va1-tatl-00100-m-m7-cal-0001
TRANSCRIPT
-
8/12/2019 VA1-TATL-00100-M-M7-CAL-0001
1/3
DOCUMENT SUBMISSION STATUS: AP
C 21.12.10 Revised as per comment sheet no. CS-M7-M-00148 PS GAK GAK
B 14.08.10 Revised as per latest Layout PS GAK GAK
A 31.03.10 Submitted for Approval PS GAK GAK
REV DATE DESCRIPTION DRWN CHKD APPD
OWNER OWNERS CONSULTANT
EPC CONTRACTOR EPC CONTRACTORS CONSULTANT
FI HTNERFichtner GMBH & Co. Kg
PROJECT TITLE
VUNG ANG 1 THERMAL POWER PLANT 2 x 600MW
M-LOT7 ASH HANDLING PLANT
CONTRACT No. 100210/LILAMA-TECPRO Dated 10.02.2010
DRAWING TITLE : WET BOTTOM ASH HOPPER JET PUMP SIZING CALCULATION
SUB-CONTRACTOR :
TE PRO SYSTEMS LIMITED
FUNCTION NAME SIGN DATE
DRWN Poonam Singh 21.12.10
CHKD G.Ashok Kumar 21.12.10
APPD G.Ashok Kumar 21.12.10
DOCUMENT No. VA1-TATL-00100-M-M7-CAL-0001
SCALE REV C
VIETNAM OIL AND GAS GROUP (PVN) POYRY ENERGY LTD
VIETNAM MACHINERY INSTALLATIONCORPORATION (LILAMA)
-
8/12/2019 VA1-TATL-00100-M-M7-CAL-0001
2/3
Sl No Parameters Terms Units Formula Value Remarks
1 Bottom Ash TBA T/hr 20.00As per Revised input Design
Parameters, Attachment no.2
2 Deletd
3 Deleted
4 Total Coarse ash generation TCA T/hr 20.00
5 Ash Generation for 8 Hrs T/shift [8 x TCA] 160.00
6 Density of Bottom Ash T/Cum 1.20As per Revised input Design
Parameters, Attachment no.2
7 Wet Bottom Ash Hopper Capacity required QBAR m3 133.33
8 Wet Bottom Ash Hopper Capacity Provided QBAp m
3
200.00
Refer calculation no.
VA1-TATL-00100-M-M7-CAL-0002
9 Evacuation Time tc Hrs 1.10As per Revised input Design
Parameters, Attachment no.2
10 Evacuation Rate Qc m3/hr [QBAP/ tc] 181.82
11 No of Jet Pumps working n Nos 2.00
3
CALCULATION SHEET
M-Lot7 Ash Handling Plant
100210/LILAMA-TECPRO dated 10.02.2010
Vietnam Oil and Gas Group (PVN)
Poyry Energy Ltd
Vietnam Machinery Installation Corporation (LILAMA)EPC Contractor
Contract No.
Owner
Owner's Consultant
Wet Bottom Ash Hopper Jet Pump Sizing Calculations
Poonam Singh
G. Ashok Kumar
EPC Contractor Consu ltant
Sub Contractor Tecpro Systems Limited
DOC. NO. : VA1-TATL-00100-M-M7-CAL-0001
Project Title
Pacakge Title
REVISION : C DATE : 21.12.10
Vung Ang 1 Thermal Power Plant 2 x 600MW
Fichtner GMBH & Co. Kg
Subject
Calculated By
Reviewed and Approved By
B
C
C
JP m r c .
13 Additional Jetting water for flushing Qj m3/hr 15.00
14 Clinker Grinder Sealing water QCG m3/hr 4.00
15 Tota l Je t Pump in le t QTJP m3/hr [QJP+Qj+QCG] 109.91
16 Jet Pump discharge pipe NB 250.00
17 Pipe OD OD mm 273.10
18 Pipe thickness t mm 36.556mm pipe thk + 20mm Basalt Lining thk
+ 10.55 mm mortar Thk
19 Pipe ID ID mm 200.00
20 Pipe Area A m2 0.03
21 Permissible velocity through the pipe V m/s 2.30
22 Permissible flow through the pipe Q m3/hr 260.23
23 Motive water (HP water) Qmot m3/hr [Q - QTJP] 150.32
Qmot m3/hr 150.00
24 Specific gravity of conveying slurry S1(Q+ash equivalent
(54.54))/Q1.210 Particle Densi ty of Ash 2 T/ m3
25 Specific gravity of Jet pump input slurry S(QTJP+ash equivalent
(54.54))/QTJP1.496 Particle Density of Ash 2 T/ m
3
26 Removal rate of Jet Pump QTJP/S 73.457Which includes other water from wet
bottom ash hopper
27 Length of conveying pipe (Maximum distance considered) L M 330.00
28 No. o f bends in pipe Nb 9.00B
B
B
B
1 of 2
-
8/12/2019 VA1-TATL-00100-M-M7-CAL-0001
3/3
29 Equivalent pipe length Leq M 3.70
30 Friction loss in pipe per 1000m Hf M 26.95
31 Hf in slurry pipe (C = 140) 8.99
32 Margin on Head [10%] H M 1.1 x Hf 9.89
33 Static head Hst M 5.00
34 Total Drop Tdrop M [Hst + Hf] 14.89
By momentum eqn
35 Head required at Jet Pump inlet MWC HxQmotx0.30 = QxTdrop 86.12 Jet Pump eff iciency = 30%
MWC 87
36 Motive water required at Jet Pump inlet 150 m3/hr at 87 MWC
B
B
2 of 2