update on landfill long-term financial assurances activities for postclosure maintenance and...
DESCRIPTION
Closure Postclosure Corrective Action Financial Assurances Goal: Protect Public Health, Safety, and the Environment into the FutureTRANSCRIPT
Update On Landfill Long-Term Financial Assurances Activities For
Postclosure Maintenance And Corrective Action
Goal: Protect Public Health, Safety, and the Environment into
the Future
Planning Costs
Financial Assurances
ClosurePostclosure
Corrective Action
Financial Assurances
Goal: Protect Public Health, Safety, and the Environment into the Future
Goals, Activities and Process
Continue AB 2296 Consulting Group Roundtable format to facilitate interaction Neutral facilitation of meetings Utilize sound science and best available
information Collect PCM standards and reduction/release
from PCM financial requirements nationwide Survey California PCM cost reductions Complete compliance review of California
landfills and ground proofing of risk model components
Workshops/MeetingsJanuary-July 2008
Date Location Activity1/23/08 Palm Desert Regional Water Board MCC Meeting – Corrective Actions
1/31/08 CalEPA Rm-1010 Key Stakeholders Meeting For Private Operators
1/31/08 CalEPA Rm-910 Key Stakeholders Meeting For Local Government at Large
2/1/08 CalEPA Rm-1010 Key Stakeholders Meeting For Environmental Groups
2/1/08 CalEPA Rm-1010 Key Stakeholders Meeting For Local Government Operators
2/11/08 Coastal Hearing Room Committee Update- P&C Committee Meeting
2/25/08 CalEPA Rm-550 Modeling Scenarios
3/10/08 CalEPA Rm-550 Postclosure Maintenance Workshop
4/14/08 CalEPA Rm-550 Corrective Action Workshop
5/12/08 CalEPA Rm-550 Phase II Informal Rulemaking
6/9/08 Coastal Hearing Room Discussion and Request for Additional DirectionP&C Committee Meeting
7/14/08 Coastal Hearing Room Request for Rulemaking Direction for Phase II P&C Committee Meeting
Key Stakeholders MeetingsJanuary/February 2008
Date Time Location Activity/Description1/23/08 Palm Desert Regional Water Board MCC Meeting – Corrective Actions
1/31/08 10:00 am-12:00 pm
CalEPA Rm-1010
Key Stakeholders Meeting For Private Operators
1/31/08 1:30 pm-3:30 pm
CalEPA Rm-910
Key Stakeholders Meeting For Local Government at Large
2/1/08 10:00 am-12:00 pm
CalEPA Rm-1010
Key Stakeholders Meeting For Environmental Groups
2/1/08 1:30 pm-3:30 pm
CalEPA Rm-1010
Key Stakeholders Meeting For Local Government Operators
Key Stakeholder Meeting Topics:Review response summary of commentsDiscuss outstanding issuesOutline upcoming schedule and approach
Workshops/MeetingsFebruary 2008
Date Time Location Activity/Description2/11/08 1:30 am- Coastal
Hearing RoomCommittee Update- P&C Committee MeetingAgenda Item updating Board with scheduled activities and dates through July 2008
2/25/08 9:30 am- 3:30 pm
CalEPA Rm-550
Modeling ScenariosDiscussion of alternate scenarios for potential State fund (PCM only, CA only, public only, private only, etc.)
Workshops/MeetingsMarch 2008
Date Time Location Activity/Description3/10/08 9:00 am-
12:00 pmCalEPA Rm-550
Postclosure Maintenance WorkshopDiscussion on definition of Postclosure Maintenance activities and proposed rulemaking
Topics:Definition of Corrective Action / Postclosure MaintenanceCriteria for determining end of postclosure maintenance activitiesUS EPA and other states (results of nationwide survey)California experience with postclosure maintenancePotential statutory amendments
Workshops/MeetingsApril 2008
Date Time Location Activity/Description4/14/08 9:00 am-
12:00 pmCalEPA Rm-550
Corrective Action WorkshopDiscussion on definition of Corrective Action and proposed rulemaking and potential statutory amendments
Topics:Results of Landfill Compliance SurveyOptions/Methodologies for classifying landfill potential threatsPotential for joint rulemaking with Water BoardPotential statutory amendments
Workshops/MeetingsMay 2008
Date Time Location Activity/Description5/12/08 9:00 am-
12:00 pmCalEPA Rm-550
Phase II Informal RulemakingDiscussion of proposed rulemaking
Issues deferred from Phase I rulemakingContingency on postclosure maintenance cost estimatesSubmittal of as-built costs after closureInsurance amendments
Potential amendments to pledge of revenue agreement Post-30 year financial assurance demonstrations Non-water quality related corrective actions – joint
rulemaking with SWRCB Closure fund-as-you-fill
Workshops/MeetingsJune 2008
Date Time Location Activity/Description6/9//08 1:30 pm- Coastal
Hearing Room
P&C Committee MeetingDiscussion and Request for Additional Directionon Long-Term PCM and CA Financial Assurances Draft Rulemaking Comprehensive Package
TopicsPresent a menu of options for long-term postclosure maintenance and non-water quality corrective action financial assurancesPhase II rulemaking itemsNeed for additional statutory authority
Workshops/MeetingsJuly 2008
Date Time Location Activity/Description7/14/08 1:30 pm- Coastal
Hearing Room
P&C Committee MeetingRequest for Rulemaking Direction for Phase IIDraft Comprehensive Rulemaking Documents for Board Consideration to Notice