u.s. banking regulatory update ii - iii . durbin amendment . volcker . cost . operational efficiency...
TRANSCRIPT
U.S. Banking Regulatory Update
February 2013
kpmg.com
Change – or Beware If we do not take change by the hand it will surely take us by the throat.
Winston Churchill
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
2
Make Up of the Industry (2003 to 2012)
Source: FDIC.
$100 million to $1B 4,244 Institutions (58.6%)
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
3
Top 10 banks control > Half of industry’s assets
$0 $5,000 $10,000 $15,000
2012
2006
2003
Combined Assets of All Others Combined Assets of Top 10 Banks
52%
40%
29% 71%
60%
48%
Dollar figures in Trillions Source: SNL, used with permission
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
4
Net improving; Earnings under pressure (2ndQ, 2012)
Source: FDIC – Quarterly Banking Profile, 2nd Q, 2012 – used with permission
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
5
ROA (2ndQ, 2012)
Source: FDIC – Quarterly Banking Profile, 2nd Q, 2012 – used with permission
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
6
“Problem” institutions (2ndQ, 2012)
Source: FDIC – Quarterly Banking Profile, 2nd Q, 2012 – used with permission
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
7
Growth in branches slows; Deposits increase
Source: SNL – Used with permission.
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
8
Preferred banking method – All age groups
Source: ABA – used with permission.
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
9
Focus areas of U.S. Banks
Regulation
Basel II - III
Durbin Amendment
Volcker
Cost
Operational Efficiency
Divesting non-core
businesses
Discretionary spend
Growth
Inorganic growth (e.g.
M&A) New product
/market development
Re-pricing
Change
“The pessimist sees difficulty in every opportunity. The optimist sees the opportunity in every difficulty.” Winston Churchill
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 116381
The “New” U.S. Regulatory Landscape & Impacts
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
12
Dodd-Frank Act Financial Regulatory Reform: Areas of Focus
Federal Bank Supervision
Systemic Risk Systemically important (“SIFI”) designation Financial Stability Oversight Counsel and Office of
Federal Register oversight . Stress testing and “living will” requirements
Financial Stability & Capital Requirements Liquidation authority Bank capital requirements Emergency stabilization
Volcker Rule Proprietary trading restrictions Hedge fund and Private Equity fund restrictions
Regulation of OTC Derivatives Swaps pushout rule Derivatives clearing and reporting requirements
Other Areas of Reform Conflict minerals disclosure requirements Interest on business deposits
Registration of Advisers SEC registration and exams Record keeping and reporting Private client disclosure
Amendments to bank regulations Deposit insurance reforms Office of Thrift Supervision elimination
Consumer Protection & Mortgage Reform Broker/dealer and securities regulation Securitization risk retention Expanded mortgage documentation requirements Consumer Financial Protection Bureau
0 500 1,000 1,500 2,500 Number of Pages
Dodd-Frank (2010): 2,319 pgs
Gramm Leach Bliley (1999): 145 pgs
Sarbanes Oxley (2002): 66 pgs
Glass Steagall (1933): 37 pgs
The Dodd-Frank Wall Street Reform and Consumer Protection Act (“The Dodd-Frank Act”) provided the most sweeping overhaul of the U.S. financial services industry and financial markets since the Great Depression
Areas of Focus
Major Financial Legislation
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
13
The Dodd-Frank Act The “New” U.S. Regulatory Landscape
Regulatory reporting requirements can be expected to change further (increase) as the regulatory structure changes.
Banks Insurance Securities Commodities/
Futures Consumers
New Agencies Changing Merging Unchanged
Federal Reserve Board Office of Thrift Supervision Office of the Comptroller of the Currency Federal Deposit Insurance Corporation Financial Stability Oversight Council Consumer Financial Protection Bureau State Bank Regulators
State Insurance Regulators
Federal Insurance Office
Security and Exchange Commission
Financial Industry Regulatory Authority
State Securities Regulators
Commodity Futures Trading Commission
Consumer Financial Protection Bureau
Graphic updated/adapted from Financial Times article
National Futures Assoc.
