www.fugro.com VC Summer Units 2 and 3 Excavation Sequence Geologic Mapping Technical Approach Data Management Nathan B. Cooke, PG, Senior Site Geologist-Shaw Nuclear Matthew F. Cooke, PG, Senior Site Geologist-Shaw Nuclear Gina Ferrugia, Site Geologist - Shaw Nuclear April 18 th , 2011

Upload: others

Post on 09-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

VC Summer Units 2 and 3Excavation Sequence

Geologic Mapping Technical Approach

Data Management

Nathan B. Cooke, PG, Senior Site Geologist-Shaw Nuclear

Matthew F. Cooke, PG, Senior Site Geologist-Shaw Nuclear

Gina Ferrugia, Site Geologist - Shaw Nuclear

April 18th, 2011

Page 2: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

EXCAVATION SEQUENCE SUMMARY

Mass Grading from Elevation 420 to 400

Temporary Retaining Wall Installation and Excavation to Top of Rock

Rock Excavation (controlled blasting) to Final Foundation Grade in NI

and CWS Area

Page 3: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Clearing Grubbing and Mass Grading from ~Elevation 420 to

~Elevation 400

– Pan Scrapers (CAT 637), Dozers, Excavators used to remove

overburden soils (Residual Soil and Saprolite)

– Geologic Mapping Performed Before and During This Phase

• Reconnaissance Mapping

• Geologic Trenches and Test Pits

EXCAVATION SEQUENCE-MASS GRADING

April 18, 2011

Page 4: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Initial Grubbing – Unit 2

August 2009

Approximate Elevation 370 to 430

EXCAVATION SEQUENCE-MASS GRADING

Page 5: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Photograph showing Unit 2 Area mass grading operations. Area is at approximate final

rough grade Elevation 400. Note pan scrape in cut area exposing features in Saprolite.

Final Grading – Unit 2

February 2010

EXCAVATION SEQUENCE-MASS GRADING

Page 6: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

EXCAVATION SEQUENCE

UNIT 2 TEMPORARY RETAINING WALL

Unit 2 Temporary Retaining Wall

1. Installation of Soldier Piles

2. Excavation performed along wall in approximate 5 to 6 foot lifts.

Simultaneous excavation by SHAW in central portion of Power Block

3. Installation of Timber Lagging

4. Drilling/Installation of Tie Backs

5. Geologic Mapping Performed During This Phase

• Retaining Wall Mapping

• Reconnaissance Mapping of Interior Excavation

• Top of Rock Mapping

Page 7: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Unit 2 Power Block Excavation Plan View

EXCAVATION SEQUENCE

UNIT 2 TEMPORARY RETAINING WALL

Page 8: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

EXCAVATION SEQUENCE

ROCK EXCAVATION UNIT 2 NUCLEAR ISLAND

Unit 2 Nuclear Island Rock Excavation

1. Development of Rock Excavation Plan and Sequence

2. Drilling and Controlled Blasting (Palmetto Rock)

3. Excavation of Blasted Rock (Shaw)

4. Rock Cleaning and Vacuuming (Shaw)

5. Final Foundation Grade Geologic Mapping (WLA)

Page 9: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

EXCAVATION SEQUENCE

ROCK EXCAVATION UNIT 2 NUCLEAR ISLAND

ROCK EXCAVATION PLAN

Review of FSAR Geotechnical Data

Review of As-Built Top of Rock

contours in NI.

GOAL: Excavate to EL 357 or to

Sound Rock, whichever is deeper

Benched Excavation Plan based on

estimated Sound Rock contours from

COLA Subsurface Investigation Data.

General Drilling and Blasting

Sequence:1. Pre-Splitting 357 Bench Outside

Perimeter

2. Removal of Rock from ~EL 379 to

357

3. Pre-Splitting Outside Perimeter

and interior benches from EL 357

to EL 342.

4. Removal of Rock from EL 357 to

EL 342.

5. Removal of Rock from EL 342 to

334.

6. Rock Excavation for Temporary

Dewatering Sump outside of NI to

EL 327.

