utility conflict management: a tale of two cities › conferences › tsc18 › ... ·...
TRANSCRIPT
![Page 1: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/1.jpg)
UTILITY CONFLICT MANAGEMENT:A TALE OF TWO CITIESAnna Pulido, San Antonio DistrictBill McCoy, Fort Worth DistrictCesar Quiroga, TTI
October 17, 2018
![Page 2: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/2.jpg)
UCM IMPLEMENTATION UPDATECesar Quiroga, Ph.D., P.E.Texas A&M Transportation Institute (TTI)
![Page 3: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/3.jpg)
Interagency Contract to Support Utility Conflict Mgmt Implementation Two Main Phases:
– Phase 1: One-day Utility Conflict Management (UCM) training course at Metro Districts
• Completed in the summer of 2016
– Phase 2:
• UCM training at all Districts
• UCM implementation at Metro District projects
– Kickoff Meeting: November 14, 2016
– Monitoring and technical support through August 2019
![Page 4: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/4.jpg)
One-Day UCM Training Course (ROW100)
![Page 5: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/5.jpg)
One-Day UCM Training Course (ROW100)Fiscal Year Participants TxDOT Participants Non-TxDOT Participants
FY 2016Total 224 136 88
Average 45 27 18Percentage 61% 39%
FY 2017Total 836 505 331
Average 35 21 14Percentage 60% 40%
FY 2018Total 411 267 144
Average 34 22 12Percentage 65% 35%
OverallTotal 1471 908 563
Average 36 22 14Percentage 62% 38%
![Page 6: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/6.jpg)
One-Day UCM Training Course (ROW100) – Participants by Title
![Page 7: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/7.jpg)
One-Day UCM Training Course (ROW100) – Participants by TitleADMINISTRATIVE ASSISTANT DEPUTY DIRECTOR MAINTENANCE DIV FEDERAL PLAN REVIEWER SPECIAL PROJECTS COORDADV PROJECT DEVELOPMENT
DIRECTOR DEPUTY DISTRICT ENGINEER GENERAL ENGINEERING TECH PLANNER SUMMER ENGINEERING TECH
AREA ENGINEER DESIGN PROJECT COORDINATOR GENERAL TRANSP SPEC PROJECT CONTROLLER SURVEY SPECIALIST
ASSISTANT AREA ENGINEER DESIGN TECHNICIAN GENERAL TRANSP TECH PROJECT DEVELOPMENT MANAGER SURVEY TECHNICIAN
ASSISTANT MAINT SECTION SUPVR DESIGN TRAINEE HVAC SPECIALIST PROJECT MANAGEMENT SPEC SURVEYOR
AUDITOR DIR OF TRANS PLANNG & DEV JOURNEYMAN ELECTICIANPROJECT PORTFOLIO MGMT SEC
DIRECTOR TRAFFIC SYSTEMS SPECIALIST
BRIDGE INSPECTION PROGRAM SPEC DIRECTOR OF CONSTRUCTION LAND SURVEYOR PSE PROCESSING SEC DIRECTORTRANSPORT MAINTENANCE CREW
CHIEF
BUSINESS ANALYST DIRECTOR OF MAINTENANCE LANDSCAPE ARCHITECT PUBLIC TRANSPORTATION SPEC TRANSPORTATION ENGINEER
CEI CONTRACTOR DIRECTOR OF OPERATIONS LOCAL R/W PROJ DELIVERY UTILITY SPEC TRANSPORTATION ENGR SUPVR
CONST RECORDS AUDITORDIRECTOR OF TRANS PLAN &
DEVELOPMENT MAINTENANCE SECTION ASSISTANTR/W PROJ DELIVERY UTILITY
SPEC*LEAD WORKER TRANSPORTATION SPECIALIST
CONSTRUCTION INSPECTOR DIRECTOR OF TRANSPORTATION OPS MAINTENANCE SECTION SUPVR R/W PROJECT DELIVERY MGR TXDOT ATTORNEY
CONSTRUCTION RECORDKEEPER DISTRICT MAINTENANCE ADMIN MAINTENANCE SUPPORT TECH REPROGRAPHIC SERVICES TECH UTILITY
CONSULTANT ENGINEERING ASSISTANT MATERIAL/PROCESS INSPECT RES AND TECH PORTFOLIO SEC MGR UTILITY COORDINATOR
CONTRACT SPECIALIST ENGINEERING INTERN OFFICE TECHNICIAN RIGHT OF WAY AGENT UTILITY COORDINATOR SUPVR
CONTRACTOR ENVIRONMENTAL SPECIALISTOUTDOOR ADVERTISING COMPL
AGENT RIGHT OF WAY SUPERVISORUTILITY PORTFOLIO SECTION
DIRECTOR
DEPUTY DIR RIGHT OF WAY DIVISION FAA CONTRACTOR PERMIT COORDINATOR ROW PROJ DELIVERY DIRECTOR WAREHOUSE COORDINATOR
![Page 8: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/8.jpg)
One-Day UCM Training Course (ROW100) – Hands-On Exercise District highway project:
– 60-90% design complete
– 2-3 miles long
– Documentation used:
• Plan views
• Profiles
• Cross sections
• Drainage plans and profiles
• Existing utility layouts
• Utility test hole sheets
• UCM utility conflict list template
• UCM utility conflict resolution analysis template
![Page 9: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/9.jpg)
Lessons Learned
Positive comments from participants taking the class
– Increased awareness of project delivery process
• Emphasis on early utility coordination and identification of conflicts
– More project managers and designers should take the class
Many practices regarding utility data documentation and conflict management
– Almost 20 sample projects reviewed and used for the afternoon exercise
– Utility investigation timing, scope, quality, and completeness
– Mapping and documentation on project files
– Information conveyed to contractors (both highway and utility)
