Update on the SOUTHWEST COASTAL LA Project
Governor’s Advisory Commission MeetingAugust 7, 2013
Abbeville, LA
committed to our coastcommitted to our coast
Coastal Protection and Restoration Authority of Louisiana
Coastal Protection and Restoration Authority of Louisiana
• The Feasibility Cost Share Agreement was signed between CPRA and the Corps in January 2009.
• The study is multi-purpose = coastal restoration and hurricane protection. Is cost shared 50-50 between the CPRA and the Corps.
• The Project Delivery Team has the active participation of many stakeholder groups and agencies.
• Study was transitioned to the Corps new 3X3X3 planning paradigm (SMART Planning).
• Funds have been made available to complete the study.
Southwest Coastal Overview
Coastal Protection and Restoration Authority of Louisiana
Status
• The Study has produced a Feasibility Scoping Report and a Value Engineering Report.
• Full structural inventory has been completed.
• Hydraulic models developed:• ADCIRC model (storm surge)• Regional Circulation (salinity)
• The current schedule indicates a Draft Feasibility Report in November 2013 and and a Chief’s Report Milestone in September 2014.
• The Alternatives Milestone (all work to date, plus the alternatives carried forward) was approved by the Corps vertical team in June 2013.
• Measure types under evaluation are in concert with the 2012
State Master Plan.
Coastal Protection and Restoration Authority of Louisiana
NER Focused Array of Alternatives
• No Action Plan (Future without-project condition)• Large Integrated Restoration Across Basins• Moderate Integrated Restoration (Hydrologic Emphasis)• Moderate Integrated Restoration, including Gum Cove• Entry Salinity Control (Emphasis)• Interior Perimeter Salinity Control (Emphasis)• Marsh and Shoreline (Minimal Hydraulic & Salinity
Control)
Coastal Protection and Restoration Authority of Louisiana
NED Focused Array of Alternatives
• No Action Plan (Future without-project condition)• Lake Charles Risk Reduction Structural Feature• Abbeville Risk Reduction Structural Feature• Lake Charles Structural and Abbeville Non-
Structural• Abbeville Structural and Lake Charles Non-
Structural• Non-structural plan
Upcoming Milestone Schedule
29 Oct 2013 Tentative Selected Plan
15 Nov 2013 Public Review/ ATR/ IEPR
30 Jun 2014 Final Report Milestone/ CWRB
25 Jul 2014 State and Agency Review Complete
30 Sep 2014 Chief’s Report Milestone
9
Coastal Protection and Restoration Authority of Louisiana
Discussion/Questions
Norwyn [email protected]
Darrel [email protected]
Southwest Coastal