update on recent decisions of the planning and …ecodirections.com/pdf/ipola_paper.pdf · update...
TRANSCRIPT
UPDATE ON RECENT DECISIONS
OF THE
PLANNING AND ENVIRONMENT COURT
AND
COURT OF APPEAL
AND AN
OVERVIEW OF THE IPOLA ACT 2001
By
John Haydon
Barrister at Law, Mediator and Case Appraiser
Townsville
15 March, 2002
© www.ecodirections.com
2
1. This paper will touch on five decisions of the Court of Appeal and a number of decisions of the Planning and
Environment Court to give an overview of what is happening with appeals generally, the scope of the conditions
power, the declarations power of the Planning and Environment Court and costs.
2. The second part of the paper deals with an overview of the Integrated Planning and Other Legislation
Amendment Act 2001. These provisions have not yet come into force. As an overview it will not deal with all of
the details.
3. The Planning and Environment Court has issued Practice Direction 1 of 2000. It includes Guidelines to Experts. All
witnesses in the Planning and Environment Court need to be aware and understand these guidelines.
4. New Planning Schemes under the Integrated Planning Act 1997 are expected to be more performance based. This
is particularly so now that no use if prohibited. Strategic Plans will continue to be important.
Selected Court of Appeal Decisions
5. The Court of Appeal in Queensland deals with questions of law arising out of decisions of the Planning and
Environment Court. The decisions provide guidance for the resolution of other planning and environment disputes
following the principles set out by the Court of Appeal. Some decisions have limited value because of the particular
facts and circumstances. Others have wider applications.
6. In Vynotas Pty Ltd v Brisbane City Council (2001) 112 LGERA 206 the Court of Appeal was dealing with the
effect of the Integrated Planning Act 1997 on existing Planning Schemes. Significantly, those Planning Scheme
no longer have the force of law the way they did under the repealed legislation. The following comments made by
the Court of Appeal Judges are of importance:-
[1] DAVIES JA: In March 1999 Brisbane City Council granted approval to a development application by the
second respondent Total Project Control Pty Ltd for a shopping centre on land at Beaudesert Road,
Calamvale. The conditions of that approval were later amended but that aspect of the matter is of no relevance
to the present application. The applicants are the owners of a rival shopping centre in the vicinity of the
approved land and made submissions to the council against the approval. They then appealed to the Planning
and Environment Court against that approval as they were entitled to pursuant to s 4.1.28 of the Integrated
Planning Act 1997. Having failed in that appeal they seek leave to appeal to this Court against the decision of
the Planning and Environment Court. Such leave will be granted only, relevantly, on the ground of error or
mistake in law.
....
[5] It is common ground that s 6.1.29 and s 6.1.30 relevantly applied to this application. Section 6.1.29
relevantly provides:.
"(3) ... the following matters, to the extent the matters are relevant to the application, apply for assessing the
application �
© www.ecodirections.com
3
...
(b) the transitional planning scheme;
...
(h) if the application is for development that before the commencement of this section would have required an
application to be made under any of the following sections of the repealed Act �
(i) section 4.3(1) � the matters stated in section 4.4(3)".
Section 6.1.30 relevantly provides:
"(3) ... the assessment manager must, if the application is for development that before the commencement of
this section would have required an application to be made under any of the following sections of the repealed
Act �
(a) section 4.3(1) � decide the application under section 4.4(5) and (5A)".
[6] Section 4.3(1) of the repealed Act, the Local Government (Planning and Environment) Act 1990, provided:
"A person may make application to a local government to amend a planning scheme or the conditions attached
to an amendment". It was common ground that, before the commencement of the Integrated Planning Act the
subject development would have required an application to the council to amend the planning scheme because
the subject land was zoned future urban and a shopping centre was, under the planning scheme a prohibited
development in that zone.
[7]...The effect of s 6.1.29(3)(h)(i) therefore, at least when read without reference to par (b), appears to be
that, in this case, those enumerated matters, to the extent only that they were relevant to the development
application, applied to the assessment of that application. To construe it so as to require that the assessment
be made as if the application was one for an amendment of the planning scheme would be to substantially
redraft it notwithstanding that it could be given a sensible operation without that.
[8] As to s 6.1.30(3)(a), s 4.4(5) of the Planning and Environment Act provided that in deciding an application
pursuant to s 4.3 a local government was required to approve the application, approve it subject to conditions
or refuse it; and s 4.4(5A) required the local government to refuse to approve an application if �
"(a) the application conflicts with any relevant strategic plan or development control plan; and
(b) there are not sufficient planning grounds to justify approving the application despite the conflict."
[9] Again leaving aside the possible effect of s 6.1.29(3)(b), the quoted requirement in s 6.1.30(3)(a) requires
no more than that, in deciding the application the assessment manager will approve it, approve it subject to
conditions or refuse it; and will refuse it if it conflicts with a relevant strategic plan or development control
plan and there are not sufficient planning grounds to justify approving it despite the conflict. The word
"under" in the context appears to mean no more than "in compliance with". Section 4.4(5) and s 4.4(5A) can
be complied with without treating the application for development approval as if it were a rezoning
application. It is simply a case of substituting the application of those provisions for the equivalent provisions
of the Integrated Planning Act.2 To construe s 6.1.30(3)(a) as requiring that the application be decided as if it
were a rezoning application would require substantial redrafting of the provision.
...
[13] Read in the context of the Act as a whole, s 6.1.29(3)(b) does not say or imply that any specific
requirements with respect to any zone under a transitional planning scheme must be imposed in deciding a
development application or that any such requirements must even be considered in so deciding. On the
contrary the transitional planning scheme, generally, is stated only as one of a number of matters which, to the
© www.ecodirections.com
4
extent that they may be relevant, "apply" for assessing the application. It says nothing about its application, if
any, to the decision making process
[14] But even as to the assessment process, the height restrictions applicable in the business zone did not
apply to the land under the transitional planning scheme at the time of assessment because the land was zoned
future urban; and they would never so apply unless the land was rezoned to business, which would not
necessarily or even probably follow from the granting of the development application. There are two reasons
for this. The first is that, as already mentioned, to rezone the land to conform to the approved use would have
required a rezoning either to the business zone or to a particular development zone. However the provisions of
the transitional planning scheme with respect to particular development zones did not contain any of the
height restrictions which applied in the business zone and there would be no reason to think that, if there had
been a rezoning to conform to the approved use, that would have been any more likely to be one to the
business zone than one to a particular development zone. Secondly a rezoning does not necessarily follow from
the granting of a development application such as this. Consequently, in my opinion, the provisions with
respect to the business zone were not relevant to the assessment of this application pursuant to s 6.1.29. It
follows that they were not required to be applied in the decision making pursuant to s 6.1.30.
[15] In any event the scheme of the Integrated Planning Act appears to be that, so far as it applies to
development and use of premises, a transitional planning scheme no longer has binding force but is of
persuasive relevance only. Thus s 2.1.23 provides that a local planning instrument, which includes a planning
scheme, may not prohibit development on, or the use of premises; and more specifically s 6.1.2(3) provides
that a prohibited use in a former planning scheme6 is taken to be no more than an expression of policy that the
use is inconsistent with the intent of the zone in which the use is prohibited.
...
[18] There was therefore no legal error in the judgment of the Planning and Environment Court and the
application for leave to appeal should be refused with costs.
[19] PINCUS JA: I have read and agree with the reasons of Davies JA, but propose to add some
observations.
[20] The general idea of the relevant provisions of the Integrated Planning Act 1997, contained in Ch 6 of that
Act, is to require attention to be given to provisions comprising a "transitional planning scheme" when
development applications under the 1997 Act are being considered; but the extent to which a transitional
planning scheme should have weight is not plainly stated. One point which is clear is that a use which is
prohibited in the transitional planning scheme may be allowed, although the fact of the prohibition is relevant,
under s 6.1.2(3) of the 1997 Act.
[21] .. it does not appear to me that the legislature intended, by the language used in Ch 6 of the 1997 Act, to
make the provisions of transitional planning schemes absolutely binding, in the decision of development
applications.
[22] On the other hand it is important to note that the 1997 Act did not by Ch 6 create a planless situation.
Citizens expect reasonable stability in the law's treatment of permitted land use. It would be unfortunate if Ch
6 were used to defeat the reasonable expectations of those who have relied on, and perhaps expended
substantial sums of the faith of, existing planning arrangements. The degree of flixibility which Ch 6
contemplates does not justify failure to give considerable weight to planning arrangements, as they existed
when Ch 6 commenced, so far as such arrangements are required to be applied by s.6.1.29(3).
© www.ecodirections.com
5
7. The Court of Appeal has recently examined the scope of the conflict with the Strategic Plan test set out in the
Local Government (Planning and Environment) Act 1990 which is made relevant to Transitional Planning
Schemes by Section 6.1.30(3) of the Integrated Planning Act 1997. The Planning and Environment Court Judge
found that there was a conflict with the Strategic Plan but went onto find that there was sufficient planning grounds
to justify approval notwithstanding the conflict. That decision was overturned by the Court of Appeal in Grosser v
Gold Coast City Council (2001) QCA 424. Justice Thomas and Justice Williams agreed with the reasons for
judgment of Justice White.
[12] WHITE J: The appellant Council of the City of Gold Coast (�the Council�) was granted leave to appeal
a decision of the Planning and Environment Court of 18 August 2000 approving an application by the
respondents for a material change of use of land at Bundall (Williams J, as his Honour then was, Cullinane
and Douglas JJ) on 12 December 2000, s 4.1.56(2) of the Integrated Planning Act 1997 (�I P Act�).
[13] Section 4.1.56(1) of the I P Act limits the grounds of appeal
! to an error or mistake in law;
! that the court had no jurisdiction to make the decision; or
! that the court exceeded its jurisdiction in making the decision. The Notice of Appeal identifies five
grounds of error or want of jurisdiction in his Honour�s reasons for judgment which the appellant
contends would warrant this court allowing the appeal and which, in broad terms, encompass his
Honour�s approach to the relevant planning scheme and his construction of s 4.4(5A) of the IP Act.
[14] The Planning and Environment Court heard two appeals. One concerned the Council�s decision to refuse
a material change of use application by the respondents (applicants below) and the other concerned an
enforcement notice issued by the Council. His Honour found in favour of the respondents on the material
change of use appeal and in favour of the Council in respect of the enforcement notice. It is only with respect
to the former that this appeal is concerned.
Background
[15] The respondents are husband and wife. Mrs Grosser, as found by his Honour, is a well-recognised
exponent of the Japanese sculptured floral art of Ikebana. She commenced teaching Ikebana to small groups in
her home in Southport in 1988. In due course this business became known as the Australian Ikebana Centre. In
1997 she and her husband decided to relocate the business to a purpose built location and to that end found
premises at 44 Ashmore Road, Bundall. The property was purchased by a company controlled by Dr and Mrs
Grosser with the intention of demolishing the existing premises and building a house suitable for teaching
Ikebana. His Honour accepted Mrs Grosser�s evidence that Ikebana needs to be taught in a residential rather
than a commercial environment. Although Dr Grosser is registered as participating in the business it is Mrs
Grosser who is its active principal.
[16] An application was made to the Council to use the property for �Home Occupation (Flower School)�
which was a permissible development in the Residential Dwelling House Zone in which this site was located
and consent was given on 30 October 1997 subject to the following conditions:
�1. The total use area of the home occupation shall not exceed one third of the gross floor area of the dwelling
house or forty-five (45) square metres, whichever is the lesser.
© www.ecodirections.com
6
2. The home occupation shall not attract clientele on a frequent or regular basis. In this regard the home
occupation shall be operated so that no more that [sic] fifteen (15) client visits are made to the premises
within any seven (7) day period.
3. The home occupation shall not operate on Sundays or public holidays or otherwise between the hours of
7.00 pm and 8.00 am.
4. No sign other than a sign not exceeding 0.3 square metres in area and bearing only the name and telephone
number of the occupier and occupation shall be displayed on the premises.�
[17] These conditions were consistent with the definition of �home occupation� in the City of Gold Coast
Planning Scheme gazetted on 11 February 1994 in Part 2 Appendix 2 (�the 1994 Scheme�). It is relevant to
set out those provisions to appreciate the limited nature of this permissible development.
�HOME OCCUPATION � The use of any dwelling house or its curtilage for an occupation or profession
where:
(i) the person carrying on the occupation or profession lives permanently in the dwelling house; and
(ii) not more than one (1) person, other than the person who lives in the dwelling house, is employed or
otherwise engaged in the conduct of the occupation or profession; and
(iii) does not involve the display of goods, whether in a window or otherwise; and
(iv) the provisions of Section 12.3 of this Scheme are complied with; and
(v) the development is licensed as a home occupation under the provisions of the Council�s By-laws.
�
The term, home occupation, shall be followed by a second term describing the type of occupation conducted
and this combination of terms shall describe the development.�
[18] Section 12.3 of the 1994 Scheme provides:
�The provisions of Clauses 12.3.1 to 12.3.3 are development standards applicable to the development of home
occupations and should be read in conjunction with the definition of home occupation contained in Section
2.2. These provisions are additional to any other relevant provisions of this Planning Scheme.
12.3.1 Operation of Home Occupations Purpose:
To ensure that a home occupation will operate without detrimental impact upon the amenity of any residential
development.
Provisions:
12.3.1.1 The total use area of the home occupation shall not exceed one third of the gross floor area of the
dwelling house or forty-five (45) square metres, whichever is the lesser.
12.3.1.2 The home occupation shall not attract clientele on a frequent or regular basis. In this regard the home
occupation shall be operated so that no more than fifteen
(15) client visits are made to the premises within any seven (7) day period. 12.3.1.3 The home occupation shall
not operate on Sundays or public holidays or otherwise between the hours of 7.00 pm and 8.00 am.
12.3.1.4 No sign other than a sign not exceeding 0.3 square metres in area and bearing only the name and
telephone number of the occupier and occupation shall be displayed on the premises.
12.3.1.5 No source of power other than single phase electric motors having a total connected load of
not more than 0.75 kilowatt shall be used.
12.3.1.6 The home occupation shall be operated in such a manner that:
© www.ecodirections.com
7
(i) it does not impose a load on any public utility greater than that which is required for typical development in
the locality; and
(ii) it does not create hazards or cause undue annoyance or disturbance to persons or premises not connected
with the home occupation; and
(iii) it does not interfere with the amenity of the neighbourhood by reason of the emission of noise, vibration,
smell, fumes, smoke, vapour, steam, soot, ash, dust, grit, oil, waste water, waste products, radio or electrical
interference or otherwise.�
[19] Plans were lodged with the Council on behalf of Dr and Mrs Grosser for a two-storied house which
showed a 45 square metre �Ikebana Teaching Area� upstairs with other rooms designated for personal
domestic use. When the home occupation application was made it was intended that Dr and Mrs Grosser�s
daughter would reside in the new premises and be involved in teaching Ikebana. This, however, did not
eventuate and no one has lived in the dwelling at 44 Ashmore Road as a home. The new building was
approved by the Council as a Class 1 Residential Dwelling, the construction of which was completed in July
1998. Since no one was to live in the house Mrs Grosser incorporated the �domestic� areas into the business.
The large downstairs area described on the plans as �Family Living� became a cafeteria and although a
resource for students of the centre was open to the public and advertised as available for catered functions
generally including external catering. The areas designated on the plans as �Home Occupant Personal
Studio� and �Home Occupant Library Media Room� became a second teaching area where guest lecturers
could give lectures on different areas of art. The area described as �Office� on the plans continued to perform
that function. The area described as �Home Occupant Bedroom Suite Den� became an area where students
practised pottery, other art and computer graphics skills. Mrs Grosser decorated the down stairs walls with
works by local artists which were available for sale to her students and to the public.
[20] In November 1998 an officer of the Council inspected the premises and in February 1999 the Council
issued a show cause notice as to why an enforcement notice should not be issued pursuant to s 4.3.11 of the I P
Act to refrain from committing a development offence or to remedy commission of a development offence by
failing to comply with the conditions of approval for the Home Occupation.
[21] Mrs Grosser responded by lodging a material change of use application under the I P Act for
Educational Establishment (Art School), Public Recreation (Art Gallery) and Cafeteria for the site the
proposal for which substantially followed the way in which the dwelling was then being used. The application
was refused by Council on 17 September 1999 and an enforcement notice issued requiring the cessation of use
of the premises in breach of the conditions which had been imposed for the use of the premises for Home
Occupation.
[22] At least by the time of the hearing below there were, in effect, a number of businesses being conducted at
44 Ashmore Road � a coffee shop offering breakfast, morning tea, lunch, afternoon tea, on-site functions and
off-site catering seven days a week; educational courses including full and part-time courses in Ikebana and
TAFE accredited Certificate in Art courses and classes and workshops in art appreciation, painting and
drawing, pottery and sculpture, garden design, gourmet cooking, use of computers and English; and an art
gallery and shop which displayed and offered for sale equipment used in Ikebana displays, jewellery, original
paintings and books. Some thirteen staff, full and part-time worked at different times at the centre.
[23] The Council refused the application for material change of use on five grounds noted by his Honour at
[11] of his judgment
© www.ecodirections.com
8
�(1) The proposal does not accord with the intent for development in the Residential Dwelling House Zone, as
stated in the former City of Gold Coast Planning Scheme 1994.
(2) The proposal does not accord with the detached housing designation of Council�s Strategic Plan.
(3) The number of on site car parking spaces is insufficient for the proposed uses on site and the car parking
layout does not accord with Gold Coast City Council Local Planning Policy No. 1 � Off Street Vehicle Parking
Requirements.
(4) The proposal is likely to result in an adverse impact on the amenity of the surrounding residential area.
(5) The issues raised by submitters objecting to the proposal are valid and are supported by Council.�
[24] Those grounds of refusal formed the basis of the grounds of appeal to the Planning and Environment
Court.
The location
[25] Number 44 Ashmore Road, Bundall is situated on the southern side of Ashmore Road, a major arterial
highway comprising two traffic lanes in each direction divided by a median strip with a dedicated parking lane
on each side. On the north of Ashmore Road, immediately opposite the subject site, are situated large
commercial enterprises including two Harvey Norman stores with an extensive on site parking area. Land on
the southern side is zoned Residential Dwelling House. On the southern side of Ashmore Road near number 44
some residences were identified below as used for a variety of home occupation and minor commercial
activities. In the two blocks bounded by Upton and Campbell Streets around number 44 his Honour noted that
of the 28 properties which fronted Ashmore Road, nine were separate medical centres and eight were for uses
approved as home occupation. These included an architect�s office, feng shui consultant (changed by the
hearing), two interior designers and a solicitor�s office. The remaining 11 were residences. His Honour also
noted that two sites appeared to be utilised for non-residential purposes without the necessary approvals. He
further noted that development on land south of number 44 along Coogeen Street, which runs parallel to
Ashmore Road, was solely residential.
