CONSTRUCTION PROGRESS REPORT Project : NGHA-SHR5 Location: Taif Building : Villa Duplex-2 Division 16 WORK STEPS Work Type (Level 6) 16.4 - Wiring Devices A Installation of Conduit D Termination of Device Level 7 B Pull Wire for Device E Testing and Comissioning C Installation of Device F SR. NO. Bldg Floor Level Section / Zone WORK STEP % PROGRESS 20% 30% 30% 10% 10% Prev Prog% This Period Prog % Cumulative Progress 20% 50% 80% 90% 100% Weigth % Weigth % Weigth % A B C D E F 1 VD-2 GF-Ground Floor ALL 54.96% 80.00% 80.00% 0.00% 0.00% 0.00% 16.49% 5.50% 21.98% 2 VD-2 01-First Floor ALL 41.22% 80.00% 80.00% 0.00% 0.00% 0.00% 12.37% 4.12% 16.49% 3 VD-2 RF-Roof ALL 3.82% 80.00% 0.00% 0.00% 0.00% 0.00% 1.15% -0.53% 0.61% Total 100% 80.00% 76.95% 0.00% 0.00% 0.00% 30.00% 9.08% 39.08% The Contractor confirms that the Cumulative Progress Weight Percentage is accurate, and the result of completed works on the site, based on the approved Work Steps above. Notes: Remarks of Engineer: Please note that this document will be considered as an official tool for invoicing until the Detailed Construction Schedule can be used. Prepared by: Checked By Approved by: Approved by: Contractor Quantity Surveyor Contractors Project Controls Manager Contractor Project Manager Nesma Project Manager Weight [%]

Upload: almaporyak

Post on 08-Jul-2016

215 views

Category:

Documents


2 download

DESCRIPTION

Wr

TRANSCRIPT

Page 1: VD-2 16.4 Wiring Devices CPR

CONSTRUCTION PROGRESS REPORT Project : NGHA-SHR5

Location: Taif

Building : Villa Duplex-2

Division 16 WORK STEPSWork Type (Level 6) 16.4 - Wiring Devices A Installation of Conduit D Termination of DeviceLevel 7 B Pull Wire for Device E Testing and Comissioning

C Installation of Device F

SR. NO. Bldg Floor Level Section / Zone

WORK STEP % PROGRESS

20% 30% 30% 10% 10% Prev Prog% This Period Prog % Cumulative Progress

20% 50% 80% 90% 100%Weigth % Weigth % Weigth %

A B C D E F

1 VD-2 GF-Ground Floor ALL 54.96% 80.00% 80.00% 0.00% 0.00% 0.00% 16.49% 5.50% 21.98%

2 VD-2 01-First Floor ALL 41.22% 80.00% 80.00% 0.00% 0.00% 0.00% 12.37% 4.12% 16.49%

3 VD-2 RF-Roof ALL 3.82% 80.00% 0.00% 0.00% 0.00% 0.00% 1.15% -0.53% 0.61%

Total 100% 80.00% 76.95% 0.00% 0.00% 0.00% 30.00% 9.08% 39.08%The Contractor confirms that the Cumulative Progress Weight Percentage is accurate, and the result of completed works on the site, based on the approved Work Steps above. Notes: Remarks of Engineer:

Please note that this document will be considered as an official tool for invoicing until the Detailed Construction Schedule can be used.

Prepared by: Checked By Approved by: Approved by:

Contractor Quantity Surveyor Contractors Project Controls Manager Contractor Project Manager Nesma Project Manager

Weight[%]