantial Completion by the Contractor (Form CO-13.2a), of the date when the Work or designated portion thereof, will be, in his opinion, substantially complete and ready for inspection and testing to determine if it has reached Substantial Completion. The notice shall be given at least ten (10) days in advance of said date and shall be forwarded through the Architect/Engineer, who will attach his written endorsement as to whether or not he concurs with the Contractor's statement that the Work will be ready for inspection and testing on the date given. The Architect/Engineer's endorsement is a convenience to the Owner only and shall not relieve the Contractor of his responsibility in the matter nor shall the Architect/Engineer's endorsement be deemed to be evidence that the Work was substantially complete and ready for inspection and testing. Inspection and testing shall take place at a time(s) mutually agreeable to the Contractor, Owner and Architect/Engineer.

The inspection shall include a demonstration by the Contractor that all equipment, systems and operable components of the project function properly and in accordance with the Contract Documents. The Contractor shall furnish access for the inspection and testing as provided in Section 21 of these General Conditions. The inspection and testing shall determine whether Substantial Completion has been accomplished and shall result in a written list of unfinished Work and Defective Work, commonly referred to as a "punch list", which must be finished and corrected to obtain Final Completion.

After successful completion of the testing and the Architect / Engineer determines that, in its opinion, the Work, either in whole or in part, is substantially complete, the Architect / Engineer shall notify the Owner, in writing on the Certificate of Partial or Substantial Completion by the Architect/Engineer (Form CO-13.1a), that the Work, or a specified portion thereof, is recommended to be declared substantially complete. The Owner shall notify the Contractor, in writing, of the date the Owner accepts the Work, or the specified portion thereof, as substantially complete or the Owner shall notify the Contractor of the deficiencies to be corrected or completed before such Work will be accepted as substantially complete.

(b) The Contractor shall notify the Owner, in writing on the Certificate of Completion by the Contractor (form CO-13.2), of the date when the Work has reached or will reach Final Completion and will be ready for final inspection and testing. The notice shall be given at least five (5) days in advance of said date and shall be forwarded through the Architect/Engineer, who will attach his endorsement as to whether or not he concurs in the Contractor's statement that the Work will be ready for inspection and testing on the date given. That inspection and any necessary testing shall be conducted in the same manner as the inspection for Substantial Completion. When the Work is

DGS-30-054 CO-7 (04/15)

49

finally and totally complete, including the elimination of all defects, the Work shall be finally accepted by the Owner and Final Payment shall be made in accordance with Section 36 of these General Conditions.

(c) The Architect/Engineer shall conduct the inspections. The Owner may elect to have other persons of its choosing also participate in the inspections. If one or more Substantial or Final Completion re-inspections are required, the Contractor shall reimburse the Owner for all costs of re-inspection or, at the Owner's option, the costs may be deducted from payments due to the Contractor.

(d) A representative of the State Fire Marshal's Office will either be present at the Substantial and Final Completion inspections or otherwise inspect the completed Work and advise the Owner whether the Work meets the fire safety requirements of the applicable building code.

(e) Approval of Work at or as a result of any inspection required herein shall not release the

Contractor or his surety from responsibility for complying with the Contract. 45. GUARANTEE OF WORK

(a) Except as otherwise specified, all Work shall be, and is hereby, guaranteed by the Contractor against defects resulting from the use of materials, equipment or workmanship, which are defective, inferior, or not in accordance with the terms of the Contract, for one (1) year from the date of Final Completion of the entire Project by the Owner. Equipment and facilities which have seasonal limitations on their operation (e.g. heating or air conditioning units) shall be guaranteed for one (1) full year from the date of seasonally appropriate tests and acceptance, in writing, by the Owner. Where the Owner agrees to take Beneficial Occupancy of a portion or phase of the Work which has been determined to be substantially complete before the entire Work is finally completed, the guarantees for the materials, equipment and workmanship in that portion or phase shall begin on the date that the Owner takes Beneficial Occupancy, unless otherwise specified in the Supplemental General Conditions, Special Conditions, or by separate agreement. At six (6) months and eleven (11) months after substantial completion, the Contractor shall meet with the Owner to review the status of and assign value to any unresolved warranty, guarantee, and punch list items.

(b) If, within any guarantee period, Work which is not in accordance with the Contract, Defective Work, or inferior material, equipment or workmanship is noted by the Owner or Architect/Engineer which requires or renders necessary repairs or changes in connection with the guaranteed Work, the Contractor shall, promptly upon receipt of notice from the Owner, such notice being given not later than two weeks after the guarantee period expires, and without expense to the Owner:

(1) Place in satisfactory condition in every particular all of such guaranteed Work and correct all defects, inferior materials, equipment or workmanship therein;

(2) Make good all damage to the structure or Site or equipment or contents thereof, which, in the opinion of the Owner or the Architect/Engineer, is the result of the use of materials, equipment or workmanship which are inferior, defective or not in accordance with the terms of the Contract; and

(3) Make good any Work or materials or the equipment and contents of structures and/or Site disturbance that results from fulfilling the provisions of this Section.

(c) In any case, when in fulfilling the requirements of the Contract and this guarantee or any other guaranty or warranty, the Contractor disturbs any work performed by a separate contractor, he shall restore such work to a condition satisfactory to the Architect/Engineer and Owner and guarantee such restored work to the same extent as if it was guaranteed under this Contract.

DGS-30-054 CO-7 (04/15)

50

(d) If the Contractor, after notice, fails to proceed promptly to comply with the terms of the guarantee as set forth in this Section, the Owner may have the defects or inferior materials, equipment or workmanship corrected and the Contractor and his surety shall be liable for all expense incurred.

(e) All special warranties and guarantees applicable to definite parts of the Work that may be stipulated in or required by the Contract Documents shall be subject to the terms of this Section during the first year of the life of such special warranty or guarantee.

(f) The guarantee of this Section shall be in addition to and not in lieu of all other warranties, express or implied, applicable to or arising from this Contract or by law.

(g) Nothing contained in this Section shall be construed to establish a period of limitation with respect to any other obligation which the Contractor might have under the Contract Documents, including liability for Defective Work under Section 30. This Section relates only to the specific obligation of the Contractor as set forth in this Section to correct the Work and does not limit the time within which his obligation to comply with the Contract Documents may be sought to be enforced, nor the time within which proceedings may be commenced to establish the Contractor's liability with respect to his other obligations under the Contract Documents.

(h) In the event the Work of the Contractor is to be modified by another contractor, either before or after the Final Inspection provided by Section 44 of the General Conditions, the first Contractor shall remain responsible in all respects under this Section's Guarantee of Work and under any other warranties or guarantees, express or implied, applicable to or arising from this Contract or by law. However, the Contractor shall not be responsible for any defects in material or workmanship introduced by the contractor modifying his Work. The first Contractor and the contractor making the modifications shall each be solely responsible for his respective work. The contractor modifying the earlier Work shall be responsible for any damage to or defect introduced into the Work by his modification. If the first contractor claims that a subsequent contractor has introduced defects of materials and/or workmanship into his Work, it shall be the burden of the contractor making the claim to demonstrate clearly the nature and extent of such introduced defects and the other contractor's responsibility for those defects. Any contractor modifying the work of another shall have the same burden if he asserts that defects in his work were caused by the contractor whose work he is modifying.

(i) The Contractor shall indemnify and hold harmless the Commonwealth of Virginia, the Owner and the Owner’s consultants, representatives, agents and employees from and against any and all claims, causes of action, losses, costs, expenses or damages, including but not limited to attorney's fees, of any kind or nature whatsoever, arising from or relating to any bodily injury, including sickness, disease or death, or any property damage, that result from or arise out of the work performed by the Contractor, or by or in consequence of any neglect in safeguarding the Work, through the use of unacceptable materials in the Work, or resulting from any act, omission, negligence, or misconduct of the Contractor, any of his subcontractors, anyone directly or indirectly employed by them or anyone for whose acts they may be liable. The Owner may retain as much of the moneys due the Contractor under the Contract as the Owner considers necessary to ensure that a fund will be available to pay a settlement or judgment of such suits, actions, or claims. If insufficient monies are or will become due, the Contractor’s surety and/or insurers will not be released from liability until all such claims and actions have been settled and suitable evidence to that effect has been furnished the Owner.

46. ASSIGNMENTS

Neither party to the Contract shall assign the Contract in whole or any part without the written consent of the other, nor shall the Contractor assign any moneys due or to become due to him hereunder, without the prior written consent of the Owner. Consent to assignment shall not be unreasonably withheld. No assignment shall relieve any party from its obligations under the Contract.

DGS-30-054 CO-7 (04/15)

51

47. CONTRACTUAL DISPUTES (§ 2.2-4363, Code of Virginia) (a) Contractual claims, whether for money or for other relief, shall be submitted, in writing, no later than

sixty (60) days after Final Payment; however, written notice of the Contractor's intention to file such claim must be given within fourteen (14) days of the time of the occurrence or beginning of the Work upon which the claim is based. Such notice shall state that it is a “notice of intent to file a claim” and include a written statement describing the act or omission of the Owner or its agents that allegedly caused or may cause damage to the Contractor and the nature of the claimed damage. The submission of a timely notice is a prerequisite to recovery under this Section. Failure to submit such notice of intent within the time and in the manner required shall be a conclusive waiver of the claim by the Contractor. Oral notice, the Owner’s actual knowledge, or a written notice given after the expiration of fourteen (14) days of time of the occurrence or beginning of the Work upon which the claim is based, shall not be sufficient to satisfy the requirements of this Section. Although the Contractor may be required to submit certain classes of claims prior to Final Payment, and the Contractor is not prevented from submitting claims during the pendency of the Work, the Owner shall not be obligated to render a final written decision on any claim until after Final Payment. All claims shall state that they are “claims” pursuant to this Section, be submitted along with all practically available supporting evidence and documentation and the certification required by Subsection 47(f), and request a final decision. Certificates for payment, applications for payment, vouchers, invoices and similar requests for payment submitted for work done by the Contractor in accordance with the expected contract performance are routine submissions and shall not be considered claims under this Section. Proposed or requested change orders, demands for money compensation or other relief, and correspondence and e-mails to the Owner or its representatives, which do not strictly comply with the requirements of this Section, shall not be considered claims under this Section.

(b) No written decision denying a claim or addressing issues related to the claim shall be considered a

denial pursuant to this Section unless the written decision makes express reference to this Section and is signed by the Agency head or his designee. The Contractor may not institute legal action prior to receipt of the Owner's final written decision on the claim unless the Owner fails to render such a decision within ninety (90) days of submission of the claim, at which time the claim shall be deemed denied.

(c) The decision of the agency head or other signatory on the Contract shall be final and conclusive unless the Contractor within six (6) months of the date of the final decision on a claim, initiates legal action as provided in § 2.2-4364 of the Code of Virginia. Failure of the Owner to render a decision within 90 days shall not result in the Contractor being awarded the relief claimed nor shall it result in any other relief or penalty. The sole result of the Owner's failure to render a decision within 90 days shall be the Contractor's right to immediately institute legal action. No administrative appeals procedure pursuant to § 2.2-4365 of the Code of Virginia has been established for contractual claims under this Contract.

(d) Pursuant to § 2.2-4366, Alternative Dispute Resolution, of the Code of Virginia, the Owner may enter into an agreement with the Contractor to submit disputes arising from the performance of this Contract to arbitration and utilize mediation and other alternative dispute resolution procedures. However, such procedures entered into by the Owner, the Commonwealth, or any department, institution, division, commission, board or bureau thereof, shall be non-binding and subject to § 2.2-514, as applicable.

(e) In the event that a dispute, claim or controversy between the Owner and the Contractor arises regarding the requirements of the Contract, the performance of the Work, payment due the Contractor, the terms of any Change Order, or otherwise, the Contractor shall not stop, suspend or delay the Work or any part of the Work to be performed under the Contract, or under any Change Order, or as ordered by the Owner. The Contractor shall continue to diligently prosecute the Work to completion, including work required in any Change Order or as directed by the Owner.

DGS-30-054 CO-7 (04/15)

52

(f) Along with a claim submitted under this Section, the Contractor shall submit a Claim Certification Form (DGS-30-234) certifying that the claim is a true and accurate representation of the claim. Claims submitted without the Claim Certification Form shall not constitute a proper claim and, if not submitted with the certification within the time required, shall be deemed to be waived.

(g) The remedies provided in these General Conditions, including costs, expenses, damages or extensions of time, shall be the Contractor’s sole remedies for the acts, omissions or breaches of the Owner, which shall survive termination or breach of the Contract.

48. ASBESTOS

(a) This subsection applies to projects involving existing buildings where asbestos abatement is not a part of the Work, when the scope of the project has been reviewed and a comprehensive survey conducted by an individual licensed by the Virginia Department of Professional and Occupational Regulation to conduct building inspections for asbestos containing materials in buildings, and where the Owner has attempted to remove or encapsulate all asbestos containing material that may become friable or damaged during this Project.

Prior to commencement of Work, the results of the comprehensive survey or any other asbestos survey shall be made available to the Contractor, who shall be responsible for performing his Work so as not to disturb any remaining asbestos, encapsulated or otherwise, identified in such survey or surveys.

If the Contractor discovers or inadvertently disturbs any material that he knows, should have known or has reason to believe, may contain asbestos that has not been previously identified, was overlooked during the removal, was deemed not to be friable or was encapsulated, the Contractor shall stop Work in the area containing or suspected to contain the asbestos, secure the area, and notify the Owner and the Architect/Engineer immediately by telephone or in person with written notice as soon as possible. The Owner will have the suspect material sampled.

If the sample is positive and must be disturbed in the course of the Work, the Owner shall have the material repaired or removed and shall pay for the bulk sample analysis.

Except as provided in § 11-4.1 of the Code of Virginia, if the material disturbed is not within the Contractor's authorized Work and/or Work area or under this Contract, the Contractor shall pay for all associated sampling and abatement costs.

(b) If asbestos abatement is included as a part of the Work, the Contractor shall assure that the asbestos abatement work is accomplished by those duly licensed as described in Section 3 of these General Conditions and in accordance with the specific requirements of the Contract and all applicable laws and regulations.

(c) If asbestos abatement is included as part of the Work, the licensed asbestos Subcontractor shall obtain the insurance required under Section 11 (e) of these General Conditions.

49. TRAINING, OPERATION AND MAINTENANCE OF EQUIPMENT

(a) As a part of the Work, the Contractor in conjunction with his Subcontractors and Suppliers shall provide the Owner's operations and maintenance personnel with adequate instruction and training in the proper operation and maintenance of any equipment, systems, and related controls provided or altered in the Work. The training requirements may be further defined in the specifications.

(b) The Contractor shall provide the Owner with a minimum of two (2) copies of operating, maintenance and parts manuals for all equipment and systems provided in the Work. Further specific requirements may be indicated in the specifications.

DGS-30-054 CO-7 (04/15)

53

50. PROJECT MEETINGS

(a) The intention of this Section is that the Contractor, the Owner and the A/E have timely exchange of information and cooperate to accomplish the Work as required by the Contract Documents. The Contractor is responsible for managing the Work, obtaining approvals and requesting clarifications on a timely, reasonable basis. The Owner and its A/E are responsible for making a reasonable effort to provide timely responses to the Contractor.

(b) Preconstruction Meeting:

Prior to the start of construction and no later than 15 calendar days after the Notice to Proceed, a "Preconstruction" meeting shall be held with attendees to include the Owner's Project Manager and Project Inspector, the Architect/Engineer's project manager and representatives of each design discipline involved in the Project, the Regional Fire Marshal, the Contractor's project manager and superintendent (and scheduler, if Contractor desires), and representatives of the Contractor's major Subcontractors. The purpose of the meeting is to clarify and discuss the specifics related to, but not limited to, the following: (1) Persons involved from each entity and their chain of authority including the names of

persons authorized to sign Change Orders and any limits to their authority. Name of Contractor’s on-site certified Responsible Land Disturber.

(2) Names, addresses, telephone numbers and FAX numbers to be used for Requests for Information (RFI), Requests for Clarification (RFC), Requests for Proposals (RFP), shop drawings, Submittals, and notices.

(3) Contractor's proposed construction schedule and Owner's sequencing requirements, if any.

(4) Schedule of Values and Certificate for Payment (Form CO-12) requirements and procedures.

(5) Procedures for shop drawings, product data and Submittals.

(6) Procedures for handling Field Orders and Change Order Form CO-11.

(7) Procedures for Contractor's request for time extension, if any.

(8) Construction Site requirements, procedures and clarifications to include: - Manner of conducting the Work - Site specialties such as dust and erosion control, stormwater management, project

signs, clean up and housekeeping, temporary facilities, utilities, security, and traffic - Safety - Layout of the Work - Quality control, testing, inspections, and notices required - Site visits by the A/E and others - Owner's Project Inspector duties - Running Punch List - As-Built Drawings

(9) Procedures and documentation of differing or unforeseen Site conditions

(10) Monthly Pay Meeting

(11) Assignment of responsibility for generation of meeting minutes of all project meetings.

(12) Project Close-Out requirements and procedures

(13) Project records

(c) Monthly Pay Meeting:

DGS-30-054 CO-7 (04/15)

54

Section 36 establishes the requirement for a monthly pay meeting which will usually be held at or near the Site. In addition to Owner, A/E and Contractor representatives, the following representatives, at a minimum, should be available to attend portions of the meeting, as applicable or necessary:

- Owner's Project Inspector - Contractor's project superintendent - A/E representative of each discipline where Work was performed for the current pay

request or where Work is projected to be performed in the coming month. - A representative of each subcontractor who performed work included in the current

pay request. - A representative of each subcontractor who is projected to perform work in the

coming month.

The following topics should be included, as a minimum, in the monthly pay meeting:

(1) Observations of status, quality and workmanship of Work in progress (2) Validation of the Schedule of Values and Certificate for payment (3) Conformance with proposed construction schedule (4) Outstanding Requests for Information, Requests for Clarification and Requests for

Proposal (5) Submittals with action pending (6) Status of pending Change Orders (7) Status of Running Punch List items (8) Work proposed for coming pay period (9) Discussions of any problems or potential problems which need attention

(d) Other Meetings: Requirements for other meetings, such as progress meetings, coordination meetings, pre-installation meetings and/or partnering meetings, may be included in the Contract Documents.

51. SMALL BUSINESS PROCUREMENT PLAN

The Owner has developed small business utilization requirements for increasing procurement from small businesses in its construction program. The Owner’s small business requirements may, at the Owner’s option, be included in the contract documents for use by the Contractor in developing its plan for involving small businesses through subcontracting, and through the purchasing of goods, materials, supplies and services in the Contractor’s construction program. The Owner’s plan provides requirements for the Contractor in developing a plan, for submitting its plan and for reporting its achievements in meeting the requirements established for the Contract.

If the Contractor is not a DSBSD certified small business, and the Contractor entered a small business participation percentage on the Bid Form, the Contractor shall, as soon as practicable after the posting of the Notice of Intent to Award but not later than 30 days after the effective date of the contract, provide a list of Subcontractors that are proposed to perform the work, including small business Subcontractors, vendors and suppliers showing their DSBSD certification numbers where applicable. Upon receipt of the list, the Owner may, based on the Agency small business procurement plan, require the Contractor to provide additional information on work that has been bid by small business Contractors, and areas in which the scope of work may be reduced in size to increase the pool of potential small business Contractors. Selection of particular Subcontractors for a certain part of the work shall be made in accord with Section 9, Subcontracts of the General Conditions.

* * * E N D O F G E N E R A L C O N D I T I O N S * * *

DGS-30- 090 CO-10.2 (Rev 12/07) Page 1 of 2

COMMONWEALTH OF VIRGINIA STANDARD BID BOND

KNOW ALL MEN BY THESE PRESENTS: That , the Contractor (“Principal”) whose

principal place of business is located at and (“Surety”) whose address for delivery

of ‘Notices’ is located at are held and firmly bound unto the Commonwealth of Virginia,

, the Owner (“Obligee”) in the amount of five percent (5%) of the Amount (Total Base Bid

plus all Additive Bid Items) Bid by Principal, for the payment whereof, Principal and Surety

bind themselves, their heirs, executors, administrators, successors and assigns, jointly and

severally, firmly by these presents.

WHEREAS, the Principal has submitted a bid for

NOW, THEREFORE, the conditions of this obligation are as follows. This Bid Bond shall guarantee that the Principal will not withdraw his bid during the period of thirty (30) days following the opening of bids; that if his bid is accepted, Principal will enter into a formal contract with the Owner in accordance with the Contract Between Owner and Contractor, Form CO-9, included as a part of the Invitation for Bids (IFB Documents); that Principal will submit a properly executed and authorized Standard Performance Bond and Standard Labor and Material Payment Bond on the forms included in the IFB documents; and that in the event of the withdrawal of said bid within said period, or failure to enter into said contract and give said bonds within ten (10) days after Principal has received notice of acceptance of his bid, Principal and Surety shall be jointly and severally liable to the Owner for the difference between the amount specified in said bid and such larger amount for which the Owner may contract with another party to perform the work covered by said bid, up to the amount of the bid guarantee. This amount represents the damage to the Owner of account of the default of the bidder in any particular thereof. The Surety represents to the Principal and to the Obligee that it is legally authorized to do business in the Commonwealth of Virginia.

DGS-30- 090 CO-10.2 (Rev 12/07) Page 2 of 2 Signed and sealed this day of Contractor / Principal (SEAL) _________________________________________ By:_________________________________ Witness Typed Name: Title: Surety (SEAL) By:_________________________________ Attorney-in-Fact Typed Name:

AFFIDAVIT AND ACKNOWLEDGEMENT OF ATTORNEY-IN-FACT COMMONWEALTH OF VIRGINIA (or alternatively, Commonwealth or State of ) CITY of I, the undersigned notary public, do certify that , whose name is signed to the foregoing bid bond in the amount of five percent (5%) of the Total Bid Amount and which names the Commonwealth of Virginia, , as Obligee, personally appeared before me today in the above jurisdiction and made oath that he/she is the attorney-in-fact of , a corporation which is the Surety in the foregoing bond, that he/she is duly authorized to execute on the above Surety’s behalf the foregoing bond pursuant to the Power of Attorney noted above and attached hereto, and on behalf of the surety, he/she acknowledged the foregoing bond before me as the above Surety’s act and deed. She/he has further certified that her/his Power of Attorney has not been revoked. [Complete if Power is recorded: Clerk’s Office: ; Deed Book/Page No. or Instrument No.: .] Given under my hand this day of . _________________________________ Notary Public (SEAL) My name (printed) is: My registration number is: My commission expires:

Division 1: General Requirements

www.dewberry.com

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. General Requirements DEI# 50076991 01 00 00 - 1

SECTION 01 00 00 GENERAL REQUIREMENTS

1.1 RELATED DOCUMENTS

A. This Division 1 shall be used with the General Conditions (HECO-7/CO-7; HECO-7CM; and HECO-7DB/CO-7DB), Supplemental General Conditions, and the other Contract Documents. The term "University" is synonymous with "Owner."

1.2 UNIVERSITY'S REPRESENTATIVES

A. The University may assign a Construction Administration Manager (CAM). The duties of the CAM are: to assist the University's Project Manager (PM) as the University’s on-site representative for the construction phase; to coordinate all construction phase Consultants; to coordinate other Consultants, the A/E, and the Construction Manager (CM) / General Contractor (GC) communications; to expedite resolution of all conflicts; to perform additional quality assurance oversight (such as inspection, verification, acceptance, rejection) and other administrative oversight. The CAM shall be provided copies of all written decisions and notices to the CM/GC and information and notices from the CM/GC. All activities not specifically required to be performed by the A/E may be performed by the CAM or by the University’s other Consultants.