The relevant planning provisions
[26] The 1994 Scheme was a planning scheme made under the Local Government (Planning & Environment)
Act 1990 (�the P & E Act�) which was in force immediately prior to the commencement of I P Act on 30
March 1998. The 1994 Scheme is a �former planning scheme� within the meaning of s 6.1.1 of the I P Act.
Section 6.1.2 of the I P Act provides that such a planning scheme continues to have effect notwithstanding the
implementation of the I P Act subject to some qualifications.
�6.1.2 Continuing effect of former planning schemes
(1) Despite the repeal of the repealed Act, each former planning scheme continues to have effect in the local
government area for which it was made, subject to subsections (2) and (3).
(2) If a provision of a former planning scheme is inconsistent with chapter 3, to the extent the provision is
inconsistent, chapter 3 prevails, unless this chapter states otherwise.
(2) A prohibited use in a former planning scheme is taken to be an expression of policy that the use is
inconsistent with the intent of the zone in which the use is prohibited.� The provisions (including any maps,
plans, diagrams or the like) of the former planning scheme comprise a �transitional planning scheme� for the
area in the absence of contrary intention in the I P Act, s 6.1.3.
© www.ecodirections.com
9
[27] It was common ground that had the application for material change of use been made under the P & E
Act, since it sought approval for a number of uses prohibited under the 1994 Scheme, it would have been an
application to amend the planning scheme by re-zoning the site pursuant to ss 4.3 and 4.4 of the P & E Act.
[28] When assessing a development application to which a transitional planning scheme applies s 6.1.29(3) of
the I P Act sets out the matters, to the extent that they are relevant, which will be applied. These include,
relevantly, the transitional planning scheme and the applicable matters stated in s 4.4(3) of the P & E Act -
traffic issues and the detrimental affect on the amenity of the neighbourhood in this case.
[29] Such a development application is required under the I P Act by s 6.1.30(3)(a) to be decided pursuant to s
4.4(5) and (5A) of the P & E Act. Section 4.4(5) obliges the local government in deciding an application made
pursuant to s 4.3 to approve the application, approve it subject to conditions or to refuse it Section 4.5(5A)
provides
�The local government must refuse to approve the application if �
(a) the application conflicts with any relevant strategic plan or development control plan; and
(b) there are not sufficient planning grounds to justify approving the application despite the conflict.�
[30] It was undisputed below that 44 Ashmore Road is within the Residential Dwelling House Zone and the
Detached Housing Preferred Dominant Land Use designation under the 1994 Scheme and is surrounded, save
for its frontage to Ashmore Road, by similarly designated sites. All planning permission to use properties in
this vicinity along the southern side of Ashmore Road as medical centres were given before the 1994 Scheme
commenced operation. If and when those properties cease to be used as medical centres, the sites will revert to
their former use as residential dwelling houses. Such a use as a medical centre is a prohibited development
under the 1994 Scheme. All of the consents permitting use of the land for home occupation were given under
the 1994 Scheme.
[31] An appeal from the refusal by the local government of a development application is a hearing de novo
and the Planning and Environment Court must decide the appeal based on the laws and policies applying
when the application was made but may give weight to any new laws and policies it considers
appropriate, s 4.1.5.2(1) and (2) of the I P Act.
[32] It is convenient now to turn to the 1994 Scheme. Part 4 relates to �Residential Zones�. The intent of the
zone as expressed in s 4.3.1 is to implement the objects of the Detached Housing Preferred Dominant Land
Use in the Strategic Plan which is described in Part 1: �The maintenance of residential amenity is a major
priority for the Council in relation to detached housing areas. Residents of such areas have consistently
expressed the view that residential development should be mainly restricted to detached housing. Accordingly
the preferred dominant land use is detached housing on individual allotments. This form of development
facilitates a wide range of domestic activities, including gardening, private recreation and the keeping of pets.
Other development may include townhouse development, integrated housing and aged persons accommodation
subject to such development being at a scale and density compatible with detached housing. A very limited
range of non-residential development which is either ancillary to residential development or directly serves the
convenience needs of the local neighbourhood may also be appropriate in some locations.
[33] Section 4.3.1 of the 1994 Scheme describes to the intent of the Residential Dwelling House Zone.
�It is intended therefore to provide for the development of detached dwelling houses in an almost exclusively
low density residential environment. All residential development with the exception of dwelling houses, dual
occupancy dwellings, aged persons accommodation, townhouse development and integrated
© www.ecodirections.com
10
housing as well as most non-residential development will be excluded from this zone. The purpose of these
restrictions on development is to provide residents with the assurance that their chosen residential area will
remain free from unwarranted intrusion by incompatible development. All development within the Residential-
Dwelling House Zone will be subject to provisions which seek to ensure a pleasant, low density living
environment. Permissible development is restricted to townhouse development, integrated housing and aged
persons accommodation at densities compatible with low density dwelling house development, as well as non-
residential development which may be compatible with and complimentary to residential development . . .
Within this zone a high priority will be given to maintaining the integrity of residential areas and accordingly
permissible development will not be approved if such development can reasonably be located elsewhere.
Permissible development should generally locate in situations which minimise impact on residential amenity
and which do not introduce additional traffic into minor residential roads including residential access, cul-
desac and minor collector roads. Any permissible development will only be approved if it can be shown that
such development is complimentary to and compatible with the surrounding area.�
[34] Section 4.3.2 sets out the Table of Development for the Residential Dwelling House Zone. Column 1
concerns permitted development which does not require the consent of the Council which is confined to
�Dwelling House and Park�. Column 2 concerns �permitted development subject to conditions�.
Those nominated are:
�(a) Dual occupancy dwelling house, Family day care home, Outdoor recreation (private non-illuminated
tennis courts only), Special accommodation.
(b) Minor building work in respect of any of the developments specified in Column 3 where that development
exists on the site and has been lawfully established�. Column 3 concerns �permissible development� which
may be undertaken only with the consent of the Council. They are: �Aged persons accommodation, Caretakers
residence (only on sites in excess of 1200 square metres), Child Care Centre, Townhouse development (only in
accordance with s 4.12), Display home, Home occupation, Integrated housing, Neighbourhood store, Outdoor
recreation (private illuminated tennis courts only), Public utility, Temporary sales office.� Column 4 concerns
�prohibited development� which is development which may not be undertaken and that is any development
other than that referred to in columns 1, 2 and 3.
[35] That the intention of the planning authority was that the Scheme was not to be lightly departed from is
reflected in s 17.1.2.3:
�Without limiting the generality of the Council�s discretion to refuse an application, it shall be sufficient
reason to refuse an application to rezone land where such rezoning would be in conflict with any provision of
this Planning Scheme applicable to the area sought to be rezoned.�
[36] It is no longer necessary to apply to rezone land if an applicant wishes to use land for purposes
prohibited by its current zoning, and a development application under the IP Act relating to a transitional
planning scheme is not to proceed as if it were a re-zoning application. The transitional planning scheme
is one of a number of matters which s 6.1.29(3) of the IP Act directs shall be considered when assessing an
application for material change of use and is, therefore, as Davies JA said [14] in Vynotas Pty Ltd v Brisbane
City Council [2001] QCA 24; (2001) 112 LGERA 206, of persuasive relevance only. Nonetheless, s 6.1.2(1)
and (3) plainly require weight to be given to the fact that the use sought was a prohibited use under the
transitional planning scheme. Making the transitional planning scheme one of several matters to take into
account does not �create a planless situation� as Pincus JA said in Vynotas. �Citizens expect reasonable
© www.ecodirections.com
11
stability in the law�s treatment of permitted land use. It would be unfortunate if Ch 6 were used to defeat the
reasonable expectations of those who have relied on, and perhaps expended substantial sums on the faith of,
existing planning arrangements. The degree of flexibility which Ch 6 contemplates does not justify failure to
give considerable weight to planning arrangements, as they existed when Ch 6 commenced, so far as such
arrangements are required to be applied by s 6.1.29(3).� [22] Thomas JA agreed with those observations at
[24]. There can be little doubt that s 6.1.2 of the IP Act maintains the importance of consistency with the intent
of a transitional planning scheme.
The judgment below
[37] The Council contends that the learned judge below exceeded his jurisdiction by reflecting upon the
appropriateness of the 1994 Scheme in so far as it concerned the application of the Residential Dwelling
House Zone to 44 Ashmore Road and concluding that it was not an appropriate designation for that site. Mr
Gibson QC for the respondents submitted that far from falling into error, his Honour was doing no more than
assessing the merits of the application which would, under a rezoning application, fall to be considered.
[38] The proper approach of the Planning and Environment Court and of its predecessor, the Local
Government Court, to matters of planning policy has long been recognised as one of restraint. Most recently
this Court affirmed the desirability of a self-limiting approach, at least when considering town planning
matters in Holts Hill Quarries Pty Ltd v Gold Coast City Council [2000] QCA 268 unreported decision of 14
July 2000. The Court quoted with apparent approval at [42] the following passage from the judgment of Quirk
DCJ in Elan Capital Corporation Pty Ltd v Brisbane City Council [1990] QPLR 209 at 211: �It should not be
necessary to repeat it but his [sic] Court is not the Planning Authority for the City of Brisbane. It is not this
Court�s function to substitute planning strategies (which on evidence given in a particular appeal might seem
more appealing) for those which a Planning Authority in a careful and proper has to adopt (sic) (Brazier v
Brisbane City Council 26 LGRA 322 at 327). As was observed by Carter J in Sheezel & Anor v. Noosa Shire
Council [1980] QPLR 130 (when he then constituted this Court), it would be quite inappropriate for this Court
to deal with an individual application for rezoning in a way which might be construed as determinative of
some wider question. Adopting the phraseology of those cases which deal with the non-derogation principle, I
feel that to allow this appeal would be to �cut across� in quite unacceptable manner, a planning strategy which
has been adopted by the Planning Authority and publicly exhibited for community comment.� This stated a
proposition which the Court said was �common sense . . . for which no authority was required�. See also
Ampol Petroleum (Q�land) Pty Ltd v Pine River Shire Council [1989] QPLR 133 per Row DCJ at 134, 136;
Bullock v Hervey Bay Town Council [1983] QPLR 98 per Carter DCJ at 100; Cherrabun Pty Ltd v Brisbane
City Council [1985] QPLR 205 per Quirk DCJ at 208; and the discussion in Fogg Land Development in
Queensland (1987) pp 390 et seq.
[39] After setting out the intent of the Residential Dwelling House Zone in the 1994 Scheme and noting that
the uses applied for of educational establishment, indoor recreation, shop and restaurant were prohibited
uses, the learned judge below said, in a passage which Mr Keane QC for the Council submitted clearly
demonstrated an erroneous approach to the task, �In order to consider the appropriateness of the provisions
of the intent for the Residential Dwelling House Zone in this case, it is necessary to consider the range and
type of uses already approved in the area� [21].
[40] It is not necessarily indicative of error to use the expression �appropriate� when referring to the intent
for the particular land designation but, in context, it may point in that direction. His Honour proceeded after
© www.ecodirections.com
12
the passage quoted above to describe the use of the land on the northern side of Ashmore Road as �intensive
commercial and retail development� and the use of the land on the two blocks around the subject site on the
southern side which, as has been mentioned above, comprise 28 properties being 9 medical centres and 8
home occupation uses and 2 unlawful non-residential uses and noted that land to the south fronting Coogeen
Street was purely residential.
[41] His Honour concluded:
�In these circumstances, having regard to the range and type of uses already approved in the area, I do not
regard the provisions of the Residential Dwelling House Zone as entirely appropriate to the subject land. No
doubt some type of residential development on the site would be possible. However, this, in my view, is unlikely
when one considers the problems presented by Ashmore Road and the commercial developments opposite (see
eg Harburg Investments Pty Ltd v Brisbane City Council & Ecovale Pty Ltd no. 2163 of 1999, unreported
decision of Skoien SJDC delivered 5 May, 2000)�. [27]
[42] There are two further passages in his honour�s reasons which Mr Keane submitted would suggest that he
evaluated and found wanting the local government�s planning policy. His Honour referred to certain evidence
given by Mr Grummit, a town planning consultant, who had given evidence about Special Development Areas
(�SDA�) particularly SDA no. 2 (low density office development) which was a special development area which
could not easily be accommodated in the existing preferred dominant land use designations described in the
1994 Scheme. These were areas situated throughout the City in locations which had a high degree of
accessibility to the main road network and a proximity to established commercial centres. The 1994 Scheme
described these areas as giving an opportunity to establish development which would provide an effective
buffer between residential premises and heavily trafficked roads adjacent to commercial development, see
Parts 1 � 23 of the 1994 Scheme.
[43] His Honour commented that the subject site was one which clearly accorded with such a description
although there was no suggestion that it was located within a SDA no. 2. A few paragraphs later there is a
suggestion that his Honour saw the southern side of Ashmore Road, in planning terms, as more appropriately
being located within just such an SDA no. 2 area. �A major negative impact upon the amenity of lots fronting
the southern side of Ashmore Road is created by the existing extensive commercial area along the northern
side of Ashmore Road and by the high traffic levels on that road. I am satisfied that the subject site and the
uses for which approval was sought will provide an effective buffer between the purely residential areas to the
south in Coogeen Street and the heavily trafficked Ashmore Road and extensive commercial development
immediately to its north� [41].
[44] It is well recognised that a town planning appeal court may depart from the planning intent of the local
government if the local government has itself departed from that intent or the subject land has been given a
designation that was and remained invalid, Beck v Council of the Shire of Atherton (1991) QPLR 56 at 59,
quoted with approval by Newton DCJ in Pacific Exchange Corporation Pty Ltd v Gold Coast City Council
[1998] QPELR 335 at 339 and following.
[45] It may be that his Honour mis-recalled some matters of fact such as caused him to suppose that the
Council had itself departed from the 1994 Scheme in its approach to sites along the southern side of Ashmore
Road in the vicinity of number 44. At [42] he said:
© www.ecodirections.com
13
�I have already observed that the respondent has approved numerous non residential uses, including some
eight medical centres in the two blocks to the east and west of the site. The majority of the medical
practitioners based at these centres are specialists, and, as such, could reasonably be expected to draw
patients from a very wide area of the city (or beyond). In these circumstances the centres are serving not just
the convenience needs of the local neighbourhood, but those of a wider area. I accept the contention that this
indicates acquiescence by the respondent in non-residential uses in the subject area and also in the
establishment of a precinct in the vicinity of the site which serves a wider function than the provision of
services to local residents only.� In the following paragraph his Honour commented that by the provision of
these services customers were drawn from a wide area and fulfilled uses envisaged by the provisions relating
to SDA no. 2 �rather than those of the detached housing designation�. He concluded:
�To some extent it may be said that the Strategic Plan so far as this particular area is concerned has simply
been overtaken by events to the stage where this portion of Ashmore Road is really dominated now by semi-
commercial aspects of the medical centres and home occupations� [73].
[46] His Honour referred to Plafaire Projects Australian Pty Ltd v Council of the Shire of Maroochy [1991]
QPLR 87 at 88. That was a very different case. Quirk DCJ noted the importance of the strategic plan as a
planning instrument but that the Shire itself had approved a rezoning to a different zone land next to the
subject land and which had affected the future of the area in a very significant way. In a passage which
resonated with his Honour, Quirk DCJ said the court was �dealing with a plan which (so far as this particular
area is concerned), has simply been overtaken by events.� See also his comments in Beck at 59.
[47] It seems that his Honour failed to recall that the medical centres upon which he appeared to place so
much reliance for this state of affairs had been approved prior to the 1994 Scheme, that none had been
approved since, that they were a prohibited development use for this area and if they ceased to operate as
medical centres the sites would revert to being residences and that they were contrary to the clearly expressed
intent of the Strategic Plan and that the Council had not department from adherence to that Plan. His Honour
made findings about amenity, traffic consideration and the objections to the application and no complaint is
made about those findings. Even though the Strategic Plan is one of the factors to take into account it is an
important factor. It appears that his Honour�s perceived error about the medical centres so infected his
approach that he impermissibly �cut across� the planning strategy adopted by the Council and exceeded his
jurisdiction.
[48] The second major ground of appeal concerns his Honour�s approach to s 4.4(5A) of the P & E Act. He
noted conflict with the Strategic Plan but, Mr Keane submitted, fell into error by identifying a threshold
discretion which is not in s 4.4(5A)(a) and exercised it in favour of the respondents without
considering the discretion in s 4.4.(5A)(b). Of s 4.4(5A)(a) his Honour said: �Despite the conflicts with the
Strategic Plan that have been identified, these are not, in my opinion, so fundamental (italics added) as to
enliven the provisions of section 4.4(5A) of the Local Government (Planning & Environment) Act 1990 which
required that an application be refused if it conflicts with any relevant strategic plan and there are not
sufficient planning grounds to justify approving the application despite the conflict�.
[49] Section 4.4(5A) is a simple two-stage process which first requires the identification of conflict with the
Strategic Plan, then, if conflict is present, the application must be refused if there are not sufficient planning
grounds to justify approving the application despite the conflict. Mr Gibson submitted that it was not
appropriate to take the words �so fundamental� out of the judgment and focus upon them as an indication that
© www.ecodirections.com
14
his Honour had introduced, in effect, a discretion at the first stage. Even though his Honour referred to
various matters which might be described as �planning grounds� earlier in his judgment, it is not at all
apparent that by using the expression �so fundamental� he did not apply a test different from that set out in
the section. This constituted an error of law and because his Honour has not overtly exercised the discretion in
the way in which he was required by s 4.4(5A)(b) his decision is flawed. [50] Mr Keane submitted that this Court ought to decide the issue of the sufficiency of the planning grounds
for itself because all the evidence that could have been adduced in favour of the respondents was before the
Planning and Environment Court. He contended that none of that material indicated any �positive� planning
grounds to support approval of the proposal. As was pointed out by Mr Gibson, the section itself does not refer
to �positive� planning grounds. However it does require that the planning grounds to be �sufficient�. The
discretion is couched in negative terms, that is, that the application must be refused if there are not sufficient
planning grounds. This might suggest that something more is required than negative impact on the
surrounding amenity and want of relevant objection.
[51] The hearing took three days before the Planning and Environment Court. No evidence was adduced
which could constitute sufficient planning grounds to approve the application despite the conflict. In argument
before this Court no potential area of evidence which might do so was identified. There is,
therefore, no utility in returning the matter to the Planning and Environment Court.
