v ramakrishnav ramakrishna, subir sen,...indian power system - present installed capacity: 147gw...
TRANSCRIPT
V Ramakrishna Central Electricit A thoritV Ramakrishna, Central Electricity Authority
Subir Sen, Power Grid Corpn. of India Ltd.
Presentation Flow
Overview of Indian Power System
F t d d l i Future demand-supply scenario
Consideration for high capacity 1200kV transmission corridor Consideration for high capacity 1200kV transmission corridordevelopment
Broad 1200kV AC technical parameters
1200kV UHVAC Test Station
Summary Summary
Indian Power System - Present
Installed Capacity: 147GW
Peak Demand : 109 GW
Transmission Grid Comprises: 765kV Lines - 1600 ckt. km
400kV Li 76 000 kt kNER
NR
400kV Lines - 76,000 ckt. km
220/132kV Lines - 115,000 ckt. km
HVDC bipoles - 3 nos.ER
HVDC back-to-back - 7 nos.
FSC – 18 nos.
TCSC – 6 nos.
WR
NER, ER, NR & WR operating as single grid of 100 GW
SR Grid – 40 GWSR AN
DAM
NIC
O
LAKSHA
Inter-regional capacity : 18,700 MW
MAN
&
OBAR
ADWEEP
National Grid - At Present
Eastern RegionNorthern
Region
North-easternRegion1260 MW g
6330 MW 1260 MW
2120 MW
Western Region
2990MW2990MW
3630 MW 1720 MW
Southern Region
Inter-regional Capacity - 18,700MW (incl. 132kV links)
NATIONAL GRID-EXISTINGInter-regional capacity : 18,700MW
NR
Inter-Regional Capacity-18700 MW
,
KOTA
AURAIYA
AGRA
GORAKHPUR
BALIA
PURISAHU
SALAKATI
MUZAFFARPUR
PATNABARH
BIHARSHARIFF
BIRPARA NERBONGAIGAON
M'SARAI/A'BAD
UJJAIN
WR
GWALIOR
RAIPUR
VINDHYACHALKORBA
MALANPUR
PURI500MW
ERBUDHIPADAR
ROURKELATALCHER
DEHRI
SASARAMMALDA
RANCHISIPAT
BALIMELA
KOLHAPUR
PONDA
CHANDRAPUR
U SILERU
1000MW
GAZUWAKA
MW1000
SRNAGJHARI
BELGAUMU.SILERU
National Grid by 2012
EasternNorthern N h
6000 MW
Eastern Region
Northern Region North-
easternRegion12130 MW 2860 MW
Western
4220 MW
Region6490 MW
3630 MW2720 MW
Southern Region
3630 MW 2720 MW
Inter-regional Capacity - 38,700MW (incl. 132kV links)
National Grid by 2012
N R
Inter-regional capacity : 38,700 MW
G O R A K H P U R
A G R A
K A N K R O LIR A PP
K O TA
A U R A IY A
FA TE H P U R
N R
B IR P A R AS IL IG U R I
B A LIAM U ZA FFA R P U R
P A TN AB A R H
N ERB O N G A IG A O N
S A LA K A TI
V IN D H Y A C H A L
W R P O O LIN GG W A LIO RU JJA IN
N A G D AZE R D A
M A LA N P U R
K O TA
ERM A LD A
S IL IG U R I
N A G A RP U R I
S IP A T
K O R B A
R O U R K ELAR A N C H I
D E H R I
S A H U
B A R HB 'S H A R IFFN A B I
B O N G A IG A O N
500M W
B U D H IP A D A R
S A S A R A MG A YA
C H A N D R A P U R
K O LH A P U R
P O N D A1000M W
M W1000
G A ZU W A K A
R A IP U RW RB A LIM ELA
R O U R K ELATA LC H E R
1000M W
U .S ILER U
N A G JH A R I
SR
B E LG A U M
G A ZU W A K A
N A R E N D R A
National Grid – A Continuing Process
Growth of Installed Capacity/Demand700
600Insta lled C apac ity
400
500D em and(P eak)In te r R eg iona l C apac ity
300
400
GW
200
0
100
2007 2012 2022Y ear
Energy Resource Map
• Hydro potential in NERand upper part of NR
• Coal reserves mainly in ER
• Ensure optimal utilisation of resources – strong National Grid is in placeNational Grid is in place and capacity is being enhanced continuously
Likely Capacity addition in next 15 years Peak Demand : 450GW Peak Demand : 450GW
Inst. Capacity : 600GW
Additional capacity addition of about 390GW would be required
Distributed 50 Hydro 80
Coastal, 90