UCM process is a good model moving forward
– Standardization is critical
Alternative Analysis and Preliminary Plans
Environmental Process
Utility Investigation, Utility Conflict Management, Utility Coordination, Utility Design, and Utility Relocation Management
Property Acquisition and Relocation Assistance
Design and PS&E Assembly
Letting
Construction
Planning Preliminary Design Detailed Design Letting Construction Post Construction
Property Management
Planning linkages
Definition, Selection, Financing, Sched.
Environmental Commitments
Right-of-Way Map Development
Agreements, Scope Update
Construction authorization
Environmental reevaluation
Environmental approval
Right-of-way authorization
Project Management
30%design
60%design
90%design
15-20%design
0%design
2 3 4 5 6 71
Early utility coordination
Utility Investigation
![Page 10: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/10.jpg)
Lessons Learned
Positive comments from participants taking the class
– Increased awareness of project delivery process
• Emphasis on early utility coordination and identification of conflicts
– More project managers and designers should take the class
Many practices regarding utility data documentation and conflict management
– Almost 20 sample projects reviewed and used for the afternoon exercise
– Utility investigation timing, scope, quality, and completeness
– Mapping and documentation on project files
– Information conveyed to contractors (both highway and utility)
UCM process is a good model moving forward
– Standardization is critical
![Page 11: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/11.jpg)
UCM Implementation Monitoring – Selected ProjectsDistrict Project DescriptionAustin FM 971, SH 95 to SH 130 in Travis County Widening lanes, shoulders, nine
bridge culvertsDallas SH 352 from Kearney St to US 80 in
Dallas CountyWidening lanes
Fort Worth
Old: FM 156 in North Tarrant County (3.78 mi)New: US 377 in Hood and Johnson Counties (2.50 mi)
Four-lane urban minor arterial, curb and gutterFour-lane divided highway with bridge over railroad
Houston SH 36 in Fort Bend County (8.06 mi) Hurricane Evacuation Route - widen to 4 lane divided highway
San Antonio
US 281 north of Stone Oak in Bexar County (4.15 mi)
Six-lane expressway with frontage roads
![Page 12: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/12.jpg)
FORT WORTH DISTRICT EXPERIENCEBill McCoyFort Worth District, TxDOT
![Page 13: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/13.jpg)
US 377 Cresson Relief Route Critical need:
– FWWR crossing at grade and switching yard
– High truck traffic volumes
– 20,500 vehicles per day
– Traffic safety/fatal crashes
– Politically charged
New corridor with 4-lane divided highway and bridge over RR tracks
– Hood County: 1.7 miles
– Johnson County: 0.8 miles
– Estimated cost: $61 million
![Page 14: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/14.jpg)
US 377 Cresson Relief Route
![Page 15: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/15.jpg)
US 377 Cresson Relief Route Environmental Clearance FONSI: 09/2017, no issues
Right of way acquisition:
– Some legal descriptions had to be revised several times
– Small number of parcels (11) but some large acreage
– 90% of parcels in Eminent Domain
– Most property owners don’t want project
– Proposed possession by 01/2019
Utilities:
– 13 utility companies and 33 utility conflicts
– 18 utility relocations
– Savings seen from 9 utility conflicts
– Property/utility owner installed pipe in ground
![Page 16: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/16.jpg)
Construction Complete12/2021
Construction Begins01/2019
Proposed Utility Complete 07/2019
Let08/2018
90% plans04/2018
Project Time Line
![Page 17: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/17.jpg)
US 377 Cresson Relief Route Management Plan:
– Staged and phased construction activities
• Staging exhibit added to bid package
– Expected positive outcome
• Fair bidding by all contractors
• Allow utilities time to relocate without affecting construction activities
• Lower risks of potential change order for delay claims
![Page 18: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/18.jpg)
US 377 Cresson Relief Route
![Page 19: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/19.jpg)
Avoid, Minimize, Accommodate (AMA) Approach
Analyze: Created a Utility Conflict Matrix with alternatives
![Page 20: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/20.jpg)
Avoid, Minimize, Accommodate (AMA) ApproachMinimize: 10” and 14” High Pressure Transmission Pipelines