B. The University may also remove/reassign from the A/E to any selected Consultants certain

inspection, verification, acceptance, rejection, and administrative duties and authority. The University shall provide the CM/GC and the A/E information in writing defining the limits of the selected Consultants’ authority.

1.3 GOVERNING AUTHORITY AND APPLICABILITY OF PROVISIONS

A. The CM/GC shall abide by all University regulations and amendments and all other applicable laws and regulations of the Commonwealth, including those that may be issued during the Contract. This governing authority applies to all employees of the CM/GC and all Trade/Subcontractors. In particular, regulations pertaining to sexual harassment, drug and alcohol use, abusive and offensive language, and smoking should be noted.

1.4 RESUMES FOR CM/GC’S PERSONNEL

A. The CM/GC shall submit to the University, at least one week prior to the Preconstruction Meeting, a resume for each principal staff member who will work on the project, including PM, Superintendent, Foreman, and Quality Control Representative.

B. Resumes shall include, at a minimum, educational background, length of time with the company,

and past work experience, with an outline of responsible positions held. C. The University reserves the right to interview and to reject any staff member for specific reasons

and request new resume submissions. 1.5 PARTNERING

A. Not Applicable 1.6 SWAM FIRM UTILIZATION

A. It is the policy of the University to contribute to the establishment, preservation, and strengthening of SWaM firms and to encourage their participation in University procurement activities. Towards that end, the University encourages CMs/GCs to provide for the participation of SWaM firms through partnerships, joint ventures, subcontracts, and other contractual opportunities. The

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. General Requirements DEI# 50076991 01 00 00 - 2

University has a SWaM firm overall participation goal of 43% for procurement opportunities. Where it is practicable for any portion of awarded contracts to be subcontracted to other firms, the University encourages the use of SWaM firms.

B. Names of SWaM firms currently registered with and certified by the Virginia Department of Small

Business and Supplier Diversity (SBSD) and desiring to work at the University may be obtained from the University Department of Procurement and Supplier Diversity Services. See http://www.procurement.virginia.edu/pagediversity for additional information.

C. If the total amount of a contract with the University exceeds $100,000, Contractors shall complete

and submit quarterly reports, on forms provided by the Department of Procurement and Supplier Diversity Services in accordance with the University’s SWaM plan, to document Trade/Subcontractor and Supplier expenditures to SWaM firms in connection with the project. The successful firm shall provide the UVA SWaM Contract Administrator with the name of the responsible person within their organization who will be the SWaM contact and who will be responsible for reporting verifiable SWaM expenditures resulting from this contract.

1.7 LEED CERTIFICATION

A. LEED certification requirements do not apply to this contract. 1.8 SECURITY AND PERSONNEL IDENTIFICATION

A. Contractors will not be required to provide identification badges to personnel onsite. B. Contractors shall be required to wear high visibility clothing or construction vests which will

identify the name of the Construction Firm performing the work. 1.9 BUILDING INFORMATION MODELING (BIM)

A. Building Information Modeling is not required for this project. 1.10 INFECTIOUS CONTROL RISK ASSESSMENT

A. Infectious Control Requirements do not apply to projects outside the UVA Health System 1.11 RFI FORM AND LOG

A. CM/GC shall use the RFI form at the end of this section or an alternate form acceptable to the University. The form is intended to be completed electronically and emailed.

B. CM/GC shall carefully study and compare Contract Documents before proceeding with fabrication

and installation of Work and shall promptly advise the A/E of any error, inconsistency, omission, or apparent discrepancy discovered.

C. CM/GC shall allot time in construction scheduling for liaison with A/E for handling queries and

clarifications. D. The University reserves the right to require the CM/GC to reimburse the University for additional

fees from the A/E and A/E’s Consultants for performing review services for the CM/GC if A/E is able to respond to a RFI by making specific reference to a Drawing Sheet or Specification Section.

E. CM/GC shall maintain in the field office a copy of an RFI Log indicating current status of each

item.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. General Requirements DEI# 50076991 01 00 00 - 3

REQUEST FOR INFORMATION Date: RFI # To: From: Project Name: State Project Code #: PIMS #: Subject: Spec Section: Drawing # REQUEST: The above request has been researched and is not answered by the Contract documents. Name: Signature: Title: RESPONSE: Name: Signature: Title:

END OF SECTION 01 00 00

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Summary of Work DEI# 50076991 01 11 00 - 1

SECTION 01 11 00 SUMMARY OF WORK

1.1 WORK COVERED UNDER THE CONTRACT DOCUMENTS

A. Project Name: Tunnel C Structural Rehabilitation B. Owner: The Commonwealth of Virginia and The Rector and Visitors of the University of Virginia

(collectively referred to as the “University”) C. A/E of Record: Dewberry Engineers Inc. D. The Work consists of the following, but is not limited to, tunnel rehabilitation of approximately 60

LF of existing 6’x7’ walk-through utility tunnel. Tunnel rehabilitation will include tunnel encasement through the use of cast-in place-concrete placed outside of existing CMU walls and a new tunnel top slab. Sheet membrane waterproofing will be used where tunnel slab is buried and a concrete admixture will be used where tunnel slab doubles as a sidewalk. See project manual and drawings for all work included in the project.

1.2 UNIVERSITY FURNISHED PRODUCTS

A. The University will furnish the products listed below. The Work for this project includes supplying the labor, material, coordination, and supervision to install these products as per the Contract Documents and General Conditions.

1.3 ASSIGNED WORK

A. Not applicable 1.4 WORK SEQUENCE

A. CM/GC shall construct Work in stages to accommodate University's occupancy requirements during the construction period. Coordinate construction schedule and operations with the University.

B. Project Duration: Contractor may begin work on June 12, 2017 and shall complete work by August 18, 2017.

END OF SECTION 01 11 00

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Work Restrictions DEI# 50076991 01 14 00 - 1

SECTION 01 14 00 WORK RESTRICTIONS

1.1 CONCURRENT UNIVERSITY OCCUPANCY

A. Partial Occupancy

1. The University intends to occupy all buildings adjacent to this project.

2. The University intends to occupy portions of the site to provide pedestrian access to all

buildings on Grounds. The limits of construction shall not obstruct access to or egress from any buildings. See project documents for more specific information.

3. The University intends to maintain access to Newcomb Road and Cabell Drive throughout

construction.

4. Parking impacts will be limited to those directly impacted by the construction. All parking lots shall remain open through construction with suitable vehicular and bus access.

5. See §1.3D for smoking restrictions.

B. Continued Occupancy – Adjacent Areas 1. Certain areas will be occupied during entire construction period for conduct of normal

operations. 2. CM/GC shall cooperate with University in scheduling operations to minimize conflict and to

permit continuous usage. Perform Work so as not to interfere with operations of occupied areas. Ingress and egress for patients, staff and support services must be continuously maintained.

3. The University intends to occupy the following areas throughout construction:

1. Clark Hall 2. Brown College 3. Minor Hall 4. Maury Hall 5. Westbound lane of McCormick Rd 6. Eastbound lane of McCormick Rd

1.2 CM/GC USE OF SITE AND PREMISES

A. Access to Site: No restrictions.

B. Emergency Egress/Access: Contractor shall maintain all building emergency exits during construction. Contractor shall maintain all fire lanes

C. Construction Operations: Limited to areas shown on drawings.

D. Time Restrictions for Performing Work: 8am – 6pm, Monday through Friday. Work outside these times shall not be construed as constituting additional cost to the University. Work hours in the vicinity of occupied housing areas are restricted to 8am – 6pm all days. No deliveries shall occur between 7 AM - 8:30 AM and 4 PM - 6:00PM Monday through Friday.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Work Restrictions DEI# 50076991 01 14 00 - 2

E. Night Work Hours: Defined as between 6 PM and 8 AM, Monday through Friday. CM/GC to request permission in writing at least five (5) days in advance for Work at these times. Work at these times must be authorized in advance in writing before proceeding. Work executed during these times shall not be construed as “overtime” and shall not result in additional cost to University.

F. Weekend Work Hours: Defined as between 6 PM Friday and 8 AM Monday. CM/GC request

permission in writing at least five (5) days in advance for Work at these times. Work at these times must be authorized in advance in writing before proceeding. Work executed during these times shall not be construed as “overtime” and shall not result in additional cost to University.

G. Contractor shall coordinate work and timing with University and current building occupants. H. Loading dock access: Maintain access to all loading docks and adjacent construction laydown

areas. I. Staging Areas: Limited to the locations as shown on the drawings.

1.3 OPERATIONS OUTSIDE CONSTRUCTION LIMITS

A. Use of certain passageways and other areas, outside of defined limits of operation, will be granted on an as needed basis. Requests must be made in writing at least seven (7) days in advance.

B. The CM/GC shall comply with designated travel paths, staging areas, dumpster locations, and

other restricted items indicated on Drawings. C. University dining facilities will not be available for general CM/GC use. D. Occupied University buildings and grounds, including the construction limits, are a non-smoking

environment. Smoking is allowed only in designated areas. For Health System projects, see http://www.healthsystem.virginia.edu/internet/environment/media/SmokingMap.pdf for prohibited smoking areas.

1.4 WORK SITE PROTECTION

A. CM/GC shall prevent traffic on lawn and landscaped areas unless indicated on the plans. B. Storage of equipment or materials shall not be allowed within the driplines of existing trees

schedule to remain. C. Contractor shall properly protect the work zone through the use of approved traffic control

measures. At the end of each work day, contractor shall cover excavation with road plates to restore two-way traffic after hours. Excavations that will remain exposed (ie. manholes) overnight shall be protect with concrete vehicular barriers and 8’ high chainlink fencing.

1.5 HOT WORKS OPERATIONS

A. The CM/GC shall follow all Virginia Occupational Safety and Health (VOSH) standards/regulations on Hot Works operations and is subject to VOSH inspections. CM/GCs certify that they have a Hot Works program in place with proper oversight that includes recognition of the risk of after-hours ignition from Hot Work and the requirement for a fire watch.

1.6 SAFETY PROCEDURES

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Work Restrictions DEI# 50076991 01 14 00 - 3

A. Contractor is required to maintain a safe working environment and have a safety plan in place for the protection of all persons within the limits of construction.

B. Use of FP&C Incident Notification Procedures & UVA Department of Risk Management

Incident Report Form is required on all projects. See links below: FP&C Cover Sheet for Incident Report UVA Risk Management Incident Report Form

1.7 ELECTRONIC DEVICES

A. Not applicable 1.8 BLASTING

A. Blasting is strictly prohibited on University Grounds. Exceptions require the approval of the Chief Facilities Officer.

1.9 STORMWATER PERMIT NOTIFICATION

A. Site work may not proceed any sooner than two (2) days after the CM/GC has filed with the Department of Environmental Quality (DEQ): 1.) A Virginia Stormwater Management Program (VSMP) General Permit for Stormwater

Discharges from Construction Activities (VAR10) Registration Statement http://www.deq.virginia.gov/Portals/0/DEQ/Water/Publications/CGPRegistrationStatement2014.pdf and

2.) A Permit Application Fee Form http://www.deq.virginia.gov/Portals/0/DEQ/Water/Publications/CGPPermitFeeForm2014.pdf See the instructions attached to each form for completion guidance.

B. For sites of 1 acre in size or greater, land disturbing operations may not proceed until the CM/GC

submits a complete and accurate registration statement and receives acceptance of the registration from the Department of Environmental Quality (DEQ). The registration statement for coverage under the General VPDES Permit for Discharges of Stormwater from Construction Activities (VAR10) is available at http://www.deq.virginia.gov/Portals/0/DEQ/Water/Publications/CGPRegistrationStatement2014.pdf.

The permit application fee form is available at http://www.deq.virginia.gov/Portals/0/DEQ/Water/Publications/CGPPermitFeeForm2014.pdf. See the instructions attached to each form for completion guidance.

C. UVA must also have received approval of any required erosion and sediment control (E&SC)

and/or stormwater management plans before land disturbing operations can begin. 1.10 RAILROAD RIGHT-OF-WAYS

A. All Contractors working for the University performing Work within and adjacent to railroad tracks owned by Norfolk Southern (NS) Railroad shall enter into an Agreement with NS governing the Contractor’s duties and liabilities as to such Work.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Work Restrictions DEI# 50076991 01 14 00 - 4

1.11 CONSTRUCTION EQUIPMENT EXHAUST A. Contractor may be required to utilize equipment with exhaust scrubbers in/around building HVAC

intakes or other sensitive areas (ie. Hospital Patient Care, etc.)

B. Idling of equipment or vehicles is not permitted.

END OF SECTION 01 14 00

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Project Utility Sources DEI# 50076991 01 18 00 - 1

SECTION 01 18 00

PROJECT UTILITY SOURCES 1.1 IDENTITY OF UTILITY COMPANIES

Identity of utility companies providing services in the vicinity of the project area: - City of Charlottesville Gas - University of Virginia Utilities

END OF SECTION 01 18 00

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Payment Procedures DEI# 50076991 01 29 00 - 1

SECTION 01 29 00 PAYMENT PROCEDURES

1.1 INVOICING

A. Unless otherwise directed by the University representative: 1. The University is committed to processing your application for payment request as

expeditiously as possible. To assist us in that effort, it is important that Contractors submit their monthly billing in the proper manner and in the correct form.

2. The University’s project team, Project Manager and Construction Administration Manager, are responsible for the processing of the Contractor’s invoices. They will provide detailed steps to assure that your invoices are processed in a timely manner. These will be discussed at your Project Preconstruction Meetings.

3. Invoice review process (Monthly Pay meeting prior to official submission):

The University’s project team along w/ appropriate representatives from the contractor team, will review a draft of the schedule of values. At the conclusion of this review/discussion, a final schedule of values will be developed/agreed upon.

4. At the conclusion of the invoice review process and as instructed by the project team, the

Contractor is to access the University’s e-Builder system and: • Enter their final agreed upon schedule of values via the e-Builder invoice process • Attach a copy of the schedule of values (excel spreadsheet)

5. The latest revised Schedule of Values form can be found here:

• http://www.fm.virginia.edu/fpc/HECOManual/HECOMForms/UVAHECO-12.xlsm

6. No other method of invoice submission, unless otherwise directed, is acceptable.

7. By utilizing and approving the appropriate steps in the e-Builder invoice process, all required signatures (contractor’s and University representatives), along with A/E’s certification signature are now electronic. (This replaces the previously required original wet signatures.)

8. Incorrect and/or nonconforming Schedule of Values may be returned for correction, thus

delaying payment.

B. Include all of the following information on the Schedule of Values in the section provided:

• Project Title * • UVA Purchase Order # * • UVA Work Order # *

* This information is located on your formal Notice to Proceed (NTP) and may also be obtained from the Contract Administrator, George Cullen, (434) 982-4620 or Facilities Management Fiscal Technician Senior, Christine Eppard, (434) 982-5856.

C. Vendors can now access invoice payment as far back as 90 days by using the Tax Payer Identification # on the Vendor Invoice/Payment Status Lookup page. https://www.procurement.virginia.edu/pagevendorinvlookup. Additional questions regarding the status of your payment may be directed to Christine Eppard ([email protected]) or (434) 982-5856.

1.2 CHANGES

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Payment Procedures DEI# 50076991 01 29 00 - 2

A. Contractor's itemized breakdown of quantities and prices used in computing a proposed change in contract price (HECO-11) shall be provided on forms HECO-GC-1, HECO-SC-1, and HECO-SS-1.

1.3 INVOICING FOR ASBESTOS REMOVAL

A. Not applicable. The University shall directly contract with asbestos abatement contractors as required by this project.

END OF SECTION 01 29 00

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Project Management and Coordination DEI# 50076991 01 31 00 - 1

SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION

1.1 PROGRESS MEETINGS

A. Scheduling: GC is required to schedule Progress Meetings throughout progress of the Work at regular intervals, and at a minimum of two (2) per month. The monthly pay meeting, required by the General Conditions, may serve as a Progress Meeting. The GC is also required to coordinate scheduled meeting dates with the University and A/E.

B. Brief Progress Summary & Work Projection: GC is required to provide a brief summary, in

narrative form, of progress since the previous meeting and report on projected Work for a minimum of the next two (2) weeks.

C. Attendance Required: Project Superintendent, major Trade/Subcontractors, and Suppliers,

representatives of the University and the A/E, as appropriate to agenda topics for each meeting. D. Agenda: Review and correct or approve minutes of the previous Progress Meeting. Review

other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project that may include:

1. Schedule 2. Issues 3. Requests for Information 4. Requests for Proposal 5. Estimated Change Orders 6. Change Orders 7. Submittals 8. Applications for Payment 9. Safety, Security, and Conduct 10. University Coordination 11. Utility Outage Requests

E. A/E will record minutes and distribute copies to participants. 1.2 PRE-INSTALLATION MEETINGS

A. GC to schedule Pre-installation Meetings for all utility systems affected by the Project,. Such meetings should include the A/E, the Project Engineer for the discipline, the CAM, the Inspector, a University Facility Operator, any Commissioning Agent, the GC’s PM and Superintendent, the Mechanical Trade/Subcontractor’s PM and Superintendent, and a representative of the major Supplier/Manufacturer.

B. GC shall require attendance of parties directly affecting, or affected by, Work of the specific

section. C. GC to notify A/E and University at least four (4) working days in advance of meeting date. D. GC to prepare agenda and summary to facilitate review of:

1. All required submittal approvals. 2. Conditions of installation, preparation, and installation procedures. 3. Coordination with related Work.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Project Management and Coordination DEI# 50076991 01 31 00 - 2

4. All required tests and reports.

E. GC to record minutes and distribute copies within three (3) days after meeting to participants, with copies to those affected by decisions made.

1.3 PRECONSTRUCTION MEETINGS

A. Required by the General Conditions, this meeting will be scheduled by the University. The A/E will record minutes and distribute copies to the participants.

1.4 MONTHLY PAY MEETINGS

A. Required by the General Conditions, this meeting will be scheduled by the A/E. The A/E will record minutes and distribute copies to the participants.

END OF SECTION 01 31 00

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Submittal Procedures DEI# 50076991 01 33 00 - 1

SECTION 01 33 00 SUBMITTAL PROCEDURES

1.1 DEFINITIONS

A. See HECOM Definitions §2.2. 1.2 SUBMITTAL FORM AND LOG

A. CM/GC shall use either the Submittal Register at http://dgs.state.va.us/tabid/820/Default.aspx?udt_1673_param_detail=274 or one of its own making acceptable to the University.

B. CM/GC shall maintain in the field office a copy of the Submittal Log / Schedule indicating the

current status of each item. C. CM/GC shall allot time in the construction scheduling for liaison with the A/E for review of

Submittals. Except for special Submittals, such as those with design calculations and/or detailed Shop Drawings, Submittals will be reviewed in an average time of 7 working days. Submittal items that are inter-related should be submitted at the same time.

D. Schedule finish sample Submittals for approval of color, texture, graining, or other finish at least

30 days before purchase, assembly, or fabrication. 1.3 SUBMITTALS, GENERAL

A. A/E will return Submittals without processing if they do not contain the CM/GC’s stamp, if they are not initialed or signed by an authorized person, if they are not dated, or if it becomes evident that they have not been properly reviewed. Resultant delays are the responsibility of the CM/GC.

B. CM/GC shall bind Submittals in a manner suitable for 8-1/2 x 11-inch file folder storage, except

where doing so is not workable. C. CM/GC shall transmit Submittals with all transportation charges prepaid. D. All submittals, shop drawings, and RFI’s shall be made electronically. CM/GC will be required to

use the University’s Sharepoint (or e-Builder) site for the distribution of electronic submittals, shop drawings, RFI’s, etc.

E. All text and figures included in the submittal shall be legible. A/E will return submittals without

processing if materials are illegible. Resultant delays are the responsibility of the CM/GC. Original electronic documents are preferred. Scans of printed material are not preferred.

F. If cutsheets contain multiple products, systems, components, sizes, etc. Contractor shall clearly indicate which product(s) is to be reviewed. Submission of general product literature is not sufficient.

1.4 SHOP DRAWINGS

A. CM/GC shall bind in complete sets and provide digital copies. Folding of prints is acceptable.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Submittal Procedures DEI# 50076991 01 33 00 - 2

B. CM/GC shall allot time in construction scheduling for liaison with A/E for review of Shop Drawings. Except for special Submittals, such as those with design calculations and/or detailed Shop Drawings, Submittals will be reviewed in an average time of 7 working days.

C. CM/GC shall present all drawings in a clear and consistent manner. Each drawing shall: contain

the project name and number; identify each element of the drawings by reference to sheet number and detail, schedule, or room number of the Contract Documents.

D. CM/GC shall show detail, materials, dimensions, thickness, methods of assembly, attachments,

relation to adjoining Work, and other pertinent data and information. E. CM/GC shall verify dimensions and field conditions and clearly indicate both. F. CM/GC shall not use Contract Drawings for Shop Drawings and shall provide original Shop

Drawings with changes from Contract Drawings clearly indicated. G. No item shall be marked as “By Others” or similarly.

1.5 PARTIAL SUBMITTALS

A. A/E will not review partial or incomplete Submittals. Complete Submittals for each item are required. Submittals will not be considered official until it is complete in every respect. Delays resulting from partial Submittals are the responsibility of the CM/GC.

1.6 RESUBMITTALS

A. The resubmittal procedure is the same as that specified for initial Submittals. Changes made since the previous Submittal are to be identified (highlighted or bubbled).

B. A/E will record time required to review resubmittals after original Submittal and first resubmittal.

University retains the right to require the CM/GC to reimburse University for additional fees from A/E and A/E's Consultants for reviewing Submittal more than two (2) times unless the processing results from approved Change Orders causing revisions to previously approved Submittals.

1.7 DISTRIBUTION

A. Duplicate and distribute reproductions of Shop Drawings, product data, samples, and other Submittals which bear A/E's stamp of approval to the Project record documents file, the Project site file, Trade/Subcontractors, Suppliers, other affected Contractors, and other entities requiring the information.

B. Provide each testing and inspection agency one set of approved Submittals for their exclusive

use in providing specified quality control testing and inspection services. See §01400. C. See HECOM §3.11 for University submittal requirements.

1.8 SUBMITTAL FORM

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Submittal Procedures DEI# 50076991 01 33 00 - 3

SUBMITTAL FORM Submit separate form for each product – see General Conditions §24

Project Name: Project Code:

TRANSMITTAL To: CM/GC Date: Submittal # A From: Trade/Subcontractor By: Resubmission

Quantity Reference #

Title / Description / Manufacturer

Spec Section Title, Paragraph / Drawing Detail Reference

Submitted for Review & Approval Resubmitted for Review & Approval Complies with Contract requirements Will be available to meet construction schedule A/E review time included in construction schedule Other remarks on above submission:

Substitution involved - substitution request attached

If substitution involved, submission includes full point by point comparative data or preliminary details

Items included in submission will be ordered immediately upon receipt of approval

TRANSMITTAL To: A/E - Attention Date Received by CM/GC:

B From: CM/GC Date Transmitted by CM/GC:

Reviewed, Coordinated, and Approved by CM/GC

Remarks on above submission: One copy retained by sender

TRANSMITTAL To: CM/GC Date Received: C From: A/E Other Signed Dated Returned:

Approved Approved as Noted Disapproved / Resubmit Not Subject to Review Submission Incomplete; Resubmit Received; No Action Required Full point by point comparative data

required to complete approval process

Provide File Copy with corrections

identified Reproducible copies

only returned

Remarks on above submission: One copy retained by sender

TRANSMITTAL To: Trade/Subcontractor Date Received:

D From: CM/GC Signed Dated Returned:

Copies University One copy retained by sen Remarks on above:

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Submittal Procedures DEI# 50076991 01 33 00 - 4

END OF SECTION 01 33 00

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Regulatory Requirements DEI# 50076991 01 41 00 - 1

SECTION 01 41 00 REGULATORY REQUIREMENTS

1.1 UTILITY EXCAVATION

A. All planned excavations on University property require a University Excavation Permit (see 1.1.D below.) The University's "Request for Excavation Permit” shall be completed and submitted by the CM/GC to the CAM and the Utilities Department within two (2) hours of contacting MISS UTILITY. The University’s "Request for Excavation Permit” notifies only the University of a planned excavation and does not result in notification of MISS UTILITY.