Coal, 80
Nuclear, 90Load centre based, 90
Future Demand-Supply Scenario
Region Installed Capacity
(GW)
Availability (GW)
Peak Demand
(GW)
Surplus(+) /Deficit (-)
GW(GW) (GW) GWNorthern 145 110 140 (-) 30
Western 135 100 130 ( ) 30Western 135 100 130 (- ) 30
Southern 135 100 130 (- ) 30
Eastern 105 80 40 (+) 40
North-eastern
80 60 10 (+) 50
Total 600 450 450Total 600 450 450
Likely power transfer requirement between various regions in next 15 years
North-eastern Region
Northern Region27 GW
18 GW
IC = 145 GW IC = 80 GW
10,000MW
Despatch = 110 GWDemand = 140 GW
Deficit = 30 GWEastern Region
Despatch = 60 GWDemand = 10 GWSurplus = 50 GW
20 GW
,
23 GWWestern Region
IC = 135 GWDespatch = 100 GW
IC = 106 GWDespatch = 80 GWDemand = 40 GWSurplus = 40 GW ALL INDIA
IC = 600 GWD d 450 GW
15 GW15 GW
Demand = 130 GWDeficit = 30 GW
Demand = 450 GW
Southern RegionIC = 135 GW
Despatch = 100 GWDemand = 130 GW
Deficit = 30,GW
Power Transfer Requirement by 2014-153,000MWJharkhand-8000MW
NERNR12,500MW
ER3,000MW
4,000MWIC = 74,000MW
Demand = 56,500MW IC = 6,300MW
1,000MW
Deficit = -19,000MW Demand = 3,000MWSurplus = 2,500MW
IC = 63,000MWDemand = 23,000MWSurplus = 18 000MW
5,000MW
WR
1,000MW
17,000MW
IC = 85 000MW
Surplus = 18,000MW
Monet:900MWJindal:1320MW
Sterlite:2400MW
1 000MW
WR
2 500MW10,000MW
IC = 85,000MWDemand = 55,000MW
Deficit = -6,000MW
Malaxmi:956MWVisa:500 MWKVK:560MWLanco:693MW
Orissa-7330MW
1,000MW1,000MW
SR
Existing/Planned
Being Planned
2,500MW1,000MW
IC = 68,000MWDemand = 49 000MW
4,000MWChattishgarh:8000MW
S Demand = 49,000MWSurplus = 6,000MW
A.P. : 12000MWTamil Nadu : 7000MW
Consideration for Future Transmission Development
1. Requirement of Bulk power transfer over Long Distances from resources rich area/region to load centersg
2. ROW constraints, limited Transmission corridors available
3. High Short Circuit Levels
4. Variation and regulation in Power Flow
Power Flow Pattern
1. Variation in generation High hydro in monsoon and summer In winter only during peak hours Power flow variations due to commercial/operational
reasons
2. Variation in load demand Daily basis (peak and off-peak) Seasonal variations
Due to above, each transmission corridor has varied fl tt i f hi h t l l dipower flow pattern ranging from high to low loading, results into wide variation in voltages
Present Technologies & its Limitations
400 kV Twin Moose - upto 600-700MW
400 kV Quad Moose - Upto 1200-1500MW 400 kV Quad Moose Upto 1200 1500MW
765 kV Line - upto 2000/3000 MW
• Sipat – Seoni first 765 kV line operated at rated voltage
HVDC bipole - + 500 kV upto 2000-2500MW
Need
1. Development of hybrid transmission system for maintaining critical parameters as well as regulations of power flow
2. Increase in MW flow per metre of ROW
3. Controlling high Short Circuit Levels
Transmission System through Narrow Area
Eastern Region/ Western Region/
North-eastern Region
Requirement of Power Flow between NER & ER/WR/NR: 50 GW
Southern RegionRegion
50 GW
Requirement of Power Flow between NER & ER/WR/NR: 50 GWRequired Transmission Capacity : 57.5 GW (15% redundancy) Existing & planned Capacity : 9.5 GWAdditional Trans. Capacity to be planned : 48 GW
Options : 1. +800kV HVDC : 8nos.2. +800kV HVDC : 5nos.; 765kV EHVAC : 6nos.3. +800kV HVDC : 4nos.; 1200kV UHVAC : 2nos.