Several pipes were located in the work zone needed to build the bridge
Pipes were not in direct conflict but weight of machinery would cause an issue
Use timber crane mats to distribute the weight over the pipes which eliminated the need to relocate
Saved substantial time and cost verses lowering pipelines
![Page 21: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/21.jpg)
Avoid, Minimize, Accommodate (AMA) ApproachAvoid: 16” High Pressure Transmission Pipeline (PL1)
AT 30% plans it was determined there was not adequate clearance between a pipeline and bridge bent
Design change to avoid the relocation could save project time and costs
Pipe would be located under 40ft of fill
– Not accessible in the future
• Not acceptable to the pipeline owner
Alternative was rejected
If accepted:
– Additional 24 months to schedule
– Cost: $40,000 (design around engineering fees)
![Page 22: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/22.jpg)
Avoid, Minimize, Accommodate (AMA) ApproachAccommodate: 16” high pressure transmission pipeline (PL1-2)
At 90% plans
Rerouted the line to a private easement which increased footage of line
Combined two separate relocations into one relocation.
Able to choose from alternative routings
Accepted:
– Reduced schedule by 38 months
– Saved $1,558,833 in relocation costs
![Page 23: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/23.jpg)
Avoid, Minimize, Accommodate (AMA) ApproachMinimize: Underground telecom
3000 feet of telecom to be relocated, cost: $108,250
Underground copper
Alternative solution:
– Install two repeaters
No need to relocate the line
Saved $95,750
Reduced schedule by 10 months
![Page 24: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/24.jpg)
Avoid, Minimize, Accommodate (AMA) ApproachMinimize: 8” natural gas gathering line
Pipeline located within a 20-foot cut and conflicted with road excavation
Researched records shows pipeline inactive for over 5 years
– Lease agreement relinquishes rights to lease if not active for more than 5 years
– Relocated a PIG launcher to another section of active pipe
– Abandoned line in place
– Saved $90,000
– Reduced schedule by 14 days
![Page 25: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/25.jpg)
Avoid, Minimize, Accommodate (AMA) ApproachMinimize: Overhead electric line (OE2-3)
Electric line located in cut area of project
Line located on property going to Eminent Domain
Main feed to a ranch property
Alternative was to back feed service to an existing line located in private easement
Line is located in Phase I of construction
Accepted:
– Saved $54,500
– Reduced schedule by 1 month
![Page 26: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/26.jpg)
Benefits
Conflict Cost Time (Months)1 $95,750 25 $10,000 07 $54,500 09 $15,400 010 $27,200 0
13A $21,000 2413B $1,558,833 3834 $28,550 140 $90,000 0
Cost and Time Savings for US 377
Total Cost Savings $1,901,233 Average Time Savings (Months) 7.2
![Page 27: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/27.jpg)
Lessons Learned Early involvement during schematic and design phase can have a positive effect on project costs and schedule
Interact more often with rural utility owners to provide guidance on TxDOT regulations (UAR)
Label UCM with size of utility
Value is measured by more than initial monetary costs
Resolution Alternative Process
– Organizes the entire project
– Standardizes techniques of utility coordination processes
– Manages utility conflict data effectively
– Provides opportunities for value engineering
– Real time tracking of all conflicts, alternatives and history (tells the story )
• Cost
• Time
• Alternatives
![Page 28: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/28.jpg)
SAN ANTONIO DISTRICT EXPERIENCEAnna Pulido, P.E.San Antonio District, TxDOT
![Page 29: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/29.jpg)
US 281 Segment 2- 0.8 miles North of Stone Oak to County Line
Scope: Two general purpose lanes and one HOV lane in each direction along with necessary transition and auxiliary lanes
Let Date: July 2018 (moved up from December 2018)
Estimated Construction Start Date: January 2019
ROW/Utilities:
54 parcels acquired (within a year timeframe)
Ongoing utility coordination with SAWS water & sewer, CPS gas, CPS overhead electric, AT&T, Spectrum, GVTC, and Level 3/CenturyLink
Joint bid utilities include SAWS water, SAWS sewer and CPS gas
Estimated Non-joint Bid Utility Clearance Date: December 2019
Estimated Construction Completion Date: Fall/Winter 2022
Let Date: July 2018
NOTE: Highlighted areas are not drawn to scale.