B. The University is a subscriber to the MISS UTILITY underground utility location and notification

system. In addition to University and MISS UTILITY requirements, the City of Charlottesville (434-971-3320) also requires that requests for excavation permits be submitted for City maintained streets or sidewalks. Any excavation of state roads requires notification and coordination with the Virginia Department of Transportation (VDOT). All planned excavations require notification of MISS UTILITY per state and federal regulations. It is the responsibility of the CM/GC to notify MISS UTILITY at 1-800-552-7001 of the planned excavation and at 1-800-552-3120 to obtain subsequent verification that utilities have been marked.

C. Excavation shall not proceed without a University Excavation Permit and the completion of the

above requirements. D. See next page for the Excavation Permit.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Regulatory Requirements DEI# 50076991 01 41 00 - 2

University of Virginia - Facilities Management - Utilities Distribution Divisions 575 Alderman Road, Charlottesville, VA 22903-2476 - Phone: 434-982-4654 - FAX: 434-982-5073

REQUEST FOR EXCAVATION PERMIT (Submit completed form to Utilities Department within two hours of notifying MISS UTILITY)

CONDITIONS OF REQUEST 1. This excavation permit is for University of Virginia property only. 2. Notify MISS UTILITY at 1-800-552-7001 of the planned excavation and at 1-800-552-3120 to obtain subsequent

verification that utilities have been marked. 3. Utility field locations are valid for 15 calendar days from date of notification. 4. This permit does not constitute project approval or acceptance, nor does it negate any requirement for project

management or review of specifications. Facilities Management project specifications may affect excavation requirements.

5. This excavation permit does not grant or confirm easement approval when required. Easement approval is required for all privately (non-University) owned cables. Contact Real Estate Management at 982-5841.

6. Trenching may occur no closer to trees than one foot for every one inch of truck diameter, measured at four feet above ground level (e.g. no digging closer then 10 feet from a tree of 10 inch diameter).

7. Trenches must be backfilled and tamped in 6-inch layers. All stone, sticks, and other debris larger then 1/2 inch shall be removed from top six inches of backfill.

8. Disturbed structures, ground turf, plants, and beds must be restored within 14 days of expiration of this permit, after which Facilities Management may undertake restoration at the expense of negligent party without prior notice.

9. Guidance on turf seed, plant replacement, exceptions, etc. is available from the Superintendent, Facilities Management Landscape Division, 982-4655, who shall inspect for and enforce compliance with these requirements.

10. Additional restrictions and exceptions:

Name of Requester Date Permit(s) needed From: To: Requester’s Organization Phone Fax Requester’s Full Address, Including Zip Code REQUIREMENTS 1. Detailed plans indicating location, depth, etc., of planned excavation must be attached. Plans must show all adjacent

buildings, streets, sidewalks, and landscape features affected, including trees, shrubs, etc. 2. Contractor has marked site of planned excavation at time of request with white paint. _______ Yes _______ No 3. Statement providing specific reason for excavation plus any other pertinent information: ________ UNIVERSITY OFFICIAL AUTHORIZING THIS ACTIVITY

Name/Signature Title Dept. Phone UVA Work Order Number Miss Utility Number During excavation of site if an unmarked line is encountered or utility line damaged, contractor must immediately contact Facilities Management Utilities Piping and Electrical Distribution at 982-4654 or 982-4641.

================================================================================================== This portion to be completed by Utilities Piping and Electrical Distribution Divisions - Request received in Utilities Department: Date/time: By whom: - Superintendent Landscape Division copied: Date/time: By whom: - ITC notified to locate utilities: Date/time: By whom: - Notice received that ITC field locations have been completed: (required within 40 hours of notification to ITC by Utilities) Date/time: By whom: - UVA utility field location complete: Date/time: By whom:

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Regulatory Requirements DEI# 50076991 01 41 00 - 3

END OF SECTION 01 41 00

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Quality Assurance and Control DEI# 50076991 01 43 00 - 1

SECTION 01 43 00 QUALITY ASSURANCE AND CONTROL

1.1 GENERAL

A. This section specifies administrative and procedural requirements for Quality Control (QC) services.

B. QC services include inspections and tests and related actions including reports performed by

independent agencies, governing authorities, and the CM/GC. They do not include Contract enforcement activities performed by the A/E.

C. Inspection and testing services are required to verify compliance with requirements specified or

indicated. These services do not relieve the CM/GC of responsibility for compliance with Contract Document requirements.

D. Requirements of this section relate to fabrication and installation procedures.

1. Specific QC requirements for individual construction activities are specified in the sections

that specify those activities. Those requirements, including inspections and tests, cover production of standard products as well as customized fabrication and installation procedures.

2. Inspections, tests, and related actions specified are not intended to limit the CM/GC’s QC

procedures that facilitate compliance with the Contract Document requirements. 3. Requirements for the CM/GC to provide QC services required by the A/E, University, or

authorities having jurisdiction are not limited by provisions of this section. 1.2 RESPONSIBILITIES

A. University testing and laboratory services: The University shall employ and pay for independent testing and laboratory services, as specified in individual Specification sections and as required under Chapter 17 - Structural Tests and Inspections of the current Virginia Uniform Statewide Building Code, and required by the other governing authorities, except where they are specifically indicated to be the CM/GC’s responsibility, or are provided by another identified entity.

B. CM/GC Responsibilities:

1. The CM/GC shall employ and pay an independent agency, to perform inspections, tests, and

similar QC services which are designated in the Specifications as a CM/GC requirement to provide.

2. Where the University has engaged a testing agency or other entity for testing and inspection

of a part of the Work and the CM/GC is also required to engage an entity for the same or related element, the CM/GC shall not employ the entity engaged by the University unless otherwise agreed in writing with the University.

3. Failure and Re-testing: Regardless of the original assignment of responsibility for inspection,

testing, or similar services, the CM/GC shall be responsible for re-testing where results of required inspections, tests, or similar services prove unsatisfactory and do not indicate compliance with Contract Document requirements. Removal and replacement Work necessitated by such noncompliance shall be at the CM/GC's expense. When inspections or tests cannot be performed after proper notification and at the fault of the CM/GC, rescheduling costs will be the CM/GC’s responsibility.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Quality Assurance and Control DEI# 50076991 01 43 00 - 2

4. Coordination: Regardless of the original assignment of responsibility for inspection, testing or similar services, the CM/GC shall coordinate, with each agency engaged to perform inspections, tests and similar services, the sequence of activities to accommodate required services with a minimum of delay. In addition the CM/GC shall coordinate with each agency’s activities to avoid the necessity of removing and replacing construction to accommodate inspections and tests. The CM/GC is responsible for:

a. Scheduling times for inspections, tests, taking samples and similar activities; b. Notifying the A/E and testing agency 48 hours in advance of operations requiring testing

services; and c. Providing incidental labor and facilities to facilitate inspections, tests, sample taking and

appropriate sample storage.

5. Protection and Repair: Regardless of the original assignment of responsibility for inspection, testing or similar services, repair and protection are the CM/GC’s responsibility. Upon completion of inspection, testing, sample-taking and similar services, repair damaged construction and restore substrates and finishes to eliminate deficiencies, including deficiencies in visual qualities of exposed finishes. Protect construction exposed by or for QC service activities, and protect repaired construction.

1.3 TEST AND INSPECTION CERTIFIED REPORTS

A. For CM/GC provided services, the CM/GC shall forward a certified written report from the independent agency of each inspection, test or similar service within one week of the test date and with four (4) copies; two (2) copies for the University and two (2) copies for A/E. Written reports of each inspection, test or similar service shall include, but not be limited to:

1. Name, address and telephone number of testing agency

2. Dates and locations of samples and tests or inspections

3. Names of individuals making the inspection or test

4. Designation of the Work and test method

5. Identification of product and Specification section

6. Complete inspection or test data

7. Test results and an interpretation of test results

8. Ambient conditions at the time of sample taking and testing

9. Professional opinion as to whether inspected or tested Work complies with Contract

Document requirements

10. Name and signature of laboratory inspector

11. Recommendations on retesting

1.4 QUALIFICATION AND CERTIFICATION OF SERVICE AGENCIES

A. All testing service agencies, engaging in inspection and testing services, including independent testing laboratories, shall be prequalified as complying with “Recommended Requirements for

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Quality Assurance and Control DEI# 50076991 01 43 00 - 3

Independent Laboratory Qualification” by the American Council of Independent Laboratories, and shall specialize in the types of inspections and tests to be performed. Each service agency engaged on the Project shall be authorized to operate in the Commonwealth of Virginia.

B. Additionally, each laboratory shall:

1. Comply with the requirements of ASTM D3740 and E329. 2. Maintain full-time registered engineer on staff to review and supervise services. 3. Calibrate testing equipment at reasonable intervals with devices of accuracy traceable to

either the National Institute of Standards and Technology (NIST) or accepted values of natural physical constants.

CM/GC’s QC REQUIRED CERTIFICATION LOG - sample

Section Paragraph Certification Requirement Certification Record Date

Completed 07141 3.1 Cold Fluid-Applied

Waterproofing Pre-application Bi-weekly CQC report

07210 3.1 Building Insulation Pre-application Bi-weekly CQC report 07270 3.1 Firestopping Pre-application Bi-weekly CQC report 07532 3.1 (CSPE) Single-ply membrane

roofing Pre-application Bi-weekly CQC report

3.2 Pre-application Bi-weekly CQC report 3.3 Post application Bi-weekly CQC report

07901 3.1 Joint Sealants Pre-application Bi-weekly CQC report 08212 3.1 Stile and Rail Wood Doors Pre-application Bi-weekly CQC report 08462 3.1 Swinging Automatic Entrance

Doors Pre-application Bi-weekly CQC report

3.7B Post application Letter 0880 3.1 Glazing Pre-application Bi-weekly CQC report 09300 3.1 Tile Pre-application Bi-weekly CQC report 09550 3.2 Wood Flooring Pre-application Bi-weekly CQC report 09660 3.1B Resilient Tile Flooring Pre-application Bi-weekly CQC report

3.2C Pre-application Bi-weekly CQC report 3.2E Pre-application Bi-weekly CQC report

09680 3.1 Carpet Pre-application Bi-weekly CQC report 09950 3.1B Wall Coverings Pre-application Bi-weekly CQC report 11132 3.1B Projection Screens Post application Bi-weekly CQC report 14100 3.1B Dumbwaiters (if picked up) Post application Bi-weekly CQC report 16030 3.2A Adjusting, Balancing, and

System Testing Pre-application Bi-weekly CQC report

3.2C Post application Letter 3.3C Post application Letter 3.4G Pre-application Letter 3.4H Pre-application Letter 3.4I Post application Letter

15050 1.4 Demolition Pre-application Letter 15060 3.1 Pipe and Pipe Fittings Pre-application Bi-weekly CQC report

3.7 Post application Letter 15210 3.1A Vibration Isolation Periodic Bi-weekly CQC report [Periodic]

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Quality Assurance and Control DEI# 50076991 01 43 00 - 4

15220 3.1B Water Treatment Post application Bi-weekly CQC report Letter 3.23 Plumbing General Provisions Post application Letter 15761 3.1E Fan Coil Units Post application Bi-weekly CQC report 15770 3.1B Packaged Air Handling Units Post application Bi-weekly CQC report

3.1E Post application Bi-weekly CQC report 3.1F Post application Bi-weekly CQC report 3.1I Pre-application Bi-weekly CQC report

15820 3.1C Fans Post application Bi-weekly CQC report 15846 3.1I Pre-fabricated Ductwork Pre-application Bi-weekly CQC report

3.2 Post application Bi-weekly CQC report 15899 3.1C Adjustable Frequency Drive

Units Post application Letter

16470 3.1 Panelboards Post application Bi-weekly CQC report 16623 3.1 Elevator Equipment Wiring Pre-application Bi-weekly CQC report 16721 3.2 Fire Alarm and Smoke

Detection System Post application Letter

16722 3.2 Intrusion Detection and Security Access System

Post application Letter

17000 3.4D Building Automation System Post application Letter 1.5 MOCKUPS A. Tunnel Waterproofing

1. Contractor shall provide a mock up demonstrating sheet membrane waterproofing installation in accordance with Division 07 specifications, including: a. Interior Corner b. Exterior Corner c. Horizontal & Vertical Lapping d. Precast seems e. Cast-in-place/Precast interface f. Terminations g. Protection Board

1.6 EQUALS AND SUBSTITUTES

A. See General Conditions §26 in either the HECO-7/CO-7.

END OF SECTION 01 43 00

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Temporary Facilities and Controls DEI# 50076991 01 50 00 - 1

SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS

1.1 TEMPORARY MATERIALS

A. Temporary materials may be new or used, but must be adequate in capacity for required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.

1.2 PROTECTION OF INSTALLED WORK

A. Protect installed Work in a manner to prevent damage from construction operations. B. Provide special protection as detailed in individual Specification sections. C. Provide temporary and removable materials for protection of installed products and to control

activity in the immediate Work area to minimize damage. D. Protect finished Work from damage, defacement, stains, scratches, and wear. E. Prohibit traffic or storage upon waterproofed or roofed surfaces. If traffic or activity is necessary

upon such surfaces, the CM/GC shall obtain recommendations for protection from the weatherproofing or roofing material manufacturer.

F. Prohibit vehicular/equipment traffic on lawn and landscaped areas.

1.3 TEMPORARY INSTALLATIONS

A. Install, maintain, and operate temporary utilities and services to ensure continuous operation, and modify and extend such temporary systems as Work progresses.

B. Install temporary facilities and controls in a manner that produces a uniform appearance, that is

structurally adequate for the required purposes, and that is properly maintained. C. Modify and relocate temporary facilities and controls as necessary to accommodate progress of

Work. 1.4 CLEANING, REMOVAL, AND RESTORATION

A. Maintain the construction site in a clean and orderly manner; provide for routine removal of trash and construction debris; provide appropriate waste receptacles and containers on site; and remove all such receptacles and containers prior to Substantial Completion inspection.

B. Remove all temporary above grade or buried utilities, equipment, facilities, controls, and materials

prior to Substantial Completion inspection. C. Repair damage caused by installation or use of temporary Work. D. Restore existing facilities and equipment used during construction to original condition.

END OF SECTION 01 50 00

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Temporary Utilities DEI# 50076991 01 51 00 - 1

SECTION 01 51 00 TEMPORARY UTILITIES

1.1 GENERAL

A. “Enclosure” is defined as the state of construction when: exterior walls are erected; doors and windows are installed; glazing, roof deck, and roofing are complete; and other openings in the exterior envelope are equipped with temporary enclosures.

1.2 ELECTRICITY AND LIGHTING

A. CM/GC Supplied Utilities: CM/GC shall provide temporary electrical service required for power and lighting, arrange provisions with utility company or University, and pay costs for service and energy consumed. The service shall be equipped with a meter, main disconnect, and over current protection. Connections to existing systems must be approved by the University. The CM/GC shall pay the costs for service and the energy consumed.

B. CM/GC shall provide electrical service sized to provide adequate temporary power and lighting. C. CM/GC shall provide a branch distribution system from the temporary power source with

distribution boxes and outlets located so that power and lighting is available throughout active Work areas.

D. Permanent receptacles may be utilized during construction. E. Existing receptacles may be utilized as a source of temporary electric service for remodeling

Work within an existing building. F. CM/GC shall replace receptacle plates and wiring devices damaged during construction. G. CM/GC shall provide lighting to ensure safe construction operations and to allow proper finishing

operations. H. Permanent lighting systems may be utilized during construction. I. Existing lighting system may be utilized for temporary lighting for remodeling Work within an

existing building. J. CM/GC shall: restore permanent (and/or existing) lighting systems used during construction to

new (and/or original) condition; replace defective fixtures, controls, and other component parts and; clean fixtures and replace lamps. Lighting shall not be directed skyward.

K. All temporary wiring shall be removed before completion of project.

1.3 HEATING, COOLING, AND VENTILATING

A. CM/GC Supplied Utilities: Prior to Enclosure, CM/GC shall provide heating, cooling, and ventilation as necessary to protect materials, products, and finishes from damage due to temperature or humidity. CM/GC shall provide and pay for costs of supervision, operation, maintenance, fuel, and energy consumed.

B. Ventilate enclosed areas to assist in the curing of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Temporary Utilities DEI# 50076991 01 51 00 - 2

C. No permanent HVAC system shall be operated without the permanent filters and/or strainers in place. Upon Substantial Completion, all filters and/or strainers shall be replaced with new filter/strainers. All temporary filters shall be removed prior to occupancy.

1.4 TELEPHONE

A. Contractor’s personnel shall have individual mobile phones, paid for by the contractor, for the purpose of executing the Work.

1.5 WATER

A. University Supplied Utilities: The University will provide the CM/GC with existing source(s) of water for construction use where feasible. The CM/GC is responsible for coordinating Work related to temporary water requirements without compromising the University’s need for water and protecting the building water supply. The CM/GC shall conserve water to the extent practicable and shall use a reasonable amount of water for construction. The CM/GC shall pay for water usage and related sewer costs above the reasonable amount if the University determines an unreasonable or excessive amount of water has been used by the CM/GC. Should the CM/GC's use of water required for Work exceed the limits of available water to the building the CM/GC shall reduce water consumed and/or pay for such modifications as required to eliminate compromising the University system’s ability to meet water requirements for existing services.

B. Where UVA water lines are not easily accessible, contractor shall provide alternate means of supplying water such as a water truck or engaging with City of Charlottesville.

1.6 UTILITY OUTAGES

A. The following restrictions apply to utility outages. B. Authority to schedule power outages must be obtained from the University. The University will

coordinate the interruption of service with the CM/GC and all University parties affected.

C. In all cases the CM/GC shall keep utility and service outages to a minimum and proceed only after written approval of the University is received.

D. CM/GC requests for outages shall include an identification of areas that will be affected by the

proposed outage. E. CM/GC requests for outages shall be submitted a minimum of five (5) working days [preferred ten

(10) days for extensive outages] in advance of the proposed outage.

END OF SECTION 01 51 00

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Construction Facilities DEI# 50076991 01 52 00 - 1

SECTION 01 52 00 CONSTRUCTION FACILITIES

1.1 FIELD OFFICES

A. Contractor is not required to provide a field office or trailer.

1.2 SANITARY FACILITIES

A. Provide and maintain temporary sanitary facilities and enclosures. Existing and new permanent facilities are not available for use.

END OF SECTION 01 52 00

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Vehicular Access and Parking DEI# 50076991 01 55 00 - 1

SECTION 01 55 00 VEHICULAR ACCESS AND PARKING

1.1 TEMPORARY ACCESS ROADS AND APPROACHES

A. Construct and maintain temporary roads and approaches to serve the construction area. Temporary roads must not interfere with public routes and must be maintained so as not to be a source of offsite dirt, debris, and litter.

B. Extend and relocate temporary access roads and approaches as Work progress requires.

Provide detours necessary for unimpeded traffic flow. C. Provide and maintain access to all fire protection equipment (ie. fire hydrants, post indicator

valves, fire department connections or Siamese connections) and keep all fire protection equipment free of obstructions.

D. Consult with authority having jurisdiction in establishing public thoroughfares to be used for site

access haul routes (i.e. the University, City of Charlottesville, Albermarle County and/or VDOT). E. Keep all public streets, drives, and walks adjacent to site and haul routes clean and free of dirt,

debris, and litter caused by construction operations. Any dirt, debris, and litter caused by construction operations must be removed immediately. Contractor shall be responsible for street sweeping on a regular basis and at the conclusion of each segment of construction.

F. Install appropriate vehicle / under carriage washing procedures as detailed in the Specifications.

1.2 TEMPORARY PARKING

A. The contractor may park within the construction fence limits.

B. If additional parking is required, parking permits for on-grounds parking may be purchased by the CM/GC from the University Parking and Transportation Office, 1101 Millmont Street, Charlottesville, VA 22903.

C. Existing on-site streets and parking facilities may not be used by construction personnel. D. CM/GC and delivery trucks may park within the staging areas indicated on the Drawings. E. Parking violators will be subject to towing and fines.

END OF SECTION 01 55 00

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Temporary Barriers and Enclosures DEI# 50076991 01 56 00 - 1

SECTION 01 56 00 TEMPORARY BARRIERS AND ENCLOSURES

1.1 TEMPORARY BARRIERS AND ENCLOSURES

A. Provide barriers to prevent unauthorized entry to construction areas and to protect existing facilities and adjacent properties from damage from construction operations.

B. Provide barricades and covered walkways required by governing authorities for public rights-of-

way and for public access to existing building. C. Provide construction fence and vehicular barriers around construction site as shown in the

Drawings; equip with gates and locks. Gates shall be “double locked” including one lock provided by the contractor and one provided by the University. 1. Chainlink fence

a. 8’ Height b. Equip with green mesh screen with sufficient opening to minimize wind damage. Number

and sizing of openings by contractor. c. Direct bury fence post. In paved areas contractor may use 2’ x 1’ stands provided they

are properly anchored with sandbags.

2. Orange Safety Fence

3. Vehicular Safety Barriers (Precast concrete or water filled)

4. Road Plates a. Contractor shall utilize road plates to return traffic to normal condition while construction

is inactive. b. Contractor shall install asphalt along edges of asphalt plate to create smooth transition of

the travelled way. c. Road plates shall be structurally capable of fully supporting highway loads. d. Contractor shall also have road plates on hand during construction of critical intersections

in order to facilitate emergency vehicle traffic.

D. Exterior Closures: 1. Provide temporary weather-tight closure at exterior openings to accommodate acceptable

working conditions and protection for products, to allow for temporary heating and maintenance of required ambient temperatures, and to prevent entry of unauthorized persons.

2. Provide access doors with appropriate hardware and locks.

E. Interior Closures:

1. Provide temporary barriers to separate construction areas from University occupied areas, to prevent penetration of dust into occupied areas, to prevent entry of unauthorized persons in construction areas, and to prevent damage to existing materials and equipment.

2. Construct of adequate framing and surface with non-combustible materials having closed

joints and sealed edges at intersections with existing surfaces. 3. Closures with fire rated corridors shall meet fire-rating equivalents.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Temporary Barriers and Enclosures DEI# 50076991 01 56 00 - 2

4. Paint surfaces exposed to view in occupied areas in colors directed by the Architect.

F. Tree and Plant Protection:

1. Preserve and protect existing trees and plants designated to remain post-construction. 2. Provide 4 foot high chain link fences around drip line or beyond as approved by the

University, with access for maintenance. 3. Consult with University Architect/Arborist; remove agreed-on roots and branches which

interfere with construction; employ University approved arborist to remove and to treat cuts. 4. Protect areas within barriers from traffic, parking, storage, dumping, chemically injurious

materials and liquids, ponding, and continuously running water. 5. Contractor shall provide wooden logging mats in wooded areas to protect against excessive

rutting of access road, damage to tree trunks or tree roots.

