va1 lsc 00100 qa m8 tpd 0006 (steel structure fabrication procedure) rev.1
DESCRIPTION
Steel structure fabricationTRANSCRIPT
-
DOCUMENT SUBMISSION STATUS: FC
1 30/03/11 ISSUED FOR CONSTRUCTION T.V.CUONG D.V.HIEU P.N.QUANG 0 11/03/11 ISSUED FOR CONSTRUCTION T.V.CUONG D.V.HIEU N.H.QUAN E 26/01/11 ISSUED FOR APPROVAL T.V.CUONG N.V.BIEN P.N.QUANG D 10/01/11 ISSUED FOR APPROVAL C 18/11/10 ISSUED FOR APPROVAL B 29/10/10 ISSUED FOR APPROVAL
REV DATE DESCRIPTION PREP. CHKD APPN
OWNER
OWNERS CONSULTANT
EPC CONTRACTOR
EPC CONTRACTORS CONSULTANT
PROJECT TITLE
VUNG ANG 1 THERMAL POWER PLANT 2 x 600MW PACKAGE: M8
CONTRACT No. 222010/ LILAMA-LISEMCO
DRAWING TITLE:
steel structure FABRICATION PROCEDURE
SUB-CONTRACTOR
HAIPHONG EQUIPMENT MANUFACTURE AND SHIPBUILDING CO.LTD, (LISEMCO)
FUNCTION NAME SIGN DATE
PREPARED TO VIET CUONG 30/03/11
CHECKED DAM VAN HIEU 30/03/11
APPROVED PHAM NGOC QUANG 30/03/11
DOCUMENT No.VA1-LSC-00100-QA-M8-TPD-0006
SCALE REV. 1
POYRY ENERGY LTD VIETNAM OIL AND GAS GROUP (PVN)
VIETNAM MACHINERY INSTALLATION CORPORATION (LILAMA)
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 1/19
Steel structure Fabrication Procedure
Steel structure Fabrication Procedure
project Vung Ang1 Thermal Power Plant Item COAL HANDLING SYSTEM M8 location Ky Loi commune - Ky Anh District-Ha Tinh province
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 2/19
Steel structure Fabrication Procedure
Index
No Title Page
1 Chapter 1: General Introduction. 2
2 Chapter 2: Fabrication procedure. 5
3 Chapter 3: Fabrication method. 6
Chapter 1: General Introduction I. General Introduction
1. Executing Organization Chart (As shown in page 4).
Hai phong Equipment Manufacture and Shipbuilding CO., LTD
a. Responsibilities and rights
Hai Phong Equipment Manufacture and Shipbuilding CO., LTD is a member
company belonging to Vietnam Machinery Installation Corporation (LILAMA).
With its big site plan (8ha), modern equipment, and the teams of experienced
engineer and equipped with knowledge and new executing technologies, a large
number of workers as well as skillful workers, Hai phong Equipment
Manufacture and Shipbuilding CO., LTD is responsible for providing materials
and installation of equipment for Vung Ang 1 thermal power plant 2x600 MW-
Coal handling plant M-lot 2
All steel structure will be fabricated in factory of Lisemco in Hai Phong to
ensure quality, error and convenience for installation process of steel structure.
The whole process of structural steel fabrication, company will carry out by
itself equipment and staff member.
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 3/19
Steel structure Fabrication Procedure
b. The director of project
Full name: Nguyen Hong Quan
Position: Project Director
Tel : 031-3522496
Fax : 031-3850120.
E-mail : [email protected]
2. Inspection unit- quality control
Inspection unit quality control belonging to quality control Department which
is an independent organization with in manufacturing units operating under the
leaderships of the parent company, is responsible for quality control, checking to
ensure the steps of manufacturing technology and installation implemented
seriously for quality assurance of construction.