Selection of Next Level Transmission Voltage i.e. 1200kV UHVAC in view of : Loading lines upto Thermal Capacity(10000 MW) compared to SIL(6000 MW) Loading lines upto Thermal Capacity(10000 MW) compared to SIL(6000 MW) Saving Right of Way
EVACUATION OF 50,000MW THROUGH
Transmission System through Narrow Area,
CHICKEN NECK AREAFrom
NER1200KV UHVAC
MW
CHICKEN NECK AREA
MynmarBhutan
SikkimNER
1200KV UHVAC120
5000 MW
5000 MW
W800KV HVDC
locationsTo differentMynma
800KV HVDC
6000 MW
800KV HVDC
6000 MW
6000 MW800KV
locin
WesternNorthern,
800KV HVDC
6000 MW
800KV HVDC
6000 MW
6000
Upto 2012
Eastern
Wand
Region
400KV EHVAC
400KV EHVAC
2000 MW
2000 MW
1200kV AC Transmission System – Considerations
In Chhattisgarh State, projects with total capacity of about35,000 MW have been planned to be commissionedprogressively in the next 4-5 years.progressively in the next 4 5 years.
Power from these projects is to be transferred to bulk loadcentres in the Western and Northern Regions.
T f ili h f h f To facilitate exchange of such quantum of power,strengthening of East-West and East-North transmissioncorridors in WR is required.q
Further, it has been observed that growth of interconnection atk / k l l ld l i i i h i i400kV/765kV level would result into increase in short circuit
level at various EHV substations beyond the limit (40kA)
1200kV AC Transmission System – A Case Study
Considering quantum of power transfer on long-term as well as toaddress high short circuit level, a high capacity 1200kV transmissioncorridor i.e, Raipur-Wardha and Wardha- Aurangabad is proposedcorridor i.e, Raipur Wardha and Wardha Aurangabad is proposed
Projects are being developed in a phased manner with less powertransfer requirement initially, it is proposed that this high capacityEast-West transmission corridor shall be operated initially at 400kVlevellevel.Accordingly, with suitable design 1200kV S/c line is initiallyproposed to be operated as a 400kV (quad) D/c line so that systemredundancy can be maintained.Subsequently, with the increase in power transfer requirementthrough this corridor line shall be operated at 1200kV levelthrough this corridor, line shall be operated at 1200kV level
Proposed 1200kV AC Transmission Corridor
Line Parameters
Line parameters of 1200kV/765kV/400kV Transmission System
1200 kV 765kV 400kV
Nominal Voltage (kV) 1150 765 400
Highest voltage(kV) 1200 800 420
Resistance (pu/km) 4.338 x10-7 1.951x10-6 1.862x10-5
Reactance (pu/km) 1.772 x10-5 4.475x10-5 2.075x10-4
Susceptance (pu/km) 6.447 x10-2 2.4x10-2 5.55x10-3
Surge Impedance Loading (MW)
6030 2315 515
Base kV :1200kV/765kV/400kV; Base MVA :100 MVA
Large Variation of Reactive MVAR
R f 1200kV AC li i 1/3 d f 765kVReactance of 1200kV AC line is 1/3rd of 765kV system
Susceptance (charging capacitance) is 2½ times more of765kV line
Wide difference in the electrical parameters shall lead to theproblems of reactive power (VAR) balance
Huge Reactive Power Generation by 1200kV line about 6MVAR/km
These uncompensated lines shall generate huge capacitivecharging reactive power for which static reactive compensationdevices like shunt reactor, bus reactor of adequate size is to beprovided
1200kV Wardha – Aurangabad line reactive power characteristic
3000
1000
2000
AR
)
0
1000
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 5500 6000 6500 7000 7500 8000Flow
( M
VA
-1000
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 5500 6000 6500 7000 7500 8000
Power Flow (MW)
Rec
ativ
e
-3000
-2000
Reactive Power Management of 1200kV LinesReactive Power Management of 1200kV Lines
Maintaining constant/optimum level of power flow on the 1200kV AC system under different operating conditionsT l h h 1200kV AC l d f To control power through 1200kV AC system a layered system of 1200kV AC transmission corridor along with 800kV, 6000MW HVDC system shall be developedHVDC system shall be developed
Control and regulation mechanisms Exchange of power between 1200kV AC system and lower g p y
level network (765kV/400kV) through HVDC back-to back links at strategic locations
Control of power flow on the 800kV HVDC bipole lines
Dynamic Reactive Power Management through Series and Shunt Dynamic Reactive Power Management through Series and Shunt Compensation
Maintaining Uniform power flow through 1200kV System
Layered high capacity transmission network with control & regulation features
1200kV UHVAC System
800kV HVDC800kV HVDC
765kV EHVAC System
400kV EHVAC System
500kV HVDC500kV HVDC
~220kV/132kV SYSTEM
Increase in Short Circuit Level
Indian system is designed for max. short circuit level – 40kA
After 30 years of operation it is expected that fault level at After 30 years of operation, it is expected that fault level atvarious S/s shall increase beyond its limit in next 4-5 years
Most of these s/s are either major pooling stations or highcapacity trans. Interconnections with major generationp y j gcomplex/substations
Development of 1200kV transmission corridors shall facilitatein controlling high short circuit level, although other mitigatingmeasures are also being taken
Other 1200kV ParametersBased on the preliminary studies, broad parameters determined as under :
SlNo.
