vd-2 16.4 wiring devices cpr
DESCRIPTION
WrTRANSCRIPT
![Page 1: VD-2 16.4 Wiring Devices CPR](https://reader036.vdocument.in/reader036/viewer/2022080315/577c78ee1a28abe05490ffa9/html5/thumbnails/1.jpg)
CONSTRUCTION PROGRESS REPORT Project : NGHA-SHR5
Location: Taif
Building : Villa Duplex-2
Division 16 WORK STEPSWork Type (Level 6) 16.4 - Wiring Devices A Installation of Conduit D Termination of DeviceLevel 7 B Pull Wire for Device E Testing and Comissioning
C Installation of Device F
SR. NO. Bldg Floor Level Section / Zone
WORK STEP % PROGRESS
20% 30% 30% 10% 10% Prev Prog% This Period Prog % Cumulative Progress
20% 50% 80% 90% 100%Weigth % Weigth % Weigth %
A B C D E F
1 VD-2 GF-Ground Floor ALL 54.96% 80.00% 80.00% 0.00% 0.00% 0.00% 16.49% 5.50% 21.98%
2 VD-2 01-First Floor ALL 41.22% 80.00% 80.00% 0.00% 0.00% 0.00% 12.37% 4.12% 16.49%
3 VD-2 RF-Roof ALL 3.82% 80.00% 0.00% 0.00% 0.00% 0.00% 1.15% -0.53% 0.61%
Total 100% 80.00% 76.95% 0.00% 0.00% 0.00% 30.00% 9.08% 39.08%The Contractor confirms that the Cumulative Progress Weight Percentage is accurate, and the result of completed works on the site, based on the approved Work Steps above. Notes: Remarks of Engineer:
Please note that this document will be considered as an official tool for invoicing until the Detailed Construction Schedule can be used.
Prepared by: Checked By Approved by: Approved by:
Contractor Quantity Surveyor Contractors Project Controls Manager Contractor Project Manager Nesma Project Manager
Weight[%]