US Army Corps of Engineers
BUILDING STRONG®
Portland District - Navigation Update
COL Steve Miles
Commander
Portland District
PNWA Annual Meeting
13 October 2009
BUILDING STRONG®PORTLAND DISTRICT 2
Topics
The Dalles D/S Gate Emergency Repairs
Columbia River Channel Improvements
MCR Jetty Major Rehab
MCR Buoy Installation
Long-Term Planning► Joint Portland / Walla Walla 5-Year Planning► Columbia River Long-Term Outage (Dec 2010)
• The Dalles • John Day
BUILDING STRONG®PORTLAND DISTRICT 3
The Dalles Downstream Miter Gate - Emergency Repairs
What Happened:
Mar 07, 08, 09: Intermediate Repairs
Nov 07: Instrument Install
28 Sep 09: ► Operator Identifies Possible Problem► Instrumentation Review► Remote Vehicle Inspect► Project Stops Operation
29 Sep 09: ► Corporate Review► River Closed
30 Sep 09:
► Diver Inspection ► Dewatering ► Letter Contract to AAC
1 Oct 09:► Cleaning / Inspection / Repair Plan► Repairs Begin
12 Oct 09: Lock Re-Opens
BUILDING STRONG®PORTLAND DISTRICT 4
The Dalles Downstream Miter Gate - Emergency Repairs
The Problem:► Cracks in both miter
gate leaves.
► Gate vibrates upon un-mitering/opening.
► Gate has no adjustability.
► Lower 30’ not mitering.
BUILDING STRONG®PORTLAND DISTRICT 6
The Fix:
► Interior girder pockets reinforced with boxes bolted in place.
The Dalles Downstream Miter Gate - Emergency Repairs
BUILDING STRONG®PORTLAND DISTRICT 7
The Dalles Downstream Miter Gate - Emergency Repairs
BUILDING STRONG®PORTLAND DISTRICT 8
The Fix:
► Interior girder pockets reinforced with boxes bolted in place.
► Web of lower girder doubled up and bolted into place.
► Replace and Re-tensioned all pintle bolts.
► Repaired 32 different areas where cracks existed by welding.
► End post to quoin block stiffeners reinforced with bolted plates.
► Additional Instrumentation
The Dalles Downstream Miter Gate - Emergency Repairs
BUILDING STRONG®PORTLAND DISTRICT 9
The Fix:
► Interior girder pockets reinforced with boxes bolted in place.
► Web of lower girder doubled up and bolted into place.
► Replace and Re-tensioned all pintle bolts.
► Repaired 32 different areas where cracks existed by welding.
► End post to quoin block stiffeners reinforced with bolted plates.
► Additional Instrumentation
The Dalles Downstream Miter Gate - Emergency Repairs
• Additional Instrumentation
BUILDING STRONG®PORTLAND DISTRICT 10
The Dalles Downstream Miter Gate - Emergency Repairs
The Future:► Increased Monitoring
• Instrumentation• Periodic ROV / Dive Inspections
► Engineering Review of repair work needed during Long-Term Outage
► Dec 09 (tent.): Interim Inspection & Lock Closure (ICW Walla Walla)
► Mar 10: Annual Outage
► Mar 10 – Dec 10 (if needed): Interim Inspection / Lock Closure
► Dec 10 – Apr 11: Long-Term Outage
BUILDING STRONG®PORTLAND DISTRICT 11
Topics
The Dalles D/S Gate Emergency Repairs
Columbia River Channel Improvements
MCR Jetty Major Rehab
MCR Buoy Installation
Long-Term Planning► Joint Portland / Walla Walla 5-Year Planning► Columbia River Long-Term Outage (Dec 2010)
• The Dalles • John Day
BUILDING STRONG®PORTLAND DISTRICT 12
