valutaiton of the leveraged firm
TRANSCRIPT
18-0
Valuation and Capital Budgeting for the Levered firm(Chapter 18)
18-1
Key Concepts and Skills
Understand the effects of leverage on the value created by a project
Be able to apply Adjusted Present Value (APV), the Flows to Equity (FTE) approach, and the WACC method for valuing projects with leverage
18-2
Adjusted Present Value Approach
APV = NPV + NPVF The value of a project to the firm can be
thought of as the value of the project to an unlevered firm (NPV) plus the present value of the financing side effects (NPVF).
There are four side effects of financing:◦ The Tax Subsidy to Debt
◦ The Costs of Issuing New Securities
◦ The Costs of Financial Distress
◦ Subsidies to Debt Financing
18-3
APV Example
0 1 2 3 4
–$1,000 $125 $250 $375 $500
50.56$
)10.1(
500$
)10.1(
375$
)10.1(
250$
)10.1(
125$000,1$
%10
432%10
−=
++++−=
NPV
NPV
The unlevered cost of equity is R0 = 10%:
The project would be rejected by an all-equity firm: NPV < 0.
Consider a project of the Pearson Company. The timing and size of the incremental after-tax cash flows for an all-equity firm are:
18-4
APV Example Now, imagine that the firm finances the project with
$600 of debt at RB = 8%. Pearson’s tax rate is 40%, so they have an interest
tax shield worth TCBRB = .40
18-5
Flow to Equity Approach Discount the cash flow from the project to
the equity holders of the levered firm at the cost of levered equity capital, RS.
There are three steps in the FTE Approach:◦ Step One: Calculate the levered cash flows
(LCFs)◦ Step Two: Calculate RS.◦ Step Three: Value the levered cash flows at
RS.
18-6
Step One: Levered Cash Flows
Since the firm is using $600 of debt, the equity holders only have to provide $400 of the initial $1,000 investment.
Thus, CF0 = –$400
Each period, the equity holders must pay interest expense. The after-tax cost of the interest is:
B
18-7
Step One: Levered Cash Flows
–$400 $221.20
CF2 = $250 – 28.80
$346.20
CF3 = $375 – 28.80
–$128.80
CF4 = $500 – 28.80 – 600
CF1 = $125 – 28.80
$96.20
0 1 2 3 4
18-8
Step Two: Calculate RS
))(1( 00 BCS RRTS
BRR −−+=
∑=
++++=4
1432 )08.1(
20.19
)10.1(
500$
)10.1(
375$
)10.1(
250$
)10.1(
125$
tt
PV
B = $600 when V = $1,007.09 so S = $407.09.
%77.11)08.10)(.40.1(09.407$
600$10. =−−+=SR
P V = $943.50 + $63.59 = $1,007.09
BS
BV
To calculate the debt to equity ratio, , start with
Note: This assumes we know the value created by the project. A more straightforward assumption is to assume that the ratio is 600/400, based on the amount provided by each source to fund the project. With these values, RS=11.80%.
18-9
Step Three: Valuation
Discount the cash flows to equity holders at RS = 11.77%
56.28$
)1177.1(
80.128$
)1177.1(
20.346$
)1177.1(
20.221$
)1177.1(
20.96$400$
432
=
−+++−=
NPV
NPV
0 1 2 3 4
–$400 $96.20 $221.20 $346.20 –$128.80
Note that the chapter examples work out nicely with the perpetuity assumption, in that each approach provides the same value. With a finite life project, the values will deviate based on assumptions made, for example, the repayment of the $600.
18-10
WACC Method
To find the value of the project, discount the unlevered cash flows at the weighted average cost of capital.
