usd copley library re-class project kanat manav gba 573 summer 2003
TRANSCRIPT
USD Copley Library USD Copley Library Re-Class ProjectRe-Class Project
Kanat MANAV
GBA 573
Summer 2003
Project OverviewProject Overview
Two different types of cataloging:
1) Dewey decimal classification.
2) Library of congress system.U.S libraries are switching from DDC to
LC.USD Copley Library Decided to change its
cataloging system to LC in January 1997.
Problems With DDCProblems With DDC
Call numbers are too long and too confusing.
Copley library was one of the few libraries that was using DDC.
High costs.
Copley Library’s DatabaseCopley Library’s Database
Library of Congress’s Library of Congress’s DatabaseDatabase
Copley Library Search ScreenCopley Library Search Screen
Expected BenefitsExpected Benefits
Ease of using for Library Patrons.Purchasing books that are already
classified.Purchasing books that are already labeled.NO extra costs.
Expected Costs Expected Costs January 2003 to August 2004January 2003 to August 2004
Estimated Costs for the Re-Class Project - Jan, 2003 to the End
Labor $/hr.Total Hours/week # of People
Total Cost/week
Total Cost
at the End
a) Part-Time / Casual Workers $6.75 30 7 $1,418 $113,400b) Catalogers 14 35 3 $1,470 $117,600c) Graduate Assistants $9 25 5 $1,125 $90,000d) Project Manager $20 25 1 $500 $40,000
Cost Per Label
# of Labels Ordered Total Cost
Printed Labels $0.09 100,000 $9,000
Per Call Number
Approx. Number Total Cost
OCLC Database/Call Number
$0.75 5,000 $3,750
Other Expenses Total Costsa) Book-Ends $20,000b) Carts $5,000c) Labels and Label Protectors $25,000
Estimated Project Total Cost $423,750
Final AnalysisFinal Analysis
The project is moving faster.Earlier finish of the project.Under budget.Cutting Costs.
QUESTIONS?QUESTIONS?