6. Replace trees and plants damaged by construction operation with ones of similar size and approved by the University. Trees lost or damaged shall be replaced on an inch for inch basis. For example, an 8-inch tree can be replaced by two (2) 4-inch trees. All replacement trees shall be 1.5” caliber or larger. Coordinate with Office of University Architect for exact type and location of replacement trees.

1.2. SECURITY

A. Provide security and facilities to protect the worksite and existing premises from unauthorized entry, vandalism, and theft.

B. Conduct all operations in a manner to avoid risk of loss, theft, or damage by vandalism.

1.3 NOISE CONTROL

A. Execute Work as quietly as practicable to avoid unnecessary disturbances to occupants within and around the premises.

B. High-level noise operations must be performed in accordance with local regulations and must be

approved by University prior to proceeding. C. Loud noise and vibrations, which cause disturbance in residential, hospital, and/or laboratory

areas, must be controlled and coordinated in advance with the University.

END OF SECTION 01 56 00

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Execution and Closeout Requirements DEI# 50076991 01 70 00 - 1

SECTION 01 70 00 EXECUTION AND CLOSEOUT REQUIREMENTS

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplemental General Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following:

1. Inspection procedures. 2. Submittal of As-Built markup project documents to A/E. 3. Submittal of Record revision by A/E to University’s PM, CAM, or Resource Center.

4. Submittal of warranties to University’s PM or CAM.

B. Closeout requirements for specific construction activities are included in the appropriate Sections in Divisions 2 through 33.

C. Detailed requirements for Record and As-Built markup documents to be submitted as part of project

closeout are to be found in Division 1 section, “Project Record Documents, Contractor’s “As-Built” Drawings”.

1.3 SUBSTANTIAL COMPLETION

A. Procedures: Comply with procedures specified in the Commonwealth of Virginia General Conditions for the Contract for Construction. Before submitting the Certificate of Partial or Substantial Completion by the Contractor (HECO-13.2a) complete the following. List exceptions in the request. 1. In the Application for Payment that coincides with, or first follows, the date Substantial

Completion is claimed, show 100 percent completion for the portion of the Work claimed as substantially complete. a. Include supporting documentation for completion as indicated in these Contract Documents

and a statement showing an accounting of changes to the Contract Sum.

b. If 100 percent completion cannot be shown, include a list of incomplete items, the value of incomplete construction, and reasons the Work is not complete.

2. Obtain and submit all releases that the University requires in order to lawfully occupy the Work without restriction.

3. Advise the University’s PM or CAM of pending insurance changeover requirements.

4. Submit Commonwealth of Virginia Affidavit of Payment of Claims (CO-13).

5. Submit specific warranties, workmanship bonds, maintenance agreements, final certifications, and similar documents. All warranties and guarantees shall be drawn in the name of the Commonwealth of Virginia and Rector and Board of Visitors of the University of Virginia.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Execution and Closeout Requirements DEI# 50076991 01 70 00 - 2

6. Submit marked-up project documents, maintenance manuals, and similar information to A/E of

Record. See section 01720 for specific requirements.

7. Deliver extra stock, and similar items

8. Discontinue and remove temporary facilities from the site, along with construction tools and similar elements.

9. Complete repair of all deficient work, including the touch up of all deficient finishes. a. The Architect will under no circumstances confirm the Work to be Substantially Complete

unless all deficient finish work has been completely repaired and all deficient finishes touched up.

10. Complete Final Cleaning. a. The Architect will under no circumstances confirm the Work to be Substantially Complete

unless Final Cleaning has been completely performed.

11. Remove temporary lock cylinders and cores.

12. Complete all start-up testing of building systems, special testing, and commissioning; deliver reports to University’s representative (PM or CM).

13. Instruct the University’s representatives in the operation of building systems and deliver Building Automation Systems manuals to University’s representative (PM or CM).

14. Complete the exterior portions of the Work to the same degree as that of the interior. a. Exterior lighting must be complete.

b. Construction operations must not impede walkways or driveways.

c. Dumpster and loading dock pads must be clear and in place.

d. Seeding, planting, and initial watering must be performed.

1.4 FINAL ACCEPTANCE

A. Procedures: Comply with procedures specified in the Commonwealth of Virginia General Conditions for the Contract for Construction. Before submitting the Certificate of Completion by the Contractor (HECO-13.2), complete the following: 1. Submit the final payment request with releases and supporting documentation not previously

submitted and accepted. Include insurance certificates for products and completed operations where required. List exceptions in the request.

2. Submit an updated final statement, accounting for final additional changes to the Contract Sum.

3. Submit a certified copy of the A/E's final inspection list of items to be completed or corrected, endorsed, and dated by the A/E. The certified copy of the list shall state that each item has

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Execution and Closeout Requirements DEI# 50076991 01 70 00 - 3

been completed or otherwise resolved for acceptance.

4. Submit final meter readings for utilities, a measured record of stored fuel, and similar data as of the date of Substantial Completion or when the University took possession of and assumed responsibility for corresponding elements of the Work.

5. Submit consent of Surety to final payment.

6. Submit evidence of final, continuing insurance coverage complying with insurance requirements.

2.0 PRODUCTS (Not Applicable)

3.1 FINAL CLEANING

A. General: Regular construction cleaning is included in Division 1 section "Construction Facilities and Temporary Controls."

B. Cleaning: Employ a professional cleaning service for final cleaning. Clean each surface or unit to

the condition expected in a normal, commercial building cleaning and maintenance program. Comply with manufacturer's instructions. 1. Complete the following cleaning operations before requesting inspection for certification of

Substantial Completion. a. Remove all temporary labels. Do not remove labels describing the fire resistance of doors

and frames.

b. Clean glass, plastic, and all reflective surfaces, including all glass in doors and windows. Remove glazing compound, and over-paint. Clean all transparent material on both surfaces.

c. Exterior hard surfaces must be free of stains, shavings, films, gum, and other foreign deposits.

d. Interior hard surfaces, including shelves within built-in casework, must be free of cobwebs, dust, stains, shavings, films, and gum.

e. Electrical and mechanical equipment must be must be free of dust, cobwebs, stains, shavings, films, gum, excess lubricant, and other substances.

f. Interior and exterior lamp lenses, reflectors, and baffles must be free of cobwebs, dust, stains, films, gum, insect droppings and carcasses.

g. Removal of Protection and Facilities: Remove temporary protection and construction facilities installed for the Work, including Contractor’s office and site fencing, as specified in Division 1 section, “Construction Facilities and Temporary Controls.” Demount, clean, repaint, and stack on site all wood fence materials removed as directed for the University to retrieve. Clean the site, including landscape development areas, of rubbish, litter, and other foreign substances. Sweep paved areas broom clean; remove stains, spills, and other foreign deposits. Rake grounds that are neither paved nor planted to a smooth, even-textured surface.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Execution and Closeout Requirements DEI# 50076991 01 70 00 - 4

C. Compliance: Comply with regulations of authorities having jurisdiction and safety standards for

cleaning. Do not burn waste materials. Do not bury debris or excess materials on the University's property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from the site and dispose of lawfully. 1. Where extra materials of value remain after completion of associated Work, they become the

University's property. Dispose of these materials as directed by the University’s PM/CAM.

END OF SECTION 01 70 00

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Closeout Submittals DEI# 50076991 01 78 00 - 1

SECTION 01 78 00 CLOSEOUT SUBMITTALS

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplemental General Conditions and other Division 1 Specification sections, apply to this section.

1.2 SUMMARY

A. The A/E shall prepare and provide to the University Record Drawings and Specifications showing the “As-Built” conditions, locations, and dimensions based on the Contractor’s As-Built set of Drawings and Specifications, and other data furnished by the Contractor to the A/E. This section includes administrative and procedural requirements for creation of the Contractor’s As-Built set of Drawings and Specifications.

B. The Contractor will provide the following Project “As-Built” documents to the A/E for Record

document preparation: 1. Marked-up copies of Contract Drawings

2. Marked-up copies of Shop Drawings

3. Newly prepared drawings (as necessary)

4. Marked-up copies of Specifications, Addenda, and Change Orders

5. Marked-up product data Submittals

6. Field records for variable and concealed conditions

7. Draw or detail information on Work that is shown only schematically

The A/E shall provide a digital copy to the University’s PM/CAM/Resource Center for University O&M use until the final Record Drawings and Specifications are prepared by the A/E.

C. Related Sections: The following sections contain requirements that relate to this section:

1. Division 1 section "Submittals" specifies general requirements for preparing and submitting

Project Record Submittals.

2. Division 1 section Execution and Closeout Requirements" specifies general closeout requirements.

3. Divisions 2 through 33 sections for specifying Project Record Submittal requirements for specific pieces of equipment or building operating systems.

D. Maintenance of Documents and Samples: Store As-Built markup documents and samples in the

field office apart from the Contract Documents used for construction. Do not use As-Built markup documents for construction purposes. Maintain As-Built markup documents in good order and in a clean, dry, legible condition. Make documents available at all times for the A/E's inspections.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Closeout Submittals DEI# 50076991 01 78 00 - 2

1.3 CONSTRUCTION PROGRESS PHOTOS

A. Contractor shall take project photos of the work as it progresses on a regular basis.

B. Photos shall be digital photos.

C. Photos shall be labelled by Station/Location.

D. Photos shall be provided to the University at the end of construction or on a period identified by the UVA CAM

1.4 AS-BUILT MARKUP DRAWINGS

A. Markup procedure: During construction, maintain a plain bond copy of Contract Drawings and Shop Drawings for Project Record Document purposes. 1. Mark these Drawings to show the actual installation where the installation varies from the

installation shown originally. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later. Marked items include, but are not limited to, the following:

a. Dimensional changes to the Drawings

b. Revisions to details shown on the Drawings

c. Locations and depths of underground utilities

d. Revisions to routing of piping and conduits

e. Changes made by Contract Change Order

f. Details not on original Contract Drawings

2. Mark prints of Contract Drawings or Shop Drawings, whichever is most capable of showing actual physical conditions, completely and accurately. Where Shop Drawings are marked, show cross-reference on Contract Drawings location.

3. Mark documents with red erasable colored pencil. Use other colors to distinguish between changes for different categories of the Work at the same location.

4. Mark important additional information that was either shown schematically or omitted from original Drawings

5. Note Construction Change Order numbers B. Responsibility for Markup: The individual or entity that obtained record data, whether the individual

or entity is the Subcontractor, or similar entity, shall markup the Contract Drawings. 1. Accurately record information in an understandable drawing technique.

2. Record data as soon as possible after obtaining it.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Closeout Submittals DEI# 50076991 01 78 00 - 3

3. Record and check the markup prior to enclosing concealed installations.

C. Review of Drawings: Immediately prior to Substantial Completion inspection, review completed marked-up drawings with the A/E. 1. Incorporate changes and additional information previously marked on print sets. Erase, redraw,

and add details and notations where applicable. Identify and date each drawing. Include the printed designation "AS-BUILT PROJECT DRAWINGS" in a prominent location on each drawing.

2. Refer instances of uncertainty to the A/E for resolution. D. Adding Drawings to the As-Built Markup Documents: Prepare new drawings when the A/E determines that neither original Contract Drawings nor Shop Drawings are suitable to show the actual installation. New drawings may be required when a Change Order is issued as a result of accepting an alternate, substitution, or other modification.

3. Consult with the A/E for proper scale and scope of detailing and notations required to record the actual physical installation and its relation to other construction. When completed and accepted, integrate newly prepared Drawings with procedures specified for organizing, copying, binding, and submitting marked-up drawings.

4. Each prime contractor has the same responsibility for newly prepared drawings as specified for mark up of prints.

D. Submission of As-Built documents: At time of Substantial Completion, submit As-Built documents to

the A/E for the creation of Record Documents for University's records. 1. Organize marked-up drawings into manageable sets. Bind sets with bond or Kraft-paper cover

sheets; print suitable titles, dates, and other identification on the cover of each set.

1.5 AS-BUILT MARKUP PROJECT MANUAL

A. During the construction period, maintain a copy of the Project Manual, including Addenda and modifications issued, for As-Built Project Document purposes. 1. Mark the Specifications to indicate the actual installation where the installation varies from that

indicated in Specifications and modifications issued. Note related As-Built Project Drawing information, where applicable. Give particular attention to substitutions, selection of product options, and information on concealed installations that would be difficult to identify or measure and record later. a. In each Specification section where products, materials, or equipment units are specified or

scheduled, mark the copy with the proprietary name and model number of the product furnished.

b. Record the name of the manufacturer, supplier, installer, and other information necessary to provide a record of selections made and to document coordination with record product data Submittals and maintenance manuals.

c. Note related record product data, where applicable. For each principal product specified,

indicate whether record product data has been submitted in a maintenance manual instead of as a product data Submittal.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Closeout Submittals DEI# 50076991 01 78 00 - 4

B. Submission of As-Built Markup Project Manual: At time of Substantial Completion, submit As-Built

Markup Project Manual to the A/E for preparation of the Record Project Manual for the University's records. 1. Bind Project Manual into heavy-duty, 3-ring, black, vinyl-covered binders, with non-stick

transparent cover and spine pockets, 1 to 3 inches thick as required to contain information. 1.6 PRODUCT DATA SUBMITTALS

A. During the construction period, maintain one copy of each Product Data Submittal for final Project Submittal purposes. 1. Mark product data to indicate the actual product installation where the installation varies

substantially from that indicated in product data submitted. Include significant changes in the product delivered to the site and changes in manufacturer's instructions and recommendations for installation.

2. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

3. Note related Change Orders and As-Built Markup Drawings, where applicable.

4. Upon completion of markup, submit a complete set of Product Data Submittals to the A/E for the University's records.

5. Where approved Product Data Submittals are required as part of maintenance manuals, submit approved Product Data Submittals as an insert in the manual instead of inclusion in separate Product Data Submittals.

B. Submission of approved Project Data Submittals: At time of Substantial Completion, submit digital

files of approved Product Data Submittals to the A/E to verify accuracy and completeness and then deliver to the PM/CAM/Resource Center for the University’s records. For Agency 209 (Health System) projects, in addition to the digital files, one printed copy of approved Project Data Submittals must be submitted to the A/E for the University's records. 1. Bind Project Data Submittals into heavy-duty, 3-ring, black, vinyl-covered binders, with non-

stick transparent cover and spine pockets, 1 to 3 inches thick as required to contain information or submit as files in folders.

1.7 MAINTENANCE AND OPERATIONS MANUAL SUBMITTAL

A. When each construction activity that requires submittal of maintenance manuals is nominally complete, but before Substantial Completion, submit maintenance manuals specified. 1. Organize operation and maintenance manuals into suitable sets of manageable size

2. Provide heavy-duty, 3-ring, vinyl-covered binders, with non-stick transparent cover and spine

pockets, 1 to 3 inches thick as required to contain information, sized for 8½” x 11” paper with inside pockets or pocket folders for folded sheets.

3. Bind data into individual binders for each manual, properly identified on front and spine. For large manuals, provide an index sheet and thumb tabs for separate information categories per

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Closeout Submittals DEI# 50076991 01 78 00 - 5

the MasterSpec Table of Contents.

4. In each maintenance manual, include information specified in individual Specification sections and the following: a. Copies of applicable Shop Drawings and Product Data Submittals.

b. Names, addresses and trades of all applicable Subcontractors, manufacturers, and

equipment.

c. Complete maintenance instructions from the manufacturer’s local representative for each item of operable equipment, as well as the name, address and telephone number of the installing Subcontractor.

d. Catalog data on all items submitted and other pertinent data such as mortar colors, brick selected, and colors selected for all finished materials and fabrics.

e. Catalog data on all furnished plumbing fixtures, valves, water heaters, heating equipment, light fixtures and similar equipment and systems. Manufacturer’s promotional literature is not acceptable.

f. Manufacturer’s name, model number, service manual, spare parts list, and descriptive literature for all components used.

g. Preventive maintenance instructions and schedules for all major equipment.

h. Lit of most frequently encountered breakdowns and repairs/trouble shooting manual(s).

i. Instructions for starting and operating the actual system as installed.

j. Detailed one-line, color-coded wiring diagrams.

k. Copies of warranties.

l. Inspection procedures.

B. Submission of Operations and Maintenance (O&M) Manual: At time of Substantial Completion, submit O&M Manual to the A/E for the University's use. 1. Submit a single draft copy to the A/E for review and comment.

2. Submit digital files of approved O&M Manual binder contents to FM Resource Center.

3. Submit 1 (one) approved final copy of O&M Manual for Academic (Agency 207) and 2 (two)

copies for Health System (Agency 209) projects.

4. Submit spare parts to the University CAM.

5. Submit keys other than those provided by FM to the University CAM.

6. The Contractor shall furnish a COBie format data sheet inventory of all installed equipment and building components to include (if applicable) elevators, fire protection systems, fire detection systems, pressure vessels, emergency lighting, emergency electrical generators, monitoring

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Closeout Submittals DEI# 50076991 01 78 00 - 6

systems, electrical, HVAC and refrigeration, roofing, water and sewer, heat distribution, carpentry, plumbing for the preventive maintenance system. The Contractor shall provide all special tools and special test equipment required for Maintenance.

1.8 MISCELLANEOUS PROJECT DOCUMENT SUBMITTALS

A. Refer to other Specification sections for miscellaneous record-keeping requirements and Submittals in connection with various construction activities. Immediately prior to Substantial Completion, complete miscellaneous records and place in good order, properly identified and bound or filed, ready for use and reference. At time of Substantial Completion, submit digital (PDF) files and 1 (one) print copy for Health System (Agency 209) projects to the A/E for the University's records. 1. Categories of requirements resulting in miscellaneous records include, but are not limited to,

the following: a. Field records on excavations and foundations.

b. Field records on underground construction and similar work.

c. Survey showing locations and elevations of underground lines.

d. Invert elevations of drainage piping.

e. Authorized measurements utilizing unit prices or allowances.

f. Ambient and substrate condition tests.

g. Certifications received in lieu of labels on bulk products.

h. Batch mixing and bulk delivery records.

i. Testing and qualification of tradesmen.

j. Documented qualification of installation firms.

k. Inspections and certifications by governing authorities.

l. Leakage tests.

m. Final inspection and correction procedures.

2.1 PRODUCTS (Not Applicable) 3.1 RECORDING

A. Post changes and modifications to the Documents as they occur. Do not wait until the end of the Project.

3.2 AS-BUILT SURVEY

A. See Section 33 05 26 for post-construction survey asbuilt requirements prior to backfill.

END OF SECTION 01 78 00

Division 2: Existing Conditions

www.dewberry.com

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Site Demolition DEI# 50076991 02 41 19 - 1

SECTION 02 41 19 SITE DEMOLITION

PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions, Supplemental General Conditions, and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes demolition and removal of the following: 1. Existing concrete and asphaltic paving within the areas designated for new construction

work shall be completely demolished and all debris removed from the site. 1.3 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site unless in-dicated to be removed and salvaged or recycled.

B. Remove and Salvage: Detach items from existing construction and deliver them to Owner.

C. Existing to Remain: Existing items of construction that are not to be removed and that are not

otherwise indicated to be removed, removed and salvaged, or recycled. 1.4 MATERIALS OWNERSHIP

A. Historic items, relics, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, antiques, and other items of interest or value to Owner that may be encountered during building demolition remain Owner's property. Carefully remove and salvage each item or object in a manner to prevent damage and deliver promptly to Owner.

1.5 SUBMITTALS

A. Information Submittals 1. Qualification Data for the Demolition firm.

2. Schedule of Demolition Activities: Indicate detailed sequence of demolition and removal

work, with starting and ending dates for each activity, interruption of utility services, and locations of temporary protection and means of egress.

3. Pre-demolition Photographs: Show existing conditions of adjoining construction and site improvements that might be misconstrued as damage caused by construction operations.

4. Submit prior to the start of demolition activities.

B. Action Submittals 1. Proposed Protection and Control Measures: Submit statement or drawing that indicates

the measures proposed for use, proposed locations, and proposed time frame for their operation. Identify options if proposed measures are later determined to be inadequate. Include measures for the following:

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Site Demolition DEI# 50076991 02 41 19 - 2

a. Environmental protection. b. Dust control. c. Noise control.

2. Landfill Records: Indicate receipt and acceptance of hazardous wastes by a landfill facili-

ty licensed to accept hazardous wastes. 1.6 QUALITY ASSURANCE

A. Demolition Firm Qualifications: An experienced firm that has specialized in demolition work similar in material and extent to that indicated for this Project.

B. Regulatory Requirements: Comply with governing EPA notification regulations before begin-

ning demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

C. Standards: Comply with ANSI A10.6 and NFPA 241.

D. Predemolition Conference: Conduct conference at Project site. 1.7 PROJECT CONDITIONS

A. Conduct building demolition so Owner's operations will not be disrupted.

B. Provide not less than 10 days notice to Owner of activities that will affect Owner's operations.

C. Maintain access to existing walkways, exits, and other adjacent occupied or used facilities. 1. Do not close or obstruct walkways, exits, roads, or other occupied or used facilities with-

out written permission from authorities having jurisdiction.

D. Owner assumes no responsibility for structures to be demolished.

E. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

F. Before building demolition, Owner will remove the following items:

1. Not Applicable

G. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

H. Hazardous materials will be removed by Owner before start of the Work.

I. If materials suspected of containing hazardous materials are encountered, do not disturb; im-

mediately notify Architect and Owner. Hazardous materials will be removed by Owner under a separate contract.

J. Storage or sale of removed items or materials on-site is not permitted.

1.8 COORDINATION

A. Arrange demolition schedule so as not to interfere with Owner's on-site operations.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Site Demolition DEI# 50076991 02 41 19 - 3

PART 2 - PRODUCTS Not Applicable PART 3 - EXECUTION 3.1 EXAMINATION

A. Survey existing conditions and correlate with requirements indicated to determine extent of building demolition required.

B. Review Project Record Documents of existing construction provided by Owner. Owner does

not guarantee that existing conditions are same as those indicated in Project Record Docu-ments.

C. Inventory and record the condition of items to be removed and salvaged.

D. When unanticipated mechanical, electrical, or structural elements are encountered, investigate

and measure the nature and extent of the element. Promptly submit a written report to Owner.

E. Perform an engineering survey of condition of site features to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during construction operations.

F. Verify that hazardous materials have been remediated before proceeding with construction op-

erations. 3.2 PREPARATION

A. Temporary Shoring: Provide and maintain interior and exterior shoring, bracing, or structural support to preserve stability and prevent unexpected movement or collapse of construction be-ing demolished.

B. Removed and Salvaged Items: Comply with the following:

1. Clean salvaged items of dirt and demolition debris 2. Pack or crate items after cleaning. Identify contents of containers. 3. Store items in secure area until delivery to Owner. 4. Transport items to Owner's storage area designated by Owner. 5. Protect items from damage during transport and storage.

3.3 PROTECTION

A. Existing Facilities: Protect adjacent walkways, loading docks, building entries, and other build-

ing facilities during demolition operations.

B. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during demolition. When permitted by Owner, items may be removed to a suitable, protected storage location during demolition and cleaned and reinstalled in their original locations after demolition operations are complete.

