![Page 1: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/1.jpg)
! Introduction to mapping
! Creating a Current State Map
! Introduction To Lean Techniques
! Creating a Future State Map
! Using a Map as a basis for Tactical Implementation Planning
AGENDA
Value Stream Mapping
![Page 2: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/2.jpg)
1. What are the customer requirements
2. How to apply Continuous Flow Processing
3. Which process is the pacemaker
4. How to control upstream processes
5. What size supermarkets (shop stock) are required
6. Is it sequential or fill-up pull
7. Where to level production
8. At what frequency will kanban be released
9. What further improvements can be made
THE 9 KEY QUESTIONS :
Future State Value Stream Mapping
![Page 3: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/3.jpg)
THE 7 STEPS
1. Customer Requirements
2. Draw Process Steps
3. Process Data
4. Inventory
5. Material Flow: Supplier to Manufacturer & Manufacturer to Customer
6. Information Driving Flow & Internal Material Flow
7. Manufacturing Lead Time & Processing Time
Creating a Future State Value Stream Map
![Page 4: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/4.jpg)
Ref.ppt
FIFO
abcProduction Control
I
OXOX 44
4
SupermarketSupermarketwith Prod Card
Supermarket with Prod Card & Withdrawal card
First In First Out sequence flow Kanban Post
Inventory
Pull Symbol
Information System VSM Symbols
Production Control
Electronic information flow Level loading Production
Signal KanbanMin & Max
Manual Information flow
Kaizen lightening burst
Truck Shipment
Mon + Wed
PUSH arrow
300 pieces 1Day
CHANGEOVER
XYZ corporation
Outside sources
Sequenced-Pull Ball
Icons for use in Future State
![Page 5: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/5.jpg)
Go to white board and change Go to white board and change current state to future state.current state to future state.
Ask the delegates to draw it with Ask the delegates to draw it with youyou
![Page 6: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/6.jpg)
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping Assembly # 2Assembly # 1Spot weld # 2Spot weld # 1Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
Cycle time= 39 minute
Change over=10 min.
Uptime =100%
1 x
10 T
Cycle time= 46 minute
Change over=10 min.
Uptime =80%
1 x
Cycle time= 62 minute
Change over=0 min.
Uptime =100%
1 x
Cycle time= 40 minute
Change over=0 min.
Uptime =100%
1 x
II I I5 days 150 A1
24 A2
I I42 A16 A2
16 A118 A2
42 A16 A2
27 A114 A2
Coils r us
500 ft coils
Tuesdayand
Thursday
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
Weekly fax
MRP
Weekly plan
Dailyshipping
plan
16 pieces/ day
10.9 days 2.1 days 3 days 2.6 days5 days
Production Lead Time = 26.6 days
Processing time = 188 mins
1 minute 39 minute 46 minute 62 minute 40 minute3 days
Current State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 7: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/7.jpg)
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping Assembly # 1Assembly # 2Spot weld # 2Spot weld # 2Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
Cycle time= 39 minute
Change over=10 min.
Uptime =100%
1 x
10 T
Cycle time= 46 minute
Change over=10 min.
Uptime =80%
1 x
Cycle time= 62 minute
Change over=0 min.
Uptime =100%
1 x
Cycle time= 40 minute
Change over=0 min.
Uptime =100%
1 x
II I I5 days 150 A1
24 A2
I I42 A16 A2
16 A18 A2
42 A16 A2
27 A114 A2
500 ft coils
Tuesdayand
Thursday
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
Weekly fax
MRP
Weekly plan
Dailyshipping
plan
16 pieces/ day
10.9 days 3 days 2.1 days 3 days 2.6 days5 days
Production Lead Time = 26.6 days
Processing time = 188 mins
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
x
1 minute 39 minute 46 minute 62 minute 40 minute
Coils r us
Add Takt Calculation
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 8: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/8.jpg)
Stamp SW 1 SW 2 Assy. 1 Assy. 2
1 min.
39 min.
46 min.
62 min.
40 min.
57.5 min.Takt
! DRAW ON FLIP CHART
Where is Continuous Flow Possible?
![Page 9: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/9.jpg)
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping Assembly # 1Assembly # 2Spot weld # 2Spot weld # 2Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
Cycle time= 39 minute
Change over=10 min.
