validation of hvac systems

Upload: navas1972

Post on 02-Jun-2018

320 views

Category:

Documents


5 download

TRANSCRIPT

  • 8/10/2019 Validation of HVAC Systems

    1/6

    Special Edition: Utilities Qualification32

    Brian Scott Jeff Hargroves

    nd

    Jerry Bauers

    V LID TION OF HV C

    SYSTEMS IN

    PH RM CEUTIC L

    & BIOTECHNOLOGY

    F CILITIES

    P RT

    Editor s Note:

    The following article

    is

    the first in a

    two-part series. Part One addresses the fund men-

    tal requirements

    nd

    installation qualification of

    HVAC systems. Part Two which will appear in the

    May issue

    of

    the Journal will discuss the opera

    tional qualification

    nd

    performance qualification

    of hese systems.

    An HVAC system, which encompasses heating,

    ventilation,

    and air conditioning, is an integral

    component

    of

    a facility's functionality. t impacts the

    safety

    of

    scientists and technicians working in a lab

    or production facility, the integrity of processes, and

    the environment outside.

    There are three core phases of HVAC system

    validation: installation qualification (IQ), opera-

    tional qualification (OQ),

    and

    performance qualifi

    cation (PQ). An important element of successful

    HVAC validation is prevalidation design work. This

    article

    explores the

    correlation

    between

    prelimi

    nary design and each

    phase

    of validation.

    HVAC SYSTEM FUNDAMENTALS

    Construction and validation of an HVAC system usu

    ally involves compiling the following documents,

    which typically are developed in the order presented

    in

    Figure

    :

    Functional Specification (the conceptual design)

    Design Drawings, Plans,

    and

    Specifications

    Validation Master Plan

    Contractor Documents e.g., shop drawings

    and submittals)

    Testing, Adjusting, and Balancing TAB) and

    Start-up Reports

    Commissioning Report (The actual execu

    tion

    of

    validation protocols may commence;

    commissioning may be performed as part

    of

    the development

    phase of

    validation.)

    Validation (IQ, OQ,

    &

    PQ)

    When PQ is complete, process validation com-

    mences

    and product

    manufacture or

    laboratory

    processes)

    can

    begin.

    Whatever the components

    of an

    HVAC system,

    the functional requirements must be determined up

    front. In fact, functional specifications are the cor

    nerstone

    of

    any project.

    t

    is

    important that design criteria

    is

    not the sole

    basis for establishing validation acceptance criteria .

    Design criteria may be written with extreme precision,

    but acceptance criteria for validation may not need to

    be

    so stringent. This determination comes from

    understanding the process in question. The design

    team must understand and assist in determining what

    a system needs to do in the context

    of

    processes

    and other operations carried out within a facility.

  • 8/10/2019 Validation of HVAC Systems

    2/6

    Special Edition: Utilities Qualification 33

    Brion Scatt JeH

    Hargraves

    and Jerry Bo uers

    Figure

    DOCUMENT T ON

    SU

    P

    POR

    TI NG CONSTRUCfION

    ND V LI D TION OF N HV C SYSTEM

    CODI.ltdOr

    Operational Qualification

    OQ)

    Performance

    Qualification

    PQ)

  • 8/10/2019 Validation of HVAC Systems

    3/6

    Special Edition: Utilities Qualification34

    Brian Scott, Jeff Hargroves,

    and

    Jerry Bauers

    A description

    of

    functional requirements

    should include:

    HVAC system functionality as it relates to

    processes.

    Points in a process that

    expose

    a

    product to

    the environment.

    Source of design guidelines (e.g., an existing

    similar facility, a domestic

    or

    foreign

    regulatory body).

    The

    following

    is an excerpt

    from

    a functional

    requirements description for a typical manufactur

    ing facility:

    Air

    handling unit

    AHU-Ol seroes

    an aseptic fill

    ing suite

    in

    the New Product Facility. The suite

    includes

    an

    aseptic area, clothes changing

    room, two

    equipment pass-throughs,

    and

    an

    incubator room.

