va1 lsc 00100 qa m8 tpd 0006 (steel structure fabrication procedure) rev.1

20
DOCUMENT SUBMISSION STATUS: FC 1 30/03/11 ISSUED FOR CONSTRUCTION T.V.CUONG D.V.HIEU P.N.QUANG 0 11/03/11 ISSUED FOR CONSTRUCTION T.V.CUONG D.V.HIEU N.H.QUAN E 26/01/11 ISSUED FOR APPROVAL T.V.CUONG N.V.BIEN P.N.QUANG D 10/01/11 ISSUED FOR APPROVAL C 18/11/10 ISSUED FOR APPROVAL B 29/10/10 ISSUED FOR APPROVAL REV DATE DESCRIPTION PREP. CHKD APPN OWNER OWNER’S CONSULTANT EPC CONTRACTOR EPC CONTRACTOR’S CONSULTANT PROJECT TITLE VUNG ANG 1 THERMAL POWER PLANT 2 x 600MW PACKAGE: M8 CONTRACT No. 222010/ LILAMA-LISEMCO DRAWING TITLE: steel structure FABRICATION PROCEDURE SUB-CONTRACTOR HAIPHONG EQUIPMENT MANUFACTURE AND SHIPBUILDING CO.LTD, (LISEMCO) FUNCTION NAME SIGN DATE PREPARED TO VIET CUONG 30/03/11 CHECKED DAM VAN HIEU 30/03/11 APPROVED PHAM NGOC QUANG 30/03/11 DOCUMENT No.VA1-LSC-00100-QA-M8-TPD-0006 SCALE REV. 1 POYRY ENERGY LTD VIETNAM OIL AND GAS GROUP (PVN) VIETNAM MACHINERY INSTALLATION CORPORATION (LILAMA)

Upload: mungnguyendinh

Post on 16-Dec-2015

54 views

Category:

Documents


4 download

DESCRIPTION

Steel structure fabrication

TRANSCRIPT

  • DOCUMENT SUBMISSION STATUS: FC

    1 30/03/11 ISSUED FOR CONSTRUCTION T.V.CUONG D.V.HIEU P.N.QUANG 0 11/03/11 ISSUED FOR CONSTRUCTION T.V.CUONG D.V.HIEU N.H.QUAN E 26/01/11 ISSUED FOR APPROVAL T.V.CUONG N.V.BIEN P.N.QUANG D 10/01/11 ISSUED FOR APPROVAL C 18/11/10 ISSUED FOR APPROVAL B 29/10/10 ISSUED FOR APPROVAL

    REV DATE DESCRIPTION PREP. CHKD APPN

    OWNER

    OWNERS CONSULTANT

    EPC CONTRACTOR

    EPC CONTRACTORS CONSULTANT

    PROJECT TITLE

    VUNG ANG 1 THERMAL POWER PLANT 2 x 600MW PACKAGE: M8

    CONTRACT No. 222010/ LILAMA-LISEMCO

    DRAWING TITLE:

    steel structure FABRICATION PROCEDURE

    SUB-CONTRACTOR

    HAIPHONG EQUIPMENT MANUFACTURE AND SHIPBUILDING CO.LTD, (LISEMCO)

    FUNCTION NAME SIGN DATE

    PREPARED TO VIET CUONG 30/03/11

    CHECKED DAM VAN HIEU 30/03/11

    APPROVED PHAM NGOC QUANG 30/03/11

    DOCUMENT No.VA1-LSC-00100-QA-M8-TPD-0006

    SCALE REV. 1

    POYRY ENERGY LTD VIETNAM OIL AND GAS GROUP (PVN)

    VIETNAM MACHINERY INSTALLATION CORPORATION (LILAMA)

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 1/19

    Steel structure Fabrication Procedure

    Steel structure Fabrication Procedure

    project Vung Ang1 Thermal Power Plant Item COAL HANDLING SYSTEM M8 location Ky Loi commune - Ky Anh District-Ha Tinh province

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 2/19

    Steel structure Fabrication Procedure

    Index

    No Title Page

    1 Chapter 1: General Introduction. 2

    2 Chapter 2: Fabrication procedure. 5

    3 Chapter 3: Fabrication method. 6

    Chapter 1: General Introduction I. General Introduction

    1. Executing Organization Chart (As shown in page 4).

    Hai phong Equipment Manufacture and Shipbuilding CO., LTD

    a. Responsibilities and rights

    Hai Phong Equipment Manufacture and Shipbuilding CO., LTD is a member

    company belonging to Vietnam Machinery Installation Corporation (LILAMA).