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
14
Impact on business and financial strategy
Intensified regulatory pressure & risks
Strategic Risk
Fee revenue from ancillary and core products & services
Increased risk management & compliance costs
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
15
Impact on infrastructure & operations
Product innovation and marketing tactics
Prioritization for operations & technology investment
M&A due diligence
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
16
Impact on behaviors & culture
Reputation Risk
Customer Experience vs. Consumer Compliance
Risks from affiliates and third parties
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
17
Implications and Challenges for US Banks
Implications & Challenges
1. Enhanced Prudential Standards for key Safety & Soundness areas affecting U.S. banks: – Enterprise risk management process and Board Risk Management oversight – Capital adequacy - Basel III; stress-testing (CCAR & CaPR); enhanced capital plans – Liquidity and Funding plans – Legal entities – oversight and rationalization; Resolution & Recovery Planning (“Living Will”) for large
banks – Enterprise Risk Management (*) – Risk Appetite and enhanced Risk Dashboards (*) – Credit exposures and concentrations (e.g., counterparties, CRE, sovereign debt) – Internal Audit process (*) – Transactions with affiliates (Reg W/23a &b) – Information security – Vendor risk management (including off-shoring) – Executive incentive compensation process (* OCC “Strong” principles)
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
18
Implications and Challenges for US Banks (continued)
Implications & Challenges
2. Increased Federal Reserve and OCC supervisory requirements for Enterprise-wide Governance, Risk Reporting, Risk Appetite and Internal Audit functions – Especially for SIFIs – but there is already a “spillover” effect on smaller firms – Expectations for “Strong” Board oversight, Risk Management, Risk Appetite & Internal Audit
processes – “Satisfactory” is no longer acceptable 3. Systemic Risk oversight under the Federal Reserve, the FDIC and the Financial Services
Oversight Council (FSOC) means a wider cross-section of U.S. financial institutions will come under federal scrutiny
4. Consumer Financial Protection Bureau (CFPB) has raised the bar on consumer protection laws, rules and requirements, including reporting
5. Increased regulatory scrutiny of Proprietary Trading and Derivatives Activities 6. Impact of regulatory reform requirements on bank product pricing and profitability, especially:
– Increased capital and liquidity requirements – Loss of revenue due to potential Volcker and derivative push out provisions move activities into non-
bank affiliates or outside the firm entirely – More rigorous consumer protection requirements and associated costs and impact on profitability – Increased regulatory reporting burden
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
19
Basel III Capital Requirements
Basel III Regulatory Capital Ratios • New ratio
• Common Equity Tier 1 • Existing ratios with adjustments to calculations. Certain adjustments phased in
• Tier 1 Capital • Tier 2 Capital • Total Capital • Leverage
Impact on Equity Calculation
• Accumulated Other Comprehensive Income (AOCI) now flows through Tier 1 Capital • Trust Preferred Securities
• Phased out of Tier 1 Capital and into Tier 2 Capital • Other Deductions to be phased in between 2013 and 2018
• Certain Deferred Tax Assets (DTAs), MSR Limits • Gain on sale associated with securitization • Defined pension benefit assets
Sample Impacts on Risk Weighted Assets (RWA) Calculation
• Residential Loans
• 2 Groups – Category 1 (35% - 100% RWA) and Category 2 (100% - 200% RWA) risk weighted based on LTV • Commercial Loans
• New risk weight for High Volatility Commercial Real Estate (HVCRE) (150%) • Investments
• Certain AFS securities receive new risk weighting (0% - 600%) • Off-Balance Sheet and Derivatives
• Unfunded Commitments – Original Maturity of one year or less now subject to risk weighting (20% Credit Conversion Factor (CCF))
