US 69Missouri River Bridge

Design-Build

Rachel Henkhaus, PE, PhDGarver

Page 2: US 69 Missouri River Bridge Design-Build

Agenda

• Project Overview & Design Goals

• Bridge Layout and Typical Sections

• Bridge Design Considerations

• Bridge Construction

Page 3: US 69 Missouri River Bridge Design-Build

Schedule

• RFQ Issued – January 9, 2014• SOQ Submitted – February 4, 2014• Shortlist – February 20, 2014• Proposal Due – June 6, 2014• Award – July 9, 2014• Design – July 2014 – Spring 2015• Construction – September 2014• New Bridge Open to Traffic - December 2016

Page 4: US 69 Missouri River Bridge Design-Build

Project Goals

1. Schedule – Open all lanes of traffic no later than December of 2016

2. Cost – Deliver a competitively priced project that is both practical and economical

3. Durability – Construct low maintenance bridge(s) that will provide at least a century of service

4. Safety – Create and sustain an exceptionally safe project work environment

Page 5: US 69 Missouri River Bridge Design-Build

Project Goals

• Method of Handling Traffic – 200 pts

• Missouri River Bridge Design – 200 pts

• Safety – 100 pts

• Cost – 500 pts

Page 6: US 69 Missouri River Bridge Design-Build

Design Goals

• Minimize Earthwork (Roadway)

• Minimize Bridge Length

• Constructability

Page 7: US 69 Missouri River Bridge Design-Build

Design Goals

• Minimize Earthwork (Roadway)

