SAP Note 676123 - Project Information Database / ValueCategory Customizing
Note Language: English Version: 4 Validity: Valid Since 31.10.2003
Summary
Symptom
o You want to know more about the project information database, about
value categories and value category customizing.
o You want to know, why it is inevitable to maintain the value
category customizing correctly and completely.
o You do not know, why the value category customizing is necessary at
all.
o You want to know, what this customizing is for and why a support
consultant or developer has asked you to review/maintain your valuecategory customizing.
o You want to know which are the guiding priciples for value category
customizing.
More Terms
Project Information Database, CJEN, OPI1, OPI4, OPI5, RPSCO, RPSQT
Cause and Prerequisites
Solution
Project Information Database
The project information database - table RPSCO - is the value table
(no quantities!) that serves as common database for:
o Hierarchy Reports
o Structure Overview
o Progress Analysis (earned value)
o Project Planning Board.
It contains values from controlling (costs, revenues, commitment) and PS
cash management (expenses, receipts, cash commitment, planned payments
...).
For earned value analysis table RPSQT contains the necessary quantities.
The values in this table occur from statistical keyfigure records in
controlling.That way you can design hierarchy reports that are able to report on all
these values in one single report.
7/28/2019 Value Category Customization - Sapnote_0000676123
http://slidepdf.com/reader/full/value-category-customization-sapnote0000676123 2/4
14.07.2009 Page 2 of 4
SAP Note 676123 - Project Information Database / ValueCategory Customizing
For quantities in earned value analysis please use transaction CNE5 or in
releases 4.6* CNSE5. To enable hierarchy reports to deal with these values,
note 523330 must be implemented.
Not all values are updated to the project information database: Settlement
records to receivers other than WBS element, network, network activity or
project related order (with WBS element assignement) are not updated to the
project information database.
--> see also note 51971.
This is, because the values in the project information database are limited
to project values. Values that have left the project are not in focus
anymore.
Value category customizing
In the project information database the value category plays the role, that
cost elements, commitment items and statistical key figures have in the
controlling tables, report-writer reports / report painter reports and lineitem reports.
The value category customizing controls this re-keying process from the
controlling tables to the project information database. It is essential!
This customizing must be set up correctly and completely. Otherwiseyou will get unpredictably wrong values in the hierarchy reports,the structure overview, earned value analysis and in the project
planning board.
Please check now, if your customizing is complete and correct.
1. Please use transaction CJVC to check your value category customizing.
All red AND yellow lights shown there have to be eliminated by correcting and completing your value category customizing. In order to
do that, please review your customizing following these guidelines:
a) Each cost element/commitment item/stat. key figure HAS TO BE
ASSIGNED exactly once to a value category. Assigning them to more
or less than one value category will lead to unpredictable results.
b) This is nessessary EVEN, IF YOU NEVER WANT TO SEE those values. Inthat case you can block the update to table RPSCO. To block the
update please create an assignment line to a value category and
activate the 'suppress' indicator on the assignment detail screen.
c) Only
- Cost elements of the same cost element type
- Commitment items of the same item category and
- Statistical key figures of the same unit of measure and the same
key figure category
are allowed to be assigned to the same value category. Other and/or
mixed assignments will lead to unpredictable results like mixing
7/28/2019 Value Category Customization - Sapnote_0000676123
http://slidepdf.com/reader/full/value-category-customization-sapnote0000676123 3/4
14.07.2009 Page 3 of 4
SAP Note 676123 - Project Information Database / ValueCategory Customizing
costs and revenues in columns or rows!
d) When you create the value categories, that replace the cost
element/commitment item/statistical key figure in the project
information database, check for the correct setting of the radio
button:
COSTS: for value categories meant to be used for cost elements of
type 1 ('costs'); for value categories meant to be used for
commitment items for expenses
REVENUES: for value categories meant to be used for cost elements
of type 11 or 12 ('revenues'); for value categories meant to be
used for commitment items for receipts.
If you want to assign STATISTICAL KEY FIGURES to the value
category, you indicate, whether the value category should contain
key figures with totals values characteristic or fixed values
characteristic.
These settings are valid for all cost elements/commitment
items/statistical key figures you assign to the value category.
2. If all red and yellow lights in transaction CJVC are eliminated,
please rebuild the Project Information Database (table RPSCO) by
transaction CJEN. Without this, changes carried out in your value
category customizing won't have any effect. That is necessary after
all changes in value category customizing, that affect values already
posted. Running CJEN is not dangerous.
3. Please rebuild the assigned values using transaction CJBN afterwards,
if you use budgeting.
4. Performance tip:
You can create more than one assignement line for one value category.
This is possible, because the assignment lines do not only contain the
controlling area and the value category but also a counter (1-999).
If you assign cost elements or cost element intervals to the value
category instead of cost element groups, you save the time, that
otherwise would be consumed for the explosion of the cost elementgroup.
For being able to do that easily, please consider the following:
Please use allways the same number of digits for all cost elements and
revenue elements - to have a reserve eventually 1 or two digits more
than you initially need. The field for cost element is an alphanumeric
field and is lexically sorted. If you do not do it that way, you will
have problems defining intervals. So please use the same number of
digits for all cost elements. The same is for commitment items and
statistical key figures.
This setup should be checked regularly to make sure, that all valuesare updated to the project information database in the correct way!
7/28/2019 Value Category Customization - Sapnote_0000676123
http://slidepdf.com/reader/full/value-category-customization-sapnote0000676123 4/4
14.07.2009 Page 4 of 4
SAP Note 676123 - Project Information Database / ValueCategory Customizing
There should be a special focus on newly created cost elements /commitment items / statistical key figures.
Header Data
Release Status: Released for Customer
Released on: 31.10.2003 14:39:00
Original Lang.: English
Priority: Recommendations/additional info
Category: Consulting
Main Component: PS-IS-ACC-HIE Hierarchy Reports
Additional Components:
PS-PRG Progress
PS-PRG-EVA Progress Analysis
CO-OM-OPA-C Budgeting
PS Project SystemPS-IS Information System
PS-IS-ACC Accounting
PS-IS-LOG Logistics
PS-ST-PPB Project Planning Board
PS-IS-LOG-STR Structure overview
The Note is release-independent
Related Notes
Number Short Text
668240 FAQ 2: Hierarchy reports
523330 PS-IS: Quantities in hierarchy reports
51971 Hierarchy reports: Displaying actual costs after settlement