[52] When the Court gave leave to appeal it ordered that the costs of the application be costs in the appeal.
[53] The orders of the Court should be:
1. Appeal allowed with costs to be assessed.
2. Set aside the order of the Planning and Environment Court and in lieu thereof order that the appeal to
that court be dismissed.
8. The question of town planning or community need is often a matter of debate before the Planning and Environment
Court. The evidence will vary in each individual case. The question of law which the Court of Appeal examined
related to whether or not the Planning and Environment Court Judge went too far in finding that there was no need
for the tavern facilities proposed in Arksmead Pty Ltd v Gold Coast City Council [2001] 1 Qd R 247. The
appeal by the unsuccessful developer to the Court of Appeal was dismissed. The following comments by the Court
of Appeal Judges are of assistance:-
[1] THE COURT: This is an appeal from a judgment given in the Planning and Environment Court at
Southport on 23 April 1999. The formal order was dated 13 May 1999.
[2] On 21 October 1997 the appellant, the owner of vacant land at 2 Bell Place, Mudgeeraba village, applied
to the first respondent under s. 4.12(1) of the Local Government (Planning and Environment) Act 1990 for
town planning consent to use the land, 8,030 square metres in area, for a tavern, a drive-through bottle shop,
showrooms, and a car wash. The first respondent failed to make a decision on the application in the required
time and so was deemed to have refused it. The appellant then instituted its appeal to the Planning and
Environment Court in which it was unsuccessful. We shall set out in greater detail later his Honour�s reasons
for dismissing the appeal, but, in summary, they were that the tavern, the bottle shop and the car wash, for
which there was no proved need in Mudgeeraba village, would adversely affect the amenity of the village. His
© www.ecodirections.com
15
Honour made it clear that the �need� he was referring to was community need �in the planning sense�, and not
the commercial need of a developer or the needs of those who oppose a development.
[3] �Amenity�, as Dr Alan Fogg wrote in his Land Development Law in Queensland (1987), is �one of the most
over-employed words in the vocabulary of planning jargon � � (p. 430), but it is accepted that the word refers
to �that element in the appearance and layout of town and country which makes for a comfortable and pleasant
life rather than a mere existence�: Ex parte Tooth & Co. Ltd; Re Parramatta City Council (1955) 55 S.R.
(N.S.W.) 282 at p. 306. The concept of amenity is wide and flexible, and intangible factors and subjective
considerations may be relevant to a decision on the effect of a proposed use on the amenity of the area
affected: see Broad v. Brisbane City Council & Anor [1986] 2 Qd. R. 317. Such factors and considerations
were relevant in this case.
[4] His Honour�s decision was then that, if the sought-after consent were to be given, the comfort and pleasure
of residents of, and visitors to, Mudgeeraba would be diminished by the intrusion of activities for which there
was no need.
[5] By operation of s. 6.1.25 of the Integrated Planning Act 1997 the Local Government (Planning and
Environment) Act, now repealed, continues to apply to this proceeding. Under s. 7.4(3) of the latter act an
appeal to this court may be made only on the grounds of error or mistake in law, or absence of, or exceeding,
jurisdiction.
[6] The appellant contends that his Honour made three errors of law: first, in considering the question of
need, secondly in dealing with the question of whether the amenity of the village would be affected by the
appellant�s proposal, and thirdly in confining his attention to the appellant�s final proposal for the
development rather than considering as well a proposal accepted after the institution of the appeal by the first
respondent.
[7] The first step in the appellant�s argument on the question of need was to refer to decisions of the Local
Government Court and the Planning and Environment Court in which it had been held that it was not essential
for success on an application for town planning consent to establish need for the proposed use: Zaini & Anor
v. Caboolture Shire Council [1984] Q.P.L.R. 223 at p. 225; W. H. Bowden v. Pine Rivers Shire Council &
Anor [1986] Q.P.L.R. 268, at pp. 269-270; Theodorou v. Redland Shire Council [1987] Q.P.L.R. 11 at p. 14;
and Ogilvy v. Redland Shire Council & Ors [1996] Q.P.E.L.R. 205 at p. 210. That proposition is not in doubt -
so far as it applies to a case in which the question of need has not become an issue. There are, it may be
accepted, many cases in which consent is applied for in which an issue of need does not arise. When that is so
there is no reason to conclude that the applicant should be required to establish need.
[8] We see no reason in principle, however, why an issue of need, or its absence, cannot properly arise on an
application for consent. As Quirk D.C.J. said in Zaini & Anor v. Caboolture Shire Council, an appeal arising
out of the respondent�s refusal of an application for consent to use land for a catering shop and fruit stall:
I am not at all sure that it is essential, where an application for approval for a consent use is being dealt with,
that it be shown that a �need� (as it is properly understood in a town planning context) for the proposal exists.
In many cases it may well be a relevant consideration . . . (p. 225, our emphasis) The same judge said this in
Theodorou v. Redland Shire Council, an appeal against the respondent�s refusal of an application for consent
to construct a service station: I should say something about �need� as the matter was raised in the appeal and
was the subject of some evidence. The relevance of �need� where a discretionary use is being considered has
been the matter of some debate. I regard it as a factor which (while by no means being determinative) can at
© www.ecodirections.com
16
times be considered. For example, the absence in an area of a particular facility which would be of benefit to
the community might be a matter which would favour an approval of a development that would lead to the
provision of such facility. It is in the context of �community interest� that such matters are judged. (p. 14)
Here the argument for the appellant was that while proved need for �licensed facilities� can work in favour of
an application, proved absence of need cannot work against a proposal.
[9] For that proposition we were referred to a passage in the reasons of Quirk D.C.J. in Hughes & Ors v.
Emerald Shire Council & Ors [1996] Q.P.E.L.R. 110, an objectors� appeal against approval of an application
for consent for the �development� of an hotel: The matter of need may, in some circumstances, work in favour
of a particular application (Theodorou v. Redland Shire Council (1987) Q.P.L.R. 11). Usually however, the
fact that a particular proposal might give rise to commercial difficulties for competitors is not relevant unless
it is �accompanied by a prospect of a resultant overall adverse effect upon the extent and adequacy of
facilities available to the local community� (Kentucky Fried Chicken Pty Ltd v. Kantidis (sic) (1978) 140
C.L.R. 675 at 687). (p. 112) There was in this case no issue of the kind referred to in the passage cited by
Quirk D.C.J. from Kentucky Fried Chicken Pty Ltd v. Gantidis, which comes from the reasons of Stephen J.,
but the question of need was an issue. It may be noted that Quirk D.C.J. did not explicitly say that proved
absence of need cannot work against a proposal, nor does it necessarily follow from what his Honour said. It
was submitted to us on behalf of the appellant that the principle it sought to draw from the passage from Quirk
D.C.J.�s words in Hughes & Ors v. Emerald Shire Council & Ors was applied in Jenk Holdings Pty Ltd v.
Whitsunday Shire Council [1998] Q.P.E.L.R.151, in which consent for use of land for a tavern was the subject
of the appeal, but as we read the reasons given in that case it was the principle drawn from Kentucky Fried
Chicken Pty Ltd v. Gantidis that was applied.
[10] In Whitehead & Ors v. Hervey Bay City Council & Ors [1998] Q.P.E.L.R. 55, an appeal arising from the
approval of an application for consent for the construction of a child care centre, the primary judge in the
present matter took the view that evidence directed to the question of need was irrelevant: During the hearing,
I ruled that the evidence directed towards the question of need in this case was irrelevant. The matter of need
might, in some circumstances, work in favour of a particular development. See, for example, the decision in
Hughes & Ors v. Emerald Shire Council & Ors (1996) Q.P.E.L.R. 110, which accepted that a clearly
demonstrated and unmet need might be a positive reason in favour of consent. At the other end of the scale, it
may be shown that a proposed development is �accompanied by a prospect of a resultant overall adverse
effect upon the extent and adequacy of facilities available to the local community�. See the decision of the
High Court in Kentucky Fried Chicken Pty Ltd v. Gantidis (1978) 140 C.L.R. 675. It became apparent that the
question of need here was in neither of those extreme categories. (p. 59) With respect, we do not think it
follows from Quirk D.C.J.�s words in Hughes & Ors v. Emerald Shire Council & Ors that the question of need
can arise only in the two �extreme categories�. At all events his Honour appears to have taken a different view
in the present matter from that he expressed in Whitehead & Ors v. Hervey Bay City Council & Ors, and it is
his analysis in this case with which we are concerned. This court is of course not bound by any decision of the
Planning and Environment Court on a question of law, although decisions of that court are entitled to respect.
[11] The respondents include Ecovale Pty Ltd, which owns the Wallaby Hotel in Mudgeeraba, and Donald and
Celia Murphy, who own and operate a licensed restaurant in the area. On their behalf we were referred to
quite a long list of cases in which need, or its absence, had been an issue. It will suffice to refer to two of the
© www.ecodirections.com
17
cases, which demonstrate clearly how the issue of need, or its absence, can be relevant. The Readymix Group
Ltd v. Brisbane City Council & Ors [1982] Q.P.L.R. 46, an appeal against the Council�s refusal of consent for
a use which could not be made of the land without consent, came before Byth D.C.J. in the Local Government
Court at Brisbane. The appellant had sought permission to operate a quarry in the non-urban zone. His
Honour dismissed the appeal. He found that the community had a continuing need for aggregates and road-
base materials, but, having regard to the �opposing factors in the case�, did not find that the community need
was such that the land in question should be quarried. His Honour said, �it would be convenient to the
operators to work this site. I find that the resources and the reserves of road-base material and aggregate in
and near Brisbane are such that it cannot be said that public need requires the quarrying of this particular
site, in all the circumstances� (p. 54). The �opposing factors� included �detriment to the present and future
amenity of the area, and damaging effects on roads by heavy haulage operations� (p. 55).
[12] A more recent decision that turned on considerations of need and effect on amenity was Trio Pearl Pty
Ltd & Anor v. Council of the City of Gold Coast & Anor [1996] Q.P.E.L.R. 179 before Newton D.C.J. in the
Planning and Environment Court at Southport. It was an objectors� appeal against a decision of the Council to
approve the use of land in a residential-dwelling house zone for a child care centre. His Honour allowed the
appeal, concluding that there would be an unacceptable impact on the amenity of the surrounding residential
properties by the noise from children and traffic expected to result from the proposed use and that no sufficient
need had been demonstrated that would warrant the proposal�s proceeding (pp. 184, 190).
[13] In each of those cases the effect on amenity and need were considered and in each a detrimental effect on
amenity together with an absence of need was decisive. It is difficult to see how it could be said that their
Honours proceeded upon a wrong principle in treating the absence of need as a relevant consideration. In
such a case, if it is decided that the proposed development would have a detrimental effect on the amenity of
the area in question, the judge must then decide whether, notwithstanding the detrimental effect on the amenity
of the area, there has been shown to be a need for the proposed use which would render the effect on the
amenity of the area justifiable.
[14] Neither the Readymix case nor the Trio Pearl case was a case in which �licensed facilities� were part of
the proposed use. On behalf of the appellant it was asserted that cases in which a liquor licence is required
are in a special category. It was argued that their being in a special category adds weight to the proposition
that the proved existence of need is something which may bring about a result favourable to an applicant but
that consideration of absence of need was denied to the Planning and Environment Court. For that proposition
reliance was placed on a number of provisions of the Liquor Act 1992 applicable to a general licence, which
was what was required by the appellant.
[15] Section 116(2) of the Liquor Act provides that an applicant for a general licence must satisfy the chief
executive of the department that the licence applied for is �necessary to provide for reasonable requirements of
the public for liquor and related services in the locality to which the application relates�. Section 116(3)
provides that an applicant must give certain specified information to the chief executive for the purpose of
satisfying him or her about the reasonable requirements of the public as mentioned in subsection (2).
Subsection (4) provides that in �deciding the reasonable requirements of the public� the chief executive must
take into account information about the matters mentioned in subsection (3) and must have regard to:
(a) the population and demographic trends in the locality; and
© www.ecodirections.com
18
(b) the number and kinds of persons residing in, resorting to or passing through the locality, or likely in the
foreseeable future to do so, and their respective requirements or expectations; and
(c) the extent to which any requirement or expectation-
(i) varies during different periods or at different times; and
(ii) is lawfully met by other premises, licensed or unlicensed; and
(d) the likely health and social impact that granting the application would have on the population of the
locality. Section 118A provides that, in relation to such an application, a member of the public may make a
written submission to the chief executive about:
(a) the reasonable requirements of the public in the locality to which the application relates; and
(b) the matters to which the chief executive must have regard under section 116.
The effect of s. 29A and s. 30 is, however, to exclude from those entitled to appeal against a decision of the
chief executive to the Liquor Appeals Tribunal members of the public who have made written submissions to
the chief executive under s. 118A.
[16] It was argued on behalf of the appellant that those provisions constituted a code in accordance with
which questions of need for premises requiring a general licence are to be decided. If that is correct then the
question of need or the absence of it would, one might think, be completely removed from the purview of the
Planning and Environment Court.
[17] How the existence of need and not its absence could then be considered relevant by the Planning and
Environment Court, as contended on behalf of the appellant, is difficult to comprehend. His Honour the
primary judge referred to that difficulty in the following passage in his reasons: In this case, town planning
need has been an actual issue between the parties. It was Arksmead�s case at the hearing that there was a
positive need for this hotel and bottle shop at Mudgeeraba. Its opponents resisted that claim, and led evidence
to the contrary. It is said for Arksmead that, while a demonstration of need would work in its favour, the
absence of need is not a factor which could work against its proposal. It is true that the presence of need does
not have to be demonstrated here to succeed in the application for consent. However, once the issue becomes
the subject of evidence, the applicant always runs the risk that there may be a finding that there is no need. If
that happens, it is disingenuous to say that the question of need should be disregarded, as it cannot work
against the proposal. If the evidence shows that there is no need, then that can ill be a reason for rejecting the
application for consent. The appellant�s argument in reliance of the Liquor Act nonetheless has we think some
merit, for to reject it results in acceptance that need may be an issue in two fora. There is, however, nothing
express in either the Liquor Act or the Local Government (Planning and Environment) Act to that effect. The
result of accepting the appellant�s argument would be to eliminate an obvious issue that in the ordinary course
of things could arise in a case in which a detrimental effect on amenity is the principal issue, as in the
Readymix and the Trio Pearl cases - and of course in this case. Such cases would then be unnaturally
circumscribed. There is also the important consideration that members of the public cannot have their
legitimate concerns aired on appeal from a decision of the chief executive. To construe the provisions of Acts
in the way contended for by the appellant would be to deprive them of an avenue of appeal. Furthermore, the
approval of more than one authority is a common feature in commercial projects that require town planning
authority approval: Walker v. Noosa Shire Council [1983] 2 Qd. R. 86, at p. 90.
[18] Taking those matters into account, we conclude that the legislature did not intend to deprive the Planning
and Environment Court of the authority to consider the question of need or the absence of it in a case like the
© www.ecodirections.com
19
present one; and see also: Bell & Ors v. Brisbane City Council & Anor [1982] Q.P.L.R. 375, at p. 378, and
Poir Hotels Pty Ltd v. Brisbane City Council & Anor [1989] Q.P.L.R. 188, at p. 190. His Honour made no
error of law on that subject. After a detailed analysis of the evidence including that of Mr Peter Kleineberg,
hotel and tavern consultant, the only witness who gave evidence on the question of need on behalf of the
appellant, his Honour concluded that the appellant had failed in its attempt to demonstrate that there was a
need for the proposed tavern and bottle shop � and indeed there was what his Honour called a �positive
absence of need�. Such a conclusion was open on the evidence and relevant to his Honour�s final
determination. We should add that the appellant�s case was argued in such a way as to treat the issues of need
and amenity as discrete. To divide his Honour�s reasons into separate compartments is to misconstrue them:
the amenity issue and the need issue were necessarily related.
[19] We now pass to the argument on the amenity issue.
[20] In the reasons his Honour gave for his decision he discussed the community of Mudgeeraba and its
character:
The evidence established that Mudgeeraba is a village whose origins lie in the last century. It is unique on the
Gold Coast. Physically, it is characterised by buildings in the distinctive colonial style. Emotionally, its
inhabitants show a sense of pride in the village, with strong community feeling. A number of local witnesses
gave evidence, in addition to the town planners. In particular, Mrs Goff and Pastor Magee spoke of the strong
sense of community among its residents. Mrs. Simpson gave evidence to the same effect. As well as appearing
on her own behalf she appeared on behalf of the Mudgeeraba Community Association. Her presence
throughout the trial was a constant reminder of the community�s rejection of Arksmead�s proposal. His
Honour referred to another nearby centre on the Gold Coast, Robina: Mudgeeraba can be compared to
Robina, which lies only three kilometres to the east. It is a very large and recent development. It is a business
centre, while Mudgeeraba remains a district centre. A development control plan for Mudgeeraba shows,
consistently with the relevant strategic plan, that one of its objectives was to �maintain and promote a colonial
village atmosphere in the Mudgeeraba Business Centre�.
[21] His Honour referred to objections to the proposal: This project has resulted in many objections. There
are 240. They concentrate on the perceived problems of increased noise from the hotel bottle shop, the
increase in traffic to the development, conflicts with the D.C.P. 3, and the impact of the development on the
�village� atmosphere of Mudgeeraba. A petition was collected. There are some 1,300 names in it. The
grounds of objections are these:
1. Undue offence, annoyance, disturbance and inconvenience to persons who reside or work or do business in
the locality, and travel to or from church and school in the locality, and
2. If the application is granted the amenity, quiet or good order of the locality would be lessened. The evidence
revealed that Ecovale had given support to the organized opposition. That is not surprising. A public meeting
was chaired by Mr David Anderson, from the Wallaby Hotel. An advertisement against the proposal was
funded by Ecovale. It is necessary to discount the level of objections, and the number of petitioners, because of
such self-interested activities. Even when that is done, it is clear that there is a high level of local opposition to
this proposal. The opposition centres on the proposed hotel and bottle shop. That opposition should be given
weight for two reasons. It is relevant to the question of amenity, and also to the question of need. Amenity does
not include just the physical appearance of the surroundings. It also includes the emotional or sentimental
feelings that people may have about a place. An explanation for the amount of opposition can be found in the
© www.ecodirections.com
20
evidence about the village character of Mudgeeraba. Not only does it have physical characteristics based on
its colonial background, it also has generated a strong community feeling about its future. Those strong
feelings have given rise to much of the present opposition. Those feelings should be taken into account, with
respect to the amenity issues.