Columbia River Channel Improvements
Project Completion: Project Completion: 31 Dec 1031 Dec 10
FY 10 Work:FY 10 Work:
► Completion of Dredging w/ Completion of Dredging w/ Dredge Oregon (Summer ’10)Dredge Oregon (Summer ’10)
► St. Helens:St. Helens:• Dredging Begins 13 Oct 09 Dredging Begins 13 Oct 09 • Blasting 1 Nov 09 – 28 Feb 10Blasting 1 Nov 09 – 28 Feb 10• Ross Island DisposalRoss Island Disposal
► Slaughter’s Bar:Slaughter’s Bar:• Dredging RM 66+00 to RM 67+05 Dredging RM 66+00 to RM 67+05 • Dibblee Point DisposalDibblee Point Disposal
BUILDING STRONG®PORTLAND DISTRICT 13
Columbia River Channel Improvements
http://www.youtube.com/watch?v=tMxyspJgGHk&feature=related
BUILDING STRONG®PORTLAND DISTRICT 14
Topics
The Dalles D/S Gate Emergency Repairs
Columbia River Channel Improvements
MCR Jetty Major Rehab
MCR Buoy Installation
Long-Term Planning► Joint Portland / Walla Walla 5-Year Planning► Columbia River Long-Term Outage (Dec 2010)
• The Dalles • John Day
BUILDING STRONG®PORTLAND DISTRICT 15
MCR Jetty Major Rehab
North Jetty 2.5 miles long 1914-1917
Washington
Pacific Ocean
Columbia River Estuary
Oregon
South Jetty 6 miles long 1885-1913
Jetty “A” 1 mile long 1938-39
View to NE
BUILDING STRONG®PORTLAND DISTRICT 16
MCR Jetty Major Rehab
North Jetty 2.5 miles long 1914-1917
Washington
Pacific Ocean
Columbia River Estuary
Oregon
South Jetty 6 miles long 1885-1913
Jetty “A” 1 mile long 1938-39
View to NE
Final approval in March 2010 (For FY ’12 Budget Cycle)► Recommended Plan: Review - Agency Technical Review ► Model Code: Review - Planning Center of Expertise► Environmental Assessment: Public Review in November
The Recommended Plan:► Addresses North, South and Jetty “A” ► Include spur groins and capping
BUILDING STRONG®PORTLAND DISTRICT 17SOUTH JETTY MAJOR REHABILATION
Pacific
Ocean
Mouth of Columbia River
N
255
270
285
30033
0
345
18019
521022
5240
360
375
= spur groin
-40
-30
-20
-10
0
10
20
30
40
50
-260 -240 -220 -200 -180 -160 -140 -120 -100 -80 -60 -40 -20 0 20 40 60 80 100 120
Ocean Side Channel Side
Existing Core StoneRelic Armor Stone
Original Seabed
1v:2h
South North
1v:2h
SA1 stone: 25 to 0 ft MLLW = 35-60 ton (mean = 50 ton)SA2 Stone: 25 to -10 ft MLLW = 8-20 ton (mean = 14 ton)
SA3 Relic Stone: -10 to -20 ft MLLW = 5-15 ton (mean = 10 ton)Reworked Relic Armor Stone = 5-15 ton (mean = 10 ton)
Reworked Core Stone = 0.5 - 7 ton (mean = 4 ton)all stone has gamma=167 lb/ft3
= SA2 select armor units: 5 to -10 ft MLLW , stone = 18 - 30 ton (mean =24 ton)
=optional area to use concrete armor units - would preclude access along crest for future repair
315
-80-70-60-50-40-30-20-10
01020304050
-260 -240 -220 -200 -180 -160 -140 -120 -100 -80 -60 -40 -20 0 20 40 60 80 100 120 140 160 180 200
Ocean/Beach Side Channel Side
Relic Armor Stone
Original Seabed
1v:2.5h
1v:3h
South North
1v:3h
1v:2.5h
= SH1 concrete armor units: 10 to -10 ft MLLW = 15-25 ton (mean = 20 ton), or sized as needed to resist wave actionSH2 Relic Stone: -10 to -20 ft MLLW = 25-45 ton (mean = 34 ton)
all stone has gamma=167 lb/ft3
Re-workedRelic Armor Stone
-40
-30
-20
-10
0
10
20