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 4/19
Steel structure Fabrication Procedure
ORGANIZATION CHART FOR LOT-M8VUNG ANG 1.THERMALPOWER PLANT PROJECT
LILAMA PMB
PROJECT MANAGERMr.NGUYEN HONG QUAN
E-mail: [email protected]@vnn.vn
DEPUTY PROJECT MANAGER& SITE MANAGERMr. PHAM NGOC QUANG
E-mail: [email protected]
PROJECT COORDINATORMr. TO VIET CUONGMobi: 01696815187
E-mail: [email protected]
QC/QA PRJ. MANAGEMENTMr. NGUYEN QUANG VINH
SAFETY&SE MANAGEMENTMr. PHAM VAN TUYEN
Mobi: 0934692591E-mail: [email protected]
MANUFACTURING MANAGERMr. NGUYEN VAN BIEN
Mobi: 0989126635E-mail: [email protected]
LISEMCO ltd,.GENERAL DIRECTOR
Mr. TRAN VIET KHANHEmail: [email protected]
Date of isuue: Otc 12th, 2010
MECHANIC AND WELDER TEAM - 25
WORK-SHOP No1Mr NGUYEN VAN DOANH
WORK-SHOP No2Mr. NGUYEN VAN HUNG
MECHANIC AND WELDER TEAM - 25
PAINTING PACKING & SHIPPMENT
Mr.DOANVAN HA
PAINTINGTEAM-01
PEOPLE 12
WORK SHOP SUPERVISORENGINEERS
OFFICE MANAGERMs.TRUONG THI HUONGMs.HO THI KHANH HOA
QC/QA PRJ. MANAGERMr. VU VAN QUANGMr MAI HUY CUONGMr.VU DUC THANH
RECEIVING EQUIPMENTAND HAND MANAGER
Mr. NGUYEN DINH QUYNH
TECHNICAL MANAGEMENTMr. DO XUAN DUNGMobi: 0982592029
MATERIALS MANAGEMENTMr. BUI DUC THIETMobi: 0904828298
SAFETY&SECURITY MANAGERMr. PHAN VAN HUNGMs: NGUYEN THI LAM
STEEL STRUCTURETEAM 02PEOPLE 35
STEEL STRUCTURETEAM 02PEOPLE 35
PACKING & SHIPPMENTTEAM -01
PEOPLE 06
STEEL STRUCTURE+MECHANIC
TEAM-02PEPLE 30
ELECTRICIAN+INSULATING+
COMMISSONINGTEAM 01PEPLE 19
PAINTERTEAM - 01PEPLE 8
WELDERTEAM - 01PEPLE 15
Inspection unit- quality control has rights of suspending activities which not
comply with procedures , and has risk of bad influence on quality manufactured
products as well as installation leading bad effects on construction quality.
Inspection shall followed he details in lines with the approved ITP which are
completed by LILAMA.
AdminPolygon
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 5/19
Steel structure Fabrication Procedure
3. Reference:
- Specification of the project.
- FLS General Workshop instructions.
- Document No. VA1-LI-00100-M-G1-ITP-0002 INSPECTION AND TEST
PLAN FOR STEEL STRUCTURE SHOP FABRICATION
- Document No. VA1-LI-00100-QA-G1-ITP-0001 INSPECTION AND TEST
PLAN FOR PAINTING
- Standard: DIN.
4. Shop, fabrication teams
Fabrication teams are responsible for executing construction in accordance with
design, quality assurance and work progress and directly carry out at shop in
lisemco.
In case of unexpected problems in construction process exceeds the capacity of
fabrication units. They can request related parts supporting technology,
eqiupment, manpower. All the requirements of fabrication groups must be
presented in writen form system of Lisemco (in case the customers do not have
special requiremetns). These requirements are given Economy-Technology
Department, Lisemco. Economy-Technology Department must have answer in
writen form within 24 hours.
II. Objects, scopes and references.
1. Objects The process of structural steel fabrication is to give a manufacturing scientific
plan, strict inspection system, ensuring quality to meet the quality control system
ISO 9001 : 2000 which company Lisemco is applying, also satifies the
customers requirements about product quality and construction progress.
2. Application scope
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 6/19
Steel structure Fabrication Procedure
This process is applied to fabrication equipment and manufacturing of steel
structure.
3. References
Shop drawings, related technical documents and standards.
The technical standards are given by Owner.
4. Fabrication chart and inspection
o Content of Work
Implementation unit Inspection criteria Evaluation criteria
Inspection tools Report form
-Check inputmaterials.
-Executing technology
-Material officer. -Quality control - Supervisor party A
- Original - Number - Dimension - Visual inspection
- Certificate oManufacturer. - Accroding toorder
- Tape-measure, caliper
- No wrapping,rust, blistery.