    With its big site plan (8ha), modern equipment, and the teams of experienced

    engineer and equipped with knowledge and new executing technologies, a large

    number of workers as well as skillful workers, Hai phong Equipment

    Manufacture and Shipbuilding CO., LTD is responsible for providing materials

    and installation of equipment for Vung Ang 1 thermal power plant 2x600 MW-

    Coal handling plant M-lot 2

    All steel structure will be fabricated in factory of Lisemco in Hai Phong to

    ensure quality, error and convenience for installation process of steel structure.

    The whole process of structural steel fabrication, company will carry out by

    itself equipment and staff member.

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 3/19

    Steel structure Fabrication Procedure

    b. The director of project

    Full name: Nguyen Hong Quan

    Position: Project Director

    Tel : 031-3522496

    Fax : 031-3850120.

    E-mail : [email protected]

    2. Inspection unit- quality control

    Inspection unit quality control belonging to quality control Department which

    is an independent organization with in manufacturing units operating under the

    leaderships of the parent company, is responsible for quality control, checking to

    ensure the steps of manufacturing technology and installation implemented

    seriously for quality assurance of construction.

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 4/19

    Steel structure Fabrication Procedure

    ORGANIZATION CHART FOR LOT-M8VUNG ANG 1.THERMALPOWER PLANT PROJECT

    LILAMA PMB

    PROJECT MANAGERMr.NGUYEN HONG QUAN

    E-mail: [email protected]@vnn.vn

    DEPUTY PROJECT MANAGER& SITE MANAGERMr. PHAM NGOC QUANG

    E-mail: [email protected]

    PROJECT COORDINATORMr. TO VIET CUONGMobi: 01696815187

    E-mail: [email protected]

    QC/QA PRJ. MANAGEMENTMr. NGUYEN QUANG VINH

    SAFETY&SE MANAGEMENTMr. PHAM VAN TUYEN

    Mobi: 0934692591E-mail: [email protected]

    MANUFACTURING MANAGERMr. NGUYEN VAN BIEN

    Mobi: 0989126635E-mail: [email protected]

    LISEMCO ltd,.GENERAL DIRECTOR

    Mr. TRAN VIET KHANHEmail: [email protected]

    Date of isuue: Otc 12th, 2010

    MECHANIC AND WELDER TEAM - 25

    WORK-SHOP No1Mr NGUYEN VAN DOANH

    WORK-SHOP No2Mr. NGUYEN VAN HUNG

    MECHANIC AND WELDER TEAM - 25

    PAINTING PACKING & SHIPPMENT

    Mr.DOANVAN HA

    PAINTINGTEAM-01

    PEOPLE 12

    WORK SHOP SUPERVISORENGINEERS

    OFFICE MANAGERMs.TRUONG THI HUONGMs.HO THI KHANH HOA

    QC/QA PRJ. MANAGERMr. VU VAN QUANGMr MAI HUY CUONGMr.VU DUC THANH

    RECEIVING EQUIPMENTAND HAND MANAGER

    Mr. NGUYEN DINH QUYNH

    TECHNICAL MANAGEMENTMr. DO XUAN DUNGMobi: 0982592029

    MATERIALS MANAGEMENTMr. BUI DUC THIETMobi: 0904828298

    SAFETY&SECURITY MANAGERMr. PHAN VAN HUNGMs: NGUYEN THI LAM

    STEEL STRUCTURETEAM 02PEOPLE 35

    STEEL STRUCTURETEAM 02PEOPLE 35

    PACKING & SHIPPMENTTEAM -01

    PEOPLE 06

    STEEL STRUCTURE+MECHANIC

    TEAM-02PEPLE 30

    ELECTRICIAN+INSULATING+

    COMMISSONINGTEAM 01PEPLE 19

    PAINTERTEAM - 01PEPLE 8

    WELDERTEAM - 01PEPLE 15

    Inspection unit- quality control has rights of suspending activities which not

    comply with procedures , and has risk of bad influence on quality manufactured

    products as well as installation leading bad effects on construction quality.

