Page 1: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

1 © The Delos Partnership 2004 Vas SCT Model

Supply Chain TechniquesSupply Chain Techniques

Choices to be made when deciding how to plan

Page 2: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

2 © The Delos Partnership 2004 Vas SCT Model

Customer Relationship Customer Relationship StrategyStrategy

Design

Purchase

Intermediate Manufacture

Sub-assemble

Finish

Distribute

WhereDo you meetTheCustomer ?

StockTo Order

Page 3: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

3 © The Delos Partnership 2004 Vas SCT Model

Periods 1 2 3 4 5 6 7 8 9 10 11 12

Forecast 25 25 25 25 25 25 25 25 20 20 20 20

Actual Demand

Proj Avail Balance

75 50 25 0 50 25 0 50 30 10 65 45

Available to Promise

CumulativeATP

Master Schedule

75 75 75

Item Level ForecastItem Level Forecast

Part Number: 12345 Lead Time: 2 periods Safety Stock: 0 Min Ord Qty: 75 On Hand: 100

Part Number: 12345 Lead Time: 2 periods Safety Stock: 0 Min Ord Qty: 75 On Hand: 100

Page 4: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

4 © The Delos Partnership 2004 Vas SCT Model

Customer Relationship Customer Relationship StrategyStrategy

Design

Purchase

Intermediate Manufacture

Sub-assemble

Finish

Distribute

WhereDo you meetTheCustomer ?

StockTo Order

Assemble to Order

Page 5: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

5 © The Delos Partnership 2004 Vas SCT Model

Product VariantsProduct Variants

Blue PenPart Number 12346

Blue PenPart Number 12346

Red PenPart Number 12345

Red PenPart Number 12345

Black PenPart Number 12347

Black PenPart Number 12347

Green PenPart Number 12348

Green PenPart Number 12348

Variant Forecast Actual

Blue 40 50

Red 60 70

Black 30 20

Pen 70 60

Total 200 200

How manyNibs

And

How manyCaps and barrelsNeeded ?

How manyNibs

And

How manyCaps and barrelsNeeded ?

Page 6: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

6 © The Delos Partnership 2004 Vas SCT Model

Planning FamilyPlanning Family

Blue OptionPart Number 12346

Blue OptionPart Number 12346

Red OptionPart Number 12345

Red OptionPart Number 12345

Black OptionPart Number 12347

Black OptionPart Number 12347

Green OptionPart Number 12348

Green OptionPart Number 12348

Common Parts46783

Common Parts46783

Pen Family43785

Pen Family43785

20 % = 0.2

30 % = 0.3

15 % = 0.15

35 % = 0.35

Forecast = 200/mth

100 % = 1.0

Page 7: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

7 © The Delos Partnership 2004 Vas SCT Model

Periods 1 2 3 4 5 6 7 8 9 10 11 12

Forecast 0 20 40 50 50 50

Actual Demand 50 30 10

Proj Avail Balance

0 0 0 0 0 0 0 0 0 0 0 0

Available to Promise

0 20 40 50 50 50

Master Schedule

50 50 50 50 50 50

Periods 1 2 3 4 5 6 7 8 9 10 11 12

DependentForecast

0 4 8 10 10 10

Actual Demand 11 7 1

Proj Avail Balance

0

Available to Promise

0 10 10 10

Master Schedule

11 10 10 10

Blue OptionPart Number 12346

Blue OptionPart Number 12346

20 %

Page 8: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

8 © The Delos Partnership 2004 Vas SCT Model

Periods 1 2 3 4 5 6 7 8 9 10 11 12

Forecast 0 20 40 50 50 50

Actual Demand 50 30 10

Proj Avail Balance

0 0 0 0 0 0 0 0 0 0 0 0

Available to Promise

0 20 40 50 50 50

Master Schedule

50 50 50 50 50 50

Periods 1 2 3 4 5 6 7 8 9 10 11 12

DependentForecast

0 4 8 10 10 10

Actual Demand 11 7 1

Proj Avail Balance

0 0 2 2 4 4 4 4 4 4 4 4

Available to Promise

0 6 10 10 10 10

Master Schedule

11 13 11 10 10 10

Blue OptionPart Number 12346

Blue OptionPart Number 12346

20 %

Overplan

Page 9: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

9 © The Delos Partnership 2004 Vas SCT Model

Planning FamilyPlanning Family

Blue OptionPart Number 12346

Blue OptionPart Number 12346

Red OptionPart Number 12345

Red OptionPart Number 12345

Black OptionPart Number 12347

Black OptionPart Number 12347

Green OptionPart Number 12348

Green OptionPart Number 12348

Common Parts46783

Common Parts46783

Pen Family43785

Pen Family43785

20 % = 0.2

30 % = 0.3

15 % = 0.15

35 % = 0.35

Forecast = 200/mth

100 % = 1.0

I

N

V

E

N

S

T

M

E

N

T

Page 10: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

10 © The Delos Partnership 2004 Vas SCT Model

Global Supply Chain Global Supply Chain planningplanning• Same product in different geographical

location

• Lead Time separates two locations

• Central management of inventory enabled

Page 11: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

11 © The Delos Partnership 2004 Vas SCT Model

Customer Relationship Customer Relationship StrategyStrategy

Design

Purchase

Intermediate Manufacture

Sub-assemble

Finish

Distribute

WhereDo you meetTheCustomer ?

StockTo Order

Page 12: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

12 © The Delos Partnership 2004 Vas SCT Model

Global Supply Chain Global Supply Chain PlanningPlanning

Bill of Distribution Same Product Code :Location code needed

Page 13: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

13 © The Delos Partnership 2004 Vas SCT Model

Periods 1 2 3 4 5 6 7 8 9 10 11 12

Forecast 25 25 25 25 25 25 25 25 20 20 20 20

Warehouse Demand

Actual Demand

Proj Avail Balance

Available to Promise

Master Schedule

150 150 150 150 150 150

Master Schedule CanadaMaster Schedule Canada

Part Number: 12345 Lead Time: 2 periods Safety Stock: 50 Min Ord Qty: 150 On Hand: 300Location : 001 Canada

Page 14: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

14 © The Delos Partnership 2004 Vas SCT Model

Periods 1 2 3 4 5 6 7 8 9 10 11 12

Forecast 0 20 40 50 50 50

Actual Demand 50

Proj Avail Balance

50 50 30 30 40 40 40 40 40 40 40 40

Available to Promise

0 50 50 50 50

Replenishment 50 50 50 50 50

Periods 1 2 3 4 5 6 7 8 9 10 11 12

ForecastDemand

10 10 10 10 10 10 10 10 10 10 10 10

WarehouseDemand

50 50 50 50 50

Proj Avail Balance

90 80 120 110 60 50 90 90 130 120 60 50

Available to Promise

100 100 100 100

Master Schedule

100 100 100

DC

Factory

100

Safety Stock = 50

100

Page 15: Vas SCT Model 1 © The Delos Partnership 2004 Supply Chain Techniques Choices to be made when deciding how to plan

15 © The Delos Partnership 2004 Vas SCT Model

Master Scheduling OptionsMaster Scheduling Options

Summary– Models can change depending on

• Service level / Customer Lead Time• Inventory Level in BOM• Set up reduction activity

– Requires careful review of planning models– Determining where to meet customer is key