u.s. atlas executive committee august 3, 2005 u.s. atlas tdaq fy06 m&o planning a.j. lankford uc...

17
U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

Upload: kristopher-waters

Post on 17-Jan-2016

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS Executive CommitteeAugust 3, 2005

U.S. ATLAS TDAQFY06 M&O Planning

A.J. Lankford

UC Irvine

Page 2: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

2

ATLAS TDAQ Overview

Page 3: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

3

Overview of FY06 TDAQ M&O Activity

TDAQ Construction Project continues beyond CD-4A. Most hardware acquisition and installation in FY06-07 Much software development, esp. HLT, continues.

TDAQ M&O activity overlaps with Construction in FY06-07. Construction Project ‘labor’ is ramping down quickly. FY06 is first year of ‘significant’ M&O activity. FY06 M&O activity focuses on DAQ & HLT Infrastructure s/w.

TDAQ M&O activities can be classified as: Hardware commissioning Hardware maintenance Software commissioning Software maintenance Operations Detector support TDAQ support

Page 4: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

4

HLT/DAQ Component View

Page 5: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

5

Pre-series Hardware

Page 6: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

6

FY06 Hardware Commissioning & Maintenance

Hardware Commissioning Complete commissioning of Pre-series system

10% scale of final system w/ components of final specs Commission final RoI Builder hardware Commission DAQ infrastructure

Network infrastructure (large central switch) - connectivity to ROS’s DAQ processors - SFI’s, SFO’s, L2SV’s, pROS’s Racks & rack instrumentation

Initial complement of HLT processors - late in year

Hardware Maintenance Pre-series system RoI Builder DAQ infrastructure Test beds - particularly “performance testbed”

Page 7: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

7

Software Development: Transition to M&O

The Combined Test Beam Release of HLT/DAQ software was nearly complete with respect to DAQ and HLT Infrastructure functionality.

This release was commissioned, operated, and maintained for the 2004 ATLAS CTB Run.

Subsequent development of this HLT/DAQ software consists of: Added functionality (e.g. fault tolerance & error recovery) HLT selection algorithm development Refinement of existing code based upon CTB and subsequent

experience and feedback Development of added functionality and algorithms is

Construction Project activity. Refinement of existing code is M&O activity. Starting in FY05, software development is increasingly M&O. After first physics run, software development will be entirely

M&O.

Page 8: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

8

FY06 Software Commissioning & Maintenance

Software Commissioning Commissioning of new functionality Examples of U.S. activity:

LVL2 Supervisor and RoI Builder software DAQ software

– Monitoring

– Inter-process communication and Information Services

– Message passing HLT Infrastructure software

– Run Control & Supervision

– LVL2 Steering

– EF Dataflow

Software Maintenance Maintenance of above (bug fixes, releases, TDAQ/Offline consistency) Incorporate new functionality based upon experience

Page 9: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

9

FY06 Operations

Operating DAQ infrastructure in USA15 and SDX1

in support of Detector (and TDAQ) commissioning

Network administration System administration (DAQ and HLT computer systems)

TDAQ support teams will start rotations once level of activity at Point 1 demands

Page 10: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

10

FY06 Detector & TDAQ Support

Detector Support ROD Crate DAQ maintenance and support Support for:

Detector-specific software development, e.g.:

– ROD software

– Online histogramming & monitoring Detector commissioning Detector calibrations (and test beam runs ?)

TDAQ Support Support development & commissioning of other TDAQ subsystems Examples:

SRB support for commissioning LVL1 trigger subsystems Integration of HLT vertical slices Network support for Dataflow performance tests

Page 11: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

11

FY05 M&O Activities

Hardware Commissioning Pre-series system, including pre-series RoIB DCS for TDAQ racks Planning for TDAQ infrastructure commissioning

Hardware Maintenance Set up RoIB test bench TDAQ test bed maintenance & administration

Software Commissioning Releases, release testing, release testing procedures

Software Maintenance Maintain code authored by U.S. members, e.g.:

Message passing, Information Services, Online Histogramming, HLT Steering, HLT Control, Monitoring

Synchronization of releases with Offline Adapt/port code to new compiler and new CERN Linux

Page 12: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

12

FY05 M&O Activities – p. 2

Operations Completion of CTB run System administration planning

Detector Support TileCal beam test Monitoring Support of production and simulation of test beam data

TDAQ Support Support integration with RoIB in CTB Support of HLT algorithm integration Test bed setup in UK, Dubna

Page 13: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

13

M&O Planning Methodology/History

Experience in FY04, particularly CTB, indicated prior estimates of M&O effort were low.