    Inspection shall followed he details in lines with the approved ITP which are

    completed by LILAMA.

    AdminPolygon

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 5/19

    Steel structure Fabrication Procedure

    3. Reference:

    - Specification of the project.

    - FLS General Workshop instructions.

    - Document No. VA1-LI-00100-M-G1-ITP-0002 INSPECTION AND TEST

    PLAN FOR STEEL STRUCTURE SHOP FABRICATION

    - Document No. VA1-LI-00100-QA-G1-ITP-0001 INSPECTION AND TEST

    PLAN FOR PAINTING

    - Standard: DIN.

    4. Shop, fabrication teams

    Fabrication teams are responsible for executing construction in accordance with

    design, quality assurance and work progress and directly carry out at shop in

    lisemco.

    In case of unexpected problems in construction process exceeds the capacity of

    fabrication units. They can request related parts supporting technology,

    eqiupment, manpower. All the requirements of fabrication groups must be

    presented in writen form system of Lisemco (in case the customers do not have

    special requiremetns). These requirements are given Economy-Technology

    Department, Lisemco. Economy-Technology Department must have answer in

    writen form within 24 hours.

    II. Objects, scopes and references.

    1. Objects The process of structural steel fabrication is to give a manufacturing scientific

    plan, strict inspection system, ensuring quality to meet the quality control system

    ISO 9001 : 2000 which company Lisemco is applying, also satifies the

    customers requirements about product quality and construction progress.

    2. Application scope

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 6/19

    Steel structure Fabrication Procedure

    This process is applied to fabrication equipment and manufacturing of steel

    structure.

    3. References

    Shop drawings, related technical documents and standards.

    The technical standards are given by Owner.

    4. Fabrication chart and inspection

    o Content of Work

    Implementation unit Inspection criteria Evaluation criteria

    Inspection tools Report form

    -Check inputmaterials.

    -Executing technology

    -Material officer. -Quality control - Supervisor party A

    - Original - Number - Dimension - Visual inspection

    - Certificate oManufacturer. - Accroding toorder

    - Tape-measure, caliper

    - No wrapping,rust, blistery.

    - By visual.

    - Certificates - Comparing orders

    - Marking andcutting

    - Workers

    -Inspections - Executing technology - Quality control

    - Dimension, beveledangel.

    - Design drawing.

    - External insepction.

    - Tape-measure.

    -Straightening -Detailed assembly -Inspection

    - Workers -Executing technology. - Quality control.

    - Dimension,straightness, welding

    joint prepared. - External inspection.

    - Design drawingand error.

    - Welding joint checking tape-measure, control wire,

    - Assembly. - Assemblyinspection

    - Executing technogy - Workers

    - Quality control - Supervisor party A

    - Straightness, square,dimension...

    -Design drawingand error

    - Meter, tape for inspection of square angle.

    - Welding beam,pillar, accessory.

    - Welder with validcertificates.

    - According to weldingprocedure system.

    - Externalinspection.

    -Executing technology.

    -Nondestructive testing.

    - Quality control. - Supervisor party A. - Subcontractor.

    - Welding jointsurrounding.

    - According towelding procedure.

    -External inspection. - Cheking welding jointinside.

    - Tecnicalrequirement o

    f

    construction.

    - By visual, welding joint tape inspection. - Checking by ultrasonic.

    - Repairingdefects. -Checking and fixing.

    - Welders. - Subcontractor.

    - According toinspection results.

    - Accroding toquality requirement o-External inspection.

    - Cheking welding jointinside.

    f - By visual, checking by ultrasonic. construction.