• Derivatives – Removal of 50% Risk Weight cap for counterparty risk
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
20
Basel III – Buffer Requirements
Capital Conservation Buffer Counter-cyclical Buffer
Comprised of Tier 1 components
Minimum of 2.5% above the regulatory requirements
Banks build up capital buffers to draw down as losses are incurred
To be monitored and implemented by National Jurisdictions
Enforced by national authority as deemed necessary
Requirements between 0 and 2.5% of risk-weighted assets
Ensures that banking sector capital requirements account for the macro-financial environment
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
21
Basel III – Liquidity Requirements
Liquidity Coverage Ratio:
Stock of high-quality liquid assets/Total net cash outflows over the next 30 calendar days
Minimum requirement = 100%
Ensures that the bank has adequate level of assets to meet liquidity needs over the next 30 days
Net Stable Funding Ratio:
Available amount of stable funding/Required amount of stable funding
Minimum requirement = 100%
Establishes minimum acceptable amount of stable funding based on asset and activity characteristics of an institution over a period of 1 year
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
22
Basel III – Transition
Planned to be implemented from 2013 – 2019
Deadline of transposition into national law: 1st January 2013
BUT: the Agencies announced a delay in the Final Rule pending further review of industry comments
During transition: the Basel Committee and US Regulators are expected to monitor economic effects
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
23
Implementation Timeline for New Regulatory Capital Minimums
Importantly, certain deductions from Common Equity Tier 1 (DTAs from operating losses and credit carryforwards, gain-on-sale associated with securitization, defined pension benefit assets, excess of expected credit loss over allowance for loan and lease losses, and change in fair value arising from the bank’s own creditworthiness) will be deducted in full from Tier 1 Capital on January 1, 2013, and transition to deductions from Common Equity Tier 1 according to the timeline above. – Throughout the transition period, the balance of the deduction that has not yet transitioned to Common Equity Tier 1 will continue to be made to
Tier 1 Capital. Goodwill will be fully deducted from Common Equity Tier 1 beginning January 1, 2013. Deductions for intangible assets other than goodwill and mortgage servicing
rights (“MSRs”) will be deducted from Common Equity Tier 1 according to the transition timeline above for phase-in of Common Equity Tier 1 deductions. Threshold deductions relating to MSRs, certain DTAs arising from temporary differences, and significant investments in unconsolidated financial entities will be phased
in according to the transition timeline above for phase-in of Common Equity Tier 1 deductions.
The US federal banking agencies are proposing to adopt an implementation timeline that is in line with the Basel III framework.
As of January 1, 2013 2014 2015 2016 2017 2018 2019
Common Equity Tier 1 3.500% 4.000% 4.500% 4.500% 4.500% 4.500% 4.500% Capital Conservation Buffer 0.625% 1.250% 1.875% 2.500% Total Common Equity Tier 1 3.500% 4.000% 4.500% 5.125% 5.750% 6.375% 7.000% Tier 1 Capital 4.500% 5.500% 6.000% 6.625% 7.250% 7.875% 8.500% Total Capital 6.500% 7.500% 8.000% 8.625% 9.250% 9.875% 10.500% Phase-In of Certain CET1
Deductions and AOCI Inclusion
0.0% 20.0% 40.0% 60.0% 80.0% 100.0%
Leverage Ratio 3.000% Advanced Approaches Banks Only Reporting Begins 2015 Minimum Effective 2018
Source: Interagency Notice of Proposed Rulemaking, “Regulatory Capital Rules: Regulatory Capital, Implementation of Basel III, Minimum Regulatory Capital Ratios, Capital Adequacy, Transition Provisions, and Prompt Corrective Action,” June 7, 2012.
Phase-in of Minimum Capital Ratios
Phase-in of Capital Conservation Buffer
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
24
What are Banks Doing?
