user guide cost & allowables
TRANSCRIPT
![Page 1: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/1.jpg)
USER GUIDE
Cost & Allowables
![Page 2: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/2.jpg)
1 | USER GUIDE - Cost & Al lowab les
Copyright © 2020 by Construction Computer Software (CCS)
This publication is protected by copyright, and permission must be
obtained from the publisher prior to any prohibited reproduction, storage
in a retrieval system, or transmission in any form or by any means,
electronic, mechanical, photocopying, recording, or likewise.
User Guide Reference: 45-CAN-TCH-UG-0001
User Guide Version: 00
User Guide Date: April 2020
Information is correct as per the functionality present in
Candy V 2.01e12.8
![Page 3: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/3.jpg)
2 | USER GUIDE - Cost & Al lowab les
TABLE OF CONTENTS
INTRODUCTION ......................................................................................................... 3
REQUIREMENTS ......................................................................................................... 3
DEFINITIONS ............................................................................................................ 3
GETTING STARTED .................................................................................................... 4
Analyse Allowable To-Date ....................................................................................... 4
Import To-Date Costs .............................................................................................. 5
Cost Adjustments ................................................................................................... 8
Reallocation ......................................................................................................................... 9
Accruals .............................................................................................................................. 9
S/C Liability ......................................................................................................................... 9
Materials ........................................................................................................................... 10
Contras ............................................................................................................................. 10
Residual ............................................................................................................................ 10
Other ................................................................................................................................ 10
Notes ................................................................................................................................ 10
Release the Costs .................................................................................................. 11
Cost Rate ............................................................................................................. 13
Cost Worksheets .................................................................................................... 16
SUBCONTRACT COSTS ............................................................................................. 19
Subcontract Cost Code ........................................................................................... 19
COST AND ALLOWABLES AT COMPLETION ............................................................... 23
NEXT VALUATION SETUP ......................................................................................... 24
BACKUP OR COPY THE JOB ...................................................................................... 24
VALUATION SETUP .................................................................................................. 26
![Page 4: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/4.jpg)
3 | USER GUIDE - Cost & Al lowab les
INTRODUCTION
Cost and Allowables monitors the financial performance of a project. The current Allowable generated by
Candy is compared to the current Cost as captured in an accounting system like BuildSmart®.
While it is essential to understand where a project stands financially at any point of time, it is more
important to have the ability to forecast its financial status at completion. The Cost and Allowables module
provides all the tools necessary to achieve this, thereby assisting the Project Team to maximise the
profitability of a project.
To summarise, Cost and Allowables are used to analyse:
• To-Date Allowables versus To-Date Cost.
• Remaining Allowables versus Remaining Cost.
• At Completion Allowables versus At Completion Cost.
There are a variety of documents and reports available that are customisable to the requirements of the
Project Team.
REQUIREMENTS
To extract the most benefit from Cost and Allowables, users should have a working knowledge of Candy
Estimating and Valuations as this manual refers to the Bill document, Valuations, Worksheets, Resources,
Project Codes and Subcontract Manager.
DEFINITIONS
Below is a list of definitions for the terminology used within this manual:
Allowable To-Date = Actual Quantity x Net Rate
Cost To-Date = Imported Cost To-Date
Variance To-Date = Allowable To-Date - Cost To-Date
Allowable Remaining = Remaining Quantity x Net Rate
Cost Remaining = Remaining Quantity x Cost Rate
Variance Remaining = Allowable Remaining – Cost Remaining
Allowable at Completion = Final Quantity x Net Rate
Cost at Completion = Cost To-Date + Cost Remaining
Variance at Completion = Allowable at Completion – Cost at Completion
![Page 5: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/5.jpg)
4 | USER GUIDE - Cost & Al lowab les
GETTING STARTED
• Step 1: In the Cost & Allowables tab, select the icon.
• Step 2: Select New Document > 1. Cost & Allowable > 1.1 Cost and Allowables by Period.
Analyse Allowable To-Date
To ensure the correct comparison between Cost and Allowables, users should measure the Actual
Quantity on the same date as the Cost Close for accounts.
• Step 1: Select 1.1 Cost and Allowables by Period.