C. Existing Utilities: Maintain utility services indicated to remain and protect them against damage

during demolition operations.

D. Do not interrupt existing utilities serving adjacent occupied or operating facilities unless author-

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Site Demolition DEI# 50076991 02 41 19 - 4

ized in writing by Owner and authorities having jurisdiction.

E. Provide temporary services during interruptions to existing utilities, as acceptable to Owner and to authorities having jurisdiction. 1. Provide at least 10 days notice to Owner if shutdown of service is required during

changeover.

F. Temporary Protection: Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction and as indicated.

G. Protect existing site improvements, appurtenances, and landscaping to remain.

H. Provide temporary barricades and other protection required to prevent injury to people and

damage to adjacent buildings and facilities to remain.

I. Provide protection to ensure safe passage of people around construction operations area and to and from occupied portions of adjacent buildings and structures.

J. Protect walls, windows, roofs, and other adjacent exterior construction that are to remain and

that are exposed to construction operations. 3.4 DEMOLITION, GENERAL

A. General: Demolish indicated items within limits shown on the drawings. Use methods required to complete the Work within limitations of governing regulations and as follows: 1. Do not use cutting torches until work area is cleared of flammable materials. Maintain fire

watch and portable fire-suppression devices during flame-cutting operations. 2. Maintain adequate ventilation when using cutting torches. 3. Locate construction equipment and remove debris and materials so as not to impose ex-

cessive loads on supporting walls, floors, or framing.

B. Engineering Surveys: Perform surveys as the Work progresses to detect hazards that may re-sult from construction activities.

C. Site Access and Temporary Controls: Conduct building demolition and debris-removal opera-

tions to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

D. Do not close or obstruct streets, walks, walkways, or other adjacent occupied or used facilities

without permission from Owner or building manager and authorities having jurisdiction. Provide alternate routes around closed or obstructed traffic ways if required by authorities having juris-diction.

E. Use water mist and other suitable methods to limit spread of dust and dirt. Comply with govern-

ing environmental-protection regulations. Do not use water when it may damage adjacent con-struction or create hazardous or objectionable conditions, such as ice, flooding, and pollution.

3.5 EXPLOSIVE DEMOLITION

A. Explosives: Use of explosives is not permitted. 3.6 SITE RESTORATION

A. Below-Grade Areas: Completely fill below-grade areas and voids resulting from building demo-lition operations with satisfactory soil materials according to backfill requirements in Specifica-

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Site Demolition DEI# 50076991 02 41 19 - 5

tion Sections "Earthwork: Utilities" and “Earth Moving”.

B. General: Promptly repair damage to adjacent construction caused by building demolition opera-tions.

C. Where repairs to existing surfaces are required, patch to produce surfaces suitable for new ma-

terials.

D. Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.

3.7 RECYCLING DEMOLISHED MATERIALS

A. General: Separate recyclable demolished materials from other demolished materials to the maximum extent possible. Separate recyclable materials by type.

B. Provide containers or other storage method approved by Architect for controlling recyclable ma-

terials until they are removed from Project site.

C. Stockpile processed materials on-site without intermixing with other materials. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.

D. Stockpile materials away from demolition area. Do not store within drip line of remaining trees.

E. Store components off the ground and protect from the weather.

F. Transport recyclable materials off Owner's property and legally dispose of them.

G. Recycling Incentives: Revenues, savings, rebates, tax credits, and other incentives received for

recycling building demolition materials shall accrue to Contractor. 3.8 DISPOSAL OF DEMOLISHED MATERIALS

A. General: Except for items or materials indicated to be recycled reused, salvaged, reinstalled, or otherwise indicated to remain Owner's property, remove demolished materials from Project site and legally dispose of them in an EPA-approved landfill.

B. Do not allow demolished materials to accumulate on-site.

C. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and

areas.

D. Burning: Do not burn demolished materials.

E. Disposal: Transport demolished materials off Owner's property and legally dispose of them. 3.9 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by building demoli-tion operations. Return adjacent areas to condition existing before building demolition opera-tions began.

END OF SECTION 02 41 19

This page intentionally left blank

Division 3: Concrete

www.dewberry.com

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 1

SECTION 03 30 00 CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions, Supplemental General Conditions, and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies cast-in place concrete, including formwork, reinforcement, concrete materials, mixture design, waterstops, placement procedures, and finishes, for the following work associated with the construction of the tunnel strengthening and any other cast-in-place structures:

1. Tunnel Walls, Base Slabs, and Top Slabs 2. Sidewalks

1.3 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Design Mixtures: For each concrete mixture. Submit alternate design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments.

1. Indicate amounts of mixing water to be withheld for later addition at Project site.

C. Steel Reinforcement Shop Drawings: Placing drawings that detail fabrication, bending, and placement. Include bar sizes, lengths, material, grade, bar schedules, stirrup spacing, bent bar diagrams, bar arrangement, splices and laps, mechanical connections, tie spacing, hoop spacing, and supports for concrete reinforcement.

D. Formwork Shop Drawings: Prepared by or under the supervision of a qualified professional engineer detailing fabrication, assembly, and support of formwork.

E. Jointing Plan: Contractor shall prepare and submit a concrete Control/Construction/Expansion Joint pattern plan. Plan sheets shall include dimensions for all concrete structures/pavement.

F. Material Certificates: For each of the following, signed by manufacturers:

1. Cementitious materials. 2. Admixtures. 3. Form materials and form-release agents. 4. Steel reinforcement and accessories. 5. Waterstops. 6. Curing compounds. 7. Bonding agents.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 2

8. Repair materials. 9. Adhesives. 10. Joint filler strips.

G. Field quality-control test and inspection reports.

H. Minutes of Pre-installation conference.

1.4 QUALITY ASSURANCE

A. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94 requirements for production facilities and equipment.

1. Manufacturer certified according to NRMCA's "Certification of Ready Mixed Concrete Production Facilities."

B. Testing Agency Qualifications: An independent agency qualified according to ASTM C 1077 and ASTM E 329 for testing indicated.

1. Personnel conducting field tests shall be qualified as ACI Concrete Field Testing Technician, Grade 1, according to ACI CP-01 or an equivalent certification program.

2. Personnel performing laboratory tests shall be ACI-certified Concrete Strength Testing Technician and Concrete Laboratory Testing Technician - Grade I. Testing Agency laboratory supervisor shall be an ACI-certified Concrete Laboratory Testing Technician - Grade II.

C. Source Limitations: Obtain each type or class of cementitious material of the same brand from the same manufacturer's plant, obtain aggregate from one source, and obtain admixtures through one source from a single manufacturer.

D. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents:

1. ACI 301, "Specification for Structural Concrete," Sections 1 through 5. 2. ACI 117, "Specifications for Tolerances for Concrete Construction and Materials."

E. Concrete Testing Service: Engage a qualified independent testing agency to perform material evaluation tests and to design concrete mixtures.

F. Preinstallation Conference: Conduct conference at project site 3 weeks before beginning work.

1. Before submitting design mixtures, review concrete design mixture and examine procedures for ensuring quality of concrete materials. Require representatives of each entity directly concerned with cast-in-place concrete to attend, including the following: a. Contractor’s superintendent b. Independent testing agency responsible for concrete design mixtures c. Ready-mix concrete manufacturer d. Concrete subcontractor e. Hydrophobic concrete admixture manufacturer representative

2. Review mix design and mix test results, mixing procedure, placement procedures, finishing options and procedures, hydrophobic concrete admixture, special inspection and testing and inspecting agency procedures for field quality control, concrete finishing,

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 3

cold and hot weather procedures, curing procedures, construction/contraction/expansion jointing, anchor rod tolerances, steel reinforcement installation, and concrete repair procedures.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending and damage. Avoid damaging coatings on steel reinforcement.

B. Waterstops: Store waterstops under cover to protect from moisture, sunlight, dirt, oil, and other contaminants. Store waterstops in location within the recommended storage temperature range specified by the manufacturer.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. In other Part 2 articles where titles below introduce lists, the following requirements apply to product selection:

1. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, products specified.

2. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, manufacturers specified.

2.2 FORM-FACING MATERIALS

A. Smooth-Formed Finished Concrete: Form-facing panels that will provide continuous, true, and smooth concrete surfaces. Furnish in largest practicable sizes to minimize number of joints.

1. Plywood, metal, or other approved panel materials.

B. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another approved material. Provide lumber dressed on at least two edges and one side for tight fit.

C. Void Forms: Biodegradable paper surface, treated for moisture resistance, structurally sufficient to support weight of plastic concrete and other superimposed loads.

D. Chamfer Strips: Wood, metal, PVC, or rubber strips, 3/4 by 3/4 inch, minimum.

E. Form-Release Agent: Commercially formulated form-release agent that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces.

1. Formulate form-release agent with rust inhibitor for steel form-facing materials.

F. Form Ties: Factory-fabricated, removable or snap-off metal or glass-fiber-reinforced plastic form ties designed to resist lateral pressure of fresh concrete on forms and to prevent spalling of concrete on removal.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 4

1. Furnish units that will leave no corrodible metal closer than 1 inch to the plane of exposed concrete surface.

2. Furnish ties with integral water-barrier plates to walls indicated to receive waterproofing.

2.3 STEEL REINFORCEMENT

A. Reinforcing Bars: ASTM A 615, Grade 60, deformed bars.

B. Plain Steel Wire: ASTM A 82.

2.4 REINFORCEMENT ACCESSORIES

A. Joint Dowel Bars: ASTM A 615, Grade 60, plain-steel bars, cut bars true to length with ends square and free of burrs.

B. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded wire reinforcement in place. Manufacture bar supports from steel wire, plastic, or precast concrete according to CRSI's "Manual of Standard Practice," of greater compressive strength than concrete and as follows:

1. For concrete surfaces exposed to view where legs of wire bar supports contact forms, use CRSI Class 1 plastic-protected steel wire or CRSI Class 2 stainless-steel bar supports.

2.5 CONCRETE MATERIALS

A. Cementitious Material: Use the following cementitious materials, of the same type, brand, and source, throughout Project:

1. Portland Cement: ASTM C 150, Type I. Supplement with the following:

a. Fly Ash: ASTM C 618, Class C or F.

B. Normal-Weight Aggregates: ASTM C 33, Class 4S coarse aggregate or better, graded. Provide aggregates from a single source.

1. Maximum Coarse-Aggregate Size: 3/4 inch nominal. 2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.

C. Water: ASTM C 94 and potable.

2.6 ADMIXTURES

A. Air-Entraining Admixture: ASTM C 260.

B. Chemical Admixtures: Provide admixtures certified by manufacturer to be compatible with other admixtures and that will not contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride.

1. Water-Reducing Admixture: ASTM C 494, Type A.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 5

2. Retarding Admixture: ASTM C 494, Type B. 3. Water-Reducing and Retarding Admixture: ASTM C 494, Type D. 4. High-Range, Water-Reducing Admixture: ASTM C 494, Type F. 5. High-Range, Water-Reducing and Retarding Admixture: ASTM C 494, Type G. 6. Plasticizing and Retarding Admixture: ASTM C 1017, Type II. 7. Color Pigment: As indicated on the drawings for sidewalks and stairs to match existing

site walkway color. 8. Hydrophobic (Waterproofing) Admixture: BSI 1881-122, Less than 1% Water Absorption.

a. Unless noted otherwise, all concrete shall include a water-based hydrophobic admixture which meets or exceeds BSI 1881-122 testing to a performance level of less than 1% water absorption.

b. Hydrophobic concrete admixture manufacturer shall have a minimum of 5 years of experience on projects of similar scope.

c. Delivery, storage, and handling shall conform to the hydrophobic concrete manufacturer’s instructions.

d. The concrete ready mix supplier shall contact the hydrophobic concrete admixture manufacturer before designing and testing any new mix designs to receive guidance on achieving proper water absorption characteristics. The concrete mix supplier shall report the test results to the hydrophobic concrete admixture manufacturer and all values shall be within the specification limits.

e. Test result requirements for hydrophobic concrete in addition to engineer’s performance requirements: Corrected 30 minute water absorption, age at test 7 days (BS 1881-122): Not greater than 1.0%.

f. All concrete shall be waterproofed by the addition of hydrophobic concrete admixture and additional ingredients including:

a. Hydrophobic concrete admixture at the rate of one U.S. gallon per cubic yard of concrete.

b. Superplasticizer at the manufacturer’s recommended rate and appropriate for the placement requirements of the project.

g. Water-Cement Ratio: 0.42 maximum for concrete employing hydrophobic concrete admixture. Water content of the hydrophobic concrete admixture and other admixtures shall be included in the water-to-cement ratio.

2.7 WATERSTOPS

A. Flexible PVC Waterstops: Not Allowed.

B. Self-Expanding Butyl Strip Waterstops: Manufactured half-circular strip, butyl rubber with sodium bentonite or other hydrophilic polymers, for adhesive bonding to concrete, 3/4 by 3/8 inch.

1. Available Products:

a. Colloid Environmental Technologies Company; Volclay Waterstop-RX. b. Concrete Sealants Inc.; Conseal CS-231. c. Greenstreak; Swellstop. d. Henry Company, Sealants Division; Hydro-Flex. e. JP Specialties, Inc.; Earthshield Type 20. f. Progress Unlimited, Inc.; Superstop. g. Carlisle Coatings & Waterproofing, Inc.

C. Extruded Bead Waterstop: Manufactured, high performance, extrudable swelling waterstop consisting of one-component, polyurethane-based waterstop meeting the following requirements:

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 6

a. Designed to swell up to 100% in potable water. b. Product shall be capable of sealing joints with head pressures up to 50 psi (115 ft

head). c. Elastic to withstand wet/dry cycling d. Temperature application rage: 50 degrees to 90 degrees e. Packaged in 20 fl oz tube. f. Tack free time of 2-3 hours at 73 degrees.

2.8 CURING MATERIALS

A. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete.

B. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.

C. Water: Potable.

D. Clear, Waterborne, Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B, dissipating.

2.9 RELATED MATERIALS

A. Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber.

B. Bonding Agent: ASTM C 1059, Type II, non-redispersible, acrylic emulsion or styrene butadiene.

C. Epoxy Bonding Adhesive: ASTM C 881, two-component epoxy resin, capable of humid curing and bonding to damp surfaces, of class suitable for application temperature and of grade to suit requirements, and as follows:

1. Types IV and V, load bearing, for bonding hardened or freshly mixed concrete to hardened concrete.

D. High-Strength Epoxy Doweling System: Epoxy doweling system shall be tested in accordance with ICC Acceptance Criteria 308 demonstrating compliance with the performance features of ACI 355.2. Submit ICC ES Evaluation Reports showing that the anchor is approved for use in uncracked and cracked concrete. The epoxy doweling system shall be installed according to manufacturer’s instructions. 1. Available Products:

a. Hilti HIT-HY 200 Epoxy Adhesive Anchoring System (ICC ESR-3187) b. ITW Red Head EPCON G5 Adhesive Anchoring System (ICC ESR-1137) c. Simpson Strong-Tie SET-XP Epoxy Adhesive Anchors (Use of SET-PAC system

not allowed). (ICC ESR-2508)

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 7

2.10 CONCRETE MIXTURES, GENERAL

A. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, according to ACI 301.

1. Use a qualified independent testing agency for preparing and reporting proposed mixturedesigns based on laboratory trial mixtures.

B. Cementitious Materials: Limit percentage, by weight, of cementitious materials other than portland cement in concrete as follows:

1. Fly Ash: 25 percent.

C. Limit water-soluble, chloride-ion content in hardened concrete to 0.15 percent by weight of cement.

D. Admixtures: Use admixtures according to manufacturer's written instructions. All admixtures shall be compatible with the hydrophobic concrete admixture.

1. Unless noted otherwise, all concrete shall include a water-based hydrophobic admixturewhich meets or exceed BSI 1881-122 testing to a performance level of less than 1%water absorption.

2. Use water-reducing, high-range water-reducing, or plasticizing admixture in concrete, asrequired, for placement and workability.

3. Use water-reducing and retarding admixture when required by high temperatures, lowhumidity, or other adverse placement conditions.

4. Use water-reducing admixture in pumped concrete and concrete with a water-cementitious materials ratio below 0.50.

5. Color Pigmentation: Include UVA standard color as indicated on the drawings (SolomanColors, Inc. #306 Colorflo liquid color (canvas) or approved equal by UVA).

2.11 CONCRETE MIXTURES

A. Tunnel Walls, Top Slab, and Base Slab: Proportion normal-weight concrete mixture as follows:

1. Minimum Compressive Strength at 28 days: 5,000 psi2. Maximum Water-Cementitious Materials Ratio: 0.423. Slump Limit: 5 inches, plus or minus 1 inch. 8 inches for concrete with verified slump of

2 to 4 inches before adding high-range water-reducing admixture or plasticizingadmixture, plus or minus 1 inch.

4. Air Content: 6 percent, plus or minus 1.5 percent at point of delivery.5. Hydrophobic Admixture: As required to limit water Absorption to 1% (Maximum)6. Color Pigmentation: Required on walking, visible surfaces (Hatch risers, Stairs,

sidewalks). Match UVA standard color (Soloman Colors, Inc. #306 Colorflo liquid color(canvas) or approved equal by UVA.

B. Sidewalks: Proportion normal-weight concrete mixture as follows:

1. Minimum Compressive Strength at 28 days: 4,000 psi2. Maximum Water-Cementitious Materials Ratio: 0.503. Slump Limit: 5 inches, plus or minus 1 inch. 8 inches for concrete with verified slump of

2 to 4 inches before adding high-range water-reducing admixture or plasticizingadmixture, plus or minus 1 inch.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 8

4. Air Content: 6 percent, plus or minus 1.5 percent at point of delivery. 5. Color Pigmentation: Required on walking surfaces (sidewalks). Match UVA standard

color (Soloman Colors, Inc. #306 Colorflo liquid color (canvas) or approved equal by UVA.

2.12 FABRICATING REINFORCEMENT

A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice."

2.13 CONCRETE MIXING

A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94, and furnish batch ticket information.

1. When air temperature is between 85 and 90 deg F, reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F, reduce mixing and delivery time to 60 minutes.

B. Project-Site Mixing: Not allowed.

PART 3 - EXECUTION

3.1 FORMWORK

A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads.

B. Construct formwork so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117.

C. Limit concrete surface irregularities, designated by ACI 347R as abrupt or gradual, as follows:

1. Class A, 1/8 inch for smooth-formed finished surfaces. 2. Class B, 1/4 inch for rough-formed finished surfaces.

D. Construct forms tight enough to prevent loss of concrete mortar.

E. Fabricate forms for easy removal without hammering or prying against concrete surfaces. Provide crush or wrecking plates where stripping may damage cast concrete surfaces. Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical.

1. Install keyways, reglets, recesses, and the like, for easy removal. 2. Do not use rust-stained steel form-facing material.

F. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required elevations and slopes in finished concrete surfaces. Provide and secure units to support screed strips; use strike-off templates or compacting-type screeds.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 9

G. Provide temporary openings for cleanouts and inspection ports where interior area of formwork is inaccessible. Close openings with panels tightly fitted to forms and securely braced to prevent loss of concrete mortar. Locate temporary openings in forms at inconspicuous locations.

H. Chamfer exterior corners and edges of permanently exposed concrete.

I. Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and bulkheads required in the Work. Determine sizes and locations from trades providing such items.

J. Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt, and other debris just before placing concrete.

K. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and maintain proper alignment.

L. Coat contact surfaces of forms with form-release agent, according to manufacturer's written instructions, before placing reinforcement.

3.2 EMBEDDED ITEMS

A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

3.3 REMOVING AND REUSING FORMS

A. General: Formwork for sides of walls and similar parts of the Work that does not support weight of concrete may be removed after cumulatively curing at not less than 50 deg F for 24 hours after placing concrete, if concrete is hard enough to not be damaged by form-removal operations and curing and protection operations are maintained.

1. Leave formwork for slabs, and other structural elements that supports weight of concrete in place until concrete has achieved at least 75 percent of its 28-day design compressive strength.

2. Remove forms only if shores have been arranged to permit removal of forms without loosening or disturbing shores.

B. Clean and repair surfaces of forms to be reused in the Work. Split, frayed, delaminated, or otherwise damaged form-facing material will not be acceptable for exposed surfaces. Apply new form-release agent.

C. When forms are reused, clean surfaces, remove fins and laitance, and tighten to close joints. Align and secure joints to avoid offsets. Do not use patched forms for exposed concrete surfaces unless approved by Engineer.

3.4 STEEL REINFORCEMENT

A. General: Comply with CRSI's "Manual of Standard Practice" for placing reinforcement.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 10

1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor retarder before placing concrete.

B. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials that would reduce bond to concrete.

C. Accurately position, support, and secure reinforcement against displacement. Locate and support reinforcement with bar supports to maintain minimum concrete cover. Do not tack weld crossing reinforcing bars.

D. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.

3.5 JOINTS

A. General: Construct joints true to line with faces perpendicular to surface plane of concrete.

B. Construction Joints: Install so strength and appearance of concrete are not impaired, at locations indicated or as approved by Engineer.

1. Place joints perpendicular to main reinforcement. Continue reinforcement across construction joints, unless otherwise indicated. Do not continue reinforcement through sides of strip placements of floors and slabs.

2. Form keyed joints as indicated. Embed keys at least 1-1/2 inches into concrete. 3. Locate horizontal joints in walls and columns at underside of slabs and at the top of

footings or floor slabs. 4. Space vertical joints in walls as indicated. 5. Use epoxy-bonding adhesive at locations where fresh concrete is placed against

hardened or partially hardened concrete surfaces. Install in accordance with manufacturer’s written instructions.

C. Doweled Joints: Install dowel bars and support assemblies at joints where indicated. Lubricate or asphalt coat one-half of dowel length to prevent concrete bonding to one side of joint.

3.6 WATERSTOPS

A. Self-Expanding Waterstops: Install in construction joints and at other locations indicated, according to manufacturer's written instructions, adhesive bonding, mechanically fastening, and firmly pressing into place. Install in longest lengths practicable.

B. Extruded Bead Waterstops: Install in construction joints and as otherwise indicated on the drawings. Install in accordance with manufacturer’s written instructions and in continuous placement as much as practicable.

3.7 CONCRETE PLACEMENT

A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections have been performed.

B. Before test sampling and placing concrete, water may be added at Project site, subject to limitations of ACI 301.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 11

1. Do not add water to concrete after adding high-range water-reducing admixtures to mixture.

C. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete will be placed on concrete that has hardened enough to cause seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as indicated. Deposit concrete to avoid segregation.

1. Deposit concrete in horizontal layers of depth to not exceed formwork design pressures and in a manner to avoid inclined construction joints.

2. Consolidate placed concrete with mechanical vibrating equipment according to ACI 301. 3. Do not use vibrators to transport concrete inside forms. Insert and withdraw vibrators

vertically at uniformly spaced locations to rapidly penetrate placed layer and at least 6 inches into preceding layer. Do not insert vibrators into lower layers of concrete that have begun to lose plasticity. At each insertion, limit duration of vibration to time necessary to consolidate concrete and complete embedment of reinforcement and other embedded items without causing mixture constituents to segregate.

D. Deposit and consolidate concrete for floors and slabs in a continuous operation, within limits of construction joints, until placement of a panel or section is complete.

1. Consolidate concrete during placement operations so concrete is thoroughly worked around reinforcement and other embedded items and into corners.