Uptime =100%
1 x
10 T
Cycle time= 46 minute
Change over=10 min.
Uptime =80%
1 x
Cycle time= 62 minute
Change over=0 min.
Uptime =100%
1 x
Cycle time= 40 minute
Change over=0 min.
Uptime =100%
1 x
II I I5 days 150 A1
24 A2
I I200 A16 A2
16 A18 A2
42 A16 A2
27 A114 A2
500 ft coils
Tuesdayand
Thursday
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
Weekly fax
MRP
Weekly plan
Dailyshipping
plan
16 pieces/ day
10.9 days 3 days 2.1 days 3 days 2.6 days5 days
Production Lead Time = 26.6 days
Processing time = 188 mins
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
Coils r us
Drawing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 10: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/10.jpg)
Stamp SW 1 SW 2 Assy. 1 Assy. 2
1 min.
39 min.
46 min.
62 min.
40 min.
! DRAW ON FLIP CHART
57.5 min.Takt
Where is Continuous Flow Possible?
![Page 11: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/11.jpg)
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping Assembly # 1Assembly # 2Spot weld # 2Spot weld # 2Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
Cycle time= 39 minute
Change over=10 min.
Uptime =100%
1 x
10 T
Cycle time= 46 minute
Change over=10 min.
Uptime =80%
1 x
Cycle time= 62 minute
Change over=0 min.
Uptime =100%
1 x
Cycle time= 40 minute
Change over=0 min.
Uptime =100%
1 x
II I I5 days 150 A1
24 A2
I I200 A16 A2
16 A18 A2
42 A16 A2
27 A114 A2
500 ft coils
Tuesdayand
Thursday
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
Weekly fax
MRP
Weekly plan
Dailyshipping
plan
16 pieces/ day
10.9 days 3 days 2.1 days 3 days 2.6 days5 days
Production Lead Time = 26.6 days
Processing time = 188 mins
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
Coils r us
Drawing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 12: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/12.jpg)
Stamp SW 1 SW 2 Assy. 1 Assy. 2
1 min.
39 min.46 min.
62 min.
40 min.
! DRAW ON FLIP CHART
57.5 min.Takt
Where is Continuous Flow Possible?
![Page 13: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/13.jpg)
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping Assembly # 1Assembly # 2Spot weld # 2Spot weld # 2Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
Cycle time= 39 minute
Change over=10 min.
Uptime =100%
1 x
10 T
Cycle time= 46 minute
Change over=10 min.
Uptime =80%
1 x
Cycle time= 62 minute
Change over=0 min.
Uptime =100%
1 x
Cycle time= 40 minute
Change over=0 min.
Uptime =100%
1 x
II I I5 days 150 A1
24 A2
I I200 A16 A2
16 A18 A2
42 A16 A2
27 A114 A2
500 ft coils
Tuesdayand
Thursday
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
Weekly fax
MRP
Weekly plan
Dailyshipping
plan
16 pieces/ day
10.9 days 3 days 2.1 days 3 days 2.6 days5 days
Production Lead Time = 26.6 days
Processing time = 188 mins
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
Coils r us
Drawing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 14: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/14.jpg)
x
Ideal No. Of Operators = Total Work ContentTakt Time
e.g.
Ideal No. Of Operators = 187 minutes of work57.5 minutes Takt
= 3.25 operators
= 4
= target of 3
Where is Continuous Flow Possible?
![Page 15: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/15.jpg)
55 55 55
(55 X 3) + 22 = 187 minutes
! DRAW ON FLIP CHART
Takt
Cycle Time
Stamp
1 min.SW 1
SW 2
Assy. 1Assy. 2
39 min.
SW 2
30 min.
16 min.
25 min.
Assy. 1
37 min.
18 min.
Assy. 2
22 min.
57.5 min.Takt
Where is Continuous Flow Possible?
![Page 16: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/16.jpg)
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping Assembly # 1Assembly # 2Spot weld # 2Spot weld # 2Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
Cycle time= 39 minute
Change over=10 min.
Uptime =100%
1 x
10 T
Cycle time= 46 minute
Change over=10 min.
Uptime =80%
1 x
Cycle time= 62 minute
Change over=0 min.