• Step 2: Open the document.
• Step 3: Select Calculate to summarise the latest information.
![Page 6: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/6.jpg)
5 | USER GUIDE - Cost & Al lowab les
The above document shows the To-Date, Remaining and At Completion Allowables for the current
Valuation.
The Task Code column is included, by default, within this document. The BuildSmart® accounting system
contains both the Task Code (Activity Code) and Cost code (Ledger Code) for more comprehensive
financial reporting. If your accounting system does not make use of Task Codes, its column can be
removed from the document (see below).
Import To-Date Costs
The To-Date Costs can get imported from:
• A text file from an accounting software package.
• An Excel file.
• The Candy Material received module.
• BuildSmart® accounting software.
![Page 7: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/7.jpg)
6 | USER GUIDE - Cost & Al lowab les
To import costs from a file, complete the following steps:
• Step 1: In Cost & Allowables > Documents > Cost & Allowables documents.
• Step 2: Select the document 3.1 Cost Import, then click Select.
• Step 3: Select Tools > Import Costs To-Date > Import from File.
• Step 4: Browse for the file to Import.
![Page 8: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/8.jpg)
7 | USER GUIDE - Cost & Al lowab les
To complete the import process, follow the two (2) steps below:
• Step 5: Select from the available column headings that match headings of the imported cost file.
• Step 6: Headings on the import document can be removed by inputting the number of lines that are
to be ignored (see below).
The Code Description does not require matching as Candy already associates the Cost Code
Description with the Cost Code.
![Page 9: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/9.jpg)
8 | USER GUIDE - Cost & Al lowab les
When the import is completed, the imported information must get checked against the Candy information
for differences.
To check this, follow the path and steps below:
• Step 1: Select Tools > Housekeeping > Check Import File
• Step 2: Select the codes to check.
If the imported file is incompatible with the information within Candy, a notification message will
display, it is most likely that the column headings within the imported document remain undefined as
Cost Codes in Candy. These can be deleted using a Control & Delete key combination.
• Step 3: Once the file corrects, repeat Step 1.
A message should display reading Validation successful as below.
Cost Adjustments
After every cost import, further adjustments can be made by the site personnel to reflect the ‘True’ Cost
To-Date. Those adjustments are performed using the imported costs on the same document, ‘3.1 Cost
Import’, and get made under the following headings:
![Page 10: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/10.jpg)
9 | USER GUIDE - Cost & Al lowab les
Reallocation
These are costs that have been misallocated and must be corrected. The total of this column must always
equate to zero.
Accruals
These are known costs uncaptured in the Accounts Ledger.
S/C Liability
This is the difference between the Subcontract Pay Amount and the Due Amount.
To see these amounts take the following step:
• Step 1: Under Subcontract Manager tab > Subcontract Document Manager > 3.1 Subcontract
Summary or select the icon to access the Subcontract Document Manager.
![Page 11: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/11.jpg)
10 | USER GUIDE - Cost & Al lowables
Materials
These are materials that have been pre-purchased but may not be claimable within the current Valuation,
such as materials off-site.
Contras
These are contra charges that have yet to be processed.
Residual
This refers to the pre-purchase of equipment, such as formwork, which must be written off over a period
of time.
Other
This refers to any other cost adjustment.
Notes
These explain the reasons for the cost adjustments.
![Page 12: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/12.jpg)
11 | USER GUIDE - Cost & Al lowables
Release the Costs
Once adjustments have been entered, Costs are releasable for comparison against the Allowable.
To view this, from the document 3.1 Cost Import, take the following steps:
• Step 1: Select Tools > Release Costs for Cost and Allowables.
The Actual Cost column (above) is used within the Cost and Allowables documents and labelled as
To-Date Cost (below).
The To-Date financial position of the Job as the Actual Allowable. This gets compared to the To-Date
costs of the Job and is broken down into the project Task code and Cost Code.
The To-date section displays the current position between Allowable and Cost, whereas the Remaining
section displays the forecast position from current to completion, future costs are influenced by:
• A change in resource rate.
![Page 13: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/13.jpg)
12 | USER GUIDE - Cost & Al lowables
• A change in the production outputs listed within the original worksheet.