    The

    air handling

    unit draws a

    mixture of

    makeup air

    and

    return air into a mixing section,

    through a series of ilters,

    and

    a cooling

    coil;

    then

    blows the air

    through

    a heating coil and dis

    charges it into distribution ductwork. Filtration

    is

    prOVided

    by 30 ASH

    RAE

    efficiency

    pre-filters,

    95% ASHRAE efficiency bag filters,

    and

    99.97%

    HEPA

    filters. Terminal

    99.995

    HEPA

    filter dif

    fusers provide

    final

    filtration

    and

    air distribution

    in

    each room.

    Air

    is

    returned

    through low wall

    louvered return grilles. Temperature is maintained

    at

    66

    F.

    Humidity

    is maintained

    between 20%

    and

    50%

    RH.

    Space pressurizations are shown on

    Drawing XX-lOJ-AA.

    Once deSigners understand the functionality of a

    faCility the next questions are who

    or

    what holds

    regulatory responsibility and what are the particular

    performance requirements.

    The

    answers to these

    questions lead to perhaps the most significant issues

    in validating

    an HVAC

    system: The processes that

    the system is supporting

    and who

    monitors the per

    formance of the facility. Validation criteria must

    be

    established within this context

    and

    not in a vacuum

    or against arbitrary right or wrong conditions.

    Personnel responsible for

    HVAC

    validation

    should

    be

    involved in the design process from

    early conceptual meetings

    through

    periodic design

    reviews to final design approval. In doing so, they

    have a voice in identifying the criteria against

    which a system

    should

    be validated and

    can

    offer

    observations

    and

    recommendations about design

    which

    might ultimately impact validation.

    VENDOR

    REQUIREMENTS

    There

    are many reasons that a

    validation

    team

    should

    participate in the design

    phase

    of a project.

    One

    is to identify the documentation that equip

    ment vendors must

    provide.

    Documentation

    should

    specify the following requirements and tol

    erances:

    Material certification (e.g., serial numbers

    for

    HEPA

    filters)

    Performance characteristics (e.g.,

    CFM

    for

    air flow

    on

    air handling units; air flow vs.

    static pressure for fans)

    TAB

    Pressure ratings (for ductwork and the

    distribution system)

    Factory performance testing of critical

    equipment

    Factory leak testing for cooling or heating

    coils

    I f contractors

    and equipment

    vendors are

    not

    told

    up front what they are required to provide, it's

    very difficult

    to

    get necessary information as a pro

    ject progresses. In many scenarios, specifications

    typically are written just for acquisition

    and

    instal

    lation of equipment. A better procedure one that

    will make

    the

    validation process more

    efficient is

    to require vendors to supply supporting documen-

    tation. Requirements also

    should

    be

    applied to

    any

    software that may

    be

    part of controls or building

    management

    systems.

    In addition to outlining documentation that ven

    dors must furnish, this is the time in the validation

    process to define responsibilities for delivery, instal

    lation, and start-up or commissioning. This proce

    dure encompasses activities such as starting air han

    dling unit motors, verifying correct fan rotation, and

    point-to-point verification

    of

    control loops.

  • 8/10/2019 Validation of HVAC Systems

    4/6

    Special Edition: Utilities Qualification 35

    INST LL TION QUALIFICATION

    The goal of IQ is to verify and document the quality,

    installation, and integrity of

    HV C

    system compo

    nents. Use design documents and literature provided

    by vendors to develop IQ protocols, which often

    take the form

    of

    inventories or checklists. Execution

    of

    IQ protocols provides assurance that an HV C sys

    tem

    is

    installed according to the manufacturer's rec

    ommendations

    and requirements for the specific

    facility being validated. (Note: Some readers may find

    that the requirements listed in the following discus

    sion are more typical of aseptic areas and may not

    be

    universal for all HV C systems.)

    A Description

    of

    Operation (System Description)

    identifies an HV C system, as well as the process

    es

    it

    supports and areas

    it

    serves.

    It

    should give a

    clear

    and

    concise description

    of

    the system

    in

    question, focusing

    on

    operational attributes of the

    system rather than

    technical specifications

    of

    equipment.

    In most

    cases,

    a one-paragraph

    description

    is

    sufficient, unless a system

    is unusu

    ally

    complex.) When appropriate and useful,

    include diagrams showing

    temperature and

    humidity control zones, room

    pressure

    relation

    ships, and other key information.