[22] His Honour recorded his conclusions as follows:
Here, the evidence shows that the tavern, the bottle shop, and the car wash, will have a detrimental impact on
the amenity of the Mudgeeraba village. Some of the physical impacts are slight and have already been
discussed � such as traffic. Inevitably, there would also be some impact from noise and the occasional unruly
behaviour of patrons, no matter how well designed the building, or well managed its operation. Such impacts
are out weighed by those of a more intangible kind. It is the very presence of a development including a tavern
and bottle shop which will be a detriment. Its location, which overlooks the playing fields of Firth Park, should
also be kept in mind. That is an area which is enjoyed by many families and children. Overall, the evidence
demonstrates that the amenity of the Mudgeeraba village will be diminished by this proposal, including as it
does a tavern and bottle shop. The proposed car wash will have a slighter impact on amenity. The question of
the midblock pedestrian linkage has been dealt with. The question of a �contribution to the village� is to be
judged by requirements of the town planning scheme. While there may be other functions which could be
introduced onto this land (as Mr Vann observes) that is not a conclusive objection. The topography, and the
absence of any residences immediately nearby, greatly reduces the impact of the criticism, that this proposal
turns its back on the village. From a design point of view, it is the car wash which attracts criticism. The
proposal here is to engraft a mock colonial design on a piece of contemporary machinery designed to assist
the owners of motor vehicles. The hotel and the showrooms might readily be given a suitable colonial design.
The bottle shop might just be included in that list. However, it is not easy to see that the car wash is a �visually
appropriate� structure. It is necessary to keep steadily in mind the planning provisions in para 2.4.5.3 � the
development that might be permitted in this precinct. The hotel and car wash (the latter accepted to be within
the meaning of �service industry�) have to be considered on merit in that precinct. This court has the
advantage of evidence not available to the Council. It is apparent that the positive absence of need, the
duplication of facilities, and the detrimental impact on amenity which would be caused by the tavern, the bottle
shop and car wash, and the undesirable appearance of the car wash, mean that the application should be
rejected. There is not �sufficient merit� to enable approval to be given. On behalf of the appellant it was
submitted that his Honour�s conclusion concerning the effect of the proposal on the amenity of the area was
flawed in that he took into account two matters which he ought not to have taken into account: first, Mrs
Eunice Simpson�s presence throughout the hearing of the appeal, which, as can be seen in a passage from his
Honour�s reasons quoted above, he described as �a constant reminder of the rejection of Arksmead�s
proposal�; and secondly, the petition with some 1,300 names on it.
[23] His Honour�s comment concerning Mrs Simpson�s attendance at the hearing does not reveal that his
Honour made the suggested error of law. It goes no further than recording, in an innoxious comment, that her
attendance for the whole of the hearing was a reminder of the substantial body of evidence before his Honour
showing community opposition to the appellant�s proposal. It was a reminder of that evidence, but not
evidence in itself.
© www.ecodirections.com
21
[24] The submission as to his Honour�s making an error of law in taking into account the petition is similarly
without merit in our view. Reliance for that proposition was placed upon the decision of Mylne D.C.J. sitting
in the Local Government Court at Cairns in Allen v. Atherton Shire Council (1977) 4 Q.L. 266. In that case
there were two appeals by objectors against the proposal of the respondent Council to use a recreation reserve
for the �development� of a library. There was tendered in evidence a petition signed by a large number of
people seeking a poll on whether the open space of the recreation reserve should be used for the building of a
library. It was argued that until such a poll was held there was good reason not to give a decision that might
result in frustrating the opinion of the electors expressed in the poll. The poll was sought under s. 53 of the
Local Government Act 1936-1977 which provided that a local authority might at any time, and should when so
directed by the relevant minister, �take a poll� of electors on certain specified questions. The respondent had
not decided, and the minister had not directed, that such a poll be held. Mylne D.C.J. concluded that the
decision of the court should not be delayed until a poll were held, adding, �[t]he petition is not a factor to be
considered in determining the merits of the appeal if the Local Government Act prescribes the method whereby
objectors to a proposed development may be heard� (p. 272). That case is clearly distinguishable from the
present case in that what was in question in that case was a petition to put machinery in motion to ascertain
the views of electors, whereas in this case the petition was a clear expression of opinion by those who signed it
on an issue which was before the Planning and Environment Court.
[25] The petition is headed �To Object to the Grant of Application for General Liquor License made by
Arksmead Pty Ltd ATF Marshall Trust, by its Nominee Anthony Whitcroft�, indicating that the people who
signed it did so in relation to an application under the Liquor Act. But the grounds of objection set out in the
petition show that it is relevant to the amenity issue before his Honour. The grounds were these:
1. Undue offence, annoyance, disturbance and inconvenience to persons
[a] who reside or work or do business in the locality
[b] travelling to and from church and school in the locality
2. If the application is granted the amenity, quiet or good order of the locality concerned would be lessened.
The coincidence of issues before the liquor licensing authorities and the Planning and Environment Court
renders the petition relevant and admissible before the latter in our view. There is always a question of weight
to be considered when reliance is placed upon a petition, and, in this case, the fact that the petition was signed
in connexion with an application for a liquor licence is perhaps a further matter to be considered when
assessing its weight. Its relevance to the issues before his Honour, however, justifies his Honour�s reception of
it in evidence and his consideration of it in reaching his decision. We see no error of law in his having done so.
[26] It was argued on behalf of the appellant that the third error of law his Honour made was in concluding
that it was open to him to consider only the plan of the appellant�s proposal, which was exhibit 20 (drawing
SK2E). Exhibit 20 was the appellant�s preferred plan at the hearing, but there were two other plans in
evidence before his Honour: exhibit 1 (drawing SK2A), the plan that was included in the application for town
planning consent and available for inspection by any potential objector, and exhibit 2 (drawing SK2D) which
was the only plan of the proposed development the first respondent supported. At the hearing it became
obvious that the appellant would accept the plan supported by the first respondent, although exhibit 20
remained its first preference. There was a difference between exhibits 1 and 2 which caused an issue to arise
before his Honour. There was, however, no difference of any moment between exhibits 1 and 20.
© www.ecodirections.com
22
[27] The Local Government (Planning and Environment) Act did not expressly confer on the Planning and
Environment Court power to approve a proposed development which was different from that which
accompanied the initial application to the local authority. This Court held, however, in Ecovale Pty Ltd v.
Gold Coast City Council [1999] 2 Qd. R. 35, that the Planning and Environment Court had a limited power
to do so, and that the limits of that power were to be derived by implication � or analogy - from s. 4.15 of the
Local Government (Planning and Environment) Act.
[28] Section 4.15 provides for modification of certain applications and approvals. Subsection (1)(a) provides
that an application may be made to a local government seeking modification of an application to which the
section applies, and subsection (1A) provides that the section applies to an application for town planning
consent under s. 4.12(1), as this application was. Subsection (2) imposes restrictions on the power of a local
government to approve an application to modify made under subsection (1). Two of those restrictions were
relevant in this case. A local government is not to approve an application to modify where:
(a) in its opinion the modification is not of a minor nature;
(b) in its opinion the modification would adversely affect any person to a degree which would, if the
circumstances allowed, cause that person to make an objection;
His Honour found that this was not a case to which (b) applied, but found that the modification in question
was not of a minor nature. It was argued on behalf of the appellant that that finding proceeded from an error
of law. The modification was the removal of access at the north-western corner of the land. Bearing in mind
the conclusions we have reached on the other points raised by the applicant in this appeal, we conclude that it
is not necessary to decide this point. That is because his Honour�s conclusions concerning the detrimental
effect on amenity and on need were based on broader considerations than that of whether or not there was
access at the north-western corner of the land. But in any event his Honour�s conclusion on this point involved
no error of law.
[29] In reaching the conclusion that the modification was not of a minor nature his Honour was guided � as he
was bound to be � by subsection (3), which is as follows:
(3) For the purposes of subsection (2), a proposed modification is of a minor nature if�
(a) the proposed use to be made of the land the subject of the modification is not varied by the addition of
different uses;
(b) the gross floor area of buildings or proposed buildings on the site is to be increased by less than 5%;
(c) the number of storeys above ground level to be contained in any building or proposed building or part
thereof on the site is not to be increased;
(d) the locations of the proposed ingress to or egress from the site are not to be substantially altered;
(e) any altered ingress to or egress from the site is to be to or from the roads�
(i) approved by the local government in dealing with the relevant application; or
(ii) specified in the relevant application;
(f) the amenity or the likely future amenity of the locality would not, in the opinion of the local government, be
adversely affected by the proposed modification. His Honour explained his conclusion in this way: Here, the
ingress might involve from between 4% to 10% of the total generated traffic to the new development. The
Council sees important differences between access at the north-west corner, compared to no such access.
Bearing in mind the standard already set in subsection 3(d), it should be concluded that this modification
© www.ecodirections.com
23
is not of a minor nature. It follows that the Council�s preferred position is untenable � drawing number SK2D
cannot form the basis of an approval. It is therefore necessary to consider Arksmead�s preferred position,
contained in drawing SK2E � Exhibit 20.
[30] It is inherent in his Honour�s reasoning that the pertinent provision was subsection (3)(d): that since the
locations of the proposed ingress to the site were not such as not to be substantially altered, the modification
of exhibit 1 made in exhibit 2 was not of a minor nature. The removal of one of two places of ingress to a site is
clearly enough capable of being found to be an alteration which does not fall into the not-substantial category,
so we detect no error of law in his Honour�s doing so.
[31] It was also argued on behalf of the appellant that in failing to consider subsection (3)(f), as he was urged
to do on behalf of the appellant, his Honour fell into error. We are not persuaded that that was an error.
Subsection (3)(d) is the relevant provision in setting a standard to be applied to alterations of the locations of
the proposed ingress to a site, just as subsection (3)(b) sets a standard for alterations of gross floor area of
buildings or proposed buildings on a site, and (3)(c) sets a standard for alterations of the number of storeys
above ground level to be contained in any building or proposed building or part of such a building on a site. It
follows that the other provisions of subsection (3) were not germane to his Honour�s deliberations. If
subsection 3(f) were to have been considered relevant, its relevance would have been so slight when compared
with subsection 3(d) as to justify his Honour�s disregarding it. We therefore conclude that the appellant has
failed on its third point.
[32] The appeal should therefore be dismissed and the appellant ordered to pay the second respondents� costs
of the appeal.
9. From time to time the High Court decision in Pioneer Concrete (Qld) Pty Ltd v Brisbane City Council (1980)
145 CLR 485 is analysed by the Planning and Environment Court and the Court of Appeal. The most recent
example of that is in Brisbane City Council v Cunningham (2001) 115 LGERA 326. The concept of a piecemeal
application was developed by the High Court. However, in Brisbane City Council v Cunningham the facts of that
case lead the Court of Appeal to come to the conclusion there was no piecemeal application. Two applications were
made. One was for code assessment and the second was for impact assessment. They were made as separate
applications dealing with different parcels of land but there was a common area of car park for each of the two
applications. Mr Cunningham had objected to the advertised application by Eastern Suburbs Leagues Club Ltd said
that it was a piecemeal application. The Court of Appeal disagreed. Relevant comments by Justice Thomas are as
follows:-
[2] THOMAS JA: The question in this appeal is whether a judge in the Planning and Environment Court
erred in holding that the so-called "rule against piecemeal applications" in Pioneer Concrete (Qld) Pty Ltd v
Brisbane City Council applied to two applications made by Eastern Suburbs Leagues Club Limited ("the
club"). Leave to appeal was granted by the court on 8 September 2000.
[3] The club made two applications. That which related to redevelopment of an existing pool area may
conveniently be referred to as "the pool application", and that which related to redevelopment of the club as
"the club application". The pool application has been approved and the club application has not yet been
determined. The respondent, Mr Cunningham, commenced proceedings in the Planning and Environment
Court seeking a declaration that the Council's approval of the pool development application was "ultra vires
© www.ecodirections.com
24
the town plan". His application was based upon a claim that there should have first been an Impact
Assessment, and that the application should not have been approved because of adverse impact on the
amenity of adjoining residential sites. In particular, he objected to the fact that carparking facilities were
provided close to his rear boundary.
[4] There is no legal basis for those submissions. The pool application sought the intensification of an existing
use as of right and was a "permitted development" of the type prescribed in column 2 of the table contained in
cl 11.3.2 of the City of Brisbane Town Plan. The power of the Council in respect of such applications, when
more than minor building work was involved (as here), was the imposition of appropriate conditions.
However, during the hearing the learned judge himself raised the question whether the club's concurrent
application in respect of the club redevelopment should have been made and advertised as part of the one
development. Despite strenuous submissions to the contrary, his Honour expressed the view that both
applications were "part of a single grandiose proposal" and that he had "the strong impression of an
integrated overall plan". His Honour upheld the "piecemeal applications" point and proceeded to declare the
Council's approval of the pool application ultra vires.
[5] I have difficulty in finding evidence to justify his Honour's view that there was a single grandiose proposal.
The club's premises, which include a ground where football matches are played and a club house, are leased
from the Council. The club's history, which goes back some 34 years, reveals progressive development of
the club house. The club's lease is over part only of a large parcel of land extending south from Norman Creek
to a residential area close to Old Cleveland Road. The Council's land (Lot 1) includes the Club, an adjoining
Bowls Club and the Langlands Park Swimming Pool area. The pool area was formerly leased to another
lessee, but in 1996 the club developed an interest in the site. In 1998, as the result of a tender, the Club
obtained a one year lease from July 1999. This was apparently to facilitate redevelopment proposals which, if
approved by the Council, would result in a 30 year lease to the club. The proposed lease requires the club to
keep the redeveloped swimming pool complex open for public use on payment of prescribed fees. It is also
made subject to various other conditions which are aimed to ensure operation as required by the Council.
[6] The club's initial proposal did not seek the provision of any carparking associated with the pool complex.
It was the club's desire to obtain some carparking rights to the unused area to the south of the swimming pool
for its club redevelopment, and if it was approved, to use that area not only for club purposes but to
accommodate parking for the pool redevelopment. That area may conveniently be referred to as "the carpark
area". However, the Council indicated that the provision of a carpark area would be required as a condition
of approval of the proposed pool redevelopment. In the event, although the applications are primarily in
respect of different areas, both applications were prepared and lodged so as to include the
carpark area in the land the subject of the application.
[7] The club redevelopment application is for the adding of a food court, gaming space and additional bar
areas. As earlier indicated, it also requests approval be given to the use of the carpark area south of the
swimming pool for club purposes. The evidence shows that the club does not intend to use the carpark which
has been approved as part of the pool redevelopment for any purpose unassociated with pool redevelopment
unless and until the Council gives approval for such use. Indeed, it could not lawfully do so.
[8] Any rational analysis of the evidence shows that the club's desire for eventual double usage of part of the
pool carpark has never been concealed. Whether or not one characterises separate projects which overlap in
one respect only as a grandiose scheme does not in the end matter. There is one point of overlap, and that is
© www.ecodirections.com
25
the circumstance upon which it must be decided whether the Pioneer case mandates a single application in
respect of both matters.
[9] The respective applications are for different uses and are subject to entirely different streams of
advertisement, objection and determination under the City of Brisbane Town Plan. The use the subject of the
swimming pool application was "outdoor sport and recreation". The use the subject of the club application
was that of "licensed club". The pool application is described as a "code assessable" application, and as
earlier indicated could not be refused by the Council, although conditions could be and were imposed.
Members of the public have no rights of appeal against the approval of such an application. The club
application is described as an "impact assessable" application, that is to say it requires an Impact Assessment
Study to be provided. Public notification is necessary, and members of the public have rights of objection and
appeal.
[10] The pool application had of course already been approved by the Council subject to prescribed
conditions prior to the commencement of Mr Cunningham's proceedings. The club application had been
advertised and had attracted objections, including one from Mr Cunningham. As earlier noted, it has not yet
been determined.
[11] The essential requirement of the decision in Pioneer Concrete is that the proposed use "must be stated in
appropriate detail in one application and all the land involved in the use must be the subject of the
application". There is no rule prohibiting the making of more than one application in respect of the one piece
of land or part of a parcel of land. The Pioneer principle required that each application for a use for a
particular purpose be for the whole of the use (including incidental and necessarily associated uses) and for
the whole of the land devoted to that use. It did not require that two separate and distinct uses be combined in
one application.
[12] Even on the learned judge's view that both applications proceeded from the one club as part of an
integrated overall plan, it is still necessary to examine the uses in question and the extent to which each
application identifies the land over which such use is sought. Pioneer is concerned with the sufficiency of an
application by reference to its subject matter (the use and the land on which that use and ancillary uses are
intended). It does not forbid the inclusion in one application of multiple uses for multiple purposes. Whilst in
certain circumstances it prohibits what are conveniently referred to as "piecemeal applications", it does not
place an embargo upon staged development except in the circumstances stated.
"All this, of course, places no obstacle in the way of applications where consent becomes necessary for the
extension of an existing use to adjoining land or where an applicant for consent to a proposed use
contemplates that there will later be an extension of that use. It is only where land is proposed to be used for
the one purpose at the one time that consent for its use must be applied for in the one application."
[13] A similar attempt to read too much into Pioneer failed in Stubberfield v Redland Shire Council. The court
observed:
"There are no significant parallels between this case and what was decided in Pioneer. Here, the subdivisional
application related to the entirety of Paradise Grove's land. While it is correct that that application did not
relate to the second phase of what Paradise Grove proposed, it dealt comprehensively with the first phase
which was relevantly comprehensive and self-contained. There was no need for the local authority to consider
matters which were involved in the combined application and the outcome of the combined application
was not determined or influenced by a favourable decision on the subdivisional application."
© www.ecodirections.com
26
[14] The same description (comprehensive and self-contained) properly applies to the present applications.
[15] If one applies the "critical integers" described by Stephen J in Pioneer Concrete, namely, land and use, it
would seem that his Honour in the present case regarded the carparking area (ie the land) and the
circumstance that a later decision could be made which would allow it to be used for another purpose as
sufficient to render the applications invalid. However, as Stephen J pointed out, "the land is merely the
passive object which is being used; the active integer, use, will determine its extent".
[16] If there is some long term desire on the part of the club to solve its parking problems through usage of
this particular carpark, it will be necessary for it to satisfy the Council that this is an appropriate use in
relation to the club application. The application for that particular use might be refused or it might be made
subject to conditions. It is not as if the making of these two applications has deprived Mr Cunningham of the
opportunity of objecting to such a usage. The club exposed its intention and Mr Cunningham has in fact
objected. If he or any other objector does not agree with the Council's decision he may appeal. The approval
of the carparking area for carparking for pool patrons, which is ancillary to the pool use, in no way makes it
difficult for the Council to forbid use of that area by club patrons, ancillary to the club use, if the Council is
minded not to approve the use of that carparking area for club purposes. In my view the club has not breached
any town planning requirement and the making of two separate applications in the circumstances of the
present case does not fall within any principle expressed in Pioneer Concrete.
