variable generation subcommittee paul arnold and michelle mizumori northwest wind integration forum...
TRANSCRIPT
Variable Generation Subcommittee
Paul Arnold and Michelle MizumoriNorthwest Wind Integration Forum
Technical Work Group
October 29, 2009
Topics
● Background● VGS Background and Work Groups
Activity Update● Relationship to NW Wind Integration
Action Plan Issues and Activities● Next Steps
Background—VGS Reporting and Staffing● VGS Reports to the Joint Guidance Committee● VGS Staffing includes:
Scott Gutting – Chair Leonard Dorr – Vice-Chair Paul Arnold – MWG Chair Bart McManus/Grant Rosenblum – OWG Chairs Ross Guttromson – PWG Chair Leonard Dorr – TWG Chair Michelle Mizumori – WECC Staff
Background—VGS Purpose
● Identify issues associated with variable generation integration, facilitate and implement solutions that add distinct value to WECC members
● Focus is on the regional operations and planning reliability, effective markets, and new technology
● Be a source of information, analysis, and coordination
Background- VGS Activities
● VG issued a survey in December 2008● Kickoff call January 15● Applied for and received DOE Grant● Work Plan presented and approved August 11● Work Groups —next meeting is November 16-18
in Salt Lake City● VGS – next meeting is December 1 in Phoenix
Marketing Workgroup Update
● Chair – Paul Arnold (ColumbiaGrid)● Workplan Activities
Markets for Ancillary Services Product Codes used in scheduling VG Effect of REC market on VG development,
marketing, reliability
NAESB activities
6
Operating Workgroup Update
● Chairs - Bart McManus (BPA)and Grant Rosenblum (CAISO)
● Workplan Activities Assess methodologies for determining reserve
requirements Inventory VG performance standards Investigate mechanisms for better utilizing resource
flexibility Inventory forecasting practices Quantify the benefits of BA cooperation
7
Planning Workgroup Update
● Chair – Ross Guttromson (PNNL)● Workplan Activities
Participate in variable generator model validation Review the NERC IVGTF report and participate in relevant
NERC activities Investigate transmission capacity assignment for VG resources Inventory best practices and provide recommendations to aid in
the standardizing and validating of planning criteria and methodologies and interconnection standards
Provide input to transmission adequacy analyses for accommodating the integration of VG
Create a centralized database for VG information Develop a VG-heavy case for TSS and SRWG to use in
analyzing dynamics related issues8
Technology Workgroup Update
● Chair – Len Dorr (First Solar)● Draft Workplan Activities
Investigate performance requirements for VG technologies
Evaluate the impact of technology cost changes on resource allocation and transmission planning
Identify complementary technologies to aid in the integration of VG- Storage- Inverters- Communications and Measurement- Smart Grid
9
Current State of WECC VGS Effort
● Task Teams are being formed and assignments have been made to address issues and activities
● If you are interested, now is a good time to get involved Anyone can join a work group
Current State of WECC VGS Effort
● WECC Study VGS Chairs, NREL and PNNL are scoping a study to
evaluate benefits of Balancing Area cooperation techniques that capture flexibility and diversity of existing resources and loads over a wider geographic area
Similar to an expanded Western Wind and Solar Integration Study effort
Further discussion at December 1 VGS Meeting
Relationship to NW Wind Integration Action Plan—Action 13
● Action 13 of the Wind Integration Action Plan Address the transmission scheduling, product
design, demand management, regulatory, contractual and cost recovery barriers to expanding the market for flexible products and services
Relationship to NW Wind Integration Action Plan-Expanded Markets for flexibility
Leverage daily and seasonal differences in system flexibility among the regions utilities
WECC-wide study will address this Through Dynamic Scheduling, allow two or
more utilities to exchange the balancing requirements for a portion of the wind in their different systems
WECC-wide study will address this
Relationship to NW Wind Integration Action Plan—Expanded Markets for flexibility
Allow independent power producers to generate additional income by monetizing the flexibility characteristics of their assets
MWG will address in white paper Create price signals for innovative demand
management strategies MWG will address in white paper
Relationship to NW Wind Integration Action Plan—Expanded Markets for flexibility
Access some of the benefits of shorter term markets without fundamental changes to Northwest market structure
MWG will address in white paper, but from larger WECC perspective
Relationship to NW Wind Integration Action Plan—WECC is starting to address markets
● MWG has an action item to develop white paper on Markets
● MIC/SIS has started discussions on a congestion management and will be making a presentation to the WECC Board in December
Next Steps
● Next meetings Work Groups – November 16-18--Salt Lake VGS – December 1--Phoenix
Questions
Michelle MizumoriManaging Director of Operations and Market Interface(360) [email protected]
Paul ArnoldVice President- ColumbiaGrid(503) [email protected]