New bottoms-up estimate of M&O effort in Jan. 2005 By “new kid on block”, w/ input from all involved Based on effort needed for commissioning and ongoing

maintenance of hardware & software components delivered by U.S. Constructed matrix of effort per component vs. time

Estimate larger than prior estimate => add Management Reserve MR added covers ~1/2 of increase in estimate

Checked total estimate w/ 20% of top-down estimate for ATLAS Coordinated w/ TDAQ Management Team

Page 14: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

14

3.6.1 Preoperations – FY06

3.6.1.1 Supervisor – RoI Builder 28k$3.6.1.1.1 ANL: 15k$; Dawson/Drake; TDAQ Support3.6.1.1.2 MSU: 12k$; Ermoline; TDAQ Support

3.6.1.2 Communications & Travel (16k)3.6.1.1.1 ANL: (8k)3.6.1.1.2 MSU: (8k)

3.6.1.3 Programming Support 103k$ (201k)3.6.1.3.1 ANL: 59k$;

Schlereth/TBN; S/w Comm, Detector Supp

3.6.1.3.2 MSU: 44k$ (17k); Ermoline/TBN; H/w+S/w Comm, Det Supp

3.6.1.3.3 UCI: 0k$ (104k); Stancu/Kolos/Negri; H/w+S/w Comm, Det+TDAQ Supp

3.6.1.3.4 UWisc: 0k$ (80k); Wiedenmann/dosAnjos/Xu; S/w Comm, Det+TDAQ Supp

Page 15: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

15

3.6.2 Operations – FY06

3.6.2.1 Supervisor – RoI Builder 137k$

3.6.2.1.1 ANL: 97k$; Dawson/Drake/Schlereth; H/w+S/w Maint, TDAQ Support

3.6.2.1.2 MSU: 40k$; Ermoline; H/w+S/w Maint, Ops, TDAQ Support

3.6.2.2 Communications & Travel 51k$

3.6.2.2.1 ANL: 13k$

3.6.2.2.2 MSU: 13k$

3.6.2.2.3 UCI: 13k$

3.6.2.2.4 UW: 13k$

3.6.2.4 Test Facilities 3.6.2.4.1 ANL: 10k$

3.6.2.4.2 MSU: 11k$

Page 16: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

16

3.6.2 Operations – FY06 (p. 2)

3.6.2.3 Programming Support 668k$ (241k)

3.6.2.3.1 ANL: 248k$Schlereth/TBN; S/w Maintenance, Detector Support

3.6.2.3.2 MSU: 90k$ (22k)Ermoline/Hauser/TBN; S/w Maintenance, Ops

3.6.2.3.3 UCI: 205k$ (206k)Stancu/Ciobotaru/Unel/Kolos/Wheerler/Negri/Rogge

H/w+S/w Maintenance, Ops, Detector+TDAQ Support

3.6.2.3.4 UW: 126k$ (13k)Wiedenmann/dosAnjos/Xu; S/w Maintenance, Det+TDAQ Support

Page 17: U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine

U.S. ATLAS FY06 TDAQ M&O PlanningAugust 3, 2005

17

FY06 Management Reserve FY06 MR priorities (in rough priority order):

Hardware commissioning: 0.25 => 0.5 FTE Software commissioning: 0.25 => 0.5 FTE Hardware maintenance: 0.5 => 1 FTE TDAQ support: 0.4 => 1 FTE Operations: 0.3 => 1 FTE Detector support: 1 => 2 FTE SRB: 1 => 1 FTE; Software maintenance: 2.5 => 2.5 FTE Total: 6.2 => 9.5 FTE ~458k$

Impact of MR: Improved readiness of TDAQ for cosmics and beam Improved efficiency of detector commissioning Improved tools for detector monitoring More efficient HLT/DAQ operations Improved efficiency of operations due to s/w enhancements

Without MR funds, either or both: Reduced DAQ support for detectors, with delays in detector commissioning Reduced effort on ongoing HLT/DAQ development, with delays in

completing critical software