update on löfstedt review and red tape challenge

18
Health and Safety Executive Health and Safety Executive Update on Löfstedt Review and Red Tape Challenge Anthony Lees HSE Construction Policy Unit

Upload: kimberley-curry

Post on 30-Dec-2015

23 views

Category:

Documents


2 download

DESCRIPTION

Update on Löfstedt Review and Red Tape Challenge. Anthony Lees HSE Construction Policy Unit. Better regulation policy. Government better regulation strategy June 2010 – Lord Young review October 2010 – ‘Common Sense, Common Safety’ February 2011 – Ministerial Statement - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Update on Löfstedt Review and Red Tape Challenge

Health and Safety Executive

Health and Safety Executive

Update on Löfstedt

Review and Red Tape

Challenge

Anthony Lees

HSE Construction Policy Unit

Page 2: Update on Löfstedt Review and Red Tape Challenge

Better regulation policy

• Government better regulation strategy

• June 2010 – Lord Young review

• October 2010 – ‘Common Sense, Common Safety’

• February 2011 – Ministerial Statement

• May 2011 – Löfstedt – call for evidence

• November 2011 – Report and Government response

Page 3: Update on Löfstedt Review and Red Tape Challenge

Better regulation policy

• April 2011 – Red Tape Challenge

• Health and Safety theme

• July 2011 – ‘spotlight’ period

• 2012 – ‘Star Chamber’ process

• Lofstedt and RTC implementation: 2011-2015?

Page 4: Update on Löfstedt Review and Red Tape Challenge

Löfstedt Report - themes

• Specific revocations and consideration of further consolidation

• Review of all ACoPs

• Self-employed exemption

• Civil liability and strict liability regulations

• Improving quality and consistency of local authority enforcement

• Influencing Europe to ensure legislation is risk-based

Page 5: Update on Löfstedt Review and Red Tape Challenge

Löfstedt recommendations – observations

• HSE welcomes the report

• Opportunity to improve regulation

• Impact limited on higher risk sectors

• Does not dilute standards

• Some uncertainty over implications of future work

Page 6: Update on Löfstedt Review and Red Tape Challenge

Specific Revocations

• Two tranches of specific revocations

• 1st tranche – 7 Statutory Instruments - consultation closed

• 2nd tranche – 14 Statutory instruments - consultation opens early April

• Three construction-specific Regulations– Construction (Head Protection) Regulations

1989– Notification of Conventional Tower Cranes

Regulations 2010 + amendment

Page 7: Update on Löfstedt Review and Red Tape Challenge

Construction (Head Protection) Regulations 1989 - rationale

• Regulations have largely delivered what they set out to

• Head protection culturally-embedded in industry practice

• Equivalent protection offered under PPE Regulations

• Behaviours unlikely to change

• Existing exemption retained

Page 8: Update on Löfstedt Review and Red Tape Challenge

Notification of Conventional Tower Cranes Regulations 2010 - rationale

• Rationale for introduction

• Target public assurance, not health and safety

• Existing legislation provides adequate framework for assurance of integrity

• Non-regulatory work has improved standards

• Have not delivered expected benefits

• Costs substantially higher than expected

Page 9: Update on Löfstedt Review and Red Tape Challenge

Specific revocations - process

• Standard 12 week public consultation

• Backed by impact assessments (form part of consultative document)

• Subject to committee scrutiny and Ministerial approval

• Any revocations expected later this year

• Need to publicise revocations and implications – industry support welcome

Page 10: Update on Löfstedt Review and Red Tape Challenge

Review of ACoPs

• ACoPs have basis in Robens Report

• Intended to add precision in the context of goal-setting legislation

• Wide support for ACoPs, but concerns over length and complexity

• Focus should be on assisting SMEs

Page 11: Update on Löfstedt Review and Red Tape Challenge

Review of ACoPs

• Review willl determine whhether each ACoP:– Is still required– Gives unambiguous guidance about

what is required– Is up to date– Is presented in the most apropriate way

• CDM ACoP outwith

• Timings

Page 12: Update on Löfstedt Review and Red Tape Challenge

Self-employed exemption

• Specific recommendation in Löfstedt

• Cannot apply to construction work due to Directive basis of CDM

• Intended to apply to low-risk activities

• Explicitly will not apply to construction

Page 13: Update on Löfstedt Review and Red Tape Challenge

Civil liability and strict liability requirements

• Löfsted concern over extent of right of civil action under regulations: fear of civil action provides a perverse incentive to employers– Pre-action protocols (‘Woolf lists’)– Strict liability

• Use of pre-disclosure lists to be restated and clarified

• Strict liability to be examined and either tempered by SFAIRP, or right to civil action restricted

Page 14: Update on Löfstedt Review and Red Tape Challenge

Other specific recommendations

• CDM

• Challenge Panel(s)

• Work at Height Regulations 2005

Page 15: Update on Löfstedt Review and Red Tape Challenge

Löfstedt: CDM 2007 recommendation

• Löfstedt said little about CDM – he was aware of the review

• Effectively recommended that HSE should now publish the CDM evaluation report

Page 16: Update on Löfstedt Review and Red Tape Challenge

Challenge Panels

• Recommended an independent panel to allow challenge of decisions

• HSE will form two panels– January 2012 – Independent

Regulatory Challenge Panel– Later 2012 – ‘wider’ challenge panel

Page 17: Update on Löfstedt Review and Red Tape Challenge

Work at Height Regulations

• Löfstedt recommended review of WAHR– Regulations are risk based, but poorly

understood and applied – the ‘2m rule dilemma’

– Particularly an issue for SMEs– Elements of gold plating – eg

stepladders

• Ministerial interest in how WAHR is misapplied or burdensome

• Construction fully played into review

Page 18: Update on Löfstedt Review and Red Tape Challenge

Red Tape Challenge

• Comments made to RTC were considered by Löfstedt

• Significant amount of discussion between departments and Ministers – ‘Star Chambers’

• Process described on RTC website

• 3 meetings so far, more planned