[17] In the present case the essential separateness of the applications is emphasised by the two regimes that
are in place for dealing with them. Whilst it would have been theoretically possible for both applications to be
combined, separate parts of that application would then have had to have been separately advertised and
separately dealt with. In substance the pool application would have to have been granted, and the club
application would have to be decided after taking due account of objections. I am at a loss to know what Mr
Cunningham has lost by reason of the bringing by the club of the two applications in the manner chosen.
[18] In my view his Honour erred in purporting to apply the Pioneer Concrete principle, and in declaring that
the Council's approval of the swimming pool application was ultra vires. The appeal must be allowed.
Costs
[19] Before the application was heard in the Planning and Environment Court the club's solicitors wrote to
Mr Cunningham informing him of their view that the application was without foundation, and indicating that
costs would be claimed if he persisted. Section 4.1.23(2)(a) of the Integrated Planning Act 1997 strictly limits
the occasions when costs may be ordered against a party in that court. In the present case it was submitted
that the application was "frivolous or vexatious". However, Mr Cunningham's concerns are at least
understandable, and despite their lack of legal merit I am not prepared to hold that his application was an
abuse of process or frivolous or vexatious. I would therefore not accede to the making of an order that he pay
the costs of the proceedings below.
[20] So far as the appeal is concerned, each appellant is entitled to its costs. However, as the decision was
given upon a point initiated entirely by the learned judge, the unsuccessful respondent should have an Appeal
Costs Fund certificate. 7 Integrated Planning Act 1997 (Qld), s 4.1.23(2)(b).
Orders
[21] 1. In appeal No 6745 of 2000 the appeal is allowed; the order of the Planning and Environment Court
dated 2 August 2000 is amended by setting aside the declaration in paragraph 2 thereof and replacing it with
an order that the application be dismissed.
© www.ecodirections.com
27
2. In appeal No 6784 of 2000 the appeal is allowed; the order of the Planning and Environment Court dated 2
August 2000 is amended by setting aside the declaration in paragraph 2 thereof and replacing it with an order
that the application be dismissed.
3. In each appeal the respondent, Mr Cunningham, is ordered to pay the costs of the appeal including the
application for leave to appeal, and the respondent is granted an indemnity certificate in respect of each
appeal.
10. From time to time the conditions power is debated as to its scope. Care needs to be taken by Local Government in
imposing conditions. They are not a matter of standard application. Each condition needs to be assessed against the
facts and circumstances of the particular Development Application. The test for a lawful condition has changed
with the legislation. Under the Local Government Act 1936 a condition was unlawful unless it was relevant and
reasonably required. That was broken up into two tests in the Local Government (Planning and Environment)
Act 1990 with the use of the word or. While the word or has continued to be used in the Integrated Planning Act
1997 the relevance test has had an additional component added to it. The current conditions power is set out in
Section 3.5.30 of the Integrated Planning Act 1997. For a relevant condition to be lawful it must not be an
unreasonable imposition on the development or the use of premises as a consequence of the development. The
second test is that the condition must be reasonably required in respect of the development or the use of premises as
a consequence of the development.
11. The test of relevance has been debated on a number of occasions and most recently by the Court of Appeal in
Maroochy Shire Council v Wise (1998) 100 LGERA 311. This decision was under the Local Government
(Planning and Environment) Act 1990 but still has some applicability because of the current test under the
Integrated Planning Act 1997 subject to the relevant condition not being an unreasonable imposition on the
development. The Court of Appeal went back to the High Court decision in Lloyd v Robinson.
Selected Planning and Environment Court Decisions
12. It is appropriate to look at decisions with respect to appeals generally, the conditions test, the declarations power
and costs.
13. In Power v Sarina Shire Council [2000] QPELR 145 Judge Wall QC examined the good quality agricultural land
(sugar cane) as part of an application to rezone the land to the Rural Residential Zone and for a subdivision
approval. The Respondent had refused the application. Some relevant comments of the Judge are as follows:-
...
State Planning Policy 1/92
This policy is Exhibit 5A. The purpose of the policy is to conserve good quality agricultural land which is
described as the "best and most versatile farming land". Such land is a "valuable resource" and "should not be
built on unless there is an overriding need for the development in terms of public benefit and no other site is
suitable for the particular purpose". The land should be "productive" or capable of being productive, either by
itself or amalgamated with other good quality agricultural land. Good quality agricultural land should be
© www.ecodirections.com
28
preserved regardless of the effect of market fluctuations on its viability. The amalgamation of small holdings
which are not agriculturally viable should be encouraged if that would enhance farm viability. Rural
residential development should occur in such a way that avoids conflict with farming operations and does not
inhibit farming practice. The policy provides that the Planning Guidelines for the Identification of Good
Quality Agricultural Land (Exhibit 5B) define "good quality agricultural land". I shall refer to these as the
Planning Guidelines.
...
A number of things can be said about the Suitability Guidelines:
* socio-economic factors in general terms are relevant to land suitability classification
* subjectivity is involved in the classification of limitations and assignment of critical values to limitations
* subjective waiting of limitations is involved in the combination of limitation of sub-classes
* information relating to all attributes of the limitations must be collected.
* discussions must be held with extension officers, agronomists, economists and farmers so that the relevant
diagnostic attributes for each limitation can be selected.
* the reliability of the surveyor's validation of the diagnostic attributes and the critical values chosen to
establish limitation sub-classes will depend on the experience of the surveyor in land evaluation studies.
* in the validation of diagnostic attributes and their critical values information should be obtained from
farmers experienced in sugar cane growing who have local knowledge of such matters.
* profitability or technological capacity is to be assessed.
* the preliminary land suitability classification assigned by the surveyor should be tested in the field with local
farmers, research and extension officers, following which revisions may be required.
* economic considerations in general terms are relevant to the assessment process as is local input from
sufficiently qualified and experienced local farmers.
According to the Plane Creek Sugar Cane Land Suitability Study, the western third of Lot 7 was assessed as
class 5 for sugar-cane and the remainder as class 3. ...
Witnesses
Detailed assessment of the agricultural quality of the subject land was carried out by the various experts but
with varying results. [His Honour then examined at length that evidence]
Need
This issue is relevant once the conclusion is reached that the land is not good quality agricultural land. It is
raised by the Planning Scheme and was dealt with in the evidence of Mr Michael McGovern a valuer and real
property consultant and Mrs Veronica Schilliing-Hauskrecht, the Respondent's consulting town planner. I
prefer the evidence of Mr McGovern. Whilst he is not currently working as a valuer or real estate agent he
does, in my view, have more relevant local experience and, I think, intuitive judgment than Mrs Schilling-
Hauskrecht. I accept his opinions as contained in his report, exhibit 15A and in his evidence. In the relevant
area the number of vacant rural residential sites has decreased from about 20 at the time he wrote his report,
August 1998, to 11-13 at present. I say "relevant area" because in my opinion it is legitimate in considering
need to look at the Alligator Creek area, where the subject land is situated, rather than the broader and more
global shire approach which I thought appeared to be favoured by Mrs Schilling-Hauskrecht, certainly in her
report, Exhibit 9D, I accept that there is a need in the particular area for this type of development whilst
recognising that on the broader approach the evidence may not be as persuasive. Mrs Schilling-Hauskrecht
© www.ecodirections.com
29
did agree that the Respondent's draft policy, Exhibit 9D, page 21, did recognise particular locality need. In
evidence she said she expected most issues connected with the subject application to be resolved by
appropriate conditions once the issues of good quality agricultural land and need were determined. She said
locality need should be considered in a whole of shire context, but agreed with Mr McGovern's figures. She
said that if the land was not good quality agricultural land the Council would probably accept that it could be
developed with appropriate buffering from adjoining uses, or at least she wouldn't have recommended against
it. I think that is a proper approach to take. Notwithstanding the fact that the adjoining subdivision was
created before the current planning scheme came into force its presence cannot be ignored; it is a fact and it is
of relevance in relation to this application. Mr Hughes conceded, correctly in my view, that the issue of need
was to be approached by reference to the community interest in such development as opposed to marketability
from the developers standpoint. I also accept Mr McGovern in relation to the fact that realistically a
development such as is proposed by the Appellant will not conflict with the surrounding farming and tramline
activities. In my view, "exceptional circumstances" for the purposes of the planning scheme exist where land
zoned rural is not good quality agricultural land and is not suitable for sustained or commercial agricultural
purposes, including horticulture, where there is an adjoining rural residential subdivision (notwithstanding
that it was created before the current planning scheme) and another very close by, where there is a need for
this type of development and where the other requirements for rezoning and subdivision to allow a rural
residential development are satisfied which is the case here.
Result
For these reasons the Appellant has established that his application should be approved. The appeal will
therefore be allowed and the application approved subject to conditions. I adjourn the further hearing of the
appeal to a date to be fixed to allow the parties to agree upon and submit a schedule of conditions.
14. In Powell v Bowen Shire Council [2000] QPELR 113 Judge Pack was dealing with a submitter’s appeal against
the Councils approval for a material change of use for a multiple dwelling under a superseded Planning Scheme.
Issues of visual impact, environmental issues and need were examined. In the course of the Reasons for Judgment
Judge Pack with respect to visual impact and views, environmental grounds and the task of the Council and the
Court, said:-
Mr Chirnside is an experienced landscape planner who gave evidence and who has provided a report which is
Exhibit 3. As I have mentioned, his report provides particularity with respect to the removal and relocation of
trees and a perspective of the effect of this by use of a transparency which forms part of the Exhibit, along with
photographs and plans. Because some palm trees are already grown to the height of the proposed building the
impact of the building will be reduced.
It is proposed to transplant coconut palms and to plant other plants to provide a significant interface of foliage
acknowledging that the developer would have to work hard work at providing a dense interface of smaller
palms underneath larger ones to ensure that the Appellant�s privacy was not invaded from lower floor levels.
He indicated that this could be achieved without difficulty. Having regard to the presence of eaves over
© www.ecodirections.com
30
windows, together with present and proposed plantings I have concluded the prospect of Mr Powell�s privacy
being invaded by occupants at higher levels is not significant.
����
The environmental grounds of appeal go on to suggest that the proposed development files to restrict
development in an area �known to be environmentally sensitive� and does not �address adverse
environmental impacts�.
With respect to beach protection, Mr Holbrook points firstly to the fact that the proposed development is to be
constructed within the bounds of the existing development. No works seaward of the existing development are
required.
Mr Holbrook addressed the issue of the locality�s stability noting that the area was vulnerable to wave over
topping and beach erosion during storm events. He referred to the Barrier Reef absorbing significant wave
energy and the rock outcrops of Rose Bay effectively providing a groin stabilising the beach and on that basis,
concluded that the beach was reasonably protected from the erosive force of wave energy. He said that this
view was supported by the existing mature trees and vegetation seaward of the subject site.
He point out that further vegetation plantings would further enhance stability.
Mr Holbrook�s report, after considering relevant legislation addresses management issues which include
water quality management, erosion and sediment control, noise abatement, environment issues, beach
protection, air quality and lighting and concludes that there is no evidence to suggest that the site provides
viable native habitat or contributes to the ecological integrity of the terrestrial surrounds. He referred
specifically to the need for erosion and sediment control and the need to control light over-spill to avoid
adverse impact on nocturnal terrestrial fauna and hatchling turtles. These matters have been addressed in the
management plan.
�����
My task is not to apply particular weight to the projected wishes of individuals, questions of amenity or with
respect to the proposal generally. The task of Council and of the Court was always and remains one of
weighing the proposal against the planning scheme.
15. In Financial Insurance Group Services Pty Ltd v Townsville City Council [2001] QPELR 88 Judge Wall QC
was looking at an appeal against the Respondent’s decision to refuse a material change of use from Residential 2 to
Professional Office. The Council’s Transitional Planning Scheme had a number of provisions which guided the
decision. In the Reasons for Judgment Judge Wall said:-
....
© www.ecodirections.com
31
The subject site does not have a �frontage� to Ross River Road, as that term is defined in the administrative
definitions of the scheme. In this sense, its frontage is to Gulliver Street, although in one sense it does face or
front the intersection including Ross River Road. I agree that one should not adopt an inflexible rather a
practical commonsense approach to the Strategic Plan objectives. Approaching the matter that way, I think
that the general provisions relied upon by the appellant are qualified by the specific provisions referred to by
the respondent and that the present application should be determined by reference to the latter. In general
terms, the Strategic Plan aims to �promote the establishment of developments which will add to the diversity of
opportunities and add to the city's economic base� (Aim 4). In support of this aim is a strategy to the effect
that �the needs of a wide variety of professional service activities and the convenient availability of these
services and facilities to the general public will be facilitated by providing a wide range of locational
opportunities for minor professional services and home occupations� (section 2.7.5(c)). In dealing with the
preferred dominant residential land use area, the Strategic Plan provides that �in the case of some developed
areas, limited small intrusions of compatible nonresidential uses exist and will be allowable in some
circumstances� (section 2.15.1). The appellant submits that the present application is such a circumstance. It
is misleading though to treat the building on the land as an existing compatible non-residential use because
the nonresidential use, namely a professional office, is occurring unlawfully. Objectives 1 and 5 of the
Strategic Plan and paragraphs (h) and (a)(i) respectively of the implementation criteria for each objective are
the particular provisions relied upon by the parties, the appellant placing emphasis on the former and the
respondent on the latter.
These are in the following terms:
�OBJECTIVE 1
To promote a high standard of amenity.
Implementation
(h) The residential amenity of some areas already suffers from traffic noise from an adjacent major road.
While the land use designation is residential some non-residential uses may be allowed. The resulting
structures should be so placed as to screen the houses to the rear.�
�OBJECTIVE 5
To most efficiently utilise the residential area by a selective allowance of non-residential uses which do not
adversely affect amenity.
Implementation
(a) The Council may allow a professional office or a medical centre on certain land in the City zoned
Residential. The Council will favourably consider this use in an existing building or in a new building
designed and constructed to maintain a 'domestic' scale and appearance and where the amenity of an area will
not be adversely affected. This land zoned Residential is as follows:
(i) land having a frontage to Ross River Road between Bowen Road, Mundingburra, and Lindeman
Avenue, Cranbrook.� In my view, Objective 5(a) governs the extent to which a professional office or a
medical centre as �limited small intrusions of compatible non-residential uses� can occur in a
residential area and the extent to which �some non-residential uses (being those particular non-
residential developments) may be allowed� in such an area. �Frontage�, for the purposes of
Objective 5(a)(i), should bear the meaning assigned to it in the definition section already referred to.
Certain developments are generally permissible in the Residential 2 zone where they are �located on
© www.ecodirections.com
32
land fronting a principal road or otherwise where they accord with the Residential Objectives of the
Strategic Plan� (section 6.4). When read with section 2.15.1 of the Strategic Plan this was said to
encompass the present application, but in my view it is qualified by column 3 of the Table of
Development for the Residential 2 zone (section 6.5.1), which lists as a permissible development a
�professional office - in accordance with the Strategic Plan�. This in turn takes one back to Objective
5(a)(i). For present purposes, paragraph (a)(i) is incorporated in the Scheme provisions and, to that
extent, assumes more importance than a mere objective related provision. To fall within column 3, the
subject site would have to front Ross River Road (clearly a principal road) in the sense of having a
frontage to it, that is having a boundary or part of a boundary coinciding with any continuous part of
the limits of Ross River Road, and this site does not. Professional offices on this site are therefore not
a permissible development in the Residential 2 zone, but are prohibited. In my view, the Strategic
Plan does not in fact envisage a professional office in a residential area in all cases where the
residential amenity of the area suffers from traffic noise from an adjacent major road, but only in
those cases encompassed by Objective 5(a). A professional office or a medical centre is a permissible
development on land zoned Residential 2 and 3, provided the land has a frontage to the roads
mentioned in Objective 5(a). In each case, the Tables of Development require that the development be
�in accordance with the Strategic Plan� and Objective 5(a) is the relevant provision of the Strategic
Plan. The same is the case in the Residential 1 zone, but only for a professional office. So far as the
Residential 2 zone is concerned other development is permissible on such residentially zoned land �
as envisaged by Objective 1(h) and section 6.4 of the Scheme - in a broader range of locations, for
example, a child care centre and a nursing home, where the residential amenity already suffers from
traffic noise from an adjacent major road and the structures are placed so as to screen the houses to
the rear, and an arts and crafts centre, a motel, a surgery and a veterinary clinic on a principal road
(not only those roads mentioned in Objective 5(a)), probably where the residential amenity already
suffers from traffic noise from that adjacent road and provided the structures are placed so as to
screen the houses to the rear. The locational scope for a professional office is not as wide as for these
types of developments; it is limited by Objective 5(a). For present purposes, land in a Residential
zone having a frontage to Ross River Road between Bowen Road and Lindeman Avenue would be
land fronting a principal road. The subject site does front a principal road - Gulliver Street - and it
does suffer from traffic noise from a major road - Ross River Road - which I am prepared to accept is
an adjacent major road, but it does not have a �frontage� to Ross River Road as that term is defined
in the Planning Scheme. For the purposes of Objective 5(a), the �certain land...zoned Residential� is
the land described in subparagraphs (i) to (viii). In the case of such land, the council �may�
generally allow a professional office. The prospects of permission being granted are enhanced if the
professional office is intended to be located �in an existing building or in a new building designed
and constructed to maintain a 'domestic' scale and appearance and where the amenity of the area will
not be adversely affected�. In such a case the council will �favourably consider� the application. The
fact that the professional office proposed in the present case is intended to be located in the existing
building on the site is not enough to assistant the appellant, because the site does not have a frontage
to Ross River Road. Had it such a frontage, the application would have been �favourably
considered� and, according to the respondent's Director of Planning Services, Mr Gopal, probably
© www.ecodirections.com
33
granted. I appreciate that the subject land is effectively located on the boundary of and adjoins a
property which has a frontage to Ross River Road and, in this sense, is very close to a �permissible�
area, but in the end result and from a planning point of view that in itself cannot amount to a
sufficient reason to elevate a prohibited proposal to a permissible proposal. �Frontage� is defined in
such a way that it is allotment neutral in the sense that a corner allotment can front both roads and it
is irrelevant that a building constructed on the allotment may in fact �front� only one of them.
