u.o no 5(10)

Upload: hussnain-azam-abdali

Post on 29-May-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 U.O NO 5(10)

    1/4

    GOVERNMENT OF THE PUNJAB

    PLANNING & DEVELOPMENT DEPARTMENT

    Subject:- CREATION OF POSTS UNDER WATER RESOURCE DEVELOPMENT

    THROUGH CONSTRUCTION OF 200 MINI DAMS WITH COMMAND

    AREA DEVOLOPMENT OF PUNJAB REGION BARANI AREA OF

    PUNJAB APPROVED BY PROVINCIAL DEVELOPMENT WORKING

    PARTY (PDWP) MEETING HELD ON 25-11-2009.

    Will the Section Officer (Regulation Wing), Government of the Punjab, Finance

    Department please refer to Finance Department letter NO. FD.SO(P&D)2-38/2006-Vol-I Dated

    22-2-2010 on the subject noted above.

    As directed by the Finance Department vide letter referred above, the pay package

    of staff of subject scheme is required to the got separately cleared from Regulation Wing of

    Fianc Department.

    The following Documents are submitted for approval of pay package of the post

    already cleared by the Finance Department:-

    i. Purposed pay package of subject scheme post cleared by Finance Department.

    ii. Copy administrative approval.

    iii. Copy of approved PC-I of subject scheme.

    iv. Minutes of PDWP Dated 25-11-2009.

    v. Copy of Clarence of posts by Finance Department dated by 22-10-2010.

    (HAMID MAHMOOD)

    Assistant Chief (RP)

    The Section Officer (Regulation Wing),

    Government of the Punjab,

    Finance Department,

    Lahore.

    U.O.No. 5(10) ABAD/P&D Dated the Lahore 19th March, 2010

  • 8/9/2019 U.O NO 5(10)

    2/4

    GOVERNMENT OF THE PUNJAB

    PLANNING & DEVELOPMENT DEPARTMENT

    Subject:- ADMINISTRATIVE APPROVAL FOR THE SCHEME TITLED

    CAPACITY BUILDING OF P&D DEPARTMENT FOR IMPROVE

    POLICY PLANNING AND MONITORING OF DEVELOPMENT

    PROCESS IN PUNJAB AT A TOTAL COST OF RS. 197.542 MILLION

    Appearing at General Sr. No.4416 in ADP-2009-2010.

    Will the Section Officer (P&D), Government of the Punjab, Finance Department

    please refer to the subject noted above.

    Administrative Approval (Revised) of the scheme titled Capacity Building of

    P&D Department For Improve Policy Planning And Monitoring of Development Process In

    Punjab at a Total Cost Of Rs. 197.542 Million Appearing at General Sr. No.4416 In ADP-2009-

    2010 is forwarded for authentication and return. A copy of approved PC-I is also enclosed.

    (CH. IFTIKHAR AHMED)

    Admin Officer (RP)

    The Section Officer (P&D),

    Government of the Punjab,

    Finance Department,

    Lahore.

    U.O.No. 93(17) RP/P&D2009 Dated the Lahore 19th April, 2010

  • 8/9/2019 U.O NO 5(10)

    3/4

    GOVERNMENT OF THE PUNJAB

    PLANNING & DEVELOPMENT DEPARTMENT

    Subject:- STAFF CLEARANCE FOR THE SCHEME PUNJAB ECONOMIC

    OPPORTUNITIES PROGRAMME (PEOP).

    Will the Section Officer (P&D), Government of the Punjab, Finance Department,

    please refer to the subject noted above.

    CDWP during its meeting held on 18-03-2010 has approved the scheme of Punjab

    Economic Opportunities Programme (PEOP) at a total cost of Rs. 729.500 million. The ECNEC

    has also accorded anticipatory approval of the scheme. The said project involved 21 posts

    (Officers / Officials) (page 23 of PC-I-flag X) starting January 2010-December 2013, over span

    of four years which requires to the cleared by Finance Department in terms of note I(IV) under

    Sr. No. 8 of the second schedule part-I, Power common to all Department under the Delegation

    of Finance Power Rules 2006.

    The following Documents are attached:-

    i. Copy of approved PC-I of Punjab Economic Opportunities Programme (PEOP).

    ii. Copy Administrative Approval (Cost: Rs.729.500). The said administrative

    approval has already been authenticated by FD and issued accordingly.

    iii. Minutes of CDWP Dated 18-03-2010.

    iv. Copy of anticipatory approval by ECNEC

    (CH. IFTIKHAR AHMED)

    Admin Officer (RP)

    To,

    The Section Officer (P&D),

    Government of the Punjab,

    Finance Department,

    Lahore.

  • 8/9/2019 U.O NO 5(10)

    4/4

    U.O.No.13 (1)RP/P&D/2010 Dated the Lahore

    GOVERNMENT OF THE PUNJAB

    PLANNING & DEVELOPMENT DEPARTMENT

    Subject:- PROPOSALS FOR RELEASE OF FUNDS AGAINST ADP 2010-11

    DURING FIRST QUARTER OF FY 2010-11

    Kindly refer to your U.O. No. 1(45)RO(ADPF)P&D/2010-11 dated 23-06- 2010

    on the subject cited above.

    Kindly find enclosed herewith requisite information pertaining to development

    programme of RP and P&D sector of the financial year 2010-11. Soft copy is also placed Chief

    (Monitoring) share folder.

    Assistant Chief (RP)

    Chief (Monitoring)

    U.O.No. RP/P&D/2010 Dated the Lahore 24th June, 2010

    CC.

    PS to Secretary, P&D Department.