• Minimize Bridge Length

• Constructability

Page 8: US 69 Missouri River Bridge Design-Build

Third Parties/Environmental Coordination

• KDOT

• Corps of Engineers

• Fairfax Drainage District Levee

• Riverside QuindaroBend Levee

• Coast Guard

• Unified Government

• City of Riverside

• Railroad

• FAA

• Casino

• Historic Fairfax Bridge

• Pallid Sturgeon

Page 9: US 69 Missouri River Bridge Design-Build

Design Goals

• MOT - Maintain one lane each direction

• Close Harvester Road

• Reroute Argosy Parkway

Page 10: US 69 Missouri River Bridge Design-Build

Design Goals

• US 69 Fill Placement

Page 11: US 69 Missouri River Bridge Design-Build

Design Goals

• US 69 Fill Placement

Page 12: US 69 Missouri River Bridge Design-Build

Existing Bridge Considerations

• Settlement Analysis

Page 13: US 69 Missouri River Bridge Design-Build

Existing Bridge Considerations

• Settlement Monitoring Plan

Page 14: US 69 Missouri River Bridge Design-Build

Existing Bridge Considerations

• Settlement Monitoring Plan

Page 15: US 69 Missouri River Bridge Design-Build

Bridge Design

• Span Layout– End Bent 10

• Superstructure– Typical Section

• Substructure– Typical Bent

• Bridge Construction

• Other Considerations

Page 16: US 69 Missouri River Bridge Design-Build

Bridge Design

Page 17: US 69 Missouri River Bridge Design-Build

Bridge Design

1 32

Page 18: US 69 Missouri River Bridge Design-Build

Bridge Design

3 54

Page 19: US 69 Missouri River Bridge Design-Build

Bridge Design

5 6 9 1087

Page 20: US 69 Missouri River Bridge Design-Build

Bridge Design – End Bent 10

• Construct MSE Wall with pile spacer

• Allow settlement

• Prebore with polymer slurry

• Drive pile to rock

• Place concrete & remove slurry

• Fill pile spacer with sand

Page 21: US 69 Missouri River Bridge Design-Build

Bridge Design – End Bent 10

• Construct MSE Wall with pile spacer

• Allow settlement

• Prebore with polymer slurry

• Drive pile to rock

• Place concrete & remove slurry

• Fill pile spacer with sand

Page 22: US 69 Missouri River Bridge Design-Build

Bridge Design – End Bent 10

• Construct MSE Wall with pile spacer

• Allow settlement

• Prebore with polymer slurry

• Drive pile to rock

• Place concrete & remove slurry

• Fill pile spacer with sand

Page 23: US 69 Missouri River Bridge Design-Build

Bridge Design – End Bent 10

• Construct MSE Wall with pile spacer

• Allow settlement

• Prebore with polymer slurry

• Drive pile to rock

• Place concrete & remove slurry

• Fill pile spacer with sand

Page 24: US 69 Missouri River Bridge Design-Build

Bridge Design – End Bent 10

• Construct MSE Wall with pile spacer

• Allow settlement

• Prebore with polymer slurry

• Drive pile to rock

• Place concrete & remove slurry

• Fill pile spacer with sand

Page 25: US 69 Missouri River Bridge Design-Build

Bridge Design – End Bent 10

• Construct MSE Wall with pile spacer

• Allow settlement

• Prebore with polymer slurry

• Drive pile to rock

• Place concrete & remove slurry

• Fill pile spacer with sand

Page 26: US 69 Missouri River Bridge Design-Build

Bridge Design – Typical Sections

Page 27: US 69 Missouri River Bridge Design-Build

Bridge Design – Midas vs. MDX

Page 28: US 69 Missouri River Bridge Design-Build

Bridge Design – Midas vs. MDX

Page 29: US 69 Missouri River Bridge Design-Build

Bridge Design – Midas vs. MDX

Page 30: US 69 Missouri River Bridge Design-Build

Bridge Design – Midas vs. MDX

Page 31: US 69 Missouri River Bridge Design-Build

Bridge Design – Typical Bent

Page 32: US 69 Missouri River Bridge Design-Build

Bridge Design – Load Combinations & Scour

• Extreme Event Full Barge: Degradation only

• Extreme Event Empty Barge: Degradation & half 100-year Scour

• Strength & Service: Degradation & 500-year Scour

• Stability Extreme Event: Scour to Bedrock

Page 33: US 69 Missouri River Bridge Design-Build

Bridge Design – Load Combinations & Scour

• Extreme Event Full Barge: Degradation only - Controls for River Bents

• Extreme Event Empty Barge: Degradation & half 100-year Scour

• Strength & Service: Degradation & 500-year Scour

• Stability Extreme Event: Scour to Bedrock

Page 34: US 69 Missouri River Bridge Design-Build

Bridge Design – Full Barge Vessel Collision

Full Model

Transverse Vessel Collision

Longitudinal Vessel Collision

Page 35: US 69 Missouri River Bridge Design-Build

Bridge Design – Full Barge Vessel Collision

Moment TorsionShear

Page 36: US 69 Missouri River Bridge Design-Build

Bridge Design – Non-Linear Soil/Rock Springs

Soil Springs

Rock Springs

Page 37: US 69 Missouri River Bridge Design-Build

Bridge Design – Non-Linear Soil/Rock Springs

Rock Springs

Page 38: US 69 Missouri River Bridge Design-Build

Bridge Design – Non-Linear Soil/Rock Springs

Page 39: US 69 Missouri River Bridge Design-Build

Demolition

Page 40: US 69 Missouri River Bridge Design-Build

Demolition

Page 41: US 69 Missouri River Bridge Design-Build

Bridge Construction

Page 42: US 69 Missouri River Bridge Design-Build

Bridge Construction

Page 43: US 69 Missouri River Bridge Design-Build

Drilled Shaft Construction

Page 44: US 69 Missouri River Bridge Design-Build

Bridge Construction

Page 45: US 69 Missouri River Bridge Design-Build

Bridge Construction

Page 46: US 69 Missouri River Bridge Design-Build

Bridge Construction

Page 47: US 69 Missouri River Bridge Design-Build

Bridge Construction

Page 48: US 69 Missouri River Bridge Design-Build

Bridge Construction

Page 49: US 69 Missouri River Bridge Design-Build

Bridge Construction

Page 50: US 69 Missouri River Bridge Design-Build

Bridge Construction

Page 51: US 69 Missouri River Bridge Design-Build

Midas Advantages

• Geometry updates for Design-Build

• Result graphics & tables

• Composite-Beam & Plate Elements

• Substructure Analysis – Global Model

–Utilize superstructure & adjacent bent

–Non-linear & Torsional soil springs

–Non-linear analysis

Page 52: US 69 Missouri River Bridge Design-Build

Midas – Lessons Learned

• Substructure – multiple design files

• Separate analysis:

– P-Delta

–Nonlinear

Page 53: US 69 Missouri River Bridge Design-Build

Thanks, Midas!Questions?