2. Maintain reinforcement in position on chairs during concrete placement. 3. Screed slab surfaces with a straightedge and strike off to correct elevations. 4. Slope surfaces uniformly to drains where required. 5. Begin initial floating using bull floats or darbies to form a uniform and open-textured

surface plane, before excess bleedwater appears on the surface. Do not further disturb slab surfaces before starting finishing operations.

E. Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures.

1. When average high and low temperature is expected to fall below 40 deg F for three successive days, maintain delivered concrete mixture temperature within the temperature range required by ACI 301.

2. Do not use frozen materials or materials containing ice or snow. Do not place concrete on frozen subgrade or on subgrade containing frozen materials.

3. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mixture designs.

F. Hot-Weather Placement: Comply with ACI 305 and as follows:

1. Maintain concrete temperature below 90 deg F at time of placement. Chilled mixing water or chopped ice may be used to control temperature, provided water equivalent of ice is calculated to total amount of mixing water. Using liquid nitrogen to cool concrete is Contractor's option.

2. Fog-spray forms, steel reinforcement, and subgrade just before placing concrete. Keep subgrade uniformly moist without standing water, soft spots, or dry areas.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 12

3.8 JOINT FILLING

A. Prepare, clean, and install joint filler according to manufacturer's written instructions. Defer joint filling until concrete has aged as long as possible. Do not fill joints until construction traffic has permanently ceased.

B. Remove dirt, debris, saw cuttings, curing compounds, and sealers from joints; leave contact faces of joint clean and dry.

C. Install joint filler at least 2 inches deep in joints. Overfill joint and trim joint filler flush with top of joint after hardening.

3.9 FINISHING FORMED SURFACES

A. Rough-Formed Finish: As-cast concrete texture imparted by form-facing material with tie holes and defects repaired and patched. Remove fins and other projections that exceed specified limits on formed-surface irregularities.

1. Apply to concrete surfaces not exposed to public view.

B. Smooth-Formed Finish: As-cast concrete texture imparted by form-facing material, arranged in an orderly and symmetrical manner with a minimum of seams. Repair and patch tie holes and defects. Remove fins and other projections that exceed specified limits on formed-surface irregularities.

1. Apply to concrete surfaces exposed to public view or to be covered with a coating or covering material applied directly to concrete.

C. Related Unformed Surfaces: At tops of walls, horizontal offsets, and similar unformed surfaces adjacent to formed surfaces, strike off smooth and finish with a texture matching adjacent formed surfaces. Continue final surface treatment of formed surfaces uniformly across adjacent unformed surfaces, unless otherwise indicated.

3.10 FINISHING SLABS

A. General: Comply with ACI 302.1R recommendations for screeding, restraightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces.

B. Float Finish: Consolidate surface with power-driven floats or by hand floating if area is small or inaccessible to power driven floats. Restraighten, cut down high spots, and fill low spots. Repeat float passes and restraightening until surface is left with a uniform, smooth, granular texture.

1. Apply float finish to surfaces to receive trowel finish or to be covered with sheet waterproofing.

C. Trowel Finish: After applying float finish, apply first troweling and consolidate concrete by hand or power-driven trowel. Continue troweling passes and restraighten until surface is free of trowel marks and uniform in texture and appearance. Grind smooth any surface defects that would telegraph through applied coatings or floor coverings.

1. Apply a trowel finish to surfaces exposed to view.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 13

D. Broom Finish: Apply a broom finish to exterior concrete sidewalks, tunnel top slabs, steps, ramps, and elsewhere as indicated.

1. Immediately after float finishing, slightly roughen trafficked surface by brooming with fiber-bristle broom perpendicular to main traffic route. Coordinate required final finish with Architect before application.

3.11 MISCELLANEOUS CONCRETE ITEMS

A. Filling In: Fill in holes and openings left in concrete structures, unless otherwise indicated, after work of other trades is in place. Mix, place, and cure concrete, as specified, to blend with in-place construction. Provide other miscellaneous concrete filling indicated or required to complete the Work.

3.12 CONCRETE PROTECTING AND CURING

A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and ACI 301 for hot-weather protection during curing.

B. Evaporation Retarder: Apply evaporation retarder to unformed concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing.

C. Formed Surfaces: Cure formed concrete surfaces, including underside of supported slabs, and other similar surfaces. If forms remain during curing period, moist cure after loosening forms. If removing forms before end of curing period, continue curing for the remainder of the curing period.

D. Unformed Surfaces: Begin curing immediately after finishing concrete. Cure unformed surfaces, including top of slabs, and other surfaces.

E. Cure concrete according to ACI 308.1, by one or a combination of the following methods:

1. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches, and sealed by waterproof tape or adhesive. Cure for not less than seven days. Immediately repair any holes or tears during curing period using cover material and waterproof tape.

2. Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Maintain continuity of coating and repair damage during curing period.

a. After curing period has elapsed, remove curing compound without damaging concrete surfaces by method recommended by curing compound manufacturer.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 14

3.13 CONCRETE SURFACE REPAIRS

A. Defective Concrete: Repair and patch defective areas when approved by Engineer. Remove and replace concrete that cannot be repaired and patched to Engineer's approval.

B. Patching Mortar: Mix dry-pack patching mortar, consisting of one part portland cement to two and one-half parts fine aggregate passing a No. 16 sieve, using only enough water for handling and placing.

C. Repairing Formed Surfaces: Surface defects include color and texture irregularities, cracks, spalls, air bubbles, honeycombs, rock pockets, fins and other projections on the surface, and stains and other discolorations that cannot be removed by cleaning.

1. Immediately after form removal, cut out honeycombs, rock pockets, and voids more than 1/2 inch in any dimension in solid concrete, but not less than 1 inch in depth. Make edges of cuts perpendicular to concrete surface. Clean, dampen with water, and brush-coat holes and voids with bonding agent. Fill and compact with patching mortar before bonding agent has dried. Fill form-tie voids with patching mortar or cone plugs secured in place with bonding agent.

2. Repair defects on surfaces exposed to view by blending white portland cement and standard portland cement so that, when dry, patching mortar will match surrounding color. Patch a test area at inconspicuous locations to verify mixture and color match before proceeding with patching. Compact mortar in place and strike off slightly higher than surrounding surface.

3. Repair defects on concealed formed surfaces that affect concrete's durability and structural performance as determined by Engineer.

D. Repairing Unformed Surfaces: Test unformed surfaces, such as floors and slabs, for finish and verify surface tolerances specified for each surface. Correct low and high areas. Test surfaces sloped to drain for trueness of slope and smoothness; use a sloped template.

1. Repair finished surfaces containing defects. Surface defects include spalls, popouts, honeycombs, rock pockets, crazing and cracks in excess of 0.01 inch wide or that penetrate to reinforcement or completely through unreinforced sections regardless of width, and other objectionable conditions.

2. After concrete has cured at least 14 days, correct high areas by grinding. 3. Repair defective areas, except random cracks and single holes 1 inch or less in

diameter, by cutting out and replacing with fresh concrete. Remove defective areas with clean, square cuts and expose steel reinforcement with at least a 3/4-inch clearance all around. Dampen concrete surfaces in contact with patching concrete and apply bonding agent. Mix patching concrete of same materials and mixture as original concrete except without coarse aggregate. Place, compact, and finish to blend with adjacent finished concrete. Cure in same manner as adjacent concrete.

4. Repair random cracks and single holes 1 inch or less in diameter with patching mortar. Groove top of cracks and cut out holes to sound concrete and clean off dust, dirt, and loose particles. Dampen cleaned concrete surfaces and apply bonding agent. Place patching mortar before bonding agent has dried. Compact patching mortar and finish to match adjacent concrete. Keep patched area continuously moist for at least 72 hours.

E. Perform structural repairs of concrete, subject to Engineer's approval, using epoxy adhesive and patching mortar.

F. Repair materials and installation not specified above may be used, subject to Engineer's approval.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 15

3.14 FIELD QUALITY CONTROL

A. Testing and Inspecting: Owner will engage a special inspector and qualified testing and inspecting agency to perform field tests and inspections and prepare test reports.

B. Inspections:

1. Steel reinforcement placement. 2. Verification of use of required design mixture. 3. Concrete placement, including conveying, depositing and consolidating. 4. Curing procedures and maintenance of curing temperature. 5. Verification of concrete strength before removal of shores and forms from beams and

slabs.

C. Concrete Tests: Testing of composite samples of fresh concrete obtained according to ASTM C 172 shall be performed according to the following requirements:

1. Testing Frequency: Obtain one composite sample for each day's pour of each concrete mixture exceeding 5 cu. yd., but less than 25 cu. yd., plus one set for each additional 50 cu. yd. or fraction thereof.

a. When frequency of testing will provide fewer than five compressive-strength tests for each concrete mixture, testing shall be conducted from at least five randomly selected batches or from each batch if fewer than five are used.

2. Slump: ASTM C 143; one test at point of placement for each composite sample, but not less than one test for each day's pour of each concrete mixture. Perform additional tests when concrete consistency appears to change.

3. Air Content: ASTM C 231, pressure method, for normal-weight concrete; one test for each composite sample, but not less than one test for each day's pour of each concrete mixture.

4. Concrete Temperature: ASTM C 1064; one test hourly when air temperature is 40 deg F and below and when 80 deg F and above, and one test for each composite sample.

5. Compression Test Specimens: ASTM C 31.

a. Cast and laboratory cure one set of four standard cylinder specimens for each composite sample.

6. Compressive-Strength Tests: ASTM C 39; test one laboratory-cured specimen at 7 days and two specimens at 28 days, and retain one specimen for later testing at 56 days if 28 day strength falls below the required specified strength.

a. A compressive-strength test shall be the average compressive strength from a set of two specimens obtained from same composite sample and tested at age indicated.

7. Strength of each concrete mixture will be satisfactory if every average of any three consecutive compressive-strength tests equals or exceeds specified compressive strength and no compressive-strength test value falls below specified compressive strength by more than 500 psi.

8. Test results shall be reported in writing to Owner, Engineer, concrete manufacturer, and Contractor within 48 hours of testing. Reports of compressive-strength tests shall contain Project identification name and number, date of concrete placement, name of concrete testing and inspecting agency, location of concrete batch in Work, design

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Cast-in-Place Concrete DEI# 50076991 03 30 00- 16

compressive strength at 28 days, concrete mixture proportions and materials, compressive breaking strength, and type of break for both 7- and 28-day tests.

9. Nondestructive Testing: Impact hammer, sonoscope, or other nondestructive device may be permitted by Engineer but will not be used as sole basis for approval or rejection of concrete.

10. Additional Tests: Testing and inspecting agency shall make additional tests of concrete when test results indicate that slump, air entrainment, compressive strengths, or other requirements have not been met, as directed by Engineer. Testing and inspecting agency may conduct tests to determine adequacy of concrete by cored cylinders complying with ASTM C 42 or by other methods as directed by Engineer.

11. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements.

12. Correct deficiencies in the Work that test reports and inspections indicate does not comply with the Contract Documents.

13. Structurally inadequate in-place concrete: If in-place concrete is found to be structurally deficient based on inspection reports, concrete testing, core tests, or other non-destructive testing, then the rejected in-place concrete shall be repaired, or removed and replaced, as directed by the owner’s representative.

END OF SECTION 03 30 00

Division 5: Metals

www.dewberry.com

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Structural Steel Framing DEI #50076991 05 12 00 - 1

SECTION 05 12 00 STRUCTURAL STEEL FRAMING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

B. Refer to contract drawings for additional requirements not listed herein for preparing and painting pipe guides, supports, and anchors.

1.2 SUMMARY

A. Section Includes:

1. Structural steel 2. Grout

1.3 SUBMITTALS

A. Submittal Restrictions: Contractor shall be required to submit anchor bolt epoxy doweling system for approval prior to preparing structural steel shop drawings as the products submitted could alter detailing of structural steel if either is different than Dewberry’s basis of design (Refer to 03 30 00, section 2.9 D).

B. Product Data: For each type of product indicated.

C. Shop Drawings: Show fabrication of structural-steel components.

1. Include details of cuts, connections, splices, camber, holes, and other pertinent data. 2. Include embedment drawings. 3. Indicate welds by standard AWS symbols, distinguishing between shop and field welds,

and show size, length, and type of each weld. 4. Indicate type, size, and length of bolts, distinguishing between shop and field bolts.

D. Welding certificates.

E. Mill Test Reports: Signed by manufacturers certifying that the following products comply with

requirements:

1. Structural steel including chemical and physical properties. 2. Bolts, nuts, and washers including mechanical properties and chemical analysis. 3. Shop primers (See contract drawings for coating requirements). 4. High-Strength, Non-shrink grout.

F. Source quality-control test reports.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Structural Steel Framing DEI #50076991 05 12 00 - 2

1.4 QUALITY ASSURANCE

A. Installer Qualifications: A qualified installer who participates in the AISC Quality Certification Program and is designated an AISC-Certified Erector, Category CSE. Engage an experienced Installer who has completed structural steel work similar in material, design, and extent to that indicated for this Project and with a record of successful in-service performance.

B. Fabricator Qualifications: A qualified fabricator who participates in the AISC Quality Certification Program and is designated an AISC-Certified Plant, Category Sbd. Engage a firm experienced in fabricating structural steel similar to that indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to fabricate structural steel without delaying the Work.

C. Welding: Qualify procedures and personnel according to AWS D1.1, "Structural Welding Code--Steel."

D. Comply with applicable provisions of the following specifications and documents:

1. AISC 303 "Code of Standard Practice for Steel Buildings and Bridges." 2. AISC 360 "Specification for Structural Steel Buildings"

1.5 DELIVERY, STORAGE, AND HANDLING

A. Store materials to permit easy access for inspection and identification. Keep steel members off ground and spaced by using pallets, dunnage, or other supports and spacers. Protect steel members and packaged materials from erosion and deterioration.

1. Store fasteners in a protected place. Clean and relubricate bolts and nuts that become

dry or rusty before use. 2. Do not store materials on structure in a manner that might cause distortion, damage, or

overload to members or supporting structures. Repair or replace damaged materials or structures as directed.

PART 2 - PRODUCTS

2.1 STRUCTURAL-STEEL MATERIALS

A. W-Shapes: ASTM A 992, Grade 50.

B. Channels, Angles, M-Shapes, S-Shapes: ASTM A 36.

C. Plate and Bar: ASTM A 36.

D. Cold-Formed Hollow Structural Sections: ASTM A 500, Grade B, structural tubing.

E. Steel Pipe (For use in Anchors): ASTM A 53, Type E or S, Grade B.

F. Welding Electrodes: Comply with AWS requirements.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Structural Steel Framing DEI #50076991 05 12 00 - 3

2.2 BOLTS, CONNECTORS, AND ANCHORS

A. High-Strength Bolts, Nuts, and Washers: ASTM A 325, Type 1, heavy-hex steel structural bolts; ASTM A 563, Grade C, heavy-hex carbon-steel nuts; and ASTM F 436, Type 1, hardened carbon-steel washers; all with plain finish.

B. Unheaded Anchor Rods: ASTM F593 CW2 (A304) with a minimum tensile stress of 85 ksi.

1. Configuration: Straight. 2. Nuts: ASTM F594 Heavy Hex (A304). 3. Washers shall meet the dimensional requirements of ASME B18.22.1, and the material

requirements matching that of bolts and nuts.

C. Threaded Rods: For use with Epoxy Doweling System (refer to 03 30 00, Section 2.9 D)

1. Stainless steel anchor rods shall be AISI Type 316 stainless steel conforming to ASTM F593 Condition CW2 with a minimum tensile stress of 100 ksi. Provide stainless steel nuts and washers of matching alloy group and minimum proof stress equal to or greater than the specified minimum full-size tensile strength of the externally threaded fastener. All nuts shall conform to ASTM F594 unless otherwise specified.

2.3 GROUT

A. Nonmetallic, Shrinkage-Resistant Grout: ASTM C 1107, factory-packaged, nonmetallic aggregate grout, noncorrosive, nonstaining, mixed with water to flowable consistency suitable for pouring into forms with a 30-minute working time. Grout shall have a minimum compressive strength of 5,800 psi at 28 days per ASTM C109. Grout shall be from one of the following manufacturers:

a. Euclid Chemical Company – NS Grout b. BASF - MasterFlow 928 c. Sika Corporation – SikaGrout 212

2.4 FABRICATION

A. Structural Steel: Fabricate and assemble in shop to greatest extent possible. Fabricate according to AISC 303 "Code of Standard Practice for Steel Buildings and Bridges" and AISC 360 "Specification for Structural Steel Buildings"

1. Identify high-strength structural steel according to ASTM A 6/ A 6M and maintain markings until structural steel has been erected.

2. Mark and match-mark materials for field assembly. 3. Complete structural-steel assemblies, including welding of units, before starting shop-

priming operations.

B. Thermal Cutting: Perform thermal cutting by machine to greatest extent possible.

1. Plane thermally cut edges to be welded to comply with requirements in AWS D1.1.

C. Bolt Holes: Cut, drill, or punch standard bolt holes perpendicular to metal surfaces.

D. Finishing: Accurately finish ends of columns and other members transmitting bearing loads.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Structural Steel Framing DEI #50076991 05 12 00 - 4

E. Cleaning: Clean and prepare steel surfaces according to SSPC-SP 2, "Hand Tool Cleaning" or SSPC-SP 3, "Power Tool Cleaning." Shop prime steel surfaces in accordance with notes on contract drawings.

F. Holes: Provide holes required for securing other work to structural steel and for passage of other work through steel framing members.

1. Cut, drill, or punch holes perpendicular to steel surfaces. Do not thermally cut bolt holes or enlarge holes by burning.

2. Base-Plate Holes: Cut, drill, mechanically thermal cut, or punch holes perpendicular to steel surfaces.

2.5 SHOP CONNECTIONS

A. Weld Connections: Comply with AWS D1.1 for welding procedure specifications, tolerances, appearance, and quality of welds and for methods used in correcting welding work.

1. Assemble and weld built-up sections by methods that will maintain true alignment of axes without exceeding tolerances of AISC 303 "Code of Standard Practice for Steel Buildings and Bridges" for mill material.

2.6 PROTECTIVE COATING

A. Epoxy Coating: Provide primer and 2 part polyamidoamine epoxy top coating as indicated on the contract drawings.

PART 3 - EXECUTION

3.1 ERECTION

A. Set structural steel accurately in locations and to elevations indicated and according to AISC 303 "Code of Standard Practice for Steel Buildings and Bridges" and AISC 360 "Specification for Structural Steel Buildings."

B. Base and Bearing Plates: Clean concrete- and masonry-bearing surfaces of bond-reducing materials, and roughen surfaces prior to setting base and bearing plates. Clean bottom surface of base and bearing plates.

1. Set base and bearing plates for structural members on leveling tabs, as detailed in the structural drawings.

2. Finger-tighten anchor rods after supported members have been positioned and plumbed using bolts on leveling tabs.

3. Promptly form edges of base plate as detailed in the structural drawings and pour grout so no voids remain. Allow grout to cure to specified 28 day strength and tension anchor bolts in accordance with Section 3.1 - B (4). Comply with manufacturer's written installation instructions for shrinkage-resistant grouts.

4. Torque all anchor bolts to 45 foot-lbs with calibrated torque wrench.

C. Align and adjust various members forming part of complete frame or structure before permanently fastening. Before assembly, clean bearing surfaces and other surfaces that will be

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Structural Steel Framing DEI #50076991 05 12 00 - 5

in permanent contact with members. Perform necessary adjustments to compensate for discrepancies in elevations and alignment.

1. Level and plumb individual members of structure. 2. Make allowances for difference between temperature at time of erection and mean

temperature when structure is completed and in service.

3.2 FIELD CONNECTIONS

A. Weld Connections: Comply with AWS D1.1 for welding procedure specifications, tolerances, appearance, and quality of welds and for methods used in correcting welding work.

1. Comply with AISC 303 "Code of Standard Practice for Steel Buildings and Bridges" and AISC 360 "Specification for Structural Steel Buildings" for bearing, adequacy of temporary connections, alignment, and removal of paint on surfaces adjacent to field welds.

2. Remove backing bars or runoff tabs, back gouge, and grind steel smooth. 3. Assemble and weld built-up sections by methods that will maintain true alignment of axes

without exceeding tolerances of AISC 303 "Code of Standard Practice for Steel Buildings and Bridges" for mill material.

3.3 FIELD QUALITY CONTROL

A. Testing Agency: Owner will engage a special inspector and a qualified independent testing and inspecting agency to inspect field welds and high-strength bolted connections.

B. Welded Connections: Field welds will be visually inspected according to AWS D1.1.

1. In addition to visual inspection, field welds will be tested according to AWS D1.1 and the following inspection procedures, at testing agency's option:

a. Liquid Penetrant Inspection: ASTM E 165. b. Magnetic Particle Inspection: ASTM E 709; performed on root pass and on

finished weld. Cracks or zones of incomplete fusion or penetration will not be accepted.

c. Ultrasonic Inspection: ASTM E 164. d. Radiographic Inspection: ASTM E 94.

C. Correct deficiencies in Work that test reports and inspections indicate does not comply with the Contract Documents.

3.4 REPAIRS AND PROTECTION

A. Touchup Painting: After installation, promptly clean, prepare, and coat field connections, rust spots, and abraded surfaces of shop coated bearing plates and other structural steel.

1. Clean and prepare surfaces by SSPC-SP 2 hand-tool cleaning or SSPC-SP 3 power-tool cleaning.

2. Apply a primer and coatings in accordance with manufacturer’s recommendations and as indicated on contract drawings.

END OF SECTION 05 12 00

This page intentionally left blank

Division 31: Earthwork

www.dewberry.com

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Site Preparation: Clearing and Grubbing DEI# 50076991 31 10 00 - 1

SECTION 31 10 00 SITE PREPARATION: CLEARING AND GRUBBING

PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions, Supplemental General Conditions, and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. The purpose of this Section is to specify the methods and requirements for site preparation, clearing and grubbing.

1.3 REFERENCES

A. Virginia "Erosion and Sediment Control Handbook", latest edition. 1.4 DELIVERY, STORAGE, AND HANDLING

A. Deliver materials to, store at the site, and handle in a manner which will maintain the materials in their original manufactured or fabricated condition until ready for use.

PART 2 - PRODUCTS

Not Applicable. PART 3 - EXECUTION 3.1 TRAFFIC

A. Conduct site clearing operations to ensure minimum interference with roads, streets, walks, businesses, and other adjacent occupied or used facilities. Do not close or obstruct streets, walks or other occupied or used facilities without prior permission from Owner, V.D.O.T., and/or authorities having jurisdiction.

3.2 PROTECTION

A. General: Provide temporary fences, barricades, coverings, or other protection to preserve existing items indicated to remain and to prevent injury or damage to persons or property. Provide protection for adjacent properties as required.

B. Restoration/Repair: Restore damaged items to condition existing prior to start of WORK.

C. Existing Trees/Vegetation: Protect existing trees and vegetation adjacent to the actual WORK

area or borrow area from physical damage. Do not store equipment or materials within tree drip line.

D. Roads and Walks: Keep roads and walks free of dirt and debris at all times.

E. Utility Lines: Protect existing utility lines that are indicated to remain from damage. Notify

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Site Preparation: Clearing and Grubbing DEI# 50076991 31 10 00 - 2

ENGINEER immediately of damage to or an encounter with any unknown existing utility lines. CONTRACTOR shall be responsible for the repairs of damage to existing utility lines that are indicated or made known to CONTRACTOR prior to start of clearing and grubbing operations. When utility lines which are to be removed are encountered within the area of operations, CONTRACTOR shall notify ENGINEER and OWNER and Utility Owner within 7 days time to minimize interruption of the service.