Can be separated into the 3 categories:
1. GSIFI (Global Systemically Financial Institutions) such as BofA, JPM, Citi etc. are responding to the NPRs while alerting shareholders of the additional capital that will be required. JPM calculated Basel III ratios based on the original Basel guidance in its 2011 Annual Report.
2. Medium sized banks are discussing internally what it means for them and those who have implemented Basel II or are a subsidiary of an overseas mandatory Basel II bank so report some Basel II requirements are probably more comfortable with the requirements.
3. Smaller banks are taking steps by completing the Basel 3 regulatory capital calculation spreadsheet and having a discussion with KPMG and other third parties.
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 116381
The “New” U.S. Regulatory Landscape & Impacts
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
26
Capital Planning, CCAR, and the Strategic Planning Process Sustainability is Key to Success
Many banks struggle with converting CCAR submissions from a “project compliance” perspective into the fully integrated business planning cycle.
CCAR can be built into the business planning cycle. To be sustainable, the following items need to be addressed:
Defined governance structure
Documented processes, procedures, and tools
Clear understanding of roles, responsibilities, and staffing needs
Monthly Quarterly Quarterly Monthly Monthly / Quarterly Monthly / Quarterly
Step 1:Develop
Macroeconomic View
Step 2:Review and
Confirm Loss Forecast
Assumptions
Step 3:Generate
Loss Forecasts
Step 4:Review Financial Assumptions & Develop and
Refine Financial Forecast
Step 5:Determine Capital
Levels
Step 6:Obtain Board
Approval
Economic Forecast Committee Meeting
Macro-Economic Forecast
Report
Consumer Loss
Forecasting Assumptions
IRE Loss Forecasting Assumptions
Commercial Loss
Forecasting Assumptions
B/S & NII, & NIE/NIR Assumptions Review
Meeting
Financial Projections
Capital Plan Report
Loss Forecasting Results Analytics
Management Review Meeting
Commercial Loss Forecasting
Assumptions Team Meeting
IRE Loss Forecasting Assumptions Team
Meeting
Consumer Loss Forecasting
Assumptions Team Meeting
A
Loss Forecasting Assumption
Report
B
Board Meeting
Capital Planning Team Leadership Meeting
E
Executive Meeting
Working Group
Loss Forecasts,
ALLL Analysis and
NPLs
C
D
NII Technical Meeting
Loss Forecasting Committee
Capital Planning & Investment Committee
Risk AnalyticsCredit Finance TreasuryFunctional Area : ABCInterdependency:
Step 1:Develop
Macroeconomic View
Step 2:Review and Confirm
Loss Forecast Assumptions
Step 3:Generate Loss
Forecasts
Step 5:Determine
Capital Levels
Step 6:Obtain Board
Approval
Step 4:Review Financial Assumptions &
Develop and Refine Financial Forecast
BOD
BOD Sponsored Committees
Special Purpose Committees
Working Groups
Associates / Lines of Business / Geographies
Strategy and Capital
Planning
Review & confirm Consumer
assumptions with team
Review and confirm IRE assumptions
with team
1a
1c
Review & confirm Commercial
assumptions with team
1b
Macro-Economic
Forecasting Report
A
Review and approve assumptions at Loss
Forecasting Committee Meeting
Generate combined assumption set
Loss Forecasting Assumption
Report
B
2 3
STRATEGIC PLAN Business strategies refreshed New Initiatives identified Capital Plan informs investment priority
BUDGET Derived from Year
1 Base Case of Capital plan
Targets and metrics drilled down from Strategic Plan
CAPITAL PLAN and CCAR Collaborative process
with cross functional participation
Leverage process for both Regulatory Reporting and Strategic Planning
Multi-Year Capital
Plan
Year 2
Year 3
Budget
Business
Other LOBS Consumer
Strategic Plan
Business Consumer
Other LOBs
Risk
Appetite Statement
Risk Appetite Statement Board of Directors set
Risk Appetite Budget should reflect
investment in acceptable business strategies
Business Planning Cycle + CCAR
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
27
“All banking organizations should have the capacity to understand fully their risks and the potential impact of stressful events and circumstances on their financial condition” – SR Letter 12-7
The stress testing framework includes clearly defined objectives, well-designed scenarios, well-documented assumptions, ongoing review, and recommended actions.