SUMP

EL. 327

EL. 334-342

Page 10: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Unit 2 Nuclear Island Intermediate Rock Excavation. View from Plant South Wall

EXCAVATION SEQUENCE

ROCK EXCAVATION UNIT 2 NUCLEAR ISLAND

Page 11: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Unit 2 Nuclear Island Excavation Final Grade. View from Plant South Wall

EXCAVATION SEQUENCE

ROCK EXCAVATION UNIT 2 NUCLEAR ISLAND

Page 12: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

GEOLOGIC MAPPING

TECHNICAL APPROACH

1. “Target of Opportunity” Reconnaissance Mapping - Ongoing

2. Unit 2 and 3 Geologic Trenches and Test Pits - Complete

3. Unit 2 Power Block Retaining Wall Mapping - Complete

4. Unit 2 Nuclear Island and CWS Area Top of Rock Mapping - Complete

5. Unit 2 Nuclear Island Final Foundation Mapping - In Progress

6. Unit 3 Power Block Retaining Wall Mapping - In Progress

7. Map Key Features in Unit 2 CWS Excavation - Later

8. Map Key Features in Balance of Power Block Excavation - Later

Page 13: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

GEOLOGIC MAPPING

TECHNICAL APPROACH:

RECONNAISSANCE MAPPING

Collected Geologic Data from Exposures in Excavations Since Beginning of Site Grading

(Late 2008)

Types of Exposures:

– Pan Scrapes

– Shear Wall Excavations

– Utility Trenches

– Rail and Road Cuts

– Sedimentation Pond Excavations

– Erosional Features

– Natural Outcrops

– Test Pits

Data Collected:

– Digital Photographs (6,000+ Photos)

– Geologic Field Notes/Sketches (10,000+ Observations)

– Compass Measurements (~400 Measurements of Structural Features)

– Samples Collected (Over 250 Specimens)

Review of Background Information

– Unit 1 Geologic Investigation

– Unit 2 and 3 COLA Subsurface Exploration

– Geologic Literature

– Aerial Photographs and Light Detection and Ranging (LIDAR) Data

Page 14: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Pan Scrapes

GEOLOGIC MAPPING

TECHNICAL APPROACH: SITE-WIDE

RECONNAISSANCE MAPPING

Page 15: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Ditch Excavations Sediment Pond Excavations

Road and Railroad Cuts Utility Trench Excavations

GEOLOGIC MAPPING

TECHNICAL APPROACH: SITE-WIDE

RECONNAISSANCE MAPPING

Page 16: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Shear Wall Excavations

Erosional Exposures

GEOLOGIC MAPPING

TECHNICAL APPROACH: SITE-WIDE

RECONNAISSANCE MAPPING

Page 17: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Dots represent locations

of reconnaissance

mapping data collection

transposed on a Lidar

topographic relief map.

Geologic

Reconnaissance

Mapping

Waypoints

GEOLOGIC MAPPING

TECHNICAL APPROACH: SITE-WIDE

RECONNAISSANCE MAPPING

Page 18: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

GEOLOGIC MAPPING

TECHNICAL APPROACH:

Unit 2 and Unit 3 Geologic Trenches

Geologic Trenches, typically 4 to 5 feet deep were excavated across the

Unit 2 and Unit 3 Power Block Areas during grading from approximately

elevation 420 to 400.

– Documentation of near surface conditions in Power Block vicinity

– Develop mapping techniques for subsequent Power Block Retaining

Wall mapping

– Trenches were divided into approximate 10’ wide panels, surveyed,

photographed and mapped.

– Encountered fill, undifferentiated surficial deposits, residual soil,

saprolite and localized zones of partially weathered rock.

– Geologic Trench Report by WLA Complete

Page 19: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

GEOLOGIC MAPPING

TECHNICAL APPROACH:

Unit 2 and Unit 3 Geologic Trenches

Geologic

Trench Location

Map

Page 20: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Unit 2 Trench Oriented East-West

GEOLOGIC MAPPING

TECHNICAL APPROACH:

Unit 2 and Unit 3 Geologic Trenches

Panels on the North Wall Unit 2

Trench

String/Tape Locations Indicated by Dark Lines

Page 21: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Unit 2 Trench South Wall Example

Photograph

GEOLOGIC MAPPING

TECHNICAL APPROACH: Unit 2 and Unit 3 Geologic Trenches

Page 22: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Unit 2 Trench Example Final Geologic Map

GEOLOGIC MAPPING

TECHNICAL APPROACH:

Unit 2 and Unit 3 Geologic Trenches

Page 23: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

GEOLOGIC MAPPING TECHNICAL APPROACH –

UNIT 2 Power Block Retaining Wall

and Top of Rock Mapping

Wall Mapping During Excavation and Construction of Unit 2 Retaining Wall

Top of Rock Mapping (Pre- and Post-Blasting)

WLA Procedures, Project Planning Document (QA Plan), Project Instructions, Work

Instructions:

1. Project Planning Document (PPD)

2. Geologic Map Data Collection Plan (Project Instruction)

3. Laboratory Testing Plan (Project Instruction)

4. Geoscience Evaluation and Analysis Plan (Project Instruction)

5. Field Records (Work Instruction)

6. Survey Control (Work Instruction)

7. Field Mapping Standards (Work Instruction)

8. Sampling Protocol Handling and Storage (Work Instruction)

9. Data Compilation and Verification (Work Instruction)

10. Units 2 and 3 Wall Photography and Mapping (Work Instruction)

11. GPS Unit Accuracy Verification (Work Instruction)

12. Unit 2 Nuclear Island and CWS Area Preliminary Geologic Mapping (Work Instruction)

13. Unit 2 Nuclear Island and CWS Area Final Foundation Mapping (Work Instruction)

Page 24: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Geologic mapping in progress along north wall in Unit 2 Power Block.

GEOLOGIC MAPPING TECHNICAL APPROACH –

UNIT 2 Power Block Retaining Wall

and Top of Rock Mapping

Page 25: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Example Retaining Wall Panel Before Mapping

GEOLOGIC MAPPING TECHNICAL APPROACH –

UNIT 2 Power Block Retaining Wall

and Top of Rock Mapping

Page 26: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Example Retaining Wall Panel After Mapping

GEOLOGIC MAPPING TECHNICAL APPROACH –

UNIT 2 Power Block Retaining Wall

and Top of Rock Mapping

Page 27: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Example Retaining Wall Geologic Map

GEOLOGIC MAPPING TECHNICAL APPROACH –

UNIT 2 Power Block Retaining Wall

and Top of Rock Mapping

Page 28: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Example Top of Rock Before Mapping

GEOLOGIC MAPPING TECHNICAL APPROACH –

UNIT 2 Power Block Retaining Wall

and Top of Rock Mapping

Page 29: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Example Top of Rock After Mapping

GEOLOGIC MAPPING TECHNICAL APPROACH –

UNIT 2 Power Block Retaining Wall and Top of

Rock Mapping

Page 30: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Example Portion of Unit 2 Nuclear Island Top of Rock Geologic Map

GEOLOGIC MAPPING TECHNICAL APPROACH –

UNIT 2 Power Block Retaining Wall

and Top of Rock Mapping

Page 31: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Example Final Foundation Sound Rock Before Mapping

GEOLOGIC MAPPING TECHNICAL APPROACH –

UNIT 2 Nuclear Island

Final Foundation Geologic Mapping

Page 32: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Example Final Foundation Sound Rock After Mapping

GEOLOGIC MAPPING TECHNICAL APPROACH –

UNIT 2 Nuclear Island

Final Foundation Geologic Mapping

Page 33: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

DATA MANAGEMENT

FIELD RECORDS

– Field Books and Notes

– Base Maps

– Annotated Data (Base Photos and Maps)

– Digital Data

Geologic Mapping Data Collection Plan, Field Records Work Instruction

On-site Storage Facility (WLA Trailer) Fire Proof File Cabinet

Field Books and Notes Scanned Each Day

Data Transmitted to Home Office Each Day for GIS

Scanned Field Books, Notes, Digital Data backed also backed up each day

on external hard drive.

Data Also Provided to Shaw Daily

Page 34: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

Site Lithologic Units(in approximate order of increasing age)

SURFICIAL UNITS

Man-made Fill

Alluvium

Colluvium

Undifferentiated Surficial Deposits

Residual Soil

Saprolite

ROCK UNITS

Winnsboro Plutonic Complex

Aplite

Pegmatite

Quartz Monzonite

Diorite

Charlotte Terrane

Quartz Veins

Migmatite

Amphibolite Schist and Gneiss

SUMMARY OF LITHOLOGIC AND ENGINEERING

UNITS

FSAR Engineering Layers

LAYER I (ML and MH)

LAYER II (ML and SM)

LAYER III (PWR, SPT N > 100bpf,

Transition Zone)

LAYER IV (MWR, RQD 0% to 50%)

LAYER V (Sound Rock, RQD 50% to 100%,

Typically > 70%)

Page 35: VC Summer Units 2 and 3 · 2012. 12. 4. · UNIT 2 TEMPORARY RETAINING WALL Unit 2 Temporary Retaining Wall 1. Installation of Soldier Piles 2. Excavation performed along wall in

www.fugro.com

CLOSING

QUESTIONS