281
10 10
410
35
35
16041604
A
5 milesSan
Antonio
46
1863
Segment 1Segment 2
Construction Cost: $179M
![Page 30: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/30.jpg)
US 281 Segment 2- 0.8 miles North of Stone Oak to County Line
Project Timeline
![Page 31: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/31.jpg)
US 281 Segment 2- 0.8 miles North of Stone Oak to County Line
Environmental Challenges:
– Pending Environmental Clearance
– Overhead electric work was included in TxDOT Biological Opinion
ROW Acquisition Challenges:
– Property Owners not wanting to vacate
Vegetation Clearing: 100% Complete
– Close coordination with our ROW team
Overhead electric power pole relocation:
– Approximately 400 poles will be relocated
– Construction started on 2/28/18
– Estimated Completion (including existing pole removal): 12/2019
– Telecoms attached to poles: Level 3/Centurylink, Spectrum, AT&T, and GVTC
![Page 32: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/32.jpg)
US 281 Segment 2- 0.8 miles North of Stone Oak to County Line
![Page 33: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/33.jpg)
Avoid, Minimize, Accommodate (AMA) Approach
Avoid:
– Lowered the profile of highway (SBFR) 5 feet to avoid transmission line adjustment
• Cost Savings: ~$3M (Utility Cost)
• Time Savings: ~2 years of design and construction time (would not have met letting date)
![Page 34: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/34.jpg)
Avoid, Minimize, Accommodate (AMA) Approach
Avoid/Minimize:
– Shifted frontage road about 5 feet closer to the main lanes
• Avoided ~1 mile of transmission 24” water line from being adjusted; only manholes to be adjusted within sidewalk
• Cost Savings: ~$1.6M (Utility Cost)
• Time Savings: ~3 months of construction time (joint bid) and ~1 month in reduced design timeline
![Page 35: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/35.jpg)
Avoid, Minimize, Accommodate (AMA) Approach
Accommodate:
– Assigned utility relocation corridors
– Vegetation Clearing for Overhead Utilities
• Utility Cost Savings: $1.8M
• Allowed TxDOT control of schedule
![Page 36: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/36.jpg)
US 281 Segment 2- 0.8 miles North of Stone Oak to County Line
![Page 37: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/37.jpg)
US 281 Segment 2- 0.8 miles North of Stone Oak to County Line
![Page 38: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/38.jpg)
US 281 Segment 2- 0.8 miles North of Stone Oak to County Line
![Page 39: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/39.jpg)
Districtwide Implemented Changes
Utility Coordination and SUE was occurring too late in the project cycle (30% or 60% PS&E)
Utilities relied on TxDOT contractor to clear ROW
Utility Owners would not begin their design until all conflicts were identified to avoid redesign
Issue
Major utility relocation could take several years to be completed
Some Utility Owners would not begin their design until ROW was acquired due to fear of canceling project
TxDOT designers and project manager will do their best to avoid, minimize, and accommodate utilities
Include Utility Coordination and SUE in Schematic Contracts
TxDOT will reimburse utility if projects are “shelved” or cancelled
1) Design includes underground features (drainage, walls, etc.) within the 30% PS&E plans to identify conflict early2) TxDOT will reimburse utility for major design changes through Master Utility Agreement
TxDOT will clear ROW far in advance of construction project using ROW division contract or bidding
March 14, 2018
Implemented Change
![Page 40: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/40.jpg)
Benefits
– Utility Cost Savings within the last 2 years:
• ~$4.6M on US281 Phase 2
• ~$2.4M on other projects districtwide
– Building Relationships: Priceless!
– Time Savings (design and construction):
• ~2.5 years on US281 Phase 2
• ~1.5 years on other projects districtwide
Redesigning around Utilities pays off!
![Page 41: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/41.jpg)
Benefits
![Page 42: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/42.jpg)
11/9/2018 42
![Page 43: UTILITY CONFLICT MANAGEMENT: A TALE OF TWO CITIES › conferences › tsc18 › ... · 2018-11-09 · – 60-90% design complete – 2-3 miles long – Documentation used: • Plan](https://reader033.vdocument.in/reader033/viewer/2022060412/5f10e8bd88e9d216d4403e14/html5/thumbnails/43.jpg)
Contact Information
ANNA PULIDOUTILITY MANAGER, SAN ANTONIO DISTRICT, TXDOTP: (210) 615-5989 E: [email protected]
BILL MCCOYR/W PROJECT DELIVERY MANAGER, FORTH WORTH DISTRICTALTERNATIVE PROJECT DELIVERYP: (817) 370-6950 E: [email protected]
CESAR QUIROGASENIOR RESEARCH ENGINEER, TTIP: (210) 321-1229 E: [email protected]