QUESTIONS? Please contact Project Manager Aaron Zutz at 608.441.6891 or [email protected] DID YOU KNOW? Did you know that asphalt pavements are America’s most recycled product. Each year nearly 100 million tons of asphalt is reused to build roads and highways. In comparison, the site of the new Verona Area High School will have placed approximately 20,000 tons of asphalt by the time the project is complete! Verona Area High School Proof Rolling Has Begun! With little precipitation allowing the ground to stay dry, site work continues to keep a great pace. That pace has now brought us to the point that asphalt preparation is nearly complete on site and proof rolling has began. A “proof roll” is completed on all areas to be paved with asphalt. To complete a proof roll, a fully loaded dump truck weighing approximately 70,000 lbs is slowly driven over the prepared subgrade. The subgrade is then inspected for deflection or rutting from the weight of the truck. Any areas found to be deflecting or rutting are then repaired prior to paving. Coming up in the weeks ahead we will see the first asphalt be placed on the track. At the same time, the excavation of the tennis courts will continue and the water main to the baseball fields will be installed. Also, the final piece of site wood of the project will be installed at the community pool reception desk! The Past Week: Competition Pool Final Fill Proof Rolling & Layout of the Track Ceilings and Shared Lights in Music Completion of Polished Concrete Coming Up in the Weeks Ahead: Tennis Court Excavation Ongoing Water Main Installation at Baseball Fields Final Site Wood Installation Track asphalt paving April 17 th , 2020

Upload: others

Post on 22-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Verona Area High School · 4/17/2020  · Verona Area High School April 17 th, 2020 The picture above is the now plastered and final filled competition pool awaiting bleacher installation

QUESTIONS? Please contact Project Manager Aaron Zutz at 608.441.6891 or [email protected]

DID YOU KNOW?Did you know that asphalt pavements are America’s most recycled product. Each year nearly 100 million tons of asphalt is reused to build roads and highways. In comparison, the site of the new Verona Area High School will have placed approximately 20,000 tons of asphalt by the time the project is complete!

Verona Area High School

Proof Rolling Has Begun!

With little precipitation allowing the ground to stay dry, site

work continues to keep a great pace. That pace has now

brought us to the point that asphalt preparation is nearly

complete on site and proof rolling has began. A “proof

roll” is completed on all areas to be paved with asphalt. To

complete a proof roll, a fully loaded dump truck weighing

approximately 70,000 lbs is slowly driven over the prepared

subgrade. The subgrade is then inspected for deflection or

rutting from the weight of the truck. Any areas found to be

deflecting or rutting are then repaired prior to paving.

Coming up in the weeks ahead we will see the first asphalt

be placed on the track. At the same time, the excavation of

the tennis courts will continue and the water main to the

baseball fields will be installed. Also, the

final piece of site wood of the project will be

installed at the community pool reception desk!

The Past Week:

• Competition Pool Final Fill

• Proof Rolling & Layout of the Track

• Ceilings and Shared Lights in Music

• Completion of Polished Concrete

Coming Up in the Weeks Ahead:

• Tennis Court Excavation Ongoing

• Water Main Installation at Baseball Fields

• Final Site Wood Installation

• Track asphalt paving

April 17th, 2020

Page 2: Verona Area High School · 4/17/2020  · Verona Area High School April 17 th, 2020 The picture above is the now plastered and final filled competition pool awaiting bleacher installation

QUESTIONS? Please contact Project Manager Aaron Zutz at 608.441.6891 or [email protected]

Verona Area High School

April 17th, 2020

The image above and to the left is a newly poured staircase outside of one of the pool entrances. The photo above shows the newly installed projector screen in the field house. The black strip to either side of the screen is acoustical panel. The photo below and to the left is the first wall that students will see entering the locker room. And the image just below shows preparation for the site concrete pour just outside of the

Performing Arts Center!

Page 3: Verona Area High School · 4/17/2020  · Verona Area High School April 17 th, 2020 The picture above is the now plastered and final filled competition pool awaiting bleacher installation

QUESTIONS? Please contact Project Manager Aaron Zutz at 608.441.6891 or [email protected]

Verona Area High School

April 17th, 2020

The picture above is the now plastered and final filled competition pool awaiting bleacher installation. The

below image contains a newly poured stretch of sidewalk just outside the competition pool. Below and to the right sits a picture of one of the shared lights to a music room. Notice the two pains of glass with vibration dampening seals around the frame in order to prevent the transfer of sound. Lastly, the image above and to the right shows one of the music corridors ready for final cleaning!