30
40
50
-260 -240 -220 -200 -180 -160 -140 -120 -100 -80 -60 -40 -20 0 20 40 60 80 100 120
Ocean Side Channel Side
Core StoneRelic Armor Stone
Original Seabed
1v:3h
South North
1v:2h
SB1 stone: 25 to -10 ft MLLW = 25-45 ton (mean = 34 ton)SB2 Select Relic Stone: below -10 ft MLLW = 5-15 ton (mean = 10 ton)
Reworked Relic Armor Stone = 5-15 ton (mean = 10 ton)Reworked Core Stone = 0.5 - 7 ton (mean = 4 ton)
all stone has gamma=167 lb/ft3
=optional area to use concrete armor units
=optional area to use concrete armor units - would preclude land access along crest for futre repair
-40
-30
-20
-10
0
10
20
30
40
50
-260 -240 -220 -200 -180 -160 -140 -120 -100 -80 -60 -40 -20 0 20 40 60 80 100 120
Ocean Side Channel Side
Core StoneRelic Armor Stone
Original Seabed
1v:3h
South North
1v:2h
SC1 stone: 25 to +5 ft MLLW = 25-45 ton (mean = 34 ton)SC2 Stone: 25 to -10 ft MLLW = 8-20 ton (mean = 14 ton)
SC3 Select Relic Stone: below -10 ft MLLW = 5-15 ton (mean = 10 ton)Reworked Relic Armor Stone = 5-15 ton (mean = 10 ton)
Reworked Core Stone = 0.5 - 7 ton (mean = 4 ton)all stone has gamma=167 lb/ft3
=optional area to use concrete armor units
1v:3h
= SC1 select armor units: 5 to -10 ft MLLW; for stone = 25 - 60 ton (mean =45 ton)
=optional area to use concrete armor units - would preclude land access along crest for futre repair
-40
-30
-20
-10
0
10
20
30
40
50
-260 -240 -220 -200 -180 -160 -140 -120 -100 -80 -60 -40 -20 0 20 40 60 80 100 120
Ocean Side Channel Side
Existing Core StoneRelic Armor Stone
Original Seabed
Interim Repair = Reach A, 9-22 ton (mean = 15 ton) / Reach B, 13-32 tone (mean 22 ton)Relic Armor Stone = 5-15 ton (mean = 10 ton)
Core Stone = 0.5 - 7 ton (mean = 4 ton)all stone has gamma=167 lb/ft3
1v:2h
South North
-40
-30
-20
-10
0
10
20
30
40
50
-260 -240 -220 -200 -180 -160 -140 -120 -100 -80 -60 -40 -20 0 20 40 60 80 100 120
Ocean/Beach Side
Channel Side
Existing Core Stone
Relic Armor Stone Benson Beach
Original Seabed
Interim Repair = 6-15 ton (mean = 10 ton)Relic Armor Stone = 5-15 ton (mean = 10 ton)
Core Stone = 0.25 - 3 ton (mean = 1.5 ton)all stone has gamma=167 lb/ft3
1v:1.5h
South North
Scoured seabed armored with relic stone
10 T
New Rock
Sand Foundation
Existing Rock
MCR Jetty Major Rehab -
Example
BUILDING STRONG®PORTLAND DISTRICT 18
31 JAN 2006
HIGHDUNE
LOW BackshoreTrestle Bay
South Jetty
Initial Priorities: - Major scour areas on South Jetty Beach
- Depressed area north of North Jetty
North Jetty
MCR Jetty Major Rehab
BUILDING STRONG®PORTLAND DISTRICT 19
Topics
The Dalles D/S Gate Emergency Repairs
Columbia River Channel Improvements
MCR Jetty Major Rehab
MCR Buoy Installation
Long-Term Planning► Joint Portland / Walla Walla 5-Year Planning► Columbia River Long-Term Outage (Dec 2010)
• The Dalles • John Day
BUILDING STRONG®PORTLAND DISTRICT 20
DATAWELL Directional Wave Buoy
CDIP Wave Rider Buoy
MCR Buoy Installation
Constructed in the Netherlands Centimeter accuracy in wave height Data transmitted via satellite. All data are disseminated on the
CDIP Website updates @ 30 minutes. Alert system if buoy breaks loose.