Uptime =100%
1 x
Cycle time= 40 minute
Change over=0 min.
Uptime =100%
1 x
II I I5 days 150 A1
24 A2
I I200 A16 A2
16 A18 A2
42 A16 A2
27 A114 A2
500 ft coils
Tuesdayand
Thursday
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
Weekly fax
MRP
Weekly plan
Dailyshipping
plan
16 pieces/ day
10.9 days 3 days 2.1 days 3 days 2.6 days5 days
Production Lead Time = 26.6 days
Processing time = 188 mins
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
Coils r us
Drawing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 17: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/17.jpg)
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
10 T
TT= 60 minute
C/T=55 min
4 x
I5 days
500 ft coils
Tuesdayand
Thursday
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
Weekly fax
MRP
Weekly plan
Dailyshipping
plan
16 pieces/ day
Work contentTo 55 min.
SW C/OSW 2uptime
2 days
Weld+ assy.
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
Target 3 Ops
Coils r us
Drawing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 18: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/18.jpg)
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
10 T
TT= 60 minute
C/T=55 min
4 x
I5 days
500 ft coils
Tuesdayand
Thursday
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
Weekly fax
MRP
Weekly plan
Dailyshipping
plan
16 pieces/ day
Work contentTo 55 min.
SW C/OSW 2uptime
2 days
1
Weld+ assy.
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
Target 3 Ops
Coils r us
Drawing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 19: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/19.jpg)
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
10 T
TT= 60 minute
C/T=55 min
4 x
I5 days
500 ft coils
Tuesdayand
Thursday
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
Weekly fax
MRP
Weekly plan
Dailyshipping
plan
16 pieces/ day
Work contentTo 55 min.
SW C/OSW 2uptime
2 days
1
1
Weld+ assy.
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
Target 3 Ops
Drawing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 20: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/20.jpg)
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
10 T
TT= 60 minute
C/T=55 min
4 x
I5 days
500 ft coils
Tuesdayand
Thursday
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
Weekly fax
MRP
Weekly plan
Dailyshipping
plan
16 pieces/ day
Work contentTo 55 min.
SW C/OSW 2uptime
2 days
1batch
Weld+ assy.
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
Target 3 Ops
Coils r us
Drawing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 21: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/21.jpg)
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
10 T
TT= 60 minute
C/T=55 min
4 x
I5 days
500 ft coils
Tuesdayand
Thursday
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
Weekly fax
MRP
Weekly plan
Dailyshipping
plan
16 pieces/ day
Work contentTo 55 min.
SW C/OSW 2uptime
2 days
1batch
1.5 daysdelivery trays
Weld+ assy.
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
Target 3 Ops
Coils r us
Drawing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 22: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/22.jpg)
11
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping
Weld+ assy.
Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
10 T
TT= 60 minute
C/T=55 min
4 x
I5 days
500 ft coils
Tuesdayand
Thursday
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
Weekly fax
MRP
Weekly plan
DailyShipping plan
16 pieces/ day
Work contentTo 55 min.
SW C/OSW 2uptime
2 days
1batch
1.5 days
1
stagedelivery trays
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
Target 3 Ops
Coils r us
Drawing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 23: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/23.jpg)
11
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping
Weld+ assy.
Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
10 T
TT= 60 minute
C/T=55 min
4 x
I5 days
500 ft coils
Tuesdayand
Thursday
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
Weekly fax
MRP
Weekly plan
DailyShipping plan
16 pieces/ day
Work contentTo 55 min.
SW C/OSW 2uptime
2 days
1batch
1.5 days
1
stage
OOXXOOXX
Pitch = 57.5 mins
delivery trays
1
2
34
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
Target 3 Ops
Coils r us
Drawing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 24: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/24.jpg)
11
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping
Weld+ assy.
Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
10 T
TT= 60 minute
C/T=55 min
4 x
500 ft coils
Daily
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
MRP
Weekly plan
DailyShipping plan
16 pieces/ day
Work contentTo 55 min.
SW C/OSW 2uptime
2 days
1batch
1.5 days
1
stage
OOXXOOXX
Pitch = 57.5mins
1.5days
delivery trays
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
Target 3 Ops
Coils r us
Drawing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 25: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/25.jpg)
11
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping
Weld+ assy.
Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
10 T
TT= 60 minute
C/T=55 min
4 x
500 ft coils
Daily
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
MRP
DailyShipping plan
16 pieces/ day
Work contentTo 55 min.
SW C/OSW 2uptime
2 days
1batch
1.5 days
1
stage
OOXXOOXX
1.5days
1.5days 1 min
1.5 days165 min
2 days
5 days
166 minutes
delivery trays
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins Pitch = 57.5 mins
Target 3 Ops
Coils r us
Drawing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 26: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/26.jpg)
Delegates to design own future state map
Value Stream Mapping
![Page 27: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/27.jpg)
Current State Map
Future State Map
GapAnalysis……………...
WHERE WILL YOU START ?
Developing an Improvement Plan
![Page 28: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/28.jpg)
11
F.A.L.
.
Pack size = 1
320 pieces/ month•200 A1•120 A2
2 shifts
Shipping
Weld+ assy.
Stamping
Cycle time= 1 minute
Change over=1 hour
Uptime =85%
1 x
10 T
TT= 60 minute
C/T=55 min
3 x
F.A.L.
500 ft coils
Daily
Production Planning30/ 60/ 90 day forecast
Daily expedite
6 week forecast
MRP
DailyShipping plan
16 pieces/ day
Work contentTo 55 min.
SW C/OSW 2uptime
2 days
1batch
1.5 days
1
stage
OOXXOOXX
1.5days
1.5days 1 min
1.5 days165 min
2 days
5 days
166 minutes
Supplier loop
Stampingloop
Pacemaker loopdelivery trays
Takt = 2(480-20)minutes = 57.5 mins16 pieces
Pitch = 57.5 mins x 1 pieces = 57.5 mins
Pitch = 57.5 mins
Target 3 Ops
Dividing a Future State Map
Slug Brackets StampingCurrents State Map Date :
1 x Daily
![Page 29: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/29.jpg)
! Introduction to mapping
! Creating a Current State Map
! Practical Exercise
! Introduction To Lean Techniques
! Creating a Future State Map
! Using a Map as a basis for Tactical Implementation Planning
AGENDA
Value Stream Mapping
![Page 30: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/30.jpg)
To set theteam
direction
To show a relevant level of detail to those concerned -NB. each loop will have it’s own execution schedules
within the implementation plan
To encourage regular reviews for signs of QCD problems -slippage's, early deliveries, continued ownership
To formalise commitment from key people:Facility Manager Value stream managerThe Unions Manufacturing EngineeringMaintenance Process Engineering
Purchasing
The key elements of a Value Stream’s Implementation planare shown in the following example.
Why Have a Formal Plan to Achieve the future State?
![Page 31: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/31.jpg)
Example - Tactical Implementation Plan (T.I.P.)
TIPOwner
5C Activity
Category
Level 1 Activity
Level 2DetailedActions
TimebasedSchedule of
activities
Type of TIPand Model Line
Responsible People
![Page 32: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/32.jpg)
! Collect data across a value stream.
! Use the 7 steps to draw a current state Value Stream Map.
! Use the 9 questions and 7 steps to draw a future state Value Stream Map.
! Identify your Material/Information loops.
! Decide the order to tackle the loops.
! Write the Tactical Implementation Plan• Set objectives for each loop as required to achieve the future state• Set measurable goals for each objective• Use the 9 questions within each loop to set an order of work• Set milestones and write up the plan• Get formal agreement from all concerned
! The leader of each work stream should produce their own execution schedule showing how to achieve each goal by it’s milestone.
Summary
![Page 33: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/33.jpg)
! Introduction to mapping
! Creating a Current State Map
! Practical Exercise
! Introduction To Lean Techniques
! Creating a Future State Map
! Using a Map as a basis for Tactical Implementation Planning
AGENDA
Value Stream Mapping
![Page 34: Value Stream Mapping - Beyond · PDF fileRef.ppt FIFO abc Production Control I OXOX 4 4 4 Supermarket Supermarket with Prod Card Supermarket with Prod Card & Withdrawal card First](https://reader036.vdocument.in/reader036/viewer/2022082217/5a7a7dcb7f8b9abd768bffb5/html5/thumbnails/34.jpg)
Summary
Just do it !Just do it !