    It is important to avoid over specifying sys

    tem attributes. For example, a diagram with arrows

    to

    indicate room-to-room directional air flows may

    be more useful than a drawing showing numeric

    pressure relationships.

    Information

    provided in

    a Description of

    Operation should cover the following:

    Brief description

    of

    the system

    Identification of all the spaces served

    by

    the

    system

    Room temperature setpoints, including

    acceptable deviations )

    Room humidity setpoints, including accept

    able deviations )

    Minimum

    space

    air

    change

    requirements

    Space particulate classifications

    IQ documentation generally is

    broken

    down into

    the following major sections:

    Brian Scott, Jeff Hargroves,

    and

    Jerry Bauers

    Installation rawings

    Specifications List) -

    Documents as-built drawings

    and

    design specifica

    tions for an HV C system about to be qualified

    (validated). As-built

    drawings

    normally

    are sup

    plied by mechanical contractors. These drawings

    offer a record of system installation in its validated

    state,

    provided

    they reflect

    changes

    made

    to the

    system during validations.

    Document

    the

    sheet

    number, description, and

    latest revision date of each drawing. Compare the

    finished installation

    to

    as-built drawings to make

    sure

    that installation conforms to the drawings.

    Major discrepancies between as-built drawings and

    conditions found during validation should be

    marked

    on the drawings and reported to the

    appropriate personnel.

    Execution

    of

    IQ may

    be

    easier if an installation

    checklist is

    generated based

    on

    information

    in

    design drawings

    and

    specifications. This checklist

    should include all fans, fan motors, coils, and filters

    in the air handling unit. Zone reheat coils and ter

    minal HEP filters also may be incorporated.

    I f construction is

    complete

    before validation

    starts,

    some

    HV C devices may

    become

    concealed

    by insulation or architectural elements.

    In these

    cases, packing lists, purchase orders, or other doc

    umentation should provide evidence that installed

    equipment

    meets design requirements. The source

    of

    information

    used

    to verify acceptance should

    be

    noted in a protocol. In addition, duct leak tes

    reports may

    be referenced and attached as evi

    dence

    that ductwork has

    been

    installed in accor

    dance

    with industry

    standards e .g ., ASHRAE

    SM CN standards).

    Materials in Product Contact -

    Normally does no

    apply to

    most HV C systems. However, in a clean

    process environment where product or ingredient

    are exposed to air provided by an HV C system

    this

    evaluation must

    consider materials used in

    construction of the system that may become air

    borne and directly contact product. Because of the

    risk of contamination to the system, such materials

    should

    be appropriate

    and

    safe for

    product

    contac

    and non-particle shedding.

    In other

    words, con

    struction materials

    should not

    be reactive, addi

  • 8/10/2019 Validation of HVAC Systems

    5/6

    Special Edition: Utilities Qualification36

    Brian Scott Jeff Hargroves and Jerry Bauers

    tive, or absorptive

    so

    as to alter the safety, identity,

    strength, quality, or purity of the drug beyond the

    official or established

    requirements.

    (21

    FR

    211.94 - Drug

    product

    containers nd closures.

    IQ

    documentation may include

    materials in

    final filters, along with any devices downstream of

    them

    that serve

    an

    area in question. These materi

    als should meet industry-accepted

    standards

    for

    suitability in drug processing, packaging, labeling,

    or other

    activities taking place.

    Lubricants -

    Identifies lubricants used to maintain

    an

    HVAC system. This list may

    be

    as simple as fan

    bearing grease. A more detailed list would include

    lubricants provided with system components prior

    to installation, such as damper lubricants.

    Food

    or

    pharmaceutical grade lubricants should

    be

    used

    if there is potential for

    product

    contact

    (where equipment design permits possible product

    contamination by the lubricant). Consult a mainte

    nance supervisor or other maintenance personnel to

    ensure that all applicable lubricants are listed here.

    Utilities -

    Lists utilities critical

    to

    the operation

    of

    an HVAC

    system.

    All

    systems require

    supporting

    utilities to function properly. Include applicable

    design

    and

    actual data for utilities as follows:

    Electrical requirements and provisions for

    each

    HVAC utility (e.g., fan, pump, condens

    ing unit, etc.) -

    Document

    voltage, phase,

    full

    load

    amperage, and conductor size.