- By visual.
- Certificates - Comparing orders
- Marking andcutting
- Workers
-Inspections - Executing technology - Quality control
- Dimension, beveledangel.
- Design drawing.
- External insepction.
- Tape-measure.
-Straightening -Detailed assembly -Inspection
- Workers -Executing technology. - Quality control.
- Dimension,straightness, welding
joint prepared. - External inspection.
- Design drawingand error.
- Welding joint checking tape-measure, control wire,
- Assembly. - Assemblyinspection
- Executing technogy - Workers
- Quality control - Supervisor party A
- Straightness, square,dimension...
-Design drawingand error
- Meter, tape for inspection of square angle.
- Welding beam,pillar, accessory.
- Welder with validcertificates.
- According to weldingprocedure system.
- Externalinspection.
-Executing technology.
-Nondestructive testing.
- Quality control. - Supervisor party A. - Subcontractor.
- Welding jointsurrounding.
- According towelding procedure.
-External inspection. - Cheking welding jointinside.
- Tecnicalrequirement o
f
construction.
- By visual, welding joint tape inspection. - Checking by ultrasonic.
- Repairingdefects. -Checking and fixing.
- Welders. - Subcontractor.
- According toinspection results.
- Accroding toquality requirement o-External inspection.
- Cheking welding jointinside.
f - By visual, checking by ultrasonic. construction.
- Grinder, welding machine.
- Sanding blast,paint.
- Manufacturing unit.
- Paintinginspection.
- Supervisor party A.
- Executing technology - Quality control.
- Surfaces preparation and paint. - Painting inspection.
- According totechnical requirement (seepainting procedure).
- Checking by visual.
- Checking by gauge for measuring thickness of paint.
III. Construction organization design.
1 -Bases on the construction design.
- Basing on technical standards of designer.
- Basing on tecnical design document of construction.
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 7/19
Steel structure Fabrication Procedure
- Basing on real condition of construction plan and construction work
quantity.
- Basing on rate canculating document for construction and construction
organization.
- Basing on material capacity, machinery, and manpower.
2 - Construction organization design.
Construction organization is very important task ensuring fast construction
process and achieved the best effect. The contractor will be responsible for this
task. They carry out the supported work like working platform, storage, yards of
materials gathered as well as products, water allocation system for construction.
The construction work quantity is mainly organized as follows:
In the shop of company
+ Fabrication of steel structure.
+ Cleaning, painting steel structure.
In the construction process, contractor is in full compliance with technical
procedures, rules and regulations of acceptance in accordance with designers
standard and owners requirement.
Basing on construction plan, the contractor carries out to clean ground, prepare
assembling platform, machinery for construction work.
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 8/19
Steel structure Fabrication Procedure
Chapter 2: Fabrication procedure
False
False
False
Assembly
False
False
Delivery for units
Inspectio Returni
Material receiving
Cutting
Repairin
Tack welding
Finish welding
blast cleaning
Inspectio Repairing
finish painting
Packing Complete payment
document
acceptance report
acceptance report
acceptance report
Inspectio Repairing
Inspectio Repairing
Inspectio Repairing
Inspectio Repairing
False
Inspectio g
False
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 9/19
Steel structure Fabrication Procedure
Chapter 3: Fabricating methods I. Check input materials of Work.
According to designers requirements, Contractor supply types of material
having clear origin, attaching material certificate.
Material inspection made as below requirement:
- Check material certificate of origin.
- Standard geometrical size: check by tape-measure, caliper
- Surface: convex, concave, void, crack, warping
- Technical characteristics of material:
- Physical-mechanical properties of steel: sampling, testing and certificating.
- Welding material properties according approved WPS & PQR.
- Components, properties of other materials.
- Control, inspection process of input materials for works following to designers
standard and the below diagram:
HaiPhong equipment Manufacture and
Shipbuilding CO., LTD
Materials
Delivering to company
material department inspection, correlation,storage
certificate of quality, quantity, weight
Gim st cng ty (QC)
check size, type of materials...