3.3 EROSION/SEDIMENT CONTROL

A. Provide appropriate erosion and sediment control measures for all off-site borrow areas in full compliance with the Virginia Erosion and Sediment Control Handbook and regulations of the local jurisdiction. CONTRACTOR shall be solely responsible for all borrow sites outside of the Project area.

3.4 CLEARING

A. Clearing shall consist of the felling, trimming, and cutting of trees into sections and the satisfactory disposal of the trees and other vegetation designated for removal, including downed timber, snags, brush, and rubbish occurring within the areas to be cleared. Cut off flush with or below the original ground surface trees, stumps, roots, brush, and other vegetation in areas to be cleared, except for trees and vegetation indicated or directed to be left standing. CONTRACTOR shall coordinate all clearing with OWNER prior to proceeding.

3.5 TREE REMOVAL

A. Where indicated or directed by OWNER, trim designated trees or remove designated trees and stumps and grub roots.

3.6 GRUBBING

A. Remove and dispose of roots larger than 3 inches in diameter, matted roots, and stumps from the indicated grubbing areas. Excavate this material together with logs, organic and metallic debris, brush, and refuse and remove to a depth of not less than 18 inches below the original soil surface in areas indicated to be grubbed and in areas indicated as construction areas for this Project. Fill depressions made by grubbing with suitable material and compact in accordance with the requirements of the Contract Documents to make the new surface conform with the existing adjacent surface of the ground.

3.7 DISPOSAL OF CLEARED AND GRUBBED MATERIALS

A. Nonsalable Materials: Disposal shall be CONTRACTOR's responsibility. 3.8 STORING MATERIALS

A. Strip and stockpile topsoiling material and other cleared materials that will be reused in the WORK.

3.9 EXISTING IMPROVEMENTS/FACILITIES

A. Remove existing improvements, both above-grade and below-grade to extent indicated or as otherwise required to permit new construction and provide for proper disposal off-site. Existing improvements and facilities such as mailboxes, signs, ornamental or decorative items, etc. that require temporary removal to permit new construction shall be promptly replaced and/or restored to the location and condition prior to construction. Improvements and facilities that are damaged by the CONTRACTOR during the course of construction shall be promptly replaced at the

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Site Preparation: Clearing and Grubbing DEI# 50076991 31 10 00 - 3

CONTRACTOR's expense. 3.10 SALVABLE ITEMS

A. No salvable items are anticipated for this project. 3.11 FUGITIVE DUST

A. Control air pollution caused by dust and dirt; comply with governing regulations. 3.12 FILLING

A. Fill depressions and voids resulting from site clearing operations. Comply with the requirements of Specification Section 312000, “Earth Moving.”

3.13 GRADING

A. Grade ground surface to conform to required contours and to provide positive surface drainage away from the WORK or borrow area.

3.14 DISPOSAL

A. Dispose of waste materials, including trash and debris, and excess topsoil, legally off-site. 3.15 BURNING

A. Burning of waste materials is prohibited for this project.

END OF SECTION 31 10 00

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Earth Moving DEI# 50076991 31 20 00 - 1

SECTION 31 20 00 EARTH MOVING

PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions, Supplemental General Conditions, and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Prior to beginning construction, the Geotechnical Engineer should evaluate the subgrade soils for suitability based on observations of proofrolling with a loaded dump truck or other method considered acceptable to the Geotechnical Engineer. Fill meeting the requirements herein shall then be placed to the grade shown.

1.3 REFERENCE SECTIONS

A. Section 02 41 19 – Site Demolition

B. Section 33 05 00 – Earthwork: Utilities

1.4 DEFINITIONS

A. Excavation: Removal of material encountered to subgrade elevations and the reuse or disposal of materials removed.

B. Subgrade: The uppermost surface of an excavation or the top surface of a fill or backfill

immediately below subbase, drainage fill, or topsoil materials.

C. Borrow: Soil material obtained off-site when sufficient approved soil material is not available from excavations.

D. Subbase Course: The layer placed between the subgrade and surface of a pavement or walk.

E. Design Subgrade: Elevation of bearing for foundations, bottom of porous fill beneath slabs on

grade (4" below bottom of slab), bottom of turn down slabs, and bottom most portion of stairs and ramps.

F. Drainage Fill: Course of washed granular material supporting slab-on-grade placed to cut off

upward capillary flow of pore water.

G. Unauthorized Excavation: Removing materials beyond indicated subgrade elevations or dimensions without direction by the Engineer. Unauthorized excavation, as well as remedial work directed by the Engineer, shall be at the Contractor's expense.

H. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and

electrical appurtenances, or other man-made stationary features constructed above or below ground surface.

I. Utilities: Include on-site underground pipes, conduits, ducts, and cables, as well as underground

services within building lines.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Earth Moving DEI# 50076991 31 20 00 - 2

1.5 SUBMITTALS

A. General: Submit the following according to the Conditions of the Contract and Division 1 Specification Sections.

B. Test Reports: In addition to test reports required under field quality control, submit the following:

1. Laboratory analysis of each soil material proposed for fill and backfill from on-site and borrow sources.

2. One optimum moisture-maximum density curve for each soil material. 3. Report of actual unconfined compressive strength and/or results of bearing tests of each

stratum tested. C. Submit excavation support system design and details for trench excavation.

1.6 QUALITY ASSURANCE

A. Codes and Standards: Perform earthwork complying with requirements of authorities having jurisdiction. These include, but are not limited to, University of Virginia, City of Charlottesville, Virginia Department of Conservation and Recreation, and the State of Virginia.

B. Testing and Inspection Service: Owner shall employ a qualified independent geotechnical

engineering testing agency to classify proposed on-site and borrow soils to verify that soils comply with specified requirements and to perform required field and laboratory testing.

1.7 PROJECT CONDITIONS

A. Existing Utilities: Do not interrupt existing utilities serving facilities occupied by the Owner or others except when permitted in writing by the Engineer and then only after acceptable temporary utility services have been provided. 1. Provide a minimum 10 day notice to the University and receive written notice to proceed

before interrupting any utility.

B. Demolish and completely remove from site existing underground utilities indicated to be removed. If utilities cannot be removed due to existing field conditions they shall be filled with flowable fill (minimum 300psi) and noted as “Abandoned” on as-built drawings. Coordinate with utility companies to shutoff services if lines are active.

C. Excavation support system design and details for trench excavation, shall be sealed and signed

by a professional engineer licensed in the Commonwealth of Virginia, copy of design shall be filed with ENGINEER.

PART 2 - PRODUCTS 2.1 SOIL MATERIALS

A. General: Provide approved borrow soil materials from off-site when sufficient approved soil materials are not available from excavations. Contractor is responsible for locating appropriate off-site borrow areas.

B. Satisfactory Soil Materials and Engineering Fill: Select material classifying CL, ML, SC, SM, SP,

SW, GC, GM, GP, or GW in accordance with ASTM D 2487. The maximum particle size should not exceed 4 inches. Fill should be free of debris, waste, frozen materials, vegetation, and any

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Earth Moving DEI# 50076991 31 20 00 - 3

other deleterious matter. Off-site borrow materials should have a CBR value no less than 6 percent.

C. Backfill and Fill Materials: Satisfactory soil materials.

D. Porous Fill: VDOT # 57 stone.

E. Filtering Material: Evenly graded mixture of natural or crushed gravel or crushed stone and

natural sand, with 100 percent passing a 1-1/2-inch sieve and 0 to 5 percent passing a No. 50 sieve.

F. Flowable Fill: Comply with ACI 229 (300 psi minimum @ 28 days).

G. Aggregate Base: VDOT 21B.

2.2 GEOTEXTILE FABRIC

A. Medium Duty Geotextile Fabric as follows: 1. Weight: 6.0 oz/sy as per ASTM D-3776-79. 2. Grab Strength: 300 lbs as per ASTM D-4632-86. 3. Grab Elongation: 15% as per ASTM D-4632-86. 4. Trapezoid Tear Strength: 115 lbs as per ASTM D-4533-85. 5. Mullen Burst Strength: 600 psi as per ASTM D-3786-87. 6. Puncture Strength: 145 lbs as per ASTM D-4833-88. 7. Wide Width Strip Tensile: 200x230 lbs/in as per ASTM D-4595-86. 8. Wide Width Strip Elongation: 15x15 % as per ASTM D-4595-86. 9. Thickness: 25 mils as per ASTM D-1777-64. 10. Permittivity: .1 sec(-1) as per ASTM D-4491-85. 11. Water Flow Rate: 9.2 gal/min/sf as per ASTM D-4491-85. 12. Apparent Opening Size: 30-70 U.S. Std Sieve as per ASTM D-4751-87. 13. Ultraviolet Stability: 90% as per ASTM D-4355-84.

PART 3 - EXECUTION 3.1 PREPARATION

A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earthwork operations.

B. Protect subgrades and foundation soils against freezing temperatures or frost. Provide

protective insulating materials as necessary.

C. Provide erosion control measures to prevent erosion or displacement of soils and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways.

D. Prior to proceeding with construction, all topsoil and other deleterious, non-soil materials shall be

stripped from proposed construction area. Stripping shall extend at least 5 feet horizontally beyond building limits, and stripping of unsatisfactory soils shall be as identified by the Geotechnical Engineer.

E. Subgrades which are to support slabs, pavements, or compacted fill shall be proofrolled using a

Scraper (i.e., Pan) or a loaded dump truck having an axle weight of at least 10 tons to identify areas of localized soft soil or unsuitable soil. Any soft or unsuitable material encountered during

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Earth Moving DEI# 50076991 31 20 00 - 4

proofrolling shall be removed and replaced with engineered fill. The Geotechnical Engineer shall observe all proofrolling operations.

3.2 DEWATERING

A. Prevent surface water and subsurface or ground water from entering excavations, from ponding on prepared subgrades, and from flooding Project site and surrounding area.

B. Protect subgrades and foundation soils from softening and damage by rain or water

accumulation.

C. Dewatering disposal shall be in accordance with Erosion and Sediment Control permit. 3.3 EXCAVATION

A. Explosives: Do not use explosives.

B. Classified Excavation: See specification Section 330500, “Earthwork: Utilities” for excavation classifications.

3.4 EXCAVATION FOR STRUCTURES

A. Excavate to indicated elevations and dimensions within a tolerance of plus or minus 0.10 foot. Extend excavations a sufficient distance from structures for placing and removing concrete formwork, installing services and other construction, and for inspections. 1. Excavations for Footings and Foundations: Do not disturb bottom of excavation.

Excavate by hand to final grade just before placing concrete reinforcement. Trim bottoms to required lines and grades to leave solid base to receive other work.

2. Excavation for Mechanical or Electrical Appurtenances: Excavate to elevations and dimensions indicated within a tolerance of plus or minus 0.10 foot. Do not disturb bottom of excavations intended for bearing surface.

3.5 APPROVAL OF SUBGRADE

A. Notify Engineer when excavations have reached required subgrade.

B. When Engineer determines that unforeseen unsatisfactory soil is present, continue excavation and replace with compacted backfill or fill material as directed.

C. Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated water, or

construction activities, as directed by the Engineer. 3.6 UNAUTHORIZED EXCAVATION

A. Fill unauthorized excavation under foundations or wall footings by extending indicated bottom elevation of concrete foundation or footing to excavation bottom, without altering required top elevation. Lean concrete fill or flowable fill may be used to bring elevations to proper position.

3.7 STORAGE OF SOIL MATERIALS

A. Stockpile excavated materials acceptable for backfill and fill soil materials, including acceptable borrow materials. Stockpile soil materials without intermixing. Place, grade, and shape stockpiles to drain surface water. Cover to prevent wind-blown dust.

3.8 BACKFILL

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Earth Moving DEI# 50076991 31 20 00 - 5

A. Backfill excavations promptly, but not before completing the following:

1. Acceptance of construction below finish grade including, where applicable, damp-proofing, waterproofing, and perimeter insulation.

2. Surveying locations of underground utilities for record documents. 3. Testing, inspecting, and approval of underground utilities. 4. Concrete form-work removal. 5. Removal of trash and debris from excavation. 6. Removal of temporary shoring and bracing, and sheeting. 7. Installing permanent or temporary horizontal bracing on horizontally supported walls.

3.9 SUBSURFACE DRAINAGE BACKFILL

A. Subsurface Drain: Place a layer of filter fabric around perimeter of drainage trench or at footing, as indicated. Place a 6-inch compacted course of filtering material on filter fabric to support drainage pipe. After installing and testing, encase drainage pipe in a minimum of 6 inches of compacted filtering material and wrap in filter fabric, overlapping edges at least 6 inches.

B. Drainage Backfill: Place and compact drainage backfill of filtering material over subsurface

drain, in width indicated, to within 18 inches of final subgrade. Overlay drainage backfill with one layer of filter fabric, overlapping edges at least 6 inches.

C. Impervious Fill: Place and compact impervious fill material over drainage backfill to final

subgrade. 3.10 FILL

A. Preparation: Remove vegetation, topsoil, debris, wet, and unsatisfactory soil materials, obstructions, and deleterious materials from ground surface prior to placing fills. 1. Plow strip, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so fill

material will bond with existing surface.

B. When subgrade or existing ground surface to receive fill has a density less than that required for fill, break up ground surface to 8 inches, pulverize, moisture-condition or aerate soil and recompact to required density.

C. Place fill material in layers to required elevations for each location listed below.

1. Under grass, use satisfactory excavated or borrow soil material. 2. Under walks and pavements, use aggregate base, or satisfactory excavated or borrow

soil material. 3. Under steps and ramps, aggregate base. 4. Under building slabs, use porous fill. 5. Under footings and foundations, use engineered fill, aggregate base, or flowable fill. 6. Behind below-grade walls, use engineered fill or porous fill.

3.11 MOISTURE CONTROL

A. Uniformly moisten or aerate subgrade and each subsequent fill or backfill layer before compaction to within 3 percent of optimum moisture content. 1. Do not place backfill or fill material on surfaces that are muddy, frozen, or contain frost or

ice. 2. Remove and replace, or scarify and air-dry satisfactory soil material that is too wet to

compact to specified density. a. Stockpile or spread and dry removed wet satisfactory soil material. b. If excavation must remain open overnight or rainfall becomes imminent while the

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Earth Moving DEI# 50076991 31 20 00 - 6

bearing soils are exposed, place a 1 to 3 inch thick “mud mat” of lean concrete be placed on the bearing soils before the placement of reinforcing steel.

3.12 COMPACTION

A. Place backfill and fill materials in layers not more than 8 inches in loose depth for material compacted by heavy compaction equipment, and not more than 4 inches in loose depth for material compacted by hand-operated tampers.

B. Place backfill and fill materials evenly on all sides of structures to required elevations. Place

backfill and fill uniformly along the full length of each structure.

C. Percentage of Maximum Dry Density Requirements: Compact soil to not less than the following percentages of maximum dry density according to ASTM D 698: 1. Under structures, slabs, and steps compact fill or backfill to 95 percent maximum dry

density. 2. Under lawn compact each layer of backfill or fill material at 90 percent maximum dry

density. 3.13 GRADING

A. General: Uniformly grade areas to a smooth surface, free from irregular surface changes. Comply with compaction requirements and grade to cross sections, lines, and elevations indicated. 1. Provide a smooth transition between existing adjacent grades and new grades. 2. Cut out soft spots, fill low spots, and trim high spots to conform to required surface

tolerances.

B. Site Grading: Slope grades to direct water away from buildings and to prevent ponding. Finish subgrades to required elevations within the following tolerances: 1. Lawn or Unpaved Areas: Plus or minus 0.10 foot. 2. Walks: Plus or minus 0.10 foot.

C. Grading Inside Building Lines: Finish subgrade to a tolerance of ½ inch when tested with a

10-foot straightedge. 3.14 POROUS FILL

A. Under slabs-on-grade, place porous fill course on prepared subgrade. 1. Compact porous fill to required cross sections and thickness.

3.15 FIELD QUALITY CONTROL

A. Testing Agency Services: Allow testing agency to inspect and test each subgrade and each fill or backfill layer. Do not proceed until test results for previously completed work verify compliance with requirements. 1. Perform field in-place density tests according to ASTM D 6938, (nuclear method)

provided that calibration curves are periodically checked and adjusted to correlate to tests performed using ASTM D 1556. With each density calibration check, check the calibration curves furnished with the moisture gages according to ASTM D 6938. a. When field in-place density tests are performed using nuclear methods, make

calibration checks of both density and moisture gages at beginning of work, on each different type of material encountered, and at intervals as directed by the Engineer.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Earth Moving DEI# 50076991 31 20 00 - 7

2. Footing Subgrade: The Geotechnical Engineer shall observe all subgrades and determine suitability to support design loads.

3. Paved and Building Slab Areas: At subgrade and at each compacted fill and backfill layer, perform at least one field in-place density test for every 2,500 sq. ft. or less of paved area or building slab, but in no case fewer than three tests.

4. Foundation Wall Backfill: In each compacted backfill layer, perform at least one field in-place density test for each 100 feet or less of wall length, but no fewer than two tests along a wall face.

B. When testing agency reports that subgrades, fills, or backfills are below specified density, scarify and moisten or aerate, or remove and replace soil to the depth required, recompact and retest until required density is obtained.

3.16 PROTECTION

A. Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion. Keep free of trash and debris.

B. Repair and re-establish grades to specified tolerances where completed or partially completed

surfaces become eroded, rutted, settled, or lose compaction due to subsequent construction operations or weather conditions. 1. Scarify or remove and replace material to depth directed by the Engineer; reshape and

recompact at optimum moisture content to the required density.

C. Settling: Where settling occurs during the Project correction period, remove finished surfacing, backfill with additional approved material, compact, and reconstruct surfacing. 1. Restore appearance, quality, and condition of finished surfacing to match adjacent work,

and eliminate evidence of restoration to the greatest extent possible. 3.17 DISPOSAL OF SURPLUS AND WASTE MATERIALS

A. Disposal: Remove surplus satisfactory soil and waster material, including unsatisfactory soil, trash, and debris, and legally dispose of it off the Owner’s property. Contractor is responsible for all costs associated with disposal and for all erosion and sediment control measures at off-site disposal areas.

END OF SECTION 31 20 00

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Dewatering DEI# 50076991 31 23 19 - 1

SECTION 31 23 19 DEWATERING

PART 1 – GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions, Supplemental General Conditions, and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

Keep all excavations and site structures free from water during construction.

1.3 REFERENCE SECTIONS

A. Section 31 25 00 – Erosion and Sediment Control

1.4 RELATED SECTIONS

A. Intent: The provisions and intent of the AGREEMENT, including the General Conditions, Supplemental General Conditions, and other requirements of the Contract Documents apply to the WORK as specified in this section. WORK related to this Section is described throughout the Specifications.

1.5 SUBMITTALS

A. Dewatering Plan: CONTRACTOR shall submit, for ENGINEER'S review, Drawings and data showing its proposed plan and required equipment for dewatering of all WORK areas. The Drawings and data shall include the planned method of dewatering excavations, wells, well points, sumps, collection and discharge lines, standby units proposed, and protective fills and ditches required for control of ground water, leachate and surface water.

B. Schedule: The plan for dewatering shall be submitted within 7 days before the start of work. CONTRACTOR shall furnish such other information as may be required for ENGINEER'S complete understanding and analysis of the dewatering, grading and excavation plan.

C. Engineer's Approval: If, during the progress of the WORK, it is determined by ENGINEER that the

dewatering system grading and excavation Drawings, text and proposed methodology are inadequate, or that CONTRACTOR'S plan of construction is inoperative, CONTRACTOR shall, at its sole expense, furnish, install and operate such additional dewatering equipment and make such changes in other features of the Dewatering Plan or operation as may be necessary to perform the WORK in a manner satisfactory to ENGINEER.

PART 2 - PRODUCTS

Not Applicable PART 3 - EXECUTION

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Dewatering DEI# 50076991 31 23 19 - 2

3.1 METHODS

A. Method: Dewatering can be accomplished by ordinary pumping methods, by the use of underdrains or deep well points, whichever will produce the above results. In order to assure the continuous dewatering, duplicate units of the selected system incorporated with emergency power should be employed so that a reliable operation may be obtained.

B. Location: All site WORK areas shall be dewatered where surface, leachate and/or ground water

flows, if any, will adversely impact construction.

C. Maintenance: All permanent improvements shall be constructed in areas free from water. Construct and maintain all permanent or temporary slopes, dikes, levees, drainage ditches, sumps, and observation wells necessary for the removal of water from WORK areas. Design, furnish, install, maintain, and operate all necessary pumping and other dewatering equipment required for dewatering the various site WORK areas and for keeping the foundation and other areas free from water from any and all sources.

D. Schedule: All dewatering shall be performed in advance of grading, excavation and/or filling. The

dewatering shall be accomplished in a manner that will prevent loss of fines from the foundation, will maintain stability of all excavated slopes and bottoms of excavations, and will permit all construction operations to be performed in the dry. Dewatering of excavations shall be performed to the extent required to permit placement of compacted fill materials in the dry and to prevent sloughing of the excavation side slopes.

E. Requirements: Lower the ground water level a minimum of 3 feet below sub-foundation grade or as

recommended by Geotechnical Engineer prior to sub-foundation preparation and placement of foundation materials. During the placement and compaction of fill or bedding materials, the water level at every point within the limits of fills being placed shall be maintained a minimum of 3 feet or greater or as recommended by Geotechnical Engineer below fill placement level in order that the required compaction can be achieved.

Where conditions are such that running or standing water occur in the trench bottom or the soil in the trench bottom displays a "quick" tendency, the water shall be removed by pumps and suitable means such as well points or previous underdrain bedding until the pipe has been installed and the backfill has been placed to a sufficient height to prevent pipe flotation. No installation will be permitted in trenches unless the subgrade is dry. If, in the opinion of the ENGINEER, the CONTRACTOR has failed to obtain an absolutely dry trench bottom by use of all known methods of trench dewatering, the ENGINEER may then order the CONTRACTOR to excavate below grade and place sufficient selected fill material over the trench bottom. Additional excavation and fill shall meet the requirements of Section 33 05 00.

3.2 PROTECTION OF FOUNDATIONS AND EXISTING FACILITIES

A. Contingency: Furnish standby equipment of sufficient size and capacity to insure continuous operation of the dewatering system. All damage to structures due to a failure of dewatering equipment shall be repaired by CONTRACTOR at its expense, to the satisfaction of ENGINEER. CONTRACTOR may consider the use of recharge systems or other methods of protection of existing facilities.

B. Completion: Dewatering shall be maintained in the WORK areas for as long as is necessary for the

completion of WORK. Upon completion of the dewatering and control of water operation, all temporary dewatering facilities shall be removed in a manner satisfactory to ENGINEER.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Dewatering DEI# 50076991 31 23 19 - 3

3.3 DISPOSAL OF DRAINAGE WATER

A. Effluent from dewatering operations shall be filtered or passed through an approved sediment trapping device, or both, and discharged in a manner that does not adversely affect flowing streams or off-site property (MS-16). An adequately sized silt/sediment bag is often used. Be sure the pumping rate will not overwhelm the bag, forcing muddy water through. Concentrated runoff (such as dewater pump discharge) shall not flow down denuded slopes unless contained within an adequate temporary or permanent channel, flume or slope drain (MS-8).