General Stress Testing Principles Elements of a Robust Program
1. Includes activities and exercises that are tailored to and sufficiently capture the banking organization’s exposures, activities, and risks.
Includes credit, market, operational, interest-rate, liquidity, country, strategic , and reputational risk.
Aligned to Risk Appetite and part of regular risk identification and monitoring practices.
Applied at various levels in the organization.
2. Employs multiple conceptually sound stress testing activities and approaches.
Uses scenario, sensitivity, enterprise-wide, and reverse stress testing approaches.
Relies on high-quality data. Documents assumptions, and degree of uncertainty.
3. Is forward-looking and flexible. Incorporates changes in the organizations activates, portfolio composition, asset quality, operating environment, business strategy, and other risks that arise over time.
Ensures MIS are capable of incorporating changes.
4. Ensures results are clear, actionable, well supported, and inform decision making.
Includes regular, documented communication to Board, management, and staff. Informs decisions related to strategies, limits, and risk profile.
5. Includes strong governance and effective internal controls.
Requires critical review of key assumptions, uncertainties, and limitations. Integrated into business lines, capital and asset-liability committees, and other
decision-making bodies; not isolated to risk management.
CCAR Framework Elements of a Robust Program
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
28
Issue Description of Issue
Process Sustainability
Incomplete design and installation of suitable controls to fully integrate a sustainable, end-to-end capital planning process in the Company's financial, operational, and enterprise risk management framework, converting from a "project compliance" perspective to a fully integrated business process.
Roles, Responsibilities, and Resources
Lack of documentation (roles and responsibilities) needed to evaluate whether management has the appropriate management oversight, adequate staffing and proper segregation of duties for certain key departments involved in the capital planning process. Lack of quantitative resources to support capital reporting and analysis.
Data Quality and Data Management
Limited historical data availability (e.g. PD, LGD, EAD for specific portfolios) may impact ability to identify trends or back-test models. Data integrity concerns due to data handoffs between technology platforms and limited reporting between systems (e.g.
loan system to GL) makes reconcilement and audit difficult. Changes in certain key assumptions may have a cascading effect in other areas not easily reconcilable across
disparate systems.
Risk Identification and Communication
Limited processes to document whether the key stakeholders in the capital planning process are considering significant business decisions made by the Company that may have an impact on the forecasted information used in the capital planning process (e.g., Risk Appetite Statement, and New Initiatives Review). Senior leadership from certain groups may not be sufficiently involved in the capital planning forecasting process to
determine if the impact of key business decisions are accurately reflected in the forecasted information used in capital planning.
Board Review of Capital Forecast
The bank’s Board and executive management and board may not be provided with sufficient and consistent information to effectively conclude on necessary capital plan revisions, including dividend policy, share repurchases or suspension, capital raising or other funding strategies.
Process and Model Imprecision
Models may not be fully back tested and validated (specifically Risk Rating tools). Imprecision in models or data quality may need to be accounted for in a “buffer” (i.e. an additional amount of capital
reserved for planning imprecision).