    Steam requirements (e.g., plant steam or clean

    steam, as applicable) for each steam coil or

    humidifier, including line size and steam

    pressure for each device - Steam flow (usually

    expressed in pounds per hour) is not easily

    measured and usually not included here.

    Hot and chilled water coil requirements,

    including supply temperature, pressure,

    and

    flow rate -

    f

    a TAB contractor has

    made adjustments to a system, reference

    the TAB report (submitted by a contractor

    certified by the National Environmental

    Balancing Bureau) for information provided

    in this section.

    Instrumentation Calibration -

    Ensures accurate con

    trol of critical operational parameters. List all calibrat

    ed instruments critical to system operation. Instrument

    calibration should be current at the time that IQ is

    performed. Document the dates that calibrations were

    executed and that recalibrations are due.

    In some cases, the only devices included in a

    routine calibration program

    are those

    used for

    closed-loop control or critical system alarms. For

    example,

    pressure

    gauges

    in chilled

    water

    lines

    entering and leaving a cooling coil may be consid

    ered non-Critical, but temperature sensors in spaces

    served by the cooling coil may

    be

    considered criti

    cal.

    f

    the

    temperature

    sensors

    are

    critical,

    they

    require routine calibration. If calibration data sheets

    are available, they may be attached to the protocol.

    Preventive Maintenance - Identifies procedures used

    to maintain an HVAC system in good operating condi

    tion. Preventive maintenance

    PM)

    also provides assur

    ance that a system will be kept in a validated state.

    List preventive

    maintenance numbers

    and

    effective dates.

    PM

    procedures for an HVAC sys

    tem

    may include

    inspection of filters, bearings,

    belts, gaskets, and

    any other

    moving parts, as well

    as parts with limited lifespans. Maintenance per

    sonnel normally write PM procedures.

    Spare Parts -

    Identifies filters, belts,

    or other

    items

    that will be replaced

    according

    to a regularly

    scheduled

    preventive maintenance

    program.

    During the life

    of

    a typical HVAC system, certain

    parts

    will need

    to be replaced

    as a

    result of

    expected wear

    and tear. Record the manufacturer

    and model

    number of

    each item. Spare parts

    should be identical or equivalent to original parts.

    A facility's maintenance department should keep

    these parts in stock.

    Special Procedures -

    Identifies special procedures,

    such as a controls system software walk-through

    and initial HEPA filter integrity testing. Certain pro

    cedures involved in HVAC system start-up should

    be

    documented

    as evidence

    of

    proper configura

    tion or performance of system elements. Some of

    this information

    may

    be useful for troubleshooting

  • 8/10/2019 Validation of HVAC Systems

    6/6

    Special Edition: Utilities Qualification 37

    A Must Have forComputer Validation

    www.ivthome.com

    PO Box 6004,Duluth, MN 55806

    218.740.7028 or 888.524.9922 U.S.OnlyFax: 218.740.6308

    Web Site: www.ivthome.comE-Mail: [email protected]

    Special Edition: Computer Validation IV

    Over 122 pages of computer-related issues, including:

    Proposed ValidationStandard VS-2 Computer-Related System Validation

    Thoughts on ComputerValidation Today

    Computer Validation: TheFive Ws andDeveloper/UserRelationships

    Guide to Documentationof Automated Systems

    Considerations forImproving SoftwareValidation

    Implementing a MedicalDevice Change Control Program forComputer Validation Documentation

    Implementing Requirements Analysis Strategies to Testand Ensure Quality Software

    Beyond Validation: The Competitive Advantages ofSoftware Process Excellence

    A Roadmap to Conducting Effective ComputerValidations

    Software/System Architecture Design as a Method to

    Simplify Validation Validation of Commercial-Off-the Self (COTS)

    Software

    Automation Qualification: A Managed and DocumentedApproach

    A History of Computer Validation Issues in ProductDevelopment

    RELATED PRODUCTS INCLUDE:

    Computer Validation II and III Computer Validation Videotapes Computer Validation Survival Kit

    A Must Have forComputer Validation

    INTERACTIVEWORKSHOPS&

    SESSIONS

    TakeAdvantageofour3%On-LineOrderDiscount