�Fronting a principal road� must logically bear the same meaning, but, in the circumstances of this
case, unfortunately that cannot assist the appellant. Adopting what has been described as a
�commonsense approach� and a �sensible practical approach� to the interpretation of the Strategic
Plan provisions, the fact that the present proposal conflicts with the Strategic Plan provisions which I
have referred to is a conflict which is �plainly identified� (see Fitzgibbons Hotel Pty Ltd & Ors v.
Logan City Council (1997) QPELR 208 at 212 and Harburg Investments Pty Ltd v. Brisbane City
Council & Anor, unreported, Planning & Environment Court, Brisbane, 5 May 2000, Skoien DCJ).
This result is of course an unfortunate one for the appellant, but I cannot agree with Mr Needham
that it leads to a �ridiculous situation�. It is a situation likely to be faced by the owner of any
property situated on a zonal boundary under the present transitional Planning Scheme. The intention
of the Residential zone in the present case is that professional offices can, with permission, be located
in such a zone on land having a frontage to Ross River Road. Elsewhere in the zone, they are
prohibited. Though the subject site does not quite have a frontage to Ross River Road, it nearly does
and it is for this reason and its related effect on residential amenity in the sense mentioned in
Objective 1(h) that the appellant also says there are in fact sufficient planning grounds to justify
approving the application despite its conflict with the Strategic Plan (see the Integrated Planning Act,
section 6.1.30, and the Local Government (Planning & Environment) Act, section 4.4(5A)). It is also
submitted that there is a need for a professional office in this location in the sense referred to in
section 4.4(3)(b) of the Local Government (Planning & Environment) Act. Generally speaking and
subject to the issue of need, Mr Gopal agreed that had part of the boundary of the subject site fronted
Ross River Road, the traffic considerations which occupied the balance of the hearing by themselves
probably would not have been sufficient to justify refusal of the proposal. The proposal conflicts with
the Strategic Plan in the sense that it is, according to column 3, a prohibited development in the zone
where it is situated. Is there, nevertheless, a need for it? I do not think there is. In my view, there is
ample other available land in the relevant part of Ross River Road generally and on the market (see
Exhibits 12, 13 and 14). I am unable to conclude that the public need requires or that there is a public
need for approval of this application in circumstances where other available land is conveniently
located in the near or immediate vicinity and exists in sufficient quantity both generally and
particularly available at the present time. This is the case even if one limits consideration to a �home
based professional office�, to use Mr Needham's words, and I am not sure in any event that it is
correct to confine a consideration of need in that way. The Planning Scheme does not distinguish
between different types of professional offices, but, having said that, I recognise that each case has to
be considered by reference to its particular facts and circumstances. In this sense, I am not persuaded
that there is a need for more land in this area which can be used for a home based professional office.
I agree with Mr Haydon that the starting point is the fact that all the land on Ross River Road in the
© www.ecodirections.com
34
relevant area is potentially available for use as professional offices and that Exhibits 12, 13 and 14
and the evidence in relation to them indicate the land available at the present time. Looked at this
way, no need exists for additional land to be designated for use as professional offices. Mr Dance, in
paragraph 3 of his report, Exhibit 1, mentions that: �Housing along Ross River Road has
progressively been turned over to professional offices or medical centres/surgeries during the life of
the Planning Scheme.� I do not agree with Mr Dance (Exhibit 1, page 16) that, in the circumstances
of this case, the �need issue is tempered by the effect of the Integrated Planning Act� in the sense that
approval of the application would not require a rezoning. Need is an issue which requires
consideration in a substantive way regardless of the technical effect which approval would produce
on the Planning Scheme. An assessment of �alternative and available sites� (to use Mr Dance's
words) leads me to the conclusion that no need has been established sufficient to warrant approval of
the present application. In those circumstances, there are not sufficient planning grounds to justify
approval of the application despite its conflict with the Strategic Plan. The appeal will therefore be
dismissed.
16. The conditions power has been looked at from time to time by the Planning and Environment Court. This analysis
is not meant to be exhaustive but to give some North Queensland examples. In Hewbridge Pty Ltd v Mackay
City Council [1999] QPELR 371 Judge Pack was looking at an appeal against conditions imposed on a
subdivision approval. In particular a drainage contribution was the condition being analysed. The relevant statutory
provisions was Section 5.3(f) and Section 6.1(1)(c) of the Local Government (Planning and Environment) Act
1990. The drainage condition sought a financial contribution per hectare calculated in accordance with a
Development Control Plan. After referring to Proctor v Brisbane City Council [1994] QPLR 309 and Maroochy
Shire Council v Wise [1999] QPELR 143 the Court went onto find:-
Whatever the level of discharge it does need to be accommodated in the Council�s drainage system. I think that
if there is some effect on drainage from the proposal, however slight, it is not something I should regard as
irrelevant. I think there is a relevant nexus between the development of the subject land and the drainage plan.
as I have indicated I think that once there is run-off from the land the Council was required to address
drainage and it is on that basis that I consider the condition to be relevant.
Accordingly, I dismiss the appeal against the imposition of condition (ix).
17. A stormwater drainage construction condition was examined as part of a subdivision approval by Judge Wall QC in
Delfin Property Group Pty Ltd v Thuringowa City Council [2000] QPELR 282. It was conceded by the
Respondent that the subdivisions add little, if any, measurable effect to the load in the Kern main drain and to the
flooding risks. The catchment for the Kern main drain at Charles Street is approximately 7 square kilometres. The
total area of these subdivisions is 8.78 hectards. The conditions tests were those under Section 3.5.30 of the
Integrated Planning Act 1997. Some relevant comments are from the Reasons for Judgment are as follows:-
The Council, in attempting to uphold the condition, relied primarily on historical reasons connected with the
development of the Willow Gardens Estate area in general. For the reasons referred to by Mr Gore QC for the
© www.ecodirections.com
35
Appellant, those reasons do not in my view provide a sufficient nexus between the condition and the
subdivisions to make the condition lawful so far as it relates to the Charles Street to Dalrymple Road section
of the drain. The Appellant has agreed to the condition for the drain from Hervey Range Road to Charles
Street.
Mr Baulch SC argued that the Appellant apprehended and anticipated such a condition as a general
requirement connected to the ongoing development of the Willow Gardens Estate. The evidence does not in my
views go that far, but, even if it did, it would not make the condition lawful.
����.
Even if the condition could be said to be relevant, which I doubt because of its wide terms which required
construction rather than a contribution to construction costs but am prepared to accept, it would in the
circumstances amount in my view to an unreasonable imposition on the development more so when one also
has regard to the obligation of the Appellant to construct the main drain to its ultimate profile between Hervey
Range Road and Charles Street as a result of these subdivisions. The cost of complying with the condition, so
far as it relates to the section of the drain between Charles Street and Dalrymple Road, is put at about
$500,000.
18. In Barro Group Pty Ltd v Thuringowa City Council [1999] QPELR 312 Judge Wall QC was looking at the
conditions of a quarry application under Section 6.1(1)(c) of the Local Government (Planning and
Environment) Act 1990. It was an extension of an existing quarry. The conditions were amended.
19. The declarations power under Section 4.1.21 and the consequential orders under Section 4.1.22 of the Integrated
Planning Act 1997 mean that any person can review planning and environment decisions of Local Government.
The Judicial Review Act 1991 does not apply to conduct and decisions under the Integrated Planning Act 1997
(Section 5.8.4). The declarations power of the Planning and Environment Court is wide enough to consider those
matters which would have proceeded as a judicial review in the Supreme Court.
20. The declarations power is also useful in determining the scope of Development Application or whether it is
required to be made.
21. In Herberton Shire Council v Vance [2001] QPELR 2 Judge Wall QC was looking at an application for a
declaration and an injunction relating to the use by the Respondents of their land for activities of an industrial
nature notwithstanding the fact that the land was situated in the Rural Zone under the Planning Scheme. In the
Reasons for Judgment the following comments appear:-
��
I am satisfied that the respondents have had ample notice of the application. They have been served with it and
with the amended application. They have also been advised of the hearing date and they have chosen not to
© www.ecodirections.com
36
appear to resist the orders sought by the applicant. In those circumstances, I considered it appropriate to hear
the application and if warranted, make orders of the nature sought, notwithstanding the absence of any
appearance by or on behalf of the Respondents
���..
Column 1 lists the development activities which can be carried on in the zone without the consent of the
council. These are, agricultural; animal husbandry; dairy; dwelling house; forestry of a particular nature;
home occupation; host farm rural stay of a particular nature; public park; public utility and trade storage
building. I am satisfied on the material before me that the activities carried out by the respondents, the subject
of complaint by the applicant, do not fall within any of these development categories. Column 2 lists the
development activities which may be undertaken only with the consent of the council. Even if it could be said
that the activities being carried out by the respondents come within the home industry activity, one of those
listed in column 2 (see also the definition of �home industry� on pages 13 and 14 of the planning scheme),
which I doubt, the fact is that the council has not given the respondents' consent to carry out such activities.
The extent to which the activities being carried out by the respondents interfere with the amenity of the
neighbourhood by reason of the omission of dust and fumes and noise, such as is referred to in the material,
lead me to the conclusion that the activities being carried out go beyond those encompassed by a home
industry. The activities which have been and still are being carried out on the land by the respondents are
referred to in the material. The commencement date for these activities is about early 1997. In the affidavit of
Gordon Kenneth Malcolm, Exhibit GKM1 contains three letters from neighbouring landowners complaining
about the respondents' activities on the land. These letters were written in June 1997 and variously refer to
those activities as a trucking and/or earthmoving business, involving numerous old trucks, trailers, trailers
loaded with junk, a grader and a bulldozer. Trucks and trailers were observed to come and go from the
property and a grader was observed working on the land. Mrs Canfield considered that the land was being
used a depot for trucks and earthmoving equipment which involved industrial noises and activity she described
as being like a junk yard. Mr and Mrs Horwood referred to the activities as being an earthmoving and truck
hauling business, a truck depot and repair yard, including a ramp used for off loading trailers and
earthmoving equipment, and a shed being constructed for the repair of numerous vehicles. They also referred
to activities involving banging and welding, all types of vehicles coming and going and repairs being carried
out on vehicles. They concluded, rightly so in my view, that some type of industrial business was being carried
out on the land. Mr and Mrs Braun in their letter referred to problems involving noise pollution, air pollution
and other activities pointing towards an industrial use of the land. They mentioned that trucks, low loaders,
graders, bobcats and cars were constantly moved in and out over the day and were intermittently revved and
tested. They also heard metal banging, clanking, hammering and the grinding of power drills. Fumes from
trucks, graders and heavy machinery also interfered with their amenity. They also observed the building of a
ramp for the unloading of heavy equipment and observed the big work shed under construction. These
activities led them to conclude that the respondents were gearing up to use the property, if not already using it,
as a truck and maintenance depot. Complaints received from neighbours of the subject land in the week
preceding Monday 23 February 1998 are summarised in the file note of Cameron Stanley, the applicant's
planning officer, Exhibit GKM7. These complaints satisfy me that the respondents were continuing to conduct
© www.ecodirections.com
37
activities on the land of an industrial nature. The complaints included grinding noises; chainsaw; revving of
trucks; tractors and cars; 20 or so heavy vehicle movements a day; excessive noise and pollution and a
perceived use of the land as a contractor's yard for an industrial type activity. Mr Cameron attended on the
property on Monday 23 February 1998. Mrs Vance was there. She told Mr Stanley that a loader was
temporarily on the property the week before. Mr Stanley observed two cars, one dozer, one small truck, two
trailers and one tip truck on the property. Only the dozers and the trailers appeared to be in working order.
Mrs Vance admitted to him that the property was used for the servicing of vehicles used in their business. She
also said that the majority of the machinery was kept on the job site. They appeared to conduct some type of
earthmoving contracting business. On 9 March 1998, Mr Stanley met with Mrs Horwood, Mrs Braun and Mrs
Canfield in relation to the use that the respondents were putting the land to. Mr Stanley's file note of that
meeting is Exhibit GKM8. The neighbours said that the situation was not as bad as in September/October
1997, but nevertheless seemed to be intensifying somewhat. Mr Stanley concluded that the land was being used
as a contractor's yard. In his file note, he said that as at March 1998 the activity was minimal, but increased
on weekends and at times when equipment was not on a job site; that is in between jobs. Mr and Mrs Horwood
again wrote to the council on 22 March 1999, again complaining about the continued use of the property as a
contractor's depot and the use of a shed on the land as a workshop for repairs, service and panel beating of
earthmoving equipment and commercial vehicles. Their letter is Exhibit GKM11 and it refers to the continuous
noises associated with banging, grinding, sanding, welding and with exhaust fumes from old commercial
vehicles being continually revved every day of the week including Saturdays and Sundays. They found this
activity to have reached an unbearable level. They considered that commercial activities were being carried
out on the land. These complaints are supported by the daily recording sheets attached to their letter. The
council have written a number of letters to the respondents and had meetings with them, but to no avail. Mrs
Vance wrote to the council in September 1997. I cannot accept what she says in that letter, which is Exhibit
GKM5. The evidence establishes more than an infrequent servicing of machinery and more than the carrying
out of minor repairs on machinery. It also establishes more than a mere storage of certain machinery items on
the land. Mrs Yvonne Horwood has sworn an affidavit and this was filed on the application. Paragraphs 6 to 9
of that affidavit deal with the position as observed by her in June 1997. Effectively, but in varying degree, that
activity has continued up until the present time. The photos, Exhibit YH1, represent some of her observations
in June 1997. She also took the photographs YH4 in March and April 1998 and those in YHA8 in March and
August 1999. These satisfy me that the land has been and is being used for an activity of an industrial nature,
contrary to the provisions of the Planning Scheme. In paragraphs 19 and 21, she refers to specific problems
she has in relation to the activities carried out on the land by the respondents. I accept what she says. In my
view, the evidence establishes that these activities are likely to continue, notwithstanding the council's attitude
to their continuation as expressed by council officers to the respondents. The respondents appear to me to be
completely ignoring the provisions of the Planning Scheme. They are, in my view, conducting an industrial
type business on and from the land and to do so is contrary to the provisions of the Planning Scheme. �Light
industry� is defined on pages 15 and 16 of the Planning Scheme and, in my view, the respondents are using the
land for such a purpose. �Industry� is defined on pages 4 and 5 of the Planning Scheme and the activities
being carried out on the land by the respondents clearly come within that definition as including the breaking
up or dismantling of vehicles or heavy equipment; the repairing, renovating or servicing of vehicles and
machinery; operations connected with the installation of equipment and services related to vehicles and
© www.ecodirections.com
38
machinery and the dismantling of motor vehicles and machinery. The activities certainly go far beyond what is
contemplated by a �home occupation� as that is defined pages 12 and 13 of the Planning Scheme and also
�home industry� as that is defined on pages 13 and 14 of the Planning Scheme. The activities being carried
out on the land by the respondents would appear to be encompassed by what is referred to as a �contractor's
depot or yard� in the definition of �light industry� on page 16 of the Planning Scheme. The activity carried
out by the respondents is clearly causing an interference with the amenity of the area by reason of the emission
of noise, smell and fumes within the definition of �light industry� on page 16 of the Planning Scheme. Giving
the term �contractor's depot or yard� an ordinary everyday meaning, it is clear to me that the activities being
carried out by the respondents which I have referred to in summary clearly come within this term. The
evidence satisfies me that the respondents are conducting some type of trucking and/or earthmoving business
involving a combination of vehicle movements, loading and unloading of machinery, mechanical repairs and
panel beating. Such activities are not allowed in the rural zone. Such activities, in my view, are also beyond
the definition of �home industry� which is an activity allowed in a rural zone with the consent of the council.
In any event, in the present case, there is no such consent. In my view, the applicant is entitled to relief of the
nature claimed. I declare that the respondents' use of the land, lot 402 on Crown Plan H25327, County of
Cardwell, Parish of Herberton, for activities of the nature defined in the Planning Scheme of the Council of the
Shire of Herberton as �light industry� are unlawful and amount to a use beyond those uses permitted by
column 1 of the Table of Development � Rural Zone in section 3.1.2 of the Planning Scheme for the Council of
the Shire of Herberton. I order that the respondents by themselves, their servants or agents be forthwith
restrained and an injunction is granted restraining them from using the land, lot 402 on Crown Plan H25327,
County of Cardwell, Parish of Herberton, for activities of the nature defined in the Planning Scheme of the
Council of the Shire of Herberton as �light industry� and being activities beyond those permitted by column 1
of the Table of Development - Rural Zone in section 3.1.2 of the Planning Scheme of the Council of the Shire
of Herberton unless the respondents first obtain development approval from the Council of the Shire of
Herberton.
22. In Barro Group Pty Ltd v Girgenti [2001] QPELR 175 Judge Wall QC dismissed an application for declarations
relevant to the use of land pursuant to Sections 183 and 183 of the Transport Infrastructure Act relating to the
extraction, crushing, screening and stockpiling and gravel. The question to be determined was whether or not the
development was exempt or assessable under the Integrated Planning Act 1997. The following comments
appear:-
���..
(2) The Respondent's land is zoned Rural B. under the Planning Scheme for Thuringowa City Council. The
planning scheme is a transitional scheme and under the scheme the land can only be used for an extractive
industry with the consent of the council i.e. with development approval.
(3) The use of the land for the extraction, crushing, screening and stockpiling of gravel is occurring under or
as a result of a notice issued under ss. 183 and 184 of the Transport Infrastructure Act 1994 (TIA). These
activities would appear to come within the definition of �extractive industry� in the planning scheme.
© www.ecodirections.com
39
(4) A development permit from the council is necessary for assessable development but not for self-assessable
or exempt development, s.3.2.4(1) and (2) Integrated Planning Act (IPA). It is an offence to carry out
assessable development without a development permit, s.4.3.1 IPA. Self-assessable development has no
application in this case. For present purposes, all development is exempt development unless it is assessable
development, s.3.1.2(1) IPA. For the purposes of a transitional Planning Scheme the term "assessable
development" has the meaning ascribed to it in s.6.1.1 IPA. "Exempt development" is defined in Schedule 10 as
development other than assessable or self-assessable development. IPA binds all persons including the State,
s.1.5.1(1) IPA.
(5) In the present case "assessable development" means development specified in Schedule 8, Part 1 IPA and
to the extent that it is not inconsistent with Schedule 8, Part 1 development that before the commencement of
IPA would have required an application to be made for town planning consent for uses that were permissible,
(s.6.1.1. IPA �assessable development� definition, paras (a) and (b)(ii)). S.3.1.2(2) IPA provides that Schedule
8 may identify exempt development that a Planning Scheme cannot make assessable development. Schedule 8
does that in Part 3. Schedule 8 Part 3, s.17 IPA is relied upon by the Respondent for the contention that the
present activity is exempt development. Sec. 17 exempts operational work if the work is carried out by or on
behalf of a public sector entity authorised under a State law to carry out the work. Such work does not require
a development permit from the council.