Suppose Pearson’s target debt to equity ratio is 1.50
)1( CBSW ACC TRBS
BR
BS
SR −
++
+=
18-11
WACC Method
%58.7
)40.1(%)8()60.0(%)77.11()40.0(
=−××+×=
W ACC
W ACC
R
R
S
B=50.1 BS =∴ 5.1
60.05.2
5.1
5.1
5.1==
+=
+ SS
S
BS
B40.060.01 =−=
+ BS
S
Note, when calculating B/S, we are using the target ratio, not the market value which is different from FTE approach
18-12
WACC Method
To find the value of the project, discount the unlevered cash flows at the weighted average cost of capital
432 )0758.1(
500$
)0758.1(
375$
)0758.1(
250$
)0758.1(
125$000,1$ ++++−=NPV
NPV7.58% = $6.68
18-13
A Comparison of the APV, FTE, andWACC Approaches
All three approaches attempt the same task: valuation in the presence of debt financing.
Guidelines:◦ Use WACC or FTE if the firm’s target debt-to-value
ratio applies to the project over the life of the project.◦ Use the APV if the project’s level of debt is known over
the life of the project.
In the real world, the WACC is, by far, the most widely used.
18-14
Summary: APV, FTE, and WACCAPV WACC FTE
Initial Investment All All Equity Portion
Cash Flows UCF UCF LCF
Discount Rates R0 RWACC RS
PV of financing effects Yes No No
18-15
Summary: APV, FTE, and WACC
Which approach is best? Use APV when the level of debt is
constant Use WACC and FTE when the debt ratio
is constant◦ WACC is by far the most common
◦ FTE is a reasonable choice for a highly levered firm
18-16
Capital Budgeting When the Discount Rate Must Be Estimated
A scale-enhancing project is one where the project is similar to those of the existing firm.
A scale-enhancing project does not diversify the company's risk in any way. However, it may be beneficial, as the project is likely within the company's core competence.
In the real world, executives would make the assumption that the business risk of the non-scale-enhancing project would be about equal to the business risk of firms already in the business.
No exact formula exists for this. Some executives might select a discount rate slightly higher on the assumption that the new project is somewhat riskier since it is a new entrant.
18-17
Beta and Leverage
Recall that an asset beta would be of the form:
2Market
Asset •
),(•
MarketUCFCov=
18-18
Beta and Leverage: No Corporate Taxes In a world without corporate taxes, and with
corporate debt ( ), it can be shown that the relationship between the beta of the unlevered firm and the beta of levered equity is:
EquityAsset •Asset
Equity• ×=
• In a world without corporate taxes, and with corporate debt, it can be shown that the relationship between the beta of the unlevered firm and the beta of levered equity is:
EquityDebtAsset •Asset
Equity•
Asset
Debt• ×+×=
0debtβ =
18-19
Beta and Leverage: With Corporate Taxes
In a world with corporate taxes, and riskless debt, it can be shown that the relationship between the beta of the unlevered firm and the beta of levered equity is:
firm UnleveredEquity •)1(Equity
Debt1•
−×+= CT
• Since must be more than 1 for a
levered firm, it follows that βEquity > βUnlevered firm
−×+ )1(
Equity
Debt1 CT
18-20
Beta and Leverage: With Corporate Taxes If the beta of the debt is non-zero, then:
LC S
BT ×−−+= )••)(1(•• Debtfirm Unleveredfirm UnleveredEquity
18-21
Summary
1. The APV formula can be written as:
2. The FTE formula can be written as:
3. The WACC formula can be written as
investment
Initial
debt
of effects
Additional
)1(1 0
−++
=∑∞
=tt
t
R
UCFAPV
−−
+=∑
∞
= borrowed
Amount
investment
Initial
)1(1tt
S
t
R
LCFFTE
investment
Initial
)1(1
−+
=∑∞
=tt
W ACC
tW ACC R
UCFNPV
18-22
Summary
4 Use the WACC or FTE if the firm's target debt to value ratio applies to the project over its life.• WACC is the most commonly used by far.
• FTE has appeal for a firm deeply in debt.
5 The APV method is used if the level of debt is known over the project’s life.• The APV method is frequently used for special
situations like interest subsidies, LBOs, and leases.
6 The beta of the equity of the firm is positively related to the leverage of the firm.
18-23
Suggested Problems
5, 9, 13