END OF SECTION 31 23 19

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Erosion and Sediment Control DEI# 50076991 31 25 00 - 1

SECTION 31 25 00 EROSION AND SEDIMENT CONTROL

PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions, Supplemental General Conditions, and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Compliance: This WORK shall be performed in accordance with the erosion and sediment control plan of the construction Drawings and the details provided therein, and as described, detailed and required by the Virginia Department of Conservation and Recreation Division of Soil and Water Conservation in the most recent edition of the Virginia Erosion and Sediment Control Handbook.

B. Details: In the event a detailed plan is not shown, CONTRACTOR shall comply with the

requirements of the local authority and provide a plan if required by that authority. 1.3 REFERENCES

A. Virginia Erosion and Sediment Control Handbook, latest edition. 1.4 SUBMITTALS

A. Temporary Seed Mixture: Provide written notification as to the temporary seed mixture to be used.

1.5 MAINTENANCE

A. Maintain all erosion and sediment control structures to be utilized during the life of the Project in compliance with the regulations of the Division of Soil and Water Conservation until vegetative cover is acceptable to the Division's field personnel and approval acceptance is received.

B. The General Contractor shall maintain all Erosion and Sediment Controls while the UVA

Landscape Department is installing plantings, vegetation, grass, mulch, etc.

PART 2 - PRODUCTS 2.1 STORM DRAIN INLET PROTECTION

A. Sediment deposits shall be removed when deposits reach approximately one-half the design depth of the trap.

PART 3 - EXECUTION 3.1 EROSION AND SEDIMENT CONTROL MEASURES

A. Measures: Silt fence, straw bales, construction entrance, check dams, temporary vegetation, and all other items for erosion and sediment control shall be constructed as directed by the

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Erosion and Sediment Control DEI# 50076991 31 25 00 - 2

ENGINEER or in the locations shown or designated on the Drawings in accordance with the details provided.

B. Schedule: CONTRACTOR shall institute the erosion and sediment control program as a part of

clearing and grubbing, and prior to rough grading. The initial program shall include, however is not limited to, the installation of silt fences, staked straw bales, diversion ditches and/or gravel weirs as shown on erosion and sediment control Drawing at the limits of clearing and grubbing where silt-carrying surface water runoff may be diverted and/or filtered prior to leaving the disturbed area.

C. Temporary Seeding: Establish temporary cover for erosion control by seeding and/or mulching

graded areas which may otherwise be exposed for a period greater than 30 days. This should be accomplished as soon as rough grading WORK is done. Begin temporary seeding within 72 hours after earth disturbance.

D. Pipe Outfalls: All pipe outfall areas disturbed by construction shall be protected with non-

erodible materials conforming to the Virginia Erosion and Sediment Control Handbook.

E. Maintenance: All siltation and erosion control devices installed during the course of construction shall be maintained in proper working order at all times, and shall not be removed until final stabilization of all disturbed areas or at the direction of the ENGINEER.

3.2 CLEANING OF ROADS AND STREETS

A. CONTRACTOR shall maintain a vehicle wash rack or gravel bed at all vehicle egress areas. All vehicles shall be thoroughly cleaned of mud and silt before leaving the construction site to avoid tracking mud and silt onto roads, streets, and highways. In the event that tracking does occur, CONTRACTOR shall immediately clean the street or road of all debris, mud or silt and shall pay all damages resulting therefrom. A daily survey of the condition of the adjacent streets and roads shall be made and recorded in the field log along with daily cleanup of the streets of the tracking from the site onto roads, alleys, parking lots, and highways.

3.3 PROTECTION OF STORMWATER SYSTEMS

A. Stormwater structures which will receive runoff from the construction shall be protected from the buildup of mud or silt as outlined by the Virginia Erosion and Sediment Control Handbook or as directed by ENGINEER.

END OF SECTION 31 25 00

Division 32: Exterior Improvements

www.dewberry.com

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Asphalt Paving DEI# 50076991 32 12 16 - 1

SECTION 32 12 16

ASPHALT PAVING

PART 1 - GENERAL

1.1 SUMMARY A. The Contractor shall be responsible for repairing asphalt concrete pavement and

preparing subgrade in those areas where improvements are proposed as shown on the plans.

1.2 REFERENCES A. Where differences between building codes, state laws, local ordinances, industry

standards, utility company regulations and the Contract Documents occur, the most stringent shall govern. The Contractor shall promptly notify the Owner’s Representative in writing of any such difference.

B. Should the Contractor perform any work that does not comply with local codes, laws and ordinances, industry standards or other governing regulations, the Work shall be corrected on noncompliance deficiencies with the Contractor bearing all costs.

C. Codes and Standards: Comply with Virginia Department of Transportation standard specifications "Road and Bridge Specifications", latest edition.

D. Specifications listed below are included by reference and are hereby incorporated into the Contract Documents.

1. University of Virginia; Facilities Design Guidelines

2. Drawings and general provisions of Contract, including General Conditions, Supplemental General Conditions, and Division 01 Specification sections, apply to work of this section.

3. Virginia Department of Transportation (VDOT) – Road and Bridge Specifications

1.3 SITE CONDITIONS A. Weather Limitations: Apply prime and tack coats when ambient temperature is above 50

degrees F. (10 degrees C), and when temperature has not been below 35 degrees F. (1 degree C.) for 12 hours immediately prior to application. Do not apply when base is wet or contains an excess of moisture.

B. Construct asphalt concrete surface course when atmospheric temperature is above 40 degrees F. (4 degrees C.), and when base is dry. Base course may be placed when air temperature is above 30 degrees F. (-1 degree C.) and rising.

C. Grade Control: Establish and maintain required lines and elevations.

PART 2 - PRODUCTS

2.1 MATERIALS A. Asphalt concrete paving and base course as shown on drawings. Contractor shall

match existing pavement for repairs. Contractor shall incorporate a pea gravel surface where necessary to match existing pavement.

B. General: Use locally available materials and gradations which exhibit a satisfactory record of previous installations. Materials shall meet requirements of VDOT "Road and Bridge Specifications."

C. Pavement-Marking Paint: Alkyd-resin type, ready mixed, complying with FS TT-P-115, Type I, or AASHTO M-248, Type N, Color: White.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Asphalt Paving DEI# 50076991 32 12 16 - 2

PART 3 - EXECUTION Materials placement shall be in accordance with VDOT "Road and Bridge Specifications."

3.1 SURFACE PREPARATION A. Remove loose material from compacted subgrade surface immediately before applying

herbicide treatment or prime coat. Proof roll prepared subgrade surface to check for unstable areas and areas requiring additional compaction under the observation of the Geotechnical Engineer. Notify Owner of unsatisfactory conditions. Do not begin paving work until deficient subgrade areas have been corrected and are ready to receive paving.

3.2 PLACING MIX A. Place asphalt concrete mixture on prepared surface, spread and strike-off. Place

inaccessible and small areas by hand. Place each course to required grade, cross-section, and compacted thickness.

B. Joints: Make joints between old and new pavements, or between successive days' work, to ensure continuous bond between adjoining work. Construction joints to have same texture, density and smoothness as other sections of asphalt concrete course. Clean contact surfaces and apply tack coat. Place asphalt within 24 hours of applying tack coat.

3.3 ROLLING A. Begin rolling when mixture will bear roller weight without excessive displacement.

Compact mixture with hot hand tampers or vibrating plate compactors in areas inaccessible to rollers.

B. Patching: Remove and replace paving areas mixed with foreign materials and defective areas. Cut-out such areas and fill with fresh, hot asphalt concrete. Compact by rolling to maximum surface density and smoothness.

C. Protection: After final rolling, do not permit vehicular traffic on pavement until it has cooled and hardened.

D. Erect barricades to protect paving from traffic until mixture has cooled enough not to become marked.

3.4 FIELD QUALITY CONTROL A. Test in-place asphalt concrete courses for compliance with requirements for thickness,

compaction, and surface smoothness. Test in-place base course for compliance with requirements for thickness and compaction. Repair or remove and replace unacceptable paving as directed by Architect.

3.5 AGGREGATES AND PAVING A. Open Pavement Cuts: All open cuts through pavement on existing dedicated street shall

be replaced with:

- 10” VDOT 21 A material + 3” BM-25.0 base + 2” SM-9.5 surface course for roadways,

- 6” VDOT 21A material + 3” BM-25.0 base + 1.5” SM-9.5 surface course for Driveways and Surface Roadways

- 6” VDOT 21A material + 2” SM-9.5 surface course for Parking Lots

END OF SECTION 32 12 16

Division 33: Utilities

www.dewberry.com

This page intentionally left blank

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Earthwork: Utilities DEI# 50076991 33 05 00 - 1

SECTION 33 05 00 EARTHWORK: UTILITIES

PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions, Supplemental General Conditions, and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. The CONTRACTOR shall furnish all labor and equipment for excavation, installation, backfill,

and testing of all utility lines and appurtenances as shown on the Drawings and specified herein. This section specifies excavation and backfill for all underground utilities.

1.3 REFERENCE SECTIONS

A. Section 02 41 19 – Site Demolition

B. Section 31 20 00 – Earth Moving 1.4 REFERENCES

A. American Society of Testing and Materials (ASTM) B. VDOT Road and Bridge Specifications C. Occupational Safety and Health Administration Regulations (OSHA)

1.5 SUBMITTALS

A. Submit Excavation support system design and details for trench excavation. Excavation support system shall be signed and sealed by a Virginia Licensed Professional Engineer.

1.6 COORDINATION

A. The CONTRACTOR shall be responsible for coordinating all excavations with the following:

All planned excavations on University property require a University "Request for Excavation Permit”, shall be completed and submitted to the CAM and the Utilities Department within two hours of contacting MISS UTILITY. The University’s "Request for Excavation Permit” notifies only the University of planned excavation and does not result in notification of MISS UTILITY.

The University is a subscriber to the "MISS UTILITY” underground utility location and notification

system. In addition to University and MISS UTILITY requirements, the City of Charlottesville (434-971-3320) also requires that requests for excavation permits be submitted for City maintained streets or sidewalks. Any excavation of state roads requires notification and coordination with the Virginia Department of Transportation (VDOT). All planned excavations require notification of MISS UTILITY per state and federal regulations. It is the responsibility of the contractor, to notify MISS UTILITY at 1-800-552-7001 of the planned excavation and at 1-800-552-3120 to obtain subsequent verification that utilities have been marked. Excavation shall not proceed without a University Excavation Permit and the completion of the above requirements.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Earthwork: Utilities DEI# 50076991 33 05 00 - 2

1.7 QUALITY ASSURANCE

A. Standards: Testing of backfill material shall comply with the following standards. ASTM D6938 Standard Test Methods for In-Place Density and Water Content of Soil and Soil-

Aggregate by Nuclear Methods (Shallow Depth). ASTM D698 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using

Standard Effort (12,400 ft-lbf/ft3 (600 kN-m/m3)).

B. Excavation support system design and details for trench excavation, shall be sealed and signed by a professional engineer licensed in the Commonwealth of Virginia, copy of design shall be filed with ENGINEER.

PART 2 - PRODUCTS 2.1 BACKFILL AND PIPE BEDDINGS MATERIALS:

A. All new pipe installed shall use crushed aggregate to meet the requirements of Aggregate Standard size No.10 as defined by VDOT standard specifications for pipe bedding. All new piping in paved area shall use backfill to meet the requirements of Aggregate Standard size No.21B as defined by VDOT standard specifications. All new pipe shall be backfilled in accordance with Section 31 20 00 – Earth Moving.

PART 3 - EXECUTION 3.1 EXCAVATION

A. General: All excavation shall be performed in accordance with the current VOSH and OSHA guidelines and all other regulatory authorities having jurisdiction. Provide adequate equipment to comply with VOSH and OSHA regulations. All excavation may be open-cut type except where otherwise shown on the Drawings. The slope of the sides of the excavation shall be kept as nearly vertical as possible consistent with the types of materials encountered. A clear area shall be maintained a sufficient distance back from the top edge of the excavation to avoid overloading which may cause slides, cave-ins or shifting of the pipe. All damage to pipes or structures occurring through settlements, heaving, water or earth pressures, slides, cave-ins or other causes shall be repaired by CONTRACTOR at its expense. CONTRACTOR has the option of shoring, including sheet piling, which shall be installed during excavation where required for the protection of workmen, banks, roadways and adjacent paving, structures, and utilities or as directed by ENGINEER.

B. Excavation Classification: Excavation will be classified as Common Excavation or Rock Excavation in accordance with the following definitions or will be designated as classified.

C. Common Excavation shall be defined as the excavation of all materials that can be excavated,

transported and unloaded by the use of heavy ripping equipment and wheel tractor-scrapers with pusher tractors or that can be excavated and dumped in place or loaded onto hauling equipment by means of excavators having a rated capacity of one cubic yard and equipped with attachments (such as shovel, bucket, backhoe, dragline or clam shell) appropriate to the character of the materials, and the site conditions. Common Earth Excavation includes removal and disposal of pavements and other obstructions visible to ground surface, underground structures and utilities indicated to be demolished and removed, material of any classification indicated in data on subsurface conditions, and other materials encountered that are not classified as rock excavation.

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Earthwork: Utilities DEI# 50076991 33 05 00 - 3

D. Rock Excavation shall be defined as any material in beds, ledges, unstratified masses, and conglomerate deposits and boulders of rock material exceeding 1 cu. yd. that cannot be removed by rock excavating equipment equivalent to late-model, track mounted hydraulic excavator; equipped with a 42-inch wide, short-tip-radius rock bucket; rated at not less than 120-hp flywheel power with bucket-curling force not less than 25,000 lbf and stick-crowd force of not less than 18,700 lbf; measured according to SAE J-1179, without systematic drilling, ram hammering or ripping (blasting not permitted).

E. Protection: Protect existing structures, utilities, sidewalks, pavements, and other facilities in

areas of work. Barricade open excavations and provide warning lights. Maintain service to/from existing homes, businesses, and facilities.

F. Shoring or Sheeting: Shoring or sheeting shall be removed as the WORK progresses, unless

left in place by written order of ENGINEER. Sheeting or shoring to remain after completion of the project shall be cut a minimum of 1’ below finished grade.

G. Trench Excavation: CONTRACTOR shall comply with all local, state and federal guidelines

when excavating trenches. The width of the trench at and below the top of the pipe shall not exceed the outside diameter of the pipe plus 24 inches, except the minimum trench width shall be 36 inches in all cases. The width of the trench above the top of the pipe may be as wide as necessary for sheeting and bracing and the proper performance of the WORK.

H. Sidewalls: The sidewalls of pipe trenches shall be as nearly vertical as practicable to a point

above the top of the pipe.

I. Over-excavation: Trenches shall be excavated to the design grade of the pipe to provide uniform bearing and support along the entire length of pipe. Care shall be taken not to over excavate. Over excavation of otherwise suitable material shall be replaced with suitable material as directed by ENGINEER. The cost of such fill shall be borne by CONTRACTOR.

J. Rock: Where the bottom of the pipe trench occurs in rock, the rock shall be excavated to a

minimum of 6 inches for pipes 24-inches in diameter and smaller and 9 inches for pipes 30-inches in diameter and larger, below the trench depth indicated on the Drawings or specified elsewhere. Over depths in rock excavation and unauthorized over depths shall be backfilled with VDOT No. 10 crushed stone or gravel at CONTRACTOR'S expense.

K. Unsuitable Material: Whenever wet or otherwise unsuitable material, which is incapable of

properly supporting the pipe, is encountered in the trench bottom, such material shall be over-excavated to a depth necessary to allow for construction of stable pipe bedding. The trench shall be backfilled with suitable materials to proper grade. The CONTRACTOR shall notify ENGINEER immediately when such conditions are encountered and the ENGINEER will determine the amount of over-excavation required.

L. Disposal: All excavated material being disposed of off site shall be done legally.

3.2 BACKFILLING

A. Operation: CONTRACTOR shall keep trenches backfilled on a daily basis. Prior to the end of the working day, each trench will be completely backfilled. All backfill shall be brought up equally along each side of the pipe in such manner as to avoid displacement of or damage to the pipe.

B. Material: Shall conform to PART 2 – PRODUCTS above.

C. No fill shall be placed until the subgrade has been checked and approved by the Geotechnical

University of Virginia Permit Set Tunnel C Structural Rehabilitation February 3, 2017 UVA WO: 2555325 PIMS: P04479

Dewberry Engineers Inc. Earthwork: Utilities DEI# 50076991 33 05 00 - 4

Engineer, and in no case shall fill be placed on a subgrade that is muddy, frozen, or that contains frost.

D. Disposal of Unsatisfactory Material: When, in the opinion of ENGINEER, the excavated

material is not satisfactory for use as backfill, the material shall be disposed of offsite legally. Select material shall be brought in by CONTRACTOR.

E. Compaction:

1. VDOT No. 10 Stone Bedding Material or sand shall be brought up in layers not exceeding 3 inches in compacted depth for the full length of pipe. Each layer shall be thoroughly compacted by mechanical tampers or hammers.

2. Compaction of pipe backfill shall conform to the requirements of Section 31 20 00 – Earth Moving.

F. Testing: The backfill shall be tested to insure that the required density is being achieved.

OWNER is responsible for costs associated with testing. ENGINEER shall select the depth at which the test is to be taken. Backfill not compacted to the required density shall be removed, recompacted, and retested at CONTRACTOR'S expense until the requirements are met.

G. Excess Disposal: Excess material shall be disposed of on site or off site legally at the

discretion of the OWNER.

H. Settlement: All backfilled areas where settlement occurs shall be filled and maintained during the life of the Project and for a period of 1 year following the date of final acceptance of all WORK.

I. Hazards: When the CONTRACTOR is notified by ENGINEER or OWNER that all backfill

presents a hazard, CONTRACTOR shall correct such hazardous condition at once. 3.3 BORROW

A. Availability: Where satisfactory materials are not available in sufficient quantity from required excavations, suitable materials shall be obtained from approved off-site borrow areas.

B. Placement: Borrow material shall be placed and compacted only when approved by

ENGINEER and a Licensed Geotechnical Engineer.

C. Payment: No separate payment will be made for furnishing and placing approved borrow material. Compensation in full is included in the agreed to price paid for this Project.

3.4 BLASTING

A. Not Applicable.

END OF SECTION 33 05 00

Appendix A: Utility Test Hole Reports

www.dewberry.com

This page intentionally left blank

McCormick Road Utility Tunnel

DepthDate TH# Utility Requested Utility Found Type Elevation Thickness Owner

11/23/2015

UtilityPavementUtilityMaterialGrade

1 Water & Utility Tunnel 6" Water 3.49' Cast Iron XXX.XX' 0.3' AsphaltUVA

Existing

Dewberry - Point of Contact: Amy Bird (804) 205-3338

Accumark - Point of Contact: Dan Clatterbuck (804) 310-6329 m

Sheet 1 of 1

TEST HOLE INVENTORY REPORT - QUALITY LEVEL "A"

Dewberry

11/23/2015 1A Utility Tunnel Utility Tunnel 5.77' Concrete XXX.XX' 0.3' AsphaltUVA

11/23/2015 3 Electric & Utility Tunnel Electric Ductbank & 2.55' Concrete XXX.XX' 0.3' AsphaltUVA

Utility Tunnel

ACCUMARK, INC. (800) 542-2990 This form and it's contents are protected by copyright, 2015

Test Hole #:

Project Name:

Requested By:

Utility Requested:

Utility Found:

Material Makeup:

Size Utility Found:

Project Numbers:

Project Location:

Work Type:

Test Hole Date:

Soil Conditions:

Utility Condition:

Pavement Cond:

Test Hole Information:Elevation / Survey Information:

Utility Width:Drawn Facing:

Cover (Bottom):

Cover (Top):

Existing grade depth @ top of utility:

Elevation at hub & tack / Pk:

Existing

Grade

3.49'

N/A

Northwest 7"

1

McCormick Road Utility

Dewberry

Amy Bird

Water & Tunnel

Water

Cast Iron

6"

15-910

McCormick Road

Infrastructure

Improvements

11/23/15

Moist Clay

Good

Fair

Located By: Benchmark Elevation

Notes:

Site Diagram / Location Details:

Scale: (NTS)

Utility Test Hole Report - Quality Level "A"

x

3.49'

Accumark, Inc. x

(Asphalt 0.3')

Elevation at top of utility:x

Northing: Easting: Elevation:

N/A N/A x

Point of Contact:

Elevation at bottom of utility:x

Station: Offset:

N/A N/A

RPS 11/25/15

804-205-3338

Charlottesville, Virginia

Utility Owner: UVA

PK nail set over crown of utility.

Tunnel at UVA

ACCUMARK, INC. (800) 542-2990 This form and it's contents are protected by copyright, 2015

Test Hole #:

Project Name:

Requested By:

Utility Requested:

Utility Found:

Material Makeup:

Size Utility Found:

Project Numbers:

Project Location:

Work Type:

Test Hole Date:

Soil Conditions:

Utility Condition:

Pavement Cond:

Test Hole Information:Elevation / Survey Information:

Utility Width:Drawn Facing:

Cover (Bottom):

Cover (Top):

Existing grade depth @ top of utility:

Elevation at hub & tack / Pk:

Existing

Grade

5.77'

N/A

Northwest 7"

1A

McCormick Road Utility

Dewberry

Amy Bird

Utility Tunnel

Utility Tunnel

Concrete

N/A

15-910

McCormick Road

Infrastructure

Improvements

11/23/15

Moist Clay

Good

Fair

Located By: Benchmark Elevation

Notes:

Site Diagram / Location Details:

Scale: (NTS)

Utility Test Hole Report - Quality Level "A"

x

5.77'

Accumark, Inc. x

(Asphalt 0.3')

Elevation at top of utility:x

Northing: Easting: Elevation:

N/A N/A x

Point of Contact:

Elevation at bottom of utility:x

Station: Offset:

N/A N/A

RPS 11/25/15

804-205-3338

Charlottesville, Virginia

Utility Owner: UVA

PK nail set over utility tunnel.

Tunnel at UVA

ACCUMARK, INC. (800) 542-2990 This form and it's contents are protected by copyright, 2015

Test Hole #:

Project Name:

Requested By:

Utility Requested:

Utility Found:

Material Makeup:

Size Utility Found:

Project Numbers:

Project Location:

Work Type:

Test Hole Date:

Soil Conditions:

Utility Condition:

Pavement Cond:

Test Hole Information:Elevation / Survey Information:

Utility Width:Drawn Facing:

Cover (Bottom Ductbank):

Cover (Top Ductbank):

Existing grade depth @ top of utility:

Elevation at hub & tack / Pk:

Existing

Grade

2.55'

4.13'

Northwest 7"

3

McCormick Road Utility

Dewberry

Amy Bird

Electric & Utility Tunnel

Electric Ductbank &

Concrete

2.30' Ductbank

15-910

McCormick Road

Infrastructure

Improvements

11/23/15

Moist Clay

Good

Fair

Located By: Benchmark Elevation

Notes:

Site Diagram / Location Details:

Scale: (NTS)

Utility Test Hole Report - Quality Level "A"

x

2.55' (Ductbank)

Accumark, Inc. x

(Asphalt 0.3')

Elevation at top of utility:x

Northing: Easting: Elevation:

N/A N/A x

Point of Contact:

Elevation at bottom of utility:x

Station: Offset:

N/A N/A

RPS 11/25/15

804-205-3338

Charlottesville, Virginia

Utility Owner: UVA

PK nail set over utility tunnel.

Tunnel at UVA

Utility Tunnel

Cover (Utility Tunnel):

8.12'