BUILDING STRONG®PORTLAND DISTRICT 21
!C
CDIP Buoy - "Clatsop Spit"Proposed LocationLNG = 124 7 41.3 WLAT = 46 12 57.3 N630 yards inshore of MCR R"2"
Washington
Oregon
North Jetty
South Jetty
Jetty “A”
Mouth of the Columbia River
(MCR)
BUILDING STRONG®PORTLAND DISTRICT 22
Topics
The Dalles D/S Gate Emergency Repairs
Columbia River Channel Improvements
MCR Jetty Major Rehab
MCR Buoy Installation
Long-Term Planning► Joint Portland / Walla Walla 5-Year Planning► Columbia River Long-Term Outage (Dec 2010)
• The Dalles • John Day
BUILDING STRONG®PORTLAND DISTRICT 23
Portland / Walla Walla District: 5-Year Planning
Joint Portland / Walla Walla Long-Term Planning since 2006
In 2007: Identified Columbia and Snake River Project Maintenance / Repair Needs and draft timeline
Served as basis for Dec 10 – Apr 11 Outage
Next steps: Update and Refine FY 12 to FY 14 Needs
BUILDING STRONG®PORTLAND DISTRICT 24
Columbia River Long-Term Outage (Dec 10 – Apr 11)
Dec Jan Feb Mar Apr May June
The Dalles
Incentive (The Dalles)
John Day
Lower Monumental
Normal Outage
BIOP ………….
Unscheduled Extension
5
5
13
27
27 13
3
13 27
14 Weeks
16 Weeks
10-14 Days
14 Days
5 Days
327
The Dalles, John Day & Lower MonumentalExtended Navigation Lock Outage
10 1313 Weeks
?
BUILDING STRONG®PORTLAND DISTRICT 25
The Dalles Critical Repairs (Dec 10 – Apr 11)
History
Mar 06, 07, 08: Intermediate Repairs
Mar 07: Instrument Install
Sep 09: Emergency Outage
Dec 09: Tentative Short-Term Outage
Mar 10: Normal Outage – Prep for Long-Term Repairs
FY 10: $5 mil for TD Repairs
BUILDING STRONG®PORTLAND DISTRICT 26
The Dalles Critical Repairs (Dec 10 – Apr 11)
Scope of Repairs
Replace Pintle Bearing Assembly
Replace Quoin Block Assembly
Replace Miter Assembly
Replace lower Portion of Gate
Re-establish Load Path
-Quoin Block
-Miter Blocks
-Pintle Bearing
BUILDING STRONG®PORTLAND DISTRICT 27
The Dalles Critical Repairs (Dec 10 – Apr 11)
Acquisition Strategy
Feb 10:
2 Supply Contracts► Pintle Assembly► Adjustable Quoin and Miter
Block Assembly
Apr 10: Repair Contract
-Quoin Block
-Miter Blocks
-Pintle Bearing
BUILDING STRONG®PORTLAND DISTRICT 28
John Day Critical Repairs (Dec 10 – Apr 11)
History Mid -90s: Critical D/S Gate Repairs Jul 07: Cracking in Friction Drum FY 08 – FY 10: Major Rehab Study Jan 08: Friction Drum Cracks Expand Mar 08: Friction Drum Emergency Repair FY 10: Friction Drum Replacement FY 09: ARRA for D/S Gate Replacement
BUILDING STRONG®PORTLAND DISTRICT 29
John Day Critical Repairs (Dec 10 – Apr 11)
Scope of Work
Replace D/S Gate Replace Friction Drums
Acquisition
Contract Awarded to Advanced American Construction (AAC) for Fabrication and Installation
BUILDING STRONG®PORTLAND DISTRICT 30
North Wall Monolith Cracking
John Day Major Rehab Report
3 Year Study (2008-2010)
Issues / Concerns► At Start (62)► Currently (4) (Includes D/S Gate
and Friction Drums)► In Final Report (Est 2)
• Movement of Lock Monoliths (Needs Stabilizing)
• Spillway Gates (May Need Strengthening)
Implement Repairs► Depends on Report Approval and
Funding (Approx 3-5 Years)
BUILDING STRONG®PORTLAND DISTRICT 31
Topics
The Dalles D/S Gate Emergency Repairs
Columbia River Channel Improvements
MCR Jetty Major Rehab
MCR Buoy Installation
Long-Term Planning► Joint Portland / Walla Walla 5-Year Planning► Columbia River Long-Term Outage (Dec 2010)
• The Dalles • John Day