A partys supervisor inspect steel tag, typ... e of materials
Type of steel for fabrication works consist of:
1. Steel plate according to project standard, or appropriate 2. Steel shape according to project standard, or appropriate 3. Materials service for fabrication: welding material, painting material, the
other auxiliary materials
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 10/19
Steel structure Fabrication Procedure
Entire above materials strictly controlled and monitored according to materials
summary tables including detailed data. After be imported to Company, the
materials delivered to executing units for fabrication
II. Construction ground preparing. In order to service for fabrication as well as asembly all parts in Company, Company perform arrangement the construction ground at units. Assemblying platform for fabrication and inspection carefully prepared achieving standard surface. III. Products fabricating
Common fabricating steps:
Step 1: The parts shall be marked and cut according to marking and cutting dwgs
and design dwgs.
Marking and cutting according to the diagram shall be performed by assembly
group, parts marked and cut on the platform under the control, monitoring of
shop, group engineering staff, and QC of Company. The parts must be checked
the size, cleaness, beveled angle, hole welding, ... according to the Project
standard by Companys QC during marking and cutting process, when QC find
out that the parts achieving requirement, they shall be moved to the next stage.
Step 2: Assembly parts
After cutting, the parts shall be moved to assembling areas where assembling
work made by assembling group. Companys QC inspects the size, joint
clearance, tack welding, reinforced measure against deformationwhen these
achieve the Projects standard, the parts moved to the welding stage.
Before welding, structure should be inspected according to FIT-UP
INSPECTION FOR WELDING No: VA1-QCF-M-15 in document No: VA1-LI-
00100-M-GI-ITP-0002 (INSPECTION AND TEST PLAN FOR STEEL
STRUCTURE SHOP FABRICATION).
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 11/19
Steel structure Fabrication Procedure
Step 3: Welding
Welded connection executed according to welding procedure (WPS) which
Lisemco submitted to the Owner and supervisors, consultants. This procedure
performed by welders having valid certificates. Overall welding process strictly
inspected by welding QC about welding materials, the welders, quality of
welding jointsso as to restrict welding defects and avoid failures at the
beginning of the stage. All welding joints checked 100% external form
according to technical requirement of the project. The defected welding joints
shall be carried out to prepare following to repairing welding joint procedure
during inspection. .
Size of the parts inspected after finish welding ensuring to be in allowable
tolerance of the Project.
The weld should be inspection according to WELDING VISUAL RECORDS
No: VA1-QCF-M-14 in document No: VA1-LI-00100-M-GI-ITP-0002
(INSPECTION AND TEST PLAN FOR STEEL STRUCTURE SHOP
FABRICATION).
After welding, the struture should be inspection according to STEEL
STRUCTURE FABRICATION FINAL INSPECTION REPORT No: VA1-
QCF-M-013 in the document No: VA1-LI-00100-M-G1-ITP-0002
(INSPECTION AND TEST PLAN FOR STEEL STRUCTURE SHOP
FABRICATION) before painting.
All of taking-over form made according to Projects requirements and after the
parties ( the Owner, TVGS, LISEMCO contractor) have finished signing the
acceptance certificate, then move to painting stage
*) Welding procedure specification, process welding, and NDT for welding
work of reclaimers, stackers, unloaders, and towers shall be completely followed
FLS General Workshop Instructions which was issued.
AdminPolygon
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 12/19
Steel structure Fabrication Procedure
Step 4: Painting.
After checking according to STEEL STRUCTURE INSPECTION RECORD
BEFORE PAINTING No: VA1-QCF-M-012 in the document No: VA1-LI-
00100-M-G1-ITP-0002 (INSPECTION AND TEST PLAN FOR STEEL
STRUCTURE SHOP FABRICATION), products will be cleaned by abrasive
grain for blasting, boring machine for hard-to-handle, ensuring technical
requirements of this project. The quality control is ensured to move painting
stage and final acceptance for packing.
All the acceptance forms are made according to project requirements and after
the parties signed acceptance report to move the working stage, its time for
packing.
Due to design of parts with its own features, the construction part of work like
scraper, piler, unloader, tower of project have some different features.