    - Grinder, welding machine.

    - Sanding blast,paint.

    - Manufacturing unit.

    - Paintinginspection.

    - Supervisor party A.

    - Executing technology - Quality control.

    - Surfaces preparation and paint. - Painting inspection.

    - According totechnical requirement (seepainting procedure).

    - Checking by visual.

    - Checking by gauge for measuring thickness of paint.

    III. Construction organization design.

    1 -Bases on the construction design.

    - Basing on technical standards of designer.

    - Basing on tecnical design document of construction.

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 7/19

    Steel structure Fabrication Procedure

    - Basing on real condition of construction plan and construction work

    quantity.

    - Basing on rate canculating document for construction and construction

    organization.

    - Basing on material capacity, machinery, and manpower.

    2 - Construction organization design.

    Construction organization is very important task ensuring fast construction

    process and achieved the best effect. The contractor will be responsible for this

    task. They carry out the supported work like working platform, storage, yards of

    materials gathered as well as products, water allocation system for construction.

    The construction work quantity is mainly organized as follows:

    In the shop of company

    + Fabrication of steel structure.

    + Cleaning, painting steel structure.

    In the construction process, contractor is in full compliance with technical

    procedures, rules and regulations of acceptance in accordance with designers

    standard and owners requirement.

    Basing on construction plan, the contractor carries out to clean ground, prepare

    assembling platform, machinery for construction work.

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 8/19

    Steel structure Fabrication Procedure

    Chapter 2: Fabrication procedure

    False

    False

    False

    Assembly

    False

    False

    Delivery for units

    Inspectio Returni

    Material receiving

    Cutting

    Repairin

    Tack welding

    Finish welding

    blast cleaning

    Inspectio Repairing

    finish painting

    Packing Complete payment

    document

    acceptance report

    acceptance report

    acceptance report

    Inspectio Repairing

    Inspectio Repairing

    Inspectio Repairing

    Inspectio Repairing

    False

    Inspectio g

    False

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 9/19

    Steel structure Fabrication Procedure

    Chapter 3: Fabricating methods I. Check input materials of Work.

    According to designers requirements, Contractor supply types of material

    having clear origin, attaching material certificate.

    Material inspection made as below requirement:

    - Check material certificate of origin.

    - Standard geometrical size: check by tape-measure, caliper

    - Surface: convex, concave, void, crack, warping

    - Technical characteristics of material:

    - Physical-mechanical properties of steel: sampling, testing and certificating.

    - Welding material properties according approved WPS & PQR.

    - Components, properties of other materials.

    - Control, inspection process of input materials for works following to designers

    standard and the below diagram:

    HaiPhong equipment Manufacture and

    Shipbuilding CO., LTD

    Materials

    Delivering to company

    material department inspection, correlation,storage

    certificate of quality, quantity, weight

    Gim st cng ty (QC)

    check size, type of materials...

    A partys supervisor inspect steel tag, typ... e of materials

    Type of steel for fabrication works consist of:

    1. Steel plate according to project standard, or appropriate 2. Steel shape according to project standard, or appropriate 3. Materials service for fabrication: welding material, painting material, the

    other auxiliary materials

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 10/19

    Steel structure Fabrication Procedure

    Entire above materials strictly controlled and monitored according to materials

    summary tables including detailed data. After be imported to Company, the

    materials delivered to executing units for fabrication

    II. Construction ground preparing. In order to service for fabrication as well as asembly all parts in Company, Company perform arrangement the construction ground at units. Assemblying platform for fabrication and inspection carefully prepared achieving standard surface. III. Products fabricating

    Common fabricating steps:

    Step 1: The parts shall be marked and cut according to marking and cutting dwgs

    and design dwgs.

    Marking and cutting according to the diagram shall be performed by assembly

    group, parts marked and cut on the platform under the control, monitoring of

    shop, group engineering staff, and QC of Company. The parts must be checked

    the size, cleaness, beveled angle, hole welding, ... according to the Project

    standard by Companys QC during marking and cutting process, when QC find

    out that the parts achieving requirement, they shall be moved to the next stage.