• A change in the amount of allowable waste.
• The necessity to employ another subcontractor with rates different to Allowable rates.
A far more accurate financial forecast is achievable by using:
• Cost Rates (future resource rate adjustment).
• Cost Worksheets.
• Subcontract Manager.
![Page 14: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/14.jpg)
13 | USER GUIDE - Cost & Al lowables
Cost Rate
It is inevitable that throughout a project, the prices of resources change. To analyse the effect of these
price changes, the Cost Rate must be entered in the following way:
• Step 1: Under Estimating > Document Manager > Resources > 2.3 Resource List with Cost
Rates.
![Page 15: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/15.jpg)
14 | USER GUIDE - Cost & Al lowables
The Final Rate (Allowable Rate) is displayed and must not be altered, while the Cost Rate defaults to the
same as the Final Rate but can be adjusted as required. Changing the Cost Rate does not change the
Allowables but does change the Forecast Cost to Completion.
In the following example, the Resource Stock Bricks has been updated to reflect the current rates.
![Page 16: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/16.jpg)
15 | USER GUIDE - Cost & Al lowables
Updating the Resource Costs has a significant impact, as seen in the Remaining Variance column as
can be seen from the example below:
Before Updating Resource Cost Rates
Step 1: Select Cost & Allowables tab > Document Manager > 1. Cost & Allowable > 1.1 Cost and Allowables
by Period.
After Updating Resource Cost Rates
![Page 17: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/17.jpg)
16 | USER GUIDE - Cost & Al lowables
Cost Worksheets
Production outputs, waste allowances and other variables may require adjustment to reflect current onsite
conditions.
To make these adjustments, complete the following steps:
• Step 1: Under the Valuations tab, select the icon.
• Step 2: Select New Document > 6. Costs to complete > 6.1 Bill with cost rates for cost w/s
adjustment.
![Page 18: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/18.jpg)
17 | USER GUIDE - Cost & Al lowables
• Step 3: Select the Price Code Worksheet requiring adjustment, then select View > Flip to Cost
Worksheet.
In this exercise, the production output of Excavate to stockpile is increased from 150m3/day to
175m3/day, and the production output of Backfill & Compact is increased 250m3/day to 300m3/day.
Original Cost worksheet – identical to Net worksheet:
![Page 19: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/19.jpg)
18 | USER GUIDE - Cost & Al lowables
Updated Cost worksheet:
Take note how the worksheet title is now ‘Cost Worksheet’ after changing the production output, the Cost
Rate now differs from the original Cost rate.
![Page 20: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/20.jpg)
19 | USER GUIDE - Cost & Al lowables
SUBCONTRACT COSTS
Forecasting the Cost to Completion for subcontract work is simplified when using the Subcontract
Manager.
Cost and Allowables reports against the Subcontract Accounts (Ledger) Code without any change to Cost
or Allowable worksheets, regardless of whether there are multiple subcontractors allocated to one or
more BOQ items. This is possible by identifying the Subcontract Cost Code and the Net Worksheet Cost
Code.
Subcontract Cost Code
The Subcontract Cost Code is the code to which payments for a specific subcontract get allocated. This
code is typically the Ledger Code used by the accounts department to identify the cost against the
subcontractor.
To define Cost Codes, take the following steps:
• Step 1: Under the Cost & Allowables tab > Main > Definitions and Settings.
• Step 2: Select 4.1 Cost Codes (Ledger Code).
![Page 21: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/21.jpg)
20 | USER GUIDE - Cost & Al lowables
The example below shows two subcontractors are executing the same Bill items; namely, Earnie’s
Earthworks, Cost Code 901, and AF Lovall, Cost Code 902.
Once the Cost Codes are defined, complete the following steps;
• Step 1: Under the Subcontract Manager tab > Main > Subcontract Manager. Alternatively, you
may select the icon on the toolbar.
• Step 3: Select the Details tab for Earnie’s Eartworks.
• Step 4: Select the Subcontract Cost Code from the dropdown list, this is the Cost Code that Cost
and Allowables gets reported against; in this example, the Subcontract Cost Code is 901.