III.1.The fabrication of Reclaimer: the fabrication of each unit
The cutting stage must carry out on CNC machine. After cutting, the plates are
connected together according to working drawing and finish welding for
connecting plates; check Nondectructive testing (NDT). If these results are
achived, conduct the assembly beam. The platform is used for assembly beam,
for example:
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 13/19
Steel structure Fabrication Procedure
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 14/19
Steel structure Fabrication Procedure
During beam assembling in three-sided process, each unit is connected
completely according to design set, bracing to avoid welding deformation; and
then weld the whole beam inside. After checking by visual about welding of
beam inside, cap the plate to control the dimension of the beam and conduct to
welding finish. Checking by visual the overall dimensions of welding seam; the
flatness of beam sides according to the length design of beam. If these results
achieved, conduct Nondestructive testing and acceptance to move for cleaning
and painting.
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 15/19
Steel structure Fabrication Procedure
Roller support is made with the same way.
Dump bailer supports in fabricating procedure and inspection are skidded on the
platform.
Dump bailer will be fabricated and accepted in accordance with gauge.
All units connecting together which are difficult to clean and paint, after
finishing, they are cleaned and painted with anticorrosive paint before
assembling.
The remains of scraper will be completely fabricated, accepted and finish
painting at the LISEMCO Contractors shop, and then conduct to assembly and
install.
III.2. The fabrication of Stacker: the fabrication of each unit
The cutting stage must carry out on CNC machine. After cutting, the plates are
connected together according to working drawing and finish welding for
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 16/19
Steel structure Fabrication Procedure
connecting plates; check Nondestructive testing (NDT). If these results are
achieved, conduct the assembly beam. The platform is used for assembly beam.
During beam assembling in three-sided process, each unit is connected
completely according to design set, bracing to avoid welding deformation; and
then weld the whole beam inside. After checking by visual about welding of
beam inside, cap the plate to control the dimension of the beam and conduct to
welding finish. Checking by visual the overall dimensions of welding seam; the
flatness of beam sides according to the length design of beam. If these results
achieved, conduct Nondestructive testing and acceptance to move for cleaning
and painting.
Roller support is made with the same way.
Band conveyor support in fabricating process and inspection is performed on
gauge support.
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 17/19
Steel structure Fabrication Procedure
All units connecting together which are difficult to clean and paint, after
finishing, they are cleaned and painted with anticorrosive paint before
assembling.
The remains of Stacker will be completely fabricated, accepted and finish
painting at the LISEMCO Contractors shop, and then conduct to assembly and
install.
III.3. Unloader machine fabrication : execution with each unit.
Cutting stage performed by CNC machine. After pleteting , the plates connected
according to fabrication drawing and finishing welded, if NDT checking is
achieved, beam assembling will be implemented. Platform used for this work
During beam assembling in three-sided process, each unit is connected
completely according to design set, bracing to avoid welding deformation; and
then weld the whole beam inside. After checking by visual about welding of
beam inside, cap the plate to control the dimension of the beam and conduct to
welding finish. Checking by visual the overall dimensions of welding seam; the
flatness of beam sides according to the length design of beam. If these results
achieved, conduct Nondestructive testing and acceptance to move for cleaning
and painting.
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 18/19
Steel structure Fabrication Procedure
The remains of unloader will be made with the same way and cleaned and
painted at the LISEMCO Contractors shop, and then conduct to pack and
install.
III.4. Fabrication for direction turning tower: Because tower structure
coupling bolt, so fabrication process is process which fabricate loose parts , after
that testing assembly each unit.
+ The pillar, beam are cut by steel shape (I,V...) with right dimension, marked by
arrows directing position of gusset plate, attaching gusset plate after drilling
hole.
+ Bracing is performed with cutting dimension, attached gusset plate, welding,
dimension inspection after welding and flatness, then move to clean and paint.
-
Hai phong equipment manufacture and shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8
Mar. 30th, 2011
Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 19/19
Steel structure Fabrication Procedure
+ Platform and ladder are fabricated with the same way.
+ After loose materials are checked, cleaned and painted.
+ Packing and installing in construction site.
IV. Inspection of dimensional tolerance
+ Measurement testing, tolerance in dimension acceptance inspection according
to project standards (Document no:VA1-FLS-00100-M-M2-DST-6040)
0.7/100 mm0.6/100 mm1.8/100 mm
2.6/100 mm5.2/100 mm
32
501000
12864
120