    Step 2: Assembly parts

    After cutting, the parts shall be moved to assembling areas where assembling

    work made by assembling group. Companys QC inspects the size, joint

    clearance, tack welding, reinforced measure against deformationwhen these

    achieve the Projects standard, the parts moved to the welding stage.

    Before welding, structure should be inspected according to FIT-UP

    INSPECTION FOR WELDING No: VA1-QCF-M-15 in document No: VA1-LI-

    00100-M-GI-ITP-0002 (INSPECTION AND TEST PLAN FOR STEEL

    STRUCTURE SHOP FABRICATION).

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 11/19

    Steel structure Fabrication Procedure

    Step 3: Welding

    Welded connection executed according to welding procedure (WPS) which

    Lisemco submitted to the Owner and supervisors, consultants. This procedure

    performed by welders having valid certificates. Overall welding process strictly

    inspected by welding QC about welding materials, the welders, quality of

    welding jointsso as to restrict welding defects and avoid failures at the

    beginning of the stage. All welding joints checked 100% external form

    according to technical requirement of the project. The defected welding joints

    shall be carried out to prepare following to repairing welding joint procedure

    during inspection. .

    Size of the parts inspected after finish welding ensuring to be in allowable

    tolerance of the Project.

    The weld should be inspection according to WELDING VISUAL RECORDS

    No: VA1-QCF-M-14 in document No: VA1-LI-00100-M-GI-ITP-0002

    (INSPECTION AND TEST PLAN FOR STEEL STRUCTURE SHOP

    FABRICATION).

    After welding, the struture should be inspection according to STEEL

    STRUCTURE FABRICATION FINAL INSPECTION REPORT No: VA1-

    QCF-M-013 in the document No: VA1-LI-00100-M-G1-ITP-0002

    (INSPECTION AND TEST PLAN FOR STEEL STRUCTURE SHOP

    FABRICATION) before painting.

    All of taking-over form made according to Projects requirements and after the

    parties ( the Owner, TVGS, LISEMCO contractor) have finished signing the

    acceptance certificate, then move to painting stage

    *) Welding procedure specification, process welding, and NDT for welding

    work of reclaimers, stackers, unloaders, and towers shall be completely followed

    FLS General Workshop Instructions which was issued.

    AdminPolygon

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 12/19

    Steel structure Fabrication Procedure

    Step 4: Painting.

    After checking according to STEEL STRUCTURE INSPECTION RECORD

    BEFORE PAINTING No: VA1-QCF-M-012 in the document No: VA1-LI-

    00100-M-G1-ITP-0002 (INSPECTION AND TEST PLAN FOR STEEL

    STRUCTURE SHOP FABRICATION), products will be cleaned by abrasive

    grain for blasting, boring machine for hard-to-handle, ensuring technical

    requirements of this project. The quality control is ensured to move painting

    stage and final acceptance for packing.

    All the acceptance forms are made according to project requirements and after

    the parties signed acceptance report to move the working stage, its time for

    packing.

    Due to design of parts with its own features, the construction part of work like

    scraper, piler, unloader, tower of project have some different features.

    III.1.The fabrication of Reclaimer: the fabrication of each unit

    The cutting stage must carry out on CNC machine. After cutting, the plates are

    connected together according to working drawing and finish welding for

    connecting plates; check Nondectructive testing (NDT). If these results are

    achived, conduct the assembly beam. The platform is used for assembly beam,

    for example:

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 13/19

    Steel structure Fabrication Procedure

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 14/19

    Steel structure Fabrication Procedure

    During beam assembling in three-sided process, each unit is connected

    completely according to design set, bracing to avoid welding deformation; and

    then weld the whole beam inside. After checking by visual about welding of

    beam inside, cap the plate to control the dimension of the beam and conduct to

    welding finish. Checking by visual the overall dimensions of welding seam; the

    flatness of beam sides according to the length design of beam. If these results

    achieved, conduct Nondestructive testing and acceptance to move for cleaning

    and painting.