(6) The Department of Transport (DOT) is carrying out road works on the Bruce Highway between Eleanor
Creek and Gap Creek. Nordev Contractors Pty Ltd (Nordev) has a contract entered into in about June 2000
worth $1,095,404.00 to supply 60,000 tonnes of gravel for that job. The gravel apparently has to be of a
particular size. To be useable the gravel must be crushed and screened. Pursuant to an arrangement with the
Respondent, Nordev extracts the gravel from a pit on the Respondent�s land using an excavator or loader and
it is then transported by truck some 350m where it is put through �the crusher, screening and conveyor
system.� It is then stockpiled and before being transported to the job it is blended with cement and water. The
gravel has to be crushed to make it useable. As at the 19th September Nordev had extracted, crushed and
screened all of the gravel and transported 12,000 tonnes to the job. The balance was stockpiled. If Nordev was
prevented from using the stockpiled gravel it would face a loss of about $500,000. To transport the gravel 20
kms to an alternative crushing site would increase the cost to Nordev by about $240,000. This extra cost was
not factored into its contract with DOT. These figures were not disputed by the Applicant. The gravel is said to
be essential for the proper and orderly completion of the road works.
(7) The Respondent contends that the work undertaken by Nordev is operational work carried out on behalf of
a public sector entity � DOT � authorised under a State law � TIA� to carry out the work. The DOT is a public
sector entity as such an entity is defined in Schedule 10. It is agreed that Nordev is carrying out the work on
behalf of DOT and that to allow Nordev to do so DOT (or Nordev as its agent) is with the consent of the
Respondent, temporarily occupying and using the Respondent�s land pursuant to a TIA notice under ss 183
and 184 TIA dated 26 June 2000. The Respondent�s land is principally used for growing sugar cane and to a
lesser extent for cattle.
(8) Under s.183 TIA the Chief Executive DOT or anyone authorised in writing by the Chief Executive may
�temporarily occupy and use land and do anything on the land that is necessary or convenient� to carry out
miscellaneous transport infrastructure works which this work is conceded to be.
© www.ecodirections.com
40
(9) The Respondent concedes that for Nordev�s work (i.e. the use and occupation of the land by DOT) to
amount to exempt development it must come within either para (a) or para (e) of the definition of �operational
work in s.1.3.6 IPA. Those paragraphs define operational work as:
�(a) extracting gravel, rock, sand or soil from the place where it occurs naturally; or
(e) undertaking work (other than destroying or removing vegetation) in, on, over or under premises that
materially affects premises or their use.� �Premises� includes land, schedule 10 IPA. If the work does not
come within paras (a) or (e) it is clearly assessable development requiring a development permit. The
Applicant relies on schedule 8, Part 1, sec. 6, IPA which provides that assessable development includes
development prescribed under a regulation under the Environmental Protection Act 1994 (EPA) for sec.6 for
carrying out an environmentally relevant activity under that Act.
(10) If the work carried out by Nordev amounts to the start of a new use of the land then it is prima facie
assessable unless it is exempt. See Environment Protection Regulation 1998, s.63A and Schedule 9, s.1.3.5 IPA
(definition of material change of use of premises) and Schedule 1 items 20(b) and 22(b) EPR. For reasons
which I will refer to later I think the work does amount to the start of a new use of the premises. The extraction
of the gravel is though exempt development because it is clearly within para (a) of the definition of operational
work. I think that para (e) of that definition encompasses work other than the extraction of gravel because
such work is already dealt with in para (a). It is difficult to understand precisely what is meant by para (e) but
I do not think it encompasses crushing and screening. In my view IPA by its incorporation of Schedule 1, EPR
evinces an intention to include the extraction, crushing and screening of gravel as assessable development
unless it can clearly be said to be exempt. Para (a) is clear so far as extraction is concerned. In my view had
the legislature intended to also make crushing and screening exempt it would have included that work in para
(a). In the circumstances of the present case I do not think that the crushing and screening is work which
materially affects the land or its use. I agree with Mr Baulch S.C. that the land merely provides a site for that
to happen. I cannot agree with Mr Monteith S.C. that to set up a crushing and screening plant materially
affects the land or its use in a relevant sense because it has an effect which is material or amounts to a use that
the land would not otherwise be put to. I concede though it is a fine line and minds could differ.
(11) The application was argued on the premise that use pursuant to ss 183 and 184 TIA is subject to IPA. The
State is bound by IPA and it cannot otherwise than by IPA make exempt what IPA makes assessable. IPA not
TIA governs whether development is exempt or assessable and in the present case IPA only exempts the
extraction of gravel.
(12) The Respondent submitted that if the crushing and screening work did not come within para (e) it was,
with stockpiling, nevertheless a use of the land which is incidental to and necessarily associated with the use of
the land for extracting gravel within the definition of �use� in Schedule 10.
(13) In my view it is clear on the evidence that crushing and screening are separate and additional processes
to extraction and go �beyond mere extraction and involve a voluntary extension of what the operation would
otherwise involve.� Both processes could be carried out elsewhere on a site specifically authorised for them.
Mr Rains of Nordev implied that an authorised crushing site does exist some 20 km from the subject land. See
Boral Resources (Qld) Pty Ltd v. Cairns City Council (1997) 2 Qd R 31 at 35-36 which was a case with some
similarity to the present although the definition of �use� while similar to the present was differently worded.
Were it not for this decision and the particular fact situation now before me I would have had no difficulty in
declaring crushing and screening to be assessable development.
© www.ecodirections.com
41
(14) According to Boral the following factors are relevant to whether a use, work or process is incidental to
and necessarily associated with an authorised use or operation:
(a) Whether the additional process constitutes a use which is unavoidably involved in the authorised
operation.
(b) Whether the authorised operation will become uneconomic unless the additional process is included within
it.
(c) Whether the additional process can be regarded as inevitably involved in the authorised operation.
(d) Whether the authorised operation is the significant use and the additional process is only insignificantly
present so that it can be regarded as no more than merely technically in existence.
(e) The character of each operation or process. See also Agtec Holdings Pty Ltd �v- Kilcoy Shire Council
[1999] QPELR 208 at 213-215.
(15) Apart from the fact that the TIA notice refers to the removal (extraction) and crushing of material (gravel)
I would not consider crushing and screening to be uses unavoidably or inevitably involved in the extraction
process nor as uses only insignificantly or technically present. Their character is also different to extraction.
The evidence does however satisfy me that in this particular instance the extraction of gravel by Nordev would
become uneconomic and financially ruinous unless the extracted gravel could also be crushed, screened and
stockpiled as required by Nordev�s contract and envisaged by DOT and the TIA notice. Relevant to this
conclusion is also the fact that the local authority and the Environmental Protection Agency have advised
Nordev and the Respondent that all of the activities or uses are exempt. I consider this advice to be wrong but
its effect on the economics of the whole operation are readily apparent. Some may doubt why the economics of
a particular operation or use should be a relevant consideration in this context but at least in a situation such
as the present where the use is of a temporary nature it does facilitate recognition of a situation which all
involved consider lawful. A somewhat different approach may be required if all of the activities were being
carried on permanently. The economic factor is probably not necessarily a relevant factor in all cases but only
those warranted by their particular circumstances. I regard the possibility of financially ruinous consequences
as allied to the economic factor certainly in a temporary use situation such as the present. For similar reasons
stockpiling in this case would be incidental to and necessarily associated with the extraction process and the
same could be said for its removal from the premises; without being able to remove the gravel there would be
no point in extracting it. See Pioneer Concrete (Qld) Pty. Ltd. �v- Brisbane City Council (1980) 44 LGRA 346
at 358-9 and Noosa Shire Council �v- Settlers Cove Development Pty. Ltd. (1996) 93 LGERA 232 at 243-4.
But for Nordev's antecedent contract with DOT crushing and screening would have been assessable
development. Any increase in the future cost of road works must be related back to IPA, alternatively
development approval should be sought for such activity associated with exempt extraction under a TIA notice.
(16) The letter which accompanied the TIA notice of entry refers to the need to meet "environmental and
legislation requirements" and I think the requirements of IPA are just that. Nordev is engaged in consultant
engineering and earthmoving contracting activities. It owns mobile crushing equipment and carries on
contract mobile crushing operations. It has been granted an itinerant licence NR269 under EPA �in respect of
carrying out the environmentally relevant activities� encompassed by items 20(c) and 22(c) Schedule 1, EPR
�as an itinerant activity throughout Queensland�. The licence is described as an �environmental authority�
and is issued subject to conditions. The notes accompanying the licence advise that the licensee may have
© www.ecodirections.com
42
additional legal obligations under the EPA, the Contaminated Land Act and other obligations at law created
by the Federal, State and Local Governments.
(17) On 23 June 2000 the Operations Manager (Licensing), Townsville of the Environmental Protection
Agency, wrote to Nordev advising that in the view of the agency "NR269 authorises extraction, crushing,
screening and stockpiling at sites not subject to the provisions of the Integrated Planning Act 1997", that the
Agency had determined that the subject quarry site (Ollera Creek quarry) was not abandoned and
recommencement of the ERAs was not a new use and not subject to IPA1997 and that Nordev's itinerant
licence authorised those activities at the quarry. On 31 August 2000, the agency repeated this advice to the
Applicant's solicitor adding that the pit was on freehold land and had a long history of use from time to time as
required to fulfil Department of Main Roads (MRD) contracts for the reconstruction and maintenance of the
Bruce Highway.
(18) For present purposes four things can be said about this advice:
(a) The licence recognises that other State legislation may impose obligations on Nordev (and implicitly on the
owner of the land)
(b) It assumes that extraction, crushing, screening and stockpiling is occurring at a site not subject to the
provisions of IPA.
(c) It assumes that the site was not abandoned and recommencement of extraction, crushing, screening and
stockpiling is not a new use and not subject to IPA.
(d) It assumes that IPA has not altered the position of a TIA notice of entry and use of land. In relation to each,
IPA is other relevant State legislation, the site is subject to IPA to the extent I have already mentioned,
whether the activities amount to a new use of the site must be determined by reference to IPA and IPA does
bind the State and thereby does affect the ambit of activities allowed under a TIA notice. I should also mention
that the Thuringowa City Council takes the view that no development permit is required �as the activities are
being carried out under the provisions of the TIA�.
(19) The Respondent's alternative contention is that the use of the land for extracting, crushing, screening and
stockpiling gravel pursuant to a notice of entry under the TIA is lawful because it was lawful before the 30
March 1998, the date IPA commenced. Reliance is placed on S.1.4.6 IPA and reference was made to the
definitions of "lawful use" and "material change of use" in ss.1.3.4 and 1.3.5.
(20) The Applicant conceded that before IPA commenced activities such as it now complains of carried out
pursuant to a notice under the TIA or a like notice constituted a lawful use of the land and were not subject to
the planning scheme of the local authority, see Local Government (Planning and Environment) Act (PEA)
s.1.4 (definition of "Crown Land") and s.2.21(2)(b) Transport Infrastructure (Roads) Act 1991, s.7.6(1) and
TIA s.33. This I think is a crucial distinction between then and now. IPA binds the State and exempt
development is not assessable development under the transitional planning scheme. Fewer activities are
encompassed by exempt development in the present case (Schedule 8, part 3, s.17) than was the position under
the PEA when land was used pursuant to a TIA notice.
(21) The Respondent contended that the relevant use for this argument was the extraction of material which, it
was submitted also encompassed its crushing, screening and stockpiling. The land is predominantly used for
sugar cane and cattle. The quarry pit which has been used for some time and from time to time under TIA
notices and like notices. Material from the pit has been used since the early 1980's to complete works
contracts for MRD. MRD has occupied the land from time to time pursuant to the provisions of the TIA or
© www.ecodirections.com
43
earlier Acts. In about August 1996 MRD occupied the land and authorised W Wall & Sons to carry out works
on its behalf by entering upon the land for the purpose of extracting, crushing and stockpiling material form
the pit. The material was then extracted over a few weeks in 1996 and crushed and stockpiled in January-
March 1997. Other contractors acting on behalf of MRD, entered the land and removed the material as and
when it was required for works contracts. The last load of material for that particular job was removed from
the land in March 1998. Penna & Co Pty Ltd entered and used the pit on behalf of MRD in September 1994 as
did Brabon Haulage in February 1985 and Readymix in 1986. The use by W. Wall & Sons may have been
under the same TIA notice used by Penna & Co.
(22) The plan and the drawing attached to the Nordev TIA notice of entry show the "existing pit" and the area
of "new excavation" for Nordev's purposes which is an area 50m x 150m and the proposed location of the
crushing plant. The "new area" is effectively a continuation of the existing pit. MRD considers "the operation
(by Nordev) as a continuation of the occupation of the land under the provisions of the TIA".
(23) The use of the land for MRD purposes seems to me to be an occasional use depending on what roadwork
is being undertaken, its location, when it is undertaken, and perhaps the choice of contractor. In this sense it is
not a continuing uninterrupted use but one which occurs from time to time but from an existing albeit
expanding pit or quarry located on the land.
(24) One must ask �what, according to ordinary terminology, is the appropriate description of the purpose
being served by the use of the premises at the material date�, the 30 March 1998? Hudak �v- Waverley
Municipal Council (1990) 18 NSWLR 709 at 714. The land was being lawfully used for cattle, sugar cane and
occasionally for extractive industry purposes as a result of TIA notices or the like. That was its use at the
relevant or material date. Before that date the land was occasionally and legislatively converted to Crown
land not subject to the relevant planning scheme. So far as the resultant use was concerned it was a temporary
occupation and use by the Crown and its servants or agents for a particular purpose and because of
s.2.21(2)(b) PEA that use was not subject to the planning scheme for as long as the premises remained Crown
land, i.e. for the duration of the occupation and use. The Respondent did not possess any equivalent use rights,
the Crown did subject to the statutory regime in force from time to time. There was no right in the
Respondent to use the land for such a purpose; there was a right in the Crown exercisable from time to time
depending on the particular circumstances. The use of the land for such a purpose was not by virtue of the
planning scheme rather it was because the planning scheme was deemed not to apply when it was so used but
in saying this I recognise that s.1.4.6 does not say �a lawful use because of (or under or by reason of) the
planning scheme� but merely �a lawful use� of the premises. After 30 March 1998 the Crown still had a right
to use the land for a similar (but not identical) purpose but it was more circumscribed and not as extensive.
The Respondent had no non-conforming use rights which he could register with the Council.
(25) Mr. Baulch SC contended that there was no maintenance by the Respondent of any use. He submitted
there was no use other than when the Director- General, Department of Transport compulsorily used the land.
In such a case the Respondent �doesn�t have a choice in it, he doesn�t have a relevant intention about
abandoning the use or maintaining it� and in the circumstances �it�s a nonsense to say that it�s a continuing
use where it is an occasional compulsory acquisition of material from his property�.
(26) The resolution of this issue involves �matters of fact and degree� (Woollahara Municipal Council �v-
Banool Development Pty. Ltd. (1973) 129 CLR 138 at 140) and the line to be drawn �may be an extremely fine
one� (Eaton & Sons Pty. Ltd. �v- Warringah Shire Council (1972) 25 LGRA 369 at 372). A provision such as
© www.ecodirections.com
44
s.1.4.6 is �designed to preserve and protect existing rights� and �ought to be liberally construed�. (Fogg
�Land Development Law in Queensland� p. 671 and Parramatta City Council �v- Brickworks Ltd. (1972) 128
CLR 1 at 25).
(27) The authorities also speak of the relevance as factors to consider of the physical operations on the land
and the intention of the owner of the land. The physical operations were carried out transiently and not by the
owner or according to or with regard to his intention but I concede that they nevertheless amounted to a
lawful use of the premises. The fact that the use (for extractive industry purposes) was occasional and not
constant is not necessarily fatal to the Respondent's argument but its resumption from time to time had nothing
to do with his intention. The use before 30 March 1998 and its use since, notwithstanding a break of more than
2 years, is the same use or type of use; the �purpose being served by the use of the premises� is the same.
(28) On balance however I do not think that the relevant use of the premises in this case is the type of use
which is protected by s.1.4.6(1) IPA. The �use� signalled out for protection is a use governed or permitted by
the planning scheme. Immediately before (and after) 30 March 1998 the use of this land according to the
planning scheme was for Rural B purposes. That use has not changed or been restricted, lessened or dismissed
by IPA. Alternatively at the time IPA commenced no use was being made of the premises pursuant to the TIA.
That use had ceased and it could not have been said that any such use of the premises would again be made
after that date. In fact it was not until 26 June 2000 that such use of the premises again commenced and that
occurred as a result of a new notice under the TIA involving a new job and a different contractor (Nordev).
Each TIA notice represented the start of a new use of the premises. The use of the premises by the Director-
General pursuant to a TIA notice immediately before 30 March 1998 had ceased by that date. The Director-
General did not again so use the premises until 26 June 2000 and then did so pursuant to a new notice under
the TIA. This was the start of a new use of the premises albeit for a similar purpose.
(29) Alternatively again it was the re-establishment on the premises of a use that had been abandoned. In
Hudak, supra, Mahoney JA said at p. 713 "Abandonment ordinarily involves, at least as one part of the
concept, that, at the relevant date, the land was being used for the purpose claimed as the existing use and that
that use has subsequently been given up or has ceased.�
(30) In the present case the use of the premises involving W. Wall & Sons and the MRD haulage contractors
ceased before 30 March 1998. That use then was �no longer in existence�. See Shanahan Crash Repairs Pty.
Ltd. �v- Port Adelaide City Corp. (1978) 20 SASR 491 at 511 and Hudak, supra, at p. 716. The use of the land
was discontinued or terminated and it was not known if it would ever recommence or commence afresh. Each
case is different and notwithstanding the distinction suggested by Prof. Fogg, supra, at p. 687 between
�abandonment� on the one hand and �discontinuance�, �cessation�, and �termination� on the other I think
they are synonymous in the circumstances of this case. The physical cessation of relevant activities is a
relevant consideration in this area. See William McKenzie Pty. Ltd. �v- Leichhardt Municipal Council (1964)
10 LGRA 137. It is not without relevance that the notice under the TIA is headed �Temporary Occupation and
Use of Land � Notice of Entry or Permission to Enter�. In my view the development in the present case started
after 30 March 1998 and would, but for the effect of Boral in this particular instance and to the extent already
indicated, be assessable development. See IPA s.1.4.6(4).