Description/Parameters Unit Value
Based on the preliminary studies, broad parameters determined as under :
1 System Nominal Operating parameters
(i) Phase – Phase kV 1150(ii) Frequency Hz 50
(iii) Number of phases Nos 32 System Maximum Voltage (Ph-Ph) kV 1200y g ( )3 System Insulation Levels
(i) Full wave impulse withstand voltage kV 2400(i) Full wave impulse withstand voltage(1.2/50 microsec.)
kV 2400
(ii) Switching impulse withstand voltage(250/2500 micro sec.) dry and wet
kV 1800( ) y
(iii) One minute power frequency dry and wetwithstand voltage (rms)
1200
Other 1200kV Parameters …contd
Sl No Description/Parameters Unit ValueSl No. Description/Parameters Unit Value
4 Short Circuit Level kA 505 Corona extinction voltage kV 762g6 Max. radio interference voltage for
frequency between 0.5 MHz and 2 MHzat 762 kV rms for 1200kV system
Micro V 1000
7 Creepage Distance mm/kV 25 i.e. (Total 30000 for1200kV system).
8 Bus Bars/Equipment Interconnections8 Bus Bars/Equipment Interconnections
(i) Tubular Bus/Connections Twin Al. 4” IPS tubes with450mm/550mm spacing.p g
(ii) Height m 18.00(iii) Strung Bus/Equipment Connections Octa Bundle Bersimis with(iii) Strung Bus/Equipment Connections
Conductor BundleOcta Bundle Bersimis with450 mm sub conductorspacing
Other 1200kV Parameters …contd
SlNo.
Description/Parameters Unit Value
9 Clearances
(i) Minimum Phase to Phase Clearance m 12.30
(ii) Minimum Phase to Earth Clearance m 8.30
(iii) Sectional clearances m 10.5
(iv) Phase to Phase distance (Pie Structure) m 27 00(iv) Phase to Phase distance (Pie Structure) m 27.00
10 System neutral earthing - Effectivelyearthed
Field Studies on 1200kV AC System
POWERGRID has undertaken various studies and tests todetermine the configuration of its 1200kV transmission lines,liklike
corona cage studies
air gap insulation studies
tests for voltage distribution on the insulator string
l t t di t t li f t f AN RIV & long term studies on test line for measurement of AN, RIV &
voltage gradient measurement at ground level
Establishment of 1200 kV AC Test Station
To develop 1200kV technology indigenously, POWERGRID
in collaboration with manufacturers establishing a 1200kVg
AC Test Station at Bina
This endeavour shall benefit the Indian Power sector and
manufacturers for
• Optimisation of transmission cost
• Ease in O&M• Ease in O&M
1200KV UHVAC Test Station
A 3 phase 1200kV Test Lines (S/C & D/C) of about 1 kmlength are being constructed. Salient features:
Variable Phase to Phase Spacings
Variable Ground Clearance
Upto 12 sub-conductor bundle
V i bl B dl di t Variable Bundle diameter
A 1200kV 3-phase test bay is being constructed to charge these A 1200kV 3-phase test bay is being constructed to charge theseTest Lines
1200KV UHVAC Test Station
Test station shall be fully equipped with testing instrumentfor field testingfor field testing
Extensive developmental tests shall be conducted on the testpline as well as on s/s equipments installed in the Test Bayjointly by Utilities, Manufacturer & Research Institute
Summary
To meet growing power transfer requirement and environmentalfriendly development, 1200kV AC system along with 800kV,6000MW HVDC system has been planned in the Indian Power6000MW HVDC system has been planned in the Indian PowerSystem
Reactive power management for 1200kV AC system is an Reactive power management for 1200kV AC system is animportant aspect which require detail analysis for suitable staticand dynamic reactive compensationand dynamic reactive compensation
Results of some of preliminary studies discussed
More studies and field tests are under process to finalise all the More studies and field tests are under process to finalise all thecritical electrical parameters
Establishment of a 1200kV AC Test Station at Bina is under Establishment of a 1200kV AC Test Station at Bina is underprogress
Thank YouTh k YThank YouThank You