Common CCAR/Stress Testing Challenges
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
29
Example Successful Quarterly Capital Planning Overview of Key Steps
Primary Functional Area(s)
Treasury Risk Analytics Credit
Risk Analytics Credit
Finance Treasury
Finance Treasury
Finance
Inputs Macroeconomic Data
Regional Market Data
Macroeconomic Forecast Report
Macroeconomic Forecasting Report
Loss Forecasting Assumptions Report
Macroeconomic Forecasting Report
Loss Forecasts, NPLs, and ALLL Analysis
Financial Projections Economic Capital Output
Results
Capital Plan Report Completed CCAR
Templates
Outputs Macroeconomic Forecast Report
Loss Forecasting Assumptions Report
Loss Forecasts, NPLs, and ALLL Analysis
Financial Projections (BS & Net Interest Income, & Non Interest Expense /Non Interest Revenue)
Capital Plan Report
n/a
Update Frequency
Monthly economic forecasting committee meeting
Quarterly assumption meeting
Quarterly run of all of the loss forecasting models based on the loss forecast assumptions and latest macroeconomic forecasts
Monthly forecast development
Monthly capital determination process
Capital Planning Working Group (monthly)
Capital Planning Investment Committee (quarterly)
Executive review (monthly)
Board review and approval (quarterly)
The example capital planning process below is organized across six key steps that require significant cross functional coordination in order to develop the CCAR submission in a timely manner. The Fed requires each step in the process to be documented and repeatable making it crucial that sustainable processes are in places for each step.
Risk Analytics Credit Finance Treasury Functional Area :
Example Quarterly Capital Planning Process
Monthly Quarterly Quarterly Monthly Monthly / Quarterly Monthly / Quarterly
Step 1: Develop
Macroeconomic View
Step 2: Review and
Confirm Loss Forecast
Assumptions
Step 3: Generate
Loss Forecasts
Step 4: Review Financial Assumptions & Develop and
Refine Financial Forecast
Step 5: Determine Capital
Levels
Step 6: Obtain Board
Approval
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
30
Model Governance and Validation Requirements
The new guidance (OCC 2011-12 and FRB SR Letter 11-07) was issued on April 4, 2011. Its main objective is to broaden the scope of the existing model risk management guidance (i.e. OCC Bulletin 2000-16) to include all key aspects of model risk management. This guidance applies to national banks, bank holding companies, state member banks, and all other institutions for which the OCC or Fed is the primary supervisor. “Previous guidance and other publications issued by the OCC and the Federal Reserve on the use of models pay particular attention to model validation … Rigorous model validation plays a critical role in model risk management; however, sound development, implementation, and use of models are also vital elements.” OCC 2011-12, pp. 2
Model Development
Developer Model Testing
Independent Model Validation
Model Implementation
and Usage
On-going Governance and
Control
The term “model” is broadly referred to as a quantitative approach, method, framework, or system that applies statistical, economic, financial, mathematical, or computational / numerical theories, techniques, and assumptions to process input data into quantitative estimates.
“Models are simplified representations of real-world relationships and dynamics among observed characteristics, values, and events.” By design, they are not perfect and are meant to operate in a very “specific” environment.
Model Cycle
The Capital Planning Process is heavily reliant on modeling assumptions and output.
Certain models may be used elsewhere – consistency and suitability for use must be evaluated.
Use of unvalidated models will conflict with the new guidance and increase risk.
© 2012 KPMG LLP, a Delaware limited liability partnership and the U.S. member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. NDPPS 111930
31
KPMG – CCAR Projection Process
Inputs Loss Data Market Data Position Data Scenarios
Baseline and Stress Projections
Analytical processes Models
Preliminary Projections
Balance Sheet Income Stmt Capital
Sensitivity Analysis
Professional Judgment
Potential On-Top by Model/Process Owner
14A schedules Final Projections are populated in 14A schedules
and capital plan Sensitivity analysis included in capital plan
Return to ‘Inputs’ step
Outcome
Projection Process
Return to ‘Sensitivity Analysis’ step
Challenge/Review Process
Projections Challenged
Includes On-Top and Sensitivity Analysis
Challenge Results
Projection and Sensitivity Analysis Pass
2nd On Top for Projection, Sensitivity Analysis Pass
Projection Pass, Sensitivity Analysis Not Pass
Projection and Sensitivity Analysis Not Pass
Risk Analytics Treasury Financial Planning Functional areas involved in projection process: Lines of Business