![Page 22: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/22.jpg)
21 | USER GUIDE - Cost & Al lowables
• Step 5: Navigate to BLAST1 Blasting.
• Step 6: Select the Details tab for AF Lovall.
• Step 7: Select the Subcontract Cost Code from the dropdown box, the Subcontract Cost Code is
902.
The Net worksheet Cost code is the Cost Code of the subcontract resource in the worksheet of the
current Subcontract Bill.
The example below shows that column 17.3 Resource Cost Code List is added to document
1.1 Subcontract Bill, indicating that the Net Worksheet Cost Code for the items in the Subcontract Bill
is 900.
![Page 23: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/23.jpg)
22 | USER GUIDE - Cost & Al lowables
Follow the procedure to display the Subcontract Costs to Completion for the above Subcontracts, take
the following steps:
• Step 1: Under the Cost and Allowables tab > Document Manager > select 1.1 Cost & Allowable
by Period.
• Step 2: Select Tools > Costs and Allowables Settings.
• Step 3: Select the option Costs for Subcontract Items from Subcontract Manager, under the
heading Advanced Calculation Options, then select OK.
![Page 24: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/24.jpg)
23 | USER GUIDE - Cost & Al lowables
This process dictates specific rules to be followed; these include:
• The Subcontract Due Quantity total must equate to the Actual Quantities listed within the leading
contract Valuation; if there is a difference, a message displays, instructing users to make the
necessary corrections.
• No Subcontract Due Quantity may exceed the Final Awarded Quantity.
• The total of Final Awarded Quantities must equate to Final Bill Quantities - to ensure this, navigate to
‘Subcontract Manager’, select ‘Document Manager’, then ‘Document 2.1 BOQ with Subcontract
Allocation’.
• If the above rules get disobeyed, a message displays instructing users to make the necessary
corrections.
• Where the main contractor and subcontractors undertake work using the same Bill items, internal
variants get created.
COST AND ALLOWABLES AT COMPLETION
The methods described above enable accurate calculation for the Forecast Cost to Completion.
The Allowable at Completion is calculated using the multiplication of Final Quantities and Net Rate, and
the Cost at Completion is the sum of Cost To-Date and Remaining Costs, these determine the financial
performance of the project at completion:
• Open and calculate the document 1.1 Cost and Allowables by Period.
• Remove the Task code to display the document below.
The changes made to Resource Costs, Cost Worksheets and Subcontract Manager reflect in the above
document with the resultant variances to Allowables shown in Remaining Variance and At Completion
Variance.
![Page 25: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/25.jpg)
24 | USER GUIDE - Cost & Al lowables
NEXT VALUATION SETUP
Completing the Cost and Allowables documents is the final stage in the Valuation cycle; therefore, it is
time to configure the next Valuation.
Setting up new Valuations copies all ‘To-Date’ Quantities and Costs into such from the previous
Valuation.
BACKUP OR COPY THE JOB
It is important to backup and copy of each Valuation Job before entering new Valuation’s quantities. To
backup or copy any job, take the following steps:
• Step 1: In the Job Manager, right-click on the Job you wish to backup or copy.
• Step 2: Select Duplicate Job.
• Step 3: Right-click on the duplicated job, then select Rename the Job.
![Page 26: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/26.jpg)
25 | USER GUIDE - Cost & Al lowables
![Page 27: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/27.jpg)
26 | USER GUIDE - Cost & Al lowables
VALUATION SETUP
To set up the next Valuation, take the following steps:
• Step 1: In the Job Manager, select the renamed job.
• Step 2: Under the Valuations tab > Main > Valuation Setup Manager.
• Step 3: Select Tools > Setup next Valuation.
• Step 4: Select Yes to confirm the Valuation backup.
![Page 28: USER GUIDE Cost & Allowables](https://reader034.vdocument.in/reader034/viewer/2022042708/6266786cb6aa8f5b1d57ea83/html5/thumbnails/28.jpg)
27 | USER GUIDE - Cost & Al lowables
Once the next Valuation is confirmed, the current Valuation gets archived, the details of the new Valuation
will display to the user. Select OK.