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 15/19

    Steel structure Fabrication Procedure

    Roller support is made with the same way.

    Dump bailer supports in fabricating procedure and inspection are skidded on the

    platform.

    Dump bailer will be fabricated and accepted in accordance with gauge.

    All units connecting together which are difficult to clean and paint, after

    finishing, they are cleaned and painted with anticorrosive paint before

    assembling.

    The remains of scraper will be completely fabricated, accepted and finish

    painting at the LISEMCO Contractors shop, and then conduct to assembly and

    install.

    III.2. The fabrication of Stacker: the fabrication of each unit

    The cutting stage must carry out on CNC machine. After cutting, the plates are

    connected together according to working drawing and finish welding for

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 16/19

    Steel structure Fabrication Procedure

    connecting plates; check Nondestructive testing (NDT). If these results are

    achieved, conduct the assembly beam. The platform is used for assembly beam.

    During beam assembling in three-sided process, each unit is connected

    completely according to design set, bracing to avoid welding deformation; and

    then weld the whole beam inside. After checking by visual about welding of

    beam inside, cap the plate to control the dimension of the beam and conduct to

    welding finish. Checking by visual the overall dimensions of welding seam; the

    flatness of beam sides according to the length design of beam. If these results

    achieved, conduct Nondestructive testing and acceptance to move for cleaning

    and painting.

    Roller support is made with the same way.

    Band conveyor support in fabricating process and inspection is performed on

    gauge support.

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 17/19

    Steel structure Fabrication Procedure

    All units connecting together which are difficult to clean and paint, after

    finishing, they are cleaned and painted with anticorrosive paint before

    assembling.

    The remains of Stacker will be completely fabricated, accepted and finish

    painting at the LISEMCO Contractors shop, and then conduct to assembly and

    install.

    III.3. Unloader machine fabrication : execution with each unit.

    Cutting stage performed by CNC machine. After pleteting , the plates connected

    according to fabrication drawing and finishing welded, if NDT checking is

    achieved, beam assembling will be implemented. Platform used for this work

    During beam assembling in three-sided process, each unit is connected

    completely according to design set, bracing to avoid welding deformation; and

    then weld the whole beam inside. After checking by visual about welding of

    beam inside, cap the plate to control the dimension of the beam and conduct to

    welding finish. Checking by visual the overall dimensions of welding seam; the

    flatness of beam sides according to the length design of beam. If these results

    achieved, conduct Nondestructive testing and acceptance to move for cleaning

    and painting.

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 18/19

    Steel structure Fabrication Procedure

    The remains of unloader will be made with the same way and cleaned and

    painted at the LISEMCO Contractors shop, and then conduct to pack and

    install.

    III.4. Fabrication for direction turning tower: Because tower structure

    coupling bolt, so fabrication process is process which fabricate loose parts , after

    that testing assembly each unit.

    + The pillar, beam are cut by steel shape (I,V...) with right dimension, marked by

    arrows directing position of gusset plate, attaching gusset plate after drilling

    hole.

    + Bracing is performed with cutting dimension, attached gusset plate, welding,

    dimension inspection after welding and flatness, then move to clean and paint.

  • Hai phong equipment manufacture and shipbuilding company limited

    Vung Ang 1 Thermal Power Plant

    Ky Loi commune, Ky Anh district, Ha Tinh province

    ITEM: COAL HANDLING SYSTEM M8

    Mar. 30th, 2011

    Rev: 1

    Code: VA1-LSC-00100-QA-M8-TPD-0006

    Page: 19/19

    Steel structure Fabrication Procedure

    + Platform and ladder are fabricated with the same way.

    + After loose materials are checked, cleaned and painted.

    + Packing and installing in construction site.

    IV. Inspection of dimensional tolerance

    + Measurement testing, tolerance in dimension acceptance inspection according

    to project standards (Document no:VA1-FLS-00100-M-M2-DST-6040)

    0.7/100 mm0.6/100 mm1.8/100 mm

    2.6/100 mm5.2/100 mm

    32

    501000

    12864

    120