(31) Sec. 6.1.51A IPA was also referred to in argument. The Respondent conceded on the facts here that it had
no application and I think that concession is correct.
(32) For these reasons the application will have to be dismissed.
© www.ecodirections.com
45
23. There are not many decisions of the Planning and Environment Court relating to costs because the general rule is
that each party pays its own costs. However, Judge Wall QC made an order for costs against the Local Government
in Evans v Townsville City Council [2000] QPELR 337. There was a failure of the Local Government to comply
with Section 4.1.40(2) of the Integrated Planning Act 1997. The order for costs was made under Section
4.1.23(1)(e) and (i) of the Integrated Planning Act 1997. Subparagraph (e) is where a party has incurred costs
because another party has defaulted in the Court’s procedural requirements. Subparagraph (i) arises where the
Local Government (among other parties) does not properly discharge its responsibilities in the proceedings.
Overview of the Integrated Planning and Other Legislation
Amendment Act 2001
24. There are many changes to the Integrated Planning Act 1997. These have not yet come into force. The changes
can be broadly described in the following areas:-
(a) Existing rights
(b) The introduction of a new compliance stage in IDAS
(c) Changes to the infrastructure provisions
(d) New EIS provisions.
25. There is also some changes to private certification.
26. It is not possible in this overview to be exhaustive. A number of quotes have been taken from the Explanatory
Notes to summarise a number of the provisions of the new legislation.
27. It should be noted that the numbering in the legislation may change from time to time. This is especially so when a
new reprint is authorised by the Parliamentary Counsel. The section numbers that I refer to are those set out in the
Explanatory Notes. You will need to check as time goes by to make sure that those numbers have not changed.
28. The objects of the legislation as set out in the Explanatory Notes are:-
The objectives of this Bill are to :
• improve the operation of aspects of the Integrated Planning Act 1997 (IPA), in particular the Integrated
Development Assessment System (IDAS) by:
� changing the way some key aspects of the Act operate;
— removing some requirements and procedures that are not adding value to the planning and
development assessment system;
— clarifying and simplifying the operation of other aspects of the IPA; and
— removing anomalies and improving the text.
© www.ecodirections.com
46
• implement IDAS for a development related approval in the Electricity Act 1994 (the Electricity Act).
• amend the Building Act 1975 (the Building Act) for consistency with an amendment to the IPA.
• Amend the Local Government and Other Legislation Amendment Act 2000 to omit a redundant
uncommenced section.
• Amend the Sewerage and Water Supply Act 1949 for consistency with changes made in this Bill; and
• Amend the Water Act 2000 for consistency with the provisions of this Bill.
29. The reasons for the legislation have been set out in the Explanatory Notes as follows:-
In August 1998, the Minister for Communication and Information, Local Government and Planning
announced an operational review of the Integrated Planning Act 1997 (IPA), to commence during the first half
of 1999. Public submissions were invited for the review in May 1999, and 120 submissions were received.
These were assessed and a preliminary
report was produced recommending various legislative and administrative changes. The report was the basis
for extensive discussions with key stakeholder groups about the actions that should be taken.
The main reason for the legislation is to make the legislative changes agreed with stakeholders to reflect the
findings of the review, and to refine the way in which parts of the IPA operate. The Bill also seeks to clarify
local governments� power to charge private certifiers a fee for carrying out certain statutory building
functions.
Way in which the objectives are to be achieved
The objectives of the Bill are to be achieved by amending the IPA and related legislation to implement the
findings of the operational review of the legislation.
30. Many of the provisions in the Act are designed to clarify and enhance the rights and liberties of individuals. This is
described in the Explanatory Notes as follows:-
Many provisions in the Bill are designed to clarify and enhance the rights and liberties of individuals.
Examples include:
• Changes to division 4 of chapter 1 of the IPA designed to simplify and clarify existing use rights. The
changes have combined and rationalized the existing provisions to make them easier to interpret, without
changing their intent or scope.
• Changes to the bases on which owners may seek early acquisition of designated premises on hardship
grounds (section 2.6.19) have been expanded to allow owners with the benefit of existing development
approvals to seek acquisition if the designation has made the proposed development unviable. Previously,
the provisions only applied to development applications that had, or were likely to be refused.
• The powers of the Planning and Environment Court to make findings of substantial compliance with
procedures have been expanded to apply to all proceedings, instead of only appeal proceedings (section
© www.ecodirections.com
47
4.1.5A). This will ensure person�s rights to hearings are not compromised on the basis of technicalities
concerning processes.
Some provisions in the Bill may adversely affect the rights and liberties of some individuals. However careful
consideration has been given in developing these provisions to ensure that any effects on individuals have been
limited, and are justified having regard to the public benefits of the provisions. These provisions are:
• Changes to designation arrangements (sections 2.6.15 and 2.6.19) for when an interest only (such as an
easement) is taken over the designated land. The changes prevent designations ceasing to have effect after
six years because technically the land would still be in private ownership. They also prevent owners
seeking acquisition of the owners� remaining interests on hardship grounds. Both of these changes
address anomalies in the existing arrangements, which do not account for the taking of easements, and
while ostensibly reducing owners rights, are of little practical disbenefit.
• Changes to the bases on which owners may seek early acquisition of designated premises on hardship
grounds which effectively combine two currently separate grounds related personal circumstances (as
opposed to development related circumstances discussed above). The two grounds concern the need to sell
land for personal reasons, and the inability to obtain a fair market value. Whereas these grounds may
currently apply independently, their combination in the Bill means that early acquisition on hardship
grounds may be claimed for personal reasons only, and where the owner has been unable to sell the land
at a fair market value. This potentially reduces the range of
available circumstances in which hardship may be claimed for personal reasons. However the changes
are considered justified having regard to:
— Practical difficulty in determining whether the inability to achieve a fair market value is related to the
designation, or a range of other factors which influence the market for the land; and
— The crucial need for clarity in applying the criteria for hardship, given the substantial financial risk
that may arise for designators, particularly for corridor designations which may affect hundreds, or
even thousands of owners. Faced with these risks, such designators may decide against designation,
which ultimately may expose the public to higher costs in providing the infrastructure.
• The declarations and orders powers of the Planning and Environment Court (sections 6.1.21 and 6.1.22)
have been modified to broaden the circumstances in which the Court can cancel a development approval.
Currently the court can only cancel an approval on the basis of fraud by the applicant. The Bill removes
this limitation, but replaces it with a requirement for the court to consider compensation for any person
who has suffered loss as a result of the cancellation. Experience in other jurisdictions suggests such a
power, when available, is only, if ever, invoked by the courts in the most extreme of circumstances.
However, without this power, development approvals that may have been given in error, and with serious
adverse consequences, would stand.
• The Bill enables �assessing authorities� to give enforcement notices for offences about extracting
material from Queensland waters without first giving a show cause notice (section 4.3.8). The provision is
© www.ecodirections.com
48
related to the pending integration of development approvals for these activities into IDAS, and reflects
enforcement arrangements under existing legislation.
Some provisions in the Bill are proposed to have retrospective effect. In all cases, this is intended to reinforce
or clarify, and not compromise, the rights of persons under the IPA. The retrospective aspects of the Bill are:
• Sections 5.3.5(6) and (7) have been amended to clarify local governments have always had the power to
charge a fee set by resolution for accepting materials from private certifiers. The validating provisions do
not affect the outcome of legal action commenced before the legislative amendments come into force.
Similarly, the validating provisions will not affect any written agreements to settle claims parties have
entered into. The validating legislation is intended to merely clarify existing arrangements and
expectations among stakeholders.
• New section 6.1.35C has been inserted to confirm and protect rights obtained under preliminary
approvals before the commencement of the section.
Immunity from proceeding or prosecution
The Bill contains no provisions conferring immunity from proceeding or prosecution. However the powers for
the Minister to call in a development application in chapter 3 part 6 have been expanded to allow the Minister
to also call in an application to change or cancel a development approval. These provisions already exclude
appeals against the Minister�s decision, so the expanded call in powers will also exclude appeals. The
Minister�s decision is however subject to judicial review by the Planning and Environment Court under
section 4.1.21.
31. Regard for aboriginal and island custom consistent with the Commonwealth Native Title Act 1993 has now been
introduced as part of IDAS.
32. Section 4.2.3 dealing with the purpose of the legislation will be amended and that amendment is described in the
Explanatory Notes as follows:-
Clause 5 amends s 1.2.3(2) to replace the existing definition of �the precautionary principle� for the purposes
of the IPA, with the definition provided in the Intergovernmental Agreement on the Environment and the
Commonwealth Environment Protection and Biodiversity Conservation Act 1999. The amendment allows for a
consistent interpretation of the term for both Commonwealth and Queensland legislation.
33. There is a new meaning of the word development and the meaning of lawful use.
34. Relevantly, a material change of use includes an increase in the intensity or scale of the use but not a reduction in
the use.
© www.ecodirections.com
49
35. Whilst there is no intention to change the substance of Part 4 of Chapter 1 dealing with uses and rights it has been
changed to improve the structure and clarity of the provisions.
36. IDAS has been replaced. The Explanatory Notes set out the following:-
Clause 27 replaces chapter 3. Major changes to chapter 3 include:
• An application must be properly made and all time frames in the IDAS process start from the time an
application is properly made.
• Acknowledgement notices are no longer a concept under the Act. Instead an assessment manager must in
some cases endorse a copy of a properly made application and return it to the applicant.
• Non-acceptance notices must be sent if the assessment manager receives an application that is not
properly made.
• Improved provisions providing further guidance about the variation of a planning scheme as part of a
preliminary approval.
• Transitional referral co-ordination is moved to chapter 3 of the Act.
• The requirements for changing applications have been refined and are dealt with in separate sections
according to their effect on the IDAS process.
• The notification stage has been changed to a �floating� stage to be more flexible and responsive to
individual circumstances, in particular changes made to development applications in the course of the
IDAS process.
• Provisions for changing or canceling development approvals are consolidated in a new part 5A of chapter
3 of the Act.
• An additional stage is added to IDAS. The compliance stage will simplify aspects of the IDAS process by
allowing for development that simply requires assessment for compliance with certain standards proceed
straight through a simple compliance check. The stage will also apply for checking documents related to
development (as opposed to checking the development itself) for compliance.
37. A new concept of compliance development and compliance assessment has been introduced into IDAS.
38. The role of a preliminary approval and how it may override a local planning instrument is subject to the following
comments in the Explanatory Notes:-
Generally,
• the provisions for preliminary approvals which vary the effect of a planning scheme, previously limited to
material changes of use requiring impact assessment, can now accommodate a broader range of
development;
• an applicant for a preliminary approval that varies a planning scheme must apply at the same time for the
change to the scheme to be made;
© www.ecodirections.com
50
• all applications for preliminary approvals involving variations to the planning scheme will require public
notification. The only exception will be where a preliminary approval is �staged� and the development
being applied for is subject to code assessment because of the operation of a preliminary approval for an
earlier stage,
• a preliminary approval for a material change of use may vary the effect of the planning scheme for
aspects of development related to the material change of use. For example, a preliminary approval for a
material change of use for a �master planned community� may vary assessment requirements or include
codes for building work associated with the material change of use (eg for building height, bulk or
density), or associated reconfiguration (eg through lot size or other lot characteristics) A preliminary
approval for other development may vary the operation of the scheme only for that aspect of development.
• a variation to the operation of a scheme as a consequence of a development approval may only be in
response to an application dealt with under this section. A local government may not vary the scheme in
this way without an application seeking the variation. Any change to the scheme that is not the
consequence of a preliminary approval dealt with under this section, would need to be made using the
Schedule 1 process in the Act.
39. Some changes have been made to the application for development approval. A non acceptance notice is not dealt
with in a new Section 3.2.3. A new Section 3.2.4 sets out when applications must be endorsed as accepted.
40. Additional third party advice or comment is retained with the original Section 3.2.7 being renumbered as Section
3.2.5 and clarified.
41. A new Section 3.2.6 deals with public scrutiny of applications and related material.
42. As to the notification stage a new Section 3.4.2(3) has been added and the Explanatory Notes describe that as
follows:-
New subsection (3) makes an exception to the requirement for public notification if a preliminary approval has
already been issued for development and the application proposes certain changes to the way subsequent
development applications would be dealt with under the approval. There is no need to publicly notify the
application provided �
• the only change in the type of assessment is from code assessment to either self assessment or compliance
assessment, and
• any new code sought to be included in the preliminary approval to apply for subsequent approvals is
substantially consistent with codes contained in the existing preliminary approval.
43. As to Negotiated Decision Notices the Explanatory Notes say as follows:-
© www.ecodirections.com
51
This division has been drafted to deal with confusion about the relationship between suspension of the
applicant�s appeal period and making representations for a negotiated decision notice. The applicant may
suspend their appeal period in writing (under section 3.5.19) before making an application for a negotiated
decision notice (under section 3.5.18). The applicant may decide to take this course of action to give them
more time to prepare their application. Alternatively, and even if the applicant takes no action to suspend their
appeal period, the appeal period will automatically be suspended as soon as the application for a negotiated
decision notice is received.
44. A new Part 6 has been added to Chapter 3 dealing with the changing or canceling of development approvals. In the
Explanatory Notes the following appears:-
Part 6 replaces sections 3.5.22 to 3.5.26, section 3.5.33, and transitional section 6.1.44 with a separate part
dealing with all changes to development approvals. Division 1 deals with all changes (including changes to
currency periods and conditions) sought by application. Division 2 deals with changing or canceling certain
conditions by the assessment manager or concurrence agency without the consent of the owner or occupier of
land.
The scope for changing a development approval under division 1 of part 6 is limited in two ways.
Firstly, section 3.6.2(5) states a deciding entity must refuse an application for a change if it is satisfied that if a
fresh application for the development, including the change, was made at the time the original application was
made, it would need to be treated in a different way to that provided for under the division.
Secondly, the use of this part is limited generally by the definition of �development approval� for the Act. The
definition states the relationship between a development application and any approval of that application. The
scope of an approval cannot exceed (but may vary or be less than) the scope of the application. Therefore an
application to change a development approval is also limited to dealing with the development originally
applied for That is, no new aspects of development can be dealt with and added by a change, but aspects may
be varied or removed.
It is not intended that an application for change under the division be used where a new development
application is necessary. Because of these constraints, it is envisaged that only relatively minor changes,
limited to the jurisdiction and interest of the deciding entity, will be dealt with through this Part. For that
reason, provision is made (see section 3.6.2(1)) for an application for change to be treated in a similar way to
a simple development application, for which there are no referral agencies, and therefore no integration or co-
ordination of referrals or responses. The deciding entity for the matter will act as the assessment manager,
wholly responsible for the application.
45. A new Part 7A has been inserted into Chapter 5 and deals with Environmental Impact Statements. The Explanatory
Notes describe when the EIS process applies and its purpose and how to apply for terms of reference as follows:-
© www.ecodirections.com
52
Section 5.7A.1 (When EIS process applies)
This section provides for part 7A to apply to assessable development or to community infrastructure on land to
be designated, that is prescribed by regulation.
The part also applies for any proposal that is a �controlled action� under the Commonwealth Environment
Protection and Biodiversity Conservation Act 1999, subject to the written agreement of the chief executive.
Section 5.7A.2 (Purpose of EIS process)
This section states the various aspects of the purpose of undertaking the EIS process for a proposal.
Section 5.7A.3 ( Applying for terms of reference)
Subsection (1) provides for the action that must be taken by a person proposing development or proposing
designation of land for community infrastructure if part 7A applies.
Subsection (2) provides for the form of an application for terms of reference for an EIS under part 7A, and for
a fee to accompany the application.
Subsections (3) and (4) provide for when an EIS that is necessary under part 7A must be prepared if an
applicant proposes to make an application for preliminary approval.
46. The EIS provisions deal with the preparation of a draft EIS (Section 5.7A.6); the public notification of the draft
EIS (Section 5.7A.7); making submissions on the draft EIS (Section 5.7A.8); the Chief Executive evaluates the
draft EIS, submissions and other relevant material (Section 5.7A.9); EIS assessment report is prepared by the Chief
Executive (Section 5.7A.10); and who the Chief Executive must give the EIS and other material to is described in
Section 5.7A.13.
47. There have been some amendments to Schedule 1 dealing with the process for making and amending Planning
Schemes.
48. Schedule 8 has been replaced. This schedule deals with assessable and self assessable development.
49. A new Schedule 9 has been included. This describes what development is exempt. The Explanatory Notes say as
follows:-
The heading is changed to clarify that the schedule refers only to development that is exempt from regulation
under a planning scheme. Development listed under this schedule is not exempt from regulation under
schedule 8 (ie parts 1 and 2.). inclusion of these items under an entirely separate schedule also reinforces this.
50. There have been considerable amendments to Schedule 10 (Dictionary). The Explanatory Notes say as follows:-
© www.ecodirections.com
53
Clause 85 replaces schedule 10. The substantial changes to the IPA in the Bill have meant that many new
definitions are included, others are amended, and others omitted. Numerous definitions previously included in
schedule 8 have also now been included in schedule 10 due to the splitting of schedule 8 up into schedules 8
and 9. Because of the extensive changes to the definitions resulting from the provisions of the Bill, and to
facilitate ease of use of the Bill, schedule 10 has been replaced entirely.
51. It is reasonable to expect that the Integrated Planning Act 1997 will stay the same way it is once these IPOLA
amendments have commenced. Now that the operational review and public submissions have been taken into
account and put into legislation it would be useful if the Integrated Planning Act 1997 could remain unamended
(except for minor amendments) so that all the stakeholders in planning and environment issues have the
opportunity of fully understanding the legislation without having to track major changes. That will help bring
certainty to the administration of development issues in Queensland.
52. It is important to note that the amendments have not change Section 4.1.48 dealing with Alternative Dispute
Resolution processes. While the legislation deals with these processes in the context of an appeal to the Planning
and Environment Court it is well recognised that Alternative Dispute Resolution (ADR) is a voluntary process
which can occur at any particular time in the development assessment procedures. Some parts of ADR can usefully
be used to assist in plan making. There are New South Wales examples of independent assessment of applications
where there are objections. All of these matters will be discussed in a seminar on ADR and Planning and
Environment Issues during 2002. The seminar series will come to Cairns, Townsville and Mackay in July, 2002.
The dates are as follows:-
Cairns, Thursday 18 July, 2002
Townsville, Tuesday 23 July, 2002
Mackay, Friday 26 July, 2002
Everyone who has responded to a questionnaire after attending the two seminars which have already been held in
the series agrees that ADR needs to be better understood by Stakeholders who deal with planning and environment
issues and that the seminar increased the level of understanding of ADR. For more information please go to the
webpage at www.ecodirections.com.